Upload
ngoduong
View
224
Download
4
Embed Size (px)
Citation preview
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015)
113
Economic Solution of Super Structure for Bridge of 20m Span Natraj Singh
1, Dr. N.P. Devgan
2, Dr. A. M. Kalra
3
1Dy. Chief Project Manager (IRSE), Dedicated Freight Corridor Corporation of India Ltd., Old Railway Colony, Near Anand
Market, Ambala Cantt.-133001, India 2Senior Structural Consultant, PEC-Centre for Consultancy Engineering, PEC University of Technology, Sector-12,
Chandigarh- 160012, India 3Formerly Prof. in Civil Engineering Department, PEC University of Technology, Sector-12, Chandigarh- 160012, India
Abstract- The present study aims at exploring the
economical solution for superstructure of 20m span bridges
among reinforced concrete T-beam, reinforced concrete I-
beam, prestressed concrete I-beam and steel composite I-
beam. The analysis and design is done under Indian Road
Congress (IRC) loading for selection of most economical
section for all four types of super structures. The effects of the
placement of span are also studied in details for normal
ground condition as well as launching above the Railway line.
In normal ground conditions, reinforced concrete T-beam &
prestressed concrete I-beam are found to be economical.
Whereas in case of above railway line prestressed concrete I-
beam proves to be more economical than other options
considered for the study. When the effect of speed restriction
is also combined with the traffic block cost then the composite
steel girder becomes the most economical option but when the
effect of periodic maintenance is also added, it becomes
costliest option. The effect of sacrificial type of shuttering is
also considered for the cost implication and this is found to be
cheaper in case of bridges over railway lines. The present
paper will facilitate as a hand on tool for selection of
economical superstructure type for 20m span bridges.
Keywords- Prestressed concrete I-beam, railway block cost,
reinforced concrete T-beam, reinforced concrete I- beam,
sacrificial shuttering, steel composite I-beam.
I. INTRODUCTION
The pace of infrastructure development in India has
increased to cope with the requirements of developing
country. The projected gross domestic product (GDP)
growth is likely to remain in double digit in near future.
This increased pace of Infrastructure development has put
lot of thrust on human as well as material resources. In
modern era of growth in Infrastructure field related to road
and rail sector, bridges consume substantial share of
resources and sometimes play a critical role in working out
the economic viability of the project. To meet the growing
demand, infrastructure has to be developed by optimizing
the resources.
Keeping in view the fund constraints faced by
infrastructure organisations, the present study aims to
develop an economic solution for construction of
superstructure for 20m span bridge under Indian Road
Congress (IRC) loading. Four different superstructure
types have been chosen for the economic analysis namely,
reinforced concrete T-beam, reinforced concrete I- beam,
prestressed concrete I-beam and steel composite I-beam.
The design of all the options is based on Indian Road
Congress (IRC) codes. The effects of placement of span in
normal conditions and launching above the railway line
have different cost implications because cost associated
with the Traffic block has a substantial cost share in
launching process. There is another aspect of speed
restriction imposed on the goods and passenger trains
during placement of span, which led to the huge monitory
loss to the Indian railways. Thus an attempt is made in this
study to quantify the cost associated with the traffic block
and the speed restriction. Another important aspect is the
use of sacrificial shuttering in combination with
conventional shuttering and its effects are explored from
the economy point of view.
II. REVIEW OF LITERATURE
Many options are available to the planners with the
advancement in design and construction technology. The
decision of choosing the best option among the available
alternatives is guided by the principal of utilisation of
minimum resources.
The researchers in the past had tried to find economic
solutions for specific conditions. Saxena, et. al.,(2013)
studied and compared the economics of T-beam and box
girder for bridge structure of 25m span. The comparison
shows that the T-beam girder bridge is more economical,
however; for the span length more than 25m the box Girder
is found to be more suitable. Misal et. al., (2014) analyzed
and designed the presstressed box girders and I-section for
span of 16.3m and 31.4m and concluded that; the box
girder is costlier than the I girder, but for the larger spans
this result may not stand true.
