ID WBS Task Name Start Finish Code Final % From Weight Duration Quantity (ECN) Unit Weight M/H Final 1 1 Construction and Installation Activities (Just For ECN Works) Fri 10/31/08 Tue 11/17/09 5.1 422.8 days 100 629859.25 2 1.1 Start Of The Project Fri 10/31/08 Fri 10/31/08 0 0 days 0 0 3 1.2 Construction - Rectifier Passage 503-12 Sat 3/28/09 Wed 5/20/09 0 59.35 days 1.18 7449.41 4 1.2.1 Operation Floor Sat 3/28/09 Wed 5/20/09 0 59.35 days 1.18 7449.41 5 1.2.1.1 Installation - Electrical Sat 3/28/09 Wed 5/20/09 0 59.35 days 1.18 7449.41 6 1.2.1.1.1 Installation - Cable Tray Sat 3/28/09 Tue 4/28/09 0 35.04 days 0.15 933.86 7 1.2.1.1.1.1 Cantilever supports installation Sat 3/28/09 Sat 4/18/09 E 0 2.42 days 97 nos. 0.03 158.33 8 1.2.1.1.1.2 Cable Tray installation Sun 4/19/09 Tue 4/28/09 E 0 10.5 days 420 mtr 0.12 775.53 9 1.2.1.1.2 Installation - Crane Bus Bars Tue 4/28/09 Wed 5/20/09 0 24.31 days 1.03 6515.55 10 1.2.1.1.2.1 Crane Bus Bar Supports installation Tue 4/28/09 Sun 5/3/09 E 0 5.22 days 87 nos. 0.09 543.99 11 1.2.1.1.2.2 Feed Junction Box Installation Sun 5/3/09 Wed 5/6/09 E 0 3.54 days 13 nos. 0.04 236.42 12 1.2.1.1.2.3 Disconnect Switch Instalation Wed 5/6/09 Thu 5/7/09 E 0 1.56 days 7 nos. 0.02 132.64 13 1.2.1.1.2.4 Interconnection cable, cableways installation Thu 5/7/09 Mon 5/11/09 E 0 3.99 days 60 nos. 0.25 1605 14 1.2.1.1.2.5 Crane feeder cables Mon 5/11/09 Wed 5/20/09 E 0 10 days 1080 mtr 0.63 3997.5 15 1.3 Construction - Potroom No. 1 (501-12A) Mon 11/24/08 Wed 7/29/09 1.92 273.91 days 11.41 71862.2 16 1.3.1 Pot 22 Mon 11/24/08 Wed 6/10/09 0.74 219.91 days 2.88 18111.55 17 1.3.1.1 SLI DELIVERABLES Mon 11/24/08 Mon 11/24/08 0 0 days 0 0 18 1.3.1.1.1 POT 22 Area Available for MPEI Construction Mon 11/24/08 Mon 11/24/08 0 0 days 0 0 19 1.3.1.2 Basement Floor Tue 12/30/08 Sun 5/3/09 0.63 137.52 days 1.22 7669.18 20 1.3.1.2.1 Installation - Electrical Tue 12/30/08 Sun 5/3/09 0.63 137.52 days 1.22 7669.18 21 1.3.1.2.1.1 Installation - Lighting System Tue 12/30/08 Sun 2/8/09 0.61 43.76 days 0.61 3873.42 22 1.3.1.2.1.1.1 PVC conduit and boxes Tue 12/30/08 Sun 1/4/09 E 0.04 5.67 days 75 mtr 0.04 243.05 23 1.3.1.2.1.1.2 Single Core Wires Sun 1/25/09 Tue 1/27/09 E 0.02 2.51 days 165 mtr 0.02 122.11 24 1.3.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supports and fixings Tue 1/27/09 Wed 1/28/09 E 0.02 0.35 days 18 nos. 0.02 145.32 25 1.3.1.2.1.1.4 Lighting Feeder cables / wires Wed 1/28/09 Sun 2/8/09 E 0.53 11.91 days 1400 mtr 0.53 3362.94 26 1.3.1.2.1.2 Installation - Emergency Shutdown Tue 4/21/09 Sun 5/3/09 0.01 12.97 days 0.6 3795.76 27 1.3.1.2.1.2.1 PVC conduit and boxes Tue 4/21/09 Wed 4/22/09 I 0.01 0.76 days 12 mtr 0.01 63.96 28 1.3.1.2.1.2.2 Instrument cables Wed 4/22/09 Sun 5/3/09 I 0 12.21 days 1944 mtr 0.59 3731.8 29 1.3.1.3 Operation Floor Tue 12/2/08 Wed 6/10/09 0.11 209.91 days 1.66 10442.38 30 1.3.1.3.1 Air Compressed System - Piping Sat 4/11/09 Sat 4/18/09 0 9 days 0.05 333.13 31 1.3.1.3.1.1 2" Equal Tee Sat 4/11/09 Tue 4/14/09 P 0 4 days 11 nos 0.03 213.2 32 1.3.1.3.1.2 2" Plug Tue 4/14/09 Tue 4/14/09 P 0 1 day 9 nos 0.01 79.95 33 1.3.1.3.1.3 1/2" Ball valve Tue 4/14/09 Wed 4/15/09 P 0 1 day 2 nos 0 10.66 34 1.3.1.3.1.4 2" x 1" Reducer Wed 4/15/09 Thu 4/16/09 P 0 1 day 2 nos 0 10.66 35 1.3.1.3.1.5 1" x 1/2" Reducer Thu 4/16/09 Sat 4/18/09 P 0 1 day 2 nos 0 10.66 36 1.3.1.3.1.6 1/2" Nipple Sat 4/18/09 Sat 4/18/09 P 0 1 day 2 nos 0 8 37 1.3.1.3.2 Delivery of sub station 305-51 from SNCLavalin to Astaldi Tue 3/31/09 Tue 3/31/09 0 0 days 0 0 38 1.3.1.3.3 Installation - Electrical Tue 12/2/08 Wed 6/10/09 0.11 209.91 days 1.61 10109.25 39 1.3.1.3.3.1 Installation - Lighting System Tue 12/2/08 Sun 12/7/08 0.08 5.04 days 0.08 523.22 40 1.3.1.3.3.1.1 Rigid Steel Conduit Tue 12/2/08 Thu 12/4/08 E 0.03 1.66 days 26 mtr 0.03 157.5 41 1.3.1.3.3.1.2 Single Core Wires Thu 12/4/08 Thu 12/4/08 E 0.03 0.79 days 300 mtr 0.03 188.82 42 1.3.1.3.3.1.3 High Bay Lighting fixtures including supports and fixings Thu 12/4/08 Sun 12/7/08 E 0.02 1.59 days 6 nos. 0.02 155.58 43 1.3.1.3.3.1.4 Lighting Feeder cables / wires Sun 12/7/08 Sun 12/7/08 E 0 1 day 8 mtr 0 21.32 44 1.3.1.3.3.2 Installation - Crane Bus Bars Sat 1/10/09 Mon 5/25/09 0.02 150.24 days 0.51 3205.04 45 1.3.1.3.3.2.1 Crane Bus Bar Supports installation Sat 1/10/09 Sat 1/10/09 E 0.02 0.69 days 16 nos. 0.02 96.37 46 1.3.1.3.3.2.2 Feed Junction Box Installation Sat 1/10/09 Sun 1/11/09 E 0 1.33 days 4 nos. 0.01 70.89 47 1.3.1.3.3.2.3 Disconnect Switch Instalation Sun 1/11/09 Mon 1/12/09 E 0 0.5 days 1 nos. 0 17.32 48 1.3.1.3.3.2.4 Interconnection cable, cableways installation Mon 1/12/09 Mon 1/12/09 E 0 1 day 5 nos. 0.02 133.25 49 1.3.1.3.3.2.5 Crane Power Feeder Cable Wed 5/20/09 Sat 5/23/09 E 0 2.64 days 350 mtr 0.42 2626.04 50 1.3.1.3.3.2.6 Cable Termination Sat 5/23/09 Mon 5/25/09 E 0 3 days 15 nos. 0.04 261.17 51 1.3.1.3.3.3 Installation - Socket / Welding Outlet Mon 1/26/09 Sun 3/15/09 0.02 52.75 days 0.06 381.71 52 1.3.1.3.3.3.1 Rigid Steel Conduit Mon 1/26/09 Tue 1/27/09 E 0.01 1.8 days 15 mtr 0.01 78.35 53 1.3.1.3.3.3.2 Single Core Wires Sat 3/14/09 Sun 3/15/09 E 0 1.33 days 50 mtr 0 27.82 54 1.3.1.3.3.3.3 Junction Box Wed 1/28/09 Thu 1/29/09 E 0 0.5 days 2 nos. 0 23.98 55 1.3.1.3.3.3.4 Welding outlet / Socket Outlet Thu 1/29/09 Thu 1/29/09 E 0 0.29 days 2 nos. 0 27.05 56 1.3.1.3.3.3.5 Socket Feeder cables Thu 1/29/09 Thu 1/29/09 E 0 0.52 days 60 mtr 0.04 224.5 57 1.3.1.3.3.4 Installation - Local Junction Box Sun 5/3/09 Wed 6/10/09 0 42.95 days 0.95 5999.29 10/31 11/24 11/24 Installation extended Material by Astaldi Material by SNC 3/31 Waiting for cable tray to be installed No junction box available No disconnect switch installation available No cables and cable tray Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2009 Task Baseline Task 2 Critical Split Progress Milestone Baseline Milestone 1 Summary Baseline Summary 1 Rev. : 02 Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan Page 1 Of 24 Project: C005 without subtotal Date: Tue 3/31/09

ECN Plan For C-005 Final

Embed Size (px)

Citation preview

Page 1: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

1 1 Construction and Installation Activities (Just For ECN Works) Fri 10/31/08 Tue 11/17/09 5.1 422.8 days 100 629859.25

2 1.1 Start Of The Project Fri 10/31/08 Fri 10/31/08 0 0 days 0 0

3 1.2 Construction - Rectifier Passage 503-12 Sat 3/28/09 Wed 5/20/09 0 59.35 days 1.18 7449.41

4 1.2.1 Operation Floor Sat 3/28/09 Wed 5/20/09 0 59.35 days 1.18 7449.41

5 1.2.1.1 Installation - Electrical Sat 3/28/09 Wed 5/20/09 0 59.35 days 1.18 7449.41

6 1.2.1.1.1 Installation - Cable Tray Sat 3/28/09 Tue 4/28/09 0 35.04 days 0.15 933.867 1.2.1.1.1.1 Cantilever supports installation Sat 3/28/09 Sat 4/18/09 E 0 2.42 days 97 nos. 0.03 158.33

8 1.2.1.1.1.2 Cable Tray installation Sun 4/19/09 Tue 4/28/09 E 0 10.5 days 420 mtr 0.12 775.53

9 1.2.1.1.2 Installation - Crane Bus Bars Tue 4/28/09 Wed 5/20/09 0 24.31 days 1.03 6515.5510 1.2.1.1.2.1 Crane Bus Bar Supports installation Tue 4/28/09 Sun 5/3/09 E 0 5.22 days 87 nos. 0.09 543.99

11 1.2.1.1.2.2 Feed Junction Box Installation Sun 5/3/09 Wed 5/6/09 E 0 3.54 days 13 nos. 0.04 236.42

12 1.2.1.1.2.3 Disconnect Switch Instalation Wed 5/6/09 Thu 5/7/09 E 0 1.56 days 7 nos. 0.02 132.64

13 1.2.1.1.2.4 Interconnection cable, cableways installation Thu 5/7/09 Mon 5/11/09 E 0 3.99 days 60 nos. 0.25 1605

14 1.2.1.1.2.5 Crane feeder cables Mon 5/11/09 Wed 5/20/09 E 0 10 days 1080 mtr 0.63 3997.5

15 1.3 Construction - Potroom No. 1 (501-12A) Mon 11/24/08 Wed 7/29/09 1.92 273.91 days 11.41 71862.2

16 1.3.1 Pot 22 Mon 11/24/08 Wed 6/10/09 0.74 219.91 days 2.88 18111.5517 1.3.1.1 SLI DELIVERABLES Mon 11/24/08 Mon 11/24/08 0 0 days 0 018 1.3.1.1.1 POT 22 Area Available for MPEI Construction Mon 11/24/08 Mon 11/24/08 0 0 days 0 0

19 1.3.1.2 Basement Floor Tue 12/30/08 Sun 5/3/09 0.63 137.52 days 1.22 7669.18

20 1.3.1.2.1 Installation - Electrical Tue 12/30/08 Sun 5/3/09 0.63 137.52 days 1.22 7669.18

21 1.3.1.2.1.1 Installation - Lighting System Tue 12/30/08 Sun 2/8/09 0.61 43.76 days 0.61 3873.4222 1.3.1.2.1.1.1 PVC conduit and boxes Tue 12/30/08 Sun 1/4/09 E 0.04 5.67 days 75 mtr 0.04 243.05

23 1.3.1.2.1.1.2 Single Core Wires Sun 1/25/09 Tue 1/27/09 E 0.02 2.51 days 165 mtr 0.02 122.11

24 1.3.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Tue 1/27/09 Wed 1/28/09 E 0.02 0.35 days 18 nos. 0.02 145.32

25 1.3.1.2.1.1.4 Lighting Feeder cables / wires Wed 1/28/09 Sun 2/8/09 E 0.53 11.91 days 1400 mtr 0.53 3362.94

26 1.3.1.2.1.2 Installation - Emergency Shutdown Tue 4/21/09 Sun 5/3/09 0.01 12.97 days 0.6 3795.7627 1.3.1.2.1.2.1 PVC conduit and boxes Tue 4/21/09 Wed 4/22/09 I 0.01 0.76 days 12 mtr 0.01 63.96

28 1.3.1.2.1.2.2 Instrument cables Wed 4/22/09 Sun 5/3/09 I 0 12.21 days 1944 mtr 0.59 3731.8

29 1.3.1.3 Operation Floor Tue 12/2/08 Wed 6/10/09 0.11 209.91 days 1.66 10442.38

30 1.3.1.3.1 Air Compressed System - Piping Sat 4/11/09 Sat 4/18/09 0 9 days 0.05 333.1331 1.3.1.3.1.1 2" Equal Tee Sat 4/11/09 Tue 4/14/09 P 0 4 days 11 nos 0.03 213.2

32 1.3.1.3.1.2 2" Plug Tue 4/14/09 Tue 4/14/09 P 0 1 day 9 nos 0.01 79.95

33 1.3.1.3.1.3 1/2" Ball valve Tue 4/14/09 Wed 4/15/09 P 0 1 day 2 nos 0 10.66

34 1.3.1.3.1.4 2" x 1" Reducer Wed 4/15/09 Thu 4/16/09 P 0 1 day 2 nos 0 10.66

35 1.3.1.3.1.5 1" x 1/2" Reducer Thu 4/16/09 Sat 4/18/09 P 0 1 day 2 nos 0 10.66

36 1.3.1.3.1.6 1/2" Nipple Sat 4/18/09 Sat 4/18/09 P 0 1 day 2 nos 0 8

37 1.3.1.3.2 Delivery of sub station 305-51 from SNCLavalin toAstaldi

Tue 3/31/09 Tue 3/31/09 0 0 days 0 0

38 1.3.1.3.3 Installation - Electrical Tue 12/2/08 Wed 6/10/09 0.11 209.91 days 1.61 10109.25

39 1.3.1.3.3.1 Installation - Lighting System Tue 12/2/08 Sun 12/7/08 0.08 5.04 days 0.08 523.2240 1.3.1.3.3.1.1 Rigid Steel Conduit Tue 12/2/08 Thu 12/4/08 E 0.03 1.66 days 26 mtr 0.03 157.5

41 1.3.1.3.3.1.2 Single Core Wires Thu 12/4/08 Thu 12/4/08 E 0.03 0.79 days 300 mtr 0.03 188.82

42 1.3.1.3.3.1.3 High Bay Lighting fixtures including supports and fixings Thu 12/4/08 Sun 12/7/08 E 0.02 1.59 days 6 nos. 0.02 155.58

43 1.3.1.3.3.1.4 Lighting Feeder cables / wires Sun 12/7/08 Sun 12/7/08 E 0 1 day 8 mtr 0 21.32

44 1.3.1.3.3.2 Installation - Crane Bus Bars Sat 1/10/09 Mon 5/25/09 0.02 150.24 days 0.51 3205.0445 1.3.1.3.3.2.1 Crane Bus Bar Supports installation Sat 1/10/09 Sat 1/10/09 E 0.02 0.69 days 16 nos. 0.02 96.37

46 1.3.1.3.3.2.2 Feed Junction Box Installation Sat 1/10/09 Sun 1/11/09 E 0 1.33 days 4 nos. 0.01 70.89

47 1.3.1.3.3.2.3 Disconnect Switch Instalation Sun 1/11/09 Mon 1/12/09 E 0 0.5 days 1 nos. 0 17.32

48 1.3.1.3.3.2.4 Interconnection cable, cableways installation Mon 1/12/09 Mon 1/12/09 E 0 1 day 5 nos. 0.02 133.25

49 1.3.1.3.3.2.5 Crane Power Feeder Cable Wed 5/20/09 Sat 5/23/09 E 0 2.64 days 350 mtr 0.42 2626.04

50 1.3.1.3.3.2.6 Cable Termination Sat 5/23/09 Mon 5/25/09 E 0 3 days 15 nos. 0.04 261.17

51 1.3.1.3.3.3 Installation - Socket / Welding Outlet Mon 1/26/09 Sun 3/15/09 0.02 52.75 days 0.06 381.7152 1.3.1.3.3.3.1 Rigid Steel Conduit Mon 1/26/09 Tue 1/27/09 E 0.01 1.8 days 15 mtr 0.01 78.35

53 1.3.1.3.3.3.2 Single Core Wires Sat 3/14/09 Sun 3/15/09 E 0 1.33 days 50 mtr 0 27.82

54 1.3.1.3.3.3.3 Junction Box Wed 1/28/09 Thu 1/29/09 E 0 0.5 days 2 nos. 0 23.98

55 1.3.1.3.3.3.4 Welding outlet / Socket Outlet Thu 1/29/09 Thu 1/29/09 E 0 0.29 days 2 nos. 0 27.05

56 1.3.1.3.3.3.5 Socket Feeder cables Thu 1/29/09 Thu 1/29/09 E 0 0.52 days 60 mtr 0.04 224.5

57 1.3.1.3.3.4 Installation - Local Junction Box Sun 5/3/09 Wed 6/10/09 0 42.95 days 0.95 5999.29

10/31

11/24

11/24

Installation extended

Material by Astaldi

Material by SNC

3/31

Waiting for cable tray to be installed

No junction box available

No disconnect switch installation available

No cables and cable tray

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 1 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 2: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

58 1.3.1.3.3.4.1 Rigid Steel Conduit Sun 5/3/09 Sun 5/10/09 E 0 7.62 days 140 mtr 0.12 744.6

59 1.3.1.3.3.4.2 Junction Box Sun 5/10/09 Tue 5/12/09 E 0 3.81 days 28 nos. 0.06 372.3

60 1.3.1.3.3.4.3 Feeder cables Tue 5/12/09 Wed 5/20/09 E 0 8.72 days 1020 mtr 0.53 3358.01

61 1.3.1.3.3.4.4 Cable Termination Mon 5/25/09 Wed 6/10/09 E 0 18 days 88 nos. 0.24 1524.38

62 1.3.2 Pot 44 Tue 1/6/09 Sat 6/27/09 0.83 189.12 days 2.48 15600.0663 4.5.2.1 SLI DELIVERABLES Tue 2/3/09 Tue 2/3/09 0 0 days 0 064 1.3.2.1.1 POT 44 Area Available for MPEI Construction Tue 2/3/09 Tue 2/3/09 0 0 days 0 0

65 1.3.2.2 Basement Floor Tue 2/3/09 Sun 5/10/09 0.8 106.72 days 1.4 8789.5766 1.3.2.2.1 Installation - Electrical Tue 2/3/09 Sun 5/10/09 0.8 106.72 days 1.4 8789.57

67 1.3.2.2.1.1 Installation - Lighting System Tue 2/3/09 Mon 4/20/09 0.79 84.77 days 0.79 4975.1668 1.3.2.2.1.1.1 PVC conduit and boxes Tue 2/3/09 Wed 2/4/09 E 0.05 2.37 days 95 mtr 0.05 303.81

69 1.3.2.2.1.1.2 Single Core Wires Wed 2/4/09 Sat 2/7/09 E 0.04 2.35 days 322 mtr 0.04 240.01

70 1.3.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Sat 2/7/09 Mon 2/9/09 E 0.04 2.1 days 34 nos. 0.04 267.7

71 1.3.2.2.1.1.4 Lighting Feeder cables / wires Mon 2/9/09 Mon 4/20/09 E 0.66 11.51 days 1738 mtr 0.66 4163.64

72 1.3.2.2.1.2 Installation - Emergency Shutdown Sat 2/21/09 Sun 5/10/09 0.01 87.34 days 0.61 3814.4173 1.3.2.2.1.2.1 PVC conduit and boxes Sat 2/21/09 Sat 2/21/09 I 0.01 0.76 days 12 mtr 0.01 63.96

74 1.3.2.2.1.2.2 Instrument cables Wed 4/29/09 Sun 5/10/09 I 0 12.21 days 1944 mtr 0.59 3731.8

75 1.3.2.2.1.2.3 Remote ASI Panel /Cabinet Sun 5/10/09 Sun 5/10/09 I 0 0.33 days 1 mtr 0 18.66

76 1.3.2.3 Operation Floor Tue 1/6/09 Sat 6/27/09 0.03 189.12 days 1.08 6810.49

77 1.3.2.3.1 Air Compressed System - Piping Tue 1/6/09 Sat 6/27/09 0.03 189.12 days 1.08 6810.4978 1.3.2.3.1.1 2" Equal Tee Tue 4/14/09 Sat 4/18/09 P 0 4 days 11 nos 0.03 213.2

79 1.3.2.3.1.2 2" Plug Sat 4/18/09 Sat 4/18/09 P 0 1 day 9 nos 0.01 79.95

80 1.3.2.3.1.3 1/2" Ball valve Sat 4/18/09 Sun 4/19/09 P 0 1 day 2 nos 0 10.66

81 1.3.2.3.1.4 2" x 1" Reducer Sun 4/19/09 Mon 4/20/09 P 0 1 day 2 nos 0 10.66

82 1.3.2.3.1.5 1" x 1/2" Reducer Mon 4/20/09 Tue 4/21/09 P 0 1 day 2 nos 0 10.66

83 1.3.2.3.1.6 1/2" Nipple Tue 4/21/09 Wed 4/22/09 P 0 1 day 2 nos 0 8

84 1.3.2.3.1.7 Installation - Electrical Tue 1/6/09 Sat 6/27/09 0.03 189.12 days 1.03 6477.36

85 1.3.2.3.1.7.1 Installation - Crane Bus Bars Tue 1/6/09 Sat 1/10/09 0.02 2.97 days 0.02 96.3786 1.3.2.3.1.7.1.1 Crane Bus Bar Supports installation Tue 1/6/09 Sat 1/10/09 E 0.02 2.97 days 16 nos. 0.02 96.37

87 1.3.2.3.1.7.2 Installation - Socket / Welding Outlet Sun 3/22/09 Sun 4/19/09 0.02 31.02 days 0.06 381.7188 1.3.2.3.1.7.2.1 Rigid Steel Conduit Sun 3/22/09 Sun 3/22/09 E 0.01 0.84 days 15 mtr 0.01 78.35

89 1.3.2.3.1.7.2.2 Single Core Wires Mon 3/23/09 Mon 3/23/09 E 0 0.36 days 50 mtr 0 27.82

90 1.3.2.3.1.7.2.3 Junction Box Sat 4/18/09 Sat 4/18/09 E 0 0.5 days 2 nos. 0 23.98

91 1.3.2.3.1.7.2.4 Welding outlet / Socket Outlet Sat 4/18/09 Sat 4/18/09 E 0 0.29 days 2 nos. 0 27.05

92 1.3.2.3.1.7.2.5 Socket Feeder cables Sat 4/18/09 Sun 4/19/09 E 0 0.52 days 60 mtr 0.04 224.5

93 1.3.2.3.1.7.3 Installation - Local Junction Box Thu 4/16/09 Sat 6/27/09 0 79.12 days 0.95 5999.2994 6.73 Rigid Steel Conduit Thu 4/16/09 Thu 4/23/09 E 0 7.83 days 140 mtr 0.12 744.6

95 3.81 Junction Box Tue 5/12/09 Sat 5/16/09 E 0 3.81 days 28 nos. 0.06 372.3

96 8.72 Feeder cables Sat 5/16/09 Sun 5/24/09 E 0 8.72 days 1020 mtr 0.53 3358.01

97 18 Cable Termination Wed 6/10/09 Sat 6/27/09 E 0 18 days 88 nos. 0.24 1524.38

98 1.3.3 Pot 66 Thu 2/12/09 Mon 7/13/09 0.07 166.78 days 2.85 17950.1999 4.5.2.1 SLI DELIVERABLES Thu 2/12/09 Thu 2/12/09 0 0 days 0 0

100 1.3.3.1.1 POT 66 Area Available for MPEI Construction Thu 2/12/09 Thu 2/12/09 0 0 days 0 0

101 1.3.3.2 Basement Floor Sat 2/28/09 Sun 5/17/09 0.01 86.47 days 1.31 8278.18102 1.3.3.2.1 Installation - Electrical Sat 2/28/09 Sun 5/17/09 0.01 86.47 days 1.31 8278.18

103 1.3.3.2.1.1 Installation - Lighting System Tue 4/7/09 Wed 5/6/09 0 32.47 days 0.71 4482.42104 1.3.3.2.1.1.1 PVC conduit and boxes Tue 4/7/09 Wed 4/22/09 E 0 16.38 days 558 mtr 0.28 1777.29

105 1.3.3.2.1.1.2 Single Core Wires Wed 4/22/09 Wed 4/22/09 E 0 0.92 days 132 mtr 0.02 96.85

106 1.3.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Wed 4/22/09 Thu 4/23/09 E 0 0.91 days 12 nos. 0.02 99.43

107 1.3.3.2.1.1.4 Lighting Feeder cables / wires Wed 4/29/09 Wed 5/6/09 E 0 7.99 days 1050 mtr 0.4 2508.86

108 1.3.3.2.1.2 Installation - Emergency Shutdown Sat 2/28/09 Sun 5/17/09 0.01 86.47 days 0.6 3795.76109 1.3.3.2.1.2.1 PVC conduit and boxes Sat 2/28/09 Sat 2/28/09 I 0.01 0.76 days 12 mtr 0.01 63.96

110 1.3.3.2.1.2.2 Instrument cables Tue 5/5/09 Sun 5/17/09 I 0 12.21 days 1944 mtr 0.59 3731.8

111 1.3.3.3 Operation Floor Tue 3/24/09 Mon 7/13/09 0.05 122.87 days 1.54 9672

112 1.3.3.3.1 Air Compressed System - Piping Sat 4/18/09 Sun 4/26/09 0 9 days 0.05 333.13113 1.3.3.3.1.1 2" Equal Tee Sat 4/18/09 Tue 4/21/09 P 0 4 days 11 nos 0.03 213.2

114 1.3.3.3.1.2 2" Plug Tue 4/21/09 Wed 4/22/09 P 0 1 day 9 nos 0.01 79.95

115 1.3.3.3.1.3 1/2" Ball valve Wed 4/22/09 Wed 4/22/09 P 0 1 day 2 nos 0 10.66

116 1.3.3.3.1.4 2" x 1" Reducer Wed 4/22/09 Thu 4/23/09 P 0 1 day 2 nos 0 10.66

2/3

Material by Astaldi

Material by SNC

Material by SNC

2/12

Material by Astaldi

Material by SNC

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 2 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 3: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

117 1.3.3.3.1.5 1" x 1/2" Reducer Thu 4/23/09 Sat 4/25/09 P 0 1 day 2 nos 0 10.66

118 1.3.3.3.1.6 1/2" Nipple Sat 4/25/09 Sun 4/26/09 P 0 1 day 2 nos 0 8

119 1.3.3.3.2 Installation - Electrical Tue 3/24/09 Mon 7/13/09 0.05 122.87 days 1.48 9338.88

120 1.3.3.3.2.1 Installation - Lighting System Tue 3/24/09 Thu 5/7/09 0.05 49.56 days 0.08 523.22121 1.3.3.3.2.1.1 Rigid Steel Conduit Tue 3/24/09 Tue 3/24/09 E 0.03 0.7 days 26 mtr 0.03 157.5

