S C E N I C E A S T E R N E S C A R PM E N T M A S T E R P L A N 3 5
East Escarpment Master Plan-0917.qxp_Layout 1 28/9/17 5:31 pm Page 35
3 6 S C E N I C E A S T E R N E S C A R PM E N T M A S T E R P L A N
7.5.2 Lookouts
Upgrade of lookouts including new fencing, platforms, signage and landscaping are proposed for 6 locations. These are:
• Marges Lookout, Knapsack Reserve DCP02LP- A2,
• Elizabeth’s Lookout, Knapsack Reserve DCP05, LP-A2,
• Siding Lookout, Lapstone Zig Zag DCP06, LP-B2,
• Quarry Lookout, Lapstone Zig Zag DCP06, LP-B2,
• Bluff Lookout, Bluff Reserve DCP09, LP- E, and
• Unnamed Lookout, Railcorp Land LP-E.
The location of these lookouts is shown in the referenced Local Area Plan (LAP) as labeled. Costing and priority for theseupgrade works are listed in the Costing Table for the relevant Local Area Plan in Section 9.3.
East Escarpment Master Plan-0917.qxp_Layout 1 28/9/17 5:31 pm Page 36
S C E N I C E A S T E R N E S C A R PM E N T M A S T E R P L A N 3 7
East Escarpment Master Plan-0917.qxp_Layout 1 28/9/17 5:31 pm Page 37
3 8 S C E N I C E A S T E R N E S C A R PM E N T M A S T E R P L A N
East Escarpment Master Plan-0917.qxp_Layout 1 28/9/17 5:31 pm Page 38
S C E N I C E A S T E R N E S C A R PM E N T M A S T E R P L A N 3 9
East Escarpment Master Plan-0917.qxp_Layout 1 28/9/17 5:31 pm Page 39
4 0 S C E N I C E A S T E R N E S C A R PM E N T M A S T E R P L A N
East Escarpment Master Plan-0917.qxp_Layout 1 28/9/17 5:31 pm Page 40
S C E N I C E A S T E R N E S C A R PM E N T M A S T E R P L A N 4 1
7.5.3 Walking Tracks
Walking tracks along with the bike trails are the primary means by which visitors access and explore the Eastern Escarpment.The Precinct Plan and the Local Area Plans show existing walking tracks and shared trails and the proposed upgrades. Themajority of the proposals are upgrades of existing tracks. The major upgrade of walking tracks are summarised in Table 11.In addition to these major upgrades, this is a range of track closures and realignments which is identified in the Local AreaPlans, the exact detail of which will be subject to site survey and environmental assessment.
Table 11: Summary of Major Walking Track Upgrades
Item no Location Proposed Action Priority Cost Estimate Plan Reference
1 Lennox Bridge to Marges Lookout track Upgrade shared track Medium $113,100 LP- A1
2 Bridal Track causeway Restore causeway creek crossing Low $81,000 LP- A1
3 Walking Track Lovers Walk to Drainage and erosion control along walking track High $72,000 LP- A2 Mitchells Pass/Whitton Memorial Park
4 Knapsack Reserve New track / realignment west of Elizabeths Lookout Medium $42,500 LP- A2
5 Lapstone Zig Zag Accessible shared path from Knapsack St to Siding Lookout Approx. 860 lm Medium $388,400 LP-B2
6 Siding Lookout to Knapsack Bridge Repair / Upgrade steps and track to class 3. Approx. 120 lm Low $101,400 LP-B2
7 Knapsack Bridge to Creek line Upgrade existing track with creek crossing and viewing platform Medium $126,300 LP-B2
8 Knapsack Bridge (creek line) to Elizabeth’s Lookout Restore and upgrade existing walking track High $337,581 LP-B2
9 Entry to Eastern Portal Lapstone Hill Tunnel (LHT) Upgrade existing walking track to shared path from Governor’s Drive to East Portal entry Medium $472,500 LP-C (following dewatering)
10 Entry to Eastern Portal Lapstone Hill Tunnel (LHT) Design and construct access track from Lucasville Rd to East Portal of the LHT along road easement Medium $90,900 LP-C (alternative land acquisition or right of way)
11 Track between LHT East Portal Upgrade steep section of existing track to class 4 level with stone steps as per bmcc pdtm. Medium $62,000 LP-C and Tunnel Gully reserve Provide erosion control to adjacent hillside.
12 Darks Common Tramway between Upgrade surface of shared track to class 1 level, following line of historic tramway. Approx. 860 lm. Explorers Road and Tramway Terminus Install seats at regular points along track. (alternative Upgrade to Lapstone Zig Zag) Medium $348,750 LP-D
13 Track to Chalmers Lookout Improve track surface from car park to Chalmers Lookout to meet Class 2 track conditions. Low $60,000 LP-E Approx. 240 lm
14 Track to picnic shelter Upgrade track surface from car park to picnic shelter to Class 2 level. Low $46,750 LP-E Rebuild stone steps at min. 900mm width
15 Track between Ross Lookout and Winding house Upgrade section of track to meet class 3 track condition requirements. Low $75,150 LP-E 105 new timber steps, 55 new stone steps, and 1 creek crossing.
16 Track Between Winding house and Rail Corp Lookout Upgrade track surface between Winding House Base and new lookout to Class 1 level. Medium $50,625 LP-E Approx. 135 lm.
Total $2,468,956
East Escarpment Master Plan-0917.qxp_Layout 1 28/9/17 5:31 pm Page 41