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015)
114
One important study about the life cycle cost is done by
Huang, et. al. for new highway bridge in Taiwan. Three
alternatives, namely the pre-stressed concrete bridge, the
steel bridges with painting, and the steel bridge with
galvanization, are considered for the new bridge and are
evaluated for their life cycle cost. The study reveals that the
life cycle cost of steel bridge is always higher than of Pre-
stressed concrete bridge and pre-stressed concrete bridge
has the lowest life-cycle cost.
The efforts of planners to reach at optimal solutions for
specific bridges are well established. In most of the cases of
cost analysis, generally two options of materials or shapes
are taken and no specific stress on erection/launching
methods is taken into account for comparison. Further in
road over bridges (above railway track), the impact of
traffic block cost on overall construction cost also needs
evaluation. Broadly, so far cost analysis of bridges is
carried with specific location and two variables.
III. DESIGN PHILOSOPHY
The super structure having 21.96m total span and 20.0m
effective span is individually analyzed by the grillage
analysis using main girders along the longitudinal direction
and slabs in the transverse direction.
The system, being a 4 girder system with spacing of
2.65m, is supported with bearings below each girder, is
analyzed separately under dead load of girder. The clear
carriageway is 7.5m and total width of Super structure is
kept 12.0m.The footpath is provided on both sides.
Composite action is considered for the slab load, super
imposed dead load and live loads. Slabs are provided
sloped in the direction of required camber. Girders are
accordingly raised with higher pedestals. Live loads are run
in position concentric to all the 4 girders, and combinations
are worked out based on the minimum distance between the
two lanes.
The depth of deck slab has been kept constant in all the
options. The depth of girders have been chosen on the basis
of guiding formulas and the section properties of all the
four different options have been given in the table I.
TABLE I
SECTIONAL PROPERTIES OF GIRDERS CONSIDERED FOR COMPARISON
No Description
Unit
RCC-
I
Sect.
RCC-
T
beam
PSC-I
Sec.
Steel
Comp.
1 Depth of
deck slab m 0.25 0.25 0.25 0.25
2 Web depth m 1.80 2.25 1.56 1.35
3
Top Flange
width (at
mid span)
m 0.70 0.93 1.00 0.40
4
Web width
(at mid
span)
m 0.35 0.33 0.29 0.012
5 Web width
(at Support) m 0.70 0.63 0.80 0.012
6
Bottom
Flange
width (at
mid span)
m 0.70 0.63 0.80 0.60
7
Area of
section (at
Mid Span)
m2 1.52 1.40 1.40 0.09
8
Area of
section (at
Support)
m2 1.93 1.86 1.94 0.09s
9
Moment of
Inertia (Izz)
at Mid Span
m4 0.69 0.69 0.51 0.02
10
Moment of
Inertia (Izz)
at Support
m4 0.80 0.81 0.62 0.02
For reinforced concrete beams M35 grade of concrete
and for prestressed concrete M40 grade of concrete have
been considered. The grade of reinforcement has been kept
Fe500 for all the options.
After carrying out the analysis, the graphs are drawn for
design shear force and bending moments for various
combination of loads.
The behavior of all four types of beams under live load
for shear force and bending moment is almost similar.
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015)
115
Fig. 1: Shear force variation along the span of beam under dead load
only
Fig. 2: Shear force variation along the span of beam under super
imposed dead load.
Fig. 3: Shear force variation along the span of beam under live load.
Fig. 4: Bending moment variation along the span of beam under dead
load
Fig. 5: Bending moment variation along the span of beam under super
imposed dead load
Fig. 6: Bending moment variation along the span of beam under live
load
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015)
116
IV. CONSTRUCTION OF SUPERSTRUCTURE
The planning and coordination between the designer and
site engineers is very important because erection/placing of
span affects the overall cost in significant way. The
erection /placement of span depends upon the ground
conditions, volume of work, repetitive nature of work,
utilization of existing resources etc.