122 1.3.3.3.2.1.2 Single Core Wires Wed 3/25/09 Wed 3/25/09 E 0.03 1.04 days 300 mtr 0.03 188.82

123 1.3.3.3.2.1.3 High Bay Lighting fixtures including supports and fixings Sun 4/19/09 Sun 4/19/09 E 0 0.84 days 6 nos. 0.02 155.58

124 1.3.3.3.2.1.4 Lighting Feeder cables / wires Wed 5/6/09 Thu 5/7/09 E 0 1 day 8 mtr 0 21.32

125 1.3.3.3.2.2 Installation - Cable Tray Sat 4/18/09 Wed 4/29/09 0 12.4 days 0.06 401.4126 1.3.3.3.2.2.1 Cantilever supports installation Sat 4/18/09 Sun 4/19/09 E 0 0.21 days 22 nos. 0 22.95

127 1.3.3.3.2.2.2 Cable Tray installation Tue 4/28/09 Wed 4/29/09 E 0 1.65 days 202 mtr 0.06 378.46

128 1.3.3.3.2.3 Installation - Blower and Transformer Feeder Tue 4/7/09 Mon 4/13/09 0 5.85 days 0.43 2725.18

129 1.3.3.3.2.3.1 Blower Feeder, Transformer Feeder Tue 4/7/09 Mon 4/13/09 E 0 5.85 days 700 mtr 0.43 2725.18

130 1.3.3.3.2.4 Installation - Local Junction Box Thu 4/16/09 Mon 7/13/09 0 97.03 days 0.9 5689.08131 1.3.3.3.2.4.1 Rigid Steel Conduit Thu 4/16/09 Wed 4/22/09 E 0 7.08 days 130 mtr 0.11 691.83

132 1.3.3.3.2.4.2 Junction Box Wed 4/22/09 Sun 4/26/09 E 0 3.54 days 26 nos. 0.05 345.92

133 1.3.3.3.2.4.3 Feeder cables Wed 4/29/09 Wed 5/6/09 E 0 8.12 days 948 mtr 0.5 3126.95

134 1.3.3.3.2.4.4 Cable Termination Sat 6/27/09 Mon 7/13/09 E 0 18 days 88 nos. 0.24 1524.38

135 1.3.4 Pot 88 Thu 2/19/09 Wed 7/29/09 0.29 177.03 days 3.21 20200.41136 4.5.2.1 SLI DELIVERABLES Thu 2/19/09 Thu 2/19/09 0 0 days 0 0137 1.3.4.1.1 POT 88 Area Available for MPEI Construction Thu 2/19/09 Thu 2/19/09 0 0 days 0 0

138 1.3.4.2 Basement Floor Sat 3/14/09 Sat 5/23/09 0.29 78.51 days 1.32 8308.64139 1.3.4.2.1 Installation - Electrical Sat 3/14/09 Sat 5/23/09 0.29 78.51 days 1.32 8308.64

140 1.3.4.2.1.1 Installation - Lighting System Sat 3/14/09 Mon 5/11/09 0.28 64.57 days 0.71 4494.23141 1.3.4.2.1.1.1 PVC conduit and boxes Sat 3/14/09 Sat 3/28/09 E 0.28 16.45 days 560 mtr 0.28 1784.88

142 1.3.4.2.1.1.2 Single Core Wires Thu 5/7/09 Thu 5/7/09 E 0 0.96 days 137 mtr 0.02 101.06

143 1.3.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Tue 5/5/09 Wed 5/6/09 E 0 0.91 days 12 nos. 0.02 99.43

144 1.3.4.2.1.1.4 Lighting Feeder cables / wires Sun 5/3/09 Mon 5/11/09 E 0 7.99 days 1050 mtr 0.4 2508.86

145 1.3.4.2.1.2 Installation - Emergency Shutdown Tue 3/24/09 Sat 5/23/09 0.01 66.89 days 0.61 3814.41146 1.3.4.2.1.2.1 PVC conduit and boxes Tue 3/24/09 Tue 3/24/09 I 0.01 0.76 days 12 mtr 0.01 63.96

147 1.3.4.2.1.2.2 Instrument cables Tue 5/12/09 Sat 5/23/09 I 0 12.21 days 1944 mtr 0.59 3731.8

148 1.3.4.2.1.2.3 Remote ASI Panel /Cabinet Sat 5/23/09 Sat 5/23/09 I 0 0.33 days 1 mtr 0 18.66

149 1.3.4.3 Operation Floor Mon 4/13/09 Wed 7/29/09 0 118.93 days 1.89 11891.76

150 1.3.4.3.1 Air Compressed System - Piping Tue 4/21/09 Wed 4/29/09 0 9 days 0.05 333.13151 1.3.4.3.1.1 2" Equal Tee Tue 4/21/09 Sat 4/25/09 P 0 4 days 11 nos 0.03 213.2

152 1.3.4.3.1.2 2" Plug Sat 4/25/09 Sun 4/26/09 P 0 1 day 9 nos 0.01 79.95

153 1.3.4.3.1.3 1/2" Ball valve Sun 4/26/09 Sun 4/26/09 P 0 1 day 2 nos 0 10.66

154 1.3.4.3.1.4 2" x 1" Reducer Sun 4/26/09 Mon 4/27/09 P 0 1 day 2 nos 0 10.66

155 1.3.4.3.1.5 1" x 1/2" Reducer Mon 4/27/09 Tue 4/28/09 P 0 1 day 2 nos 0 10.66

156 1.3.4.3.1.6 1/2" Nipple Tue 4/28/09 Wed 4/29/09 P 0 1 day 2 nos 0 8

157 1.3.4.3.2 Installation - Electrical Mon 4/13/09 Wed 7/29/09 0 118.93 days 1.84 11558.64

158 1.3.4.3.2.1 Installation - Lighting System Sat 4/18/09 Sat 5/9/09 0 23.13 days 0.14 887.79159 1.3.4.3.2.1.1 Rigid Steel Conduit Sat 4/18/09 Sat 4/18/09 E 0 0.7 days 25 mtr 0.03 157.5

160 1.3.4.3.2.1.2 Single Core Wires Sat 4/18/09 Sun 4/19/09 E 0 1.04 days 300 mtr 0.03 188.82

161 1.3.4.3.2.1.3 High Bay Lighting fixtures including supports and fixings Sun 4/19/09 Mon 4/20/09 E 0 0.84 days 6 nos. 0.02 155.58

162 1.3.4.3.2.1.4 Lighting Feeder cables / wires Thu 5/7/09 Sat 5/9/09 E 0 0.7 days 100 mtr 0.06 385.89

163 1.3.4.3.2.2 Installation - Cable Tray Sun 4/19/09 Thu 4/30/09 0 13.84 days 0.06 401.4164 1.3.4.3.2.2.1 Cantilever supports installation Sun 4/19/09 Sun 4/19/09 E 0 0.21 days 22 nos. 0 22.95

165 1.3.4.3.2.2.2 Cable Tray installation Wed 4/29/09 Thu 4/30/09 E 0 1.65 days 202 mtr 0.06 378.46

166 1.3.4.3.2.3 Installation - Crane Bus Bars Tue 5/5/09 Tue 5/26/09 0 23.36 days 0.43 2703.64167 1.3.4.3.2.3.1 Disconnect Switch Instalation Tue 5/5/09 Tue 5/5/09 E 0 0.5 days 1 nos. 0 17.32

168 1.3.4.3.2.3.2 Interconnection cable, cableways installation Tue 5/5/09 Wed 5/6/09 E 0 1 day 5 nos. 0.02 133.25

169 1.3.4.3.2.3.3 Crane Power Feeder Cable Wed 5/6/09 Sat 5/9/09 E 0 2.48 days 330 mtr 0.39 2466.88

170 1.3.4.3.2.3.4 Cable Termination Mon 5/25/09 Tue 5/26/09 E 0 0.99 days 5 nos. 0.01 86.19

171 1.3.4.3.2.4 Installation - Blower and Transformer Feeder Mon 4/13/09 Sat 4/18/09 0 5.85 days 0.43 2725.18

172 1.3.4.3.2.4.1 Blower Feeder, Transformer Feeder Mon 4/13/09 Sat 4/18/09 E 0 5.85 days 700 mtr 0.43 2725.18

173 1.3.4.3.2.5 Installation - Socket / Welding Outlet Wed 4/22/09 Sat 4/25/09 0 2.51 days 0.06 381.71174 1.3.4.3.2.5.1 Rigid Steel Conduit Wed 4/22/09 Thu 4/23/09 E 0 0.84 days 15 mtr 0.01 78.35

2/19

2/19

Material by Astaldi

Material by SNC

Material by SNC

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 3 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 4: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

175 1.3.4.3.2.5.2 Single Core Wires Thu 4/23/09 Thu 4/23/09 E 0 0.36 days 50 mtr 0 27.82

176 1.3.4.3.2.5.3 Junction Box Thu 4/23/09 Thu 4/23/09 E 0 0.5 days 2 nos. 0 23.98

177 1.3.4.3.2.5.4 Welding outlet / Socket Outlet Thu 4/23/09 Sat 4/25/09 E 0 0.29 days 2 nos. 0 27.05

178 1.3.4.3.2.5.5 Socket Feeder cables Sat 4/25/09 Sat 4/25/09 E 0 0.52 days 60 mtr 0.04 224.5

179 1.3.4.3.2.6 Installation - Local Junction Box Wed 4/22/09 Wed 7/29/09 0 107.95 days 0.71 4458.92180 1.3.4.3.2.6.1 Rigid Steel Conduit Wed 4/22/09 Wed 4/29/09 E 0 7.62 days 140 mtr 0.12 744.6

181 1.3.4.3.2.6.2 Junction Box Wed 4/29/09 Sun 5/3/09 E 0 3.81 days 28 nos. 0.06 372.3

182 1.3.4.3.2.6.3 Feeder cables Sun 5/3/09 Thu 5/7/09 E 0 4.72 days 550 mtr 0.29 1817.64

183 1.3.4.3.2.6.4 Cable Termination Mon 7/13/09 Wed 7/29/09 E 0 18 days 88 nos. 0.24 1524.38

184 1.4 Construction - Potroom No. 2 (501-22A) Sat 11/22/08 Sun 6/14/09 3.16 226.15 days 11.78 74187.76

185 1.4.1 Pot 22 Sat 11/22/08 Sat 5/30/09 0.75 209.84 days 3.26 20550.51186 1.4.1.1 SLI DELIVERABLES Sat 11/22/08 Sat 11/22/08 0 0 days 0 0187 1.4.1.1.1 POT 22 Area Available for MPEI Construction Sat 11/22/08 Sat 11/22/08 0 0 days 0 0

188 1.4.1.2 Basement Floor Sat 11/22/08 Tue 4/21/09 0.63 167.68 days 1.22 7669.18

189 1.4.1.2.1 Installation - Electrical Sat 11/22/08 Tue 4/21/09 0.63 167.68 days 1.22 7669.18

190 1.4.1.2.1.1 Installation - Lighting System Sat 11/22/08 Thu 2/5/09 0.61 84.89 days 0.61 3873.42191 1.4.1.2.1.1.1 PVC conduit and boxes Sat 11/22/08 Sun 11/23/08 E 0.04 2.28 days 75 mtr 0.04 243.05

192 1.4.1.2.1.1.2 Single Core Wires Thu 11/27/08 Sat 11/29/08 E 0.02 0.82 days 165 mtr 0.02 122.11

193 1.4.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Wed 11/26/08 Thu 11/27/08 E 0.02 1.26 days 18 nos. 0.02 145.32

194 1.4.1.2.1.1.4 Lighting Feeder cables / wires Thu 1/29/09 Thu 2/5/09 E 0.53 8.53 days 1400 mtr 0.53 3362.94

195 1.4.1.2.1.2 Installation - Emergency Shutdown Thu 2/12/09 Tue 4/21/09 0.01 75.97 days 0.6 3795.76196 1.4.1.2.1.2.1 PVC conduit and boxes Thu 2/12/09 Thu 2/12/09 I 0.01 0.76 days 12 mtr 0.01 63.96

197 1.4.1.2.1.2.2 Instrument cables Sat 4/11/09 Tue 4/21/09 I 0 12.21 days 1944 mtr 0.59 3731.8

198 1.4.1.3 Operation Floor Sat 11/22/08 Sat 5/30/09 0.13 209.84 days 2.05 12881.33

199 1.4.1.3.1 Air Compressed System - Piping Tue 4/14/09 Wed 4/22/09 0 9 days 0.05 333.13200 1.4.1.3.1.1 2" Equal Tee Tue 4/14/09 Sat 4/18/09 P 0 4 days 11 nos 0.03 213.2

201 1.4.1.3.1.2 2" Plug Sat 4/18/09 Sat 4/18/09 P 0 1 day 9 nos 0.01 79.95

202 1.4.1.3.1.3 1/2" Ball valve Sat 4/18/09 Sun 4/19/09 P 0 1 day 2 nos 0 10.66

203 1.4.1.3.1.4 2" x 1" Reducer Sun 4/19/09 Mon 4/20/09 P 0 1 day 2 nos 0 10.66

204 1.4.1.3.1.5 1" x 1/2" Reducer Mon 4/20/09 Tue 4/21/09 P 0 1 day 2 nos 0 10.66

205 1.4.1.3.1.6 1/2" Nipple Tue 4/21/09 Wed 4/22/09 P 0 1 day 2 nos 0 8

206 1.4.1.3.2 Installation - Electrical Sat 11/22/08 Sat 5/30/09 0.13 209.84 days 1.99 12548.21

207 1.4.1.3.2.1 Installation - Lighting System Sat 11/22/08 Tue 12/2/08 0.08 12.4 days 0.08 501.9208 1.4.1.3.2.1.1 Rigid Steel Conduit Sat 11/22/08 Sat 11/22/08 E 0.03 0.71 days 26 mtr 0.03 157.5

209 1.4.1.3.2.1.2 Single Core Wires Mon 12/1/08 Tue 12/2/08 E 0.03 0.92 days 300 mtr 0.03 188.82

210 1.4.1.3.2.1.3 High Bay Lighting fixtures including supports and fixings Tue 12/2/08 Tue 12/2/08 E 0.02 0.77 days 6 nos. 0.02 155.58

211 1.4.1.3.2.2 Installation - Crane Bus Bars Thu 12/4/08 Wed 5/13/09 0.03 176.84 days 0.9 5665.31212 1.4.1.3.2.2.1 Crane Bus Bar Supports installation Thu 12/4/08 Tue 12/9/08 E 0.02 4.84 days 16 nos. 0.02 96.37

213 1.4.1.3.2.2.2 Feed Junction Box Installation Tue 12/9/08 Wed 12/10/08 E 0.01 1.38 days 4 nos. 0.01 70.89

214 1.4.1.3.2.2.3 Disconnect Switch Instalation Wed 12/10/08 Wed 12/10/08 E 0 0.46 days 1 nos. 0 17.32

215 1.4.1.3.2.2.4 Interconnection cable, cableways installation Wed 5/6/09 Thu 5/7/09 E 0 1 day 5 nos. 0.02 133.25

216 1.4.1.3.2.2.5 Crane Power Feeder Cable Thu 5/7/09 Tue 5/12/09 E 0 5.2 days 682 mtr 0.82 5172.5

217 1.4.1.3.2.2.6 Cable Termination Tue 5/12/09 Wed 5/13/09 E 0 2.01 days 10 nos. 0.03 174.98

218 1.4.1.3.2.3 Installation - Socket / Welding Outlet Tue 12/9/08 Wed 2/4/09 0.02 63.41 days 0.06 381.71219 1.4.1.3.2.3.1 Rigid Steel Conduit Tue 12/9/08 Wed 12/10/08 E 0.01 0.87 days 15 mtr 0.01 78.35

220 1.4.1.3.2.3.2 Single Core Wires Mon 2/2/09 Tue 2/3/09 E 0 0.46 days 50 mtr 0 27.82

221 1.4.1.3.2.3.3 Junction Box Tue 2/3/09 Tue 2/3/09 E 0 0.91 days 2 nos. 0 23.98

222 1.4.1.3.2.3.4 Welding outlet / Socket Outlet Tue 2/3/09 Wed 2/4/09 E 0 0.65 days 2 nos. 0 27.05

223 1.4.1.3.2.3.5 Socket Feeder cables Wed 2/4/09 Wed 2/4/09 E 0 0.52 days 60 mtr 0.04 224.5

224 1.4.1.3.2.4 Installation - Local Junction Box Mon 4/6/09 Sat 5/30/09 0 59.84 days 0.95 5999.29225 1.4.1.3.2.4.1 Rigid Steel Conduit Mon 4/6/09 Mon 4/13/09 E 0 7.62 days 140 mtr 0.12 744.6

226 1.4.1.3.2.4.2 Junction Box Mon 4/13/09 Thu 4/16/09 E 0 3.81 days 28 nos. 0.06 372.3

227 1.4.1.3.2.4.3 Feeder cables Thu 4/16/09 Thu 4/23/09 E 0 8.72 days 1020 mtr 0.53 3358.01

228 1.4.1.3.2.4.4 Cable Termination Wed 5/13/09 Sat 5/30/09 E 0 18 days 88 nos. 0.24 1524.38

229 1.4.2 Pot 44 Sat 12/27/08 Tue 5/12/09 0.81 150.59 days 2.18 13753.32230 1.4.2.1 SLI DELIVERABLES Fri 1/23/09 Fri 1/23/09 0 0 days 0 0231 1.4.2.1.1 POT 44 Area Available for MPEI Construction Fri 1/23/09 Fri 1/23/09 0 0 days 0 0

232 1.4.2.2 Basement Floor Sat 12/27/08 Mon 4/27/09 0.78 134.2 days 1.37 8641.5233 1.4.2.2.1 Installation - Electrical Sat 12/27/08 Mon 4/27/09 0.78 134.2 days 1.37 8641.5

11/22

11/22

Electrical rooms not ready

Material by Astaldi

Material by SNC

No cable and cable trays

junction box details to be submitted

Material not yet approved by SNC

1/23

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 4 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 5: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

234 1.4.2.2.1.1 Installation - Lighting System Sat 12/27/08 Sun 2/15/09 0.77 55.26 days 0.77 4827.09235 1.4.2.2.1.1.1 PVC conduit and boxes Sat 12/27/08 Mon 12/29/08 E 0.05 2.33 days 95 mtr 0.05 303.81

236 1.4.2.2.1.1.2 Single Core Wires Sat 1/24/09 Sat 1/24/09 E 0.03 1.21 days 228 mtr 0.03 168.43

237 1.4.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Wed 1/21/09 Thu 1/22/09 E 0.03 1.77 days 24 nos. 0.03 191.21

238 1.4.2.2.1.1.4 Lighting Feeder cables / wires Thu 2/5/09 Sun 2/15/09 E 0.66 9.93 days 1738 mtr 0.66 4163.64

239 1.4.2.2.1.2 Installation - Emergency Shutdown Thu 2/19/09 Mon 4/27/09 0.01 74.3 days 0.61 3814.41240 1.4.2.2.1.2.1 PVC conduit and boxes Thu 2/19/09 Thu 2/19/09 I 0.01 0.76 days 12 mtr 0.01 63.96

241 1.4.2.2.1.2.2 Instrument cables Wed 4/15/09 Mon 4/27/09 I 0 12.21 days 1944 mtr 0.59 3731.8

242 1.4.2.2.1.2.3 Remote ASI Panel /Cabinet Mon 4/27/09 Mon 4/27/09 I 0 0.33 days 1 mtr 0 18.66

243 1.4.2.3 Operation Floor Sat 12/27/08 Tue 5/12/09 0.03 150.59 days 0.81 5111.82

244 1.4.2.3.1 Air Compressed System - Piping Sat 4/18/09 Wed 5/6/09 0 21 days 0.05 333.13245 1.4.2.3.1.1 2" Equal Tee Sat 4/18/09 Tue 4/21/09 P 0 4 days 11 nos 0.03 213.2

246 1.4.2.3.1.2 2" Plug Sun 5/3/09 Mon 5/4/09 P 0 1 day 9 nos 0.01 79.95

247 1.4.2.3.1.3 1/2" Ball valve Mon 5/4/09 Mon 5/4/09 P 0 1 day 2 nos 0 10.66

248 1.4.2.3.1.4 2" x 1" Reducer Mon 5/4/09 Tue 5/5/09 P 0 1 day 2 nos 0 10.66

249 1.4.2.3.1.5 1" x 1/2" Reducer Mon 5/4/09 Tue 5/5/09 P 0 1 day 2 nos 0 10.66

250 1.4.2.3.1.6 1/2" Nipple Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 8

251 1.4.2.3.2 Installation - Electrical Sat 12/27/08 Tue 5/12/09 0.03 150.59 days 0.76 4778.69

252 1.4.2.3.2.1 Installation - Crane Bus Bars Sat 12/27/08 Sun 12/28/08 0.02 0.99 days 0.02 96.37253 1.4.2.3.2.1.1 Crane Bus Bar Supports installation Sat 12/27/08 Sun 12/28/08 E 0.02 0.99 days 16 nos. 0.02 96.37

254 1.4.2.3.2.2 Installation - Socket / Welding Outlet Sat 1/24/09 Wed 2/4/09 0.02 14.14 days 0.06 381.71255 1.4.2.3.2.2.1 Rigid Steel Conduit Sat 1/24/09 Tue 1/27/09 E 0.01 5 days 15 mtr 0.01 78.35

256 1.4.2.3.2.2.2 Single Core Wires Tue 1/27/09 Wed 1/28/09 E 0 0.84 days 50 mtr 0 27.82

257 1.4.2.3.2.2.3 Junction Box Wed 1/28/09 Thu 1/29/09 E 0 0.72 days 2 nos. 0 23.98

258 1.4.2.3.2.2.4 Welding outlet / Socket Outlet Thu 1/29/09 Thu 1/29/09 E 0 0.5 days 2 nos. 0 27.05

259 1.4.2.3.2.2.5 Socket Feeder cables Wed 2/4/09 Wed 2/4/09 E 0 0.29 days 60 mtr 0.04 224.5

260 1.4.2.3.2.3 Installation - Local Junction Box Mon 4/13/09 Tue 5/12/09 0 32.53 days 0.68 4300.62261 1.4.2.3.2.3.1 Rigid Steel Conduit Mon 4/13/09 Sat 4/18/09 E 0 6 days 110 mtr 0.09 586.3

262 1.4.2.3.2.3.2 Junction Box Sat 4/18/09 Tue 4/21/09 E 0 3.81 days 28 nos. 0.06 372.3

263 1.4.2.3.2.3.3 Feeder cables Tue 4/21/09 Sun 4/26/09 E 0 4.72 days 550 mtr 0.29 1817.64

264 1.4.2.3.2.3.4 Cable Termination Sun 4/26/09 Tue 5/12/09 E 0 18 days 88 nos. 0.24 1524.38

265 1.4.3 Pot 66 Sat 1/31/09 Thu 5/28/09 0.79 130.65 days 2.84 17917.57266 1.4.3.1 SLI DELIVERABLES Sat 1/31/09 Sat 1/31/09 0 0 days 0 0267 1.4.3.1.1 POT 66 Area Available for MPEI Construction Sat 1/31/09 Sat 1/31/09 0 0 days 0 0

268 1.4.3.2 Basement Floor Sun 3/1/09 Thu 5/7/09 0.71 75.42 days 1.31 8282.39269 1.4.3.2.1 Installation - Electrical Sun 3/1/09 Thu 5/7/09 0.71 75.42 days 1.31 8282.39

270 1.4.3.2.1.1 Installation - Lighting System Sat 3/14/09 Wed 4/22/09 0.71 43.74 days 0.71 4486.63271 1.4.3.2.1.1.1 PVC conduit and boxes Sat 3/14/09 Sat 3/28/09 E 0.28 16.38 days 558 mtr 0.28 1777.29

272 1.4.3.2.1.1.2 Single Core Wires Sun 4/19/09 Sun 4/19/09 E 0.02 0.96 days 135 mtr 0.02 101.06

273 1.4.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 4/16/09 Sat 4/18/09 E 0.02 0.91 days 12 nos. 0.02 99.43

274 1.4.3.2.1.1.4 Lighting Feeder cables / wires Tue 4/14/09 Wed 4/22/09 E 0.4 7.99 days 1050 mtr 0.4 2508.86

275 1.4.3.2.1.2 Installation - Emergency Shutdown Sun 3/1/09 Thu 5/7/09 0 75.42 days 0.6 3795.76276 1.4.3.2.1.2.1 PVC conduit and boxes Sun 3/1/09 Mon 3/2/09 I 0 0.76 days 12 mtr 0.01 63.96

277 1.4.3.2.1.2.2 Instrument cables Mon 4/27/09 Thu 5/7/09 I 0 12.21 days 1944 mtr 0.59 3731.8

278 1.4.3.3 Operation Floor Tue 3/24/09 Thu 5/28/09 0.08 72.53 days 1.53 9635.17

279 1.4.3.3.1 Air Compressed System - Piping Tue 4/21/09 Thu 5/14/09 0 26 days 0.05 333.13280 1.4.3.3.1.1 2" Equal Tee Tue 4/21/09 Sat 4/25/09 P 0 4 days 11 nos 0.03 213.2

281 1.4.3.3.1.2 2" Plug Mon 5/11/09 Tue 5/12/09 P 0 1 day 9 nos 0.01 79.95

282 1.4.3.3.1.3 1/2" Ball valve Tue 5/12/09 Tue 5/12/09 P 0 1 day 2 nos 0 10.66

283 1.4.3.3.1.4 2" x 1" Reducer Tue 5/12/09 Wed 5/13/09 P 0 1 day 2 nos 0 10.66

284 1.4.3.3.1.5 1" x 1/2" Reducer Tue 5/12/09 Wed 5/13/09 P 0 1 day 2 nos 0 10.66

285 1.4.3.3.1.6 1/2" Nipple Wed 5/13/09 Thu 5/14/09 P 0 1 day 2 nos 0 8

286 1.4.3.3.2 Installation - Electrical Tue 3/24/09 Thu 5/28/09 0.08 72.53 days 1.48 9302.05

287 1.4.3.3.2.1 Installation - Lighting System Tue 3/24/09 Tue 4/21/09 0.08 31.28 days 0.14 887.79288 1.4.3.3.2.1.1 Rigid Steel Conduit Tue 3/24/09 Tue 3/24/09 E 0.03 0.7 days 26 mtr 0.03 157.5

289 1.4.3.3.2.1.2 Single Core Wires Sun 4/19/09 Mon 4/20/09 E 0.03 1.04 days 300 mtr 0.03 188.82

290 1.4.3.3.2.1.3 High Bay Lighting fixtures including supports and fixings Mon 4/20/09 Mon 4/20/09 E 0.02 0.84 days 6 nos. 0.02 155.58

291 1.4.3.3.2.1.4 Lighting Feeder cables / wires Mon 4/20/09 Tue 4/21/09 E 0 0.7 days 98 mtr 0.06 385.89

On going

On going

Material by Astaldi

Material by SNC

Material by SNC

No manlift available

1/31

Material by Astaldi

Material by SNC

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 5 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 6: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

292 1.4.3.3.2.2 Installation - Blower and Transformer Feeder Sat 4/18/09 Thu 4/23/09 0 5.85 days 0.43 2725.18

293 1.4.3.3.2.2.1 Blower Feeder, Transformer Feeder Sat 4/18/09 Thu 4/23/09 E 0 5.85 days 700 mtr 0.43 2725.18

294 1.4.3.3.2.3 Installation - Local Junction Box Sat 4/18/09 Thu 5/28/09 0 44.53 days 0.9 5689.08295 1.4.3.3.2.3.1 Rigid Steel Conduit Sat 4/18/09 Sat 4/25/09 E 0 7.08 days 130 mtr 0.11 691.83

296 1.4.3.3.2.3.2 Junction Box Sat 4/25/09 Tue 4/28/09 E 0 3.54 days 26 nos. 0.05 345.92

297 1.4.3.3.2.3.3 Feeder cables Tue 4/28/09 Tue 5/5/09 E 0 8.12 days 948 mtr 0.5 3126.95

298 1.4.3.3.2.3.4 Cable Termination Tue 5/12/09 Thu 5/28/09 E 0 18 days 88 nos. 0.24 1524.38

