Upload
lamnga
View
222
Download
2
Embed Size (px)
Citation preview
EAST COAST MAIN LINE - LESSONS LEARNED REPORT
AUGUST 2010
Published by the Office of Rail Regulation
East Coast Main line Lessons Learned Report
Contents
Executive summary .............................................................................................1
1. Introduction....................................................................................................5
Purpose ...........................................................................................................5
Background .....................................................................................................5
The consultation ..............................................................................................6
Structure of this document...............................................................................7
Next steps........................................................................................................7
2. Findings and recommendations...................................................................9
Introduction......................................................................................................9
Network Rail’s role...........................................................................................9
ORR’s role .....................................................................................................27
Funders’ role..................................................................................................44
Train operators’ role ......................................................................................47
Other issues ..................................................................................................49
Current position .............................................................................................51
Annex A – chronology .......................................................................................53
Annex B – list of consultees/responses ..........................................................61
Annex C – summary of recommendations ......................................................63
OFFICE of RAIL REGULATION • August 2010 Doc # 378117.05
Executive summary
Introduction
1. This document sets out the Office of Rail Regulation (ORR)’s findings and
recommendations from the lessons learned review into the process that led
up to the issue of directions and approvals for the various East Coast Main
Line (ECML) passenger track access applications on 11 February 2010.
2. In February 2010 ORR issued directions on three applications and approved a
fourth granting three passenger train operators - East Coast Main Line
Company Limited, Grand Central Railway Company Limited and Hull Trains
Company Limited - the rights to operate additional and/or amended services
on the ECML. The process leading up to this took two years - full details are
on our website1.
3. Whilst the industry knows that difficulties were encountered at various stages
along the way, it believes that, overall, the process took too long. If the
industry is to learn from this we need to look constructively at the whole
process, including our own areas of responsibility, in order to establish:
(a) what went well;
(b) what went less well;
(c) how the process could be improved in future; and
(d) what the industry could have done differently, with the benefit of
hindsight.
4. It is clear from the information gathered that there are strong feelings within
the industry on how this process was handled. It is important that the industry
takes forward the findings and recommendations in a constructive and
positive way.
1 http://www.rail-reg.gov.uk/server/show/nav.1993
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 1
Summary of findings
5. In summary, the main findings to come out of our discussions with
stakeholders and their representations are:
(a) Network Rail was not proactive enough in managing the access and
timetable development process and failed to take a firm line in refusing
to try and accommodate operators’ and funders’ changing requirements.
Some of the reasons for this were:
(i) the lack of a clear and transparent policy on how it integrates its
strategic planning vision into its timetable development activity and how
it prepares for major forthcoming changes in the timetable;
(ii) it does not give timetabling a high enough priority within the
company, even though the timetable is its main product;
(iii) the lack of rigorous project planning disciplines; and
(iv) the lack of a ‘controlling mind’ to ensure that the timetable is
developed in a way which is consistent with the industry’s strategic
needs;
(b) apparent problems with the resources and skills available within Network
Rail for timetabling – possibly more to do with the mix of skills than the
overall level of resource;
(c) ORR did not provide the industry with a clear enough remit, including
timescales and milestones, at the outset of the process;
(d) ORR did not ensure that clear deadlines were set for the submission of
aspirations and applications, and was not proactive in chasing Network
Rail when things lagged or progress was slow;
(e) ORR should review its policy on the publication of information during
such a process;
(f) the lack of alignment between the access planning and franchising
processes;
2 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
(g) the role of funders, in particular DfT, in writing its own timetable, and the
failure to take a more holistic approach;
(h) the changing requirements of train operators, which introduced
significant delays; and
(i) the lack of a constructive and joined up approach by train operators,
particularly in relation to their dealings with Network Rail.
Our views on these findings are set out in the body of the report.
Summary of recommendations
6. In order to address these findings our report makes a number of
recommendations for the industry and ourselves to take forward. These are
summarised at Annex C and include:
(a) suggestions for improving processes and communication;
(b) ensuring that robust and appropriate project management
arrangements are in place;
(c) ensuring that the necessary resources are in place;
(d) being clear and transparent about what is expected of all stakeholders;
and
(e) seeking to align as far as possible the access planning and franchising
processes.
As the report indicates, many of these recommendations have already been
acted upon. For example, in launching the West Coast Main Line (WCML)
capacity allocation exercise in June, Network Rail and ORR have tried to
ensure that as many of the failures of the ECML process as possible are
taken on board. For our part we have issued Network Rail with a clear remit,
and put in place appropriate project management arrangements with clear
milestones and timescales. Network Rail has similarly put in place suitable
project management arrangements, including the appointment of a project
manager and senior responsible officer. It has also ensured that there are
clear lines of communication across its organisation and that the necessary
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 3
resources have been allocated to the project. To date these are working
effectively.
The way forward
7. Neither Network Rail nor ORR are complacent about what remains to be
done, and we will continue to work closely together to ensure that matters
continue to improve, not just in the area of timetable development and
capacity allocation, but across all major projects. I have already met with
Robin Gisby and Paul Plummer of Network Rail to discuss our findings and
am pleased to say that they welcome the recommendations for the industry as
set out in this report. We have also discussed what further steps should be
taken to develop the industry's ‘strategic timetabling’ capability, where we
believe that Network Rail is well placed to play a more proactive role in
working with its customers to identify opportunities for timetable
improvements.
8. But it is not just about Network Rail and ORR. Whilst it is our view that
Network Rail was perhaps rather too flexible in its approach to the ECML – in
particular in trying to meet the various competing and changing demands - it
has to be recognised that it has a difficult task in managing an industry
process on behalf of a range of parties. As our report explains, finding the
right balance is not always easy and funders and train operators must play
their part and work more constructively with the aim of securing the best
whole industry solution – clearly this was not always the case in respect of the
ECML process.
9. There have been positive signs over the last year or so to show that the
industry recognises the need to work together – for example, through the
outputs of the current joint industry review of access planning processes. This
must continue and, as the report indicates, we intend to play our part.
10. We look forward to continuing to work with the industry to ensure that all of
the recommendations are implemented as quickly and efficiently as possible.
John Thomas
Director, Railways Markets and Economics
20 August 2010
4 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
1. Introduction
Purpose
1.2 The purpose of this document is to set out the findings of our review into the
process that led up to the issue of directions and approvals for the various
East Coast Main Line (ECML) passenger track access applications on
11 February 2010.
1.3 We have reached these findings following discussions with some of the
interested stakeholders and we are grateful to them for their helpful and
detailed contributions. Through this document we report on the comments
received and set out our findings.
Background
1.4 The process began on 29 February 2008 when we wrote to the industry to
identify all operators’ aspirations for additional track access rights on the
ECML. In this letter we advised that we would consider and decide the future
capacity allocation on this important part of the national network.
1.5 In the letter we referred to our reasons document of 6 April 2006 on the
competing applications from Grand Central Railway Company Limited
(Grand Central), Great North Eastern Railway Limited (GNER) and
Hull Trains Company Limited (Hull Trains) for access rights on the ECML.
In that document we said that, due to the uncertainty about the capacity
available, the approval of rights for further additional inter-city services (over
and above those contemplated by our decision) should await the completion
of the ECML Route Utilisation Strategy (RUS), unless there was compelling
evidence to the contrary. We said that we expected to receive a number of
applications for track access rights following the establishment of the RUS,
either for new services or firm long-term rights in place of those running under
contingent or short-term rights. The RUS was established on 29 April 2008
and in anticipation of any applications, we wanted to ensure that we could
consider the relevant questions of access allocation as quickly as possible in
the full knowledge of all operators’ aspirations. This was the reason for our
request to operators to let us know if they intended to make any applications.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 5
1.6 Subsequently, a number of operators submitted track access applications.
Whilst it was difficult for Network Rail to assess the total available capacity
because of the various service permutations applied for, it was clear at the
outset that there was insufficient capacity to accommodate all the rights
sought by all the operators. We therefore initiated two work streams - a
capacity and performance assessment by Network Rail and our own
economic assessment of the competing applications. Our letters setting out
the process, various reports, stakeholders' comments, and decision
documentation are available from our website2.
1.7 In total the process took some two years and a number of difficulties were
encountered at various stages along the way. A chronology of events is
attached at Annex A. In the light of that it was decided to carry out a lessons
learned review. In order to get the most from such a review we decided at the
outset to look constructively at the whole process, including our own areas of
responsibility, in order to establish:
(a) what went well;
(b) what went less well;
(c) how the process could be improved in future; and
(d) what the industry could have done differently with the benefit of
hindsight.
1.8 We wrote to interested stakeholders, listed at Annex B, on 5 March 2010
informing them of the review and inviting their contributions.
The consultation
1.9 We held meetings with those stakeholders with a direct interest in the ECML,
namely: Network Rail, the ECML passenger operators who had been seeking
rights (East Coast Trains, Grand Central and Hull Trains), the major freight
operators (DB Schenker Rail (UK) Limited (DB Schenker) and Freightliner
Group Limited (Freightliner)), the funders (the Department for Transport (DfT)
and Transport Scotland (TS)), and the passenger representative bodies
(Passenger Focus and London TravelWatch). Alliance Rail Holdings (Alliance
Rail) and Northern Rail Limited also accepted our offer to meet other
2 http://www.rail-reg.gov.uk/server/show/nav.1993.
6 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
recipients of our letter. Four consultees, Alliance Rail, London TravelWatch,
the Rail Freight Group and TS also submitted written responses, and these
have been posted on our website3.
1.10 We are grateful to the industry for its contributions and the detailed and
helpful suggestions received.
1.11 Alliance Rail felt that we should extend the review to examine the process
leading up to the original granting of rights to Grand Central, as many of the
difficulties encountered there manifested themselves again with the more
recent applications. However, we felt that this was not appropriate because
we wanted to focus on learning the lessons from this specific exercise and we
were not convinced that there was any more to be gained from going back to
the original Grand Central decision.
1.12 For ease of reference the term East Coast Trains (ECT) has been used
throughout to represent the ECML long distance franchise operator,
irrespective of whether East Coast, GNER or NXEC Trains Limited (NXEC)
was operating the services.
Structure of this document
1.13 This document represents our final report and conclusions and is structured
as follows:
(a) Chapter 2 sets out our findings and recommendations;
(b) Annex A contains a chronology of events from 28 February 2008 to
12 February 2010, when the parties entered into their contracts/
agreements;
(c) Annex B lists consultees and responses/interviews; and
(d) Annex C summarises the recommendations for ease of reference.
Next steps
1.14 Work is of course already in hand to rectify many of the problems that
occurred during the ECML project. In particular, the industry’s review of
access planning4 is making improvements to the access planning process,
3 http://www.rail-reg.gov.uk/server/show/nav.2434.
4 For further information see http://www.rail-reg.gov.uk/server/show/nav.2253.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 7
including the introduction of an ‘overhauled’ Part D of the Network Code, and
the introduction of some guidance to ensure closer alignment between the
access planning and franchising processes. Through our review of access
policy5 we expect to introduce further changes to improve, simplify and
streamline our processes.
1.15 Since starting this review we published a letter on 14 May 2010 seeking to
identify all operators’ aspirations, both passenger and freight, for new or
amended access rights on the West Coast Main Line (WCML) and setting out
the process and timescales involved6. In doing so we have, as far as
possible, picked up many of the concerns the industry had with the ECML
process:
(a) setting out clear timescales and process;
(b) keeping aspirations confidential during the early stages of the process, to
prevent tactical applications;
(c) agreeing not to publish interim capacity allocation and associated
timetabling and performance information until we publish our decision;
and
(d) agreeing a clear remit with Network Rail.
For its part, Network Rail has put in place robust project management
arrangements, including the appointment of a project manager.
1.16 We recognise that some of the recommendations contained in this report will
take longer to implement. Nevertheless, we will work with the industry to
ensure that the necessary changes and improvements are introduced as
quickly as possible.
5 For further information see http://www.rail-reg.gov.uk/server/show/nav.2254.
6 http://www.rail-reg.gov.uk/server/show/nav.2437.
8 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
2. Findings and recommendations
Introduction
2.1 As explained in Chapter 1, we decided to look at the whole process, from the
point at which Network Rail received multiple requests for access through to
its implementation of our decisions on the various access applications.