The construction of superstructure involves cast in situ
in case of T-Beam and casting or fabrication of span in
yard and placing it with hydraulic crane in other methods.
Normally in urban areas, the bridges are constructed for
grade separation or for crossing the Railway track. Hence,
following two ground conditions are considered.
A. Normal Ground Condition
In this condition, it is considered that the supporting
ground is having sufficient bearing capacity to support the
launching/erection crane and there is a sufficient space for
stabling the crane for launching without disturbing the local
traffic.
B. Above Railway Track
In this condition, it is considered that the supporting
ground is having sufficient bearing capacity but traffic
block from Railways is required for launching/erection of
super-structure.
Considering above mentioned two ground conditions,
following methods are adopted for erection/placement of
superstructure of 20 M span of bridge.
1. Using Form work (Cast in situ Beams and deck slab)
2. With land based hydraulic cranes (Pre-cast Beams and
Caste-in-situ deck slab)
V. ESTIMATION METHODOLOGY
All the major activities affecting the cost of super-
structure are bifurcated and effects of these activities are
analyzed while calculating the total cost of super-structure.
The activities are bifurcated on the basis of different
Ground Conditions. In this work, two type of shuttering
combinations are considered. In first case the conventional
shuttering is used for casting of girders and deck slab.
This will require placement of shuttering and de-
shuttering for both the girder and deck slab. In other case,
the combination of conventional and sacrificial shuttering
is considered in which conventional shuttering is opted for
the beams and sacrificial shuttering is opted for deck slab.
The sacrificial shuttering is left in place permanently and
will not require temporary support system. This system will
reduce the requirement of speed restriction. The various
steps involved in construction of superstructure common in
both the ground conditions and effects of conventional and
sacrificial shuttering with traffic block and speed restriction
are given in flow chart , i.e., Fig 7.
A. Estimation and Costing details
The estimation of resources and its costing has been
divided into various categories to appreciate effects of each
stage over total costing of super structure.The different
stages involved in estimation for both ground conditions
are shown in the flow chart, i.e., Fig 8.
The various stages of estimation and costing are
discussed below:
B. Attributed to Material Quantities
The quantities of materials have been calculated based
on design parameters. While considering the sacrificial
shuttering, the advantage of substituting the tensile
reinforcement in composite deck slab is not considered.
The quantities of shuttering materials are calculated based
on the two methods. In first method, conventional
shuttering is considered for girders and deck slab and in
second method, conventional shuttering for girders and
sacrificial shuttering for deck slab has been considered.
Among the four options used for comparison, the
superstructure with reinforced cement concrete-T bean is
constructed Caste-in-situ using conventional shuttering
both for girder and deck slab. In all other three options the
pre-caste/pre-fabricated girders are launched with the help
of crane. The casting of girders is done with the
conventional shuttering and the casting of deck slab has
been considered with two options, the first one with
conventional shuttering and second with the sacrificial
shuttering.
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015)
117
Fig: 7- Flow Chart for various steps of construction of superstructure.
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015)
118
Fig: 8- Flow Chart for Estimation and costing.
TABLE II
QUANTITIES OF MATERIALS REQUIRED FOR VARIOUS TYPE OF SUPER-STRUCTURES OF 20 M SPAN
No
Type of
Superstructur
e
Qty of Material per Span (Including Deck Slab Concrete)
Concrete
Reinforcement
Conventiona
l Shuttering
Combination of Shuttering Pre-
Stressing
Cable
Structural
Steel Conventional for
girders
Sacrificial for deck
slab
Unit Cum MT Sqm Sqm Sqm Kg. MT
1 RCC T-beam 159.0 29.0 680.0 680.0 0.0 0.0 0.0
2 RCC I-beam 173.0 38.0 644.0 427.0 217.0 0.0 0.0
3 PSC I-Section 162.0 19.5 563.0 373.0 190.0 3420.0 0.0
4 Composite
Steel girder and
RCC deck slab
62.0 9.5 243.0 0.00 243.0 0.00 35.0
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015)
119
The rates adopted for the estimation of cost are based on
the Bridge works executed by Indian Railways in Northern
Part of India. The old tender rates are updated based on
WPI index. For the sacrificial shuttering rates are taken
from market. The cost estimation for casting/ fabrication of
girders including deck slab considering conventional
shuttering only and combination of conventional and
sacrificial shuttering has been calculated by multiplying the
quantities (given in Table-II) with Cost and this cost is
considered same for both the cases, i.e., in normal ground
condition as well as above railway track.