299 1.4.4 Pot 88 Sun 1/25/09 Sun 6/14/09 0.81 155.19 days 3.49 21966.37300 1.4.4.1 SLI DELIVERABLES Thu 2/5/09 Thu 2/5/09 0 0 days 0 0301 1.4.4.1.1 POT 88 Area Available for MPEI Construction Thu 2/5/09 Thu 2/5/09 0 0 days 0 0

302 1.4.4.2 Basement Floor Sat 3/14/09 Tue 5/19/09 0.71 74.18 days 1.32 8308.64303 1.4.4.2.1 Installation - Electrical Sat 3/14/09 Tue 5/19/09 0.71 74.18 days 1.32 8308.64

304 1.4.4.2.1.1 Installation - Lighting System Sat 3/14/09 Sat 3/28/09 0.71 16.45 days 0.71 4494.23305 1.4.4.2.1.1.1 PVC conduit and boxes Sat 3/14/09 Sat 3/28/09 E 0.28 16.45 days 560 mtr 0.28 1784.88

306 1.4.4.2.1.1.2 Single Core Wires Sun 3/15/09 Sun 3/15/09 E 0.02 0.96 days 137 mtr 0.02 101.06

307 1.4.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Sun 3/22/09 Sun 3/22/09 E 0.02 0.91 days 12 nos. 0.02 99.43

308 1.4.4.2.1.1.4 Lighting Feeder cables / wires Sat 3/21/09 Sat 3/28/09 E 0.4 7.99 days 1050 mtr 0.4 2508.86

309 1.4.4.2.1.2 Installation - Emergency Shutdown Thu 4/30/09 Tue 5/19/09 0 21.22 days 0.61 3814.41310 1.4.4.2.1.2.1 PVC conduit and boxes Thu 4/30/09 Thu 4/30/09 I 0 0.76 days 12 mtr 0.01 63.96

311 1.4.4.2.1.2.2 Instrument cables Thu 5/7/09 Tue 5/19/09 I 0 12.21 days 1944 mtr 0.59 3731.8

312 1.4.4.2.1.2.3 Remote ASI Panel /Cabinet Tue 5/19/09 Tue 5/19/09 I 0 0.33 days 1 mtr 0 18.66

313 1.4.4.3 Operation Floor Sun 1/25/09 Sun 6/14/09 0.09 155.19 days 2.17 13657.73

314 1.4.4.3.1 Air Compressed System - Piping Sat 4/25/09 Sat 5/16/09 0 23 days 0.05 333.13315 1.4.4.3.1.1 2" Equal Tee Sat 4/25/09 Tue 4/28/09 P 0 4 days 11 nos 0.03 213.2

316 1.4.4.3.1.2 2" Plug Tue 4/28/09 Wed 4/29/09 P 0 1 day 9 nos 0.01 79.95

317 1.4.4.3.1.3 1/2" Ball valve Wed 4/29/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66

318 1.4.4.3.1.4 2" x 1" Reducer Thu 4/30/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66

319 1.4.4.3.1.5 1" x 1/2" Reducer Thu 4/30/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66

320 1.4.4.3.1.6 1/2" Nipple Thu 5/14/09 Sat 5/16/09 P 0 1 day 2 nos 0 8

321 1.4.4.3.2 Installation - Electrical Sun 1/25/09 Sun 6/14/09 0.09 155.19 days 2.12 13324.6

322 1.4.4.3.2.1 Installation - Lighting System Mon 3/23/09 Tue 4/21/09 0.08 33.27 days 0.14 887.79323 1.4.4.3.2.1.1 Rigid Steel Conduit Mon 3/23/09 Mon 3/23/09 E 0.03 0.7 days 25 mtr 0.03 157.5

324 1.4.4.3.2.1.2 Single Core Wires Sun 4/19/09 Mon 4/20/09 E 0.03 1.04 days 300 mtr 0.03 188.82

325 1.4.4.3.2.1.3 High Bay Lighting fixtures including supports and fixings Mon 4/20/09 Tue 4/21/09 E 0.02 0.84 days 6 nos. 0.02 155.58

326 1.4.4.3.2.1.4 Lighting Feeder cables / wires Tue 4/21/09 Tue 4/21/09 E 0 0.7 days 100 mtr 0.06 385.89

327 1.4.4.3.2.2 Installation - Cable Tray Sun 4/19/09 Wed 4/29/09 0 12.65 days 0.06 382.29328 1.4.4.3.2.2.1 Cantilever supports installation Sun 4/19/09 Sun 4/19/09 E 0 0.35 days 32 nos. 0.01 38.24

329 1.4.4.3.2.2.2 Cable Tray installation Tue 4/28/09 Wed 4/29/09 E 0 1.5 days 189 mtr 0.05 344.05

330 1.4.4.3.2.3 Installation - Crane Bus Bars Sun 1/25/09 Thu 5/14/09 0.02 121.87 days 0.71 4488.71331 1.4.4.3.2.3.1 Crane Bus Bar Supports installation Sun 1/25/09 Mon 1/26/09 E 0.02 1.94 days 16 nos. 0.02 96.37

332 1.4.4.3.2.3.2 Feed Junction Box Installation Mon 1/26/09 Mon 1/26/09 E 0 0.33 days 1 nos. 0 17.59

333 1.4.4.3.2.3.3 Disconnect Switch Instalation Tue 5/5/09 Tue 5/5/09 E 0 0.5 days 1 nos. 0 17.32

334 1.4.4.3.2.3.4 Interconnection cable, cableways installation Tue 5/5/09 Wed 5/6/09 E 0 1 day 5 nos. 0.02 133.25

335 1.4.4.3.2.3.5 Crane Power Feeder Cable Wed 5/6/09 Sun 5/10/09 E 0 4.16 days 550 mtr 0.66 4138

336 1.4.4.3.2.3.6 Cable Termination Wed 5/13/09 Thu 5/14/09 E 0 0.99 days 5 nos. 0.01 86.19

337 1.4.4.3.2.4 Installation - Blower and Transformer Feeder Thu 4/23/09 Tue 4/28/09 0 5.85 days 0.43 2725.18

338 1.4.4.3.2.4.1 Blower Feeder, Transformer Feeder Thu 4/23/09 Tue 4/28/09 E 0 5.85 days 700 mtr 0.43 2725.18

339 1.4.4.3.2.5 Installation - Socket / Welding Outlet Sun 4/19/09 Tue 4/21/09 0 2.51 days 0.06 381.71340 1.4.4.3.2.5.1 Rigid Steel Conduit Sun 4/19/09 Sun 4/19/09 E 0 0.84 days 15 mtr 0.01 78.35

341 1.4.4.3.2.5.2 Single Core Wires Sun 4/19/09 Mon 4/20/09 E 0 0.36 days 50 mtr 0 27.82

342 1.4.4.3.2.5.3 Junction Box Mon 4/20/09 Mon 4/20/09 E 0 0.5 days 2 nos. 0 23.98

343 1.4.4.3.2.5.4 Welding outlet / Socket Outlet Mon 4/20/09 Mon 4/20/09 E 0 0.29 days 2 nos. 0 27.05

344 1.4.4.3.2.5.5 Socket Feeder cables Mon 4/20/09 Tue 4/21/09 E 0 0.52 days 60 mtr 0.04 224.5

345 1.4.4.3.2.6 Installation - Local Junction Box Sat 4/18/09 Sun 6/14/09 0 62.53 days 0.71 4458.92346 1.4.4.3.2.6.1 Rigid Steel Conduit Sat 4/18/09 Sat 4/25/09 E 0 7.62 days 140 mtr 0.12 744.6

347 1.4.4.3.2.6.2 Junction Box Sat 4/25/09 Tue 4/28/09 E 0 3.81 days 28 nos. 0.06 372.3

348 1.4.4.3.2.6.3 Feeder cables Wed 4/29/09 Mon 5/4/09 E 0 4.72 days 550 mtr 0.29 1817.64

349 1.4.4.3.2.6.4 Cable Termination Thu 5/28/09 Sun 6/14/09 E 0 18 days 88 nos. 0.24 1524.38

350 1.5 Construction - South Qtr. Passageway 503-22 Sat 2/28/09 Wed 5/13/09 0 83.5 days 2.69 16954.65

Electrical room not ready

Material not approved

2/5

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 6 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 7: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

351 1.5.1 SLI DELIVERABLES Sat 2/28/09 Sat 2/28/09 0 0 days 0 0352 1.5.1.1 1st- QTR Passageway Available for MPEI Construction Sat 2/28/09 Sat 2/28/09 0 0 days 0 0

353 1.5.2 Operation Floor Sun 4/5/09 Wed 5/13/09 0 43.5 days 2.69 16954.65354 1.5.2.1 Installation - Electrical (Operation Floor) Sun 4/5/09 Wed 5/13/09 0 43.5 days 2.69 16954.65355 1.5.2.1.1 Installation - Lighting System Wed 4/8/09 Sun 5/3/09 0 26.19 days 0.16 1030.61356 1.5.2.1.1.1 High Bay Lighting fixtures including supports and fixings Wed 4/8/09 Sat 4/11/09 E 0 2 days 9 nos. 0.04 234.52

357 1.5.2.1.1.2 Rigid Steel Conduit Sat 4/11/09 Mon 4/13/09 E 0 2.76 days 55 mtr 0.05 330.99

358 1.5.2.1.1.3 Single Core Wires Mon 4/13/09 Tue 4/14/09 E 0 1.66 days 150 mtr 0.02 97.33

359 1.5.2.1.1.4 Lighting Feeder cables / wires Sat 5/2/09 Sun 5/3/09 E 0 0.69 days 90 mtr 0.06 367.77

360 1.5.2.1.2 Installation - Cable Tray Sun 4/5/09 Sat 5/2/09 0 30.5 days 0.55 3457.17361 1.5.2.1.2.1 Cantilever supports installation Sun 4/5/09 Sat 4/11/09 E 0 6.5 days 265 nos. 0.09 577.64

362 1.5.2.1.2.2 Cable tray installation Sat 4/11/09 Sat 5/2/09 E 0 24 days 1591 mtr 0.46 2879.53

363 1.5.2.1.3 Installation - Crane Bus Bars Sat 4/11/09 Wed 5/13/09 0 37 days 1.98 12466.87364 1.5.2.1.3.1 Feed Junction Box Installation Sat 4/11/09 Tue 4/14/09 E 0 4 days 8 nos. 0.02 138.58

365 1.5.2.1.3.2 Disconnect Switch Instalation Tue 4/14/09 Wed 4/15/09 E 0 1 day 4 nos. 0.01 69.29

366 1.5.2.1.3.3 Interconnection cable, cableways installation Wed 4/15/09 Tue 5/12/09 E 0 30 days 600 mtr 1.9 11992.5

367 1.5.2.1.3.4 Cable termination Tue 5/12/09 Wed 5/13/09 E 0 2 days 15 nos 0.04 266.5

368 1.6 Construction - Potroom No. 1 (501-12B) Fri 3/6/09 Thu 8/13/09 0 178.05 days 11.32 71304.69

369 1.6.1 Pot 110 Fri 3/6/09 Wed 6/3/09 0 99.05 days 2.99 18863.48370 4.7.1.1 SLI DELIVERABLES Fri 3/6/09 Fri 3/6/09 0 0 days 0 0371 4.7.1.1.1 POT 110 Area Available for MPEI Construction Fri 3/6/09 Fri 3/6/09 0 0 days 0 0

372 1.6.1.2 Basement Floor Sat 4/25/09 Sat 5/30/09 0 39.22 days 1.12 7043.12

373 1.6.1.2.1 Installation - Electrical Sat 4/25/09 Sat 5/30/09 0 39.22 days 1.12 7043.12

374 1.6.1.2.1.1 Installation - Lighting System Thu 5/7/09 Mon 5/18/09 0 12.7 days 0.51 3228.7375 1.6.1.2.1.1.1 PVC conduit and boxes Thu 5/7/09 Sat 5/9/09 E 0 1.96 days 66 mtr 0.03 212.67

376 1.6.1.2.1.1.2 Single Core Wires Sat 5/9/09 Sun 5/10/09 E 0 1.12 days 156 mtr 0.02 117.9

377 1.6.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 5/7/09 Sat 5/9/09 E 0 1.12 days 15 nos. 0.02 122.38

378 1.6.1.2.1.1.4 Lighting Feeder cables / wires Mon 5/11/09 Mon 5/18/09 E 0 8.84 days 1167 mtr 0.44 2775.76

379 1.6.1.2.1.2 Installation - Emergency Shutdown Sat 4/25/09 Sat 5/30/09 0 39.22 days 0.61 3814.41380 1.6.1.2.1.2.1 PVC conduit and boxes Sat 4/25/09 Sat 4/25/09 I 0 0.76 days 12 mtr 0.01 63.96

381 1.6.1.2.1.2.2 Instrument cables Mon 5/18/09 Sat 5/30/09 I 0 12.21 days 1944 mtr 0.59 3731.8

382 1.6.1.2.1.2.3 Remote ASI Panel /Cabinet Sat 5/30/09 Sat 5/30/09 I 0 0.33 days 1 mtr 0 18.66

383 1.6.1.3 Operation Floor Sat 4/11/09 Wed 6/3/09 0 59.05 days 1.88 11820.37

384 1.6.1.3.1 Installation - Electrical Sat 4/11/09 Wed 6/3/09 0 59.05 days 1.82 11487.24

385 1.6.1.3.1.1 Installation - Lighting System Sat 4/18/09 Mon 5/4/09 0 17.64 days 0.37 2341.92386 1.6.1.3.1.1.1 Rigid Steel Conduit Sat 4/18/09 Sun 4/19/09 E 0 1.4 days 52 mtr 0.05 315

387 1.6.1.3.1.1.2 Single Core Wires Sun 4/19/09 Thu 4/23/09 E 0 5.04 days 1410 mtr 0.15 915.03

388 1.6.1.3.1.1.3 Junction Box Thu 4/23/09 Thu 4/23/09 E 0 0.22 days 2 nos. 0.01 36.35

389 1.6.1.3.1.1.4 High Bay Lighting fixtures including supports and fixings Thu 4/23/09 Sun 4/26/09 E 0 1.64 days 12 nos. 0.05 303.76

390 1.6.1.3.1.1.5 Lighting Feeder cables / wires Sun 5/3/09 Mon 5/4/09 E 0 1.4 days 196 mtr 0.12 771.78

391 1.6.1.3.1.2 Installation - Cable Tray Sat 4/11/09 Mon 5/4/09 0 25.35 days 0.02 110.86392 1.6.1.3.1.2.1 Cantilever supports installation Sat 4/11/09 Sun 4/12/09 E 0 0.07 days 9 nos. 0 7.65

393 1.6.1.3.1.2.2 Cable Tray installation Mon 5/4/09 Mon 5/4/09 E 0 0.45 days 55 mtr 0.02 103.22

394 1.6.1.3.1.3 Installation - Blower and Transformer Feeder Tue 4/28/09 Mon 5/4/09 0 5.85 days 0.42 2653.46

395 1.6.1.3.1.3.1 Blower Feeder, Transformer Feeder Tue 4/28/09 Mon 5/4/09 E 0 5.85 days 700 mtr 0.42 2653.46

396 1.6.1.3.1.4 Installation - Socket / Welding Outlet Thu 4/23/09 Sun 4/26/09 0 2.51 days 0.06 381.71397 1.6.1.3.1.4.1 Rigid Steel Conduit Thu 4/23/09 Thu 4/23/09 E 0 0.84 days 15 mtr 0.01 78.35

398 1.6.1.3.1.4.2 Junction Box Thu 4/23/09 Sat 4/25/09 E 0 0.5 days 2 nos. 0 23.98

399 1.6.1.3.1.4.3 Single Core Wires Sat 4/25/09 Sat 4/25/09 E 0 0.36 days 50 mtr 0 27.82

400 1.6.1.3.1.4.4 Welding outlet / Socket Outlet Sat 4/25/09 Sat 4/25/09 E 0 0.29 days 2 nos. 0 27.05

401 1.6.1.3.1.4.5 Socket Feeder cables Sat 4/25/09 Sun 4/26/09 E 0 0.52 days 60 mtr 0.04 224.5

402 1.6.1.3.1.5 Installation - Local Junction Box Thu 4/30/09 Wed 6/3/09 0 38.15 days 0.95 5999.29403 1.6.1.3.1.5.1 Rigid Steel Conduit Thu 4/30/09 Thu 5/7/09 E 0 7.62 days 140 mtr 0.12 744.6

404 1.6.1.3.1.5.2 Junction Box Thu 5/7/09 Sun 5/10/09 E 0 3.81 days 28 nos. 0.06 372.3

405 1.6.1.3.1.5.3 Feeder cables Sun 5/10/09 Mon 5/18/09 E 0 8.72 days 1020 mtr 0.53 3358.01

406 1.6.1.3.1.5.4 Cable Termination Mon 5/18/09 Wed 6/3/09 E 0 18 days 88 nos. 0.24 1524.38

407 1.6.1.3.2 Air Compressed System - Piping Sat 4/25/09 Thu 4/30/09 0 6 days 0.05 333.13408 1.6.1.3.2.1 2" Equal Tee Sat 4/25/09 Tue 4/28/09 P 0 4 days 11 nos 0.03 213.2

409 1.6.1.3.2.2 2" Plug Sun 4/26/09 Mon 4/27/09 P 0 1 day 9 nos 0.01 79.95

410 1.6.1.3.2.3 1/2" Ball valve Mon 4/27/09 Tue 4/28/09 P 0 1 day 2 nos 0 10.66

2/28

3/6

3/6

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 7 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 8: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

411 1.6.1.3.2.4 2" x 1" Reducer Tue 4/28/09 Wed 4/29/09 P 0 1 day 2 nos 0 10.66

412 1.6.1.3.2.5 1" x 1/2" Reducer Tue 4/28/09 Wed 4/29/09 P 0 1 day 2 nos 0 10.66

413 1.6.1.3.2.6 1/2" Nipple Wed 4/29/09 Thu 4/30/09 P 0 1 day 2 nos 0 8

414 1.6.2 Pot 132 Tue 3/31/09 Sat 6/20/09 0 89.73 days 3.95 24908.58415 1.6.2.1 SLI DELIVERABLES Tue 3/31/09 Tue 3/31/09 0 0 days 0 0416 1.6.2.1.1 POT 132 Area Available for MPEI Construction Tue 3/31/09 Tue 3/31/09 0 0 days 0 0

417 1.6.2.2 Basement Floor Sat 4/25/09 Wed 6/3/09 0 44.13 days 1.25 7885.02418 1.6.2.2.1 Installation - Electrical Sat 4/25/09 Wed 6/3/09 0 44.13 days 1.25 7885.02

419 1.6.2.2.1.1 Installation - Lighting System Sat 5/9/09 Sat 5/23/09 0 14.96 days 0.65 4089.26420 1.6.2.2.1.1.1 PVC conduit and boxes Sat 5/9/09 Mon 5/11/09 E 0 2.45 days 84 mtr 0.04 265.83

421 1.6.2.2.1.1.2 Single Core Wires Mon 5/11/09 Tue 5/12/09 E 0 1.4 days 198 mtr 0.02 147.37

422 1.6.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Sun 5/10/09 Mon 5/11/09 E 0 1.4 days 19 nos. 0.02 152.97

423 1.6.2.2.1.1.4 Lighting Feeder cables / wires Tue 5/12/09 Sat 5/23/09 E 0 11.22 days 1478 mtr 0.56 3523.08

424 1.6.2.2.1.2 Installation - Emergency Shutdown Sat 4/25/09 Wed 6/3/09 0 44.13 days 0.6 3795.76425 1.6.2.2.1.2.1 PVC conduit and boxes Sat 4/25/09 Tue 4/28/09 I 0 4 days 12 mtr 0.01 63.96

426 1.6.2.2.1.2.2 Instrument cables Mon 5/25/09 Wed 6/3/09 I 0 11 days 1944 mtr 0.59 3731.8

427 1.6.2.3 Operation Floor Sun 4/12/09 Sat 6/20/09 0 76.98 days 2.7 17023.57

428 1.6.2.3.1 Installation - Electrical Sun 4/12/09 Sat 6/20/09 0 76.98 days 2.65 16690.44

429 1.6.2.3.1.1 Installation - Lighting System Sun 4/19/09 Mon 5/4/09 0 16.94 days 0.14 887.79430 1.6.2.3.1.1.1 Rigid Steel Conduit Sun 4/19/09 Mon 4/20/09 E 0 0.7 days 25 mtr 0.03 157.5

431 1.6.2.3.1.1.2 Single Core Wires Mon 4/20/09 Tue 4/21/09 E 0 1.04 days 300 mtr 0.03 188.82

432 1.6.2.3.1.1.3 High Bay Lighting fixtures including supports and fixings Tue 4/21/09 Tue 4/21/09 E 0 0.84 days 6 nos. 0.02 155.58

433 1.6.2.3.1.1.4 Lighting Feeder cables / wires Mon 5/4/09 Mon 5/4/09 E 0 0.7 days 100 mtr 0.06 385.89

434 1.6.2.3.1.2 Installation - Cable Tray Sun 4/12/09 Sun 5/10/09 0 31.68 days 0.02 110.86435 1.6.2.3.1.2.1 Cantilever supports installation Sun 4/12/09 Sun 4/12/09 E 0 0.07 days 9 nos. 0 7.65

436 1.6.2.3.1.2.2 Cable Tray installation Sat 5/9/09 Sun 5/10/09 E 0 1 day 55 mtr 0.02 103.22

437 1.6.2.3.1.3 Installation - Crane Bus Bars Sun 5/3/09 Mon 5/11/09 0 9.19 days 1.06 6657.33438 1.6.2.3.1.3.1 Crane Bus Bar Supports installation Sun 5/3/09 Sun 5/3/09 E 0 0.96 days 16 nos. 0.02 96.37

439 1.6.2.3.1.3.2 Feed Junction Box Installation Sun 5/3/09 Mon 5/4/09 E 0 0.33 days 1 nos. 0 17.59

440 1.6.2.3.1.3.3 Disconnect Switch Instalation Mon 5/4/09 Mon 5/4/09 E 0 0.5 days 1 nos. 0 17.32

441 1.6.2.3.1.3.4 Interconnection cable, cableways installation Mon 5/4/09 Tue 5/5/09 E 0 1 day 5 nos. 0.03 159.9

442 1.6.2.3.1.3.5 Crane Power Feeder Cable Tue 5/5/09 Mon 5/11/09 E 0 6.4 days 840 mtr 1.01 6366.15

443 1.6.2.3.1.4 Installation - Blower and Transformer Feeder Mon 5/4/09 Sat 5/9/09 0 5.85 days 0.42 2653.46

444 1.6.2.3.1.4.1 Blower Feeder, Transformer Feeder Mon 5/4/09 Sat 5/9/09 E 0 5.85 days 700 mtr 0.42 2653.46

445 1.6.2.3.1.5 Installation - Socket / Welding Outlet Thu 4/23/09 Sun 4/26/09 0 2.51 days 0.06 381.71446 1.6.2.3.1.5.1 Rigid Steel Conduit Thu 4/23/09 Sat 4/25/09 E 0 0.84 days 15 mtr 0.01 78.35

447 1.6.2.3.1.5.2 Single Core Wires Sat 4/25/09 Sat 4/25/09 E 0 0.36 days 50 mtr 0 27.82

448 1.6.2.3.1.5.3 Junction Box Sat 4/25/09 Sun 4/26/09 E 0 0.5 days 2 nos. 0 23.98

449 1.6.2.3.1.5.4 Welding outlet / Socket Outlet Sun 4/26/09 Sun 4/26/09 E 0 0.29 days 2 nos. 0 27.05

450 1.6.2.3.1.5.5 Socket Feeder cables Sun 4/26/09 Sun 4/26/09 E 0 0.52 days 60 mtr 0.04 224.5

451 1.6.2.3.1.6 Installation - Local Junction Box Thu 5/7/09 Sat 6/20/09 0 48.53 days 0.95 5999.29452 1.6.2.3.1.6.1 Rigid Steel Conduit Thu 5/7/09 Wed 5/13/09 E 0 7.62 days 140 mtr 0.12 744.6

453 1.6.2.3.1.6.2 Junction Box Wed 5/13/09 Sun 5/17/09 E 0 3.81 days 28 nos. 0.06 372.3

454 1.6.2.3.1.6.3 Feeder cables Sun 5/17/09 Mon 5/25/09 E 0 8.72 days 1020 mtr 0.53 3358.01

455 1.6.2.3.1.6.4 Cable Termination Wed 6/3/09 Sat 6/20/09 E 0 18 days 88 nos. 0.24 1524.38

456 1.6.2.3.2 Air Compressed System - Piping Tue 4/28/09 Mon 5/4/09 0 6 days 0.05 333.13457 1.6.2.3.2.1 2" Equal Tee Tue 4/28/09 Sat 5/2/09 P 0 4 days 11 nos 0.03 213.2

458 1.6.2.3.2.2 2" Plug Thu 4/30/09 Thu 4/30/09 P 0 1 day 9 nos 0.01 79.95

459 1.6.2.3.2.3 1/2" Ball valve Thu 4/30/09 Sat 5/2/09 P 0 1 day 2 nos 0 10.66

460 1.6.2.3.2.4 2" x 1" Reducer Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66

461 1.6.2.3.2.5 1" x 1/2" Reducer Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66

462 1.6.2.3.2.6 1/2" Nipple Sun 5/3/09 Mon 5/4/09 P 0 1 day 2 nos 0 8

463 1.6.3 Pot 154 Wed 4/22/09 Mon 7/20/09 0 98.19 days 2.11 13302.51464 1.6.3.1 SLI DELIVERABLES Wed 4/22/09 Wed 4/22/09 0 0 days 0 0465 1.6.3.1.1 POT 154 Area Available for MPEI Construction Wed 4/22/09 Wed 4/22/09 0 0 days 0 0

466 1.6.3.2 Basement Floor Tue 4/28/09 Wed 6/10/09 0 47.67 days 1.16 7280.3467 1.6.3.2.1 Installation - Electrical Tue 4/28/09 Wed 6/10/09 0 47.67 days 1.16 7280.3

468 1.6.3.2.1.1 Installation - Lighting System Mon 5/11/09 Sun 5/31/09 0 22.03 days 0.55 3465.89469 1.6.3.2.1.1.1 PVC conduit and boxes Mon 5/11/09 Wed 5/13/09 E 0 2.03 days 69 mtr 0.03 220.26

470 1.6.3.2.1.1.2 Single Core Wires Wed 5/13/09 Thu 5/14/09 E 0 1.2 days 167 mtr 0.02 126.32

3/31

4/22

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 8 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 9: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

471 1.6.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Mon 5/11/09 Tue 5/12/09 E 0 1.19 days 16 nos. 0.02 130.03

472 1.6.3.2.1.1.4 Lighting Feeder cables / wires Sat 5/23/09 Sun 5/31/09 E 0 9.52 days 1244 mtr 0.47 2989.28

473 1.6.3.2.1.2 Installation - Emergency Shutdown Tue 4/28/09 Wed 6/10/09 0 47.67 days 0.61 3814.41474 1.6.3.2.1.2.1 PVC conduit and boxes Tue 4/28/09 Wed 4/29/09 I 0 0.76 days 12 mtr 0.01 63.96

475 1.6.3.2.1.2.2 Instrument cables Sun 5/31/09 Wed 6/10/09 I 0 12.21 days 1944 mtr 0.59 3731.8

476 1.6.3.2.1.2.3 Remote ASI Panel /Cabinet Wed 6/10/09 Wed 6/10/09 I 0 0.33 days 1 mtr 0 18.66

477 1.6.3.3 Operation Floor Thu 4/30/09 Mon 7/20/09 0 88.19 days 0.96 6022.21

478 1.6.3.3.1 Installation - Electrical Thu 4/30/09 Mon 7/20/09 0 88.19 days 0.9 5689.08

479 1.6.3.3.1.1 Installation - Local Junction Box Thu 4/30/09 Mon 7/20/09 0 88.19 days 0.9 5689.08480 1.6.3.3.1.1.1 Rigid Steel Conduit Thu 4/30/09 Thu 5/7/09 E 0 7.08 days 130 mtr 0.11 691.83

481 1.6.3.3.1.1.2 Junction Box Thu 5/7/09 Mon 5/11/09 E 0 3.54 days 26 nos. 0.05 345.92

482 1.6.3.3.1.1.3 Feeder cables Mon 5/11/09 Mon 5/18/09 E 0 8.12 days 948 mtr 0.5 3126.95

483 1.6.3.3.1.1.4 Cable Termination Sat 7/4/09 Mon 7/20/09 E 0 18 days 88 nos. 0.24 1524.38

