Economics of Water Supply

Embed Size (px)

Citation preview

  • 8/8/2019 Economics of Water Supply

    1/27

    TRIBHUVANUNIVERSITY

    INSTITUTEOFENGINEERING

    DEPARTMENTOFARCHITECTUREANDURBANPLANNING

    PULCHOWKCAMPUS

    MODULE:ECONOMICS

    SUBMITTEDTO:

    DR.JIBGARJOSHI

    SUBMITTEDBY:

    KIRANMANJOSHI|066MUP205

    MONICAMANANDHAR|066MUP207

    SACHEENMAHARJAN|066MUP214

    SAMIRBYANJANKAR|066MUP215

    SUCHITABAJRACHARYA|066MUP

    218

    ASEMINARON

    EECCOONNOOMMIICCSS

    OOFF

    WWAATTEERRAALLLLOOCCAATTIIOONN

  • 8/8/2019 Economics of Water Supply

    2/27

    EconomicsofWaterAllocation

    2|P a g e

    CHAPTER1|INTRODUCTION

    1.1Background

    Water israpidlybecomingscarce inalmostallcountriesandcitiesoftheworldwithgrowingpopulationon

    onehandandfastgrowingeconomics,commercial,industrialanddevelopmentalactivitiesontheother.This

    scarcity makes water both social & economic commodity. Being an essential component of life, the use of

    waterisindependentofeconomicconditionoroccupationofthepeoplealthoughitmayaffectitsdemand.

    Tremendous socioeconomic, political, commercial, educational and other activities are going on every

    moment.Forallsuchactivities,water isessential.Buttherateof increaseofsupplyofwater isvery lowas

    compared to the rate of population growth and urban expansion coupled with hectic social, industrial,

    commercialandotheractivities.Morethanthat,itisheartbreakingtoknowthatthetotalamountofwater

    that

    can

    be

    harnessed

    insidethe

    Kathmandu

    Valley

    in

    no

    way

    will

    be

    able

    to

    meet

    the

    future

    demand

    of

    Kathmandu.Insufficiencyinwatersupplymeantfurtherdeteriorationoftheproblemofwastewater.So,any

    delay in finding a solution for the water supply and waste water treatment could lead to a serious

    environmentaldisasterinKathmandu.

    1.2Introduction - Wateraseconomiccommodity

    Inadditiontobeingabasicneedandanonhomogeneousgood,watercouldbe excludable, nonexcludable,

    rival or nonrival, depending on the way in which it ispackaged. For example, rainwater is a non

    rival

    and

    non

    excludable

    good;

    a

    private

    metered

    connection

    is

    rival

    and

    excludable.

    A

    non

    rival

    good

    is

    onewhoseconsumptionbyonepersondoesnotreducetheconsumptionbyothers. Agoodisnonexcludable

    if it is prohibitively costly to exclude someone from receiving the benefits of the good after it has become

    available. Apublicgoodischaracterizedbynorivalryinconsumption.

    Therearebothexcludableandnonexcludablepublicgoods. Anonexcludablepublicgoodisagoodthatis

    non rival in consumption and that cannot be denied to a person who does not pay for it. Therefore, the

    benefit derived from improved water supply is a non excludable. Water has public good characteristics

    because improved water services to households translates to better health of the community,

    improvement in theworkforce, and reduction in the demand for health care. Using water that is

    belowstandard can lead to waterbased, waterborne, or other waterrelated diseases such asdiarrhea,

    ring worm. In many developing countries, millions of dollars are spent every year to treat outbreaks of

    disease most of which are waterrelated. Such expenditures are usually part of the budget of the

    ministry of health which most times cannot afford these costs. To satisfy minimum health and safety

    requirements,asufficientquantityofwaterforconsumptionpurposesmustbeatoraboveacertainquality

    level,topreventwaterbasedillnesses. Waterforbathingmustbeofacertainqualitytopreventskinrelated

    waterbornediseases. Otherhouseholdsinthecommunitymustsatisfytheseconstraintsaswellto prevent

    negative externalities resulting from water borne disease spread within theneighborhood.

    Health benefits clearly are a public good aspect of improved water quality.Reducingthetimewomen

    and children spend fetching water allows them to engage in other economic activities that contribute to

  • 8/8/2019 Economics of Water Supply

    3/27

    EconomicsofWaterAllocation

    3|P a g e

    improvedfamilywellbeingandtheeconomyatlarge.Provision of adequate water supply will also reduce

    the time girls spend infetchingwaterallowingthemmoretimeforschoolwork. Girlseducationyieldsa

    higher rate of return than any other investment in developing countries. Educating girls has large social

    benefits in terms of savings from improved hygiene and birth control, as educated women choose to have

    fewer children. Bringing water closer to home and reducing the time girls have to spend fetching water

    therefore

    has

    a

    positive

    externality

    or

    benefit

    that

    accrues

    to

    society

    as

    a

    whole.

    Arguments

    of

    whether

    these

    benefits are public or private are issues of concern in the literature. But the fact that improved water

    supply and sanitation provide health benefits to society as awholeisapparentandundisputable.

    1.3Objectives

    ToknowabouteconomicsfactorinvolvedinwaterSupplyanditsproperdisposal Tounderstandthecostfactor,economicandfinancialbenefitsinvolvedinawatersupplyprojects

    1.4Scopeandlimitation

    The study is an attempt to understand the economic principles behind public water supply systemtakingthereferenceofMelamchiWaterSupplyProject

    Thestudyisconductedwithinaveryshortperiodoftimedependinguponreadymadedata. The study of MWSP project has been done taking the reference of financial and economic analysis

    carriedoutattimeofADBsfundingoftheproject.Theprojecthasgonethroughseveralchanges in

    policies,budgetandstrategywithinthatperiod.

    1.5Methodologies

    Theadoptedmethodologiesareasfollows:

    A.SelectionoftheTopic:

    Throughtherigorousgroupdiscussion,thetopicEconomicsofwatersupplyprojectsfortheseminarwasselected.

    B.Literature

    Review:

    Referencebooksand relatedpaperswerestudiedandplanningwasdone for the interpretation of the raw

    data.

    C.Datacollection:

    TheSecondarydatawascollectedfromtheinternetsources.

    D.Analysis:

    Analysisofdataintermsofeconomicsaspects

    E.DataPresentation:

  • 8/8/2019 Economics of Water Supply

    4/27

    EconomicsofWaterAllocation

    4|P a g e

    The raw data was analyzed and developed in a form of graphical representation. Conclusion and

    recommendationareextractedfromcasestudy.

    CHAPTER2|WATERANDWATERSUPPLY

    2.1Water

    sources

    2.1.1Surfacewater

    Theseareopensourcesofwaterwhichincludesriver,ponds,streamsetc.Theyareusuallythemainsources

    ofwater forwater supply system.Since theyareexposed toair, they aregenerallypollutedandshouldbe

    firstly purified, collected before distributing. The main sources of water in Nepals Context are rivers. The

    presenceofHimalayasmakesNepalrichinwaterresources.Theriversarefedthroughmeltingofsnowinthe

    Himalayas.Riversarerenewablesourceofwater.Water isavailablefromtheseriversalltheyearroundbut

    duringrainyseasonswaterlevelishigher.Thismakesthesurfacewatermostfeasibleforuseinwatersupply

    watersystem.

    2.1.2GroundWater

    Groundwatercanbeacheapandreliablesourceofwaterwhereitisavailable.Groundwatercanbeobtained

    thoughwellordeepboring(byhandpumps).Groundwaterisusuallycleanfromimpuritiesbutitmaycontain

    dissolved salts, mineralsand sometimes harmful metals likearsenic. Ingeneral,groundwater is safer from

    pollutionwhen the aquifer isdeepand confined; even then it isadvisable touseground water forgeneral

    purposeotherthandrinking.i.e.nonpotableuse.Onedrawbackofgroundwater isthat it isnotrenewable

    naturallyinashortperiodandextremerelianceanduseofgroundwatercancausegeologicaldisorder.One

    waytotacklethisproblemisbyrecharginggroundwaterduringrainyseasonsbyrainwater.