This chapter reflects the information we have received from stakeholders
either in writing or through face to face interviews. This is set out by issue,
followed by our findings and, where appropriate, a recommendation.
Network Rail’s role
Overview
2.2 There was considerable criticism of Network Rail from all stakeholders on
many aspects of its performance. There was general agreement that Network
Rail lacked strategic vision and preparedness. This was evidenced by its
failure to plan for forthcoming events such as refranchising, the
commissioning of enhancements and, in the case of ECML, the constraints
on capacity, given its knowledge that operators were seeking increased
access. Stakeholders also felt that throughout the ECML process Network
Rail took too long to respond, that it was reactive rather than proactive, and
that the shortcomings exhibited in the ECML process had also been evident
during the earlier WCML and Midland Main Line timetable developments.
2.3 Many stakeholders put these failings down to Network Rail’s management
structure and the culture within the organisation, which was considered to be
overly bureaucratic, negative and lacking in clear leadership, particularly at a
senior level. The ECML timetable was developed without the benefit of
rigorous project planning and many stakeholders were unhappy with the way
in which they were involved in the process.
2.4 However, there was a general feeling from passenger operators that the work
produced by Network Rail’s timetable planning team was good and that when
they were given clear instructions it had gone well, although, as discussed
below, freight operators felt sidelined. It was also generally agreed that much
better progress was made when Network Rail eventually established
workshops and scheduled bi-lateral meetings with operators. Even though
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 9
it may have taken some time to produce the timetable that accompanied
Network Rail’s report, it did actually meet the majority of train operator
requirements.
ORR’s views
2.5 Many of the issues raised by stakeholders are discussed in more detail
below, but in general we agree with many of the criticisms. Overall, it is clear
that Network Rail should have taken a more proactive role in managing the
process and in preventing operators’ and funders’ changing requirements
from extending timescales to the extent they did.
Network Rail’s views
2.6 Network Rail recognises that it can do better in developing new timetables,
but has pointed out that there will always be a difficult balance when
managing an industry process on behalf of a range of parties, all of whom will
have different objectives. It also said that more often than not it had to work to
very tight and fixed deadlines. It also made the valid point that the rest of the
industry must share some of the responsibility and demonstrate a more
joined up and constructive approach. For example, stakeholders must
understand that it is difficult for Network Rail to start developing a detailed
timetable without specifications from all the affected operators. Funders
should also support Network Rail in delivering agreed processes.
Strategic approach
Findings
2.7 The majority of stakeholders expressed strong views that Network Rail:
(a) has a lack of strategic planning and vision in its timetable planning
process, including a lack of preparedness for significant forthcoming
events such as the ECML process;
(b) displays a lack of service planning, instead focusing on the detailed
timetable: and
(c) has no overall process when a major timetable change is envisaged.
2.8 It was felt that Network Rail does not look at the bigger picture. This was
seen by many to be an institutional problem, with timetable planners only
expecting to validate bids when they are told to do so, rather than having the
skills to plan ahead and design efficient and commercially attractive
10 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
timetables. For example, Network Rail was aware that operators wanted to
increase their usage of the ECML and that to accommodate them a standard
pattern timetable would be necessary. But it did nothing until prompted by
ORR to do so.
2.9 Operators’ negative attitude and lack of faith in Network Rail is due in part to
Network Rail having shown both a lack of understanding of the available
capacity and how to optimise its allocation. Its previous failure to identify
capacity for ECT’s Leeds half-hourly services and Grand Central’s
Sunderland services was noted. In 2005 there were 124 long distance
franchised services plus 12 Hull Trains services, and Network Rail said there
was capacity for only six more (three each way) – a total of 142 long-distance
services. In May 2011 there will be 189 per day. Had Network Rail
understood the capacity actually available, instead of saying that it could not
offer any further paths in addition to those already in the timetable, Grand
Central could have been running its Bradford services much earlier.
ORR’s views
2.10 There appear to be significant shortcomings in Network Rail’s strategic
planning and its ability to look ahead and become a proactive rather than a
reactive organisation. The proposals currently being developed by the
industry working group (IWG) to establish a calendar of events and project
working groups7 to oversee significant projects such as the ECML process
will help to ensure that:
(a) Network Rail is better placed to take a more proactive approach in
leading the industry, as evidenced by its current approach on the WCML,
and ensuring that it can respond more effectively to the needs of its
customers; and
(b) interested stakeholders are involved at the outset, providing them with a
process that enables them to work with Network Rail to make best use of
capacity.
2.11 In addition to the changes being proposed through the review of access
planning, Network Rail is currently undertaking a major restructuring of its
train planning function which will see this operation centralised by the end of
7 These new arrangements, which are still in the process of being developed, will be
enshrined in Part D in due course.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 11
August 20108. This should deliver a number of benefits and improvements
including a more joined up, consistent service and a more effective way of
planning ahead.
2.12 As already indicated above, ORR has discussed with Network Rail what
further steps should be taken to develop the industry's ‘strategic timetabling’
capability. It was agreed that Network Rail is well placed to play a more
proactive role in working with its customers to identify opportunities for
timetable improvements - seeking to balance the need for improved reliability
with frequency and journey times and to strengthen the link to RUSs.
However, it was recognised that the financial incentives on the organisation
were not balanced, partly because these incentives had been designed to
focus particularly on performance improvement and on the delivery of
infrastructure enhancements. Network Rail considered that it was seeking to
"do the right thing" despite the apparent incentives while discussing with
ORR, Government and its customers how these incentives could be
improved through the Value for Money study and the periodic review. It was
also recognised that the organisation had made significant investments in
capacity, timetable and performance analysis people, systems and
processes, but that further work was needed in conjunction with Network
Rail's customers. It was agreed that Network Rail and ORR should continue
to develop their plans concerning access planning to address these issues.
2.13 Notwithstanding the above, we also believe that it would be helpful to the
industry if Network Rail was to develop and publish a clear and transparent
policy statement on how it will integrate its strategic planning vision with its
timetable development activity and, for significant projects, appoint a
‘controlling mind’ who ensures that the access planning process is carried out
in a way that is consistent with the strategic needs of the industry and its
customers. Any such statement should include the role of stakeholders and
what Network Rail expects of them in terms of pre-planning and information.
2.14 Recommendation - Network Rail should:
(a) develop and publish a clear and transparent policy on how it will
integrate its strategic planning vision with its timetable
8 Although the majority of Network Rail Operations Planning staff will be based in Milton
Keynes from that date, a satellite office will remain in Leeds until 2012.
12 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
development activity – this should probably be included in Network
Rail’s network statement; and
(b) appoint a ‘controlling mind’ who ensures that the access planning
process is carried out in a way that is consistent with the strategic
needs of the industry and its customers.
ECML RUS
Findings
2.15 There was a general view, particularly from train operators, that the root
cause of the problems experienced on the ECML actually started much
earlier than two years ago with the development of the ECML RUS, which
many believed had led the industry astray. It was also pointed out that the
idea of a five trains per hour standard pattern timetable was first discussed
with Railtrack by ECT back in 1999, although very little came out of it.
2.16 The former Strategic Rail Authority started work on an ECML RUS in 2002,
and completed it in early 2005, but it was never published. In April 2005
responsibility passed to Network Rail, who restarted the process, but it was
two years in the making and used data which was three years out of date.
It was acknowledged that an already complex RUS was further complicated
by the intense competition for capacity between ECT, Hull Trains and Grand
Central on the one hand, and passenger versus freight services on the other.
It was also felt that Network Rail’s unwillingness to produce an outline
timetable to inform the RUS did not help matters.
2.17 In June 2007 the draft RUS concluded that without infrastructure
enhancements a timetable with six long distance passenger trains plus one
freight train per hour (6 + 1) was not possible without an unacceptable impact
on performance and journey times. The effect of the draft RUS was to put the
industry on a hostile footing and as a consequence it was challenged by ECT
in September 2007. It is argued that the RUS was not fit for purpose, given
that subsequent timetable development work has produced a 6 + 1 timetable
with ‘generally’ improved, rather than worse, journey times and no significant
predicted impact on performance
2.18 Despite having a RUS, at the start of the ECML process Network Rail gave
every indication of not knowing what the capacity of the core route actually
was. Indeed, one stakeholder questioned whether Network Rail understood
what additional capacity will be made available by the CP4 enhancements.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 13
There was also criticism that, even after publication of the RUS, Network Rail
was still unwilling to agree to sell rights for any additional services.
As a result, operators were forced to prepare and submit section 17 or 22A
applications which cost them additional time and money.
ORR’s views
2.19 We agree that there needs to be better alignment and correlation between
RUSs and other industry strategic planning processes, including franchising
and access planning and timetabling. It would clearly be beneficial if RUSs
were established prior to the signing of new franchises and track access
applications, which would mean prioritising them. This did not happen on the
ECML and will not happen on the WCML unless DfT extends the current
West Coast franchise.
2.20 On Network Rail’s willingness or otherwise to sell rights, it is important to note
the interaction between service specification and the consumption of
capacity. Whilst Network Rail may know what capacity is available, this does
not mean it will be in a position to say whether a specific permutation of
services, which comprise a complex mix of stopping patterns,
converging/diverging services and train types/speeds etc., can be
accommodated. This is why our letter of 14 May 2010, in which we sought
aspirations for new services on the WCML, set out very clearly the
information that we felt Network Rail required in order to assess the
aspirations.
2.21 However, work is in hand through the industry’s access planning review not
only to improve access planning processes, but also to consider how the
interaction between the current franchising and access planning processes
could be improved to ensure that users obtain maximum benefit from the
process, including more clarity for franchise bidders. Work is under way to
produce a statement setting out proposed principles for industry engagement
during the period leading up to the Invitation to Tender (ITT) and formalisation
of a franchise specification. If adopted, this should improve the overall
process and outcomes of refranchising. This policy would of course be
subject to the discretion of franchising authorities.
2.22 Work is also in hand, through our review of access policy, to clarify the role of
RUSs. This will consider how we will take them into account when making
access decisions.
14 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
2.23 Recommendation:
(a) Network Rail to ensure that there is better alignment between the
access planning and RUS processes;
(b) funders are encouraged to support an approach which gives better
alignment between the access planning and franchising processes;
and
(c) ORR to clarify the relationship between RUSs and decisions on the
allocation of capacity and set these out in its criteria and
procedures document.
Network Rail’s structure & culture
Findings
2.24 The appropriateness of Network Rail’s structure was questioned by a number
of stakeholders. It is seen by some to be a very bureaucratic organisation
operating in silos, with an apparent lack of empowerment at key levels of the
organisation. This is an impediment to it reaching quick decisions.
For example, it was thought that there was very limited communication and
interaction between the commercial, strategic planning and timetable
planning teams, resulting in a lack of continuity between short/medium term
timetabling, long-term timetabling and the contractual arrangements.
Furthermore, the process for achieving internal approval takes too long and
involves too many people e.g. freight operator customer teams may have to
contact numerous people within Network Rail to get matters resolved.
2.25 It was also suggested that Network Rail is incentivised not to want additional
services running on the network as they may impact adversely on the PPM
targets. PPM is now so important that it is seen as an impediment to growth.
As a result, operators are not always willing to work and engage
constructively with Network Rail. Notwithstanding commercial interests, there
is an unwillingness to look at the bigger picture with Network Rail’s letters of
June and October 2009 being cited as evidence. It was also argued that, if it
can be proved that more trains can run without infrastructure enhancement,
some of Network Rail’s investment schemes could be in jeopardy: a further
incentive for Network Rail to refuse additional services.
2.26 Furthermore, the person doing most of the timetable development on the
ECML had a limited idea of the commercial value of individual paths as
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 15
Network Rail’s timetable planners tend to work in isolation from the
commercial team. This also meant that the commercial team did not appear
to be fully versed in what the timetable planners were doing, as the timetable
planners were just trying to fit everyone in, and were paying limited attention
to journey times and other revenue-related issues.
