Upload
zoe-osborne
View
220
Download
1
Tags:
Embed Size (px)
Citation preview
ECE 476 Power System Analysis
Lecture 15: Power Flow Sensitivities, Economic Dispatch
Prof. Tom Overbye
Dept. of Electrical and Computer Engineering
University of Illinois at Urbana-Champaign
Announcements
• Read Chapter 6, Chapter 12.4 and 12.5 • HW 7 is 6.50, 6.52, 6.59, 12.20, 12.26; due October
22 in class (no quiz)
2
Balancing Authority Areas
• An balancing authority area (use to be called operating areas) has traditionally represented the portion of the interconnected electric grid operated by a single utility
• Transmission lines that join two areas are known as tie-lines.
• The net power out of an area is the sum of the flow on its tie-lines.
• The flow out of an area is equal to
total gen - total load - total losses = tie-flow 3
Area Control Error (ACE)
• The area control error (ace) is the difference between the actual flow out of an area and the scheduled flow, plus a frequency component
• Ideally the ACE should always be zero.• Because the load is constantly changing,
each utility must constantly change its generation to “chase” the ACE.
int schedace 10P P f
4
Automatic Generation Control
• Most utilities use automatic generation control (AGC) to automatically change their generation to keep their ACE close to zero.
• Usually the utility control center calculates ACE based upon tie-line flows; then the AGC module sends control signals out to the generators every couple seconds.
5
Power Transactions
• Power transactions are contracts between generators and loads to do power transactions.
• Contracts can be for any amount of time at any price for any amount of power.
• Scheduled power transactions are implemented by modifying the value of Psched used in the ACE calculation
6
PTDFs
• Power transfer distribution factors (PTDFs) show the linear impact of a transfer of power.
• PTDFs calculated using the fast decoupled power flow B matrix
1 ( )
Once we know we can derive the change in
the transmission line flows
Except now we modify several elements in ( ),
in portion to how the specified generators would
participate in the pow
θ B P x
θ
P x
er transfer7
Nine Bus PTDF Example
10%
60%
55%
64%
57%
11%
74%
24%
32%
A
G
B
C
D
E
I
F
H
300.0 MW 400.0 MW 300.0 MW
250.0 MW
250.0 MW
200.0 MW
250.0 MW
150.0 MW
150.0 MW
44%
71%
0.00 deg
71.1 MW
92%
Figure shows initial flows for a nine bus power system
8
Nine Bus PTDF Example, cont'd
43%
57% 13%
35%
20%
10%
2%
34%
34%
32%
A
G
B
C
D
E
I
F
H
300.0 MW 400.0 MW 300.0 MW
250.0 MW
250.0 MW
200.0 MW
250.0 MW
150.0 MW
150.0 MW
34%
30%
0.00 deg
71.1 MW
Figure now shows percentage PTDF flows from A to I
9
Nine Bus PTDF Example, cont'd
6%
6% 12%
61%
12%
6%
19%
21%
21%
A
G
B
C
D
E
I
F
H
300.0 MW 400.0 MW 300.0 MW
250.0 MW
250.0 MW
200.0 MW
250.0 MW
150.0 MW
150.0 MW
20%
18%
0.00 deg
71.1 MW
Figure now shows percentage PTDF flows from G to F
10
WE to TVA PTDFs
11
Line Outage Distribution Factors (LODFS)
• LODFs are used to approximate the change in the flow on one line caused by the outage of a second line– typically they are only used to determine the change in
the MW flow– LODFs are used extensively in real-time operations– LODFs are state-independent but do dependent on the
assumed network topology
,l l k kP LODF P
12
Flowgates
• The real-time loading of the power grid is accessed via “flowgates”
• A flowgate “flow” is the real power flow on one or more transmission element for either base case conditions or a single contingency– contingent flows are determined using LODFs
• Flowgates are used as proxies for other types of limits, such as voltage or stability limits
13
NERC Regional Reliability Councils
NERCis theNorthAmericanElectricReliabilityCouncil
Image: http://www.nerc.com/AboutNERC/keyplayers/Documents/NERC_Regions_Color.jpg 14
NERC Reliability Coordinators
Image: www.nerc.com/pa/rrm/TLR/Pages/Reliability-Coordinators.aspx 15