    2.1.3RainWater

    Rainwater istheultimatesourceofwaterwhich feedstheentiresecondarysource includingSurfacewater

    and Ground water. Even though it is primary source of water, practical implementation of rain water

    harvestingwasnotseenuntilrecently.Directcollectionanduseofrainwaterishowever,widelypracticedat

    aninformallevelbyhouseholders.Althoughitcannotbeconsideredasreliablesourceofwater,thefactthat

    itisrenewableandfreesourceofwatermakesitimportantsourceofwater.

    2.2Watersupplysystem

    2.2.1Stateownedsystem

    Sincewatersupplysystemisextremelycapitalintensive,andthefinancialbenefitsachievedarealsolowbut

    theeconomicalbenefitsthatthewatersupplyprojectsprovideareofmajorimportance.Itisthemainreason

    whymostwatersupplyprojectsaremainlycarriedoutbythegovernment.

    The main goal of the state owned system is to provide service to general public. It is however usually

    inefficient,nonflexibleandnonresponsive.

  • 8/8/2019 Economics of Water Supply

    5/27

    EconomicsofWaterAllocation

    5|P a g e

    2.2.2Privatesystem

    Beingaprofitbasedsystem,itisefficient,responsiveandfeasible.Howeverprivatesystemmaynotlookafter

    environmentalandsustainabilityfactorbecausethemainaimisprofit.

    ExampleofPrivatesystemisGroundwatersupplyinapartmentsthroughdeepboringandothermeans.Since

    profit is main factor, environmental issues such as making retention pond , ground water recharging are

    usuallynot

    covered

    2.2.3PublicPrivatePartnershipsystem

    PPPisthenewmodelforimplementingpublicprojects.ThemainideaofPPPmodelisthattheprivatesector,

    community organizations and non government and government organizations should be partners in

    development.TheMillenniumDevelopmentGoal (MDG)AssessmentStudy forNepalestimated that33per

    cent of the expenditure necessary to achieve the MDGs will have to come from nongovernment sources.

    Publicprivate

    partnerships

    are

    one

    of

    the

    means

    of

    achieving

    this.

    A.DefinitionofPublicPrivatePartnerships

    There isnoclearagreementonwhatdoesandwhatdoesnotconstituteapublicprivatepartnership (PPP).

    UnderatypicalPPPscheme,thegovernmentspecifiestheservicesitwantstheprivatesectortodeliver,and

    then the private partner designs and builds an asset for that purpose, finances its construction, and

    subsequently operates the asset and provides the services deriving from it. This contrasts with traditional

    public investmentwherethegovernmentdesignsandfinancesanassetandthencontractswiththeprivate

    sectortobuildit.

    In most cases, the government then operates the asset once it is built. The difference between these two

    approaches reflects a belief that giving the private sector combined responsibility for designing, building,

    financing,andoperatinganassetisasourceoftheincreasedefficiencyinservicedeliverythatjustifiesPPPs.

    B.StakeholdersofPublicPrivatePartnership

    The Partnership generics evolve from the possible linkages among the stakeholders involved in the UWM

    System.

    In

    general,

    there

    are

    three

    major

    groups

    of

    stakeholders

    and

    three

    categories

    of

    partnerships

    linkages.ThePPP isparticularlyknownaspartnershipbetweentheGovernmentandthePrivateSector.This

    categoryofpartnershipisthepartofconcernandwillbediscussedmoreindepth.

    TheothertwoformsofpartnershipbetweentheGovernmentandtheCommunities,andpartnershipbetween

    the Private Sector and the communities or Civil Society are not discussed. The partnership between the

    GovernmentandtheCivilSocieties isbasedonthepolicyoftheGovernmentonparticularsectorto include

    andempowertheCivilSocietieswhenrequired.

  • 8/8/2019 Economics of Water Supply

    6/27

    EconomicsofWaterAllocation

    6|P a g e

    The partnership between Business and Civil Societies is based on the Social and Corporate Responsibility

    policyadoptedbytheBusinesshousesandbecomestheir internalmatter.However,the latesttwoformsof

    partnership are more conveniently understood based on the modalities discussed for Public Private

    Partnership.

    C.PublicPrivatePartnershipStructure

    The stakeholder under the Government category included the Central and Local Government Bodies as

    Ministries, Departments, Municipalities, DDC and VDC. The Donor Agencies and other Government Owned

    Agenciesalsofallunderthiscategory.ThesecondcategoryofstakeholderistheFormalandInformalPrivate

    Sector comprising of profit making and nonprofit making organizations as business houses, industries,

    companies,enterprises,serviceproviders,NGO,CBO,andindividuals.Thethirdcategoryofstakeholdersisthe

    consumers comprising of service users from Government to citizens who are responsible for generation of

    waste.

    D.PartnershipDevelopmentApproach

    Theapproaches

    of

    Partnership

    Development

    are

    TopDownApproachwheretheGovernmenttakesinitiativesandcallforPartnership.

    SuchinitiativesarealmostrareunlessitismediatedandpressurizedbytheCivilSocieties.

    Bottom Up Approach This requires influenceonPolicy, PlansandPrograms of the Governmentand very

    difficulttoachieve.

    Lateral Approach This approach is not dependent on Government Policy. Mostly it is carried out by the

    CommunitiesandPrivateSectoratgrassrootlevelfollowingtheirCorporateandIdealisticResponsibility.The

    LateralPartnership

    has

    very

    strong

    effect

    on

    Government

    Policy

    depending

    upon

    the

    strength

    and

    extends

    of

    spatialcoverageofmembershipof thepartnership.The recentpoliticalchanges inNepalcouldattribute to

    this form of partnership where the communities and individual informal partners united for achieving a

    particulargoalofpoliticalchange.

  • 8/8/2019 Economics of Water Supply

    7/27

    EconomicsofWaterAllocation

    7|P a g e

    CHAPTER3.0|ECONOMYBEHINDWATERSUPPLY

    3.1FactorsinvolvedinwaterSupply

    Followingfactorsaretobeanalyzedbeforemakingeconomicalanalysisofwatersupplysystem

    A. Water supply and Sanitary are interconnected with each other. Once water is delivered to household,itisboundtogeneratewastewater.Thewatersupplycostshouldincludetheprovisionandcost

    ofremovalandtreatmentofwastewatergenerated.

    B. Watersupplyandsanitationservicesarebroadlyconceivedashugesocietalenterprise.Itsdaytodayneedanditsrequirementforlotsofdaytodayactivitiesforallsectorsofsocietymakesitaimportant

    partofurbanecology.Reliableandefficientwatersupplyisgoodmeasureofadevelopedandhealthy

    society.

    ForanexampleifwecomparethewatersupplyandsanitationsystemofEuropeancitiesandcitiesof

    developingnationslikeKathmanduwecanseehugedifferenceinqualityofservicewhichreflectsthe

    developmentconditionofsociety.

    C. Theprovisionofwaterandsanitationservicesisverycapitalintensive.Moreover,inmanycasesthereare significant economies of scale, and the physical capital tends to be longlived. This has several

    important implications. It iscritical togetthe investmentplanningdecisions rightbecauseonecan

    makebigmistakesbyoverbuilding,bybuildingtoofarinadvanceofdemand,bybuildingfacilitiesthat

    noonewants,orbyfailingtomaintainandoperatesuchcapitalintensivefacilitiesefficiently.

    Foranexample,inKathmanduValley,wherewatersupplyisintermittent,majorcauseforinefficient

    distributionofwaterislackofeffectivevalvesystem.Duetothesehouseholdsnearthereservoirare

    always getting excess water while those away from it are getting none at all. Although initial

    investmentmaybeonhigherend,usingvalveandtwopipesystemsmaybeabetterchoicehere.

    D. Household demand for very small quantities of drinking water is extremely price inelastic becausepeople must have water to live. If there are no other sources of water, the amount of money

    someone will pay for 34 liters of water per day is limited only by his/her income. This extremely

    inelasticdemandforsmallquantitiescoupledwithshortagesofwatersupplycancombinetocreate

    situationsinthedevelopingworldthatarebeyondtheexperienceofpeopleinrichercountries.

