Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
RuralE.Evolution
Deliverable D 4.1. “Implementation of the
provisional methodology in each target area ”
RuralE.Evolution
Public-Private Partnerships for RES Agro-energy districts
Issued by: HANGYA
DATE: July 2010
CONTRACT N°:IEE/07/579/SI2.499063
1
Content
1. Introduction 3
2. General remarks arising during implementation 4
3. Common and specific features of implementation 7
4. Reports on the implementation in each target area 10
Greek case study 11
Hungarian case study 21
Italian case study 29
Portuguese case study 35
Spanish case study 40
5. Annex (Questionnaire to the implementation of provisional
methodology in each target area) 45
Summary of answers to questionnaire 49
2
Introduction
The main objective of the Work Package (WP) 4 is to test the soundness of the provisional
methodology, giving concrete applications in each target area. For this purpose all partners
between months 12-20 will implement, step by step, their specific provisional methodology
described in the guidelines for the application of PPP schemes to agro-energy districts
resulting from WP2, applying options emerging from WP3 (pre-feasibility).
The pre-feasibility studies elaborated evaluate the proper combination of elements, able to
comply with target area characteristics and needs. This process has to finalize the main frame
of potential partnership amongst local public authorities, agricultural SMEs, associations of
entrepreneurs and financial institutions as well. This frame helps to draw up the potential PPP
contract scheme as a precondition for the signature of the Memoranda of Understanding by all
interested partners.
According to the Annex 1 of the project contract at the beginning of WP4 each partner has
already collected necessary information and elements to put into practice the provisional
methodology. The focus will be switched on the concept of “Bio-energy chain” or “Agro-
energy chain”.
The first step each national component will implement, is the definition of the actual Bio-
energy chain in the selected target areas. According to local characteristics, a proper chain
will be developed and identified actors belonging to this chain will be addressed.
The meetings and round-table discussion will result in high level of awareness related to the
advantages arising from the realization of agro-energy PPP projects. This process of
involvement, consultation and discussion with stakeholders will end with the identification of
commonly agreed schemes of PPP and Agro-energy districts between all future PPP partners.
3
General remarks arising during implementation
The project partners have very different positions, circumstances and experiences related to
PPP. As an excellent guidebook1 of good governance of PPP mentioned, countries tend to go
through a number of distinct phases before a PPP programme becomes fully operational. Most
countries are at a first stage where the development of actual projects is still numerically small.
Only at the third phase, where relatively few countries are currently situated, the programme
becomes significant. At this stage countries will have developed the required institutions, e.g. the
PPP unit, the capital markets as well as the know-how and expertise and can therefore turn their
attention to more sophisticated projects and financial arrangements. The maturity of the PPP
market in the different countries is characterized in the figure2 below.
Figure 1: Maturity of the PPP market
The figure clearly expresses that in the four “old “Member States, the general frame of PPP is
more developed, in comparison to Hungary as a “new” Member State. “Stage two” represents
that these countries:
- introduce legislative reforms
- publish policy and practice guidelines
- establish dedicated PPP units
1 edited by United Nations Economic Commission for Europe in 20082 source Deloitte and Touche USA LLP
4
- refine PPP delivery models
- continue to foster marketplace
- expand project pipeline and extend to new sectors
- leverage new sources of funds
The differences amongst administration of countries also cause different conditions mainly to
the public partners, based on the principle of subsidiarity giving more spaces to them in the
less centralized countries (Spain, Italy). The administrative differences also influence the legal
systems and because of compulsory legal act, related PPPs exists on EU level only to public
procurement and service concession, there are significant distinctions concerning the legal
conditions amongst the countries.
There are also significant differences amongst countries, concerning the attitude of financing
institutes related to PPP projects. (Sometimes this difference exits within one country as well,
like the relatively expensive credit causes low level of PPP in the south part of Italy.).
Therefore the clear risk-sharing one of the most important elements of planning and
implementation.
Although the present project focuses to the preparation activity of PPP, the final output
(contract amongst partners) requires considering and applying the principles of good
governance in PPPs. It means that during the adaptation of prefeasibility analysis and
preparing the contract it has to be found:
- a good balance amongst potential stakeholders,
- optimal technical solutions;
- such financial solution which provides sources both to the construction and to the
sustainable operation of investment.
Therefore the project partner during the implementation of project has to provide such
information and create such conditions to the local actors in which the general principles of
the good governance in PPP will show up, e.g.
- participation
- decency
- transparency
- accountability
- fairness
5
- efficiency
The prefeasibility analysis, as output of WP3 provides mainly technical and financial
proposals to the partners; therefore the complexity of PPPs requires creative contribution both
from the project partners and the local stakeholders during the implementation process.
6
Common and specific features of implementation
The characterization and the positioning of the implementation process has been drawn up
by the countries’ report and by a questionnaire. The reports providing the project partners
are in the next chapter, while the questionnaire is summarized in the Annex.
All partners reported a successful process of preparation, which makes probable the
contractual liaisons amongst the determinable local partners. At the same time, there are
significant differences related to readiness of the cases are significant differences.
The identification of the needs, commitment and motivations clearly underlined that the
main driving forces of this process are the local authorities and the farmers’ communities.
In Spain, the regional government represents the public need, in this project. At the same
time the ranking of partners’ interest dredged up that the individual farmers, except in
Greece and in Italy, have only slight motivation to participate in this improvement. The
problem also came up from the analysis of potential risks where in two countries
(Hungary and Portugal) the lack of safe supply is also mentioned. These facts underline
the further need to reach better conditions and higher awareness of the farmers, related to
biomass utilisation.
At the same time the environmental benefits were identified as main motivation in each
questionnaire. Similarly, high ranking motivations are the better utilisation of biomass and
the alternative income for farmers as well. The general economic advantages and job
creation are an important but less determinable motivation, according to the answers. The
decrease in external energy dependency, which can be a main object of “agro-energy
districts”, was checked on the list only in two questionnaires (Greece and Italy), although
in the Portuguese case the connection to the electric grid, with its difficulties, is an
important element.
The planned project is highly related to the political situation, according to the answers.
This risk is marked in all questionnaires: that is basically due to the determinable role of
local authorities as public partners; therefore, the feasibility of the planned activity tightly
coheres with the political stability of the regional, local authorities.
7
In the majority of the PPP schemes exist a fear of the unbalanced risks amongst partner.
Beyond this, the unbalanced financial power is presumable, because local authorities, due
to their attributes, have less financial and more political forces and the private partners are
in the opposite position. The changes in the economic situation and/or in the legal frame
(including the governmental incentitives as well), represent similarly high level of risk to
the actors.