484 1.6.3.3.2 Air Compressed System - Piping Sat 5/2/09 Thu 5/7/09 0 7 days 0.05 333.13485 1.6.3.3.2.1 2" Equal Tee Sat 5/2/09 Tue 5/5/09 P 0 4 days 11 nos 0.03 213.2

486 1.6.3.3.2.2 2" Plug Mon 5/4/09 Mon 5/4/09 P 0 1 day 9 nos 0.01 79.95

487 1.6.3.3.2.3 1/2" Ball valve Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 10.66

488 1.6.3.3.2.4 2" x 1" Reducer Wed 5/6/09 Thu 5/7/09 P 0 1 day 2 nos 0 10.66

489 1.6.3.3.2.5 1" x 1/2" Reducer Wed 5/6/09 Thu 5/7/09 P 0 1 day 2 nos 0 10.66

490 1.6.3.3.2.6 1/2" Nipple Thu 5/7/09 Thu 5/7/09 P 0 1 day 2 nos 0 8

491 1.6.4 Pot 176 Thu 5/14/09 Thu 8/13/09 0 101.65 days 2.26 14230.11492 1.6.4.1 SLI DELIVERABLES Thu 5/14/09 Thu 5/14/09 0 0 days 0 0493 1.6.4.1.1 POT 176 Area Available for MPEI Construction Thu 5/14/09 Thu 5/14/09 0 0 days 0 0

494 1.6.4.2 Basement Floor Thu 5/14/09 Wed 6/17/09 0 37.36 days 1.28 8072.21495 1.6.4.2.1 Installation - Electrical Thu 5/14/09 Wed 6/17/09 0 37.36 days 1.28 8072.21

496 1.6.4.2.1.1 Installation - Lighting System Mon 5/18/09 Tue 6/2/09 0 17.21 days 0.68 4276.45497 1.6.4.2.1.1.1 PVC conduit and boxes Mon 5/18/09 Wed 5/20/09 E 0 2.59 days 88 mtr 0.04 281.02

498 1.6.4.2.1.1.2 Single Core Wires Wed 5/20/09 Thu 5/21/09 E 0 1.44 days 205 mtr 0.02 151.59

499 1.6.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Mon 5/18/09 Tue 5/19/09 E 0 1.47 days 20 nos. 0.03 160.62

500 1.6.4.2.1.1.4 Lighting Feeder cables / wires Sat 5/23/09 Tue 6/2/09 E 0 11.73 days 1544 mtr 0.58 3683.22

501 1.6.4.2.1.2 Installation - Emergency Shutdown Thu 5/14/09 Wed 6/17/09 0 37.36 days 0.6 3795.76502 1.6.4.2.1.2.1 PVC conduit and boxes Thu 5/14/09 Thu 5/14/09 I 0 0.76 days 12 mtr 0.01 63.96

503 1.6.4.2.1.2.2 Instrument cables Sat 6/6/09 Wed 6/17/09 I 0 12.21 days 1944 mtr 0.59 3731.8

504 1.6.4.3 Operation Floor Thu 5/14/09 Thu 8/13/09 0 101.65 days 0.98 6157.91

505 1.6.4.3.1 Installation - Electrical Thu 5/14/09 Thu 8/13/09 0 101.65 days 0.92 5824.78

506 1.6.4.3.1.1 Installation - Lighting System Sat 5/23/09 Tue 5/26/09 0 3.28 days 0.14 887.79507 1.6.4.3.1.1.1 Rigid Steel Conduit Sat 5/23/09 Sun 5/24/09 E 0 0.7 days 26 mtr 0.03 157.5

508 1.6.4.3.1.1.2 Single Core Wires Sun 5/24/09 Mon 5/25/09 E 0 1.04 days 300 mtr 0.03 188.82

509 1.6.4.3.1.1.3 High Bay Lighting fixtures including supports and fixings Mon 5/25/09 Mon 5/25/09 E 0 0.84 days 6 nos. 0.02 155.58

510 1.6.4.3.1.1.4 Lighting Feeder cables / wires Mon 5/25/09 Tue 5/26/09 E 0 0.7 days 98 mtr 0.06 385.89

511 1.6.4.3.1.2 Installation - Crane Bus Bars Thu 5/14/09 Thu 5/14/09 0 0.96 days 0.02 96.37512 1.6.4.3.1.2.1 Crane Bus Bar Supports installation Thu 5/14/09 Thu 5/14/09 E 0 0.96 days 16 nos. 0.02 96.37

513 1.6.4.3.1.3 Installation - Socket / Welding Outlet Thu 5/14/09 Sun 5/17/09 0 2.99 days 0.06 381.71514 1.6.4.3.1.3.1 Rigid Steel Conduit Thu 5/14/09 Thu 5/14/09 E 0 1 day 15 mtr 0.01 78.35

515 1.6.4.3.1.3.2 Single Core Wires Thu 5/14/09 Sat 5/16/09 E 0 0.84 days 50 mtr 0 27.82

516 1.6.4.3.1.3.3 Junction Box Sat 5/16/09 Sat 5/16/09 E 0 0.36 days 2 nos. 0 23.98

517 1.6.4.3.1.3.4 Welding outlet / Socket Outlet Sat 5/16/09 Sun 5/17/09 E 0 0.5 days 2 nos. 0 27.05

518 1.6.4.3.1.3.5 Socket Feeder cables Sun 5/17/09 Sun 5/17/09 E 0 0.29 days 60 mtr 0.04 224.5

519 1.6.4.3.1.4 Installation - Local Junction Box Wed 6/10/09 Thu 8/13/09 0 71.65 days 0.71 4458.92520 1.6.4.3.1.4.1 Rigid Steel Conduit Wed 6/10/09 Wed 6/17/09 E 0 7.62 days 140 mtr 0.12 744.6

521 1.6.4.3.1.4.2 Junction Box Wed 6/17/09 Sun 6/21/09 E 0 3.81 days 28 nos. 0.06 372.3

522 1.6.4.3.1.4.3 Feeder cables Sun 6/21/09 Wed 6/24/09 E 0 4.72 days 550 mtr 0.29 1817.64

523 1.6.4.3.1.4.4 Cable Termination Tue 7/28/09 Thu 8/13/09 E 0 18 days 88 nos. 0.24 1524.38

524 1.6.4.3.2 Air Compressed System - Piping Thu 5/14/09 Wed 5/20/09 0 7 days 0.05 333.13525 1.6.4.3.2.1 2" Equal Tee Thu 5/14/09 Mon 5/18/09 P 0 4 days 11 nos 0.03 213.2

526 1.6.4.3.2.2 2" Plug Sat 5/16/09 Sun 5/17/09 P 0 1 day 9 nos 0.01 79.95

527 1.6.4.3.2.3 1/2" Ball valve Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66

528 1.6.4.3.2.4 2" x 1" Reducer Tue 5/19/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66

529 1.6.4.3.2.5 1" x 1/2" Reducer Tue 5/19/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66

5/14

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 9 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 10: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

530 1.6.4.3.2.6 1/2" Nipple Tue 5/19/09 Wed 5/20/09 P 0 1 day 2 nos 0 8

531 1.7 Construction - Potroom No. 2 (501-22B) Sat 2/28/09 Wed 7/8/09 0 145.65 days 11.3 71167.76

532 1.7.1 Pot 110 Sat 2/28/09 Mon 6/22/09 0 127.65 days 3.05 19187.68533 4.5.2.1 SLI DELIVERABLES Sat 2/28/09 Sat 2/28/09 0 0 days 0 0534 1.7.1.1.1 POT 110 Area Available for MPEI Construction Sat 2/28/09 Sat 2/28/09 0 0 days 0 0

535 1.7.1.2 Basement Floor Thu 4/30/09 Tue 5/26/09 0 27.67 days 1.12 7043.12

536 1.7.1.2.1 Installation - Electrical Thu 4/30/09 Tue 5/26/09 0 27.67 days 1.12 7043.12

537 1.7.1.2.1.1 Installation - Lighting System Thu 5/7/09 Sun 5/24/09 0 18.29 days 0.51 3228.7538 1.7.1.2.1.1.1 PVC conduit and boxes Thu 5/7/09 Sat 5/9/09 E 0 1.96 days 66 mtr 0.03 212.67

539 1.7.1.2.1.1.2 Single Core Wires Sat 5/9/09 Sun 5/10/09 E 0 1.12 days 156 mtr 0.02 117.9

540 1.7.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 5/7/09 Sat 5/9/09 E 0 1.12 days 15 nos. 0.02 122.38

541 1.7.1.2.1.1.4 Lighting Feeder cables / wires Sat 5/16/09 Sun 5/24/09 E 0 8.84 days 1167 mtr 0.44 2775.76

542 1.7.1.2.1.2 Installation - Emergency Shutdown Thu 4/30/09 Tue 5/26/09 0 27.67 days 0.61 3814.41543 1.7.1.2.1.2.1 PVC conduit and boxes Thu 4/30/09 Sat 5/2/09 I 0 0.76 days 12 mtr 0.01 63.96

544 1.7.1.2.1.2.2 Instrument cables Thu 5/14/09 Mon 5/25/09 I 0 12.21 days 1944 mtr 0.59 3731.8

545 1.7.1.2.1.2.3 Remote ASI Panel /Cabinet Mon 5/25/09 Tue 5/26/09 I 0 0.33 days 1 mtr 0 18.66

546 1.7.1.3 Operation Floor Mon 4/13/09 Mon 6/22/09 0 77.65 days 1.93 12144.56

547 1.7.1.3.1 Installation - Electrical Mon 4/13/09 Mon 6/22/09 0 77.65 days 1.88 11811.44

548 1.7.1.3.1.1 Installation - Lighting System Sun 4/19/09 Mon 4/27/09 0 9.7 days 0.37 2341.92549 1.7.1.3.1.1.1 Rigid Steel Conduit Sun 4/19/09 Mon 4/20/09 E 0 1.4 days 52 mtr 0.05 315

550 1.7.1.3.1.1.2 Single Core Wires Mon 4/20/09 Sat 4/25/09 E 0 5.04 days 1410 mtr 0.15 915.03

551 1.7.1.3.1.1.3 Junction Box Sat 4/25/09 Sat 4/25/09 E 0 0.22 days 2 nos. 0.01 36.35

552 1.7.1.3.1.1.4 High Bay Lighting fixtures including supports and fixings Sat 4/25/09 Sun 4/26/09 E 0 1.64 days 12 nos. 0.05 303.76

553 1.7.1.3.1.1.5 Lighting Feeder cables / wires Sun 4/26/09 Mon 4/27/09 E 0 1.4 days 196 mtr 0.12 771.78

554 1.7.1.3.1.2 Installation - Cable Tray Mon 4/13/09 Sat 5/16/09 0 35.66 days 0.06 382.29555 1.7.1.3.1.2.1 Cantilever supports installation Mon 4/13/09 Tue 4/14/09 E 0 0.35 days 32 nos. 0.01 38.24

556 1.7.1.3.1.2.2 Cable Tray installation Thu 5/14/09 Sat 5/16/09 E 0 1.5 days 189 mtr 0.05 344.05

557 1.7.1.3.1.3 Installation - Blower and Transformer Feeder Sat 5/9/09 Thu 5/14/09 0 5.85 days 0.42 2653.46

558 1.7.1.3.1.3.1 Blower Feeder, Transformer Feeder Sat 5/9/09 Thu 5/14/09 E 0 5.85 days 700 mtr 0.42 2653.46

559 1.7.1.3.1.4 Installation - Socket / Welding Outlet Sun 4/19/09 Wed 4/22/09 0 3.23 days 0.07 434.47560 1.7.1.3.1.4.1 Rigid Steel Conduit Sun 4/19/09 Mon 4/20/09 E 0 0.84 days 15 mtr 0.01 78.35

561 1.7.1.3.1.4.2 Single Core Wires Mon 4/20/09 Tue 4/21/09 E 0 1.08 days 50 mtr 0.01 80.59

562 1.7.1.3.1.4.3 Junction Box Tue 4/21/09 Tue 4/21/09 E 0 0.5 days 2 nos. 0 23.98

563 1.7.1.3.1.4.4 Welding outlet / Socket Outlet Tue 4/21/09 Tue 4/21/09 E 0 0.29 days 2 nos. 0 27.05

564 1.7.1.3.1.4.5 Socket Feeder cables Tue 4/21/09 Wed 4/22/09 E 0 0.52 days 60 mtr 0.04 224.5

565 1.7.1.3.1.5 Installation - Local Junction Box Sat 4/25/09 Mon 6/22/09 0 64.91 days 0.95 5999.29566 1.7.1.3.1.5.1 Rigid Steel Conduit Sat 4/25/09 Sat 5/2/09 E 0 7.62 days 140 mtr 0.12 744.6

567 1.7.1.3.1.5.2 Junction Box Sat 5/2/09 Tue 5/5/09 E 0 3.81 days 28 nos. 0.06 372.3

568 1.7.1.3.1.5.3 Feeder cables Sat 5/16/09 Sun 5/24/09 E 0 8.72 days 1020 mtr 0.53 3358.01

569 1.7.1.3.1.5.4 Cable Termination Sun 6/7/09 Mon 6/22/09 E 0 18 days 88 nos. 0.24 1524.38

570 1.7.1.3.2 Air Compressed System - Piping Tue 4/28/09 Sat 5/16/09 0 20 days 0.05 333.13571 1.7.1.3.2.1 2" Equal Tee Tue 4/28/09 Sat 5/2/09 P 0 4 days 11 nos 0.03 213.2

572 1.7.1.3.2.2 2" Plug Thu 4/30/09 Thu 4/30/09 P 0 1 day 9 nos 0.01 79.95

573 1.7.1.3.2.3 1/2" Ball valve Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66

574 1.7.1.3.2.4 2" x 1" Reducer Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66

575 1.7.1.3.2.5 1" x 1/2" Reducer Sat 5/2/09 Sun 5/3/09 P 0 1 day 2 nos 0 10.66

576 1.7.1.3.2.6 1/2" Nipple Sat 5/16/09 Sat 5/16/09 P 0 1 day 2 nos 0 8

577 1.7.2 Pot 132 Wed 3/18/09 Mon 6/22/09 0 106.98 days 3.87 24355.97578 4.5.2.1 SLI DELIVERABLES Wed 3/18/09 Wed 3/18/09 0 0 days 0 0579 1.7.2.1.1 POT 132 Area Available for MPEI Construction Wed 3/18/09 Wed 3/18/09 0 0 days 0 0

580 1.7.2.2 Basement Floor Sat 5/9/09 Mon 6/1/09 0 25.6 days 1.26 7938.4581 1.7.2.2.1 Installation - Electrical Sat 5/9/09 Mon 6/1/09 0 25.6 days 1.26 7938.4

582 1.7.2.2.1.1 Installation - Lighting System Sat 5/9/09 Sun 5/31/09 0 23.88 days 0.66 4142.64583 1.7.2.2.1.1.1 PVC conduit and boxes Sat 5/9/09 Mon 5/11/09 E 0 2.45 days 84 mtr 0.04 265.83

584 1.7.2.2.1.1.2 Single Core Wires Mon 5/11/09 Tue 5/12/09 E 0 1.4 days 198 mtr 0.02 147.37

585 1.7.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Sun 5/10/09 Mon 5/11/09 E 0 1.4 days 19 nos. 0.02 152.97

586 1.7.2.2.1.1.4 Lighting Feeder cables / wires Wed 5/20/09 Sun 5/31/09 E 0 11.39 days 1498 mtr 0.57 3576.46

587 1.7.2.2.1.2 Installation - Emergency Shutdown Tue 5/19/09 Mon 6/1/09 0 13.79 days 0.6 3795.76588 1.7.2.2.1.2.1 PVC conduit and boxes Tue 5/19/09 Wed 5/20/09 I 0 0.76 days 12 mtr 0.01 63.96

2/28

2/28

3/18

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 10 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 11: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

589 1.7.2.2.1.2.2 Instrument cables Thu 5/21/09 Mon 6/1/09 I 0 12.21 days 1944 mtr 0.59 3731.8

590 1.7.2.3 Operation Floor Tue 4/14/09 Mon 6/22/09 0 77.3 days 2.61 16417.57

591 1.7.2.3.1 Installation - Electrical Tue 4/14/09 Mon 6/22/09 0 77.3 days 2.55 16084.45

592 1.7.2.3.1.1 Installation - Lighting System Mon 4/20/09 Mon 4/27/09 0 7.6 days 0.14 887.79593 1.7.2.3.1.1.1 Rigid Steel Conduit Mon 4/20/09 Mon 4/20/09 E 0 0.7 days 25 mtr 0.03 157.5

594 1.7.2.3.1.1.2 Single Core Wires Mon 4/20/09 Tue 4/21/09 E 0 1.04 days 300 mtr 0.03 188.82

595 1.7.2.3.1.1.3 High Bay Lighting fixtures including supports and fixings Tue 4/21/09 Wed 4/22/09 E 0 0.84 days 6 nos. 0.02 155.58

596 1.7.2.3.1.1.4 Lighting Feeder cables / wires Sun 4/26/09 Mon 4/27/09 E 0 0.7 days 100 mtr 0.06 385.89

597 1.7.2.3.1.2 Installation - Cable Tray Tue 4/14/09 Wed 5/20/09 0 41.16 days 0.06 382.29598 1.7.2.3.1.2.1 Cantilever supports installation Tue 4/14/09 Tue 4/14/09 E 0 0.35 days 32 nos. 0.01 38.24

599 1.7.2.3.1.2.2 Cable Tray installation Tue 5/19/09 Wed 5/20/09 E 0 1.5 days 189 mtr 0.05 344.05

600 1.7.2.3.1.3 Installation - Crane Bus Bars Thu 5/14/09 Sun 5/24/09 0 9.48 days 0.91 5727.14601 1.7.2.3.1.3.1 Crane Bus Bar Supports installation Thu 5/14/09 Sat 5/16/09 E 0 0.96 days 16 nos. 0.02 96.37

602 1.7.2.3.1.3.2 Feed Junction Box Installation Sat 5/16/09 Sun 5/17/09 E 0 0.67 days 2 nos. 0.01 35.71

603 1.7.2.3.1.3.3 Disconnect Switch Instalation Sun 5/17/09 Sun 5/17/09 E 0 0.5 days 1 nos. 0 17.32

604 1.7.2.3.1.3.4 Interconnection cable, cableways installation Sun 5/17/09 Mon 5/18/09 E 0 1 day 5 nos. 0.03 159.9

605 1.7.2.3.1.3.5 Crane Power Feeder Cable Mon 5/18/09 Sat 5/23/09 E 0 5.36 days 700 mtr 0.85 5331.65

606 1.7.2.3.1.3.6 Cable Termination Sat 5/23/09 Sun 5/24/09 E 0 0.99 days 5 nos. 0.01 86.19

607 1.7.2.3.1.4 Installation - Blower and Transformer Feeder Thu 5/14/09 Tue 5/19/09 0 5.85 days 0.42 2653.46

608 1.7.2.3.1.4.1 Blower Feeder, Transformer Feeder Thu 5/14/09 Tue 5/19/09 E 0 5.85 days 700 mtr 0.42 2653.46

609 1.7.2.3.1.5 Installation - Socket / Welding Outlet Mon 4/20/09 Wed 4/22/09 0 3.23 days 0.07 434.47610 1.7.2.3.1.5.1 Rigid Steel Conduit Mon 4/20/09 Tue 4/21/09 E 0 0.84 days 15 mtr 0.01 78.35

611 1.7.2.3.1.5.2 Single Core Wires Tue 4/21/09 Tue 4/21/09 E 0 1.08 days 50 mtr 0.01 80.59

612 1.7.2.3.1.5.3 Junction Box Tue 4/21/09 Wed 4/22/09 E 0 0.5 days 2 nos. 0 23.98

613 1.7.2.3.1.5.4 Welding outlet / Socket Outlet Wed 4/22/09 Wed 4/22/09 E 0 0.29 days 2 nos. 0 27.05

614 1.7.2.3.1.5.5 Socket Feeder cables Wed 4/22/09 Wed 4/22/09 E 0 0.52 days 60 mtr 0.04 224.5

615 1.7.2.3.1.6 Installation - Local Junction Box Sat 5/2/09 Mon 6/22/09 0 57.29 days 0.95 5999.29616 1.7.2.3.1.6.1 Rigid Steel Conduit Sat 5/2/09 Sat 5/9/09 E 0 7.62 days 140 mtr 0.12 744.6

617 1.7.2.3.1.6.2 Junction Box Sat 5/9/09 Tue 5/12/09 E 0 3.81 days 28 nos. 0.06 372.3

618 1.7.2.3.1.6.3 Feeder cables Sun 5/24/09 Sun 5/31/09 E 0 8.72 days 1020 mtr 0.53 3358.01

619 1.7.2.3.1.6.4 Cable Termination Sun 6/7/09 Mon 6/22/09 E 0 18 days 88 nos. 0.24 1524.38

620 1.7.2.3.2 Air Compressed System - Piping Sat 5/2/09 Sun 5/17/09 0 17 days 0.05 333.13621 1.7.2.3.2.1 2" Equal Tee Sat 5/2/09 Tue 5/5/09 P 0 4 days 11 nos 0.03 213.2

622 1.7.2.3.2.2 2" Plug Mon 5/4/09 Mon 5/4/09 P 0 1 day 9 nos 0.01 79.95

623 1.7.2.3.2.3 1/2" Ball valve Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 10.66

624 1.7.2.3.2.4 2" x 1" Reducer Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 10.66

625 1.7.2.3.2.5 1" x 1/2" Reducer Tue 5/5/09 Wed 5/6/09 P 0 1 day 2 nos 0 10.66

626 1.7.2.3.2.6 1/2" Nipple Sat 5/16/09 Sun 5/17/09 P 0 1 day 2 nos 0 8

627 1.7.3 Pot 154 Sun 4/5/09 Tue 6/30/09 0 95.61 days 2.15 13530.95628 4.5.2.1 SLI DELIVERABLES Sun 4/5/09 Sun 4/5/09 0 0 days 0 0629 1.7.3.1.1 POT 154 Area Available for MPEI Construction Sun 4/5/09 Sun 4/5/09 0 0 days 0 0

630 1.7.3.2 Basement Floor Mon 5/11/09 Mon 6/8/09 0 30.69 days 1.18 7412.38631 1.7.3.2.1 Installation - Electrical Mon 5/11/09 Mon 6/8/09 0 30.69 days 1.18 7412.38

632 1.7.3.2.1.1 Installation - Lighting System Mon 5/11/09 Thu 5/21/09 0 11.21 days 0.57 3597.96633 1.7.3.2.1.1.1 PVC conduit and boxes Mon 5/11/09 Wed 5/13/09 E 0 2.03 days 69 mtr 0.03 220.26

634 1.7.3.2.1.1.2 Single Core Wires Wed 5/13/09 Thu 5/14/09 E 0 1.2 days 167 mtr 0.02 126.32

635 1.7.3.2.1.1.3 Lighting Feeder cables / wires Wed 5/13/09 Thu 5/14/09 E 0 0.17 days 16 mtr 0.01 53.38

636 1.7.3.2.1.1.4 Crane feeder cables Thu 5/14/09 Thu 5/21/09 E 0 8 days 1244 mtr 0.51 3198

637 1.7.3.2.1.2 Installation - Emergency Shutdown Wed 5/20/09 Mon 6/8/09 0 20.57 days 0.61 3814.41638 1.7.3.2.1.2.1 PVC conduit and boxes Wed 5/20/09 Wed 5/20/09 I 0 0.76 days 12 mtr 0.01 63.96

639 1.7.3.2.1.2.2 Instrument cables Wed 5/27/09 Mon 6/8/09 I 0 12.21 days 1944 mtr 0.59 3731.8

640 1.7.3.2.1.2.3 Remote ASI Panel /Cabinet Mon 6/8/09 Mon 6/8/09 I 0 0.33 days 1 mtr 0 18.66

641 1.7.3.3 Operation Floor Wed 4/22/09 Tue 6/30/09 0 76.23 days 0.97 6118.57

642 1.7.3.3.1 Installation - Electrical Sat 5/9/09 Tue 6/30/09 0 57.67 days 0.92 5785.45

643 1.7.3.3.1.1 Installation - Crane Bus Bars Sat 5/16/09 Sun 5/17/09 0 0.96 days 0.02 96.37644 1.7.3.3.1.1.1 Crane Bus Bar Supports installation Sat 5/16/09 Sun 5/17/09 E 0 0.96 days 16 nos. 0.02 96.37

645 1.7.3.3.1.2 Installation - Local Junction Box Sat 5/9/09 Tue 6/30/09 0 57.67 days 0.9 5689.08646 1.7.3.3.1.2.1 Rigid Steel Conduit Sat 5/9/09 Thu 5/14/09 E 0 7.08 days 130 mtr 0.11 691.83

647 1.7.3.3.1.2.2 Junction Box Thu 5/14/09 Mon 5/18/09 E 0 3.54 days 26 nos. 0.05 345.92

4/5

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 11 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 12: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

648 1.7.3.3.1.2.3 Feeder cables Sun 5/31/09 Mon 6/8/09 E 0 8.12 days 948 mtr 0.5 3126.95

649 1.7.3.3.1.2.4 Cable Termination Sun 6/14/09 Tue 6/30/09 E 0 18 days 88 nos. 0.24 1524.38

650 1.7.3.3.2 Air Compressed System - Piping Wed 4/22/09 Mon 5/18/09 0 28.9 days 0.05 333.13651 1.7.3.3.2.1 2" Equal Tee Wed 4/22/09 Sun 4/26/09 P 0 4 days 11 nos 0.03 213.2

652 1.7.3.3.2.2 2" Plug Thu 4/23/09 Sat 4/25/09 P 0 1 day 9 nos 0.01 79.95

653 1.7.3.3.2.3 1/2" Ball valve Sun 4/26/09 Mon 4/27/09 P 0 1 day 2 nos 0 10.66

654 1.7.3.3.2.4 2" x 1" Reducer Sun 4/26/09 Mon 4/27/09 P 0 1 day 2 nos 0 10.66

655 1.7.3.3.2.5 1" x 1/2" Reducer Sun 4/26/09 Mon 4/27/09 P 0 1 day 2 nos 0 10.66

656 1.7.3.3.2.6 1/2" Nipple Sun 5/17/09 Mon 5/18/09 P 0 1 day 2 nos 0 8

657 1.7.4 Pot 176 Thu 4/23/09 Wed 7/8/09 0 84.94 days 2.24 14093.16658 1.7.4.1 SLI DELIVERABLES Thu 4/23/09 Thu 4/23/09 0 0 days 0 0659 1.7.4.1.1 POT 176 Area Available for MPEI Construction Thu 4/23/09 Thu 4/23/09 0 0 days 0 0

660 1.7.4.2 Basement Floor Wed 5/13/09 Sun 6/14/09 0 35.54 days 1.29 8125.59661 1.7.4.2.1 Installation - Electrical Wed 5/13/09 Sun 6/14/09 0 35.54 days 1.29 8125.59

662 1.7.4.2.1.1 Installation - Lighting System Wed 5/13/09 Thu 5/28/09 0 17.91 days 0.69 4329.83663 1.7.4.2.1.1.1 PVC conduit and boxes Wed 5/13/09 Sat 5/16/09 E 0 2.59 days 88 mtr 0.04 281.02

664 1.7.4.2.1.1.2 Single Core Wires Sat 5/16/09 Sun 5/17/09 E 0 1.44 days 205 mtr 0.02 151.59

665 1.7.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Wed 5/13/09 Sat 5/16/09 E 0 1.47 days 20 nos. 0.03 160.62

666 1.7.4.2.1.1.4 Lighting Feeder cables / wires Mon 5/18/09 Thu 5/28/09 E 0 11.9 days 1554 mtr 0.59 3736.6

667 1.7.4.2.1.2 Installation - Emergency Shutdown Wed 5/20/09 Sun 6/14/09 0 26.69 days 0.6 3795.76668 1.7.4.2.1.2.1 PVC conduit and boxes Wed 5/20/09 Thu 5/21/09 I 0 0.76 days 12 mtr 0.01 63.96

669 1.7.4.2.1.2.2 Instrument cables Wed 6/3/09 Sun 6/14/09 I 0 12.21 days 1944 mtr 0.59 3731.8

670 1.7.4.3 Operation Floor Thu 4/23/09 Wed 7/8/09 0 84.94 days 0.95 5967.57

671 1.7.4.3.1 Installation - Electrical Thu 4/23/09 Wed 7/8/09 0 84.94 days 0.89 5634.45