    Forexample,insomeplacesinruralTanzaniaa20literbucketofwatercancostadayswagesofan

    unskilled laborer. Youcantakeyourchoice:walkalldayforwater,orworkallday inthefieldsand

    buyabucketofwater.

    E. Thefactthatthepriceinelasticityforsmallquantitiesofwaterissolow,andtheprovisionofservicesis very capital intensive, the water supply system provides large opportunities for bribery and

    kickbacksonconstructioncontractsandequipmentpurchases. Theseproblemsgreatly increasethe

    transactioncostsofdoingbusiness,andthusthetotalcostofprovidingimprovedwaterandsanitation

    servicesinmanydevelopingcountries.

  • 8/8/2019 Economics of Water Supply

    8/27

    EconomicsofWaterAllocation

    8|P a g e

    ForExample,oneofthecauses forcost increaseandsubsequentdelay inconstructionofMelamchi

    WaterSupplyProjectisduetocorruptionduringvariousphasesofconstruction.

    F. Water isverydifferent than electricpowerwhen itcomes tostorageand transport.Thestorageofwaterisrelativelyeasy,whiletransportingwaterlongdistancestourbancentersisexpensivebecause

    waterissovoluminous. Withelectricity,bycontrast,storageisexpensiveandtransportationiseasy.

    Becausewater

    is

    typically

    expensive

    to

    transport

    long

    distances,

    it

    can

    be

    prohibitively

    expensive

    to

    providecustomerswithveryhighlevelsofservicereliability.

    3.2FinancialandEconomicAnalysis

    3.2.1WithandWithoutProjectCases

    Afterchoosingthebestamongalternatives,thenextstepistotestthefinancial and economic viability of

    the project, which is the chosen, leastcost alternative. The initial step in testing the financial and

    economicviabilityofaprojectistoidentifyandquantifythecostsandbenefits.

    To identify project costs and benefits and to compare the net benefit flows, the withoutproject

    situationshouldbecomparedwiththewithprojectsituation.Thewithoutprojectsituation isdifferentfrom

    thebeforeprojectsituation. Thewithoutproject situation is that one which would prevail without the

    project visvisfactors likepopulation increase.Aswater isgettingscarcer,thewaterusepatternandthe

    costarealsolikelytochange.

    3.2.2FinancialVsEconomicAnalysis

    Financial

    and

    economic

    analyses

    have

    similar

    features.

    Both

    estimate

    the

    net

    benefits

    of

    an

    investment

    projectbasedonthedifferencebetweenthewithprojectandthewithoutprojectsituations.

    However, the concept of financial net benefit is not the same aseconomicnetbenefit. Whilefinancial

    netbenefitprovidesameasureofthecommercial(financial)viabilityoftheprojectontheprojectoperating

    entity,economicnetbenefitindicatestherealworthofaprojecttothecountry.

    Financialandeconomicanalysesarealsocomplementary. Foraprojecttobeeconomicallyviable,itmustbe

    financially sustainable. If a project is not financially sustainable, there will be no adequate funds to

    properly operate, maintain and replace assets; thus the quality of the water service will deteriorate,

    eventuallyaffecting

    demand

    and

    the

    realization

    of

    financial

    revenues

    and

    economic

    benefits.

    It has sometimes been suggested that financial viability not be made aconcernbecauseas longasa

    projectiseconomicallysound,itcanbesupportedthroughgovernment subsidies. However, in most cases,

    governments face severe budgetaryconstraints and consequently, the affected project entity may run

    into severe liquidityproblems,therebyjeopardizingevenitseconomicviability.

    The basic difference between the financial and economic benefitcostanalysesoftheprojectisthatthe

    former compares benefits and costs to the enterprise in constant financial prices, while the latter

    compares the benefits and costs to the whole economy measured in constant economic prices.

    Financial prices are market prices of goods and services that include the effects of government

    intervention anddistortions inthemarketstructure. Economicpricesreflectthetruecostandvaluetothe

  • 8/8/2019 Economics of Water Supply

    9/27

    EconomicsofWaterAllocation

    9|P a g e

    economy of goods and services after adjustment for the effects of government intervention and

    distortions in the market structure through shadow pricing of the financialprices. Insuchanalyses,

    depreciationcharges,sunkcostsandexpectedchangesinthegeneralpriceshouldnotbeincluded.

    In financial analysis, the taxes and subsidies included in the price ofgoodsandservicesareintegralparts

    offinancialprices,buttheyaretreateddifferently ineconomic analysis. Financialandeconomicanalyses

    alsodiffer

    in

    their

    treatment

    of

    external

    effects

    (benefits

    and

    costs),

    favorable

    effects

    on

    health

    and

    the

    UFW

    ofaWSP.

    Economicanalysisattemptstovaluesuchexternalities,healtheffectsandnontechnicallosses.

    3.2.3Financialvs.EconomicViability

    Thestepsindeterminingthefinancialviabilityoftheproposedprojectinclude:

    (i) Identifyingandquantifyingthecostsandrevenues;

    (ii) Calculatingtheprojectnetbenefits;

    (iii) Estimatingtheaverageincrementalfinancialcost,financialnetpresentvalueandfinancialinternalrate

    ofreturn(FIRR).

    TheFIRR istherateofreturnatwhichthepresentvalueofthestreamof incrementalnetflows infinancial

    prices iszero. If the FIRR isequal toor greater than the financial opportunitycostofcapital, theproject is

    consideredfinanciallyviable. Thus,financialbenefitcostanalysiscoverstheprofitabilityaspectoftheproject.

    Thestepsindeterminingtheeconomicviabilityofaprojectincludethefollowing:

    (i) Identifyingandquantifying(inphysicalterms)thecostsandbenefits;

    (ii) Valuingthecostsandbenefits,totheextentfeasible,inmonetaryterms;and

    (iii) Estimating the EIRR or economic net present value (NPV) discounted at EOCC = 12% by comparing

    benefitswiththecosts.

    The EIRR is the rate of return for which the present value of the netbenefit stream becomes zero, or

    at which the present value of thebenefit stream is equal to the present value of the cost stream. For

    aprojecttobeacceptable,theEIRRshouldbegreaterthantheeconomicopportunitycostofcapital.TheBank

    uses12%

    as

    the

    minimum

    rate

    of

    return

    for

    projects;

    but

    for

    projects

    with

    considerable

    no

    quantifiablebenefits,10%maybeacceptable.

    3.2.4ProceduresforEconomicAnalysis

    The economic analysis of a Water Supply Projects (urban or rural) has to follow a sequence of

    interrelated steps:

    A. DefiningtheprojectobjectivesandeconomicrationaleUnderthiswillbedefiningthemaingoaloftheproject,whyitisneededandhowitwillbeachieved.

    To acquire theknowledgeabout the physical features,present situation regarding existing facilities

  • 8/8/2019 Economics of Water Supply

    10/27

    EconomicsofWaterAllocation

    10|P a g e

    andtheiruseconstraints(ifany)againsttheiroptimaluse,thecommunitiesandtheirsocioeconomic

    conditions,surveysandfieldvisitsneedtobedone.

    Foranexample if thearea is ruralorbasedoneconomiccondition of thehousehold in thearea,a

    community taps serving few household may be more beneficial socioeconomically than providing

    individualtaps

    B. Demandanalysisandforecastingeffectivedemandforprojectoutputs.This is to be based on either secondary information sources or socioeconomic and other

    surveysintheprojectarea.Demandofwaterisdependedonthetariffrateofwater.Thedemandof

    water also fluctuates withseasonand on the timeofa day. The project needs to access the peak

    demand.

    C. Establishing the gap between future demand and supply from existing facilities after ensuring theiroptimum

    use.

    Forexampleifthefuturedemandofwaterofanarea(ascalculatedfromthesurvey)isexpectedtobe

    16mlpd and existing facilities provides around 5mlpd with their optimum use then water supply

    systemwhichcanprovideadditional11mlpdwillberequired.

    The optimal use of facilities (if applicable) here need to be achieved through physical and policy

    related measures. The physical measures are like leakage control, replacing faulty valves and

    adequatemaintenanceandoperation, (unlessnewnetworksystemsareproposed forwatersupply)

    etc; policy measurescan be charging an economically efficient tariffand implementing institutional

    reforms.