Amongst the risk factors, fear from the unsafe supply has also to be mentioned, typically
in such cases when the farmers’ motivation and awareness is low.
The access to capital is also mentioned amongst the risky factors, namely in Portugal. At
the same time this risk generally exists in all countries where the financial institutes are
not well prepared to the PPP, or the general economic conditions are unfavourable to PPP.
It was mentioned by Portuguese partners also as risky factor the bureaucratic and limited
access to electric grid. This problem exists in each country and this is a serious limitation
to achieve the real agro-energy district.
According to the questionnaire during the adaptation of the prefeasibility study some
countries had some difficulties.
- In Greece, the feasibility study carried out in WP3, was expanded in order to have a
broader supply of biomasses, e.g. biomass from adjacent areas, that will be used in
addition to the pomegranate residues, and the energy produced will not be used only
for refrigeration purposes, but also to cover the energy needs of the Municipality and
to sell the excess to the national grid.
- In Hungary, the public partners (local authorities), due to the lack of database and
experiences both in alternative energy and PPP as well, overestimated their potential
abilities to utilize the biomasses locally during the WP3, and at the same time, the
regional power plant became more open to collaborate with them. These changes
provided a totally different system in comparison to the prefeasibility analysis of WP3.
- In Italy, the whole situation framework is regular; only a consideration related to the
new agronomical method to manage the pruning was mentioned, but it will take a few
resource to fit the concept with the project research.
8
- In Spain the expansion of the feasibility study carried out in WP3, was performed in
order to have an additional issue, involving new stakeholders (Province Government –
DIPCAS and a private investor).
Due to the above mentioned significant changes during this implementation phase, the
majority of the partners (except Greece and Italy, where within the project team are
strong scientific knowledge) needs additional information to help the decision of local
actors. This need includes different items, like technical, financial, legal and
environmental analysis and therefore this will be tasks of the local partners.
9
Country reports on the implementation in each target
area
- Greece
- Hungary
- Italy
- Portugal
- Spain
10
GREEK CASE STUDY
1. Identification of area’s needs (motivations, reasons)
Figure 2: Location of Prefecture of Kilkis in Greece
Kilkis Prefecture is located in Central Macedonia Region, in the northernmost part of Greece.
Its capital is the city of Kilkis. It includes 11 Municipalities & 1 independent community and
covers an area of 2,519 km2, with 86.086 inhabitants. The mountains near Kilkis are Paiko to
the west, parts of the western part of Kerkini to the northeast and Krousia to the east. Lake
Doirani is situated to the north and shares its eastern portion of the lake. Kilkis is bounded by
the prefectures of Serres to the east, Thessaloniki to the south, Pella to the west and the
international border of Greece with the Former Yugoslav Republic of Macedonia (Gevgelija
municipality) to the north.
The Prefecture of Kilkis has an agriculture-based economy with 45% of the active population
involved in the primary sector of the economy. Our main area of concern is the Municipality
of Evropos, where the “Tobacco Cooperative of Toumpa Kilkis” (TCTK) is based. TCTK was
founded in 1983 in order to organize and trade its members' production of eastern type
tobacco. Today it is the longest lived tobacco co-operative in Greece, which was established
as one of the leading co-operatives in production, processing and supply of Virginia variety of
tobacco.
However, following the adoption of total decoupling for the tobacco sector in Greece,
production fell by 80%. Only four processing plants remained operative in 2009 in the whole
11
country. Concerning employment, existing estimates suggest that the number of permanent
employees was reduced by 50%, whilst the number of seasonal workers has been reduced
from pre-reform levels of 7,000 to about 2,000.
Therefore, in 2006, almost all the members of TCTK abandoned the Virginia tobacco growing
and turned to the search and experimentation of other alternative cultivations. In this context
and evaluating the trends of the European and global market, they have initiated the plantation
of pomegranate trees. The production of pomegranate fruits in 2008 reached 4000-8000
tonnes and there are plans to increase the cultivated hectares within the next years and plant
even more different kind of trees.
This choice was seen as an opportunity to maintain farmers’ jobs and create a competitive
rural economy that will be independent from subsidies and will eventually lead to sustainable
agriculture and sustainable development of the Prefecture that currently possesses the last
place in the development indicators (GDP etc.), and has been also included in the list of Greek
areas with high risk of desertification due to intensive agriculture & soil degradation (Greek
National Committee for Combating Desertification).
Enhancing the effort for the development of the area, the Greek partners of the
RuralE.Evolution project decided to study the scenario of using the agricultural residues of
the area for the production of energy, that could potentially be used for the needs of the
Cooperative (refrigeration of the fruits and the extracted juices) and the local energy needs of
the Municipality of Evropos, selling the excessive energy produced to the national grid.
There seems to be a great potential for the use of the field crop residues. The general
treatment in Greece is either to incorporate them into the soil or burn them in the field. A part
is already exploited and used in several energy and non-energy markets, for example:
Cereal straw is used for various purposes such as animal feeding and animal bedding; in
some cases also used for heat production in greenhouses;_
There are no alternative markets for cotton, corn stalks and corncobs but difficulties in
harvesting and handling;
Olive pruning (especially the large stems) are used in stoves and chimneys for residential
heating.
12
2. Partners
2.1 Tobacco Cooperative of Toumpa Kilkis
Figure 3: Aerial photo of TCTK offices and storage rooms
As already mentioned, the Tobacco Co-operative of Toumpa Kilkis is the longest lived
tobacco co-operative in the country. In 1987, they moved on to full reconversion of the
tobacco growing by replacing the Kaba Kulak (classic) variety with the Virginia variety. At
the same time, they created and operated a unit of 180 dryers under the supervision of the Co-
operative's technical personnel. In 2005, the co-operative consisted of 180 members, with
4.500 quarter acres tobacco growing and a production of 1.348.000 kilos of Virginia variety
tobacco. In 2006, with the application of the new Common Rural Policy, almost all its
members abandoned the Virginia tobacco growing and turned to the search of alternative
growing. Today the Co-operative consists of 80 members.
Aiming to expand its members' plantations with high quality saplings at reasonable prices, the
Co-operative was immediately engaged in producing multiplicative pomegranate matter. At
the same time, and targeting the product's powerful and flexible access to the market,
members of the co-operative created the company "Rodonas" Ltd, which now activates in
every section of the production, processing, promotion and trading of pomegranate products
in the local and international market.
13
In cooperation with the company "Rodonas" Ltd, it supplies pomegranate plants to the co-
operative as well as to anyone interested, under the regime of Agriculture by Contract. Today,
over 150 producers, with over 2000 quarter acres of pomegranate trees around the country,
are contracted.