2.27 There was a strong view from the interviews that there exists within Network
Rail a ‘can’t do, won’t do’ culture, with everything seen as a battle, and an
approach that appears to focus on demonstrating why new proposals cannot
be accommodated rather than on generating solutions. Network Rail is also
seen as being too negative and too far removed from both its customers and
the passengers and other end users. It will always revert to the easiest
solution, rather than the best, erring on the side of caution. Essentially,
Network Rail is seen as a risk-averse organisation. Some of the criticisms
were qualified by statements that this does not apply to individuals, such as
the timetable planners, but to senior management.
2.28 For its part Network Rail accepted that communication between teams had
been poor, but felt that getting the CRE teams involved in the process was
one of the things that had worked well. In terms of understanding the
commercial values of paths, Network Rail said that its planning team do take
into account the commercial and societal value of the services affected in
making capacity allocation decisions. However, it argued that its view is
limited by the extent of its detailed knowledge on variables such as revenue
or indeed the sensitivity of that revenue to the various possible timetabling
decisions. Network Rail accepts that it does not always get it right. It also
pointed out that given the extent of change to the specification over the
ECML development period, it would seem that those with access to more
detailed information also do not always get it right first time.
ORR’s views
2.29 Whilst we acknowledge some of the criticism levelled at Network Rail, it
appears to us that many of the issues arose from other factors rather than the
organisational structure. For example:
(a) poor communication within the organisation;
(b) the lack of a dedicated project manager; and
(c) the lack of an overall ‘controlling mind’ to look after the project.
16 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
2.30 On culture, we are aware that there have been a number of issues and the
impression certainly appears to have been in the past that the default
response was often to explain why things cannot be done – rather than to
investigate how they might be done. It is not unknown for Network Rail to
refuse access, only for a train operator to demonstrate how its needs can be
met. There also appears to be evidence of a disconnect between Network
Rail’s timetabling function and the needs of passengers and freight
customers. It is worth saying that we do not feel that this sort of response was
true of the Network Rail team that undertook the ECML work. Indeed, as
explained elsewhere in this report, we felt that Network Rail was perhaps too
flexible. Having said that, Network Rail recognises that change is required
and that there is a need for it to develop good, long-term working
relationships with its stakeholders and customers that are built upon
openness, fairness and trust, so that it is as easy as possible for people to do
business with it. Network Rail has already introduced changes and an
important element of these is its Stakeholder Relations code of practice9,
which lets people know what they can expect from Network Rail, every time
they deal with the organisation.
2.31 As part of its project management arrangements for significant timetable
developments, Network Rail must ensure that it always appoints a project
manager and designates someone at a senior level as the ‘controlling mind’.
The former will drive the project, keeping it on track, ensuring timescales are
met and ensuring good cross organisational working and communications.
The latter has to be an experienced service planner, with a good
understanding of timetabling, resourcing and commercial requirements.
2.32 Network Rail appears to have taken these points on board and is ensuring
that appropriate project management arrangements are in place, e.g. in
respect of the WCML process. More generally, Network Rail will be reflecting
these lessons in all future workstreams, for example, its preparation for the
expected recommencement of DfT’s refranchising programme later in the
year.
2.33 Network Rail has recognised the need to develop a greater understanding
within the organisation that the timetable is its fundamental offering to its
customers and stakeholders and that all activities should be focused on
9 See Network Rail’s website at http://www.networkrail.co.uk/aspx/1544.aspx for further
information.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 17
delivering it. This heightened recognition of the central importance of the
timetable, together with the adoption of a more systematic project
management approach to major re-casts, should result in a more pro-active,
two-way exchange of information between train planning and other Network
Rail functions.
2.34 Recommendation - Network Rail to:
(a) ensure that internal communications are improved between teams
working on the access planning activity and that it has in place
clear guidelines and processes;
(b) continue with its work on introducing updated guidance on
stakeholder engagement; and
(c) review its project management arrangements for timetable
development to ensure that they are rigorous and include the
appointment of a dedicated project manager and a senior
responsible officer.
Timetabling & resources
Timetabling
Findings
2.35 There was a general feeling from passenger operators that the work
produced by Network Rail’s timetable planning team was good and that,
when they were given clear instructions, it had gone well. However, some
considered the remit for the timetable planners was too restricted, resulting in
Network Rail looking at the timetable specification from a very narrow
viewpoint, without considering the consequences. For example, Network Rail:
(a) developed a timetable option which it thought best met everyone’s needs
but it was not what the funders wanted;
(b) overlooked some of the issues such as the benefits of the Durham Coast
re-signalling; and
(c) concentrated on the Edinburgh – London and Leeds – London routes for
passenger trains and Peterborough – Doncaster for freight services,
ignoring the routes beyond these core routes. Therefore, path matching
for freight services could not be carried out.
18 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
2.36 On the latter point, freight operators generally felt sidelined, even though they
confirmed that in parallel workstreams they were fully engaged throughout,
e.g. the development of the ECML RUS and in the Strategic Capacity work
stream. Their main concerns were:
(a) freight services were always being left until last in timetabling terms,
irrespective of the level of rights held by the respective passenger and
freight operators;
(b) that at all stages the information provided by Network Rail on which they
were being asked to comment was incomplete. This made it difficult for
them to comment fully as they were unable to assess the implications for
their current services and for capacity remaining to accommodate future
freight services. As a result they wasted much time and effort attending
meetings; and
(c) the timetabling work did not establish whether the paths identified for
freight services on the ECML were compatible with available paths on
adjacent routes. This meant that the effects on freight services/paths
could not be considered for the through journeys from origin to
destination, with the freight operators unable to ascertain whether what
was being proposed complied with their access rights.
2.37 In its response to our consultation, the Rail Freight Group (RFG) wrote
pointing out that, although the freight operators had provided their
requirements at the beginning of the process, they were not taken into
account in the December 2008 capacity report. By October 2009 when the
draft timetable was issued, although some progress had been made, there
were still significant freight issues outstanding. Given our plan to make an
early decision on specific rights, RFG was surprised that decisions were
about to be taken when the impact on freight was unknown and unresolved.
Whilst accepting that most of the issues were resolved by the time we finally
issued directions, RFG said that it failed to see why it took two years from
freight operators submitting their requirements to reach a position where
pathing of existing freight services and paths for freight growth were resolved.
It concluded that the requirements of freight and other users must be included
at the outset of timetable development, not as an afterthought. Sadly, the
ECML is not the only example of such an approach.
2.38 Stakeholders also acknowledged that Network Rail had to be responsible for
the development of the timetable, though one suggestion was that the service
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 19
design could have been contracted out with the detailed timetabling then
undertaken by Network Rail. A couple of stakeholders suggested that rather
than adapting the existing timetable it would have been better to start again,
e.g. by using the Taktfahrplan concept to develop a completely new timetable
using external resources if necessary.
2.39 Grand Central commented that it had not benefited form the standard pattern
timetable; in fact, the opposite applied, with journey times on average longer.
It queried why, if there had to be only one open access service in the hour,
did it have to be at the same time each hour – why not a different path on
alternate hours, slower for Hull Trains, with its additional station stops, faster
for Grand Central, non-stop south of Doncaster or York? Hull Trains too
thought that it would have been better if Network Rail had varied the standard
pattern.
2.40 Alliance Rail expressed the view that Network Rail was not flexible enough in
developing the timetable, instead taking a dogmatic approach and using the
existing timetable as the base, with the Anglo-Scottish service not leaving
King’s Cross at a time to make maximum use of the capacity available.
Furthermore, instead of looking at a standard pattern timetable for the whole
route, Network Rail should have looked at creating standard paths over
separate sections of the route. Also, Network Rail had not made maximum
use of the capacity available - for example, having ECT’s departures from
King’s Cross five minutes apart when the signal headway is only three
minutes.
2.41 We did not ask Network Rail to produce a weekend timetable, because the
priority was to establish that an acceptable weekday timetable could be
delivered containing all the services for which we had said we would grant
approval. Nevertheless, operators felt that Network Rail should have
produced a weekend timetable. Indeed, Grand Central noted that, if Network
Rail had produced an acceptable weekend timetable at the same time as that
for weekdays, it might not have objected to the worsening of its weekday
timetable, given that Grand Central’s best train loadings are on Sundays.
Resources
Findings
2.42 There was general agreement that Network Rail had not devoted sufficient
resources to the development of the timetable. Questions were raised as to
20 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
whether Network Rail generally is sufficiently resourced, both in terms of
quality and quantity, to deal with timetable requests, let alone to be proactive
and come to the operators with proposals. Respondents said that Network
Rail does not have enough train planners with the necessary knowledge and
experience who know the route. It is not unknown for it to rely on timetabling
input from the train operators. Whilst the passenger operators were generally
able to engage on this basis, this was not easily achieved by national freight
operators, who have to deal with all the planning offices and have neither the
time nor the staff to help Network Rail in detailed timetable development
work.
2.43 Given that Network Rail sometimes has difficulty in covering its normal
timetable workload, it was suggested that it should use external resources
when something like the ECML process comes up, as it had when the
December 2008 WCML timetable had been developed. It was felt that that
resource should be independent - the use of a resource from one of the
applicants not being acceptable due to lack of impartiality. However, some
stakeholders felt that Network Rail already has sufficient people in its access
planning function (thought to be over 300). The problem is that they work in
three separate functions – strategic (including performance modelling),
permanent and short term timetable planning. When there is a priority in one
area it appears that staff cannot be drafted in from one or both of the other
two functions to help to resolve a major issue quickly.
2.44 There were also differing views on Network Rail’s policy of consolidation of
timetabling in one location (Milton Keynes) rather than it being in separate
offices. Some saw this as beneficial because it would avoid the issue of the
separate planning offices appearing to operate independently, looking only at
their particular area of responsibility rather than the end to end timetable –
this was of particular relevance to long distance freight services. However,
most stakeholders felt that Network Rail’s future timetabling capability is at
risk given the unwillingness of some experienced staff to move to Milton
Keynes. They felt that there is a long learning curve and local knowledge is
important, so centralisation was not a good idea. A few stakeholders noted
that Network Rail has already lost many experienced timetablers and raised
questions over how and when it is going to replace them. It was also pointed
out that Network Rail was relying on one experienced timetable planner to
complete the ECML timetable before he retires this month.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 21
2.45 Although there is a belief that ITPS, when functioning properly, will make
matters easier for Network Rail and the industry, Network Rail will still need
experienced staff to produce complex new timetables, such as those on the
WCML and ECML. The next twelve months will be challenging for Network
Rail.
ORR’s views
2.46 Whilst we acknowledge the work produced by Network Rail’s timetabling
team, we have some sympathy with the general view expressed by
stakeholders that Network Rail gives insufficient priority to timetabling and
therefore does not devote sufficient resources to it. It needs to be much better
resourced in terms of the number of staff as well as their knowledge. Network
Rail’s ethos appears to be to give the job to one person and let him/her get
on with it, meaning he/she has to deal with all the train operators. Whilst
he/she appears to be trying to satisfy the needs of everyone, it sometimes
means that the operator who shouts loudest and most often gets what it
wants. Such an approach also led to a lack of suitable cover when the senior
timetable planner was absent on leave or otherwise out of the office.
Everyone interviewed agreed that the process took too long and the lack of
resource in this area was one of the main contributing factors throughout the
two years.
2.47 On the issues raised by the freight sector (paragraph 2.36 above), again we
have some sympathy with the views expressed and we are certainly
concerned to ensure that the requirements of freight operators are taken into
account and not sidelined, particularly where they hold established access
rights. However, it should be remembered that the purpose of the ECML
exercise was to establish a standard pattern passenger timetable - freight
does not, of course, conform to a standard pattern. Therefore, in our view, the
only way Network Rail could sensibly undertake this work was to first
establish the broad standard passenger pattern and then determine whether
it left sufficient space for the required freight services.
2.48 It was widely recognised across the industry that a standard pattern timetable
was the best way forward in order to create the extra capacity required to
meet as many of the demands for additional paths as possible. It was our
understanding that a standard pattern timetable was necessary to
accommodate all the services that we approved in the decision of February
2009. We did set a number of parameters for Network Rail – namely that the
22 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
WCML timetable should not need to be amended and that a major re-write of
the ScotRail timetable was not an option. This fixed Transpennine Express,
CrossCountry, West Coast Trains and some ScotRail services at
Manchester, Birmingham, Glasgow and Edinburgh, which limited the room for
change on the ECML. The open access operators had every opportunity
during the process to make their views known.