C. Composite cost for Normal Ground Condition
To arrive at total cost, the estimation of machinery and
other resources required for launching of beams is
calculated for the normal ground condition.
It is considered that two cranes will work simultaneously
from both ends.
There is no constraint on working hours of crane and
sufficient space is available for working of cranes. The
crane capacity for reinforced concrete I- beam and
prestressed concrete I- beam is kept 75 MT which is more
than double the load to be carried. The rates for hiring of
cranes are taken from the market.
The Composite Steel girder having weight 8 MT is the
lightest among all the four options and launching cost of
Rs. 80,000.0 for composite steel girder is least among all
the categories considered. The launching cost of Rs.
3,00,000.0 for pre-stressed concrete beams having weight
65MT and reinforced concrete beams having weight 75
MT is same and is approximately 3.75 times the launching
cost of steel beams.
The total cost of superstructure in case of normal ground
conditions is calculated by adding the cost attributed to
material quantities, launching resources and other allied
activities.
TABLE III
COMPOSITE COST STATEMENT CONSISTING OF CONSTRUCTION/FABRICATION COST (MATERIAL COST )AND PLACEMENT COST IN CASE OF NORMAL
GROUND CONDITIONS (IN INDIAN RUPEES)
N
o
Type of
Superstructu
re
Construction/ Fabrication Cost
(material cost)
Launching
Cost by
Crane(placeme
nt cost)
Total Cost
Conventional
Shuttering
Combinati
on of
Shuttering
With Conventional
Shuttering
With Sacrificial
Shuttering
1 RCC T-beam 3341800 3341800 NA 3341800 3341800
2 RCC- I-beam 4041500 4160850 300000 4341500 4460850
3 PSC I-Section 3253000 3357500 300000 3553000 3657500
4
Composite
Steel and
RCC Girder
3797200 3857950 80000 3877200 3937950
D. Composite cost above Railway Track
To arrive at total cost in this case, the cost of railway
traffic block and cost associated with speed restrictions and
launching is considered. The Railway traffic block due to
detention of moving trains plays significant role in the total
cost of super structure. Presently, there are no clear
guidelines to charge the cost effect of speed restriction in
addition to the traffic block cost.
The railway traffic block cost depends upon no of trains
plying in the section. This cost of block per hour has been
calculated for trains varying from 20 to 80 running on
section per 24 hours. The cost associated with speed
restriction of 20 Kmph in a stretch of 100 meters has also
been calculated.
The work of placement of spans above railway track will
be carried out during the traffic block. There is provision of
extra crane to meet out any failure during the block period.
The capacity of extra crane is kept the same to utilize in
case of defect in the regular working crane. Two Crane will
work simultaneously from both ends and third crane will be
kept as stand by. It is assumed that work of placement of
girders in the traffic block will be completed in two days.
The cost of hiring of cranes is taken for complete job per
span, which is Rs. 6, 00,000.0 for reinforced & prestressed
beams and Rs. 1, 60,000.0 for steel composite beams.
The cost of placement of super-structure includes cost of
launching and block cost. Here cost of speed restriction is
not included.
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015)
120
The cost of placement for all the four options of super-
structure is calculated by adding the cost of launching and
cost of traffic block for various frequencies of running of
trains in a section.
