Upload
erol-dag
View
213
Download
0
Embed Size (px)
Citation preview
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 1/18
A 16.05.2016 İLK YAYINLANIŞ E.D
Rev.No.
Date DescriptionPREPARED CHECKED CONTR. BY ONAY EDOPEC
ORIGINATOR Published by
EDOPEC ENERJİ PETROL MÜHENDİSLİK SANAYİİ VE TİCARET
LİMİTED ŞİRKETİ
Head OfficePalmıye Mah. Adnan Menderes
Bulvarı 1225 Sokak.Oktay
SıtesıNo: 6 Kat 8 D:17 PK-
33100 Yenısehır –Mersın – TurkeyP:+90 324 3260595
F:+90 324 3260596
www.edopec.com.
Document Title
WORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Document No.
EDO WMS COR CNS INT XXX 016 686 885 Rev A Co.Org.Cod
DocType
Disc.Code
UnitCode
Prj.type
Prj.No
Prıj. Year
Pro.Doc.Seq.No
DCCSeq.No
Page Scale 18
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 2/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 2 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
TABLE OF CONTENTS
1 EXECUTIVE SUMMARY ................................................................................................. 3
2 SCOPE AND PURPOSE ................................................................................................. 4
2.1 Purpose.................................................................................................................................. 4
2.2 Scope ..................................................................................................................................... 4
3 DEFINITIONS AND ABBREVIATIONS........................................................................... 5
4 CODES STANDARDS AND REFERANCES .................................................................. 6
5
DESCRIPTION OF THE PIPELINE SYSTEM ................................................................. 8
6 SOIL RESISTIVITY SURVEY.......................................................................................... 9
6.1 General................................................................................................................................... 9
6.2 Measuring Equipment ........................................................................................................... 9
6.3
Procedure
............................................................................................................................ 10
7 AUTHORITY AND PERMITS REQUIREMENTS
........................................................... 12
8 LAND ACQUISITION REQUIREMENTS ....................................................................... 13
9 H&S REQUIREMENTS .............................................................................................. 14
10 ENVIRONMENT ASSESSMENT ................................................................................ 15
11 COMMUNITY RELATIONS ASSESSEMENTS .......................................................... 16
12
SECURITY ASSESSEMENT
...................................................................................... 17
13 QA / QC ...................................................................................................................... 18
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 3/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 3 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
1 EXECUTIVE SUMMARY
Matcor Inc. with the assistance of Ergil Makina provides engineering, materials andinstallation, supervision for cathodic protection system of Baku-Tbilisi-Ceyhan CrudeOil Pipeline Ceyhan Marine Terminal Onshore and Offshore Project. This workmethod statement summarizes the methods and the procedures that Matcor Inc. willbe using to obtain the most accurate soil resistivity measurements to engineerCeyhan Terminal’s Load Lines temporary cathodic protection (TCP) groundbeds.
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 4/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 4 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
2 SCOPE AND PURPOSE
2.1 Purpose
This work method statement describes methods and procedures that will be used insoil resistivity survey of the Load Lines of the Baku-Tbilisi-Ceyhan Crude OilPipeline Project for the TCP System.
2.2 Scope
This Work Method Statement covers the resurvey and verify the soil resistivitymeasurements along the Load Lines route at approximately every 100 meters.
Resurvey along the pipeline route to assess the conductivity of the soil will becarried out to ensure continues flow and evenly distribution of current fromcathodic protection transformer/rectifier units. This soil resistivity survey willprovide information in determining the temporary cathodic protection (TCP)current requirements along the pipeline. This data will be used to verify and, ifnecessary, modify the previous consultant’s test results. Any change to projectspecifications if made, will be submitted to the Employer with supportivedocumentation.