2.49 Whilst the process for development of a detailed timetable may still work on
those parts of the network where there is a dominant operator (providing that
operator is prepared to work closely with Network Rail), it does not work well
where there are multiple operators, such as on the ECML. The process for
significant long term change to the timetable has been conducted very much
on an ad hoc basis up to now. As a result it can be expensive, lengthy,
possibly lead to sub-optimal use of scarce capacity and can even present a
barrier to entry for new operators. This issue has been addressed by the
recent review of access planning, and the proposals of that review are being
incorporated into the process for considering new access applications for the
WCML.
2.50 We have already mentioned at paragraph 2.11 Network Rail’s plans for
centralising its timetable planning discipline which, when established, is
intended to remove many of the planning and resourcing issues experienced
on the ECML. It is also worth repeating the good work that has been carried
out by the IWG in overhauling Part D of the network code to produce a
process that is clear, transparent and works. The proposal for change is
currently going through the consultation process. The IWG will follow up with
a further proposal for change that will introduce the Calendar of Events and
project working groups, which are first being tested on a specific December
2011 timetable change, and a revised Decision Criteria.
2.51 Recommendation: The timetabling process should be accorded more
priority within Network Rail, properly resourced and conducted in line
with rigorous project planning disciplines. Network Rail should produce
and publish a clear process which would accurately reflect the
requirements of the network code.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 23
Stakeholder engagement
Findings
2.52 The general message we received was that the industry workshops, when
eventually organised, worked well. This was because they created the
opportunity for Network Rail to get an understanding of all stakeholders’
requirements and enabled compromises to be agreed, so that the best overall
solution could be more easily identified. However, some stakeholders felt that
as the process continued the workshops became shorter, with Network Rail
becoming more defensive and not giving enough opportunity for discussion of
what it had produced.
2.53 The point was also made that the Network Rail/ORR/ECT meetings in
December 2009 achieved a lot, with Robin Gisby’s approach at these
meetings removing many of the blockages. Whilst this was welcomed,
respondents asked how the industry got into a position where the May 2011
timetable Priority Date had to be deferred.
2.54 Concern was expressed that after we issued our decision in February 2009,
ECT worked with Network Rail unilaterally on its own aspirations, but that
only one month’s real work was done by Network Rail before the process
became multilateral. It was only with the three days of workshops in
August 2009 that progress began to be made. Stakeholders said that, without
our prompting Network Rail to start talking to the operators and other
stakeholders, the process would have been delayed even further.
2.55 Network Rail acknowledged that whilst some of the one to one meetings had
been productive, others were not, as it tried to respond to changing
requirements put to it during those meetings. With hindsight it recognised that
it should have exerted better control earlier in the process.
2.56 The passenger representative bodies were pleased that we included them in
our consultations, but were concerned that the industry does not always
involve them. In the case of the ECML process, they thought they were not
involved early enough in the process and were not involved in any of the
timetable development meetings. They saw an enhanced role for
stakeholders in the development of timetables, so that they are for the benefit
of passengers. The formal involvement of stakeholders is vital to the outcome
producing the correct balance between the interests of the operators,
24 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
funders, infrastructure manager and the end users, both passengers and
freight customers.
2.57 Passenger Focus argued that there needs to be sufficient transparency for
passengers and stakeholders to understand and discuss the issues at two
stages in the process:
(a) an outline specification showing quantum, indicative stopping patterns,
and, where applicable, journey times. The specification should also
provide detail about what individual operators are trying to achieve – e.g.
maximisation of revenues, or better utilisation of rolling stock; and
(b) a detailed timetable, which must be the whole timetable – i.e. including
local services on the route and services feeding into those on the route.
When a timetable is already well developed it is very difficult to change the
principles, which is why passengers need to be asked their views at the
outset. Similarly, the views of local authorities, regional stakeholders and user
groups should be obtained.
2.58 Passenger Focus understood why we only consult the industry and the
passenger representative bodies about track access applications but said
that as we make decisions which affect the service that passengers get,
we needed to involve them as well. Such a consultation would flush out the
downsides, which can be glossed over at present. Passenger Focus believes
it is important to ensure that there is a good understanding of the advantages
and disadvantages of proposals.
2.59 Many consultees were in favour of the proposals to establish stakeholder
working groups, with a clear remit and project plan incorporating a Calendar
of Events for major timetable changes, coming out of the access planning
review, and to be included in Part D of the network code. It was suggested
that we should monitor delivery of the project. Both passenger representative
bodies would like to see a more holistic approach, and believed that creating
a project group, involving them, to oversee any major change in the timetable
of a route - caused by a new franchise, new services, new infrastructure etc.
would be beneficial. It would provide them with an opportunity to take a
strategic view of the timetable and remind operators of the need to sense
check the emerging work against passenger needs.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 25
2.60 However, there were some concerns, in particular that Network Rail would
use such a forum as a means of delay and that it would only work when
operators had been allocated a quantum of paths by ORR – i.e. not in the first
part of the process, when operators do not have any certainty of the paths
they would be granted and Network Rail is trying to work out what could be
accommodated. Concern was also expressed that such a group, with
representatives of each of the main operators, would become a discussion
group for the rehearsed positions of each of the three lobbies – franchised
operators, freight operators and open access operators.
2.61 Whilst the forthcoming WCML timetable development process should be less
complex than the ECML process, as the WCML timetable is likely to be a
variation on what exists now rather than a complete re-write, TS believes that
a project group is necessary and wishes to be involved in such a group. This
is in view of the importance to Scottish Ministers and TS of Anglo-Scottish
services between Glasgow/Edinburgh and the North West/West
Midlands/London. TS also said it would be important that, should franchised
services be in competition for capacity with planned new open access
services, we make clear the value we place on say, Glasgow – London and
Glasgow – West Midlands services, and the methodology we will apply to
evaluate them against the open access services.
ORR’s views
2.62 We agree with the general view of stakeholders that the ECML process
highlighted the need for a structured programme with adequate opportunities
for them to input and that somebody needs to take ownership, with a suitable
forum for discussion. There is a need to establish early on at what point
stakeholders should become involved and who should be involved, e.g. when
funders should be involved and when and whether there needs to be
consultation with passenger representative bodies. We certainly agree that
they should be involved.
2.63 Those interviewed all agreed that the bilateral meetings with individual
operators and the workshops helped to move things along considerably, but
they should have been arranged much earlier in the process. Although the
Network Rail/ORR/ECT meetings may have achieved a lot, this was not the
ideal way to move the process along because of the lack of transparency to
the other interested stakeholders. Again, this is another issue that Network
26 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
Rail has already taken on board, for example, on the WCML capacity project
bi-lateral meetings have been programmed from the outset.
2.64 Joint meetings of the affected operators, rather than individual meetings
between the operators and Network Rail, are usually more effective in making
progress, as these create the opportunity to understand everyone’s
requirements and enable compromises to be agreed so that the best overall
solution can be identified more easily.
2.65 As many stakeholders acknowledged, the issue of stakeholder engagement
is already being picked up through the access planning review and the
development of proposals for a Calendar of Events and the establishment of
project working groups for significant timetable workstreams such as the
ECML process. These arrangements will be included in Part D, which itself is
being overhauled to make it clearer and more transparent. Delivery of this
work is being monitored by the Industry Steering Group, of which we are a
member. We do not accept that Network Rail will be able to use the new
arrangements to introduce delay – the whole point behind the new
arrangements is that it would have clear deadlines to meet.
2.66 Recommendation: Network Rail and ORR to continue with the work of
improving stakeholder engagement. The industry generally to ensure
that the passenger representative bodies are included at an appropriate
stage.
ORR’s role
Overview
2.67 It was generally agreed that it was a good idea for ORR to get the process
under way early on with the launch of a letter asking operators to make their
service proposals known, and that we should adopt the same approach for
the expected requests for capacity on the WCML10. Our open and transparent
way of handling the process, including the consultation process, ensuring that
all interested stakeholders had an opportunity to input, was also appreciated.
2.68 There were also many positive comments about the way in which we arrived
at the decision even though not everyone agreed with it. We were not swayed
10 Letter issued to the industry on 14 May 2010, available at http://www.rail
reg.gov.uk/server/show/nav.2437.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 27
by pressure from the funders and/or the franchised operator as evidenced by
our decisions to make some of ECT’s rights contingent, and to include
defeasance provisions where necessary in some access contracts. London
TravelWatch (LTW) said that we considered the competing applications fairly
and equitably and came to a decision based on the evidence.
2.69 However, there was criticism about:
(a) the timescales and deadlines;
(b) the clarity of the remit and the way in which it was interpreted by Network
Rail;
(c) ORR’s process, which can be seen as complex and confusing; and
(d) the lack of clarity over whether ORR or Network Rail was leading the
process.
ORR’s views
2.70 We accept many of the criticisms, particularly in relation to timescales, remits
and our role in the process, and these issues are discussed in detail below. In
terms of the clarity of our process, we have over the last two years or so
carried out a programme of work aimed at achieving a more focused and
effective approach towards access regulation, which is consistent with the
Government’s Better Regulation Initiative. We have done this by ensuring
that we are focussing on those issues where we can add most value,
facilitating a public interest outcome, reducing the regulatory burden/cost on
the industry and withdrawing where this makes sense and the industry is in a
position to take more responsibility.
2.71 This has resulted in a number of significant changes, including the adoption
of a more proportionate response to all applications, allowing the industry
more flexibility on the more straightforward and minor service changes
through the wider use of general approvals and ensuring that there is, as far
as possible, better alignment and integration of track access processes with
the industry’s own processes. We also published clearer and more
transparent criteria and procedures last year.
2.72 This work continues. We are working closely with the industry through the
review of access planning to ensure that we:
28 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
(a) provide greater transparency and understanding to those funding,
planning and using rail services;
(b) enable Network Rail to respond to all applications in a more consistent,
efficient, reliable and timely way; and
(c) provide more effective processes for operators to work together with
Network Rail in optimising their use of capacity.
2.73 We are also working with the industry to produce a clearer and more
transparent Part D to the Network Code through our involvement in the
industry’s access planning review11 . We will also be reviewing our model
clauses, particularly the ways in which Schedule 5 in the passenger model
contract could be improved, looking to see what scope there is for extending
the use of general approvals and making our application forms easier to
complete.
2.74 Recommendation: ORR will continue to work with the industry to find
ways of improving, simplifying and streamlining industry processes,
including its own.
Timescales
Findings
2.75 Whilst the industry acknowledged that dealing with the various ECML track
access applications had not been an easy task, the key issue for most
stakeholders was the length of time the process took, as evidenced in the
chronology, and the fact that in reality it is still ongoing.
2.76 It was suggested that the real timescale is arguably longer in that it started
with the letting of the ECT franchise and the commitment to deliver Service
Level Commitment 2 (SLC2), in August 2007. There was then a further delay
awaiting the establishment of the RUS at the end of April 2008. Even then,
detailed timetable planning work did not start until March 2009, work on the
Saturday timetable did not start until April 2010, and work on the Sunday
timetable, representing some operators’ busiest day of the week, only started
in June 2010. Effectively the process is likely to take three years and the
delay has caused numerous problems, including creating business
11 See http://www.rail-reg.gov.uk/server/show/nav.2253 for further information.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 29
uncertainty for all operators. Most importantly, the provision of new improved
passenger services has been delayed.
2.77 There was also general agreement that we should have been more forceful in
our dealings with Network Rail. This applied particularly to the time we
allowed it to undertake specific pieces of work: it was suggested that we
should have forced Network Rail to allocate more resources. We allowed
timescales to slip too easily through a lack of proper project management.
Even when we set deadlines, Network Rail still did not produce a full
timetable - operators quoted the absence of a weekend timetable and fully
validated freight paths from origin to destination.
ORR’s views
2.78 We accept that the process took too long. There are many reasons for this.
As the chronology demonstrates, there were delays throughout the process
and it is fair to say that all stakeholders, including ORR, must share some of
the responsibility. However, we are confident that the changes being made
through the industry’s access planning review will result in a more efficient
and transparent process that involves all interested stakeholders, such as is
now happening on WCML.