From the table IV, it is clear that cost of placement is
less in case of RCC T Beam and steel composite girders.
The cost of placement of RCC I Beam and PSC I Section is
same but is higher than the other two options. As the
frequency of trains increases in a section, the difference in
cost in the placement of girders for options 1 & 4 and 2 & 3
increases sharply.
The total cost of Super-Structure above Railway Track is
calculated by adding the construction/fabrication cost of
girders, launching cost of girders, Cast-In-Situ cost (T
Beam), and Railway Traffic Block cost. This total cost of
Super-Structure has been calculated for both combinations
of shuttering and various frequencies of trains in a section.
This cost comparison does not include the cost of speed
restriction and the affect of sacrificial shuttering is not
appreciable in the table VA & VB.
TABLE IV
COST STATEMENT CONSISTING OF PLACEMENT OF SPAN INCLUDING LAUNCHING COST AND BLOCK COST ABOVE RAILWAY TRACK (IN INDIAN RUPEES)
S
N
o
Type of
Superstructur
e
Block
Duratio
n (in
hours)
Total Cost for Placement of Span
20 Trains per
day
35 Trains per
day
50 Trains per
day
65 Trains per
day
80 Trains per
day
1 RCC T-beam 2 4137036 7009383 9881731 12754078 15626426
2 RCC- I-beam 3 6805553 7609383 15422596 19731118 24039639
3 PSC I-Section 3 6805553 7609383 15422596 19731118 24039639
4
Composite
Steel and RCC
Girder
2 4297036 7169383 10041731 12914078 15786426
TABLE VA .
COMPOSITE COST STATEMENT CONSISTING OF CONSTRUCTION/FABRICATION COST (MATERIAL COST) AND PLACEMENT COST ABOVE RAILWAY TRACK
(IN INDIAN RUPEES)
No
Type of Super-
Structure
20 Trains per day 35 Trains per day 50 Trains per day
with
Conventional
Shuttering
with
Sacrificial
Shuttering
with
Conventional
Shuttering
with
Sacrificial
Shuttering
with
Conventional
Shuttering
with
Sacrificial
Shuttering
1 RCC T-beam 7478836 7478836 10351183 10351183 13223531 13223531
2 RCC- I-beam 10847053 10966403 11650883 11770233 19464096 19583446
3 PSC I-Section 10058553 10163053 10862383 10966883 18675596 18780096
4
Composite
Steel and RCC
Girder
8094236 8154986 10966583 11027333 13838931 13899681
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015)
121
TABLE VB
COMPOSITE COST STATEMENT CONSISTING OF CONSTRUCTION/FABRICATION COST (MATERIAL COST) AND PLACEMENT COST ABOVE RAILWAY
TRACK (IN INDIAN RUPEES)
No Type of Superstructure
65 Trains per day 80 Trains per day
with Conventional
Shuttering
with Sacrificial
Shuttering
with Conventional
Shuttering
with Sacrificial
Shuttering
1 RCC T-beam 16095878 16095878 18968226 18968226
2 RCC- I-beam 23772618 23891968 28081139 28200489
3 PSC I-Section 22984118 23088618 27292639 27397139
4 Composite Steel and RCC
Girder 16711278 16772028 19583626 19644376
To understand the benefits of sacrificial shuttering, the
affect of cost of speed restriction imposed during the
construction of Super-Structure is added in the already
calculated total cost vide table VA-VB . It is assumed that
speed restriction of 20 KMPH for conventional shuttering
of deck slab will be imposed for 45 days for reinforced
concrete T-beam and 21 days for other three types of
superstructure.
This time period will remain same for reinforced
concrete T- beam and will be reduced to 07 days for
sacrificial shuttering of deck slab for other three types. In
Table No. VI the cost has been calculated for conventional
shuttering only.
Table No. VII shows total cost for placement of super-
structure including the cost of speed restriction imposed for
combination of conventional shuttering for girder &
sacrificial shuttering for deck slab.