2.2 Municipality of Evropos
Figure 4: Characteristic ancient findings from the area
Evropos is the public authority in the target area that is motivated to participate in the agro-
energy PPP. Evropos is a municipality in the Paionia Province of Kilkis Prefecture in Central
Macedonia, with a population of 6,042 based on the 2001 census. The income of the majority
of the population is based on agricultural activities. The greatest advantage of the area is the
high percentage of irrigated land and the possibility to extend it with further land reclamation
works.
2.3 Company “Rodonas” (www.rodonas.gr)
Figure 5: The logo of the company and a pomegranate photo
One Private investor, an SME interested to share the entrepreneurial risk together with the
Municipality of Evropos is the company “Rodonas” Ltd that was created in 2006 by members
14
of the Tobacco Co-operative of Toumba of the Prefecture of Kilkis to reinforce the producers’
personal responsibility in all collective activities that have to do with production, processing
and trading of their products.
The company’s main guideline is a turn to products that are safe and beneficial (in addition to
their alimentary value) for the consumer’s health (functional food). Its goal is powerful and
flexible access of these products to the local and international market.
Today, in cooperation with the Tobacco Co-operative of Toumba Kilkis it activates in
pomegranate growing under the regime of Agriculture by Contract.
2.4 Other actors
The Aristotle University of Thessaloniki and the Tobacco Cooperative of Toumpa Kilkis
(Greek partners of the RuralEvolution project) still communicate with potential partners to
close the partnership, including actors of the supply chain, providers of technology etc. The
results of these negotiations will be announced in autumn 2010. For example, there are
ongoing negotiations with private companies that could provide the technical expertise for the
construction of the plant, like the company “PHILIPPOPOULOS ENERGY TECHNICAL
S.A.” that designs and constructs industrial units for the energy utilization of Biomass and
Solid Waste. The company has 35 years of specialist experience and already more than 100
installed projects.
The communication is ongoing to define the role of each partner in the partnership and it will
be finalized in autumn 2010.
However, the basic roles are distributed as follows:
The Tobacco Cooperative of Toumpa Kilkis will provide the land and invest in the
construction of the plant. It will motivate its members for the provision of biomass to the
plant.
The Municipality of Evropos will use the energy produced from the plant to cover the
electricity needs of its buildings.
The company “Rodonas” Ltd will provide raw material to the plant.
15
Round table meetings with all potential partners are continuous in order to define the exact
role of each partner and include more potential actors in the PPP scheme. The partners are all
located in the Municipality of Evropos, so their meetings are easily scheduled and carried out.
3. Description of potential PPP
The Tobacco Cooperative of Toumpa Kilkis (TCTK) plans to construct a plant in the
Municipality of Evropos in order to produce pomegranate juice. The PPP concept considers
the use of biomass residues from this plant (such as seeds and peels) as well as the use of
biomass residues from the adjacent areas cultivations for the production of energy. The
produced energy can be used for the following purposes:
(a) cool and preserve the fruit and fruit juice produced from pomegranates;
(b) heat/cool public buildings in the Municipality;
(c) sell the surplus energy to the National Public Power Corporation as energy from RES.
The energy plant that will be built within the framework of the PPP agro-energy district aims
to collect biomass residues from a maximum radius of 30km. Outside this distance is usually
not efficient to transfer the biomass.
Figure 6: Google earth map with Toumpa Kilkis in the middle and the potential areas (3
radius: 10km, 20km, 30km) that agricultural biomass could originate
16
Table 1: Public and private provision infrastructure
Public project Private project
Public-Private Partnership
Contract Type Public-sector
procurement
Franchise
(Affermage)
Design-Build
Finance-
Operate
(DBFO)3
Build-Transfer-
Operate (BTO)4
Build-Operate-
Transfer
(BOT)5
Build-Own-
Operate (BOO)
Construction Public Sector6 Public Sector (2) Private Sector Private Sector Private Sector Private Sector
Operation Public Sector7 Public Sector Private Sector Private Sector Private Sector Private Sector
Ownership8 Public Sector9 Public Sector Private Sector
Private Sector
during
construction,
then public
sector
Private Sector
during
construction,
then public
sector
Private Sector
Who pays? Public Sector Users
Public Sector
or users
Public Sector
or users
Public Sector
or users
Private Sector
offtaker10
Who is paid? n/a Private Sector Private Sector Private Sector Private Sector Private Sector
The Power Purchase Agreement (PPA), developed in the United States in the 1980s, provided
the template for modern PPP Contracts. PPAs began after the 1978 Private Utility Regulatory
Policy Act (PURPA), which encouraged the construction of cogeneration plants, whose
electricity could be sold to the regulated power utilities. PPAs arrived in Europe in the early
1990s, with the privatization of the British electricity industry; this encouraged the separation
between private-sector companies, involved in power generation and those involved in
distribution, and the development of independent power projects to increase competition in
power generation.
The PPA as first developed was a 'Build-Own-Operate' (BOO) contract between private-
sector parties, whereby the ownership of the power station remains with its investors. This
3 Also known as Design-Construct-Manage-Finance (DCMF) or Design-Build-Finance-Maintain (DBFM)4 Also known as Build-Transfer-Lease (BTL), Build-Lease-Operate-Transfer (BLOT) or Build-Lease-Transfer (BLT)5 Also known as Build-Own-Operate-Transfer (BOOT).6 Public sector normally designs the Facility and engages private sector contractors to carry out construction on its behalf (design-bid-built).7 Public sector may enter into service (outsourcing) contracts (for operation and maintenance) with private-sector contractors.8 In all cases, ownership may be in the form of a joint venture between the public and private sectors.9 Ownership may be through an independent publicly-owned Project Company, i.e. a 'Public-Public Partnership'.10 The BOO Contract form applies to PPPs in the minority of cases where ownership of the Facility does not revert to the Public Authority at the end of the PPP Contract.
17
PPP scheme will be used in the case of the agro-energy district in the Municipality of
Evropos. Table 1 provides a summary of the different ways of providing public infrastructure,
and shows how PPPs lie on the spectrum from wholly public-sector projects (and risk) to
wholly private sector projects. The selected PPP scheme has been highlighted.
Opportunities
1. The great advantage of the area is the availability of agro-forestry residues, due to the
extensive agricultural land. Zootechnical and food industry residues also exist for future
use;
2. Farmers want to get rid of the residues from their fields so it’s easy to collect them;
3. The Introduction of Law Ν.3389/2005 on PPP that concentrates all relevant aspects in one
coherent framework, has created a much more transparent frame that lowers the
hesitations of partners to enter partnerships;
4. The deregulation of the energy market of Greece facilitates the selling of electricity
produced by an agro-energy plant to the Public Power Corporation. The connection to the
PPC network is relatively easy.