672 1.7.4.3.1.1 Installation - Lighting System Thu 4/23/09 Mon 4/27/09 0 4.59 days 0.1 644.69673 1.7.4.3.1.1.1 Rigid Steel Conduit Thu 4/23/09 Sat 4/25/09 E 0 2 days 26 mtr 0.03 173.22

674 1.7.4.3.1.1.2 Single Core Wires Sat 4/25/09 Sun 4/26/09 E 0 1.04 days 300 mtr 0.03 188.82

675 1.7.4.3.1.1.3 Junction Box Sun 4/26/09 Sun 4/26/09 E 0 0.64 days 6 nos. 0.02 105.75

676 1.7.4.3.1.1.4 High Bay Lighting fixtures including supports and fixings Sun 4/26/09 Mon 4/27/09 E 0 0.84 days 6 nos. 0.02 155.58

677 1.7.4.3.1.1.5 Lighting Feeder cables / wires Mon 4/27/09 Mon 4/27/09 E 0 0.07 days 8 mtr 0 21.32

678 1.7.4.3.1.2 Installation - Crane Bus Bars Sun 5/17/09 Mon 5/18/09 0 0.96 days 0.02 96.37679 1.7.4.3.1.2.1 Crane Bus Bar Supports installation Sun 5/17/09 Mon 5/18/09 E 0 0.96 days 16 nos. 0.02 96.37

680 1.7.4.3.1.3 Installation - Socket / Welding Outlet Thu 4/23/09 Sun 4/26/09 0 3.23 days 0.07 434.47681 1.7.4.3.1.3.1 Rigid Steel Conduit Thu 4/23/09 Thu 4/23/09 E 0 0.84 days 15 mtr 0.01 78.35

682 1.7.4.3.1.3.2 Single Core Wires Thu 4/23/09 Sat 4/25/09 E 0 1.08 days 50 mtr 0.01 80.59

683 1.7.4.3.1.3.3 Junction Box Sat 4/25/09 Sun 4/26/09 E 0 0.5 days 2 nos. 0 23.98

684 1.7.4.3.1.3.4 Welding outlet / Socket Outlet Sun 4/26/09 Sun 4/26/09 E 0 0.29 days 2 nos. 0 27.05

685 1.7.4.3.1.3.5 Socket Feeder cables Sun 4/26/09 Sun 4/26/09 E 0 0.52 days 60 mtr 0.04 224.5

686 1.7.4.3.1.4 Installation - Local Junction Box Thu 5/14/09 Wed 7/8/09 0 60.59 days 0.71 4458.92687 1.7.4.3.1.4.1 Rigid Steel Conduit Thu 5/14/09 Thu 5/21/09 E 0 7.62 days 140 mtr 0.12 744.6

688 1.7.4.3.1.4.2 Junction Box Thu 5/21/09 Mon 5/25/09 E 0 3.81 days 28 nos. 0.06 372.3

689 1.7.4.3.1.4.3 Feeder cables Mon 6/8/09 Thu 6/11/09 E 0 4.72 days 550 mtr 0.29 1817.64

690 1.7.4.3.1.4.4 Cable Termination Mon 6/22/09 Wed 7/8/09 E 0 18 days 88 nos. 0.24 1524.38

691 1.7.4.3.2 Air Compressed System - Piping Sun 4/26/09 Tue 5/19/09 0 25.9 days 0.05 333.13692 1.7.4.3.2.1 2" Equal Tee Sun 4/26/09 Wed 4/29/09 P 0 4 days 11 nos 0.03 213.2

693 1.7.4.3.2.2 2" Plug Mon 4/27/09 Tue 4/28/09 P 0 1 day 9 nos 0.01 79.95

694 1.7.4.3.2.3 1/2" Ball valve Wed 4/29/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66

695 1.7.4.3.2.4 2" x 1" Reducer Wed 4/29/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66

696 1.7.4.3.2.5 1" x 1/2" Reducer Thu 4/30/09 Thu 4/30/09 P 0 1 day 2 nos 0 10.66

697 1.7.4.3.2.6 1/2" Nipple Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 8

698 1.8 Construction - Crane Workshop 512-1 Thu 1/15/09 Sat 4/25/09 0.01 109.95 days 1.53 9660.25

699 1.8.1 SLI DELIVERABLES Thu 1/15/09 Thu 1/15/09 0 0 days 0 0700 1.8.1.1 Crane Work shop Building Avaialbale for MPEI

ConstructionThu 1/15/09 Thu 1/15/09 0 0 days 0 0

701 1.8.2 Installation - Electrical Sat 2/7/09 Sat 4/25/09 0.01 84.95 days 1.53 9660.25

702 1.8.2.1 Installation - Crane Bus Bars Sat 2/7/09 Sat 4/25/09 0.01 84.95 days 1.53 9660.25703 1.8.2.1.1 Crane Bus Bar Supports installation Sat 2/7/09 Sat 2/7/09 E 0.01 0.59 days 14 nos. 0.01 83.09

704 1.8.2.1.2 Feed Junction Box Installation Tue 4/14/09 Tue 4/14/09 E 0 0.28 days 1 nos. 0 16.98

705 1.8.2.1.3 Disconnect Switch Instalation Tue 4/14/09 Wed 4/15/09 E 0 0.88 days 4 nos. 0.01 68.6

706 1.8.2.1.4 Crane Power Feeder Cable Wed 4/15/09 Wed 4/22/09 E 0 8.1 days 1110 mtr 1.46 9192.25

4/23

1/15

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 12 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 13: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

707 1.8.2.1.5 Cable Termination Wed 4/22/09 Sat 4/25/09 E 0 2.4 days 23 nos. 0.05 299.33

708 1.9 Construction - Central Passageway 503-32 Sat 3/7/09 Mon 5/11/09 0 73.11 days 0.72 4515.6

709 4.5.2.1 SLI DELIVERABLES Sat 3/7/09 Sat 3/7/09 0 0 days 0 0710 1.9.1.1 Central Passageway Available for MPEI Construction Sat 3/7/09 Sat 3/7/09 0 0 days 0 0

711 1.9.2 Operation Floor Mon 4/13/09 Mon 5/11/09 0 31.1 days 0.72 4515.6712 1.9.2.1 Installation - Electrical Mon 4/13/09 Mon 5/11/09 0 31.1 days 0.72 4515.6713 1.9.2.1.1 Installation - Lighting System Mon 4/13/09 Mon 5/11/09 0 31.1 days 0.14 851.68714 1.9.2.1.1.1 Rigid Steel Conduit Mon 4/13/09 Thu 4/16/09 E 0 4.26 days 50 mtr 0.05 298.96

715 1.9.2.1.1.2 Single Core Wires Thu 4/16/09 Sun 4/19/09 E 0 2 days 153 mtr 0.02 99.67

716 1.9.2.1.1.3 Lighting Feeder cables / wires Sun 5/10/09 Mon 5/11/09 E 0 1 day 110 mtr 0.07 453.05

717 1.9.2.1.2 Installation - Cable Tray Wed 4/29/09 Sun 5/10/09 0 12.11 days 0.17 1060.4718 1.9.2.1.2.1 Cantilever supports installation Wed 4/29/09 Mon 5/4/09 E 0 5.19 days 140 nos. 0.05 304.29

719 1.9.2.1.2.2 Cable Tray installation Mon 5/4/09 Sun 5/10/09 E 0 6.92 days 420 mtr 0.12 756.11

720 1.9.2.1.3 Installation - Crane Bus Bars Tue 4/14/09 Tue 5/5/09 0 23.78 days 0.41 2603.52721 1.9.2.1.3.1 Feed Junction Box Installation Tue 4/14/09 Wed 4/15/09 E 0 0.72 days 4 nos. 0.01 69.08

722 1.9.2.1.3.2 Disconnect Switch Instalation Wed 4/15/09 Thu 4/16/09 E 0 1.78 days 8 nos. 0.02 139.94

723 1.9.2.1.3.3 Interconnection cable, cableways installation Thu 4/16/09 Sun 4/19/09 E 0 2.97 days 15 nos. 0.06 395.75

724 1.9.2.1.3.4 Crane feeder cables Sat 5/2/09 Tue 5/5/09 E 0 5 days 800 0.32 1998.75

725 1.10 Construction - Potroom No. 1 (501-12C) Thu 5/21/09 Thu 9/24/09 0 139.9 days 12.01 75624.57

726 1.10.1 Pot 198 Thu 5/21/09 Sun 8/30/09 0 111.9 days 2.75 17348.11727 4.5.2.1 SLI DELIVERABLES Thu 6/4/09 Thu 6/4/09 0 0 days 0 0728 1.10.1.1.1 POT 198 Area Available for MPEI Construction Thu 6/4/09 Thu 6/4/09 0 0 days 0 0

729 1.10.1.2 Basement Floor Tue 6/2/09 Tue 6/23/09 0 23.06 days 1.15 7244.8

730 1.10.1.2.1 Installation - Electrical Tue 6/2/09 Tue 6/23/09 0 23.06 days 1.15 7244.8

731 1.10.1.2.1.1 Installation - Lighting System Tue 6/2/09 Thu 6/11/09 0 9.52 days 0.55 3449.04732 1.10.1.2.1.1.1 PVC conduit and boxes Thu 6/4/09 Sat 6/6/09 E 0 2.03 days 68 mtr 0.03 220.26

733 1.10.1.2.1.1.2 Single Core Wires Sat 6/6/09 Sun 6/7/09 E 0 1.04 days 148 mtr 0.02 109.48

734 1.10.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 6/4/09 Sat 6/6/09 E 0 1.19 days 16 nos. 0.02 130.03

735 1.10.1.2.1.1.4 Lighting Feeder cables / wires Tue 6/2/09 Thu 6/11/09 E 0 9.52 days 1244 mtr 0.47 2989.28

736 1.10.1.2.1.2 Installation - Emergency Shutdown Thu 6/4/09 Tue 6/23/09 0 21.32 days 0.6 3795.76737 1.10.1.2.1.2.1 PVC conduit and boxes Thu 6/4/09 Thu 6/4/09 I 0 0.76 days 12 mtr 0.01 63.96

738 1.10.1.2.1.2.2 Instrument cables Sat 6/13/09 Tue 6/23/09 I 0 12.21 days 1944 mtr 0.59 3731.8

739 1.10.1.3 Delivery of sub station 305-52 from SNCLavalin to Astaldi Thu 5/21/09 Thu 5/21/09 0 0 days 0 0

740 1.10.1.4 Operation Floor Thu 6/4/09 Sun 8/30/09 0 96.4 days 1.6 10103.31

741 1.10.1.4.1 Installation - Electrical Thu 6/4/09 Sun 8/30/09 0 96.4 days 1.55 9770.18

742 1.10.1.4.1.1 Installation - Crane Bus Bars Thu 6/4/09 Mon 6/15/09 0 12.27 days 0.53 3336.42743 1.10.1.4.1.1.1 Crane Bus Bar Supports installation Thu 6/4/09 Thu 6/4/09 E 0 0.96 days 16 nos. 0.02 96.37

744 1.10.1.4.1.1.2 Feed Junction Box Installation Thu 6/4/09 Sun 6/7/09 E 0 1.67 days 5 nos. 0.01 89.01

745 1.10.1.4.1.1.3 Disconnect Switch Instalation Sun 6/7/09 Tue 6/9/09 E 0 3 days 6 nos. 0.02 103.94

746 1.10.1.4.1.1.4 Interconnection cable, cableways installation Tue 6/9/09 Wed 6/10/09 E 0 1 day 5 nos. 0.03 159.9

747 1.10.1.4.1.1.5 Crane Power Feeder Cable Wed 6/10/09 Sat 6/13/09 E 0 2.64 days 350 mtr 0.42 2626.04

748 1.10.1.4.1.1.6 Cable Termination Sat 6/13/09 Mon 6/15/09 E 0 3 days 15 nos. 0.04 261.17

749 1.10.1.4.1.2 Installation - Socket / Welding Outlet Thu 6/4/09 Sun 6/7/09 0 3.23 days 0.07 434.47750 1.10.1.4.1.2.1 Rigid Steel Conduit Thu 6/4/09 Thu 6/4/09 E 0 0.84 days 15 mtr 0.01 78.35

751 1.10.1.4.1.2.2 Single Core Wires Thu 6/4/09 Sat 6/6/09 E 0 1.08 days 50 mtr 0.01 80.59

752 1.10.1.4.1.2.3 Junction Box Sat 6/6/09 Sun 6/7/09 E 0 0.5 days 2 nos. 0 23.98

753 1.10.1.4.1.2.4 Welding outlet / Socket Outlet Sun 6/7/09 Sun 6/7/09 E 0 0.29 days 2 nos. 0 27.05

754 1.10.1.4.1.2.5 Socket Feeder cables Sun 6/7/09 Sun 6/7/09 E 0 0.52 days 60 mtr 0.04 224.5

755 1.10.1.4.1.3 Installation - Local Junction Box Wed 6/17/09 Sun 8/30/09 0 82.03 days 0.95 5999.29756 1.10.1.4.1.3.1 Rigid Steel Conduit Wed 6/17/09 Wed 6/24/09 E 0 7.62 days 140 mtr 0.12 744.6

757 1.10.1.4.1.3.2 Junction Box Wed 6/24/09 Sun 6/28/09 E 0 3.81 days 28 nos. 0.06 372.3

758 1.10.1.4.1.3.3 Feeder cables Sun 6/28/09 Sun 7/5/09 E 0 8.72 days 1020 mtr 0.53 3358.01

759 1.10.1.4.1.3.4 Cable Termination Thu 8/13/09 Sun 8/30/09 E 0 18 days 88 nos. 0.24 1524.38

760 1.10.1.4.2 Air Compressed System - Piping Thu 6/4/09 Tue 6/9/09 0 6 days 0.05 333.13761 1.10.1.4.2.1 2" Equal Tee Thu 6/4/09 Mon 6/8/09 P 0 4 days 11 nos 0.03 213.2

762 1.10.1.4.2.2 2" Plug Sat 6/6/09 Sun 6/7/09 P 0 1 day 9 nos 0.01 79.95

763 1.10.1.4.2.3 1/2" Ball valve Sun 6/7/09 Mon 6/8/09 P 0 1 day 2 nos 0 10.66

764 1.10.1.4.2.4 2" x 1" Reducer Mon 6/8/09 Tue 6/9/09 P 0 1 day 2 nos 0 10.66

765 1.10.1.4.2.5 1" x 1/2" Reducer Mon 6/8/09 Tue 6/9/09 P 0 1 day 2 nos 0 10.66

3/7

6/4

5/21

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 13 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 14: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

766 1.10.1.4.2.6 1/2" Nipple Tue 6/9/09 Tue 6/9/09 P 0 1 day 2 nos 0 8

767 1.10.2 Pot 220 Wed 6/24/09 Tue 9/8/09 0 84.42 days 2.39 15074.31768 4.5.2.1 SLI DELIVERABLES Thu 6/25/09 Thu 6/25/09 0 0 days 0 0769 1.10.2.1.1 POT 220 Area Available for MPEI Construction Thu 6/25/09 Thu 6/25/09 0 0 days 0 0

770 1.10.2.2 Basement Floor Wed 6/24/09 Tue 7/7/09 0 14.57 days 1.22 7687.83771 1.10.2.2.1 Installation - Electrical Wed 6/24/09 Tue 7/7/09 0 14.57 days 1.22 7687.83

772 1.10.2.2.1.1 Installation - Lighting System Wed 6/24/09 Sat 7/4/09 0 10.71 days 0.61 3873.42773 1.10.2.2.1.1.1 PVC conduit and boxes Thu 6/25/09 Sat 6/27/09 E 0 2.24 days 76 mtr 0.04 243.05

774 1.10.2.2.1.1.2 Single Core Wires Sat 6/27/09 Sun 6/28/09 E 0 1.16 days 166 mtr 0.02 122.11

775 1.10.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 6/25/09 Sat 6/27/09 E 0 1.33 days 18 nos. 0.02 145.32

776 1.10.2.2.1.1.4 Lighting Feeder cables / wires Wed 6/24/09 Sat 7/4/09 E 0 10.71 days 1400 mtr 0.53 3362.94

777 1.10.2.2.1.2 Installation - Emergency Shutdown Thu 6/25/09 Tue 7/7/09 0 13.3 days 0.61 3814.41778 1.10.2.2.1.2.1 PVC conduit and boxes Thu 6/25/09 Thu 6/25/09 I 0 0.76 days 12 mtr 0.01 63.96

779 1.10.2.2.1.2.2 Instrument cables Thu 6/25/09 Tue 7/7/09 I 0 12.21 days 1944 mtr 0.59 3731.8

780 1.10.2.2.1.2.3 Remote ASI Panel /Cabinet Tue 7/7/09 Tue 7/7/09 I 0 0.33 days 1 mtr 0 18.66

781 1.10.2.3 Operation Floor Thu 6/25/09 Tue 9/8/09 0 83.15 days 1.17 7386.47

782 1.10.2.3.1 Installation - Electrical Thu 6/25/09 Tue 9/8/09 0 83.15 days 1.12 7053.35

783 1.10.2.3.1.1 Installation - Lighting System Thu 6/25/09 Sun 6/28/09 0 3.58 days 0.08 523.22784 1.10.2.3.1.1.1 Rigid Steel Conduit Thu 6/25/09 Thu 6/25/09 E 0 0.7 days 26 mtr 0.03 157.5

785 1.10.2.3.1.1.2 Single Core Wires Thu 6/25/09 Sat 6/27/09 E 0 1.04 days 300 mtr 0.03 188.82

786 1.10.2.3.1.1.3 High Bay Lighting fixtures including supports and fixings Sat 6/27/09 Sun 6/28/09 E 0 0.84 days 6 nos. 0.02 155.58

787 1.10.2.3.1.1.4 Lighting Feeder cables / wires Sun 6/28/09 Sun 6/28/09 E 0 1 day 8 mtr 0 21.32

788 1.10.2.3.1.2 Installation - Crane Bus Bars Thu 6/25/09 Thu 6/25/09 0 0.96 days 0.02 96.37789 1.10.2.3.1.2.1 Crane Bus Bar Supports installation Thu 6/25/09 Thu 6/25/09 E 0 0.96 days 16 nos. 0.02 96.37

790 1.10.2.3.1.3 Installation - Socket / Welding Outlet Thu 6/25/09 Sun 6/28/09 0 3.23 days 0.07 434.47791 1.10.2.3.1.3.1 Rigid Steel Conduit Thu 6/25/09 Thu 6/25/09 E 0 0.84 days 15 mtr 0.01 78.35

792 1.10.2.3.1.3.2 Single Core Wires Thu 6/25/09 Sat 6/27/09 E 0 1.08 days 50 mtr 0.01 80.59

793 1.10.2.3.1.3.3 Junction Box Sat 6/27/09 Sun 6/28/09 E 0 0.5 days 2 nos. 0 23.98

794 1.10.2.3.1.3.4 Welding outlet / Socket Outlet Sun 6/28/09 Sun 6/28/09 E 0 0.29 days 2 nos. 0 27.05

795 1.10.2.3.1.3.5 Socket Feeder cables Sun 6/28/09 Sun 6/28/09 E 0 0.52 days 60 mtr 0.04 224.5

796 1.10.2.3.1.4 Installation - Local Junction Box Thu 6/25/09 Tue 9/8/09 0 83.15 days 0.95 5999.29797 1.10.2.3.1.4.1 Rigid Steel Conduit Thu 6/25/09 Thu 7/2/09 E 0 7.62 days 140 mtr 0.12 744.6

798 1.10.2.3.1.4.2 Junction Box Thu 7/2/09 Sun 7/5/09 E 0 3.81 days 28 nos. 0.06 372.3

799 1.10.2.3.1.4.3 Feeder cables Sun 7/5/09 Mon 7/13/09 E 0 8.72 days 1020 mtr 0.53 3358.01

800 1.10.2.3.1.4.4 Cable Termination Sun 8/23/09 Tue 9/8/09 E 0 18 days 88 nos. 0.24 1524.38

801 1.10.2.3.2 Air Compressed System - Piping Thu 6/25/09 Tue 6/30/09 0 6 days 0.05 333.13802 1.10.2.3.2.1 2" Equal Tee Thu 6/25/09 Mon 6/29/09 P 0 4 days 11 nos 0.03 213.2

803 1.10.2.3.2.2 2" Plug Sat 6/27/09 Sun 6/28/09 P 0 1 day 9 nos 0.01 79.95

804 1.10.2.3.2.3 1/2" Ball valve Sun 6/28/09 Mon 6/29/09 P 0 1 day 2 nos 0 10.66

805 1.10.2.3.2.4 2" x 1" Reducer Mon 6/29/09 Tue 6/30/09 P 0 1 day 2 nos 0 10.66

806 1.10.2.3.2.5 1" x 1/2" Reducer Mon 6/29/09 Tue 6/30/09 P 0 1 day 2 nos 0 10.66

807 1.10.2.3.2.6 1/2" Nipple Tue 6/30/09 Tue 6/30/09 P 0 1 day 2 nos 0 8

808 1.10.3 Pot 242 Thu 7/16/09 Thu 9/24/09 0 77.9 days 3.65 22993.46809 1.10.3.1 SLI DELIVERABLES Thu 7/16/09 Thu 7/16/09 0 0 days 0 0810 1.10.3.1.1 POT 242 Area Available for MPEI Construction Thu 7/16/09 Thu 7/16/09 0 0 days 0 0

811 1.10.3.2 Basement Floor Thu 7/16/09 Thu 7/30/09 0 15.82 days 1.15 7244.8812 1.10.3.2.1 Installation - Electrical Thu 7/16/09 Thu 7/30/09 0 15.82 days 1.15 7244.8

813 1.10.3.2.1.1 Installation - Lighting System Thu 7/16/09 Thu 7/30/09 0 15.82 days 0.55 3449.04814 1.10.3.2.1.1.1 PVC conduit and boxes Thu 7/16/09 Sat 7/18/09 E 0 2.03 days 68 mtr 0.03 220.26

815 1.10.3.2.1.1.2 Single Core Wires Sat 7/18/09 Sun 7/19/09 E 0 1.04 days 148 mtr 0.02 109.48

816 1.10.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 7/16/09 Sat 7/18/09 E 0 1.19 days 16 nos. 0.02 130.03

817 1.10.3.2.1.1.4 Lighting Feeder cables / wires Wed 7/22/09 Thu 7/30/09 E 0 9.52 days 1244 mtr 0.47 2989.28

818 1.10.3.2.1.2 Installation - Emergency Shutdown Thu 7/16/09 Tue 7/28/09 0 12.97 days 0.6 3795.76819 1.10.3.2.1.2.1 PVC conduit and boxes Thu 7/16/09 Thu 7/16/09 I 0 0.76 days 12 mtr 0.01 63.96

820 1.10.3.2.1.2.2 Instrument cables Thu 7/16/09 Tue 7/28/09 I 0 12.21 days 1944 mtr 0.59 3731.8

821 1.10.3.3 Operation Floor Thu 7/16/09 Thu 9/24/09 0 77.9 days 2.5 15748.66

822 1.10.3.3.1 Installation - Electrical Thu 7/16/09 Thu 9/24/09 0 77.9 days 2.45 15415.53

823 1.10.3.3.1.1 Installation - Lighting System Thu 7/16/09 Wed 7/22/09 0 6.48 days 0.26 1632.66824 1.10.3.3.1.1.1 Rigid Steel Conduit Thu 7/16/09 Sat 7/18/09 E 0 1.4 days 52 mtr 0.05 315

6/25

7/16

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 14 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 15: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

825 1.10.3.3.1.1.2 Single Core Wires Sat 7/18/09 Sun 7/19/09 E 0 1.04 days 300 mtr 0.03 188.82

826 1.10.3.3.1.1.3 Junction Box Sun 7/19/09 Sun 7/19/09 E 0 1 day 2 nos. 0.01 53.3

827 1.10.3.3.1.1.4 High Bay Lighting fixtures including supports and fixings Sun 7/19/09 Tue 7/21/09 E 0 1.64 days 12 nos. 0.05 303.76

828 1.10.3.3.1.1.5 Lighting Feeder cables / wires Tue 7/21/09 Wed 7/22/09 E 0 1.4 days 196 mtr 0.12 771.78

829 1.10.3.3.1.2 Installation - Cable Tray Thu 7/16/09 Wed 7/22/09 0 6.3 days 0.02 110.86830 1.10.3.3.1.2.1 Cantilever supports installation Thu 7/16/09 Thu 7/16/09 E 0 0.07 days 9 nos. 0 7.65

831 1.10.3.3.1.2.2 Cable Tray installation Tue 7/21/09 Wed 7/22/09 E 0 0.45 days 55 mtr 0.02 103.22

832 1.10.3.3.1.3 Installation - Blower and Transformer Feeder Thu 7/16/09 Tue 7/21/09 0 5.85 days 0.42 2653.46

833 1.10.3.3.1.3.1 Blower Feeder, Transformer Feeder Thu 7/16/09 Tue 7/21/09 E 0 5.85 days 700 mtr 0.42 2653.46

834 1.10.3.3.1.4 Installation - Local Junction Box Thu 7/16/09 Thu 9/24/09 0 77.9 days 1.75 11018.55835 1.10.3.3.1.4.1 Rigid Steel Conduit Thu 7/16/09 Wed 7/22/09 E 0 7.5 days 130 mtr 0.96 6021.3

836 1.10.3.3.1.4.2 Junction Box Wed 7/22/09 Sun 7/26/09 E 0 3.54 days 26 nos. 0.05 345.92

837 1.10.3.3.1.4.3 Feeder cables Sun 7/26/09 Sun 8/2/09 E 0 8.12 days 948 mtr 0.5 3126.95

838 1.10.3.3.1.4.4 Cable Termination Tue 9/8/09 Thu 9/24/09 E 0 18 days 88 nos. 0.24 1524.38

839 1.10.3.3.2 Air Compressed System - Piping Thu 7/16/09 Thu 7/23/09 0 8 days 0.05 333.13840 1.10.3.3.2.1 2" Equal Tee Thu 7/16/09 Mon 7/20/09 P 0 4 days 11 nos 0.03 213.2

841 1.10.3.3.2.2 2" Plug Mon 7/20/09 Tue 7/21/09 P 0 1 day 9 nos 0.01 79.95

842 1.10.3.3.2.3 1/2" Ball valve Tue 7/21/09 Tue 7/21/09 P 0 1 day 2 nos 0 10.66

843 1.10.3.3.2.4 2" x 1" Reducer Tue 7/21/09 Wed 7/22/09 P 0 1 day 2 nos 0 10.66

844 1.10.3.3.2.5 1" x 1/2" Reducer Tue 7/21/09 Wed 7/22/09 P 0 1 day 2 nos 0 10.66

845 1.10.3.3.2.6 1/2" Nipple Wed 7/22/09 Thu 7/23/09 P 0 1 day 2 nos 0 8

846 1.10.4 Pot 264 Thu 8/6/09 Thu 9/24/09 0 54.65 days 3.21 20208.7847 4.5.2.1 SLI DELIVERABLES Thu 8/6/09 Thu 8/6/09 0 0 days 0 0848 1.10.4.1.1 POT 264 Area Available for MPEI Construction Thu 8/6/09 Thu 8/6/09 0 0 days 0 0

849 1.10.4.2 Basement Floor Thu 8/6/09 Sat 8/22/09 0 17.52 days 1.25 7879.23850 1.10.4.2.1 Installation - Electrical Thu 8/6/09 Sat 8/22/09 0 17.52 days 1.25 7879.23

851 1.10.4.2.1.1 Installation - Lighting System Thu 8/6/09 Sat 8/22/09 0 17.52 days 0.65 4064.82852 1.10.4.2.1.1.1 PVC conduit and boxes Thu 8/6/09 Sat 8/8/09 E 0 2.38 days 81 mtr 0.04 258.24

853 1.10.4.2.1.1.2 Single Core Wires Sat 8/8/09 Sun 8/9/09 E 0 1.24 days 176 mtr 0.02 130.53

854 1.10.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 8/6/09 Sat 8/8/09 E 0 1.4 days 19 nos. 0.02 152.97

855 1.10.4.2.1.1.4 Lighting Feeder cables / wires Wed 8/12/09 Sat 8/22/09 E 0 11.22 days 1477 mtr 0.56 3523.08

