ECE 5377 / 6377 Power Transmission and Distribution Project

Embed Size (px)

Citation preview

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    1/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    2/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    3/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    4/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    5/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    6/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    7/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    8/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    9/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    10/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    11/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    12/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    13/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    14/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    15/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    16/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    17/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    18/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    19/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    20/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    21/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    22/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    23/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    24/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    25/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    26/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    27/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    28/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    29/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    30/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    31/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    32/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    33/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    34/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    35/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    36/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    37/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    38/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    39/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    40/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    41/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    42/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    43/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    44/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    45/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    46/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    47/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    48/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    49/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    50/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    51/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    52/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    53/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    54/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    55/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    56/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    57/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    58/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    59/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    60/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    61/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    62/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    63/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    64/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    65/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    66/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    67/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    68/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    69/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    70/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    71/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    72/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    73/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    74/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    75/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    76/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    77/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    78/241

    What follows Refers to the Guide for the Project Task # 1:

    1. (Almost identical with the first paragraph on the Guide, page4)

    As it was specified on the Project Objective, power plants canbe built at sites A and C, with an upper limit on the active powersupplied from site C of 200 /MW/. How it is shown on the ProjectSolution, for the solved case it came out that the best version isthat one with a power plant at C (along with that one at A). But donot understand from here that also you must have a power plant atC. Your data are not the same with data given on the ProjectSolution. It means that it is possible that in your case, byconsidering technical and economical factors, to result that the bestversion is without a power plant at C.

    2. (Almost identical with the second paragraph on the Guide,page 4)

    How it is stated on the Project Tasks, page 4, item 1, the loadmust be supplied 100% just if one component of the new powersystem section is out of service. Such, do not forget to check that

    just when a generating unit, or a transformer unit, or a lines circuitis out of service, what it is left on can carry the load, including activeand reactive power losses.

    3. (Identical with the third paragraph on the Guide, page 4)

    For the network components you have to check if eachcomponent that is in operation can carry the maximum apparentpower that it must be carried.

    4. (A little different from the fourth paragraph of the Guide, page4, but read both, they are referred to the same topics)

    In defining the number, rated power and voltage of different systemcomponents, it must be estimated what value has the apparentpower that must be carried by each component of the system. For

    that reason, starting from the load side, the components loading isestimated.On the Project Solution the active and reactive powers lost havebeen defined in a more exact way. Here it is suggested a verysimple way to estimate the powers lost, and then the apparentpower at the sending end of an equivalent network component (hereby the equivalent network component it is understood the

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    79/241

    equivalent of the same type components parallel connected).Lets assume that the loads total active power consumed is 1,000/MW/ and, since the total active power lost is estimated to be 5%, itresults that the total active power lost is 50 /MW/. Lets assumethat for the configuration in discussion there are three powersubstations and four transmission lines that is a total of sevenequivalent network components. Then, as a simple estimation, itwill stated that each equivalent network component has an activepower lost of (50/7) = 7.14 /MW/.Similarly, starting with the loads total reactive power consumed andwith the percent of total reactive power lost (estimated as being10%), it is estimated the reactive power lost per equivalent networkcomponent.

    Having both active and reactive powers lost for each equivalentnetwork component, and also the active and reactive power at thereceiving end of the equivalent component, now it can be estimated

    the active and reactive, and then the apparent powers at the sendingend of each equivalent network component.

    (Take care, on the Guide, page 4, fourth row, the correct apparentpower should be 1068.27 /MW/, not 1187.94 /MW/)

    5. (Identical with the first distinct paragraph on the Guide, page4)

    Again, as it was already stated, for units that are to operate inparallel (as generating units in a power plant, transformer units in apower substation, lines circuits for a line), it is very probable thatthe investment cost is lower as the number of these units is lowerand the corresponding units size and their rated/carrying capabilitypower is higher. But at the same time the supplementaryinvestment cost for the back-up units is higher. Such it must beseen how this cost is compared with the cost of more units inparallel, each of a lower rated power.

    6. (Almost identical with the second distinct paragraph on theGuide, page 4)

    On the above decision also it must be counted the circuit flexibility

    and responsiveness to the actual loading.

    Lets assume that for a power substation it is known that theannual peak load is 200 /MVA/, and the annual minimum load is 100/MVA/.

    Version # 1: Lets assume that, offering a lower cost, it isdecided to install there only two transformer units, each of

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    80/241

    200 /MVA/ rated power. At the first view, for the peak load itlooks ok. But for the minimum loading the first temptationwill be to have in operation only one transformer, which canhandle that power. But that it is forbidden. If for somereasons that single transformer goes out of service theconnection through that power substation is interrupted.Always it must be at least two transformers in operation.That is, now at the minimum loading, each transformer isloaded with 50 /MVA/, that is 25% of its rated power, andthis is not an economical operation.