Threats
1. The land is divided in small parts to many different "land owners-farmers“ and therefore
(a) a common initiative is absolutely necessary;
(b) there are many land owners & increased harvesting and transportation costs.
2. The road infrastructure requires improvement and expansion;
3. Opportunity cost of the residue (e.g. cereals straw has already a market price as it is sold
for animal feeding purposes);
4. Lack of commercial harvesting machinery for certain residue types (e.g. cotton residues).
4. List of information and communication activities during the
implementation. The Tobacco Cooperative of Toumpa Kilkis with the assistance of the Aristotle University of
Thessaloniki organized the 1st Local Initiative in Toumpa Kilkis (target area in Greece) in the
evening of 8th of May 2009. The event was hosted at the premises of the Municipality of
Evropos and managed to attract the interest of local stakeholders, entrepreneurs and farmers
on the implementation of agro-energy districts and the risks and opportunities related to their
potential involvement in a local Public-Private Partnership (PPP).
18
5. PPP scheme description
Table 2: PPP characteristics in Greece
PPP Key factors DescriptionPLANT PRIVATE
BIOMASS PRIVATEINCOME
SOURCESSELLING ELECTRICITY AND HEAT
In Figure 7, a PPP is shown: the Public Body is represented by the Municipality of Evropos,
that will be the user of the energy (heat/electricity) produced, the biomass will be furnished by
a private society, that is the cooperative of Toumpa Kilkis. The energy conversion plant will
be owned by the private investors and by the agricultural cooperative.
Figure 7: PPP scheme description for Greece
HUNGARIAN CASE STUDY
19
1. Identification of area’s needs (motivations, reasons)
The target area of this project is composed by 7 villages (see the map in Figure 8), about 85
km from Budapest in Northern Hungary, covering about 150 km2 with about 18.000
inhabitants. The main economic activity of this population is agri- and silviculture.
Figure 8: Hungary target area
The residues from the agri- and silvicultural activity (stalk, straw, cutting) represent
significant amount of energy (283765 GJ/year), which is utilised at this time locally without
any system. The increasing demands towards cheaper energy supply motivate the new and
more efficient utilisation of these materials.
According the initiative of Abasár local authority, the other 6 local communities are ready
to participate in a project by which agricultural residues (maybe later municipality wastes as
well) will be transformed into electric energy at the local power plant, partly supplying their
needs. Within the target area is located one of the significant actors in the national energy
20
supply, the Mátrai Hőerőmű (Mátra Power Plant) which is working with earth coal. The
power plant is ready to improve its activity, changing technology in one of its burning block,
to utilise also biomass from the target area. The electric energy will be sold to the national
grid and the biomass suppliers, the local authorities and the power plant will benefit of the
profit of this activity. There is also a potential alternative to built small (5-10-MW) power
plant(s) together to the Mátra Power Plant, improving the local energy supply.
2. PartnersThe potential public partners in this project are the 7 local authorities forming a
consortium. The leader of this consortium is the local authority of Abasár. The determinable
motivations of the local authorities related to the project are:
- creating job preparing raw materials for energy utilisation;
- helping local farmers and generally local people to improve their environment;
- a cleaner environment can help other activities (e.g. tourism, health care) in these villages;
- finding some solution supplying the public areas with cheaper energy (schools, institutes
of cultural and health services etc.).
At the same time the local authorities identified their limitations to create a local power plant
for own energy supply. The main limitations are:
- the financial resources (including the local authorities and private persons as well)
required to convert the system of energy supply.
- the legal frames, till 2010, save the monopoly situation of the regional energy (electric
energy, heat) suppliers and these barriers indirectly still exist.
With regard to the above mentioned circumstances, the local authorities changed their original
conception looking at such partners, which have interest in utilizing the locally produced
biomass to generate energy. The Mátra Power Plant, located in the target area, currently is
not a direct energy supplier of the region, because the electric energy it produces is sold via
the national network, and the waste heat energy is utilized to cover energy demands
respectively to the other companies located within the own industrial area of Power Plant. At
the same time, the environmental prescriptions (CO2 quota) push the Power Plant to change
its technology and turn to use more biomasses. This is the main reason why the public
authorities find a real partner in the Power Plant as private one. The Power Plant at this
moment also uses biomass (wood and communal waste), but the transportation costs reduce
the thrift.
21
The common interest of local authorities and Power Plant provides suitable circumstances to
convince farmers and other biomass producers to sell the residues from the agri- and
silvicultural activity (stalk, straw, cutting, slashes). At this moment the farmers’ motivation
is very limited due to technical limitations (lack of equipments, lack of logistic system) of the
collection and required preparation system and the Power Plant as well. Therefore the farmers
now have and apply two options, burning the residues in place or transport to own house and
burning in alternative heating system.
The majority of the forestry in the area is owned and cultivated by the state owned Egererdő
(Eger Forestry) Company. The company has a real motivation to participate in the supply
of Power Plant as alternative market of wood and slashes. The Power Plant also has interest,
because of a short logistic distance and the out-of-season buffering of the supply of other
sources of biomass.
The complexity of the project demands further partners in the region, including the scientific
base. The Károly Róbert High School, Gyöngyös can be such partner, which has high
scientific background including an experimental local Power Plant, based on biomass with
1MW capacity. To find other partners there is also important liaison with an informal and
cluster-forming civil association (Ökoland Association), which includes different companies,
institutes and authorities of the region.
The communication amongst the partners includes different activities. The local authorities
were invited twice by the leader village to round table discussions to identify their needs and
benefits related to this activity. The partnership with the Power Plant started with the second
meeting when the representatives of the company were invited to present their expectations.
As a result, these meetings outlined the main principles and tasks of the collaboration amongst
the local authorities and Power Plant.
The idea was introduced at the third meeting where the representatives of producers and
Forestry Co. participated as well. The meeting pointed out the present difficulties which have
to be solved to fulfil the demands of Power Plant related to the continuous supply with
prepared biomass. In the next communication phase will be introduced the whole system,
including the technical and financial items as well.
22
3. Description of potential PPP
The common interest of the main actors (local authorities, Power Plant and producers) is to
set up and optimize the logistic system which supplies the Power Plant with biomass.
Therefore, the main object of this project is to establish this frame which guarantees their
benefits to the partners in this logistic chain.
The biomass producers are in different situation, the farmers need services to transform their
biomass outputs to make them suitable for Power Plant use, the Forestry Co. has all the
equipment and conditions to supply the partner. Farmers provided materials are available in a
narrow period of vegetation, therefore the forestry can and has to cover the continuous
demands of energy producer.