    D. Identifying project alternatives to meet the above gap in terms oftechnology,process,scaleandlocationthroughaleastcostand/orcostEffectivenessanalysisusingeconomicpricesforallinputs.

    This includesshort listingand identifyingthe leastcostalternativeofachievingtherequiredoutput.

    Allthelifecyclecosts(marketandnonmarket)associatedwitheachalternativearetobetakeninto

    account.

    Thealternativesarenottobeconfinedtotechnicalorphysicalelementsonly,e.g.,groundwateror

    surface water, gravity or pumping, large or small scale, etc. They can also include activities due to

    policy measures, e.g. leakage detection and control, institutional reforms and managerial

    reorganization.

    Foranexample,weassumethatcitiesneartheseascaneasilyaddress itswaterneed.Butmostof

    thetimeitisactuallycheapertouseothersourcesofwaterthantopurifyandremovesaltfromthe

    sea water (the process known as desalination) and distribute the desalinated water to higher level

    (sincesealevel liebelownormalland level).Theleastcostanalysisofdifferentprojectswillreveal if

    thewatersupplyprojectisfeasibleenoughtoimplementornot.

    E. Identifying benefits, both quantifiable and nonquantifiable, and determining whethereconomicbenefitsexceedeconomiccosts.

  • 8/8/2019 Economics of Water Supply

    11/27

    EconomicsofWaterAllocation

    11|P a g e

    Foranexample,whenthedamwasproposedforconstruction intheNarayaniRiver inChitwan,the

    financialstudyrevealedthattheprojectwouldreallytakealongtimetoattainthefinancialbreakeven

    state.Buttheprojectwasconsideredeconomicallyfeasibleduetofollowingreason

    Withthenewirrigationnetwork,thefarmerswillbeabletoproducemorecrops,whichwillresultinincrease ineconomicactivityand farmersenduppayingmore taxes.Alsoasasocialbenefitnation

    willget

    more

    food

    yield.

    These

    non

    market,

    economic

    and

    social

    benefits

    cannot

    be

    easily

    quantified

    butthesefactorsareconsideredforanalyzingofeconomicbenefitsoftheprojects.

    Generally,iftheaverageincomeofthefarmersintheareabeforetheprojectis5000permonthandifduetotheprojecttheycould increasetheircropyieldandearn incomeofaround15000permonth

    then10000 isconsideredaseconomicbenefitoftheproject. Intheabovecase ifthefarmerearns

    10000 more it is assumed that certain% (say 1020% i.e. 1000 to 2000) of the earned income will

    returntogovernmentintheformoftaxpaidwhichisconsideredasfinancialgaininthecaseofstate

    projects

    F. Assessing whether the projects net benefits will be sustainablethroughout the life of theproject

    through

    cost

    recovery,

    tariff

    and

    subsidy

    (if

    any)

    based

    on

    financial

    (liquidity)

    analysis

    and financialbenefitcostanalysis.

    Thebenefitsofthewatersupplyprojectsaremoreeconomicalandsocialthanfinancialbutgiventhat

    it isthestatewhichgenerally invests inwatersupplyprojectswhich lowpriorityof financialreturn.

    But for water supply projects to be sustainable, the operation and maintenance cost and future

    upgrading cost has to be provided by the end users. Failing to achieve this will make the project

    unfeasibleevenatcostofitssocialbenefits.

    In case of above example of water supply for irrigation in Chitwan thorough Narayani river, the

    farmershas

    to

    pay

    the

    charges

    for

    using

    water

    for

    irrigation.

    Prices

    are

    charged

    as

    per

    unit

    of

    land

    irrigated.ThiscostcollectedshouldcovertheO&Mcostoftheprojectsotheproject is financially

    sustainablethroughoutthelifeofproject.

    G. Testingforrisksassociatedwiththeprojectthroughsensitivityandriskanalyses.IncalculatingtheEIRRorENPVforWSPs,themost likelyvaluesofthevariablesare incorporated in

    the cost and benefit streams. Future values are difficult to predict and there will always be some

    uncertaintyabouttheprojectresults. Sensitivity analysis is therefore undertaken to identify those

    benefit and costparametersthatarebothuncertainandtowhichEIRRandFIRRaresensitive.

    AsensitivityindicatorshowsthepercentagechangeinNPV(or EIRR) to the percentagechange in a

    selectedvariable.Ahighvaluefortheindicatorindicatesprojectsensitivitytothevariable.Measures

    minimizing against major sources of uncertainty are incorporated into the project design, thus

    improvingit.

    For an example some of the variable that may affect the water supply projects includes long term

    reliabilityofwatersource,WTP(Willingnesstopay)factorsoftheconsumer,thegovernmentpolicies

    andeconomicabilityofthegovernment,politicalstabilityofthecountrywhichshouldbetaken into

    account.

  • 8/8/2019 Economics of Water Supply

    12/27

    EconomicsofWaterAllocation

    12|P a g e

    3.3CostinvolvedinWaterSupplySystem

    Assaidearlier,developmentofwatersupplysystemisextremelycapitalintensive.Thetreatmentanddelivery

    ofwatertothehouseholdsandremovalandtreatmentofthewastewatergeneratedcostseriousmoney.The

    financialbenefitsachievedarealsolowbuttheeconomicalbenefitsthatthewatersupplyprojectsprovideare

    of major importance. It is the main reason why water supply projects are mainly carried out by the

    government.The

    private

    sectors

    (whose

    main

    goal

    is

    profit)

    hence

    generally

    refrain

    for

    water

    supply

    projects

    unlesslowinterestdonationsandgrantsareinvolvedintheproject.

    3.3.1MarketCosts

    Theeconomiccostsofprovidingahouseholdwithmodernwaterandsanitationservicesarethesumofseven

    principalcomponents:

    A. Opportunitycostsofdivertingrawwaterfromalternativeusestothehousehold (orresourcerents)If,forexample,adrinkingwaterprojectuses raw water diverted from agriculture, theuseofthis

    water

    for

    drinking

    will

    result

    in

    a

    loss

    for

    farmers.

    These

    costs

    are

    measured

    as

    the

    opportunity

    cost

    of water which, in this example, equals the benefits foregone of the use of that water in

    agriculture.

    B. StorageandtransmissionofuntreatedwatertotheurbanareaThis includes cost in construction and operation of infrastructure used for trapping and storing

    (pumps,dams)thewatersourceandtransmissionofthewatertotheareaofdistribution.

    C. TreatmentofrawwatertodrinkingwaterstandardsThemostcommonlyadoptedandcheapmethodhereissandfiltrationandchlorination.

    D. DistributionoftreatedwaterwithintheurbanareatothehouseholdMakingSupplyNetworkandprovidinghouseholdconnectionsofthetreatedwatercompriseamajor

    costcomponent.

    E. Collectionofwastewaterfromthehousehold(seweragecollection)F. Treatmentofwastewater(sewagetreatment)G. Anyremainingcostsordamagesimposedonothersbythedischargeoftreatedwastewater(negative

    externalities).

  • 8/8/2019 Economics of Water Supply

    13/27

    EconomicsofWaterAllocation

    13|P a g e

    Table1.Costestimates:improvedwaterandsanitationservices

    No. Costcomponent US$perm3 %oftotal

    1 Opportunitycostofrawwatersupply 0.05 2%

    2 Storageandtransmissiontotreatmentplant 0.15 6%

    3 Treatmenttodrinkingwaterstandards 0.15 6%

    4 Distribution of water to households (including

    houseconnections)

    0.75 30%

    5 Collection of waste water from home and

    conveyancetowastewatertreatmentplant

    1.00 40%

    6

    Wastewatertreatment

    0.35

    14%

    7 Damages associated with discharge of treated

    wastewater

    0.05 2%

    Total 2.50 100%

    Table1presentssome illustrativeaverageunitcostsforeachofthesesevencostcomponents,expressed in

    U.S.dollarspercubicmeter. Thecostestimates inTable1 includebothcapitalexpensesandoperationand

    maintenanceexpenses. Thecalculationofannualcapitalcostsusesacapitalrecoveryfactorof0.12,assuming

    adiscountrateof10%andanaveragelifeofcapitalequipmentandfacilitiesof20years.