Generation Dispatch
• Since the load is variable and there must be enough generation to meet the load, almost always there is more generation capacity available than load
• Optimally determining which generators to use can be a complicated task due to many different constraints– For generators with low or no cost fuel (e.g., wind and solar
PV) it is “use it or lose it”– For others like hydro there may be limited energy for the year – Some fossil has shut down and start times of many hours
• Economic dispatch looks at the best way to instantaneously dispatch the generation
16
Generator types
• Traditionally utilities have had three broad groups of generators– baseload units: large coal/nuclear; always on at max.– midload units: smaller coal that cycle on/off daily– peaker units: combustion turbines used only for several
hours during periods of high demandWind and solarPV can be quite variable;usually they areoperated at max.available power
17
Example California Wind Output
Source: www.megawattsf.com/gridstorage/gridstorage.htm
18
Image shows wind output for a month by hour and day
Thermal versus Hydro Generation
• The two main types of generating units are thermal and hydro, with wind rapidly growing
• For hydro the fuel (water) is free but there may be many constraints on operation– fixed amounts of water available– reservoir levels must be managed and coordinated– downstream flow rates for fish and navigation
• Hydro optimization is typically longer term (many months or years)
• In 476 we will concentrate on thermal units and some wind, looking at short-term optimization
19
Block Diagram of Thermal Unit
To optimize generation costs we need to develop
cost relationships between net power out and operating
costs. Between 2-6% of power is used within the
generating plant; this is known as the auxiliary power20
Modern Coal Plant
Source: Masters, Renewable and Efficient Electric Power Systems, 200421
Turbine for Nuclear Power Plant
Source: http://images.pennnet.com/articles/pe/cap/cap_gephoto.jpg22
Basic Gas Turbine
Compressor
Fuel100%
Fresh air
Combustion chamber
Turbine
Exhaustgases 67%
Generator
ACPower 33%
1150 oC
550 oC
Brayton Cycle: Working fluid is always a gas
Most common fuel is natural gas
Maximum Efficiency
550 2731 42%
1150 273
Typical efficiency is around 30 to 35%
23
Combined Cycle Power Plant
Efficiencies of up to 60% can be achieved, with even highervalues when the steam is used for heating. Fuel is usually natural gas
24
Generator Cost Curves
• Generator costs are typically represented by up to four different curves– input/output (I/O) curve– fuel-cost curve– heat-rate curve– incremental cost curve
• For reference– 1 Btu (British thermal unit) = 1054 J– 1 MBtu = 1x106 Btu– 1 MBtu = 0.293 MWh– 3.41 Mbtu = 1 MWh
25
I/O Curve
• The IO curve plots fuel input (in MBtu/hr) versus net MW output.
26
Fuel-cost Curve
• The fuel-cost curve is the I/O curve scaled by fuel cost. A typical cost for coal is $ 1.70/Mbtu.
27
Heat-rate Curve
• Plots the average number of MBtu/hr of fuel input needed per MW of output.
• Heat-rate curve is the I/O curve scaled by MW
Best for most efficient units are
around 9.0
28
Incremental (Marginal) cost Curve
• Plots the incremental $/MWh as a function of MW.• Found by differentiating the cost curve
29
Mathematical Formulation of Costs
• Generator cost curves are usually not smooth. However the curves can usually be adequately approximated using piece-wise smooth, functions.
• Two representations predominate– quadratic or cubic functions– piecewise linear functions
• In 476 we'll assume a quadratic presentation
2( ) $/hr (fuel-cost)
( )( ) 2 $/MWh
i Gi i Gi Gi
i Gii Gi Gi
Gi
C P P P
dC PIC P P
dP
30
Coal Usage Example 1
• A 500 MW (net) generator is 35% efficient. It is being supplied with Western grade coal, which costs $1.70 per MBtu and has 9000 Btu per pound. What is the coal usage in lbs/hr? What is the cost?