Based on these the main actors and potential founder of the PPP scheme are the local
authorities providing services to the farmers and the Power Plant which has a strong
commitment to utilize the by-product biomass from its surroundings. The Power Plant
expects the following phases for preparation of biomass:
- collection from the production site;
- temporary storage;
- standardization /size, water content etc./ (according to the character of the matter);
- preparation to the transport;
- transportation to Power Plant.
Consortia of local authorities are generally able and ready to carry out these activities,
providing service to the farmers, except for the first step (collection of matters from the
fields), therefore this step has to be dealt with by the farmers. There is need also of some
investments for the equipments for standardization, preparation and transport. These
investments and the actuation of the whole service will be carried out by the joint venture of
the consortia and Power Plant (see the green arrow below) forming the PPP scheme. The
Forestry Co. will contract directly with the Power Plant, but its supplying period will
harmonize with the supply from the joint venture (see the red arrow below, representing the
way of biomass).
23
Farmers Forestry Company
Local authoritiesPower Plant
Joint venture
Figure 9: Joint venture scheme
This PPP scheme can optimize the physical and financial resources to utilize the waste
biomass of the producers, providing opportunities:
- to create more job and more income to the local peoples;
- to improve the environment of the villages, giving chance to the tourism and health care.
The threats related to the sustainability of the project can arise due to:
- low level of farmers’ interest to sell the waste materials via joint venture;
- unbalanced internal forces within joint venture (potential power superiority of Power
Plant);
- changing of priorities due to political change on the level of local authorities.
24
4. List of information and communication activities during the
implementation.
Table 3: List of information and communication activities during the implementation
Activities When Stakeholders Objective(s)
Round table
discussion
2009
August
Majors of villages,
Representative of Power Plant
First initiative of the Power
Plant to collaborate
Bilateral
meeting
2009
October
Major of Abasár,
Representative of Power Plant
Identification of the
common interest and
strategy to involve the
partners
Round table
discussion
2010
February
Majors of villages,
Representative of Power Plant,
Representative of Egererdő Co.,
Representative of Róbert
Károly High School
Brainstorming and
preparation of the frame of
collaboration
Round table
discussion
2010
March
Majors and farmers Identification of the
farmers’ interest
External
communication
2010
June Major of Abasár
Introduction of the project at
the general assembly of
Ökoland Association,
invitation to further
collaboration
5. PPP scheme description
Table 4: PPP characteristics in Hungary
PPP Key factors DescriptionPLANT/SERVICE PUBLIC PRIVATE SHAREDBIOMASS PRIVATESTORAGE LOCAL AUTHORITIESINCOME SOURCE SELLING POWER
25
Figure 10: PPP scheme for Hungary
The project aims to produce power from the co-combustion of biomass and coal in the Matra
Power plant that is public-private shared. The biomass will be produced by private farmers
and other private enterprises. The public body will be involved in the storage of biomass.
26
ITALIAN CASE STUDY
1. Identification of area’s needs (motivations, reasons)
Montefalco
Figure 11: Montefalco Municipality
The Montefalco Municipality has a large availability of vineyard pruning residuals.
The entrepreneurial context is characterized by a high demand of electric energy, due to the
presence of the local craft district. The entrepreneurial network can allow the organization an
efficient raw material supply chain, considering the land characteristics.
The vineyards in the target area have a surface of about 600 ha and they produce about 2
ton/ha. These could be used to produce heat in a biomass boiler. The agro-energy chain deals
with the realization of a plant for energy recovering of vineyards pruning residues and it is
divided into different phases, that is: harvesting and storage by round baler, chipping
27
cylindrical bales to obtain bio-chips, whose size is consistent with the biomass boiler,
chemical-physical characterization of biochips and energy conversion phase.
The vineyard pruning production has been estimated to be around 1000 ton/year.
This could provide a heating power of about 2 MWth. Assuming that it couldn’t be possible to
harvest completely all the biomass, the estimated feasible capacity of the plant would be 1
MWth. This could be used to provide heat to big energy sinks as hospital or schools or sport
centres etc.
The round baler is simple to charge and manage as material. Many of the agricultural
entrepreneurs can store and manage the raw material dry process easily.
The technology used will be a 1 MWth moving grate biomass chips boiler, designed for
woodchips.
The payback for the investment has been estimated in 4,8 years.
2. On-site collaboration with Local Key Actors and Stakeholders
A careful Partner search was started. The aim was to find and involve the most motivated
stakeholders within the region border, interested to invest in agro-energy production.
The project team, as a first step, has outlined a precise partner identikit. The foreseen
partnership has to be composed by municipality, local agricultural SMEs and a cluster of craft
SMEs. At the moment, a direct involvement of credit institutes or banks is excluded. This
choice is due to the need to simplify the actual process, but we are including banks as suitable
partners in the methodology. The participations of credit sector can give strength to this kind
of projects and can facilitate the rating evaluation processes to obtain cash funds .
A particular analysis was carried out on the agricultural SMEs role. These SMEs can play a
double role:
as simple supplier in the production chain;
as investors, sharing incomes.
These two alternatives can lead the single SMEs to different perspectives. Our aim is to
address the SMEs to run the second way as the only possibility to give balance to the raw
material price and origin guarantees.
A different role is drowning for the craft SMEs as energy buyer, but also as owner of capital
share. In the methodology, particular care has to be taken into account in order to select the
28
right management level drained from the craft SMEs, to complete the management lacks
coming from agriculture entrepreneurship.
The communication strategy was led at three levels:
by direct contacts;
by the Municipality support;
exploiting the Enterprise Europe Network communication tools (Is necessary to underline
that Coldiretti is the Umbrian representative of EEN)
direct contacts with other SMEs and Associations (as Industries, craft, etc.)
The direct contact is our natural way to proceed as SMEs association in particular towards the
agricultural sector.
The Municipality structure actions were another important way to evaluate potential partners.
Finally, focused alerts were sent to the entrepreneurial local tissue in order to inform and
involve at the best level. However, the best communication tool was the local meeting held in
the territory to directly explain the project aims.
3. Opportunities/ threats identified
The opportunities are due to the strong interest in alternative energies and government
incentives, the link with other regulation, as the nitrogen rationalisation need in agriculture
and, finally, the good trend in investments in the agricultural sector.
Current technologies are evolving quickly, so they could satisfy the new territorial needs,
related to the new pruning management, giving tools to face this problem, finding economical
and sustainable solutions.
4. Information and communication activities during the implementation.
A communication event was held on May 2009, to spread the project aims in our region.
4 meetings have been held with the administration of Municipality of Montefalco, on March,
April and June.
A technical and institutional task force has been provided by the Municipality of Montefalco.