TABLE VI
COMPOSITE COST STATEMENT CONSISTING OF CONSTRUCTION/FABRICATION COST (MATERIAL COST), PLACEMENT COST AND SPEED RESTRICTION
COST ABOVE RAILWAY TRACK (CONVENTIONAL SHUTTERING) IN INDIAN RUPEES
No Type of Superstructure 20 Trains per
day
35 Trains per
day
50 Trains per
day
65 Trains per
day
80 Trains per day
1 RCC T-beam 14485354 21128511 27771674 34414831 41057995
2 RCC- I-beam 14116762 16680303 26253230 32321462 38389698
3 PSC I-Section 13328262 15891803 25464730 31532962 37601198
4 Composite Steel and RCC
Girder 11363944 15996003 20628064 25260123 29892185
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015)
122
TABLE VII
COMPOSITE COST STATEMENT CONSISTING OF CONSTRUCTION/FABRICATION COST (MATERIAL COST), PLACEMENT COST AND SPEED RESTRICTION
COST ABOVE RAILWAY TRACK (COMBINATION OF SACRIFICIAL SHUTTERING) IN INDIAN RUPEES
No Type of Superstructure 20 Trains per
day
35 Trains per
day
50 Trains per
day
65 Trains per
day
80 Trains per day
1 RCC T-beam 14485354 21128511 27771674 34414831 41057995
2 RCC- I-beam 12056306 13446706 21846491 26741583 31636675
3 PSC I-Section 11252956 12643356 21043141 25938233 30833325
4 Composite Steel and RCC
Girder 9244888 12703806 16162725 19621643 23080562
The total cost for the reinforced concrete T- beam
remains same in table VI & VII, because caste-in-situ
construction of reinforced concrete T- beam considered
with conventional shuttering only. There will be no
advantage of using sacrificial shuttering in this case,
because speed restriction will remain in place due to the
erection of staging along the track for support of cast-in-
situ beam.
E. Maintenance Cost
Among the four options used for comparison, only
composite steel beam will require periodic painting and
maintenance. All other three options are being constructed
with cement concrete and will not require any periodic
maintenance as concrete structures are considered free from
maintenance. The normal frequency for painting of steel
structure of the bridge is as taken as 6 years.
The total area of the steel composite girders for complete
super structure is calculated as 437.0Sqm, and the cost per
unit area of painting has been arrived at Rs. 115.0 per sqm
as per the current prevailing rates. It is assumed that the
bridge will be painted 16 times in its life span of 100 years.
By considering 5% yearly inflation in the rates, the total
cost of all the 16 cycles of paintings comes out to Rs.
14273117.
F. Effect of web-depth of girder on bridge approaches
It is clear from the table I, that the web-depth varies
considerably in all four superstructure types. The maximum
web depth is of reinforced concrete T-beam among all the
four options. The extra cost required for more height of
approaches due to increase in web depth in case of T-beam
in comparison with all other three options is tabulated in
table VIII.
TABLE VIII
EXTRA COST OF MATERIAL CONSUMED IN APPROACHES BY THE REINFORCED CONCRETE T-BEAM IN COMPARISON WITH OTHER OPTIONS DUE TO
DIFFERENCE IN WEB-DEPTH.
No Cost details Reinforced cement I-
beam
Prestressed I-
beam
Steel composite I-beam
1 Cost of Retaining wall
a. with Reinforced Earth wall 94500 144900 189000
b. with Reinforced Concrete wall 216000 331200 432000
2 Cost of Filling material 48600 74520 97200
3 Total cost with RE wall 143100 219420 286200
4 Total Cost with RC wall 264600 405720 529200
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015)
123
VI. CONCLUSIONS
The conclusions are drawn for different ground
conditions, different shuttering types, different shapes and
their effects on approaches. The lifecycle cost of
superstructure considering the initial capital cost and
periodic maintenance cost is considered for evaluating
various options.