    Theunitcostsofthesedifferentcostcomponentscouldvarywidely indifferent locations.Forexample, ina

    locationwithabundantfreshwatersupplies,item1(theopportunitycostofdivertingwaterfromexistingor

    future users to the potential target group) and item 7 (the damages imposed by the discharge of treated

    wastewater) may, in fact, be very low or even zero. However, in more and more places these opportunity

    costsassociatedwithwaterdiversionandtheexternalitiesfromwastewaterdischargearebeginningtoloom

    large.

    Some

    cost

    components

    are

    subject

    to

    significant

    economies

    of

    scale,

    particularly

    storage

    and

    transmission

    (item2),thetreatmentofrawwatertodrinkingwaterstandards(item3),andthetreatmentofsewage(item

    6).Thismeansthatthelargerthequantityofwaterorwastewatertreated,thelowertheperunitcost.Onthe

    other hand, some cost components are experiencing diseconomies of scale. As large cities go farther and

    fartherawayinsearchofadditionalfreshwatersupplies,andgoodreservoirsitesbecomehardertofind,the

    unitcostofstoringandtransportingrawwatertoacommunity increases.Therearealsotradeoffsbetween

    differentcostcomponents:onecanbereduced,butonlyattheexpenseofanother.Forexample,wastewater

    canreceiveonlyprimarytreatment,whichismuchcheaperthansecondarytreatment;butthenthenegative

    externalitiesassociatedwithwastewaterdischargewillincrease.

  • 8/8/2019 Economics of Water Supply

    14/27

    EconomicsofWaterAllocation

    14|P a g e

    Theopportunitycostsofrawwatersupplies(item1)arestillquitelowinmostplaces,ontheorderofafew

    centspercubicmeter.Even inplaceswhereurbanwatersuppliesarediverted from irrigatedagricultureor

    valuableenvironmentalassets,theunitcostswillrarelybeaboveUS$0.25percubicmeter.

    Rawwaterstorageandtransmissionandsubsequenttreatment(items2and3)willtypicallycostUS$0.30per

    cubic meter. Within a city, the water distribution, collection and conveyance of sewage to a wastewater

    treatmentplant

    (item

    5)

    is

    even

    more

    expensive

    than

    the

    water

    distribution;

    this

    will

    cost

    about

    US$1.00

    per

    cubic meter, 40% of the total cost. Secondary wastewater treatment (item 6) will cost about US$ 0.35 per

    cubic meter. Damages resulting from the discharge of treated wastewater are very sitespecific, but

    environmentalistscorrectlyremindusthatthattheycanbesignificant.

    Asshown,totaleconomiccostscomestoaboutUS$2.50percubicmeterinmostlocation.Howeverthisvalue

    isboundtochangedependingonvariousfactors.Forexample,insmallcommunitiesinthemountainousareas

    ofUpperNepal,costofWaterandSanitaryservicescaneasilybedoubleor tripletheseamountspercubic

    meter.(Source:DesigningOptimalWaterSupplySystemforDevelopingcountries)

    Otherfactors

    which

    affect

    the

    economic

    cost

    of

    water

    includes

    the

    following:

    3.3.2NonMarketCosts

    Subsidies

    Generally inDevelopingCountries,thesubsidiesprovidedtoconsumersofwaterandsanitationservicesare

    not only huge, but also regressive. It is often not politically desirable for the majority of people to

    understand that middle and upperincome households, who generally use more water, are thus actually

    receivingthemostbenefitfromsubsidies.Mostfundamentally,poorhouseholdsareoftennotconnectedto

    theW&S

    network

    at

    all

    and

    hence

    cannot

    receive

    the

    subsidized

    services.

    Even

    ifthey

    do

    have

    connections,

    thepooruselesswaterthanricherhouseholds,thusreceivinglowerabsoluteamountsofsubsidy.

    For an example, the tariff rate of water for Nepal is among lowest in Asia due to subsidy provided by

    GovernmentwhichstandasRs80forunmeteredtapsandmaximumof250(Rs50forsewerage)formetered

    taps.ThepeopleofKathmanduareunwillingtopaymoretariffsforwatersupplyduetounreliabilityofthe

    service.Thiscoupledwithhighratiooflossduetoexistinguseofoldpipeisleadingtofailureofexistingwater

    supplysysteminitssocialgoalandfinancially.

    SustainabilityCost

    Itcanbereferredcostadded toensurethe futureavailabilityof resourceandensure itssustainability.This

    specially applies to ground water whose excessive use can decrease the ground water table, making the

    groundwaterdifficulttoobtainornotavailableatallinthefuture.Hence,tocopewithsuchsituation,special

    costcalledScarcityPremiumisaddedtotheresources.

    EnvironmentalCost

    Thisincludesthecosttocompensatefortheenvironmentalimpact(ifany)resultingduetouseofwaterfrom

    thesourceandduetowastewaterdischarge.

    Foran

    example,

    using

    water

    from

    the

    wetland

    for

    irrigation

    may

    disturb

    the

    ecosystem

    of

    the

    wetlands.

    The

    environmentalcosthelpstocompensateforsuchimpacts

  • 8/8/2019 Economics of Water Supply

    15/27

    EconomicsofWaterAllocation

    15|P a g e

    3.4CostRecovery

    In general, the cost of the water supply project is expected to be recovered by increasing the tariff rate.

    Whereas there is cost recovery in most of the countries (Capital, O & M, Debt services etc), in developing

    countries

    it

    is

    not

    always

    so.

    The

    greater

    gap

    between

    cost

    and

    prices

    leads

    to

    lower

    service

    reliability

    and

    sustainability.

    Most of the time, in developing countries, the cost of the project is not expected ot be recovered. The

    government invests itsowncapital for the project,and the cost collected is used to cover thepresent and

    future operation and maintenance goals only. The goal here is to achieve economic feasibility rather than

    financial.

    CHAPTER4|WATERSUPPLYSYSTEMINKATHMANDU

    4.1WaterSupply

    In KMC, water is supplied by Nepal Water and Sewerage Corporation (NWSC) and private tanker services.

    Besides these there are few community based supply system for specific towns and villages. For example

    Siddhipur Water Supply project carried out by combined effort of NGOs, Community and Local level

    Governemnt. Inadditiontothat,many industries,hotels,hospitalsanda largenumberofhouseholdsusea

    hugeamountofgroundwaterextractedbypumping.

    The

    existing

    water

    pricing

    policy

    in

    the

    Kathmandu

    is

    partly

    based

    on

    block

    rate

    tariff(BRT)

    mechanism,

    althoughtheusersschargefailstocoverthecostofservicesortogeneraterevenueforevvectivetreatment

    of available water supply and augment new water sources. In KMC, the tariff rate charged by NWSC is as

    follows

    4.2Currentdrinkingwatertariffs

    Pipe

    size

    (in

    inch)

    Minimum

    consumption

    (ltr)

    MinimumtariffinNRs Effective from 17th

    September 2004 as per volume

    ofwater(priceper1000Liters)

    Household

    Government,Institutional&

    public

    Commercial&

    industrial

    Household Government,institutional&

    public

    Commercial&

    industrial

    10,000 50 50 50 15 15 15

    27,000 810 810 810 30 30 30

    1 56,000 1,680 1,680 1,680 30 30 30

    1.5 155,000 4,650 4,650 4,650 30 30 30

    2 320,000 9,600 9,600 9,600 30 30 30

    3 881,000 26,430 26,430 26,430 30 30 30

    4 1,810,000 54,300 54,300 54,300 30 30 30

    ForthosehouseholdwhodoesntowemeterhavetopayminimumRs552.00/month.