856 1.10.4.2.1.2 Installation - Emergency Shutdown Thu 8/6/09 Tue 8/18/09 0 13.3 days 0.61 3814.41857 1.10.4.2.1.2.1 PVC conduit and boxes Thu 8/6/09 Thu 8/6/09 I 0 0.76 days 12 mtr 0.01 63.96

858 1.10.4.2.1.2.2 Instrument cables Thu 8/6/09 Tue 8/18/09 I 0 12.21 days 1944 mtr 0.59 3731.8

859 1.10.4.2.1.2.3 Remote ASI Panel /Cabinet Tue 8/18/09 Tue 8/18/09 I 0 0.33 days 1 mtr 0 18.66

860 1.10.4.3 Operation Floor Thu 8/6/09 Thu 9/24/09 0 54.65 days 1.96 12329.46

861 1.10.4.3.1 Installation - Electrical Thu 8/6/09 Thu 9/24/09 0 54.65 days 1.9 11996.34

862 1.10.4.3.1.1 Installation - Cable Tray Thu 8/6/09 Wed 8/12/09 0 6.3 days 0.02 110.86863 1.10.4.3.1.1.1 Cantilever supports installation Thu 8/6/09 Thu 8/6/09 E 0 0.07 days 9 nos. 0 7.65

864 1.10.4.3.1.1.2 Cable Tray installation Tue 8/11/09 Wed 8/12/09 E 0 0.45 days 55 mtr 0.02 103.22

865 1.10.4.3.1.2 Installation - Crane Bus Bars Thu 8/6/09 Wed 8/12/09 0 7.45 days 0.69 4338.62866 1.10.4.3.1.2.1 Crane Bus Bar Supports installation Thu 8/6/09 Thu 8/6/09 E 0 0.96 days 16 nos. 0.02 96.37

867 1.10.4.3.1.2.2 Disconnect Switch Instalation Thu 8/6/09 Sat 8/8/09 E 0 0.5 days 1 nos. 0 17.32

868 1.10.4.3.1.2.3 Interconnection cable, cableways installation Sat 8/8/09 Sun 8/9/09 E 0 1 day 5 nos. 0.03 159.9

869 1.10.4.3.1.2.4 Crane Power Feeder Cable Sun 8/9/09 Wed 8/12/09 E 0 4 days 525 mtr 0.63 3978.85

870 1.10.4.3.1.2.5 Cable Termination Wed 8/12/09 Wed 8/12/09 E 0 0.99 days 5 nos. 0.01 86.19

871 1.10.4.3.1.3 Installation - Blower and Transformer Feeder Thu 8/6/09 Tue 8/11/09 0 5.85 days 0.42 2653.46

872 1.10.4.3.1.3.1 Blower Feeder, Transformer Feeder Thu 8/6/09 Tue 8/11/09 E 0 5.85 days 700 mtr 0.42 2653.46

873 1.10.4.3.1.4 Installation - Socket / Welding Outlet Thu 8/6/09 Sun 8/9/09 0 3.23 days 0.07 434.47874 1.10.4.3.1.4.1 Rigid Steel Conduit Thu 8/6/09 Thu 8/6/09 E 0 0.84 days 15 mtr 0.01 78.35

875 1.10.4.3.1.4.2 Single Core Wires Thu 8/6/09 Sat 8/8/09 E 0 1.08 days 50 mtr 0.01 80.59

876 1.10.4.3.1.4.3 Junction Box Sat 8/8/09 Sun 8/9/09 E 0 0.5 days 2 nos. 0 23.98

877 1.10.4.3.1.4.4 Welding outlet / Socket Outlet Sun 8/9/09 Sun 8/9/09 E 0 0.29 days 2 nos. 0 27.05

878 1.10.4.3.1.4.5 Socket Feeder cables Sun 8/9/09 Sun 8/9/09 E 0 0.52 days 60 mtr 0.04 224.5

879 1.10.4.3.1.5 Installation - Local Junction Box Thu 8/6/09 Thu 9/24/09 0 54.65 days 0.71 4458.92880 1.10.4.3.1.5.1 Rigid Steel Conduit Thu 8/6/09 Thu 8/13/09 E 0 7.62 days 140 mtr 0.12 744.6

881 1.10.4.3.1.5.2 Junction Box Thu 8/13/09 Sun 8/16/09 E 0 3.81 days 28 nos. 0.06 372.3

882 1.10.4.3.1.5.3 Feeder cables Sun 8/16/09 Thu 8/20/09 E 0 4.72 days 550 mtr 0.29 1817.64

883 1.10.4.3.1.5.4 Cable Termination Tue 9/8/09 Thu 9/24/09 E 0 18 days 88 nos. 0.24 1524.38

884 1.10.4.3.2 Air Compressed System - Piping Thu 8/6/09 Tue 8/11/09 0 6 days 0.05 333.13

8/6

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 15 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 16: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

885 1.10.4.3.2.1 2" Equal Tee Thu 8/6/09 Mon 8/10/09 P 0 4 days 11 nos 0.03 213.2

886 1.10.4.3.2.2 2" Plug Sat 8/8/09 Sun 8/9/09 P 0 1 day 9 nos 0.01 79.95

887 1.10.4.3.2.3 1/2" Ball valve Sun 8/9/09 Mon 8/10/09 P 0 1 day 2 nos 0 10.66

888 1.10.4.3.2.4 2" x 1" Reducer Mon 8/10/09 Tue 8/11/09 P 0 1 day 2 nos 0 10.66

889 1.10.4.3.2.5 1" x 1/2" Reducer Mon 8/10/09 Tue 8/11/09 P 0 1 day 2 nos 0 10.66

890 1.10.4.3.2.6 1/2" Nipple Tue 8/11/09 Tue 8/11/09 P 0 1 day 2 nos 0 8

891 1.11 Construction - Potroom No 2 (501-22C) Thu 5/14/09 Wed 8/19/09 0 107.9 days 11.61 73108.92

892 1.11.1 Pot 198 Thu 5/14/09 Thu 6/25/09 0 46.87 days 2.96 18614.31893 4.5.2.1 SLI DELIVERABLES Thu 5/14/09 Thu 5/14/09 0 0 days 0 0894 1.11.1.1.1 POT 198 Area Available for MPEI Construction Thu 5/14/09 Thu 5/14/09 0 0 days 0 0

895 1.11.1.2 Basement Floor Sat 5/16/09 Thu 6/25/09 0 45.16 days 1.15 7244.8

896 1.11.1.2.1 Installation - Electrical Sat 5/16/09 Thu 6/25/09 0 45.16 days 1.15 7244.8

897 1.11.1.2.1.1 Installation - Lighting System Sat 5/16/09 Sun 6/7/09 0 24.84 days 0.55 3449.04898 1.11.1.2.1.1.1 PVC conduit and boxes Sat 5/16/09 Sun 5/17/09 E 0 2.03 days 68 mtr 0.03 220.26

899 1.11.1.2.1.1.2 Single Core Wires Sun 5/17/09 Mon 5/18/09 E 0 1.04 days 148 mtr 0.02 109.48

900 1.11.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Sat 5/16/09 Sun 5/17/09 E 0 1.19 days 16 nos. 0.02 130.03

901 1.11.1.2.1.1.4 Lighting Feeder cables / wires Thu 5/28/09 Sun 6/7/09 E 0 9.52 days 1244 mtr 0.47 2989.28

902 1.11.1.2.1.2 Installation - Emergency Shutdown Wed 6/10/09 Thu 6/25/09 0 16.44 days 0.6 3795.76903 1.11.1.2.1.2.1 PVC conduit and boxes Wed 6/10/09 Wed 6/10/09 I 0 0.76 days 12 mtr 0.01 63.96

904 1.11.1.2.1.2.2 Instrument cables Sun 6/14/09 Thu 6/25/09 I 0 12.21 days 1944 mtr 0.59 3731.8

905 1.11.1.3 Operation Floor Thu 5/14/09 Thu 6/25/09 0 46.87 days 1.81 11369.5

906 1.11.1.3.1 Installation - Electrical Thu 5/14/09 Thu 6/25/09 0 46.87 days 1.75 11036.38

907 1.11.1.3.1.1 Installation - Crane Bus Bars Mon 5/18/09 Wed 5/27/09 0 11.13 days 0.73 4602.61908 1.11.1.3.1.1.1 Crane Bus Bar Supports installation Mon 5/18/09 Mon 5/18/09 E 0 0.96 days 16 nos. 0.02 96.37

909 1.11.1.3.1.1.2 Feed Junction Box Installation Mon 5/18/09 Wed 5/20/09 E 0 1.67 days 5 nos. 0.01 89.01

910 1.11.1.3.1.1.3 Disconnect Switch Instalation Wed 5/20/09 Wed 5/20/09 E 0 0.5 days 1 nos. 0 17.32

911 1.11.1.3.1.1.4 Interconnection cable, cableways installation Wed 5/20/09 Thu 5/21/09 E 0 1 day 5 nos. 0.03 159.9

912 1.11.1.3.1.1.5 Crane Power Feeder Cable Thu 5/21/09 Mon 5/25/09 E 0 4 days 525 mtr 0.63 3978.85

913 1.11.1.3.1.1.6 Cable Termination Mon 5/25/09 Wed 5/27/09 E 0 3 days 15 nos. 0.04 261.17

914 1.11.1.3.1.2 Installation - Socket / Welding Outlet Thu 5/14/09 Sun 5/17/09 0 3.23 days 0.07 434.47915 1.11.1.3.1.2.1 Rigid Steel Conduit Thu 5/14/09 Thu 5/14/09 E 0 0.84 days 15 mtr 0.01 78.35

916 1.11.1.3.1.2.2 Single Core Wires Thu 5/14/09 Sat 5/16/09 E 0 1.08 days 50 mtr 0.01 80.59

917 1.11.1.3.1.2.3 Junction Box Sat 5/16/09 Sun 5/17/09 E 0 0.5 days 2 nos. 0 23.98

918 1.11.1.3.1.2.4 Welding outlet / Socket Outlet Sun 5/17/09 Sun 5/17/09 E 0 0.29 days 2 nos. 0 27.05

919 1.11.1.3.1.2.5 Socket Feeder cables Sun 5/17/09 Sun 5/17/09 E 0 0.52 days 60 mtr 0.04 224.5

920 1.11.1.3.1.3 Installation - Local Junction Box Thu 5/21/09 Thu 6/25/09 0 38.15 days 0.95 5999.29921 1.11.1.3.1.3.1 Rigid Steel Conduit Thu 5/21/09 Thu 5/28/09 E 0 7.62 days 140 mtr 0.12 744.6

922 1.11.1.3.1.3.2 Junction Box Thu 5/28/09 Mon 6/1/09 E 0 3.81 days 28 nos. 0.06 372.3

923 1.11.1.3.1.3.3 Feeder cables Mon 6/1/09 Tue 6/9/09 E 0 8.72 days 1020 mtr 0.53 3358.01

924 1.11.1.3.1.3.4 Cable Termination Tue 6/9/09 Thu 6/25/09 E 0 18 days 88 nos. 0.24 1524.38

925 1.11.1.3.2 Air Compressed System - Piping Thu 5/14/09 Wed 5/20/09 0 6.35 days 0.05 333.13926 1.11.1.3.2.1 2" Equal Tee Thu 5/14/09 Mon 5/18/09 P 0 4 days 11 nos 0.03 213.2

927 1.11.1.3.2.2 2" Plug Sat 5/16/09 Sun 5/17/09 P 0 1 day 9 nos 0.01 79.95

928 1.11.1.3.2.3 1/2" Ball valve Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66

929 1.11.1.3.2.4 2" x 1" Reducer Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66

930 1.11.1.3.2.5 1" x 1/2" Reducer Mon 5/18/09 Tue 5/19/09 P 0 1 day 2 nos 0 10.66

931 1.11.1.3.2.6 1/2" Nipple Tue 5/19/09 Wed 5/20/09 P 0 1 day 2 nos 0 8

932 1.11.2 Pot 220 Wed 6/3/09 Sun 7/12/09 0 42.89 days 2.4 15091.58933 4.5.2.1 SLI DELIVERABLES Thu 6/4/09 Thu 6/4/09 0 0 days 0 0934 1.11.2.1.1 POT 220 Area Available for MPEI Construction Thu 6/4/09 Thu 6/4/09 0 0 days 0 0

935 1.11.2.2 Basement Floor Wed 6/3/09 Wed 7/1/09 0 32 days 1.22 7687.83936 1.11.2.2.1 Installation - Electrical Wed 6/3/09 Wed 7/1/09 0 32 days 1.22 7687.83

937 1.11.2.2.1.1 Installation - Lighting System Wed 6/3/09 Sat 6/13/09 0 10.71 days 0.61 3873.42938 1.11.2.2.1.1.1 PVC conduit and boxes Thu 6/4/09 Sat 6/6/09 E 0 2.24 days 76 mtr 0.04 243.05

939 1.11.2.2.1.1.2 Single Core Wires Sat 6/6/09 Sun 6/7/09 E 0 1.16 days 166 mtr 0.02 122.11

940 1.11.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 6/4/09 Sat 6/6/09 E 0 1.33 days 18 nos. 0.02 145.32

941 1.11.2.2.1.1.4 Lighting Feeder cables / wires Wed 6/3/09 Sat 6/13/09 E 0 10.71 days 1400 mtr 0.53 3362.94

942 1.11.2.2.1.2 Installation - Emergency Shutdown Wed 6/10/09 Wed 7/1/09 0 23.22 days 0.61 3814.41943 1.11.2.2.1.2.1 PVC conduit and boxes Wed 6/10/09 Thu 6/11/09 I 0 0.76 days 12 mtr 0.01 63.96

5/14

6/4

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 16 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 17: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

944 1.11.2.2.1.2.2 Instrument cables Sun 6/21/09 Wed 7/1/09 I 0 12.21 days 1944 mtr 0.59 3731.8

945 1.11.2.2.1.2.3 Remote ASI Panel /Cabinet Wed 7/1/09 Wed 7/1/09 I 0 0.33 days 1 mtr 0 18.66

946 1.11.2.3 Operation Floor Thu 6/4/09 Sun 7/12/09 0 41.62 days 1.18 7403.74

947 1.11.2.3.1 Installation - Electrical Thu 6/4/09 Sun 7/12/09 0 41.62 days 1.12 7070.62

948 1.11.2.3.1.1 Installation - Lighting System Thu 6/4/09 Sun 6/7/09 0 3.58 days 0.09 540.49949 1.11.2.3.1.1.1 Rigid Steel Conduit Thu 6/4/09 Thu 6/4/09 E 0 0.7 days 26 mtr 0.03 157.5

950 1.11.2.3.1.1.2 Single Core Wires Thu 6/4/09 Sat 6/6/09 E 0 1.04 days 300 mtr 0.03 188.82

951 1.11.2.3.1.1.3 High Bay Lighting fixtures including supports and fixings Sat 6/6/09 Sun 6/7/09 E 0 0.84 days 6 nos. 0.02 155.58

952 1.11.2.3.1.1.4 Lighting Feeder cables / wires Sun 6/7/09 Sun 6/7/09 E 0 1 day 8 mtr 0.01 38.59

953 1.11.2.3.1.2 Installation - Crane Bus Bars Thu 6/4/09 Thu 6/4/09 0 0.96 days 0.02 96.37954 1.11.2.3.1.2.1 Crane Bus Bar Supports installation Thu 6/4/09 Thu 6/4/09 E 0 0.96 days 16 nos. 0.02 96.37

955 1.11.2.3.1.3 Installation - Socket / Welding Outlet Thu 6/4/09 Sun 6/7/09 0 3.23 days 0.07 434.47956 1.11.2.3.1.3.1 Rigid Steel Conduit Thu 6/4/09 Thu 6/4/09 E 0 0.84 days 15 mtr 0.01 78.35

957 1.11.2.3.1.3.2 Single Core Wires Thu 6/4/09 Sat 6/6/09 E 0 1.08 days 50 mtr 0.01 80.59

958 1.11.2.3.1.3.3 Junction Box Sat 6/6/09 Sun 6/7/09 E 0 0.5 days 2 nos. 0 23.98

959 1.11.2.3.1.3.4 Welding outlet / Socket Outlet Sun 6/7/09 Sun 6/7/09 E 0 0.29 days 2 nos. 0 27.05

960 1.11.2.3.1.3.5 Socket Feeder cables Sun 6/7/09 Sun 6/7/09 E 0 0.52 days 60 mtr 0.04 224.5

961 1.11.2.3.1.4 Installation - Local Junction Box Thu 6/4/09 Sun 7/12/09 0 41.62 days 0.95 5999.29962 1.11.2.3.1.4.1 Rigid Steel Conduit Thu 6/4/09 Thu 6/11/09 E 0 7.62 days 140 mtr 0.12 744.6

963 1.11.2.3.1.4.2 Junction Box Thu 6/11/09 Sun 6/14/09 E 0 3.81 days 28 nos. 0.06 372.3

964 1.11.2.3.1.4.3 Feeder cables Sun 6/14/09 Mon 6/22/09 E 0 8.72 days 1020 mtr 0.53 3358.01

965 1.11.2.3.1.4.4 Cable Termination Thu 6/25/09 Sun 7/12/09 E 0 18 days 88 nos. 0.24 1524.38

966 1.11.2.3.2 Air Compressed System - Piping Thu 6/4/09 Tue 6/9/09 0 6 days 0.05 333.13967 1.11.2.3.2.1 2" Equal Tee Thu 6/4/09 Mon 6/8/09 P 0 4 days 11 nos 0.03 213.2

968 1.11.2.3.2.2 2" Plug Sat 6/6/09 Sun 6/7/09 P 0 1 day 9 nos 0.01 79.95

969 1.11.2.3.2.3 1/2" Ball valve Sun 6/7/09 Mon 6/8/09 P 0 1 day 2 nos 0 10.66

970 1.11.2.3.2.4 2" x 1" Reducer Mon 6/8/09 Tue 6/9/09 P 0 1 day 2 nos 0 10.66

971 1.11.2.3.2.5 1" x 1/2" Reducer Mon 6/8/09 Tue 6/9/09 P 0 1 day 2 nos 0 10.66

972 1.11.2.3.2.6 1/2" Nipple Tue 6/9/09 Tue 6/9/09 P 0 1 day 2 nos 0 8

973 1.11.3 Pot 242 Thu 6/25/09 Tue 7/28/09 0 36.74 days 2.81 17689.9974 4.5.2.1 SLI DELIVERABLES Thu 6/25/09 Thu 6/25/09 0 0 days 0 0975 1.11.3.1.1 POT 242 Area Available for MPEI Construction Thu 6/25/09 Thu 6/25/09 0 0 days 0 0

976 1.11.3.2 Basement Floor Thu 6/25/09 Thu 7/9/09 0 15.52 days 1.15 7244.8977 1.11.3.2.1 Installation - Electrical Thu 6/25/09 Thu 7/9/09 0 15.52 days 1.15 7244.8

978 1.11.3.2.1.1 Installation - Lighting System Thu 6/25/09 Thu 7/9/09 0 15.52 days 0.55 3449.04979 1.11.3.2.1.1.1 PVC conduit and boxes Thu 6/25/09 Sat 6/27/09 E 0 2.03 days 68 mtr 0.03 220.26

980 1.11.3.2.1.1.2 Single Core Wires Sat 6/27/09 Sun 6/28/09 E 0 1.04 days 148 mtr 0.02 109.48

981 1.11.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 6/25/09 Sat 6/27/09 E 0 1.19 days 16 nos. 0.02 130.03

982 1.11.3.2.1.1.4 Lighting Feeder cables / wires Tue 6/30/09 Thu 7/9/09 E 0 9.52 days 1244 mtr 0.47 2989.28

983 1.11.3.2.1.2 Installation - Emergency Shutdown Thu 6/25/09 Tue 7/7/09 0 12.97 days 0.6 3795.76984 1.11.3.2.1.2.1 PVC conduit and boxes Thu 6/25/09 Thu 6/25/09 I 0 0.76 days 12 mtr 0.01 63.96

985 1.11.3.2.1.2.2 Instrument cables Thu 6/25/09 Tue 7/7/09 I 0 12.21 days 1944 mtr 0.59 3731.8

986 1.11.3.3 Operation Floor Thu 6/25/09 Tue 7/28/09 0 36.74 days 1.66 10445.09

987 1.11.3.3.1 Installation - Electrical Thu 6/25/09 Tue 7/28/09 0 36.74 days 1.61 10111.97

988 1.11.3.3.1.1 Installation - Lighting System Thu 6/25/09 Tue 6/30/09 0 5.7 days 0.26 1615.71989 1.11.3.3.1.1.1 Rigid Steel Conduit Thu 6/25/09 Sat 6/27/09 E 0 1.4 days 52 mtr 0.05 315

990 1.11.3.3.1.1.2 Single Core Wires Sat 6/27/09 Sun 6/28/09 E 0 1.04 days 300 mtr 0.03 188.82

991 1.11.3.3.1.1.3 Junction Box Sun 6/28/09 Sun 6/28/09 E 0 0.22 days 2 nos. 0.01 36.35

992 1.11.3.3.1.1.4 High Bay Lighting fixtures including supports and fixings Sun 6/28/09 Mon 6/29/09 E 0 1.64 days 12 nos. 0.05 303.76

993 1.11.3.3.1.1.5 Lighting Feeder cables / wires Mon 6/29/09 Tue 6/30/09 E 0 1.4 days 196 mtr 0.12 771.78

994 1.11.3.3.1.2 Installation - Cable Tray Thu 6/25/09 Tue 6/30/09 0 6 days 0.01 57.35995 1.11.3.3.1.2.1 Cantilever supports installation Thu 6/25/09 Thu 6/25/09 E 0 0.21 days 22 nos. 0 22.95

996 1.11.3.3.1.2.2 Cable Tray installation Tue 6/30/09 Tue 6/30/09 E 0 0.15 days 22 mtr 0.01 34.41

997 1.11.3.3.1.3 Installation - Crane Bus Bars Thu 6/25/09 Thu 6/25/09 0 0.96 days 0.02 96.37998 1.11.3.3.1.3.1 Crane Bus Bar Supports installation Thu 6/25/09 Thu 6/25/09 E 0 0.96 days 16 nos. 0.02 96.37

999 1.11.3.3.1.4 Installation - Blower and Transformer Feeder Thu 6/25/09 Tue 6/30/09 0 5.85 days 0.42 2653.46

1000 1.11.3.3.1.4.1 Blower Feeder, Transformer Feeder Thu 6/25/09 Tue 6/30/09 E 0 5.85 days 700 mtr 0.42 2653.46

1001 1.11.3.3.1.5 Installation - Local Junction Box Thu 6/25/09 Tue 7/28/09 0 36.74 days 0.9 5689.081002 1.11.3.3.1.5.1 Rigid Steel Conduit Thu 6/25/09 Wed 7/1/09 E 0 7.08 days 130 mtr 0.11 691.83

6/25

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 17 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 18: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

1003 1.11.3.3.1.5.2 Junction Box Wed 7/1/09 Sun 7/5/09 E 0 3.54 days 26 nos. 0.05 345.92

1004 1.11.3.3.1.5.3 Feeder cables Sun 7/5/09 Sun 7/12/09 E 0 8.12 days 948 mtr 0.5 3126.95

1005 1.11.3.3.1.5.4 Cable Termination Sun 7/12/09 Tue 7/28/09 E 0 18 days 88 nos. 0.24 1524.38

1006 1.11.3.3.2 Air Compressed System - Piping Thu 6/25/09 Tue 6/30/09 0 6 days 0.05 333.131007 1.11.3.3.2.1 2" Equal Tee Thu 6/25/09 Mon 6/29/09 P 0 4 days 11 nos 0.03 213.2

1008 1.11.3.3.2.2 2" Plug Sat 6/27/09 Sun 6/28/09 P 0 1 day 9 nos 0.01 79.95

1009 1.11.3.3.2.3 1/2" Ball valve Mon 6/29/09 Tue 6/30/09 P 0 1 day 2 nos 0 10.66

1010 1.11.3.3.2.4 2" x 1" Reducer Mon 6/29/09 Tue 6/30/09 P 0 1 day 2 nos 0 10.66

1011 1.11.3.3.2.5 1" x 1/2" Reducer Mon 6/29/09 Tue 6/30/09 P 0 1 day 2 nos 0 10.66

1012 1.11.3.3.2.6 1/2" Nipple Tue 6/30/09 Tue 6/30/09 P 0 1 day 2 nos 0 8

1013 1.11.4 Pot 264 Thu 7/16/09 Wed 8/19/09 0 38.15 days 3.45 21713.141014 4.5.2.1 SLI DELIVERABLES Thu 7/16/09 Thu 7/16/09 0 0 days 0 01015 1.11.4.1.1 POT 264 Area Available for MPEI Construction Thu 7/16/09 Thu 7/16/09 0 0 days 0 0

1016 1.11.4.2 Basement Floor Thu 7/16/09 Sat 8/1/09 0 17.22 days 1.25 7879.231017 1.11.4.2.1 Installation - Electrical Thu 7/16/09 Sat 8/1/09 0 17.22 days 1.25 7879.23

1018 1.11.4.2.1.1 Installation - Lighting System Thu 7/16/09 Sat 8/1/09 0 17.22 days 0.65 4064.821019 1.11.4.2.1.1.1 PVC conduit and boxes Thu 7/16/09 Sat 7/18/09 E 0 2.38 days 81 mtr 0.04 258.24

1020 1.11.4.2.1.1.2 Single Core Wires Sat 7/18/09 Sun 7/19/09 E 0 1.24 days 176 mtr 0.02 130.53

1021 1.11.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 7/16/09 Sat 7/18/09 E 0 1.4 days 19 nos. 0.02 152.97

1022 1.11.4.2.1.1.4 Lighting Feeder cables / wires Tue 7/21/09 Sat 8/1/09 E 0 11.22 days 1477 mtr 0.56 3523.08

1023 1.11.4.2.1.2 Installation - Emergency Shutdown Thu 7/16/09 Tue 7/28/09 0 13.3 days 0.61 3814.411024 1.11.4.2.1.2.1 PVC conduit and boxes Thu 7/16/09 Thu 7/16/09 I 0 0.76 days 12 mtr 0.01 63.96

1025 1.11.4.2.1.2.2 Instrument cables Thu 7/16/09 Tue 7/28/09 I 0 12.21 days 1944 mtr 0.59 3731.8

1026 1.11.4.2.1.2.3 Remote ASI Panel /Cabinet Tue 7/28/09 Tue 7/28/09 I 0 0.33 days 1 mtr 0 18.66

1027 1.11.4.3 Operation Floor Thu 7/16/09 Wed 8/19/09 0 38.15 days 2.2 13833.91

1028 1.11.4.3.1 Installation - Electrical Thu 7/16/09 Wed 8/19/09 0 38.15 days 2.14 13500.78

1029 1.11.4.3.1.1 Installation - Cable Tray Thu 7/16/09 Tue 7/21/09 0 6 days 0.01 57.351030 1.11.4.3.1.1.1 Cantilever supports installation Thu 7/16/09 Thu 7/16/09 E 0 0.21 days 22 nos. 0 22.95

1031 1.11.4.3.1.1.2 Cable Tray installation Tue 7/21/09 Tue 7/21/09 E 0 0.15 days 22 mtr 0.01 34.41

1032 1.11.4.3.1.2 Installation - Crane Bus Bars Thu 7/16/09 Thu 7/23/09 0 7.78 days 0.69 4356.211033 1.11.4.3.1.2.1 Crane Bus Bar Supports installation Thu 7/16/09 Thu 7/16/09 E 0 0.96 days 16 nos. 0.02 96.37

1034 1.11.4.3.1.2.2 Feed Junction Box Installation Thu 7/16/09 Sat 7/18/09 E 0 0.33 days 1 nos. 0 17.59

1035 1.11.4.3.1.2.3 Disconnect Switch Instalation Sat 7/18/09 Sat 7/18/09 E 0 0.5 days 1 nos. 0 17.32

1036 1.11.4.3.1.2.4 Interconnection cable, cableways installation Sat 7/18/09 Sun 7/19/09 E 0 1 day 5 nos. 0.03 159.9

1037 1.11.4.3.1.2.5 Crane Power Feeder Cable Sun 7/19/09 Wed 7/22/09 E 0 4 days 525 mtr 0.63 3978.85

1038 1.11.4.3.1.2.6 Cable Termination Wed 7/22/09 Thu 7/23/09 E 0 0.99 days 5 nos. 0.01 86.19

1039 1.11.4.3.1.3 Installation - Blower and Transformer Feeder Thu 7/16/09 Tue 7/21/09 0 5.85 days 0.42 2653.46