A. Normal ground conditions
1. Considering total capital cost
From Table III, it is clear that the total cost of
superstructure consisting of fabrication/casting cost
(Material Cost ) and placement cost in normal ground
conditions using conventional shuttering is minimum for
reinforced cement concrete-T beam and the total cost using
combination of conventional and sacrificial shuttering is
also minimum for reinforced cement concrete-T beam
among the four options used for comparison.
In normal ground conditions, the total superstructure
cost with sacrificial shuttering is higher than the total cost
with conventional shuttering. However, the difference in
both the cases is small, but where the time is essence for
early completion of the project; the sacrificial shuttering
may proves to be better choice.
2. Considering maintenance cost(Life Cycle Cost)
Considering the periodic maintenance requirement, the
composite steel I-beam becomes the costliest option and
reinforced concrete T beam is again the most economical
option among all the four superstructure types.
3. Considering the effects on approaches
After adding the additional cost of approaches due to
increase in the height of superstructure, the cost of
superstructure with reinforced concrete T-beam and
prestressed concrete I-beam is almost same subject to the
condition that, approaches are built with reinforced earth
walls. If the approaches are built with reinforced concrete
retaining wall then prestressed concrete I-beam is the most
economical option.
B. Above railway track
1. Considering total capital cost
From Table V-A & V-B, it is clear that the total cost of
superstructure consisting of fabrication/casting cost
(Material Cost) and placement cost (launching cost
including railway block Cost), using conventional
shuttering as well as combination of conventional and
sacrificial shuttering; is minimum for reinforced concrete-
T beam among the four options used for comparison.
It is important to mention that the cost is considerably
less in case of reinforced concreteT- beam being case-in-
situ.
From table V-A & V-B, it is clear that among the
options of pre-casted/pre-fabricated, the cost of Composite
steel girder is lowest in both the cases, i.e. with
conventional and with sacrificial shuttering. With increase
in number of trains per day in the section the cost
implication is increased considerably, but the Composite
steel girder remains the cheapest. The reinforced concrete-
I beam and pre-stressed concrete-I girders are costliest with
little cost difference between them.
From table VI, it is clear that the total cost of
superstructure consisting of fabrication/casting cost
(Material Cost), placement cost (launching cost,railway
block Cost and speed restriction cost), using conventional
shuttering; the cost of Composite steel girder is lowest.
With increase in no of trains per day in the section the cost
implication is increased considerably, but the Composite
steel girder remains the cheapest. The reinforced concrete-
T beam is the costliest due to imposition of longer duration
of speed restriction for casting of deck slab.
From table VII, it is clear that the total cost of
superstructure consisting of fabrication/casting cost
(Material Cost), placement cost( launching cost, railway
block Cost and speed restriction cost), using combination
of conventional and sacrificial shuttering; the cost of
Composite steel girder is lowest. With increase in no of
trains per day in the section the cost implication is
increased considerably, but the Composite steel girder
remains the cheapest. The reinforced concrete T- beam is
the costliest due to imposition of longer duration of speed
restriction for casting of deck slab.
2. Considering maintenance cost (life cycle cost)
Considering the periodic maintenance requirement, the
composite steel I-beam becomes the costliest option and
prestressed concrete I-beam comes out most economical
option among all the four superstructure types.
3. Considering the effects on approaches
After adding the additional cost of approaches due to
increase in the height of superstructure, the cost of
superstructure with prestressed concrete I-beam is most
economical with any type of retaining wall in approaches.
From the overall study it is concluded that, in all the four
options used for study; total cost for placement of spans is
higher with sacrificial shuttering than conventional
shuttering for normal ground conditions as well as over
railway track without considering the speed restriction cost.
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 5, Issue 7, July 2015)
124
The advantage of sacrificial shuttering comes into
picture when the cost implication of the speed restriction is
also combined with the traffic block cost.