This task force is composed by:
29
the Councillor for Productive Activities, for overall local coordination, Representation of
Municipality, relationship with UTFP (Italian Technical Unit of Project Financing) and
communication with local SMEs, stakeholders and key actors;
the technical responsible for urban planning and development;
the responsible for administrative and accountancy activities;
the Municipal secretary office.
In the framework of the activities located in Montefalco, two particular and unexpected
constraints were found:
the administrative elections held in Italy on 6/7 June 2009 caused the decadence of the
previous Municipality administration and the necessity to completely restart the process
aiming at involving the new administration as an active stakeholder. This caused a delay
in implementing the planned activities;
In this framework, we knew that the new administration was carrying on an autonomous
initiative in matter of production of energy by RES, with some possible conflict points
with RuralE.Evolution project, in terms of “political” commitment of the new
administration itself. The project in which the new Montefalco administration has been
involved aims to build an agro-energy plant exploiting local biomasses.
Within the meetings a work group has been appointed, with the participation of technical and
political representative figures representing the Municipality itself.
An initial group of local stakeholders (mainly represented by agricultural SMEs belonging to
Coldiretti Umbria) and some local service providers has been appointed. These local
providers are GESENU (body responsible for waste management http://www.gesenu.it/),
VUS (body responsible for water, methane, and waste treatment
http://www.valleumbraservizi.it/); the Action Local Group Valle Umbra e Sibillini belonging
to Leader+ programme (http://www.valleumbraesibillini.com/). On the basis of what
described on RuralE.Evolution project, a specific information and awareness activity has been
carried out, mainly focused on the economic advantage in diversifying the sources of incomes
(not only agricultural products, but also supply of raw material for RES production).
Partner CRB supported these activities from the scientific point of view, providing
information on the better exploitation of local resources in the framework of the production of
energy by RES and providing studies and information, both carried out specifically for the
project and based on its own literature.
30
A deepest collaboration with UTFP (Unità Tecnica Finanza di Progetto – Italian PPP Task
Force http://www.utfp.it/default_eng.htm) has been processed and the initiative carried on in
Montefalco has been enclosed in the UTFP agenda. Furthermore a working Group has been
appointed c/o UTFP to support the Municipality of Montefalco in processing the PPP
activities.
5. Next Steps
We foresee other meetings:
a) At least one technical tailored meeting in order to steady a local PPP;
b) At least one with all the regional municipalities, in order to spread the methodology;
c) Other technical tailored meetings with the stakeholders in order to improve the partnership
and the project efficiency;
d) Finally a meeting with the Umbria region representative authorities to add our project
final and fine tuned methodology in the official energy regional plan.
6. PPP scheme description
31
Table 5: PPP characteristics in Italy
PPP Key factors DescriptionPLANT PUBLICBIOMASS PRIVATEINCOME SOURCE SELLING HEAT
Figure 12: PPP scheme for Italy
The Public Body (Municipality of Montefalco) will make a public call for a concession to
realize a biomass heating plant. The plant will be built by a private partner. The biomass will
be produced by private partners. The heat obtained from biomass conversion will be sold to a
public school.
32
PORTUGUESE CASE STUDY
7. Introduction
When RuralE.Evolution was started, together with EDV Energia, the target area was a
municipality in the north of the country, Oliveira de Azemeis where the Mayor was
committed with the project. After the withdraw of EDV, the situation changed. Oliveira de
Azemeis is far from Lisbon, and it would be difficult to implement the project. After EDV’s
withdraw, there was only a meeting with the Mayor of Oliveira de Azemeis and all the
contacts got not reply. It was then decided to change the target area to Alvito, in the region of
Alentejo, in the south, closer to Lisbon and with a committed Mayor and a committed farmer
organization (UCASUL).
This change of target area delayed the project, namely because the Local Initiatives had been
delayed and contacts with new stakeholders had to restart, chosing new potential partners, but
the delay was totally recovered.
8. Identification of Area Needs/Motivation
The region of Alentejo, in the southern Portugal, is the main region of olive oil production in
the country, having, according to official figures, (DRAP Alentejo), in late 2009, 159914,6 ha
of olive trees planted and planting intentions for over 11 000 ha. According to experts, about
40000 ha were planted or replanted over the past 10 years. These numbers show the strength
of the industry and reflect the potential growth.
The transformation of the olive oil is carried out in various mills, of variable size, distributed
throughout the region. The pomace resulting from the transformation process is directed to
units of oil extraction from this by-product. The largest of these, that handles the largest
amount of pomace and with the most actual technology in the region, is located in the
municipality of Alvito and property of the Union of Olive Oil Cooperatives, UCASUL.
The dynamics of the olive oil sector with the growth of the planted areas and production of
olives has led to an increase of the production of olive oil and pomace, which is expected to
continue. UCASUL is the organization that processes the largest amount of pomace in the
33
region. Being UCASUL located in the municipality of Alvito, a solution that creates
conditions to process this by-product would be strategic for the industry and the region,
creating value and giving a solution to what could become an environmental problem – using
the pomace to produce energy.
Ucasul, receives the pomace from the units that produce the olive oil and extract the pomace
oil. After this extraction, the pomace processed is a biomass that can be used to produce
energy. The actual capacity of UCASUL is 75000000 kg of processed pomace (in an
increasing trend). This biomass is the most relevant existing in the Municipality of Alvito.
Other sources don´t have relevance compared to this.
9. Potential Partners that have shown interest to participate in the project
The Municipality of Alvito
Alvito is located in Alentejo, a Portuguese area with problems of economic development. The
project can be an opportunity to create jobs and develop the local economy. Moreover, it is
very important to create a solution for the pomace after the extraction of the oil, because it
may become an environmental problem.
Figure 13: Alvito Municipality
Ucasul is an Union of Olive Oil Cooperatives, located in the Municipality of Alvito in
Alentejo (south of Portugal). Ucasul is a cooperative that owns the biomass and is the cluster
of suppliers. The aim of this union of cooperatives is to use the pomace of olives (the by-
products of the olive oil production), from the associated cooperatives and other suppliers
from Alentejo, and extract the oil of pomace.
34
To increase the value of the pomace, transforming it in energy, after the extraction of the oil
will increase the competitiveness of all the lines of production. Besides that, it can contribute
to local development, especially by giving jobs in the region.
Financial Partners At the moment, the project doesn’t have a financial partner clearly
motivated to invest in it. Some contacts were made with the Regional Cooperatives Credit
Banks (Crédito Agrícola), that have shown interest to follow the Project and eventually
participate in it, but without a clear commitment. They were present in both the Local
Initiatives held in Alvito.
10. Proposed PPP
In Portugal, the legal significance of PPP is strict and applies only to contracts between the
central state and private in specific areas laid down by law, including roads, health, transports.