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 5/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 5 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
3 DEFINITIONS AND ABBREVIATIONS
ANSI American National Standards Institute
API American Petroleum Institute
ASTM American Society for Testing and Materials
HSE Health, Safety and Environmental
IEC International Electro technical Commission
IEEE Institute of Electrical and Electronics Engineers
IP Institute of Petroleum
ISO International Standards Organisation
NACE National Association of Corrosion Engineers
CP Cathodic Protection
TCP Temporary Cathodic Protection
LL Loading Line
BTC Baku-Tbilisi-Ceyhan Crude Oil Pipeline
HSE Health, Safety and Environmental
QA Quality Assurance
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 6/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 6 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
4 CODES STANDARDS AND REFERANCES
ANSI / IEEE C2-93 National Electrical Safety Code
ANSI / IEEE C62.11 Standard for Metal-Oxide Surge Arrestors for Alternating Current Power Circuits
API RP 540 Electrical Installations in Petroleum ProcessingPlants
API RP 550 Manual on Installation of Refinery Instrumentationand Control Systems
API 1102 Steel Pipelines Crossing Railroads and Highways
ASTM A123 Standard Specification for Zinc (Hot DipGalvanised) Coatings on Iron and Steel Products
ASTM A153/A153M Standard Specification for Zinc Coating (Hot-Dip)on Iron and Steel Hardware
BS 8800, 1996 Guide to Occupational Health and SafetyManagement Systems
ISO 1800, 1996 Safety Management Systems
ISO 9000: 1994
ISO 9004-1 1994
ISO 14001, 1996 Environmental Management Systems
IEEE 81 Guide for Measuring Earth Resistivity, GroundImpedance, and Earth Surface Potentials of aGrounded System
IP Code Part 3 Model Code of Safe Practice in the PetroleumIndustry: Refining
IEC 529 Degrees of Protection Provided by Enclosures (IP- Code)
IEC 99-2 Lighting Arrestors Part 2: Expulsion-Type Lightning Arrestors First Edition (withdrawn)
IEC 146-1 Semi-Conductor Converters-General Requirementsand Line Commuted Converters
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 7/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 7 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
IEC 227-1 to 5 Polyvinyl Chloride Insulated Cables, Rated Voltageup to and including 450/750V
IEC 269-1 Low Voltage Fuses Part 1: General Requirements,
Second Edition
IEC 76-3 Insulation levels and dielectric tests
NACE RP0169 Control of External Corrosion on Underground or Submerged Metallic Piping Systems
NACE RP0177 Mitigation of Alternating Current and LighteningEffects on Metallic Structures and CorrosionControl Systems
NACE RP0190 External Protective Coatings for Joints, Fittings,and Valves on Metallic Underground or SubmergedPipelines and Piping Systems
NACE RP0274 High Voltage Electrical Inspection of PipelineCoating Prior to Installation
NACE RP0286 The Electrical Isolation of Cathodically ProtectedPipelines
NACE RP0572 Design, Installation, Operation and Maintenance of
Impressed Current Deep Ground Beds
NACE RP0792 Standard Format for Computerised Close InternalSurvey Data
NACE RP0572 Design, Installation, Operation and Maintenance ofImpressed Current Deep Groundbeds
KOÇ, T., “Elektrokimya”, Palme Press, Ankara, 1999
YALÇIN, H., KOÇ, T., “Katodik Koruma”, Palme Press, Ankara, 1998
YALÇIN, H., KOÇ, T., “Mühendisler İçin Korozyon”, Nitelik Press, Ankara, 1998
I
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 8/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 8 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
5 DESCRIPTION OF THE PIPELINE SYSTEM
The cathodic protection system shall protect the following pipeline bundle:
Pipeline Dia. Length (m)
Loading Lines 2 x 42” 3,000
Fire Water Line 30” 3,000
Service Water 4” 3,000
Portable Water 2” 3,000
Vapour Recovery 24” 150
Foam Concentrate 6” 150
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 9/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 9 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
6 SOIL RESISTIVITY SURVEY
6.1 General
A soil resistivity survey along the pipeline route to assess the corrosionlikelihood of the soil will be carried out to identify corrosive areas and todetermine locations where temporary cathodic protection (TCP) is required.
Table 1: Classification of Soil Resistivity
Soil Resistivity,(ohm.cm)
Corrosive Characteristic of Soil
Up to 1000 Severely corrosive
1000 to 5000 Corrosive
5000 to 10,000 Moderately corrosive
10,000 and above Slightly corrosive
Severely corrosive soils Soils with humic acid and sulphide minerals.
Corrosive soils Soil, which has the capability or tendency to causecorrosion.
Moderately corrosive soils Marshlands, agricultural areas, clays, marls, clayeysoils, shale, schist and clay cemented sandstones.