2.79 Recommendation: ORR will ensure that rigorous project planning
disciplines are applied to all future projects of a similar nature,
including the setting of clear timescales and milestones.
Setting deadlines for applications
Findings
2.80 There was concern from a number of stakeholders about the submission of
last minute applications from both new aspirants and existing operators trying
to ‘block’ a rival’s bid. We were asked to consider whether we could impose a
deadline on applications for competing capacity, to avoid the problems
created by late applications, and also impose a deadline on major changes to
those applications, to avoid the problems created by changes to ECT’s
requirements. It was suggested that we should use the Part D process, with a
deadline linked to the Priority Date.
2.81 Alliance Rail re-iterated its belief that we had been wrong to accept a late
change in ECT’s destination from Leeds to York, and that these paths should
have been made available for all operators, including Alliance Rail, to apply
30 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
for. Alliance Rail could find no reasoning for this change which appeared to it
to be outside the network code, our criteria and procedures, and had no
justification. It also again brought into question the validity of the RUS
process.
2.82 Alliance Rail also noted that the ECML RUS had identified Halifax and
Bradford as destinations for additional services, so Grand Central’s
application of 18 April 2008 was both consistent with the RUS and with its
earlier application which had passed our ‘not primarily abstractive’ test, but
had been rejected because of lack of capacity. In contrast, Hull Trains’
application of 8 May 2008 for services to Harrogate was for a destination not
identified in the RUS, and not mentioned by Hull Trains during the RUS
discussions.
2.83 When we suggested that Hull Trains had not declared its hand for fear of
copycat applications, Alliance Rail said it did not accept that an existing
operator should not reveal its aspirations during the RUS development
process. It was not right that we had treated the two applications as equals.
We should have given higher priority to an application in line with the RUS.
ORR’s views
2.84 This is not a new issue. During our review of our Criteria and Procedures for
the Approval of Track Access Contracts in 2007, we consulted on the
principle of establishing a process for setting deadlines and parameters for
the submission of applications. There was a mixed response, the main
concern being that deadlines could limit a train operator’s flexibility to adapt to
late changes in demand. Some consultees considered that any deadlines
should not restrict late applications in certain extenuating circumstances.
2.85 It was also suggested that deadlines should be appropriate to the type of
application, i.e. more significant applications should require an earlier
deadline. The different types of application could be distinguished by
‘materiality criteria’ and deadlines should not apply to applications arising out
of the timetabling process. However, there was general recognition of the
problems with conflicting applications, particularly those that arrive late in the
process, with operators being required to make known their aspirations
during Network Rail’s consultation process. As a result of concerns at that
time that we may not be able to impose deadlines because under the
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 31
Railways Act 1993 (the Act) anyone can submit an application at any time,
the proposal went no further.
2.86 However, we have reviewed the position again in the light of further
experience. Notwithstanding the right under the Act for anyone to make an
application at any time, we believe that there is a strong case for priority to be
given to more significant applications where we have set out clear timescales,
particularly on congested parts of the railway. This is the approach we have
adopted for the WCML, where we said that we would only take account of
aspirations received by a given date for the purposes of that project.
However, it was made clear that, whilst this did not preclude anyone from
submitting an application, which would still be considered in line with our
usual processes, it would not be given the same level of priority unless there
was strong justification.
2.87 This is particularly true where a train operator might seek to ‘block’ another
company’s access application by making a rival application. We will try to
manage this around the Network Rail-led consultation process and, where
appropriate, through the changes to the access planning process which are
being considered as part of the review of access planning workstream12 .
2.88 On Alliance Rail’s first point, although not a matter for this review, it is our
view that this issue was addressed thoroughly in our letter of 25 November
200913 . On its second point, we have some sympathy with Hull Trains in
wishing to keep its aspirations quiet, given that shortly after they were made
public, ECT decided that it too wished to operate services to Harrogate.
In fact, we had been aware of Hull Trains’ aspirations for some time, following
a confidential presentation by Hull Trains.
2.89 Finally, in relation to giving priority to applications consistent with a RUS, as
part of our review of access policy14, we will be looking at how we can/should
make RUSs more useful for access decisions and more generally providing
greater clarity on our approach to them. The industry will be consulted in due
course.
12 http://www.rail-reg.gov.uk/server/show/nav.2253.
13 http://www.rail-reg.gov.uk/upload/pdf/ecml-orr-letter-251109.pdf.
14 For further information on our review of access policy, see http://www.rail
reg.gov.uk/server/show/nav.2254.
32 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
2.90 Recommendation: ORR will develop and introduce arrangements, in
certain specified circumstances, for a cut-off date, and these will be set
out in its criteria and procedures document15 .
Remits
Findings
2.91 There was a general, but not unanimous, view that we should have provided
a clearer and more prescriptive remit and specification for Network Rail,
particularly given that Network Rail does not appear to go beyond what is
specifically asked of it, i.e. it is seen as a reactive rather than a proactive
organisation.
2.92 The minority view was that our remit was possibly too constraining, and that it
should have been more open to Network Rail to develop proposals.
2.93 Network Rail agreed that it needs a clear remit at the start of such a project,
clearly setting out the aspirations of each of the operators, particularly in
terms of service patterns, journey times, calling patterns etc. It should be a
fixed remit with a change control process, and a cut off point for funders
and/or operators seeking changes. Network Rail also made the point that
whilst the initial remit was essentially to prove that it could accommodate
6 + 1 per hour, it also had to work on a 5 + 2 option to satisfy the stated
aspirations of the freight operators.
2.94 Network Rail said it had written to us back in October 2009 saying that further
significant changes had been sought by DfT and that this was creating
difficulties because it required a fixed base to develop the timetable - whilst
this base continued to move, it was unable to complete essential parts of
the process.
ORR’s views
2.95 We accept many of the points raised by stakeholders and that we need to be
more precise in setting remits and be clear about what operators actually
want. However, it is important that in doing so we strike a balance. Network
Rail is the infrastructure manager with responsibility for timetabling and it is
15 “Criteria and procedures for the approval of track access contracts”, Office of Rail
Regulation, London, November 2009, available at http://www.railreg.gov.uk/server/show/nav.2409.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 33
important that any specification should not tie Network Rail down too tightly
it must have the opportunity and scope to develop the best timetable based
on its experience and knowledge of the network and its capabilities.
We clearly need to engage more with Network Rail in agreeing the remit,
but it is also true that Network Rail could and should have been more
proactive in obtaining clear remits from the operators and funders in
developing the timetable.
2.96 In order to carry out our economic assessment of competing applications
where it is known, or indeed merely believed, that there is insufficient
capacity to satisfy them all, we need an outline timetable. One of the
difficulties we faced during the ECML process was the lack of knowledge of
the capacity available and the absence of an outline timetable – hence the
work Network Rail had to undertake in 2008, before we reached our February
2009 decision.
2.97 Our remit, which we published on 30 June 201016, for the WCML capacity
work picks up on the lessons learned from the ECML and will provide the
basis for all future projects going forward.
2.98 Recommendation: ORR to ensure that:
(a) it provides Network Rail with clear and unambiguous
instructions/remits;
(b) strong project management arrangements are in place, both in
Network Rail and within its own organisation; and
(c) interested stakeholders understand how the timetable development
process will work, and their role in it.
ORR’s attendance at industry meetings
Findings
2.99 There was a belief from train operators and Network Rail that it would have
been valuable for us to attend meetings as an observer, particularly the
industry stakeholder ones, so that we would have had a better understanding
of what was actually happening. Indeed, Network Rail argued that it would
16 http://www.rail-reg.gov.uk/upload/pdf/wcml-capacity-letter-300610.pdf.
34 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
have been helpful had we been more proactive when we did attend meetings,
rather than just acting as an observer.
2.100 TS said that it was important for Network Rail’s internal work to be challenged
and that there was no reason why we should not be involved in the process
and attend meetings, believing that would be in line with our section 4 duties
under the Act.
ORR’s views
2.101 We decided at an early stage in the process not to attend industry meetings,
even as an observer, because of possible conflicts with our role in approving
applications and/or acting as the appeal body in the event of any subsequent
timetabling dispute. Accordingly, we had to be very careful about getting too
involved in the detailed discussions on timetabling. We did attend the initial
stakeholder meeting, to explain what was happening and to address any
questions, but not the subsequent ones. However, towards the end of the
process, we did get more involved, attending two meetings with Network Rail
and ECT in December 2009 to help move matters along.
2.102 We believe that the responsibility for managing processes such as this one
lies squarely with Network Rail. It is its responsibility both to undertake an
appraisal of network capacity and to come to conclusions as to how it should
be allocated and timetabled. It is then our role to ensure that the allocation of
that capacity by Network Rail is fair and efficient, and to determine that
allocation if there is any dispute, as happened on the ECML. This is the
approach that both Network Rail and we have taken on the WCML capacity
work, where Network Rail has been remitted to produce a capacity and
performance report, including a recommendation on how capacity should be
allocated. This will include the development of a prototype timetable.
2.103 It is also worth reminding Network Rail and the industry that the former’s
network licence requires it to run an efficient and effective timetabling
process. Notwithstanding the above, and having regard to the need to be
careful not to prejudice our appellant role, we will consider further our role in
similar exercises to see how we could add value by attending meetings
without prejudicing our regulatory position.
2.104 Recommendation - ORR will in future:
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 35
(a) attend initial meetings of industry stakeholders to explain its
position and to set out what it hopes to achieve from the project;
and
(b) consider attending other meetings throughout a particular project
as an observer on a case by case basis.
Project management arrangements
Findings
2.105 There were strong views that we should have ensured that suitable project
management arrangements were in place both in Network Rail and within
ORR. Also, it was thought that we should have been more proactive in telling
Network Rail to make swift progress after 29 February 2009. The chronology
suggests that not much happened for some time after that date and that we
therefore did not take a sufficiently tough stance with Network Rail and the
industry. Furthermore, there was an unacceptable delay between the
submission of some applications, e.g. ECT’s track access application in
June 2008, and our decision at the end of February 2009, which meant that
eight of the 18 months available for the then planned December 2009
implementation were used up.
2.106 It was suggested that there were times when it was not clear who in ORR
was dealing with the project. TS indicated that whilst it felt we were clear
about what we were trying to achieve, there was a lack of clarity about what
the ECML timetable would look like. In future there needs to be clarity about
the objective and a clear project plan showing how the industry achieves it.
Whilst our letters to the industry included next steps, they did not go further.
ORR’s views
2.107 We accept the criticism about the lack of robust and appropriate project
management for the ECML work and that we were not proactive enough in
monitoring progress. As a result, unnecessary and significant delays were
introduced into the project timetable.
2.108 However, we do not accept the point that there was no clear point of contact.
It has been standard operating practice within ORR for many years to have a
sole point of contact for each and every project or workstream. This was no
different for the ECML case. The named case officer through whom all
36 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
contact should have been made was in contact with all relevant stakeholders.
Indeed, we were not aware that this was ever an issue.
2.109 Recommendation: ORR will ensure that:
(a) both ORR and Network Rail establish suitable project management
arrangements at the outset of any project, including the early
publication of a project plan detailing timescales, milestones and
resources; and
(b) the sole point of contact, together with others involved in a
particular piece of work, is clearly detailed at the outset.
ORR’s timetabling & planning resources
Findings
2.110 Some stakeholders raised the issue of whether ORR should employ external
consultants to provide a timetabling and performance assessment in the
same way that we employ external consultants for an economic assessment
of the applications. The general view was that we should not, as this would
allow Network Rail an excuse if it then had problems in implementing what
our consultants had produced. Instead, ORR should use its powers to ensure
that Network Rail does its job properly. However, some suggested that we
should not rely on Network Rail. As the independent regulator, they
considered that we should have our own timetabling resources to assess
what Network Rail has produced, or at least seek an independent view.
We were reminded that this point had been made in an ORR Board paper
back in 2004.
2.111 A minority view was that timetable planning should not be undertaken by
Network Rail at all. Instead, an independent company should be formed
which is incentivised by us to maximise utilisation of the network. It was
suggested that Network Rail’s culture is one of caution and to take no risks
with reliability. It was seen as perverse that the infrastructure provider is
tasked with overseeing slack timetables which cope with poorly performing
infrastructure. These respondents believed that, as long as Network Rail
controls the process, the industry will continue to see the same problems
occurring.