1040 1.11.4.3.1.3.1 Blower Feeder, Transformer Feeder Thu 7/16/09 Tue 7/21/09 E 0 5.85 days 700 mtr 0.42 2653.46

1041 1.11.4.3.1.4 Installation - Socket / Welding Outlet Thu 7/16/09 Sun 7/19/09 0 3.23 days 0.07 434.471042 1.11.4.3.1.4.1 Rigid Steel Conduit Thu 7/16/09 Thu 7/16/09 E 0 0.84 days 15 mtr 0.01 78.35

1043 1.11.4.3.1.4.2 Single Core Wires Thu 7/16/09 Sat 7/18/09 E 0 1.08 days 50 mtr 0.01 80.59

1044 1.11.4.3.1.4.3 Junction Box Sat 7/18/09 Sun 7/19/09 E 0 0.5 days 2 nos. 0 23.98

1045 1.11.4.3.1.4.4 Welding outlet / Socket Outlet Sun 7/19/09 Sun 7/19/09 E 0 0.29 days 2 nos. 0 27.05

1046 1.11.4.3.1.4.5 Socket Feeder cables Sun 7/19/09 Sun 7/19/09 E 0 0.52 days 60 mtr 0.04 224.5

1047 1.11.4.3.1.5 Installation - Local Junction Box Thu 7/16/09 Wed 8/19/09 0 38.15 days 0.95 5999.291048 1.11.4.3.1.5.1 Rigid Steel Conduit Thu 7/16/09 Thu 7/23/09 E 0 7.62 days 140 mtr 0.12 744.6

1049 1.11.4.3.1.5.2 Junction Box Thu 7/23/09 Sun 7/26/09 E 0 3.81 days 28 nos. 0.06 372.3

1050 1.11.4.3.1.5.3 Feeder cables Sun 7/26/09 Mon 8/3/09 E 0 8.72 days 1020 mtr 0.53 3358.01

1051 1.11.4.3.1.5.4 Cable Termination Mon 8/3/09 Wed 8/19/09 E 0 18 days 88 nos. 0.24 1524.38

1052 1.11.4.3.2 Air Compressed System - Piping Thu 7/16/09 Wed 8/12/09 0 30.25 days 0.05 333.131053 1.11.4.3.2.1 2" Equal Tee Thu 7/16/09 Mon 7/20/09 P 0 4 days 11 nos 0.03 213.2

1054 1.11.4.3.2.2 2" Plug Sat 7/18/09 Sun 7/19/09 P 0 1 day 9 nos 0.01 79.95

1055 1.11.4.3.2.3 1/2" Ball valve Sun 7/19/09 Mon 7/20/09 P 0 1 day 2 nos 0 10.66

1056 1.11.4.3.2.4 2" x 1" Reducer Mon 7/20/09 Tue 7/21/09 P 0 1 day 2 nos 0 10.66

1057 1.11.4.3.2.5 1" x 1/2" Reducer Mon 7/20/09 Tue 7/21/09 P 0 1 day 2 nos 0 10.66

1058 1.11.4.3.2.6 1/2" Nipple Tue 8/11/09 Wed 8/12/09 P 0 1 day 2 nos 0 8

1059 1.12 Construction - North Qtr. Passageway 503-42 Mon 6/29/09 Thu 7/23/09 0 27.58 days 0.41 2581.32

1060 4.5.2.1 SLI DELIVERABLES Thu 7/16/09 Thu 7/16/09 0 0 days 0 01061 1.12.1.1 North Qtr. Passage Area (503-42) Available for MPEI

ConstructionThu 7/16/09 Thu 7/16/09 0 0 days 0 0

7/16

7/16

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 18 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 19: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

1062 1.12.2 Operation Floor Mon 6/29/09 Thu 7/23/09 0 27.58 days 0.41 2581.321063 1.12.2.1 Installation - Electrical Mon 6/29/09 Thu 7/23/09 0 27.58 days 0.41 2581.321064 1.12.2.1.1 Installation - Lighting System Mon 6/29/09 Thu 7/23/09 0 27.58 days 0.26 1668.291065 1.12.2.1.1.1 High Bay Lighting fixtures including supports and fixings Mon 6/29/09 Thu 7/2/09 E 0 3.32 days 15 nos. 0.06 389.3

1066 1.12.2.1.1.2 Rigid Steel Conduit Thu 7/16/09 Tue 7/21/09 E 0 4.98 days 100 mtr 0.09 597.23

1067 1.12.2.1.1.3 Single Core Wires Tue 7/21/09 Wed 7/22/09 E 0 1.66 days 150 mtr 0.02 97.33

1068 1.12.2.1.1.4 Lighting Feeder cables / wires Thu 7/23/09 Thu 7/23/09 E 0 0.85 days 110 mtr 0.09 584.43

1069 1.12.2.1.2 Installation - Crane Bus Bars Thu 7/16/09 Thu 7/23/09 0 7.78 days 0.14 913.031070 1.12.2.1.2.1 Feed Junction Box Installation Thu 7/16/09 Sat 7/18/09 E 0 2 days 4 nos. 0.01 69.29

1071 1.12.2.1.2.2 Disconnect Switch Instalation Sat 7/18/09 Mon 7/20/09 E 0 2 days 8 nos. 0.02 138.58

1072 1.12.2.1.2.3 Interconnection cable, cableways installation Mon 7/20/09 Thu 7/23/09 E 0 3.78 days 25 nos. 0.11 705.16

1073 1.13 Construction - Potroom No. 1 (501-12D) Mon 8/10/09 Tue 11/17/09 0 110.14 days 11.79 74238.24

1074 1.13.1 Pot 286 Mon 8/10/09 Sun 9/13/09 0 38.26 days 3.55 22384.241075 4.5.2.1 SLI DELIVERABLES Mon 8/10/09 Mon 8/10/09 0 0 days 0 01076 1.13.1.1.1 POT 286 Area Available for MPEI Construction Mon 8/10/09 Mon 8/10/09 0 0 days 0 0

1077 1.13.1.2 Basement Floor Mon 8/10/09 Mon 8/24/09 0 16.3 days 1.11 7004.23

1078 1.13.1.2.1 Installation - Electrical Mon 8/10/09 Mon 8/24/09 0 16.3 days 1.11 7004.23

1079 1.13.1.2.1.1 Installation - Lighting System Mon 8/10/09 Mon 8/24/09 0 16.3 days 0.51 3208.471080 1.13.1.2.1.1.1 PVC conduit and boxes Mon 8/10/09 Tue 8/11/09 E 0 1.89 days 64 mtr 0.03 205.07

1081 1.13.1.2.1.1.2 Single Core Wires Tue 8/11/09 Wed 8/12/09 E 0 1 day 139 mtr 0.02 105.27

1082 1.13.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Mon 8/10/09 Mon 8/10/09 E 0 1.12 days 15 nos. 0.02 122.38

1083 1.13.1.2.1.1.4 Lighting Feeder cables / wires Sun 8/16/09 Mon 8/24/09 E 0 8.84 days 1167 mtr 0.44 2775.76

1084 1.13.1.2.1.2 Installation - Emergency Shutdown Mon 8/10/09 Sat 8/22/09 0 12.97 days 0.6 3795.761085 1.13.1.2.1.2.1 PVC conduit and boxes Mon 8/10/09 Mon 8/10/09 I 0 0.76 days 12 mtr 0.01 63.96

1086 1.13.1.2.1.2.2 Instrument cables Mon 8/10/09 Sat 8/22/09 I 0 12.21 days 1944 mtr 0.59 3731.8

1087 1.13.1.3 Operation Floor Mon 8/10/09 Sun 9/13/09 0 38.15 days 2.44 15380.01

1088 1.13.1.3.1 Installation - Electrical Mon 8/10/09 Sun 9/13/09 0 38.15 days 2.39 15046.88

1089 1.13.1.3.1.1 Installation - Lighting System Mon 8/10/09 Wed 8/12/09 0 3.58 days 0.09 540.491090 1.13.1.3.1.1.1 Rigid Steel Conduit Mon 8/10/09 Mon 8/10/09 E 0 0.7 days 26 mtr 0.03 157.5

1091 1.13.1.3.1.1.2 Single Core Wires Mon 8/10/09 Tue 8/11/09 E 0 1.04 days 300 mtr 0.03 188.82

1092 1.13.1.3.1.1.3 High Bay Lighting fixtures including supports and fixings Tue 8/11/09 Wed 8/12/09 E 0 0.84 days 6 nos. 0.02 155.58

1093 1.13.1.3.1.1.4 Lighting Feeder cables / wires Wed 8/12/09 Wed 8/12/09 E 0 1 day 8 mtr 0.01 38.59

1094 1.13.1.3.1.2 Installation - Cable Tray Mon 8/10/09 Sun 8/16/09 0 7.35 days 0.06 382.291095 1.13.1.3.1.2.1 Cantilever supports installation Mon 8/10/09 Mon 8/10/09 E 0 0.35 days 32 nos. 0.01 38.24

1096 1.13.1.3.1.2.2 Cable Tray installation Sat 8/15/09 Sun 8/16/09 E 0 1.5 days 189 mtr 0.05 344.05

1097 1.13.1.3.1.3 Installation - Crane Bus Bars Mon 8/10/09 Wed 8/19/09 0 11.1 days 0.87 5471.351098 1.13.1.3.1.3.1 Crane Bus Bar Supports installation Mon 8/10/09 Mon 8/10/09 E 0 0.96 days 16 nos. 0.02 96.37

1099 1.13.1.3.1.3.2 Feed Junction Box Installation Mon 8/10/09 Wed 8/12/09 E 0 1.67 days 5 nos. 0.01 89.01

1100 1.13.1.3.1.3.3 Disconnect Switch Instalation Wed 8/12/09 Wed 8/12/09 E 0 0.5 days 1 nos. 0 17.32

1101 1.13.1.3.1.3.4 Interconnection cable, cableways installation Wed 8/12/09 Thu 8/13/09 E 0 1 day 5 nos. 0.03 159.9

1102 1.13.1.3.1.3.5 Crane Power Feeder Cable Thu 8/13/09 Tue 8/18/09 E 0 4.96 days 650 mtr 0.78 4933.77

1103 1.13.1.3.1.3.6 Cable Termination Tue 8/18/09 Wed 8/19/09 E 0 2.01 days 10 nos. 0.03 174.98

1104 1.13.1.3.1.4 Installation - Blower and Transformer Feeder Mon 8/10/09 Sat 8/15/09 0 5.85 days 0.42 2653.46

1105 1.13.1.3.1.4.1 Blower Feeder, Transformer Feeder Mon 8/10/09 Sat 8/15/09 E 0 5.85 days 700 mtr 0.42 2653.46

1106 1.13.1.3.1.5 Installation - Local Junction Box Mon 8/10/09 Sun 9/13/09 0 38.15 days 0.95 5999.291107 1.13.1.3.1.5.1 Rigid Steel Conduit Mon 8/10/09 Mon 8/17/09 E 0 7.62 days 140 mtr 0.12 744.6

1108 1.13.1.3.1.5.2 Junction Box Mon 8/17/09 Wed 8/19/09 E 0 3.81 days 28 nos. 0.06 372.3

1109 1.13.1.3.1.5.3 Feeder cables Wed 8/19/09 Thu 8/27/09 E 0 8.72 days 1020 mtr 0.53 3358.01

1110 1.13.1.3.1.5.4 Cable Termination Thu 8/27/09 Sun 9/13/09 E 0 18 days 88 nos. 0.24 1524.38

1111 1.13.1.3.2 Air Compressed System - Piping Mon 8/10/09 Sat 8/15/09 0 6 days 0.05 333.131112 1.13.1.3.2.1 2" Equal Tee Mon 8/10/09 Thu 8/13/09 P 0 4 days 11 nos 0.03 213.2

1113 1.13.1.3.2.2 2" Plug Tue 8/11/09 Wed 8/12/09 P 0 1 day 9 nos 0.01 79.95

1114 1.13.1.3.2.3 1/2" Ball valve Wed 8/12/09 Thu 8/13/09 P 0 1 day 2 nos 0 10.66

1115 1.13.1.3.2.4 2" x 1" Reducer Thu 8/13/09 Sat 8/15/09 P 0 1 day 2 nos 0 10.66

1116 1.13.1.3.2.5 1" x 1/2" Reducer Thu 8/13/09 Sat 8/15/09 P 0 1 day 2 nos 0 10.66

1117 1.13.1.3.2.6 1/2" Nipple Sat 8/15/09 Sat 8/15/09 P 0 1 day 2 nos 0 8

1118 1.13.2 Pot 308 Thu 8/27/09 Wed 9/30/09 0 38.15 days 2.79 17545.161119 4.5.2.1 SLI DELIVERABLES Thu 8/27/09 Thu 8/27/09 0 0 days 0 01120 1.13.2.1.1 POT 308 Area Available for MPEI Construction Thu 8/27/09 Thu 8/27/09 0 0 days 0 0

1121 1.13.2.2 Basement Floor Thu 8/27/09 Sun 9/13/09 0 18.06 days 1.21 7646.15

8/10

8/27

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 19 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 20: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

1122 1.13.2.2.1 Installation - Electrical Thu 8/27/09 Sun 9/13/09 0 18.06 days 1.21 7646.15

1123 1.13.2.2.1.1 Installation - Lighting System Thu 8/27/09 Sun 9/13/09 0 18.06 days 0.61 3831.741124 1.13.2.2.1.1.1 PVC conduit and boxes Thu 8/27/09 Sat 8/29/09 E 0 2.24 days 77 mtr 0.04 243.05

1125 1.13.2.2.1.1.2 Single Core Wires Sat 8/29/09 Sun 8/30/09 E 0 1.2 days 167 mtr 0.02 126.32

1126 1.13.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 8/27/09 Sat 8/29/09 E 0 0.91 days 12 nos. 0.02 99.43

1127 1.13.2.2.1.1.4 Lighting Feeder cables / wires Wed 9/2/09 Sun 9/13/09 E 0 10.71 days 1400 mtr 0.53 3362.94

1128 1.13.2.2.1.2 Installation - Emergency Shutdown Thu 8/27/09 Tue 9/8/09 0 13.3 days 0.61 3814.411129 1.13.2.2.1.2.1 PVC conduit and boxes Thu 8/27/09 Thu 8/27/09 I 0 0.76 days 12 mtr 0.01 63.96

1130 1.13.2.2.1.2.2 Instrument cables Thu 8/27/09 Tue 9/8/09 I 0 12.21 days 1944 mtr 0.59 3731.8

1131 1.13.2.2.1.2.3 Remote ASI Panel /Cabinet Tue 9/8/09 Tue 9/8/09 I 0 0.33 days 1 mtr 0 18.66

1132 1.13.2.3 Operation Floor Thu 8/27/09 Wed 9/30/09 0 38.15 days 1.57 9899.01

1133 1.13.2.3.1 Installation - Electrical Thu 8/27/09 Wed 9/30/09 0 38.15 days 1.52 9565.88

1134 1.13.2.3.1.1 Installation - Cable Tray Thu 8/27/09 Wed 9/2/09 0 7.35 days 0.06 382.291135 1.13.2.3.1.1.1 Cantilever supports installation Thu 8/27/09 Thu 8/27/09 E 0 0.35 days 32 nos. 0.01 38.24

1136 1.13.2.3.1.1.2 Cable Tray installation Tue 9/1/09 Wed 9/2/09 E 0 1.5 days 189 mtr 0.05 344.05

1137 1.13.2.3.1.2 Installation - Crane Bus Bars Thu 8/27/09 Thu 8/27/09 0 0.96 days 0.02 96.371138 1.13.2.3.1.2.1 Crane Bus Bar Supports installation Thu 8/27/09 Thu 8/27/09 E 0 0.96 days 16 nos. 0.02 96.37

1139 1.13.2.3.1.3 Installation - Blower and Transformer Feeder Thu 8/27/09 Tue 9/1/09 0 5.85 days 0.42 2653.46

1140 1.13.2.3.1.3.1 Blower Feeder, Transformer Feeder Thu 8/27/09 Tue 9/1/09 E 0 5.85 days 700 mtr 0.42 2653.46

1141 1.13.2.3.1.4 Installation - Socket / Welding Outlet Thu 8/27/09 Sun 8/30/09 0 3.23 days 0.07 434.471142 1.13.2.3.1.4.1 Rigid Steel Conduit Thu 8/27/09 Thu 8/27/09 E 0 0.84 days 15 mtr 0.01 78.35

1143 1.13.2.3.1.4.2 Single Core Wires Thu 8/27/09 Sat 8/29/09 E 0 1.08 days 50 mtr 0.01 80.59

1144 1.13.2.3.1.4.3 Junction Box Sat 8/29/09 Sun 8/30/09 E 0 0.5 days 2 nos. 0 23.98

1145 1.13.2.3.1.4.4 Welding outlet / Socket Outlet Sun 8/30/09 Sun 8/30/09 E 0 0.29 days 2 nos. 0 27.05

1146 1.13.2.3.1.4.5 Socket Feeder cables Sun 8/30/09 Sun 8/30/09 E 0 0.52 days 60 mtr 0.04 224.5

1147 1.13.2.3.1.5 Installation - Local Junction Box Thu 8/27/09 Wed 9/30/09 0 38.15 days 0.95 5999.291148 1.13.2.3.1.5.1 Rigid Steel Conduit Thu 8/27/09 Thu 9/3/09 E 0 7.62 days 140 mtr 0.12 744.6

1149 1.13.2.3.1.5.2 Junction Box Thu 9/3/09 Sun 9/6/09 E 0 3.81 days 28 nos. 0.06 372.3

1150 1.13.2.3.1.5.3 Feeder cables Sun 9/6/09 Mon 9/14/09 E 0 8.72 days 1020 mtr 0.53 3358.01

1151 1.13.2.3.1.5.4 Cable Termination Mon 9/14/09 Wed 9/30/09 E 0 18 days 88 nos. 0.24 1524.38

1152 1.13.2.3.2 Air Compressed System - Piping Thu 8/27/09 Tue 9/1/09 0 6 days 0.05 333.131153 1.13.2.3.2.1 2" Equal Tee Thu 8/27/09 Mon 8/31/09 P 0 4 days 11 nos 0.03 213.2

1154 1.13.2.3.2.2 2" Plug Sat 8/29/09 Sun 8/30/09 P 0 1 day 9 nos 0.01 79.95

1155 1.13.2.3.2.3 1/2" Ball valve Sun 8/30/09 Mon 8/31/09 P 0 1 day 2 nos 0 10.66

1156 1.13.2.3.2.4 2" x 1" Reducer Mon 8/31/09 Tue 9/1/09 P 0 1 day 2 nos 0 10.66

1157 1.13.2.3.2.5 1" x 1/2" Reducer Mon 8/31/09 Tue 9/1/09 P 0 1 day 2 nos 0 10.66

1158 1.13.2.3.2.6 1/2" Nipple Tue 9/1/09 Tue 9/1/09 P 0 1 day 2 nos 0 8

1159 1.13.3 Pot 330 Tue 9/15/09 Wed 10/7/09 0 24.76 days 2.37 14901.371160 4.5.2.1 SLI DELIVERABLES Thu 9/17/09 Thu 9/17/09 0 0 days 0 01161 1.13.3.1.1 POT 330 Area Available for MPEI Construction Thu 9/17/09 Thu 9/17/09 0 0 days 0 0

1162 1.13.3.2 Basement Floor Tue 9/15/09 Tue 9/29/09 0 15.04 days 1.15 7263.46

1163 1.13.3.2.1 Installation - Electrical Tue 9/15/09 Tue 9/29/09 0 15.04 days 1.15 7263.46

1164 1.13.3.2.1.1 Installation - Lighting System Tue 9/15/09 Thu 9/24/09 0 9.52 days 0.55 3449.041165 1.13.3.2.1.1.1 PVC conduit and boxes Thu 9/17/09 Sat 9/19/09 E 0 2.03 days 68 mtr 0.03 220.26

1166 1.13.3.2.1.1.2 Single Core Wires Sat 9/19/09 Sun 9/20/09 E 0 1.04 days 148 mtr 0.02 109.48

1167 1.13.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 9/17/09 Sat 9/19/09 E 0 1.19 days 16 nos. 0.02 130.03

1168 1.13.3.2.1.1.4 Lighting Feeder cables / wires Tue 9/15/09 Thu 9/24/09 E 0 9.52 days 1244 mtr 0.47 2989.28

1169 1.13.3.2.1.2 Installation - Emergency Shutdown Thu 9/17/09 Tue 9/29/09 0 13.3 days 0.61 3814.411170 1.13.3.2.1.2.1 PVC conduit and boxes Thu 9/17/09 Thu 9/17/09 I 0 0.76 days 12 mtr 0.01 63.96

1171 1.13.3.2.1.2.2 Instrument cables Thu 9/17/09 Tue 9/29/09 I 0 12.21 days 1944 mtr 0.59 3731.8

1172 1.13.3.2.1.2.3 Remote ASI Panel /Cabinet Tue 9/29/09 Tue 9/29/09 I 0 0.33 days 1 mtr 0 18.66

1173 1.13.3.3 Operation Floor Thu 9/17/09 Wed 10/7/09 0 23.02 days 1.21 7637.92

1174 1.13.3.3.1 Installation - Electrical Thu 9/17/09 Wed 10/7/09 0 23.02 days 1.16 7304.79

1175 1.13.3.3.1.1 Installation - Lighting System Thu 9/17/09 Tue 9/22/09 0 5.7 days 0.26 1615.711176 1.13.3.3.1.1.1 Rigid Steel Conduit Thu 9/17/09 Sat 9/19/09 E 0 1.4 days 52 mtr 0.05 315

1177 1.13.3.3.1.1.2 Single Core Wires Sat 9/19/09 Sun 9/20/09 E 0 1.04 days 300 mtr 0.03 188.82

1178 1.13.3.3.1.1.3 Junction Box Sun 9/20/09 Sun 9/20/09 E 0 0.22 days 2 nos. 0.01 36.35

1179 1.13.3.3.1.1.4 High Bay Lighting fixtures including supports and fixings Sun 9/20/09 Mon 9/21/09 E 0 1.64 days 12 nos. 0.05 303.76

9/17

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 20 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 21: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

1180 1.13.3.3.1.1.5 Lighting Feeder cables / wires Mon 9/21/09 Tue 9/22/09 E 0 1.4 days 196 mtr 0.12 771.78

1181 1.13.3.3.1.2 Installation - Local Junction Box Thu 9/17/09 Wed 10/7/09 0 23.02 days 0.9 5689.081182 1.13.3.3.1.2.1 Rigid Steel Conduit Thu 9/17/09 Thu 9/17/09 E 0 1 day 130 mtr 0.11 691.83

1183 1.13.3.3.1.2.2 Junction Box Thu 9/17/09 Thu 9/24/09 E 0 7.08 days 26 nos. 0.05 345.92

1184 1.13.3.3.1.2.3 Feeder cables Thu 9/24/09 Mon 9/28/09 E 0 3.54 days 948 mtr 0.5 3126.95

1185 1.13.3.3.1.2.4 Cable Termination Wed 9/30/09 Wed 10/7/09 E 0 8.12 days 88 nos. 0.24 1524.38

1186 1.13.3.3.2 Air Compressed System - Piping Thu 9/17/09 Tue 9/22/09 0 6 days 0.05 333.131187 1.13.3.3.2.1 2" Equal Tee Thu 9/17/09 Mon 9/21/09 P 0 4 days 11 nos 0.03 213.2

1188 1.13.3.3.2.2 2" Plug Sat 9/19/09 Sun 9/20/09 P 0 1 day 9 nos 0.01 79.95

1189 1.13.3.3.2.3 1/2" Ball valve Sun 9/20/09 Mon 9/21/09 P 0 1 day 2 nos 0 10.66

1190 1.13.3.3.2.4 2" x 1" Reducer Mon 9/21/09 Tue 9/22/09 P 0 1 day 2 nos 0 10.66

1191 1.13.3.3.2.5 1" x 1/2" Reducer Mon 9/21/09 Tue 9/22/09 P 0 1 day 2 nos 0 10.66

1192 1.13.3.3.2.6 1/2" Nipple Tue 9/22/09 Tue 9/22/09 P 0 1 day 2 nos 0 8

1193 1.13.4 Pot 352 Wed 10/7/09 Tue 11/17/09 0 45.13 days 3.08 19407.461194 4.5.2.1 SLI DELIVERABLES Thu 10/8/09 Thu 10/8/09 0 0 days 0 01195 1.13.4.1.1 POT 352 Area Available for MPEI Construction Thu 10/8/09 Thu 10/8/09 0 0 days 0 0

1196 1.13.4.2 Basement Floor Wed 10/7/09 Tue 10/20/09 0 13.95 days 1.25 7860.581197 1.13.4.2.1 Installation - Electrical Wed 10/7/09 Tue 10/20/09 0 13.95 days 1.25 7860.58

1198 1.13.4.2.1.1 Installation - Lighting System Wed 10/7/09 Sun 10/18/09 0 11.22 days 0.65 4064.821199 1.13.4.2.1.1.1 PVC conduit and boxes Thu 10/8/09 Sat 10/10/09 E 0 2.38 days 81 mtr 0.04 258.24

1200 1.13.4.2.1.1.2 Single Core Wires Sat 10/10/09 Sun 10/11/09 E 0 1.24 days 176 mtr 0.02 130.53

1201 1.13.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 10/8/09 Sat 10/10/09 E 0 1.4 days 19 nos. 0.02 152.97

1202 1.13.4.2.1.1.4 Lighting Feeder cables / wires Wed 10/7/09 Sun 10/18/09 E 0 11.22 days 1477 mtr 0.56 3523.08

1203 1.13.4.2.1.2 Installation - Emergency Shutdown Thu 10/8/09 Tue 10/20/09 0 12.97 days 0.6 3795.761204 1.13.4.2.1.2.1 PVC conduit and boxes Thu 10/8/09 Thu 10/8/09 I 0 0.76 days 12 mtr 0.01 63.96

1205 1.13.4.2.1.2.2 Instrument cables Thu 10/8/09 Tue 10/20/09 I 0 12.21 days 1944 mtr 0.59 3731.8

1206 1.13.4.3 Operation Floor Thu 10/8/09 Tue 11/17/09 0 44.15 days 1.83 11546.89

1207 1.13.4.3.1 Installation - Electrical Thu 10/8/09 Tue 11/17/09 0 44.15 days 1.78 11213.76

1208 1.13.4.3.1.1 Installation - Crane Bus Bars Thu 10/8/09 Sun 10/18/09 0 10.87 days 1 6320.371209 1.13.4.3.1.1.1 Crane Bus Bar Supports installation Thu 10/8/09 Thu 10/8/09 E 0 0.96 days 16 nos. 0.02 96.37

1210 1.13.4.3.1.1.2 Feed Junction Box Installation Thu 10/8/09 Sun 10/11/09 E 0 2.33 days 7 nos. 0.02 124.19

1211 1.13.4.3.1.1.3 Disconnect Switch Instalation Sun 10/11/09 Mon 10/12/09 E 0 1.5 days 3 nos. 0.01 51.97

1212 1.13.4.3.1.1.4 Crane Power Feeder Cable Mon 10/12/09 Sun 10/18/09 E 0 6.08 days 800 mtr 0.96 6047.84

1213 1.13.4.3.1.2 Installation - Socket / Welding Outlet Thu 10/8/09 Sun 10/11/09 0 3.23 days 0.07 434.471214 1.13.4.3.1.2.1 Rigid Steel Conduit Thu 10/8/09 Thu 10/8/09 E 0 0.84 days 15 mtr 0.01 78.35

1215 1.13.4.3.1.2.2 Single Core Wires Thu 10/8/09 Sat 10/10/09 E 0 1.08 days 50 mtr 0.01 80.59

1216 1.13.4.3.1.2.3 Junction Box Sat 10/10/09 Sun 10/11/09 E 0 0.5 days 2 nos. 0 23.98

1217 1.13.4.3.1.2.4 Welding outlet / Socket Outlet Sun 10/11/09 Sun 10/11/09 E 0 0.29 days 2 nos. 0 27.05

1218 1.13.4.3.1.2.5 Socket Feeder cables Sun 10/11/09 Sun 10/11/09 E 0 0.52 days 60 mtr 0.04 224.5

1219 1.13.4.3.1.3 Installation - Local Junction Box Sat 10/17/09 Tue 11/17/09 0 34.15 days 0.71 4458.921220 1.13.4.3.1.3.1 Rigid Steel Conduit Sat 10/17/09 Sat 10/24/09 E 0 7.62 days 140 mtr 0.12 744.6