  • 8/8/2019 Economics of Water Supply

    16/27

    EconomicsofWaterAllocation

    16|P a g e

    WatersuppliedbyNSWCorprivatetankersorextractedandusedbyvarious institutionsorhouseholdsare

    neither controlled by a uniform law nor well managed by the existing institutions. It was nationally and

    internationallyacceptedthattheproblemofwatersupplybothinquantityandqualityarebasicallyduetothe

    organizational and functional weakness of the major supplier of water, namely, Nepal Water Supply and

    Sewerage Board which was reorganized as Nepal Water Supply Corporation in 1989 (NWSC). In order to

    improve

    the

    situation,

    donors

    expressed

    the

    opinion

    that

    HMG/Nepal

    should

    bring

    in

    a

    private

    operator

    (PO)

    to manage the water system assets and made this a condition for loans and grants. Taking this fact into

    consideration,HisMajestyofGovernmentofNepal(HMG/N)thenproposedthreemajorreformsanddecided

    Tobringinprivatecompanytomanagethewatersupplystaffandequipment Torepair,upgradeandexpandthepresentwatersupplynetwork;and ToconstructatunnelfromtheMelamchivalleytobringinmorewater.

    Allthesereformsrequiredahugeamountofmoney.Thetotalcostofthereformwasestimatedtobearound

    US$

    468

    million

    and

    is

    expected

    to

    be

    financed

    by

    loans

    (59%),

    grants

    (11%)

    and

    HMG/N

    (30%)

    to

    be

    spent

    between2002and2007.Thisappearstobeaveryexpensiveproject(US$300perpersoninthevalley).The

    rolesofpublicandprivatesectorsintheabovereformprocesscanbeunderstoodclearlyfromthefollowing

    allocationsoffunds:

    ForprivatecompanyUS$4milliontobespentundercertaincondition ForsystemupgradingUS$136million ForMelamchitunnelUS$328million

    CHAPTER5.0|MELAMCHIWATERSUPPLYPROJECT

    5.1Background

    In 1988, the Government of Nepal decided that a tunnel should be built from the Melamchi Valley to the

    Kathmandu Valley to improve the water supply in Kathmandu, Nepals capital city. The Melamchi Water

    SupplyProject(MWSP)wasinitiallyfundedbya$71millionloanfromtheWorldBank.However,sevenyears

    latertheprojectstalledwhenitwasrevealedthatafractionofthisamounthadactuallybeenspent.

    TheWorldBankdemandedthatanoperatorfromtheprivatesectorbebroughtinbeforefurtherfundingwas

    offered. This condition remained when the World Bank withdrew and the Asian Development Bank (ADB)

    becamethemaindonor.By2006,SevernTrentWater Internationalwastheonlycompanytohavemadea

    validbidfortheproject.

    TheMWSPwasanexpensiveprojectfundedbyanextensiveforeignloan,whichthegovernmentwouldhave

    to repay. The tunnel was taking years to happen and there was concern that the ordinary people of

    Kathmandu,especiallythe40,000poorcitizens livingwithoutawaterconnection,wouldhavenosay inthe

    designandplanningoftheprojectandnoshareinitspotentialbenefits.

  • 8/8/2019 Economics of Water Supply

    17/27

    EconomicsofWaterAllocation

    17|P a g e

    Since1973,thegovernmentofNepalhasdoneseveralstudiesandimplementedtheschemestofindoutthe

    bestsolutiontomeetthewatersupplydemandfortherapidgrowthofpopulationintheKatmanduvalley.In

    1988,morespecificpre feasibilitystudieswerecarriedoutforthewatersupplysourcesforthevalley.Based

    onthesestudies,theMelamchischemewas identifiedas thebest longtermsolution tosolve theconstant

    watershortageinthevalley.Subsequently,in1997,thegovernmentestablishedtheMelamchiwaterLimited

    to

    seek

    funding

    for

    and

    implement

    the

    Melamchi

    Water

    Supply

    Project.

    In

    1998,

    it

    was

    replaced

    by

    the

    MelamchiWaterSupply Development Board (MWSDB)while somekeydonors,suchasAsianDevelopment

    Bank, Governments of Japan and Norway took interest in funding the project. Currently the government,

    throughMWSDBisimplementingtheproject.

    5.2Introduction

    MelamchiWaterSupplyProject ismuchdebated

    megaproject.Theprojectwasvisualizedin1973.

    It is an alternative to address acute water

    problems of Capital Kathmandu. The Project is

    located in Sindhupalchok District, but covers

    Kavrepalanchok, Kathmandu, Lalitpur and

    Bhaktapur.5100MillionLitterswaterperdaywill

    bedivertedfromsnowfedMelamchi, Larkeand

    YangririverstoKTM.InKathmandu,perday180

    MillionLiterswaterisnecessary.

    The Melamchi Water Supply Project and

    institutional reformswerecarried forward in the period inaccordancewith thegovernments twopronged

    strategytoachievesustainableandconsumerorientedwatersupplyandsanitationservicesintheKathmandu

    Valley.

    TheMelamchiWaterSupplyProjectwillbeimplementedwithhighprioritytoprovidealongtermsustainable

    bulk water supply in the Kathmandu Valley. The tunnel excavation works will be carried forward and

    remaining road works are also being completed. Preparatory works will also be undertaken towards the

    constructionofa170MLDWaterTreatmentPlant inKathmanduValley.Theoperationsofthewatersupply

    andsanitation

    services

    will

    be

    handed

    over

    to

    the

    Kathmandu

    Upatyaka

    Khanepani

    Limited

    (KUKL).

    A

    major

    program for repair, replacement,rehabilitationandexpansionof theageolddistributionsystem isplanned

    andbeingworkedouttocontrolleaks.Institutionalefficiencywillalsobeincreased.

    5.3ProjectAimsandObjectives

    Withthestartingoftheproject,ithadfollowingobjectives:

    SolvethechronicwatersupplyshortageandimprovethewatersupplyinKathmandu(KTM) Valley Rehabilitateand/orreplaceexistingwatersupplynetworkandassociatedequipment

  • 8/8/2019 Economics of Water Supply

    18/27

    EconomicsofWaterAllocation

    18|P a g e

    Provideaccesstocleanandsafewatersupplyensuringgoodhealthsanitation Establishefficientwatersupplynetworkingsystemonasustainablebasis Reducewaterpollutionthroughestablishmentofsewer andwastewatertreatmentplants To improveriverecology,religioussites,andculturalGhats locatedatriverbanksbyaugmentingwater

    flowat

    Bagmati

    and

    its

    tributaries

    ToexpandthedepletinggroundwatersourcesofKTM5.4MWSP:CostEstimation

    The total project cost was originally estimated at US$464 million; JBIC,Norway and Sweden agreed toco

    financetheproject.Tunnelconstructionwouldcover32%ofthetotalcost,rehabilitationofthenetwork,46%,

    and the management contract plus institutional reforms, 4%. The World Bank earlier agreed to provide

    financialsupporttothePSPprocessbutpulledout inmid2002;ADBthencame intohelppreparea5year

    managementcontract.

    Themaincostitems(basecosts)aretheMDS($74.29million),WTP($39.33million),BDS($48.47million),and

    thedistributionnetworkimprovements($65.95million).Thefollowingtablegivesasummaryoftheestimated

    costs:

    ItemForeign

    Exchange

    Local

    CurrencyTotalcost

    A. Base

    1.InfrastructureImprovements 193.03 83.36 276.39

    2.SocialandEnvironmentalSupport 2.10 10.34 12.44

    3.Institutionalreforms 1.80 0.76 2.56

    4.ProjectImplementationSupport 24.89 7.74 32.63

    Subtotal(A) 221.82 102.2 324.02

    B. Contingencies

    1.Physical 22.20 10.20 32.40

    2.Price 21.40 9.40 30.80

    Subtotal(B) 43.6 19.6 63.2

    C.

    Interestduring

    Construction

    and

    Fees

    7.60

    33.20

    40.80

    D. Taxesandduties 0.00 36.00 36.00

    Total 273.00 191.00 464.00

    Percent 58.80 41.20 100

    FullcostrecoveryforurbanwatersuppliesisamongthereformsinstitutedthroughtheMelamchiproject.In

    2004, the government decided to increase prices annually by 15%. For the past two years the tariff has

    remainedthesame,whichmeansthenext increasewouldbeawhopping30%.ConsumerspayingRs50for

    10,000liters,

    for

    instance,

    would

    have

    to

    pay

    Rs

    66.