Energy is not included at the moment. The meaning of public-private partnership for the
purpose of the project will be broadly based and it has to be defined the exact role of each
partner in the project. So far, UCASUL and Alvito’s municipality are the partners that have
shown more interest on the project. UCASUL has identified its main needs that the
municipality might contribute: administrative and legal issues. The model of PPP should be
closer to the Build-Own-Operate (BOO), as it is defined in deliverable 3.2. The main
constraint identified is the lack of an answer for a “PIP” – request for previous information,
which, if positive, is a license to link the private production of electricity to the public
electricity line.
11. Communication strategy adopted to reach potential partnersCONFAGRI gave preference to personal contacts to the potential partners identified, as well
as meetings with those. Depending on the interest shown, it held private meetings, round
tables and public local initiatives. It also disseminated the information on the project
RuralE.Evolution in its website www.confagri.pt, in its magazine Espaço Rural and made
available to Foundation Valenciana a list of e-mail contacts to send the RuralE.Evolution
Newsletter.
35
12.Information and communication activities during the implementationTable 6: Information and communication activities during the implementation
Activities When Stakeholders Objective(s)
Telephone
contacts
UCASUL, Alvito’s municipality,
Farmer’s Cooperatives,
Agriculture Cooperative Banks
(Crédito Agrícola Mútuo)
Introduction to the RuralE.Evolution project
Scheduling presencial meetings
Meeting July, 2009 UCASUL RuralE.Evolution project presentation
Round table September,
2009
UCASUL and Alvito’s
municipality
RuralE.Evolution project presentation11
Meeting April, 2010 UCASUL Discussion of the main advantages and constraints of the
project’s implementation
Local
initiative
April, 2010 UCASUL, organizations of
farmers and Agricultural
Cooperative Banks in the region
RuralE.evolution presentation, including its background,
objectives, what has been done, advantages and
constraints and the next steps of the project.
Open ground to discuss the interest of the local
stakeholders on the project, as well as their view and role
on the project
Round table June, 2010 Alvito’s mayor and UCASUL RuralE.Evolution project presentation, including the role
that the municipality can have – its duties and benefits as
a partner in the project
Local
initiative
June, 2010 Alvito’s municipality, UCASUL,
Minister of Agriculture, Farmer’s
organizations,
Local member’s of political
parties,
Agriculture Cooperative Banks
(Crédito Agrícola Mútuo),
Private Companies interested in
energy.
RuralE.Evolution project presentation, identifying the
main advantages and constraints.
Publicly, the mayor gave the support of the municipality
on the project. The minister of Agriculture also identified
the main constraints and stated that is promoting a
conversation with the Ministry of Economy, to solve
them.
11 After this meeting, in October 2009, the mayor sent the letter of intention, manifesting the municipality’s interest, after the unanimous approval of the Executive Body of the Municipality. However, with the elections taken afterwards, a new mayor was elected, so in April 2010 the RuralE.evolution project was presented to the recently elected mayor.
36
13.PPP scheme description
Table 7: PPP characteristics in Portugal
PP Key factors DescriptionPLANT PRIVATEBIOMASS PRIVATESUPPORT LOCAL AUTHORITIESINCOME SOURCE SELLING POWER
Figure 14: PPP scheme for Portugal
The private plant will be realized by UCASUL (the Union of Olive Cooperatives) that will
produce the biomass, transform it into power, that will be sold on the grid. The public body
will furnish its support to the initiative.
37
SPANISH CASE STUDY AREA
1. Introduction
When RuralE.Evolution was started, the scope of the project was Benasal's municipality, and
the aim the constitution of a PPP for the utilization of the animal wastes closely to 2.100
swine breeding farm, to obtain of biogas, its thermoelectric recovery and utilization, to
improve the environmental conditions and the economic diversification of the target area.
Since then, a series of event have modified the aim of the project, extending its potential
applicability to other four (4) municipalities, following the model initially chosen as PPP, all
this reflected the report dated on May the 15th , 2010, entitled " Intercoop.Rural Evolution
Target Group ".
This change of target area delayed the project, namely because the Local Initiatives had been
delayed and contacts had to be restarted stakeholders, chosing new potential partners, but for
sure at the end the delay will be totally recovered.
2. Identification of Area Needs/Motivation
The area (Benassal and North East of Castellón Province) inland is a rural area with scarce
economic value, based on some crops cultivation, incipient rural tourism and a big
concentration of animal livestock, basically swine farms (in intensive growing) and cattle in
extensive (half-pastureland) production. Around 1,2 millions permanent head of swine alive
in this area of Castellon Northern, the environmental impact is relevant, and the nuisance for
the population and potential rural tourism too. The possibilities for a potential manure and
other animal by-products treatment and recovery is high.
In 1999, a project initiative promoted from the Castellón Province Government threw an
ambitious project for the construction, storage and managing of these residues in the province
by means of 4 lagoons of storage and ulterior treatment of the lines of liquid and solid.
38
The project, due to different reasons, did not reach the aims that it had planned, but part of
the facilities they are usable and are located in good places for the logistics and the later
treatment, effecting the necessary technological Up-Grades to the current plants.
3. Potential Partners that have shown interest to participate in the project
The Municipality of Benassal is at 15 km from Albocasser Municipality, place when exist one
of four oldest provincial facilities for swine manure treatment plant and center of an area with
problems of rural and economic development, including the others three manure treatment
facilities (Salsadella, Sant Mateu and Todolella). The project can be an opportunity to create
jobs and develop the local economy. Moreover, it is very important to create a solution for the
swine and other animal by-products treatment, recovery and valuation because it may become
a big environmental, animal welfare and human health problem due to bad agricultural
practices applied in the past.
Figure 15: Spain target area
Financial Partners: Intercoop Group, with another private investor (Biotecnología Agrícola
and a Dutch Company) created a new company named “Biogás Castellón”, and negotiated
with the Province Government a new administrative permit and contract for manage the 4
39
facilities during the next 20 years. The Province Government (DIPCAS) contributes with a fix
price for m3 of treated manure.
4. Proposed PPP
In Spain, the legal significance of PPP is strict and applies only to contracts between the
central state and private in specific areas laid down by law, including roads, health, transports.
Energy is not included at the moment. The meaning of public-private partnership for the
purpose of the project will be broadly based and we must define the exact role of each partner
in the project.
Biogás Castellón has identified its main needs that the Province Government (DIPCAS) might
contribute: administrative and legal issues for a 20 years management contract. The model of
PPP should be closer to the Build-Own-Operate (BOO), as it is defined in the 3.2. deliverable.
The main constraint identified is for a “PIP” – request for previous information, which, if
positive, is a license to link the private production of electricity to the public electricity line,
and consequent the long time needed for achieving the final electrical network permits.