2.112 A number of stakeholders were critical that we had issued directions for
detailed access rights without any performance modelling having been
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 37
undertaken on the then latest iteration of the timetable17 . As a result, train
operators did not, and still do not, know the impact the new timetable is likely
to have on their PPM. One consultee widened the discussion to express
concerns about the limitation of current performance modelling approaches.
In its view Railsys has serious limitations and is not an appropriate tool for
modelling a large part of the network. The only available alternative at
present is to rely on expert judgement, but clearly this is also unsatisfactory.
There is a pressing need for the industry to develop better performance
modelling techniques.
2.113 One operator also said it was concerned that when we change our economic
consultants – as we did for this series of applications - there is a risk of them
taking a different approach, if only in the way that the data is presented,
which creates additional work for the operators, who are expecting to see it
presented in the same way as last time.
ORR’s views
2.114 Network Rail has a clear responsibility to provide capacity, timetabling and
performance services to the rail industry and should be resourced to provide
the necessary assessments to a high professional standard. The industry
should expect Network Rail to conduct analysis of the economic issues and
to demonstrate to us and the wider industry how it reached its views. For this
reason there should be no need for us to employ our own consultants on a
routine basis: this would be a duplication of effort which would increase our,
and therefore industry, costs.
2.115 On the point about economic consultants, as a public body it is necessary for
us to tender for consultancy work, and on this occasion the consultants used
previously had already been appointed by one of the applicants, so could not
be invited to tender for the work. However, the consultants we appointed had
access to all the previous data and documentation, and, of course, we
maintained an overview to ensure consistency.
2.116 Recommendation: No change to ORR’s current position, although ORR
will work with Network Rail to ensure that it has suitable arrangements
in place so that it can provide high quality professional advice and
assessments.
17 Note: some modelling had been undertaken on the timetable which informed our decision
of February 2009.
38 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
ORR’s publication policy
Findings
2.117 There was almost unanimous agreement that we should not in future publish
timetables which were still under development because it led to a lot of
additional work managing stakeholders and fielding enquiries, which could
only be answered in an inconclusive way – that is, it was for DfT and the
operators to specify their requirements. It also led to false hopes and
misunderstandings, for both passengers and freight customers, particularly
when the industry is then unable to deliver. This is a particular issue on a
shared route such as the ECML where the overall timetable available to
passengers is spread between multiple train operators and is also dependent
upon DfT specification, Network Rail timetabling and our approval of track
access rights. It would be far better to keep timetable iterations within industry
processes.
2.118 The exception to the general view was Passenger Focus, who argued that if
we had not published the draft timetables no one would have known what
was being proposed, and thus would have been denied the opportunity to
comment on the downsides for those using particular stations. However, the
timetables should have been more clearly caveated as work in progress.
More generally, the passenger representative bodies would like to see more
of the confidential commercial information which accompanies track access
applications made available to them, to inform their responses to
consultations.
2.119 Freightliner also raised a more general question about the extent to which we
should publish operators’ views where there are issues or conflicts. It said
this was not always helpful, can create issues unnecessarily and cause
uncertainty in the minds of freight customers. Ideally, publication should not
take place until a decision has been made.
ORR’s views
2.120 As previously indicated, we have already taken Freightliner’s point on board
in the WCML capacity work, where we have said at the outset that during the
early stages of the process we will not publish any of the responses received.
Rather we will wait until after the completion of the process and publish all
relevant documentation when we publish our decision. However, we believe
that Passenger Focus made a number of legitimate points, and our views on
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 39
its involvement are discussed below. The same principle should apply to
consultees’ responses in respect of track access applications.
2.121 Recommendation: ORR will review its policy on the publication of
material and provide further clarifying guidance as necessary in its
criteria and procedures document.
Industry structure
Findings
2.122 The problems experienced have raised the question among some
stakeholders as to the appropriateness of the current industry structure, i.e.
allowing a system that provides for owning groups to compete with each
other to win a tightly specified franchise under which the successful bidder
has to then compete for capacity with open access operators, both passenger
and freight. If there is a limit on capacity then inevitably there will be conflict.
2.123 It has been argued that having such a competitive environment delayed the
introduction of ECT’s Leeds half hourly services by 18 months, and has
delayed introduction of SLC2 by the same timescale. Open access operators
are prevented from making calls which might be in the interest of passengers
because they would fail the ‘not primarily abstractive’ test. As a result there
may be too many trains running non-stop between London and Doncaster or
York in the May 2011 timetable, which would not be an efficient use of limited
capacity.
ORR’s views
2.124 The structure of the industry is not a matter for ORR. However, the
Government has recently announced a review of franchising and is of course
jointly sponsoring with us the rail Value for Money study.
Allocation of capacity between passenger and freight services
Findings
2.125 Freight operators have ongoing concerns about how we allocate capacity
between passenger and freight services and reiterated the fact that freight
trains only run when there are goods to be moved, i.e. in reaction to customer
demand, whereas passenger trains run irrespective, i.e. in anticipation of
customer demand. The reluctance of freight operators to operate empty or
40 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
under utilised trains simply to utilise a path often gives the incorrect
impression that there remains sufficient capacity for freight growth.
ORR’s views
2.126 In making access decisions we already take account of the potential for future
growth in freight services, as indeed we did on the ECML. Nevertheless, we
recognise the concerns over how we decide between passenger and freight
services when allocating scarce capacity. This is why, as part of our ongoing
review of access policy18, we looked at the issue and consulted the industry
on some proposals drawing on a separate industry workstream looking at
freight values of time. Our conclusions on this consultation are due to be
published shortly.
ORR’s role in protecting the interests of open access operators
Findings
2.127 It was suggested that ORR tends to favour open access operators - in part it
was felt that this appeared to be the result of a bias in favour of competition
rather than co-ordination and best use of capacity. Some stakeholders said
that we might be expected to favour the largest operator in order to generate
the greatest benefits, but this does not appear to happen.
2.128 On the other hand, it was argued that open access operators, with few
services, were in need of more protection than franchised operators who
obtain the access they want at the expense of those open access operators,
irrespective of the overall passenger benefits. For example, there are no
incentives for Network Rail to deliver good journey times for open access
operators – providing they are within contractual limits. Some respondents
believed that we should have been more positive in our decision letter,
stressing the importance of open access operators having good journey
times.
ORR’s views
2.129 We already ensure that all applications before us are dealt with in a fair,
transparent and balanced way and in accordance with legislative
requirements and published policies. We are content that this happened in
the case of the ECML. We accept that our decision letter might have been
18 http://www.rail-reg.gov.uk/server/show/nav.2254.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 41
more explicit on the specific issue of journey times; however, we believe that
there is also an onus on stakeholders to look after their own interests. We
also note that the Decision Criteria (in Part D of the Network Code) already
provide an incentive for Network Rail to deliver good journey times, though
the dispute resolution process is not an attractive proposition for an operator
to get what it wants.
2.130 More generally, our ongoing review of access policy is already looking at the
issue of conflicting capacity and competition19 .
2.131 Recommendation: ORR will ensure that journey times are given more
recognition in any similar exercise (this has already been noted as an
issue for the WCML capacity exercise).
Other issues
DB Schenker
2.132 DB Schenker raised ORR’s failure to recognise its section 22A application for
additional rights on the ECML in the decision of 29 February 2009. Had we
done so, it would have been a lot easier for DB Schenker to get the Level 1
rights it was seeking.
ORR’s views
2.133 We accept that this was an oversight on our part, but note that this did not
affect the outcome for DB Schenker. Our decision on DB Schenker’s ECML
application, which was set out in our decision letter, still stands.
Defeasance
2.134 ECT referred to the six weeks it took ORR (and Network Rail) to come up
with a satisfactory (to them – the operators were not consulted) wording for
the defeasance provisions, and contrasted it with the time it took the
timetable development “team” to come up with a solution to the one known
breach of an operator’s existing track access rights (Grand Central’s rights to
an 11:10 -11:40 departure from King’s Cross).
2.135 DfT said it was disappointing that ORR and Network Rail had failed to resolve
this conflict before we made our final decision on access rights, particularly
as a straightforward solution was found soon afterwards. Had this issue been
19 http://www.rail-reg.gov.uk/server/show/nav.2254.
42 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
addressed properly, there would have been no need to make some of ECT’s
rights contingent.
ORR’s views
2.136 We do not agree that it took six weeks to come up with the defeasance
provision – we already had a standard template provision which was made
available to Network Rail when the need became apparent. Although
amendments were made to the provision to ensure compatibility with the
particular circumstances on the ECML, there was no need to consult
operators. It is also worth noting that the availability of the defeasance
provision was not on the critical path for bringing matters to a conclusion.
2.137 We too were disappointed that a timetabling solution was not found in time,
but it was not for us to do so. It was clearly a matter for the industry.
Freightliner
2.138 Freightliner expressed the view that the rights we had granted the passenger
operators were quite generic and it would rather have seen the rights drafted
more tightly, as this would have made it clearer what capacity they would
actually use. Freightliner said this view was perhaps an expression of a lack
of trust in Network Rail managing the timetable properly.
2.139 Freightliner also expressed concern that the passenger operators are
increasingly seeking to run more trains rather than run longer trains, thus
using the remaining capacity inefficiently.
ORR’s views
2.140 Freightliner is alone in its view that the rights we had granted the passenger
operators were quite generic, and we believe that we struck the right balance
between giving Network Rail the necessary flexibility to develop future
timetables and giving the operators sufficient certainty to proceed with
changes and/or additions to their services.
2.141 On the length of trains, whilst this a commercial matter for operators and, of
course, a natural consequence of starting up new services, at least initially,
we do have regard to train lengths as part of our economic analysis of
competing applications.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 43
Funders’ role
Findings
2.142 Train operators expressed a number of concerns about the role of funders
(essentially DfT and TS) in the process, particularly in relation to their
apparent unwillingness to take a holistic view. Some also felt that TS should
have had less input in determining the outputs for English services. DfT, in
particular, is seen by the open access operators as being against competition
and opposed to open access. DfT acknowledged that its role as the funder of
the ECT franchise meant its objectives took into account the interests of both
passengers and taxpayers and therefore are not necessarily fully aligned with
our statutory duties. These include a requirement to have regard to issues
such as competition, benefits to passengers and other users and protecting
the taxpayer (through the funds available to the Secretary of State), which
means that we might attach different weights to those of the funder. DfT also
pointed out that its objectives may conflict with those of others for the route.
This in turn can cause difficult conflicts with EU and UK legislation in relation
to promoting competition.
2.143 A major issue raised by some stakeholders was the granting of a franchise to
ECT, including SLC2, before it had been established with Network Rail that
there was capacity available within the existing infrastructure to
accommodate the additional services and before any timetabling work had
been undertaken to establish whether the journey time improvements
required were achievable. It was also suggested that running services to
Lincoln was not an efficient use of capacity and took up paths that could
otherwise have been used by other operators. It was pointed out that this is
not a new problem, and funders should engage earlier with Network Rail and
the industry to ensure that the SLC is deliverable before entering into the
franchise agreement. This problem is compounded where there are
competing operators also planning to introduce new or additional services.
2.144 A related issue was the relationship between Network Rail and DfT. The view
was expressed that the industry needs to understand at the outset what
Government requirements are but, having established them, funders should
then keep out of the process until the later stages. To support this view, it
was felt that when DfT was not present at industry meetings the debate
between the operators was more constructive and progress was made. For
the future, operators suggested that it would be better if they first reached
44 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
agreement, based on the options available, before the franchised operators
approached funders for their consent.
2.145 It was also felt that funders should not be specifying the SLC in detail, rather
they should be selecting from deliverable options. Although it was accepted
by some stakeholders that DfT’s current approach requires it to be closely
involved, the general view was that there was undue interference from DfT,
just as there had been in the earlier WCML process. This position was not
helped by the fact that DfT has its own timetable planners with their own
views. This further contributed to DfT’s interference in the detail, which it
should have left to Network Rail. As already discussed above, DfT, in
particular, kept changing its mind, which not only created extra work for
Network Rail and delayed the process, but also created extra work for other
operators, who found their paths being amended to take account of changes
to ECT and/or other franchisee requirements.
