73
ECED June 2019 Demolition of iconic (ikonicky) structures at Sellafield Bruce Wilson Head of Projects Beta Gamma Remediation

ECED June 2019

  • Upload
    others

  • View
    9

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ECED June 2019

ECED June 2019

Demolition of iconic (ikonicky) structures at Sellafield

Bruce Wilson

Head of ProjectsBeta Gamma Remediation

Page 2: ECED June 2019

Contents

1. Remediation Value Stream

2. Pile 1 Chimney

3. First Generation Reprocessing Plant

Stack Demolition

2

Page 3: ECED June 2019
Page 4: ECED June 2019

Sellafield

Page 5: ECED June 2019

Headlines

• > £2Bn annual spend

• 7 Nuclear reactors

• 3 Reprocesing plants

• Thorp reprocessing

plant has completed it’s

mission

• Magnox reprocessing

plant closes 2020

• Transformation plan in

place

5

Page 6: ECED June 2019

Remediation Value Stream

• Remediation c. £150m

annual spend

• c. £40m/yr projects

• 5 key drivers:

– Risk reduction (nuclear)

– Risk reduction

(conventional)

– Land clearance for

major projects

– Reduction in care &

maintenance cost

– Skyline change – to

demonstrate progress!

6

Page 7: ECED June 2019

27 June 2019 7

Pile 1 Chimney Demolition

Page 9: ECED June 2019

Summary

Diffuser Start

Diffuser

Finish

Barrel Start

Barrel Finish

Page 10: ECED June 2019

Pile 1 Chimney Demolition Challenges

Construction

c.1949/50• Built over 60 years ago to

standards below current

requirements

•Increased contamination from

1957 fire

•Large quantity of concrete to

remove from circa 120 metres

•Close to ageing legacy

buildings

Page 11: ECED June 2019

Pile 1 Chimney Demolition

• Pile 1 Chimney Filter Gallery demolition

completed.

• Over 700te of concrete, brick and steel

disposed of

•158m tall tower crane installed to lower

concrete blocks to ground

• 3500 tonnes of structural steel and concrete

to be demolished.

•Removal of structure in block form using

diamond wire cutting

• Project timeline Dec 2016 to June 2028

Page 12: ECED June 2019

Block Removal

Page 13: ECED June 2019
Page 14: ECED June 2019

Blocks 46 & 47 ready for final cut

Page 15: ECED June 2019

Rows A-C removed c. 330te concrete & 3m height

Page 16: ECED June 2019

16

Page 17: ECED June 2019

17

Page 18: ECED June 2019

18

Page 19: ECED June 2019

Barrel demolition concept

• Driver is skyline

change and care

& maintenance

cost, not risk

reduction

• Use crane to

construct platform

• Detailed Design

ongoing

• Planned direct

award to

incumbent DDP

partner

Page 20: ECED June 2019

20

Page 21: ECED June 2019

27 June 2019 21

First Generation Reprocessing Plant

Page 22: ECED June 2019

22

Page 23: ECED June 2019

• First Generation Reprocessing Plant (FGRP) Stack was constructed and commissioned in

the early 1950’s

• The FGRP Stack was an authorised gaseous aerial discharge outlet for a number of

operational and decommissioning buildings

• Standing 120m above ground the stack consisted of a reinforced concrete wind shield

with stainless steel flue liner.

• The stack structure did not meet modern structural standards.

• Consequence of a stack collapse was potential damage to a number of Nuclear Facilities.

• Key enablers for the demolition of the stack was the completion of the SAV project

First Generation Reprocessing Plant (FGRP) Stack

Page 24: ECED June 2019

Stack Demolition - 2 Part SolutionPart 1 - SAV

• Part 1 - The key enabler for Stack

Demolition is the transfer of operations to

a new ventilation discharge stack facility

and associated systems

• The SAV Facility took over ventilation

operations in Aug 2016

Page 25: ECED June 2019

• Nuvia LTD - main contractors & demolition experts.

• Delta International – Sub Contactors – Steeplejack Experts and

SCP operators.

• Alimak – site access specialists

• A 3 tier Self Climbing Platform (SCP) is to be utilised to ascend to

the top of the Stack.

• The SCP is supported by 3 friction bands (2off restraining bands

1off lifting band) which holds it in position on the stack.

Stack Demolition - 2 Part SolutionPart 2 - SCP

Page 26: ECED June 2019

26

SCP Climbing methodology

Lifting Band

Upper Restraining

Band

URB

Lower Restraining

Band

LRB

Lifting band

Tightened to

stack face

Lifting band

lifted to

required height

of move

URB loosened

LRB loosened

U&LRB lifted

with the SCP

URB tightened

Lifting band

loosened ready for

next move

LRB tightened

Page 27: ECED June 2019

Stack Demolition – timeline

• SCP ascent completed December 17

• Demolition in progress

• 7 day cycle

• Drilling 2 days

• Bursting

• Decontam

• Plasma cutting

• Prep day

• Move day

• Category A Hazard Retirement Point

(47m) June 2018 - COMPLETED

• Demolition Forecast Complete Nov

2019

• Project Closure Forecast Complete

Apr 2020

Page 28: ECED June 2019

28

• Approximately 640 tonnes of Very Low Level, Non Hazardous waste

concrete will be removed from the stack and disposed off within the

Sellafield boundary (CLESA)

• Approximately 25 tonnes of stainless steel waste will be removed from

the flue. Radiological monitoring will be carried out when steel

becomes accessible and waste disposed appropriately

Demolition

Page 29: ECED June 2019
Page 30: ECED June 2019
Page 31: ECED June 2019
Page 32: ECED June 2019
Page 33: ECED June 2019
Page 34: ECED June 2019
Page 35: ECED June 2019
Page 36: ECED June 2019
Page 37: ECED June 2019
Page 38: ECED June 2019
Page 39: ECED June 2019
Page 40: ECED June 2019
Page 41: ECED June 2019
Page 42: ECED June 2019
Page 43: ECED June 2019
Page 44: ECED June 2019
Page 45: ECED June 2019
Page 46: ECED June 2019
Page 47: ECED June 2019
Page 48: ECED June 2019
Page 49: ECED June 2019
Page 50: ECED June 2019
Page 51: ECED June 2019
Page 52: ECED June 2019
Page 53: ECED June 2019
Page 54: ECED June 2019
Page 55: ECED June 2019
Page 56: ECED June 2019
Page 57: ECED June 2019
Page 58: ECED June 2019
Page 59: ECED June 2019
Page 60: ECED June 2019
Page 61: ECED June 2019
Page 62: ECED June 2019
Page 63: ECED June 2019
Page 64: ECED June 2019
Page 65: ECED June 2019
Page 66: ECED June 2019
Page 67: ECED June 2019
Page 68: ECED June 2019
Page 69: ECED June 2019
Page 70: ECED June 2019
Page 71: ECED June 2019
Page 72: ECED June 2019

72

Current status• The stack height has been reduced by 43 metres

Page 73: ECED June 2019

Thank you & any questions?