Agenda• Proposition 1 – Proposed Scope Items• Proposition 2 – Proposed Scope Items• Appel Osborne Site Update Presentation• Facility Use Plan• Financial Update• Public information Campaign Update• Project Schedule Update• SEQRA Discussion
EDEN CSD 2020
Possible Scope ItemsPROPOSITION #1
• New Secure Entry• Create District Office Space• Renovate Main Office
• Exterior Masonry Improvements• Interior Upgrades (ceilings, doors,
cafeteria, auditorium, etc.)• Renovate Toilet Rooms• Technology Upgrades
• Mechanical Improvements
• Electrical Improvements• Plumbing Improvements• Site Improvements
• Move 6th Grade into building • Music Rm. & Aud. Upgrades
• Exterior Doors• Classroom Upgrades
• Renovate Kindergarten Rooms• Renovate Cafeteria
Proposition #1 Total Cost = $12.25 Million
EDEN CSD 2020
Possible Scope ItemsPROPOSITION #2
**Prop #2 Cannot Pass Without Prop #1 Passing**
Proposition #2 Total Cost = $9.9 Million
• Art, Music, and Technology Upgrades• Auditorium / Cafetorium • Exterior Upgrades• Site Improvements
• Concession Stand / Toilet Rooms• Turf Field
• Stadium Concept• Gymnasium Upgrades
EDEN CSD 2020
Appel Osborne Site Update Presentation
• Turf Field Information• Sports Lighting Information
Conceptual Image
EDEN CSD 2020
Facility Use Plan
• Addresses use of Multi-Sport Complex
• The Plan is being Developed
• Building/Facility Use Sub Committee
• The Plan will be approved by administration and BOE
EDEN CSD 2020
Project Financial Update
• Proposition #1 is tax neutral to tax payers
• Proposition #2 has a $34 per $100,000 household
proposed tax increase
• State Aid / Interest Rates adjustments in November
EDEN CSD 2020
Major Dates:
• BOE Approval of SEQRA September 16, 2015
• BOE Resolution (potential) October 21, 2015
• Public meeting December 9, 2015 - 6:30 p.m.
• Referendum Vote (potential) December 15, 2015
Public Information — Potential “Deliverables”
• PowerPoint for meetings Week of October 5
• Lobby boards October 23
• Fact sheet October 23(handed out at meetings, with lobby boards, etc.)
• Mailer announcing the project details Mailed out November 23(delivered to homes 1-2 weeks prior to vote)
• Website section On-going(includes all components)
Preliminary Public Information
Preliminary Public Information
Potential “Components” to be used as needed in each Deliverable:• Letter from Superintendent and/or BOE?
• Description of the process (public input, etc.)
• Polling location(s)
• Financial breakdown— simple pie charts for each proposition(include total referendum value / aid / local tax impact)
• Scope of each proposition in the referendum
• FAQs
• Vote date / time / location
• Public meeting dates / locations
• BOE and Superintendent’s names
Other activities • Schedule Group Meetings
Faculty meetings Local groups
EDEN CSD 2020
EDEN CSD 2020
Project Schedule Update
• Referendum Passes December 2015
• Design & Programming Development Spring – Summer 2016
• SED Review and Approval Fall-Winter 2016-17
• Bid & Award April – May 2017
• Construction Start June 1, 2017
• Construction Substantial Completion December 2018
• Project Close-out Winter 2018-19
EDEN CSD 2020
Legal Information
• SEQRA Process / Lead Agency
• Proposition Language 10/21 for Review