  • 8/8/2019 Economics of Water Supply

    19/27

    EconomicsofWaterAllocation

    19|P a g e

    Sector

    AvailableBudget BudgetRequiredas

    perThreeYear

    InterimPlan

    ResourceGap

    FY 000

    Waterand

    Sanitation

    Sector

    2007/08 2316231 4270234 1954003

    2008/09

    2547854

    6618883

    4071029

    2009/10 2802640 6618883 3816243

    Total 7666725 17508000 9841275

    The estimated project cost is US$ 465 million. The Donors for the project are ADB, JBIC (Japanese Bank of

    International Cooperation), NORAD (Norwegian Agency for International Cooperation), SIDA (Swedish

    InternationalDevelopmentCooperationAgency.AsianDevelopmentBank(ADB)iskeydonorandfundingon

    followingcomponents:

    A. ConstructionB. SocialandEnvironmentC. Consultant

    ThemainloanfortheprojectwillbeprovidedbyAsianDevelopmentBank.TheloanofSpecialDrawingRight

    (SDR) 93,253,000.00 ($120.0 million equivalent)willbeprovidedwith a termof30 years including agrace

    period of 8 years, and an interest charge of 1% per annum during the grace period and 1.5% per annum

    thereafter.TheADBfundsfortheProjectaswellasallotherfundswillbeprovidedtotheutilityinanequal

    mixofloanandgrant.Interestfortheloanwillbeat8%perannumrepayableover20yearsincluding7years

    ofgrace.

    5.5FinancialAnalysis5.5.1CostRecoveryPolicyandAssumptions

  • 8/8/2019 Economics of Water Supply

    20/27

    EconomicsofWaterAllocation

    20|P a g e

    Duringthepreprojectperiod,averagetariffsareexpectedtorise fromNRs6.9/m3 in2000toNRs12.8/m3 in

    2006(in2000prices)tomeetcashO&Mcostsaswellas

    private operator and regulatory costs. The financial

    projectionsassume:

    Improvedcollectionefficiency; Meteredstandpipeschargedatthelifelinerate; Usersmeetingpaymentobligations; Groundwater charges for nondomestic

    consumers;

    Wastewaterchargedasa50%surchargeonthewater tariff. Postproject, average tariffswill be

    nrs23.0/m3 by 2008, adequate to cover O &M,

    debt

    servicing,regulatory,

    and

    private

    operator

    costs. All nondomestic use of groundwater is

    assumedtoceaseby2008.

    5.5.2FinancialInternalRateofReturn

    The overall financial internal rate of return for the

    Projectis

    4.7%.

    This

    may

    be

    compared

    with

    aweighted

    averagecostofcapitalfortheProjectof0%,wherethe

    onlending rate is 8% and domestic inflation is 8%

    resulting in a real interest rate of 0%. Similar to other

    urbanwatersupplyprojects,thefinancialinternalrateof

    return showed sensitivity to increases in capital costs

    andrevenues.

    5.5.3FinancialSustainability

    Thereare

    mainly

    three

    aspects

    of

    financial

    sustainability

    inconnectionwithMWSP:

    (i) Project funding and fiscal impact on government

    budget.WSPsarefrequentlyfundedbythegovernment

    and full cost recovery especially from poor water users may not be possible even for their basic minimum

    needs.

    (ii)Fullorpartialcostrecoveryofprojectcostsfromprojectbeneficiaries.WSPs,likeprojectsinothersectors,

    canhardlybesustainedongovernmentsubsidyalone,withouttherevenuegenerationfromthesectoritself.

    Costrecoveryandproperdesignofwatertariffbasedonthecostsofsupplyarerequired.

    WTPandCostrecovery

    In1989,The town in Indonesiawasfacingwith

    sameproblemascurrentlyfaced inKathmandu.

    The water supply system was unreliable,

    inefficient and owning to these facts people

    were unwilling to pay more tariff for water

    supply. Although water use was 38 m3 per

    household,therewas largenoofhouseholdnot

    getting water at all and those getting it ware

    misusingitowningtolowtariff

    The old water supply system was becoming a

    failureinitssocialgoalandfinancialparttoo.

    To improvethissituation, thegovernmentafter

    heavy investment, introducedanewer,efficient

    andreliablewatersupplysystemtothecity.The

    tariff was increased by 115%for domestic use

    and 170% for non domestic use. Given the

    reliabilityandeffectivenessofnew services the

    peoplewerewillingtopayforit.

    Theincreaseintariffratemadetheconsumption

    ofwaterperhousehold todropform38m3per

    month to 27 m3per month. The water loss in

    new systemwas significantly lesserandproject

    was successful both economically and

    financially.

    Hence Willingness to Pay (WTP)factorplays a

    major role incost recoveryofprojectandprice

    increase with proper and reliable service

    increasesthepeoplesWTPfactor

    (Developing optimized water supply system for

    developingcountriesbyGraceUkoliOnodipe)

  • 8/8/2019 Economics of Water Supply

    21/27

    EconomicsofWaterAllocation

    21|P a g e

    (iii)Financialincentivesarenecessarytoensureparticipationintheprojectofallstakeholders.Inthecontext

    ofaWSP,theparticipantsinclude:

    lenderswholendmoneyforcapitalinvestment guarantors who guarantee the loan (In public projects like WSPs, the government is often the

    guarantor)

    suppliers

    of

    inputs

    to

    the

    project

    users of project output (households/industries); and the organization which sponsors and runs theproject(waterenterprise)

    5.6EconomicAnalysis

    5.6.1withandWithouttheProject

    The withoutproject option offers a very miserable scenario for Kathmandu Valley. Since NWSC would be

    unable tomeetdemand,pipedwaterdeliverywouldcontinue tobe limited to less than2hoursevery two

    days, pressures and water quality would be poor, and inequality would persist for water distribution.

    Therefore,theeconomicpriceofwaterwouldrisefromNRs40/m3currentlytoNRs110/m3in2012.

    A number of alternative options, including invalley storages were considered, but were found to be

    impractical because of various shortcomings, such as high financial and social costs, low yield, and other

    problemsassociatedwithpopulationdensityand landuse.Theproposeddesign involvesa lowleveltunnel,

    no

    impoundment

    storage,

    and

    no

    hydropower,

    and

    was

    considered

    a

    leastcost

    and

    least

    environmentally

    disruptiveoption.Furthermore,itretainstheoptionforlowcostgravityexpansionofsupplyfromtheYangri

    andLarkeriversandinvalleystorageinthefuture.

    5.6.2EconomicInternalRateofReturn

    Theeconomicevaluationassumesbaseeconomiccostsof$322millionandincrementalO&Mcostsat1%of

    totalcostsplus$0.04/m3ofwaterproduction.Astandardconversionfactorof0.9isassumed.Totalcostsare

    highbecause

    of

    the

    need

    to

    provide

    asound

    basis

    for

    future

    expansion.

    Benefits

    are

    estimated

    at

    NRs1,500

    million/yearinitiallyandincreasetoaboutNRs6,000million/yearinsubsequentyears.

    Theeconomicinternalrateofreturn(EIRR)fortheProject(with170MLDcapacity)is13.5%,whiletheEIRRfor

    thefulldevelopmentis15.3%.TheEIRRwastestedforsensitivitytotarifflevels,waterlosses,incomegrowth,

    nondomestictariffs,andcapitalcosts.TheEIRR isestimatedtobe10.1%atthecurrentwater loss figureof

    40%,11.9%withrealincomegrowthreducedto1%peryear,12.9%witha50%decreaseinthenondomestic

    tariffs,and12.6%witha10%increaseincapitalcosts.

  • 8/8/2019 Economics of Water Supply

    22/27

    EconomicsofWaterAllocation

    22|P a g e

    5.7ProjectBenefit

    TheProjectsprimarytargetpopulationisthe1.5millionpeople(180,000households)livingintheKathmandu

    Valley. The urban inhabitants will benefit from improved water supply services with better water quality,

    increasedquantity, improvedsupply,extendedserviceareas,moreequitablewaterdistribution,andbetter

    customerservices.Thesebenefitswillgohandinhandwithraisedpublichealth,hygiene,andenvironmental

    awareness,

    and

    improved

    sanitation

    facilities

    and

    maintenance.