Slightly corrosive or
Non-corrosive soils Silts, sands, silica and limestone cementedsandstones, conglomerates and limestone
6.2 Measuring Equipment
The following instruments and any additional instruments which shall be reasonablynecessary shall be available on site for the TCP/PCP survey, testing, and
installation:
AC resistance bridge or megger (frequency approx. 108 Hz) Multimeter for AC and DC voltage, current and resistance measurements GPS receiver Cu/CuSO4 half-cells Shunt, 1 megohm Miscellaneous hand tools
The measuring equipment to be used for the survey shall be subject to the approvalof the BTC P/L Directorate. All equipment will be calibrated annually.
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 10/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 10 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
6.3 Procedure
The soil resistivity will be calculated immediately after the test is performed. If themeasurement between two consecutive readings has either increased or decreasedby a factor of two, then intermediate soil measurements will be done.
The test set-up utilizes the mechanics of the Wenner "Four Pin-Electrode Method".The resultant resistivity is the average resistivity of the soil (electrolyte) to a depthequal to the spacing between adjacent electrodes (soil pins). When using the 4 pinmethod to measure soil resistance, the 4 pins are driven into the ground in astraight line at the spacing stated below. Good contact with the soil is important.The two “C” binding posts are connected to the two end pins, and the two “P”binding posts are connected to the adjacent center pins.
Wenner 4-Pin Method
The soil resistivity will be carried out by the Wenner 4-Pin method. The resultantresistivity is the average resistivity of the soil (electrolyte) to a depth equal to thespacing between adjacent electrodes (soil pins).
The distances between the inner electrodes " P1- P2" and between the inner and theneighboured outer electrodes "C1-C2 will be as follows:
1st series of measurements, Wenner methoda = 2.0 m
2nd series of measurements,a = 4.0 m
Each measurement series will comprise consecutive individual measurementsperformed at equal intervals over the total length to be surveyed. If necessary,greater distances of "a" will be used.
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 11/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 11 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
Soil resistivity measurements will be obtained along the pipeline route at depths of2, and 4 meters.
Soil resistivity measurements will be plotted on a graph of resistivity versus distance(km). This graph will be used to locate areas with less than 2000 ohm cm soilresistivity. At these locations, a TCP test station will be installed.
The soil resistivity survey will be carried out under the supervision and control ofproject engineers.
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 12/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 12 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
7 AUTHORITY AND PERMITS REQUIREMENTS
Presently no additional requirement is foreseen, if any such permits to be obtained,the same will be obtained in accordance with the requirements.
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 13/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 13 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
8 LAND ACQUISITION REQUIREMENTS
Presently no additional land requirement is foreseen, if any such requirement anaddendum will be prepared and submitted to Employer for approval.
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 14/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 14 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
9 H&S REQUIREMENTS
Refer attached JSEA and Risk assessments .
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 15/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 15 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
10 ENVIRONMENT ASSESSMENT
No special environmental assessments is required any how
All environmental incidents will be reported.
All debris and waste materials will be removed from the easement eachworking day to Employer approved location.
Toilet facilities will be provided on the easement at all times.
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 16/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 16 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
11 COMMUNITY RELATIONS ASSESSEMENTS
Whenever and wherever the COL department service required, they will beinformed in advance in a timely manner to carry out their work.
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 17/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 17 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
12 SECURITY ASSESSEMENT
None.
8/16/2019 Edo Wms Cor Cns Int Xxx 016 686 885 Rev 0 Work Method Statement for Soil
http://slidepdf.com/reader/full/edo-wms-cor-cns-int-xxx-016-686-885-rev-0-work-method-statement-for-soil 18/18
TS EN ISO 9001:2008 ;TS EN ISO 14001:2005TS OHSAS 18001:2008 ; Certificate No: 764/01/02/03
Page 18 of 18
Project: EDOPEC ENERJİ Proj. Identification:
Document Title:ORK METHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FOR
TEMPORARY CATHODIC PROTECTION (TCP)Document No.:
EDO-WMS-COR-CNS-INT-XXX-016-686-885-REV-0-WORKMETHOD STATEMENT FOR SOIL RESISTIVITY SURVEY FORTEMPORARY CATHODIC PROTECTION (TCP)
Revision: A Date: 16.05.2016
13 QA / QC
All the works will be carried out in accordance with approved procedure andspecifications.