    Also it must be counted that periodically units must go into amaintenance process. If on the above power substation thereare installed only two transformers, and since the operationcannot remain with only one transformer, it means that notransformer can go out for a maintenance schedule, which ofcourse cannot be accepted.

    Version # 2: Now lets assume that for the same power

    substation it is decided to have installed three transformers,each of a 100 /MVA/ rated power (if one unit is out, the othertwo can carry 200 /MVA/). For the minimum loading of 100/MVA/, it can remain in operation only two transformers,each being loaded with 50 /MVA/, which represents 50% ofits rated loading.

    Now it is clear that there is a more economical loading thanbefore. Also transformers can be scheduled for maintenanceone by one with no problem. And just if one transformer ofthose two operating at minimum loading is going out ofservice, still it can be transferred 100 /MVA/ through thepower station. Such, just if this version results with highercost than the cost of Version # 1, this version must beselected.

    7. (Identical with the last paragraph on the Guide, page 4)

    The same judgment must be applied for generating units orlines circuits that are operating in parallel.

    8. What follows is related to Fig. B7-1, page B-129:

    Since the Line Loading in SIL curve was defined for an extra-highvoltage line, for a shorter lower voltage line the curve data must beadjusted.

    Such the curve will be used for defining the Line Loading in SIL asfunction of the line length, but if it is coming out a multiple of SIL

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    81/241

    higher than 1.5, it will selected 1.5, not higher.

    What follows Refers to the Guide for the Project Task # 2:

    Page 5:---------

    1. Take care, after you define the minimum needed cross section areafor conductor, from Table A.1. you have to select the correspondingconductor that it is available. If you do not find a conductor thatsatisfy exactly the calculated needed cross section, then you haveto selected the immediate next available conductor that has a crosssection higher that the minimum cross section area calculated.

    Page 6, items 2.4 and 2.5:----------------------------------

    2. For the parallel identical circuits installed on the same tower it mustbe defined parameters and build the corresponding sequenceequivalent circuits (for positive = negative and for zero sequences)for when only one circuit is in operation, and for when all circuitsinstalled on that tower are in operation.

    3. If between terminal X and terminal Y there are parallel circuitsinstalled on more than one tower, then circuits installed on onetower define a line. Such, between terminal X and terminal Y will bemore parallel lines.For each of these lines it must be done what it is stated on the item2 above.Also, it must be calculated and built the corresponding sequenceequivalent circuits when all parallel lines between terminals X and Yare in operation.

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    82/241

    What follows Refers to the Guide for the Project Task # 3:

    Page 2, item 3.2:---------------------

    1. For identical transformers parallel connected between two terminalsX and Y it must be calculated parameters and build thecorresponding sequence equivalent circuits (for positive=negativeand for zero sequences) for when only one transformer is inoperation and for when all identical parallel transformers are inoperation.

    2. If between two terminals X and Y there are connected transformersof different characteristics, then for the set of transformers ofidentical characteristics it is applied what it is stated on the aboveitem 1

    Finally, it must be defined parameters and build the correspondingsequence equivalent circuits when all transformers parallelconnected between terminals X and Y are in operation.

    What follows Refers to the Guide for the Project Task # 4:

    Page 1, item 4.2:---------------------

    On the equivalent circuits the series parameters to be defined andshownas impedances components (R and jX), and the shunt parameters tobe defined and shown as admittance components (G and jB)

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    83/241

    What follows Refers to the Guide for the Project Task # 5:

    Page 2:----------

    Here it is given another equation for defining the circuits current

    Im, as(take care, on what follows all complex quantities, that are phasors,impedances, admittances, and the complex power are shown with

    larger size letters),

    Sn*Im = (1+ ZmnYm0) x --- + (Ym0+ Yn0+ Zmnx Ym0x Yn0)x Vn

    Vn*

    What follows Refers to the Guide for the Project Task # 7:

    Page 1, item 7.1:---------------------

    The generating units parameters are selected as the average valueof the range shown on Table A.4, Task # 3.

    Page 1, item 7.2:---------------------

    When the load parameters are calculated, to be considered thatnow by load it is understood the actual load and, where it the case,the shunt reactive compensation used for that load.

    The reactive compensating devices are considered as passivecomponents Y connected and with the neutral grounded.

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    84/241

    Page 2, item 7.3:---------------------

    Take care that, when the zero sequence impedance diagram is built itmust be counted the transformers winding connection, and that thisfact will decide which power system components will participate inthe zero sequence impedance diagram.