The effect of sacrificial shuttering is more pronounced
when the numbers of trains in a section are high. The
difference in cost for conventional and combination of
sacrificial shuttering for prestressed I-beam is Rs. 2075300
with 20 trains in a section and this difference increases to
Rs. 6767873 with 80 trains in a section.
Fig:9- variation in cost of superstructure with Conventional and
Combination of sacrificial shuttering due to increase in frequency of
trains in section.
Overall the prestressed concrete I-beam proves to be
most economical in all the conditions studied for arriving at
best solution for the selection of superstructure for 20m
span.
REFERENCES
[1] Alimchandani C.R., Kumar Vijay, Kanitkar V.K., and Shukla U. J., Ganga Bridge at Bhagalpur, Indian Road Congress Journal, 2005,
Paper No 492.
[2] Fowler John R., and Stofko Bob, Precast options for bridge superstructure design, Economical and Social Linkages Session,
2007 Annual Conference of the Transportation Association of Canada, Saskatoon, Saskatchewan.
[3] Heggade V.N., Mehta R.K., and Prakash R., Design and
Construction of Pre-Tensioned Sutlej Bridge in Punjab, Indian Road Congress Journal, 2006, Paper No 524.
[4] Huang Rong-yau, and Chen Ping Fu, Life Cycle Cost Analysis of
Steel and Pre-stressed Concrete Bridges-A case study of a New
Highway Bridge in Taiwan, Doctoral Thesis.
[5] Khatri Vikash, Singh P.K., and Maiti P. R., Comparative Study of
Economical Design Aspect of Steel-Concrete Composite Bridge with MS, HPS, and Hybrid Steel, International Journal of
Engineering Research and Development, 2012, Volume 4(6).
[6] Khatri Vikash, Singh P.K. and Maiti P. R., Comparative Study of Prestressed steel-concrete composite bridge of different span length
and girder spacing, International Journal of Modern Engineering
Research,2012, Volume 2(5), pp 3917-3922.
[7] Khatri Vikash, Singh P.K.and Maiti P.R., Comparative Study for
Different Girder Spacing of Short Span Steel-Concrete Composite bridges with MS and HPS, International Journal of Emerging
Technology and Advanced Engineering, 2012, Volume 2(9).
[8] M. Kishore Kumar and Rao Ch. Hanumantha, Economics of Alternative Structural Schemes of Prestressed Concrete Bridge: Few
Case Studies, International Journal of Civil and Structural
Engineering,2010, Volume 1(3).
[9] Misal Vishal U, Gore N. G. and Salunke P. J., Analysis and design
of Prestressed Concrete Girder, International Journal of Incentive Engineering and sciences, 2014, Volume 2(2).
[10] Pawar A.R. and Pataskar S.V, Life cycle Cost Analysis of bridge
Superstructure, International Journal of Emerging Technology and Advanced Engineering, Volume 2(9).
[11] Vasani P.C. and Mehta Bhoomika P, Different types of Bridges and Its Suitability, Structural Engineering Forum of India.
[12] Saxena Amit and Maru Dr. Savitri, Comparative Study of the Analysis and Design of T-Beam Girder and Box Girder
Supersructure, International Journal of Research in Engineering &
Advanced Technology, April-May 2013, Vol-I, Issue 2.
[13] Design criteria for Pre-stressed concrete road bridges (Post-
tensioned Concrete), IRC: 18-2000, The Indian Road Congress.
[14] Standard Specifications and code of practice for road bridges, IRC:
6-2000, The Indian Road Congress.
[15] Code of practice for Pre-stressed concrete, IS: 1343-1980, Bureau of Indian Standards.
[16] Standard Specifications and code of practice for road bridges, section III-cement concrete (plain & reinforced), IRC: 21-2000, The
Indian Road Congress.
[17] Standard Specifications and code of practice for road bridges, section IV- composite construction (first revision), IRC: 22-1986,
The Indian Road Congress.
[18] Raju N. Krishna, Design of Bridges, Oxford & IBH Publishing Co.
Pvt. Ltd., Fourth Edition 2009.