    The

    Project

    will

    also

    accumulate

    positive

    socioeconomicandpovertyreductionbenefitstotheMelamchiValleypopulation(40,000).Thesewillinclude

    increased incomes from the expanded market and upgraded skills, reduced workload for women, better

    educationforchildren,andreducedincidenceoftraffickingofgirls.

    Benefittothosepeopleresidingintheareabygettingadequatesupplyofwater Water supply within the context of comprehensive water resource management, institutional and

    sectoradministrationresponsibilities,

    Levelsofserviceincludingthosetotheurbanpoor Capitalinvestmentmechanismsanddevelopmentplans Privatesectorparticipation Subsidiesandcostrecoveryobjectives Humanresourcesdevelopment Publicawarenessandhygieneeducation Promotes the efficient use of potable water, with less ground water extraction, resulting in

    environmentalbenefits

    Withtheintroductionoftheprojectandthesystemupgrade,peoplewouldbewillingtopaymoreforthefacility,helpingineconomicfeasibility.

    5.8Other

    factors

    5.8.1IssuesinMelamchiImplementation

    Breakevenpointwilltakemanyyearstoachieve Expensiveconsume80%oftotalinvestmentonwater DiversionofMelamchirivereffectsthelivelihoodofpeopleandecologyofthearea

    5.8.2Impactonpoverty

    Socioeconomic surveys conducted during project preparation suggest that about 20% of households in

    KathmanduValleyliveinpoverty,withincomeslessthanNRs6,000permonth.Themajorprojectbenefitsare

    savingsandincrementalbenefitsaccumulatingtowaterusersandtotheeconomy,fromtheimprovedwater

    supplyandmanagement.Anexaminationofthedemandcurves indicatesthatthenetbenefitaccruingtoa

    poorhousehold (benefit lesstariffpaid) isaboutthesameasthataccruingtoanotsopoorhousehold,but

    thecompositionofthebenefits isdifferent.Thepoorhouseholdhasasmallabsolutesavingsbenefitanda

    large absolute incremental benefit. Assuming a single rate tariff, the distribution of the net benefits to

    consumers isaboutequaltothedistributionofthepopulation.However,therelative impactonthepoor is

    better,with impact ratios ofnetbenefit over incomeestimatedat1.6 for thepoorand0.4 for thenotso

    poor.Assumingasteppedtariffstructure,theimpactratioforthepoorincreasesto1.8,whilethatforthenot

    sopoor

    decreases

    to

    0.3.

  • 8/8/2019 Economics of Water Supply

    23/27

    EconomicsofWaterAllocation

    23|P a g e

    5.11Costestimates

    Theprojectisestimatedtocost$464million includingcontingencies,interestduringconstruction,andtaxes

    andduties.Foreignexchangecostsareestimatedat59%oftotalcosts,localcurrencycostsat41%.

    CHAPTER6|CONCLUSION

    The benefits achieved from water supply projects should be measured more in terms ofsocial andeconomicalfactorsratherthanfinancial

    Subsidiesmayberequired forequity inwaterdistribution,butnottotheextentthatthispromotesmisuseandincreasesburdenonthesystem

    Participation of local communities during both design and implementation is crucial for projectefficiency,sustainabilityandsuccess.

    ProjectdesignshouldinstituteappropriateO&Mmechanismsandproperlydelineateresponsibilities. Good governance and anticorruption measures contribute to a more favorable project

    implementationenvironment.

    Private sector participation should be encouraged, especially in the marketing, distribution, andmaintenanceofprojectoutputs.

  • 8/8/2019 Economics of Water Supply

    24/27

    REFERENCES:

    1. PlanningapproachesinNepal Dr.JibgarJoshi

    2. HandbookfortheEconomicAnalysisofWaterSupplyProjects AsianDevelopmentBank

    3.

    Report

    and

    recommendation

    of

    the

    president

    to

    the

    board

    of

    directors

    on

    a

    proposed

    loan

    to

    the

    kingdomofNepalfortheMelamchiwatersupplyproject AsianDevelopmentBank

    4. Designingoptimalwatersupplysystems fordevelopingcountries GraceUkoliOnodipe,B.Sc.,M.S.

    5. The Economic Costs and Benefits of Investments in Municipal Water and Sanitation Infrastructure: A

    GlobalPerspective Dale WhittingtonandW.M.Hanemann

    6. Lecturenotes ProvidedbyDr.JibgarJoshi

  • 8/8/2019 Economics of Water Supply

    25/27

    ACKNOWLEDGEMENT

    Our sincere appreciation goes to Mr. Jibgar Joshi, course coordinator of Economics, for his

    encouragement in preparing this seminar report. His valuable guidance, suggestions and

    wholeheartedsupportishighlyappreciable.

    Wehighlyappreciatetimelyassistanceprovidedbyguestlecturer,Mr.TopeBahadurBasnet for

    hisvaluableguidanceandsuggestions.

    We would also like to thank program coordinator Mr. Ajaya Chandra Lal, Mr. Sudarshan

    Raghubanshi , Mr. Suresh G.C and Mrs. Leela Pandey for their valuable supports and

    cooperation.

    Last but not the least we would like to express our sincere gratitude to all our friends who

    helpedustopreparethisreport.

  • 8/8/2019 Economics of Water Supply

    26/27

    LISTOFACRONYMS

    ADB AsianDevelopmentBank

    EIA EnvironmentalImpactAssessment

    NWSC NepalWaterandSewerageCorporation

    NWSC

    NepalWater

    Supply

    Corporation

    KMC KathmanduMetropolitanCity

    HMG HisMajestyofGovernment

    WSP WaterSupplyProject

    IRR InternalRateofReturn

    FIRR FinancialInternalRateofReturn

    EIRR

    EnvironmentalInternal

    Rate

    of

    Return

    NPV NetPresentValue

    WTP WillingnessToPlay

    MWSP MelamchiWaterSupplyProject

    MWSDB MelamchiWaterSupplyDevelopmentProject

    KUKL KathmanduUpatyakaKhanepaniLimited

    JBIC JapaneseBankofInternationalCooperation

    NORAD NorwegianAgencyforInternationalCooperation

    SIDA SwedishInternationalDevelopmentCooperationAgency

    O&M OperationandMaintenance

    PPP PublicPrivatePartnership

    BDS BulkDistributionSystem

    MLPD MillionLitersPerDay

    VDC

    VillageDevelopment

    Committee

    PO PrivateOperator

  • 8/8/2019 Economics of Water Supply

    27/27

    TableOfContents

    Chapter1|INTRODUCTION...................................................................................................................................2

    1.1Background..................................................................................................................................................2

    1.2Introduction Wateraseconomiccommodity............................................................................................2

    1.3Objectives

    .....................................................................................................................................................

    3

    1.4Scopeandlimitation.....................................................................................................................................3

    1.5Methodologies.............................................................................................................................................3

    Chapter2|WATERANDWATERSUPPLY..............................................................................................................4

    2.1Watersources..............................................................................................................................................4

    2.2Watersupplysystem....................................................................................................................................4

    Chapter3.0|ECONOMYBEHINDWATERSUPPLY................................................................................................7

    3.1FactorsinvolvedinwaterSupply.................................................................................................................7

    3.2FinancialandEconomicAnalysis..................................................................................................................8

    3.3CostinvolvedinWaterSupplySystem.......................................................................................................12

    3.4CostRecovery.............................................................................................................................................15

    Chapter4|WATERSUPPLYSYSTEMINKATHMANDU........................................................................................15

    4.1WaterSupply..............................................................................................................................................15

    4.2Currentdrinkingwatertariffs....................................................................................................................15

    Chapter5.0|MELAMCHIWATERSUPPLYPROJECT............................................................................................16

    5.1Background................................................................................................................................................16

    5.2Introduction...............................................................................................................................................17

    5.3ProjectAimsandObjectives.......................................................................................................................17

    5.4MWSP:CostEstimation..............................................................................................................................18

    5.5Financial

    Analysis

    .......................................................................................................................................

    19

    5.6EconomicAnalysis......................................................................................................................................21

    5.7ProjectBenefit............................................................................................................................................22

    5.8Otherfactors..............................................................................................................................................22

    5.11Costestimates..........................................................................................................................................23

    Chapter6|CONCLUSION....................................................................................................................................23

    References:...........................................................................................................................................................24