5. Communication strategy adopted to reach potential partnersINTERCOOP Group like Confagri in Portugal gave preference to personal contacts to the
potential partners identified, as well as meetings with those. Depending on the interest shown,
it held private meetings, round tables and public local initiatives. It also disseminated the
information on the project RuralE.Evolution in its website www.intercoop.es in its different
Intercoop’s magazine and brochures and made available to Foundation Valenciana-FCVRE a
list of e-mail contacts to send the RuralE.Evolution Newsletter.
40
6. Information and communication activities during the implementation
Table 8: Information and communication activities during the implementation
Activities When Stakeholders Objective(s)
Personal
contacts
2009 Regional and
Provincial
Governments,
Private Partners
Introduction to the RuralE.Evolution project
Scheduling on-person meetings
Meeting November,
2009
FCVRE-Feria
EGETICA Valencia
RuralE.Evolution project presentation
Round
table
September,
2009
EGETICA RuralE.Evolution project presentation.
Meetings
November
2009-July
2010
Province Gov,
private investors,
Intercoop
Discussion of the main advantages and constraints of the
project’s implementation. New permits long term
exploitation and managing.
Local
initiative
February,
2010
Intercoop
organizations and
stakeholders
RuralE.Evolution presentation, including its background,
objectives, what has been done, advantages and
constraints and the next steps of the project.
Open ground to discuss the interest of the local
stakeholders on the project, as well as their view and role
on the project
Round
table
February,
2010
Intercoop and
stakeholders
RuralE.Evolution project presentation, including the role
that the Province Gov can have – its duties and benefits as
a partner in the project for the authorization.
Local
initiative
(1)
July, 2010 Intercoop and new
PPP created (Biogás
Castellón)
RuralE.Evolution project presentation, identifying the
main advantages and constraints. Due Diligence makes
trough Province Gov, electrical connection permits
presented, technical projects design and presented for
construction authorization.
7. PPP scheme description
Table 9: PPP characteristics in Spain
PPP Key factors DescriptionPLANT PRIVATEBIOMASS PRIVATESUPPORT LOCAL AUTHORITIESINCOME SOURCE SELLING POWER AND HEAT
41
Figure 16: PPP scheme for Spain
A private society formed by Intercoop Group and private investors (Biotecnologia Agricola
and a Dutch Company), named Biogas Castellon will manage 4 biogas facilities situated in
Albocasser, Salsadella, Sant Mateu and Todolella). The biomass (mainly manure) will be
furnished by private farmers. The Municipalities will be involved supporting the project.
Annex
42
Questionnaire
On implementation of the provisional methodology in each
target area
43
Questionnaire12
1. The feasibility analysis from WP 3 is fully fit to the local situation?
Yes No
If no:
Which are the main reasons?
- lack of adequate database preparing of pre-feasibility
study
- changing of the partners during the preparation
- changing of the technical circumstances
- changing of the legal frame
- changing of the economic situation
- other (specify!)
2. The feasibility analysis provides sufficient information to the decision of
actors related to implementation of their PPP scheme?
Yes No
If no:
Which type of additional information need to the local implementation?
- technical alternatives
- financial alternatives
- value for money (VFM) analysis
12 Please indicate by underline, if there isn’t any other instruction
44
3. How strong is the commitment of the key actors to implement the PPP
scheme? Please ranking them (the highest value is 1).
Actors Value
- Farmers
- Farmers’ organization
- Other SMEs
- Local authorities
- Other public partner (please specify below)
- Investors
- Private company
- Banks
- Other private partner (please specify below)
4. Which are the main motivations of the implementation? (multiple choice,
indicating in bracket the adequate partner/s/)
- better utilisation of biomass
- alternative income of farmers
- sufficient profit to the investors
- decreasing of the external energy dependency
- environmental benefits
- long- term benefits from the investment
- profitable banking placement
- others (specify!)
5. Which type of risks arising till this time related to the implementation?
(multiple choice)
45
- lack of safe biomass supply in long term
- unbalanced risk amongst partners
- changing of the motivation of potential partners
- changing of the economic circumstances
- changing in the legal frame
- changing of local/national political situation
- personal risks associated with representatives of partners
- others (specify!)
6. Is a clear common vision of partners to establish a management structure
to the implementation of PPP scheme?
Yes No
If no:
Which partner will manage the implementation process providing
transparency to all potential partners? (please specify the guarantee of
transparency!)
46
Table 5: Summary of answers to Questionnaire
Summary of answers to questionnaireQuestion Greece Hungary Italy Portugal Spain
The feasibility
analysis from WP
3 is fully fit to the
local situation?
no no yes yes no
The feasibility
analysis provides
sufficient
information to the
decision of actors
related to
implementation of
their PPP scheme?
yes no yes no no
Ranking the
commitment of the
key actors to
implement the PPP
scheme
1.Farmers' organisation,
2.Farmers, private
companies 3.Local
authorities, 4.Other
SME-s
1. Local
authority 2.
Private company
3. State owned
company
4.Farmers
1.Farmers, Farmers'
organisation,local
authorities 2.Banks
3.Other SME-s,
investors, private
companies
1.Farmers'
organisation
2.Local authorities
3. Banks, other
private partner
1. Regional
government,
investor, private
company
2.Farmers'
organisation,
local authority
3.Farmers, other
SME-s 5. Banks
Main motivations
of the
implementation
better utilisation of
biomass, alternative
income of farmers,
sufficient profit to
investor, decreasing of
the external energy
dependency,
environmental benefit,
long- term benefits from
investment
better utilisation
of biomass,
alternative
income of
farmers,
environmental
benefit, creating
jobs
better utilisation of
biomass, alternative
income of farmers,
sufficient profit to
investor, decreasing of
the external energy
dependency,
environmental benefit,
long- term benefits from
investment, profitable
banking placement
better utilisation of
biomass,
alternative income
of farmers,
sufficient profit to
investor,
environmental
benefit, creating
jobs and increasing
local economy
sufficient profit to
investor,
environmental
benefit
Which type of
risks arising till
this time related to
the implementation
?
unbalanced risks
amongst
partners,economic
circumstances, legal
frame, political
situation, administrative
governmental
incentitives
lack of safe
biomass,
unbalanced risks
amongst
partners,
political
situation
Unbalanced risks
amongst partners,
changing the motivation
of partners, economic
circumstances,
governmental
incentitives
Economic
circumstances,
legal frame,
political situation,
access to capital,
difficulties to link
to electric grid
lack of safe
biomass,legal
frame, political
situation
Is a clear common
vision of partners
to establish a
management
structure to the
implementation of
yes yes yes no yes
47
PPP scheme?
48