2.146 TS was generally satisfied with the outcome of the process, a significant
improvement in average Edinburgh – London journey times, and with its
involvement in the process. However, there were some bilateral discussions
between DfT/ECT and Network Rail which resulted in timetable iterations
which had unacceptable impacts in Scotland – for ScotRail in timetabling
terms and for TS in funding terms. It was widely accepted by stakeholders
that communications between DfT and TS, and DfT and ECT, were not
always good, e.g. their differing views on journey times and calling patterns.
DfT was criticised for not being sufficiently involved in discussions with some
of the franchised operators regarding the specification of their rights, in
contrast to its ‘over’ involvement in specifying ECT’s rights.
2.147 DfT recognised that towards the end of the period when NXEC was operating
the franchise, Network Rail was getting mixed messages from the operator
and DfT and that there was a need for better interaction between DfT and
Network Rail so that they take a common approach. That apart, DfT felt that it
and the operators generally worked well together.
ORR’s views
2.148 We understand that the objectives and commercial considerations of funders,
operators and other stakeholders will not always be aligned and will in some
cases conflict. Whilst we agree it is important that the industry endeavours to
take a holistic view, it has to be recognised that DfT and TS must be able to
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 45
input in order to meet the policies and strategies set down by their respective
Ministers, in line with statutory duties and responsibilities. For example, we
feel that it is legitimate for TS to input to discussions on issues south of the
border in circumstances where they might impact upon ScotRail services.
However, as evidenced by the review of access planning, there is some
appetite across the industry for alignment of the franchising and access
planning processes. In particular consultees agreed that:
(a) there should be earlier engagement by funders with the industry
(particularly with Network Rail) to see if the capacity required is actually
available;
(b) train operators generally want a greater degree of validation of a
prospective timetable both to reduce and understand risk before the
funder issues an ITT20; and
(c) there is a need for clear industry involvement in the ITT/formalisation of
specification processes.
2.149 We hope that the industry, including funders, supports the policy of ensuring
that there is more alignment between the access planning and franchising
processes and to be actively engaged in the establishment of the industry
best practice statement as proposed by the IWG. It is particularly important
that funders align their processes better with train operators and Network Rail
in developing franchise specifications and particularly in managing change to
those specifications accordingly. The level of capacity depends very largely
on the service specification. If that is changed, then the level of capacity can
increase or decrease substantially, which makes it difficult for Network Rail to
plan.
2.150 Also, as mentioned earlier in this document, we consider that timetable
development is Network Rail’s responsibility. It needs to ensure that proper
project management arrangements are in place and that it controls and
manages the process in a fair and balanced way. As part of that, it is
important that funders are involved throughout. We believe that the proposed
new arrangements to establish a Calendar of Events and project working
groups for all future major timetabling projects will help to improve
20 This is particularly important where a franchise introduces services onto the network that
will affect a number of operators and/or impact on other routes. This could in part be resolved by ensuring the early engagement of funders within the Calendar of Events process proposed under workstream 1 of the access planning review.
46 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
communications between all stakeholders and ensure that the industry works
together in a constructive and positive way.
2.151 Recommendation: Funders are encouraged to support the policy of
improved alignment between the access planning and franchising
processes, and to be actively engaged in the establishment of an
industry best practice statement.
Train operators’ role
Findings
2.152 Generally, stakeholders acknowledged that they needed to take projects such
as the ECML one more seriously and ensure that that they are fully engaged.
A number of stakeholders acknowledged that they should have also been
more proactive in telling Network Rail what they needed at the outset. Freight
operators agreed they need to work with Network Rail, but said it was more
difficult for them to say with certainty what their future demand would be.
On the other hand, some operators felt that they could not have done
anything more, having attended all the meetings to which they were invited,
and provided Network Rail and ORR with all the information requested.
2.153 Two operators, in acknowledging that the process took a long time, said that
the eventual outcome worked well for them, but only because their people
had a very clear idea of what they wanted, what they could compromise on,
and made sure that they were fully involved. It was said that there is a big
onus on operators to be proactive because Network Rail’s commercial team
and its timetable planners do not communicate as well as they should. As a
result, operators need to have their own internal processes in place and
aligned with those of Network Rail.
2.154 Some non-ECML operators, albeit those who were directly affected by any
decisions, said that they had not been involved until we had decided what
quantum of paths we were prepared to approve, by which time it was too late
to contribute. In some cases this had resulted in negative outcomes in
respect of resourcing over which they had had no say, which earlier
constructive discussions with Network Rail would have probably resolved.
2.155 Network Rail acknowledged that operators such as First Capital Connect,
Northern and ScotRail, with their detailed knowledge of diagram issues, had
a major beneficial input to the process when they discussed the timetable on
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 47
a one to one basis. Bringing the operators’ commercial and operational and
timetabling staff together had also brought benefits. Network Rail noted that
this collaborative working had started before the workshops.
2.156 More generally, Network Rail said that the industry needed to show more
trust in it if the industry was to move forward. Of particular concern was the
lack of availability of business cases and other commercially sensitive
information, the provision of which would help it to make more informed
judgements about capacity allocation and timetable development.
Notwithstanding operators’ commercial considerations, it was also felt that
there was scope for them to show more willingness to work co-operatively
both with Network Rail and other operators and to take a more holistic
approach on major issues like the ECML process. Operators sometimes used
tactics aimed at blocking each others’ aspirations.
2.157 As indicated above, there was much criticism of operators changing
requirements throughout the process. This related particularly to DfT and
ECT, which many stakeholders, including those directly involved, believed
had resulted in considerable delays in the process. For example, Network
Rail had devoted considerable time and effort to establishing that it could not
deliver acceptable paths to Bradford and Harrogate via Leeds, only for the
requirements to change overnight when the franchisee changed. The
publication of ECT’s ‘Eureka!’ timetable and subsequent roadshows resulted
in further changes to the timetable requirements and generated more work,
which Network Rail had not planned into the project timescales21 .
ORR’s views
2.158 It is clear from the comments received that there are still problems even
though the industry is trying to work together. We believe that the changes
that the industry itself is proposing to the access planning process will go a
long way to improving matters and negating the conflicts that currently exist.
We agree with Network Rail that stakeholders need to show more trust in its
ability, but it is also true that such trust has to be earned. Again, we believe
that the changes we are recommending in this report that Network Rail
should make, particularly in relation to project management and the
involvement of all interested stakeholders, will help to achieve this.
21 The operator’s plans have of course again changed with the decision to no longer run the
majority of the planned Lincoln services.
48 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
2.159 Recommendation: Train operators should:
(a) be clear about their requirements for timetable development and
ensure that these are communicated to Network Rail in a timely and
constructive way; and
(b) maintain adequate processes to ensure that they are able to
respond and contribute as necessary to the access planning
process.
Other issues
Rules of the Plan
Findings
2.160 It was brought to our attention during the interviews that the Rules of the Plan
(ROTP) on the ECML are more generous than on other main routes for
historical reasons. For example, far longer is allowed for trains to turn round
at King’s Cross than at Euston, Paddington or St Pancras. Furthermore, on
much of the ECML, timetable planning headways are four minutes where
signalling headways are only 1.5 minutes, a larger difference than on other
routes and one which has an effect on the available capacity.
ORR’s views
2.161 We are not in a position to confirm this variance, but it is something that
Network Rail needs to assess. However, we believe that in order for Network
Rail to optimise the use of the infrastructure it will have to consider more than
just the ROTP.
2.162 Recommendation: Network Rail to investigate the optimum use of route
capability, including a review of the ROTP and taking into account both
infrastructure and rolling stock, so as to maximise the benefit of
commercial train services whilst delivering a timetable that can be
operated day in and day out on the ECML, and to agree a plan, with
affected train operators, by the end of September 2010, for developing
potential improvements to feed into ECML timetables at the earliest
practical opportunity.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 49
Track access application forms
Findings
2.163 It was noted that track access application forms do not always explain the
expected timetable changes, including any downsides, as a result of changes
in the rights sought. It would be helpful, to those representing the passengers
in particular, if such information was consistently made available.
2.164 Recommendation: ORR will review its application forms to ensure that
the relevant questions are clear, and remind the industry of the need to
give clear and concise information.
MOIRA
Findings
2.165 LTW expressed concern that MOIRA does not properly reflect passenger
demand – this is worrying, as it is used by the industry in the development of
RUSs and by us in our ‘not primarily abstractive’ test.
ORR’s views
2.166 We recognise the limitations of MOIRA, particularly in estimating the demand
for new direct services between locations which currently have a limited, or
no such, service. Whilst we understand that an updated version of MOIRA is
being developed, it is possible that it will have similar limitations. However,
our five stage ‘not primarily abstractive’ test is designed to overcome this
limitation, and in particular it takes MOIRA estimates as a starting point and
then develops an overall assessment taking into account the known
weaknesses in the MOIRA forecasts and benchmarking against experience
from previous new direct services. We have now built up a significant body of
evidence on the impact of new services and believe that the five stage test
remains fit for purpose, although we are considering what improvements can
be made as part of our access policy review.
2.167 Recommendation: ORR is currently reviewing the ‘not primarily
abstractive’ test as part of its review of access policy, and is expecting
to publish conclusions shortly.
50 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
Current position
Findings
2.168 Even after the approval of track access rights in February 2010 there were
still concerns about the current position of the timetable work before
implementation, leaving some stakeholders to suggest that there was a
significant risk to a satisfactory delivery of the new timetable in May 2011.
2.169 Whilst the planned introduction of a standard pattern timetable has provided
more clarity on the available capacity for freight services, freight operators
remain concerned that there may not be enough capacity to accommodate
future demand. Also, there is uncertainty about how the standard pattern
timetable will affect freight operators’ existing services, not just on the ECML
but also on the routes leading to and from the ECML.
2.170 More recently, some stakeholders questioned the announcement by ECT that
it no longer planned to operate seven weekday services each way between
Lincoln and London – in our February 2009 decision letter we said we would
approve access rights for them. Instead it wished to operate one service each
way, with a further four services each way operating between Newark and
London. It indicated that it intended to submit a track access application to
amend its rights.
ORR’s views
2.171 We understand that Network Rail has been working closely with all
stakeholders and that it quickly put in place a project plan with clear
milestones and timescales. We are in regular contact with Network Rail
regarding progress and have been reassured that everything is on course to
ensure the introduction of the timetable in May 2011. More recently, we have
been advised that, following an industry meeting on 12 August 2010, there
are no outstanding major issues and that all stakeholders are reasonably
content. However, given the ongoing concerns of a few operators, we
continue to monitor the situation.
2.172 In relation to ECT’s recent proposal to change its Lincoln services, we have
issued a letter to the industry setting out our position22 .