1221 1.13.4.3.1.3.2 Junction Box Sat 10/24/09 Tue 10/27/09 E 0 3.81 days 28 nos. 0.06 372.3

1222 1.13.4.3.1.3.3 Feeder cables Tue 10/27/09 Sun 11/1/09 E 0 4.72 days 550 mtr 0.29 1817.64

1223 1.13.4.3.1.3.4 Cable Termination Sun 11/1/09 Tue 11/17/09 E 0 18 days 88 nos. 0.24 1524.38

1224 1.13.4.3.2 Air Compressed System - Piping Thu 10/8/09 Tue 10/13/09 0 6 days 0.05 333.131225 1.13.4.3.2.1 2" Equal Tee Thu 10/8/09 Mon 10/12/09 P 0 4 days 11 nos 0.03 213.2

1226 1.13.4.3.2.2 2" Plug Sat 10/10/09 Sun 10/11/09 P 0 1 day 9 nos 0.01 79.95

1227 1.13.4.3.2.3 1/2" Ball valve Sun 10/11/09 Mon 10/12/09 P 0 1 day 2 nos 0 10.66

1228 1.13.4.3.2.4 2" x 1" Reducer Mon 10/12/09 Tue 10/13/09 P 0 1 day 2 nos 0 10.66

1229 1.13.4.3.2.5 1" x 1/2" Reducer Mon 10/12/09 Tue 10/13/09 P 0 1 day 2 nos 0 10.66

1230 1.13.4.3.2.6 1/2" Nipple Tue 10/13/09 Tue 10/13/09 P 0 1 day 2 nos 0 8

1231 1.14 Construction - Potroom No. 2 (501-22D) Tue 7/28/09 Wed 10/28/09 0 102.84 days 12.26 77203.88

1232 1.14.1 Pot 286 Tue 7/28/09 Sat 9/5/09 0 43.34 days 3.62 22818.721233 4.5.2.1 SLI DELIVERABLES Tue 7/28/09 Tue 7/28/09 0 0 days 0 01234 1.14.1.1.1 POT 286 Area Available for MPEI Construction Tue 7/28/09 Tue 7/28/09 0 0 days 0 0

1235 1.14.1.2 Basement Floor Tue 7/28/09 Sun 8/9/09 0 13.08 days 1.11 7004.23

1236 1.14.1.2.1 Installation - Electrical Tue 7/28/09 Sun 8/9/09 0 13.08 days 1.11 7004.23

1237 1.14.1.2.1.1 Installation - Lighting System Tue 7/28/09 Thu 8/6/09 0 11.3 days 0.51 3208.471238 1.14.1.2.1.1.1 PVC conduit and boxes Tue 7/28/09 Wed 7/29/09 E 0 1.89 days 64 mtr 0.03 205.07

1239 1.14.1.2.1.1.2 Single Core Wires Wed 7/29/09 Thu 7/30/09 E 0 1 day 139 mtr 0.02 105.27

10/8

7/28

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 21 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 22: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

1240 1.14.1.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Tue 7/28/09 Tue 7/28/09 E 0 1.12 days 15 nos. 0.02 122.38

1241 1.14.1.2.1.1.4 Lighting Feeder cables / wires Wed 7/29/09 Thu 8/6/09 E 0 8.84 days 1167 mtr 0.44 2775.76

1242 1.14.1.2.1.2 Installation - Emergency Shutdown Tue 7/28/09 Sun 8/9/09 0 12.97 days 0.6 3795.761243 1.14.1.2.1.2.1 PVC conduit and boxes Tue 7/28/09 Tue 7/28/09 I 0 0.76 days 12 mtr 0.01 63.96

1244 1.14.1.2.1.2.2 Instrument cables Tue 7/28/09 Sun 8/9/09 I 0 12.21 days 1944 mtr 0.59 3731.8

1245 1.14.1.3 Operation Floor Tue 7/28/09 Sat 9/5/09 0 43.23 days 2.51 15814.48

1246 1.14.1.3.1 Installation - Electrical Tue 7/28/09 Sat 9/5/09 0 43.23 days 2.46 15481.36

1247 1.14.1.3.1.1 Installation - Lighting System Tue 7/28/09 Thu 7/30/09 0 3.58 days 0.09 540.491248 1.14.1.3.1.1.1 Rigid Steel Conduit Tue 7/28/09 Tue 7/28/09 E 0 0.7 days 26 mtr 0.03 157.5

1249 1.14.1.3.1.1.2 Single Core Wires Tue 7/28/09 Wed 7/29/09 E 0 1.04 days 300 mtr 0.03 188.82

1250 1.14.1.3.1.1.3 High Bay Lighting fixtures including supports and fixings Wed 7/29/09 Thu 7/30/09 E 0 0.84 days 6 nos. 0.02 155.58

1251 1.14.1.3.1.1.4 Lighting Feeder cables / wires Thu 7/30/09 Thu 7/30/09 E 0 1 day 8 mtr 0.01 38.59

1252 1.14.1.3.1.2 Installation - Cable Tray Tue 7/28/09 Mon 8/3/09 0 7.35 days 0.06 382.291253 1.14.1.3.1.2.1 Cantilever supports installation Tue 7/28/09 Tue 7/28/09 E 0 0.35 days 32 nos. 0.01 38.24

1254 1.14.1.3.1.2.2 Cable Tray installation Sun 8/2/09 Mon 8/3/09 E 0 1.5 days 189 mtr 0.05 344.05

1255 1.14.1.3.1.3 Installation - Crane Bus Bars Tue 7/28/09 Thu 8/6/09 0 11.1 days 0.87 5471.351256 1.14.1.3.1.3.1 Crane Bus Bar Supports installation Tue 7/28/09 Tue 7/28/09 E 0 0.96 days 16 nos. 0.02 96.37

1257 1.14.1.3.1.3.2 Feed Junction Box Installation Tue 7/28/09 Thu 7/30/09 E 0 1.67 days 5 nos. 0.01 89.01

1258 1.14.1.3.1.3.3 Disconnect Switch Instalation Thu 7/30/09 Thu 7/30/09 E 0 0.5 days 1 nos. 0 17.32

1259 1.14.1.3.1.3.4 Interconnection cable, cableways installation Thu 7/30/09 Sat 8/1/09 E 0 1 day 5 nos. 0.03 159.9

1260 1.14.1.3.1.3.5 Crane Power Feeder Cable Sat 8/1/09 Wed 8/5/09 E 0 4.96 days 650 mtr 0.78 4933.77

1261 1.14.1.3.1.3.6 Cable Termination Wed 8/5/09 Thu 8/6/09 E 0 2.01 days 10 nos. 0.03 174.98

1262 1.14.1.3.1.4 Installation - Blower and Transformer Feeder Tue 7/28/09 Sun 8/2/09 0 5.85 days 0.42 2653.46

1263 1.14.1.3.1.4.1 Blower Feeder, Transformer Feeder Tue 7/28/09 Sun 8/2/09 E 0 5.85 days 700 mtr 0.42 2653.46

1264 1.14.1.3.1.5 Installation - Socket / Welding Outlet Tue 7/28/09 Thu 7/30/09 0 3.23 days 0.07 434.471265 1.14.1.3.1.5.1 Rigid Steel Conduit Tue 7/28/09 Tue 7/28/09 E 0 0.84 days 15 mtr 0.01 78.35

1266 1.14.1.3.1.5.2 Single Core Wires Tue 7/28/09 Wed 7/29/09 E 0 1.08 days 50 mtr 0.01 80.59

1267 1.14.1.3.1.5.3 Junction Box Wed 7/29/09 Thu 7/30/09 E 0 0.5 days 2 nos. 0 23.98

1268 1.14.1.3.1.5.4 Welding outlet / Socket Outlet Thu 7/30/09 Thu 7/30/09 E 0 0.29 days 2 nos. 0 27.05

1269 1.14.1.3.1.5.5 Socket Feeder cables Thu 7/30/09 Thu 7/30/09 E 0 0.52 days 60 mtr 0.04 224.5

1270 1.14.1.3.1.6 Installation - Local Junction Box Tue 7/28/09 Sat 9/5/09 0 43.23 days 0.95 5999.291271 1.14.1.3.1.6.1 Rigid Steel Conduit Tue 7/28/09 Tue 8/4/09 E 0 7.62 days 140 mtr 0.12 744.6

1272 1.14.1.3.1.6.2 Junction Box Tue 8/4/09 Thu 8/6/09 E 0 3.81 days 28 nos. 0.06 372.3

1273 1.14.1.3.1.6.3 Feeder cables Thu 8/6/09 Sat 8/15/09 E 0 8.72 days 1020 mtr 0.53 3358.01

1274 1.14.1.3.1.6.4 Cable Termination Wed 8/19/09 Sat 9/5/09 E 0 18 days 88 nos. 0.24 1524.38

1275 1.14.1.3.2 Air Compressed System - Piping Tue 7/28/09 Thu 8/13/09 0 18.33 days 0.05 333.131276 1.14.1.3.2.1 2" Equal Tee Tue 7/28/09 Sat 8/1/09 P 0 4 days 11 nos 0.03 213.2

1277 1.14.1.3.2.2 2" Plug Wed 7/29/09 Thu 7/30/09 P 0 1 day 9 nos 0.01 79.95

1278 1.14.1.3.2.3 1/2" Ball valve Sat 8/1/09 Sun 8/2/09 P 0 1 day 2 nos 0 10.66

1279 1.14.1.3.2.4 2" x 1" Reducer Sat 8/1/09 Sun 8/2/09 P 0 1 day 2 nos 0 10.66

1280 1.14.1.3.2.5 1" x 1/2" Reducer Sat 8/1/09 Sun 8/2/09 P 0 1 day 2 nos 0 10.66

1281 1.14.1.3.2.6 1/2" Nipple Wed 8/12/09 Thu 8/13/09 P 0 1 day 2 nos 0 8

1282 1.14.2 Pot 308 Sat 8/15/09 Tue 9/29/09 0 50.58 days 2.79 17591.051283 4.5.2.1 SLI DELIVERABLES Sat 8/15/09 Sat 8/15/09 0 0 days 0 01284 1.14.2.1.1 POT 308 Area Available for MPEI Construction Sat 8/15/09 Sat 8/15/09 0 0 days 0 0

1285 1.14.2.2 Basement Floor Sat 8/15/09 Mon 8/31/09 0 18.06 days 1.22 7692.041286 1.14.2.2.1 Installation - Electrical Sat 8/15/09 Mon 8/31/09 0 18.06 days 1.22 7692.04

1287 1.14.2.2.1.1 Installation - Lighting System Sat 8/15/09 Mon 8/31/09 0 18.06 days 0.62 3877.631288 1.14.2.2.1.1.1 PVC conduit and boxes Sat 8/15/09 Sun 8/16/09 E 0 2.24 days 77 mtr 0.04 243.05

1289 1.14.2.2.1.1.2 Single Core Wires Sun 8/16/09 Mon 8/17/09 E 0 1.2 days 167 mtr 0.02 126.32

1290 1.14.2.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Sat 8/15/09 Sun 8/16/09 E 0 1.33 days 18 nos. 0.02 145.32

1291 1.14.2.2.1.1.4 Lighting Feeder cables / wires Thu 8/20/09 Mon 8/31/09 E 0 10.71 days 1400 mtr 0.53 3362.94

1292 1.14.2.2.1.2 Installation - Emergency Shutdown Sat 8/15/09 Wed 8/26/09 0 13.3 days 0.61 3814.411293 1.14.2.2.1.2.1 PVC conduit and boxes Sat 8/15/09 Sat 8/15/09 I 0 0.76 days 12 mtr 0.01 63.96

1294 1.14.2.2.1.2.2 Instrument cables Sat 8/15/09 Wed 8/26/09 I 0 12.21 days 1944 mtr 0.59 3731.8

1295 1.14.2.2.1.2.3 Remote ASI Panel /Cabinet Wed 8/26/09 Wed 8/26/09 I 0 0.33 days 1 mtr 0 18.66

1296 1.14.2.3 Operation Floor Sat 8/15/09 Tue 9/29/09 0 50.58 days 1.57 9899.01

1297 1.14.2.3.1 Installation - Electrical Sat 8/15/09 Tue 9/29/09 0 50.58 days 1.52 9565.88

1298 1.14.2.3.1.1 Installation - Cable Tray Sat 8/15/09 Thu 8/20/09 0 7.35 days 0.06 382.29

8/15

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 22 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 23: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

1299 1.14.2.3.1.1.1 Cantilever supports installation Sat 8/15/09 Sat 8/15/09 E 0 0.35 days 32 nos. 0.01 38.24

1300 1.14.2.3.1.1.2 Cable Tray installation Wed 8/19/09 Thu 8/20/09 E 0 1.5 days 189 mtr 0.05 344.05

1301 1.14.2.3.1.2 Installation - Crane Bus Bars Sat 8/15/09 Sat 8/15/09 0 0.96 days 0.02 96.371302 1.14.2.3.1.2.1 Crane Bus Bar Supports installation Sat 8/15/09 Sat 8/15/09 E 0 0.96 days 16 nos. 0.02 96.37

1303 1.14.2.3.1.3 Installation - Blower and Transformer Feeder Sat 8/15/09 Wed 8/19/09 0 5.85 days 0.42 2653.46

1304 1.14.2.3.1.3.1 Blower Feeder, Transformer Feeder Sat 8/15/09 Wed 8/19/09 E 0 5.85 days 700 mtr 0.42 2653.46

1305 1.14.2.3.1.4 Installation - Socket / Welding Outlet Sat 8/15/09 Mon 8/17/09 0 3.23 days 0.07 434.471306 1.14.2.3.1.4.1 Rigid Steel Conduit Sat 8/15/09 Sat 8/15/09 E 0 0.84 days 15 mtr 0.01 78.35

1307 1.14.2.3.1.4.2 Single Core Wires Sat 8/15/09 Sun 8/16/09 E 0 1.08 days 50 mtr 0.01 80.59

1308 1.14.2.3.1.4.3 Junction Box Sun 8/16/09 Mon 8/17/09 E 0 0.5 days 2 nos. 0 23.98

1309 1.14.2.3.1.4.4 Welding outlet / Socket Outlet Mon 8/17/09 Mon 8/17/09 E 0 0.29 days 2 nos. 0 27.05

1310 1.14.2.3.1.4.5 Socket Feeder cables Mon 8/17/09 Mon 8/17/09 E 0 0.52 days 60 mtr 0.04 224.5

1311 1.14.2.3.1.5 Installation - Local Junction Box Sat 8/15/09 Tue 9/29/09 0 50.58 days 0.95 5999.291312 1.14.2.3.1.5.1 Rigid Steel Conduit Sat 8/15/09 Sat 8/22/09 E 0 7.62 days 140 mtr 0.12 744.6

1313 1.14.2.3.1.5.2 Junction Box Sat 8/22/09 Mon 8/24/09 E 0 3.81 days 28 nos. 0.06 372.3

1314 1.14.2.3.1.5.3 Feeder cables Sat 9/5/09 Sun 9/13/09 E 0 8.72 days 1020 mtr 0.53 3358.01

1315 1.14.2.3.1.5.4 Cable Termination Sun 9/13/09 Tue 9/29/09 E 0 18 days 88 nos. 0.24 1524.38

1316 1.14.2.3.2 Air Compressed System - Piping Sat 8/15/09 Wed 8/19/09 0 6 days 0.05 333.131317 1.14.2.3.2.1 2" Equal Tee Sat 8/15/09 Tue 8/18/09 P 0 4 days 11 nos 0.03 213.2

1318 1.14.2.3.2.2 2" Plug Sun 8/16/09 Mon 8/17/09 P 0 1 day 9 nos 0.01 79.95

1319 1.14.2.3.2.3 1/2" Ball valve Tue 8/18/09 Wed 8/19/09 P 0 1 day 2 nos 0 10.66

1320 1.14.2.3.2.4 2" x 1" Reducer Tue 8/18/09 Wed 8/19/09 P 0 1 day 2 nos 0 10.66

1321 1.14.2.3.2.5 1" x 1/2" Reducer Tue 8/18/09 Wed 8/19/09 P 0 1 day 2 nos 0 10.66

1322 1.14.2.3.2.6 1/2" Nipple Wed 8/19/09 Wed 8/19/09 P 0 1 day 2 nos 0 8

1323 1.14.3 Pot 330 Mon 8/31/09 Thu 10/15/09 0 49.65 days 2.37 14901.371324 4.5.2.1 SLI DELIVERABLES Wed 9/2/09 Wed 9/2/09 0 0 days 0 01325 1.14.3.1.1 POT 330 Area Available for MPEI Construction Wed 9/2/09 Wed 9/2/09 0 0 days 0 0

1326 1.14.3.2 Basement Floor Mon 8/31/09 Mon 9/14/09 0 15.04 days 1.15 7263.461327 1.14.3.2.1 Installation - Electrical Mon 8/31/09 Mon 9/14/09 0 15.04 days 1.15 7263.46

1328 1.14.3.2.1.1 Installation - Lighting System Mon 8/31/09 Wed 9/9/09 0 9.52 days 0.55 3449.041329 1.14.3.2.1.1.1 PVC conduit and boxes Wed 9/2/09 Thu 9/3/09 E 0 2.03 days 68 mtr 0.03 220.26

1330 1.14.3.2.1.1.2 Single Core Wires Thu 9/3/09 Sat 9/5/09 E 0 1.04 days 148 mtr 0.02 109.48

1331 1.14.3.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Wed 9/2/09 Thu 9/3/09 E 0 1.19 days 16 nos. 0.02 130.03

1332 1.14.3.2.1.1.4 Lighting Feeder cables / wires Mon 8/31/09 Wed 9/9/09 E 0 9.52 days 1244 mtr 0.47 2989.28

1333 1.14.3.2.1.2 Installation - Emergency Shutdown Wed 9/2/09 Mon 9/14/09 0 13.3 days 0.61 3814.411334 1.14.3.2.1.2.1 PVC conduit and boxes Wed 9/2/09 Wed 9/2/09 I 0 0.76 days 12 mtr 0.01 63.96

1335 1.14.3.2.1.2.2 Instrument cables Wed 9/2/09 Mon 9/14/09 I 0 12.21 days 1944 mtr 0.59 3731.8

1336 1.14.3.2.1.2.3 Remote ASI Panel /Cabinet Mon 9/14/09 Mon 9/14/09 I 0 0.33 days 1 mtr 0 18.66

1337 1.14.3.3 Operation Floor Wed 9/2/09 Thu 10/15/09 0 47.91 days 1.21 7637.92

1338 1.14.3.3.1 Installation - Electrical Wed 9/2/09 Thu 10/15/09 0 47.91 days 1.16 7304.79

1339 1.14.3.3.1.1 Installation - Lighting System Wed 9/2/09 Mon 9/7/09 0 5.7 days 0.26 1615.711340 1.14.3.3.1.1.1 Rigid Steel Conduit Wed 9/2/09 Thu 9/3/09 E 0 1.4 days 52 mtr 0.05 315

1341 1.14.3.3.1.1.2 Single Core Wires Thu 9/3/09 Sat 9/5/09 E 0 1.04 days 300 mtr 0.03 188.82

1342 1.14.3.3.1.1.3 Junction Box Sat 9/5/09 Sat 9/5/09 E 0 0.22 days 2 nos. 0.01 36.35

1343 1.14.3.3.1.1.4 High Bay Lighting fixtures including supports and fixings Sat 9/5/09 Sun 9/6/09 E 0 1.64 days 12 nos. 0.05 303.76

1344 1.14.3.3.1.1.5 Lighting Feeder cables / wires Sun 9/6/09 Mon 9/7/09 E 0 1.4 days 196 mtr 0.12 771.78

1345 1.14.3.3.1.2 Installation - Local Junction Box Wed 9/2/09 Thu 10/15/09 0 47.91 days 0.9 5689.081346 1.14.3.3.1.2.1 Rigid Steel Conduit Wed 9/2/09 Tue 9/8/09 E 0 7.08 days 130 mtr 0.11 691.83

1347 1.14.3.3.1.2.2 Junction Box Tue 9/8/09 Sat 9/12/09 E 0 3.54 days 26 nos. 0.05 345.92

1348 1.14.3.3.1.2.3 Feeder cables Sun 9/13/09 Sun 9/20/09 E 0 8.12 days 948 mtr 0.5 3126.95

1349 1.14.3.3.1.2.4 Cable Termination Tue 9/29/09 Thu 10/15/09 E 0 18 days 88 nos. 0.24 1524.38

1350 1.14.3.3.2 Air Compressed System - Piping Wed 9/2/09 Mon 9/7/09 0 6 days 0.05 333.131351 1.14.3.3.2.1 2" Equal Tee Wed 9/2/09 Sun 9/6/09 P 0 4 days 11 nos 0.03 213.2

1352 1.14.3.3.2.2 2" Plug Thu 9/3/09 Sat 9/5/09 P 0 1 day 9 nos 0.01 79.95

1353 1.14.3.3.2.3 1/2" Ball valve Sun 9/6/09 Mon 9/7/09 P 0 1 day 2 nos 0 10.66

1354 1.14.3.3.2.4 2" x 1" Reducer Sun 9/6/09 Mon 9/7/09 P 0 1 day 2 nos 0 10.66

1355 1.14.3.3.2.5 1" x 1/2" Reducer Sun 9/6/09 Mon 9/7/09 P 0 1 day 2 nos 0 10.66

1356 1.14.3.3.2.6 1/2" Nipple Mon 9/7/09 Mon 9/7/09 P 0 1 day 2 nos 0 8

1357 1.14.4 Pot 352 Wed 9/23/09 Wed 10/28/09 0 39.13 days 3.48 21892.741358 4.5.2.1 SLI DELIVERABLES Thu 9/24/09 Thu 9/24/09 0 0 days 0 0

9/2

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 23 Of 24

Project: C005 without subtotalDate: Tue 3/31/09

Page 24: ECN Plan For C-005 Final

ID WBS Task Name Start Finish Code Final %From

Weight

Duration Quantity(ECN)

Unit Weight M/H Final

1359 1.14.4.1.1 POT 352 Area Available for MPEI Construction Thu 9/24/09 Thu 9/24/09 0 0 days 0 0

1360 1.14.4.2 Basement Floor Wed 9/23/09 Tue 10/6/09 0 13.95 days 1.25 7860.581361 1.14.4.2.1 Installation - Electrical Wed 9/23/09 Tue 10/6/09 0 13.95 days 1.25 7860.58

1362 1.14.4.2.1.1 Installation - Lighting System Wed 9/23/09 Sun 10/4/09 0 11.22 days 0.65 4064.821363 1.14.4.2.1.1.1 PVC conduit and boxes Thu 9/24/09 Sat 9/26/09 E 0 2.38 days 81 mtr 0.04 258.24

1364 1.14.4.2.1.1.2 Single Core Wires Sat 9/26/09 Sun 9/27/09 E 0 1.24 days 176 mtr 0.02 130.53

1365 1.14.4.2.1.1.3 Low Bay, Wall Mounted Lighting fixtures including supportsand fixings

Thu 9/24/09 Sat 9/26/09 E 0 1.4 days 19 nos. 0.02 152.97

1366 1.14.4.2.1.1.4 Lighting Feeder cables / wires Wed 9/23/09 Sun 10/4/09 E 0 11.22 days 1477 mtr 0.56 3523.08

1367 1.14.4.2.1.2 Installation - Emergency Shutdown Thu 9/24/09 Tue 10/6/09 0 12.97 days 0.6 3795.761368 1.14.4.2.1.2.1 PVC conduit and boxes Thu 9/24/09 Thu 9/24/09 I 0 0.76 days 12 mtr 0.01 63.96

1369 1.14.4.2.1.2.2 Instrument cables Thu 9/24/09 Tue 10/6/09 I 0 12.21 days 1944 mtr 0.59 3731.8

1370 1.14.4.3 Operation Floor Thu 9/24/09 Wed 10/28/09 0 38.15 days 2.23 14032.16

1371 1.14.4.3.1 Installation - Electrical Thu 9/24/09 Wed 10/28/09 0 38.15 days 2.17 13699.03

1372 1.14.4.3.1.1 Installation - Crane Bus Bars Thu 9/24/09 Mon 10/12/09 0 19.52 days 1.15 7265.271373 1.14.4.3.1.1.1 Crane Bus Bar Supports installation Thu 9/24/09 Thu 9/24/09 E 0 0.96 days 16 nos. 0.02 96.37

1374 1.14.4.3.1.1.2 Feed Junction Box Installation Thu 9/24/09 Sun 9/27/09 E 0 2.33 days 7 nos. 0.02 124.19

1375 1.14.4.3.1.1.3 Disconnect Switch Instalation Sun 9/27/09 Tue 9/29/09 E 0 2 days 4 nos. 0.01 69.29

1376 1.14.4.3.1.1.4 Interconnection cable, cableways installation Tue 9/29/09 Wed 9/30/09 E 0 1 day 5 nos. 0.03 159.9

1377 1.14.4.3.1.1.5 Crane Power Feeder Cable Wed 9/30/09 Mon 10/5/09 E 0 6.24 days 820 mtr 0.99 6207

1378 1.14.4.3.1.1.6 Cable Termination Mon 10/5/09 Mon 10/12/09 E 0 6.99 days 35 nos. 0.1 608.53

1379 1.14.4.3.1.2 Installation - Socket / Welding Outlet Thu 9/24/09 Sun 9/27/09 0 3.23 days 0.07 434.471380 1.14.4.3.1.2.1 Rigid Steel Conduit Thu 9/24/09 Thu 9/24/09 E 0 0.84 days 15 mtr 0.01 78.35

1381 1.14.4.3.1.2.2 Single Core Wires Thu 9/24/09 Sat 9/26/09 E 0 1.08 days 50 mtr 0.01 80.59

1382 1.14.4.3.1.2.3 Junction Box Sat 9/26/09 Sun 9/27/09 E 0 0.5 days 2 nos. 0 23.98

1383 1.14.4.3.1.2.4 Welding outlet / Socket Outlet Sun 9/27/09 Sun 9/27/09 E 0 0.29 days 2 nos. 0 27.05

1384 1.14.4.3.1.2.5 Socket Feeder cables Sun 9/27/09 Sun 9/27/09 E 0 0.52 days 60 mtr 0.04 224.5

1385 1.14.4.3.1.3 Installation - Local Junction Box Thu 9/24/09 Wed 10/28/09 0 38.15 days 0.95 5999.291386 1.14.4.3.1.3.1 Rigid Steel Conduit Thu 9/24/09 Thu 10/1/09 E 0 7.62 days 140 mtr 0.12 744.6

1387 1.14.4.3.1.3.2 Junction Box Thu 10/1/09 Sun 10/4/09 E 0 3.81 days 28 nos. 0.06 372.3

1388 1.14.4.3.1.3.3 Feeder cables Sun 10/4/09 Mon 10/12/09 E 0 8.72 days 1020 mtr 0.53 3358.01

1389 1.14.4.3.1.3.4 Cable Termination Mon 10/12/09 Wed 10/28/09 E 0 18 days 88 nos. 0.24 1524.38

1390 1.14.4.3.2 Air Compressed System - Piping Thu 9/24/09 Tue 9/29/09 0 6 days 0.05 333.131391 1.14.4.3.2.1 2" Equal Tee Thu 9/24/09 Mon 9/28/09 P 0 4 days 11 nos 0.03 213.2

1392 1.14.4.3.2.2 2" Plug Sat 9/26/09 Sun 9/27/09 P 0 1 day 9 nos 0.01 79.95

1393 1.14.4.3.2.3 1/2" Ball valve Mon 9/28/09 Tue 9/29/09 P 0 1 day 2 nos 0 10.66

1394 1.14.4.3.2.4 2" x 1" Reducer Mon 9/28/09 Tue 9/29/09 P 0 1 day 2 nos 0 10.66

1395 1.14.4.3.2.5 1" x 1/2" Reducer Mon 9/28/09 Tue 9/29/09 P 0 1 day 2 nos 0 10.66

1396 1.14.4.3.2.6 1/2" Nipple Tue 9/29/09 Tue 9/29/09 P 0 1 day 2 nos 0 8

9/24Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2009

Task

Baseline Task 2

Critical

Split

Progress

Milestone

Baseline Milestone 1

Summary

Baseline Summary 1

Rev. : 02Date : 2009/Feb./15 QATALUM C-005 MPEI - Reduction Area Plan

Page 24 Of 24

Project: C005 without subtotalDate: Tue 3/31/09