    What follows Refers to the Project Solution

    Page 41:-----------

    The sentence to be read as: In the following it will be definedparameters for when one or for when both circuits are in operation.

    Page 61:-----------

    On the second paragraph it is stated that To satisfy this constraint,analytically it was found that .

    Since you are not yet ready to solve this case analytically, you haveto solve the case by trying.

    Page 101:------------

    As it can be seen on Figure 8.4, the series parameters of each circuitof line AB are equal to two times (X = 0068 /pu/) parameters forboth circuits of line AB in operation (see Figure 4.1, page 57, wherefor line AB, X = 0.034 /pu/).

    Since, just with the short circuit on to one of the circuits, bothcircuits are in operation, the shown procedure must be applied.

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    85/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    86/241

    O. Crisan, ECE 5377/6377

    Project Updated Specifications-----------------------------------------

    Spring 2012-----------------

    To the given Project Guide, the following changes apply:

    1. On the Section PROJECT OBJECTIVE, page 1, first paragraph, tobe read: to become operational on the year 2,016.

    2. On page 2 of the Section Given Data:

    - The data shown at item # 1 become:

    d1= (30 + 2 n) /km/; d2= (200 - 2 n) /km/; d3= (100 + 2.5 n)/km/.

    - The data shown at item # 2, become:

    PA = (20 + n) /MW/, PB = (250 + 2 n) /MW/,

    PC = (300 3 n) /MW/.

    - Item # 4, first paragraph, becomes:

    Load Curves for that day of the year 2016

    - For the figure on page # 3 the title becomes:

    Daily load curves, (2,016 2,025),

    3. On the Section Project Tasks:

    - Page # 4, Item # 1, second paragraph, to be read:

    - Along a 10 years period, starting with year 2,016 andending with year 2,025, .

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    87/241

    O. Crisan, ECE 5377/6377

    - 2 -

    - Page 5, Item # 5, the shown table: on the table head, line Year,to

    be read:

    | 2,016 | 2,017 | |2,025|

    - Page 6, Item # 8, second phrase, it would be read as:

    For the section of the power system composed of the higher

    voltage side bus of the step-up power substation at side A, and thetransmission line AB, design the primary and back-up protectionsystems.

    4. General Comments: On the Sections Guide for the Project Task # 1, ,

    8, and on the Section PROJECT SOLUTION, every time whenyears

    are involved, it must be understood that now, along the designinterval the

    first year is 2,016, and the last year is 2,025!

    5. When defining the line parameters, for the return path resistance in the ground (see PROJECT SOLUTION, page 34), instead of 0.05

    //km/, to

    be considered Rgu= 0.06 //km/!!!! Also, for the equivalent distanceto the

    ground, instead of 1000 /m/ (see the same section, page 37) to beconsidered

    as Deq.cg

    = 850 /m/!!!!!!

    6. The Tasks Time-Schedule becomes:

    Task #: Due Date (Along Year 2012):

    1 Wednesday, February 15

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    88/241

    2 Wednesday, February 293 Monday, March 194 Monday, March 195 Monday, April 26 Monday, April 27 Monday, April 168 Monday, April 30

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    89/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    90/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    91/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    92/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    93/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    94/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    95/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    96/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    97/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    98/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    99/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    100/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    101/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    102/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    103/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    104/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    105/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    106/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    107/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    108/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    109/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    110/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    111/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    112/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    113/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    114/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    115/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    116/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    117/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    118/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    119/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    120/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    121/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    122/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    123/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    124/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    125/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    126/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    127/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    128/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    129/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    130/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    131/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    132/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    133/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    134/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    135/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    136/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    137/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    138/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    139/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    140/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    141/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    142/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    143/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    144/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    145/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    146/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    147/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    148/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    149/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    150/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    151/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    152/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    153/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    154/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    155/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    156/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    157/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    158/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    159/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    160/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    161/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    162/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    163/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    164/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    165/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    166/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    167/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    168/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    169/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    170/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    171/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    172/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    173/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    174/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    175/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    176/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    177/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    178/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    179/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    180/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    181/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    182/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    183/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    184/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    185/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    186/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    187/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    188/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    189/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    190/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    191/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    192/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    193/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    194/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    195/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    196/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    197/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    198/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    199/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    200/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    201/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    202/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    203/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    204/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    205/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    206/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    207/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    208/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    209/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    210/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    211/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    212/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    213/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    214/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    215/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    216/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    217/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    218/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    219/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    220/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    221/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    222/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    223/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    224/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    225/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    226/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    227/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    228/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    229/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    230/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    231/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    232/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    233/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    234/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    235/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    236/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    237/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    238/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    239/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    240/241

  • 7/25/2019 ECE 5377 / 6377 Power Transmission and Distribution Project

    241/241