At 35% efficiency required fuel input per hour is
500 MWh 1428 MWh 1 MBtu 4924 MBtuhr 0.35 hr 0.29 MWh hr
4924 MBtu 1 lb 547,111 lbshr 0.009MBtu hr
4924 MBtu $1.70Cost = 8370.8 $/hr or $16.74/MWh
hr MBtu
31
Coal Usage Example 2
• Assume a 100W lamp is left on by mistake for 8 hours, and that the electricity is supplied by the previous coal plant and that transmission/distribution losses are 20%. How coal has been used?
With 20% losses, a 100W load on for 8 hrs requires
1 kWh of energy. With 35% gen. efficiency this requires
1 kWh 1 MWh 1 MBtu 1 lb1.09 lb
0.35 1000 kWh 0.29 MWh 0.009MBtu
32
Incremental Cost Example
21 1 1 1
22 2 2 2
1 11 1 1
1
2 22 2 2
2
For a two generator system assume
( ) 1000 20 0.01 $ /
( ) 400 15 0.03 $ /
Then
( )( ) 20 0.02 $/MWh
( )( ) 15 0.06 $/MWh
G G G
G G G
GG G
G
GG G
G
C P P P hr
C P P P hr
dC PIC P P
dP
dC PIC P P
dP
33
Incremental Cost Example, cont'd
G1 G2
21
22
1
2
If P 250 MW and P 150 MW Then
(250) 1000 20 250 0.01 250 $ 6625/hr
(150) 400 15 150 0.03 150 $6025/hr
Then
(250) 20 0.02 250 $ 25/MWh
(150) 15 0.06 150 $ 24/MWh
C
C
IC
IC
34
Economic Dispatch: Formulation
• The goal of economic dispatch is to determine the generation dispatch that minimizes the instantaneous operating cost, subject to the constraint that total generation = total load + losses
T1
m
i=1
Minimize C ( )
Such that
m
i Gii
Gi D Losses
C P
P P P
Initially we'll ignore generatorlimits and thelosses
35
Unconstrained Minimization
• This is a minimization problem with a single inequality constraint
• For an unconstrained minimization a necessary (but not sufficient) condition for a minimum is the gradient of the function must be zero,
• The gradient generalizes the first derivative for multi-variable problems:
1 2
( ) ( ) ( )( ) , , ,
nx x x
f x f x f xf x
( ) f x 0
36
Minimization with Equality Constraint
• When the minimization is constrained with an equality constraint we can solve the problem using the method of Lagrange Multipliers
• Key idea is to modify a constrained minimization problem to be an unconstrained problem
That is, for the general problem
minimize ( ) s.t. ( )
We define the Lagrangian L( , ) ( ) ( )
Then a necessary condition for a minimum is the
L ( , ) 0 and L ( , ) 0
T
x λ
f x g x 0
x λ f x λ g x
x λ x λ37
Economic Dispatch Lagrangian
G1 1
G
For the economic dispatch we have a minimization
constrained with a single equality constraint
L( , ) ( ) ( ) (no losses)
The necessary conditions for a minimum are
L( , )
m m
i Gi D Gii i
Gi
C P P P
dCP
P
P
1
( )0 (for i 1 to m)
0
i Gi
Gi
m
D Gii
PdP
P P
38
Economic Dispatch Example
D 1 2
21 1 1 1
22 2 2 2
1 1
1
What is economic dispatch for a two generator
system P 500 MW and
( ) 1000 20 0.01 $/
( ) 400 15 0.03 $/
Using the Largrange multiplier method we know
( )20 0
G G
G G G
G G G
G
G
P P
C P P P hr
C P P P hr
dC PdP
1
2 22
2
1 2
.02 0
( )15 0.06 0
500 0
G
GG
G
G G
P
dC PP
dP
P P
39
Economic Dispatch Example, cont’d
1
2
1 2
1
2
1
2
We therefore need to solve three linear equations
20 0.02 0
15 0.06 0
500 0
0.02 0 1 20
0 0.06 1 15
1 1 500
312.5 MW
187.5 MW
26.2 $/MWh
G
G
G G
G
G
G
G
P
P
P P
P
P
P
P
40