22 This is available on the ORR website at http://www.rail-reg.gov.uk/upload/pdf/ecml-orr
letter-110810.pdf.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 51
52 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
Annex A – chronology
29 February 2008 ECML RUS published
29 February 2008 ORR letter to industry Asking for aspirations
11 March 2008 ORR meeting with Network Rail To discuss process going forward
20 March 2008 Grand Central Sunderland 4th path section 22A submitted to ORR
28 March 2008 Deadline for responses to ORR’s letter of 29 February
16 substantive responses received
4 April 2008 ORR forwarded responses to Network Rail
18 April 2008 Grand Northern Bradford section 17 submitted to ORR
24 April 2008 ORR meeting with Network Rail and DfT
Update on process going forward – Network Rail concentrating on December 2008 timetable
29 April 2008 ECML RUS established
8 May 2008 Hull Trains Harrogate section 17 submitted to ORR
21 May 2008 ORR meeting with Network Rail and DfT
Network Rail presented its view of the 1 February timetable bids for PCD December 2008
5 June 2008 ORR letter to Network Rail and DfT
Network Rail was asked to undertake a capacity study to enable ORR to reach a decision on the track access applications received and expected
10 June 2008 NXEC section 17/22A applications submitted to ORR
25 June 2008 ORR meeting with Network Rail and DfT
Including discussion of remit and arrangements for the capacity and performance analysis
27 June 2008 Letter from DfT to ORR Setting out its detailed specification for the timetabling work
9 July 2008 Letter from ORR to Network Rail Confirming actions arising out of meeting of 25 June, including meeting with timetable planners to be arranged
11 July 2008 Network Rail published its December 2008 timetable options assessment
Concluded that it was unable to offer any paths in addition to those currently running
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 53
16 July 2008 ORR letter to stakeholders Setting out a specification for Network Rail to undertake a capacity assessment and report back by 19 September
25 July 2008 ORR meeting with Network Rail To discuss progress
28 July 2008 Network Rail provided ORR with a standard two hourly pattern timetable (option 0)
31 July 2008 ORR commented on the timetable
8 August 2008 ORR letter to stakeholders Advising that ORR proposed to extend some rights which would otherwise expire
11 August 2008 Network Rail responded to ORR’s comments on the timetable
19 August 2008 ORR letter to stakeholders Outlining approach to potentially competing applications
20 August 2008 Industry capacity planning meeting
Meeting of Network Rail, ORR, DfT and operators using the ECML to review the standard pattern timetable and receive comments
27 August 2008 ORR meeting with Freightliner Freightliner wished to ensure that the timetable development fully reflected the freight position
29 August 2008 Network Rail provided ORR with a draft updated standard pattern timetable (option 1)
29 August 2008 ORR provided comments and asked a number of questions
end August 2008 ORR appointed MVA to undertake an economic evaluation of the competing applications
This followed a tendering process
1 September 2008 Network Rail answered ORR questions of 29 August
1 September 2008 ORR meeting with EWS EWS wished to ensure that the timetable development fully reflected the freight position
1 September 2008 Network Rail issued an updated standard pattern timetable to stakeholders (an amended option 1)
3 September 2008 Second industry capacity planning meeting
To discuss latest iteration of timetable – ORR did not attend
54 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
5 September 2008 Deadline for responses to ORR’s letter of 19 August
Two responses received
16 September 2008 ORR meetings with NXEC, Hull Trains and Grand Central
To discuss planned economic analysis methodology
17 September 2008 ORR meeting with Network Rail Network Rail provided an initial draft of its capacity report
24 September 2008 ORR provided comments on the draft
25 September 2008 ORR meeting with EWS To discuss the economic appraisal of the applications
26 September 2008 ORR meeting with MVA To discuss progress23
26 September 2008 Network Rail issued its capacity report
Original deadline for receipt of report was 19 September – ORR agreed extension of one week
29 September 2008 ORR circulated Network Rail’s capacity report to stakeholders
30 September 2008 ORR meeting with Alconbury Developments
To discuss Alconbury’s aspirations for paths on the ECML
6 October 2008 Deadline for comments on Network Rail’s capacity report
17 responses received
14 October 2008 ORR meeting with Transport Scotland
To discuss Transport Scotland’s concerns
23 October 2008 ORR letter to stakeholders Advising that ORR will be asking Network Rail to undertake further work
24 October 2008 ORR meeting with Network Rail To discuss and agree the further work required
27 October 2008 ORR meeting with Hull Trains To discuss Hull Trains’ track access applications and problems being created by the delay in reaching a decision
30 October 2008 Letter from ORR to Network Rail Setting out the detailed remit for the further work; reporting back no later than 19 December
5 November 2008 Network Rail provided ORR with a timetable update (option 2)
10 November 2008 ORR meeting with EWS and Network Rail
To discuss EWS’s concerns
11 November 2008 ORR meeting with Network Rail’s performance team
To discuss performance issues
17 November 2008 EWS provided ORR with details of expected new freight flows
Confidential to ORR – used to inform ORR’s decision
Note: other meetings between ORR and MVA are not recorded in this document
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 55
23
18 November 2008 ORR comments to Network Rail Comments on latest iteration of timetable
25 November 2008 Industry performance workshop
28 November 2008 ORR meeting with Network Rail To discuss latest iteration of timetable
2 December 2008 ORR letter to stakeholders Reserving dates for possible hearing (subsequently not held)
9 December 2008 Network Rail letter to stakeholders
Setting out performance impact of 6 + 1 timetable
12 December 2008 MVA provided ORR with its draft economic assessment
12 December 2008 Network Rail provided ORR with a draft of its capacity report
18 December 2008 ORR provided Network Rail with some minor comments on its draft report
18 December 2008 Network Rail issued its capacity report to ORR (an amended option 2)
19 December 2008 ORR circulated the capacity report to stakeholders
Asking for comments by 5 January (deadline subsequently extended)
24 December 2008 ORR letter to DfT Seeking comments on DfT’s support for SLC2b and financial effect on the Secretary of State’s budget
24 December 2008 ORR letter to stakeholders Update on progress, including extension of deadline for responses to capacity report
9 January 2009 ORR issued the draft MVA economic assessment to the four applicants
Comments requested by 20 January
12 January 2009 Deadline for responses to Network Rail’s capacity report
15 responses received
13/14/15 January 2009
ORR meetings with the four applicants
To discuss the draft MVA economic assessment
20 January 2009 ORR letter to Network Rail with questions on capacity report
22 January 2009 ORR Directors Group met and agreed the case team’s recommendation
28 January 2009 Network Rail responded to ORR’s questions
Nothing in the response to change the case team’s recommendation
29 January 2009 ORR issued its proposed decision
Representations requested by 13 February
56 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
29 January 2009 ORR also issued the final MVA report
4 February 2009 ORR meeting with Hull Trains to discuss its request for extended term
At Hull Trains’ request. Note: Hull Trains subsequently provided further written justification in response to request from ORR
13 February 2009 Deadline for receipt of representations
10 responses received
16 February 2009 DfT response to proposed decision
Included offer to facilitate changes to other operators’ rights
19 February 2009 ORR meeting with CrossCountry At CrossCountry’s request – to discuss its aspirations
24 February 2009 ORR meeting with DfT At ORR’s request - to discuss DfT’s offer to facilitate changes to other operators’ rights
24 February 2009 ORR directors met with the case team to agree the decision
27 February 2009 ORR issued its decision Changed from proposed decision as a result of DfT’s offer to facilitate changes to other operators’ rights
2 March 2009 Network Rail email to all the ECML operators
Advising that Network Rail would be meeting the affected operators 1:1 to agree the process to take things forward
13 March 2009 Network Rail email to all the ECML operators
Advising that it had met them, would continue to develop the options and no further meetings would be held until there was something worth sharing
13 March 2009 ORR meeting with Grand Central
Meeting at Grand Central’s request to discuss aspects of our decision
March 2009 Network Rail holding fortnightly internal Steering Group meetings
Meetings covering operations, property, safety and performance
30 March 2009 NXEC advised Network Rail that it did not wish to implement any part of the SLC2b timetable in December 2009
1 April 2009 NXEC meeting with Network Rail to discuss progress with timetable development
Meeting with timetable planners
1 April 2009 ORR meeting with Network Rail To discuss progress and the way ahead. Agreed to hold stakeholder meetings when core timetable developed
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 57
6 May 2009 ORR letter to Network Rail Expressing concern that Network Rail was proposing that the new timetable should be delayed until PCD 2010, rather than SCD 2010
15 May 2009 Network Rail reply Would be two months before Network Rail was in a position to say whether a change in May was deliverable
17 May 2009 Network Rail email to all the ECML operators
Advising that it hoped to share some timings with the operators by 22 May 2009
20 May 2009 ORR reply to Network Rail’s letter of 15 May 2009
Suggesting that Network Rail put out a statement to that effect
26 May 2009 Network Rail issued a further iteration of the timetable to the operators (option 3)
A big improvement on the previous iteration according to NXEC
5 June 2009 ORR meeting with Network Rail in Leeds
To discuss progress with timetable development. ORR subsequently expressed concerns that the current timetable did not reflect some aspects of the February decision
8 June 2009 ORR meeting with Network Rail To discuss track access contract matters
18 June 2009 ORR meeting with Network Rail To discuss timetable development and ORR’s concerns
3 July 2009 Network Rail issued ECML standard pattern timetable options document
Setting out two timetable options, which of the two it recommended and asking for comments by 17 July
3 July 2009 ORR meeting with Grand Central
To update ORR on various issues
24 July 2009 Network Rail letter to stakeholders
Proposing way forward and timescales
6 August 2009 ORR letter to Network Rail Concurring with Network Rail’s proposed way forward and timescales
17/18/19 August 2009
Industry workshops organised by Network Rail
Attended by DfT, Transport Scotland and train operators
26 August 2009 ORR meeting with Grand Central and Network Rail
To discuss contractual issues and current position of ECML timetable development - Grand Central concerned
26 August 2009 Network Rail letter to ORR Updating ORR on progress
27 August 2009 ORR letter to Network Rail Noting that Grand Central felt it was being disadvantaged
58 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
11 September 2009 Network Rail issued a further iteration of the timetable
2 October 2009 Network Rail provided ORR with the latest timetable produced that week
16 October 2009 Network Rail issued its ECML SLC2 timetable report
19 October 2009 ORR letter to stakeholders Inviting comments on Network Rail’s report by 2 November
19 October 2009 ORR meeting with DfT To discuss Network Rail report and other known issues
20 October 2009 ORR meeting with Hull Trains To discuss investment provisions
23 October 2009 ORR letter to Network Rail Initial comments on its report
30 October 2009 Network Rail’s reply
2 November 2009 Deadline for comments on Network Rail’s report
18 responses received
11 November 2009 Network Rail issued KX platform analysis
Confirming that all services could be accommodated at KX
12 November 2009 ORR meeting with DfT To discuss SCL2 timetable implementation
20 November 2009 ORR meeting with East Coast At director level
20 November 2009 Network Rail issued an updated timetable to stakeholders
The first of fortnightly updates
25 November 2009 ORR letter to stakeholders Commenting on destination of fifth East Coast path
27 November 2009 ORR meeting with Network Rail and East Coast
High level meeting to agree what detail of access rights Network Rail was able to offer
7 December 2009 Network Rail issued an updated timetable to stakeholders
The second fortnightly update
8 December 2009 ORR meeting with Network Rail and DfT
To discuss what agreements were necessary and the process for getting them in place before the Priority Date
9 December 2009 Grand Central letter to ORR in response
Setting out financial effects of the standard pattern timetable
9 December 2009 ORR meeting with Network Rail and East Coast
High level meeting
15 December 2009 Network Rail provided ORR with the main body and some of the schedules of the Hull Trains’ contract
These documents were revised and the outstanding schedules provided and revised as necessary through to 2 February
16 December 2009 ORR meeting with Network Rail and Grand Central
To discuss track access rights
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 59
16 December 2009 ORR meeting with Grand Central
To discuss the economic impact of the standard pattern timetable on Grand Central
16 December 2009 Network Rail wrote to the industry
Proposing that the Priority Date for the May 2011 timetable be put back from 8 January to 12 February
18 December 2009 Network Rail issued its final timetable report
18 December 2009 East Coast provided ORR with the first draft of its proposed supplemental agreement, excluding the new Schedule 5
There was further correspondence and the agreement was amended as necessary through to 4 February
23 December 2009 ORR letter to stakeholders Setting out next steps, assuming the Priority Date was put back
23 December 2009 Network Rail provided ORR with the first draft of the proposed Grand Central Bradford contract
There was further correspondence and the contract was amended as necessary through to 2 February
4 January 2010 East Coast provided ORR with the first draft of its proposed new Schedule 5
There was further correspondence and the schedule was amended as necessary through to 4 February
5 January 2010 Network Rail letter to the industry
Confirming that the Priority Date had been put back
29 January 2010 ORR meeting with Network Rail To discuss defeasance
2 February 2010 ORR issued draft directions in respect of the Grand Central Bradford and Hull Trains applications
4 February 2010 ORR issued draft directions in respect of the East Coast application
11 February 2010 ORR issued directions in respect of three applications and said it would approve the fourth
11 February 2010 ORR issued its reasons letter
12 February 2010 The parties entered into the two contracts and agreement as directed, and the other agreement was approved
Priority Date for SCD May 2011 timetable
60 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
Annex B – list of consultees/responses
Alliance Rail Holdings – letter dated 26 March and interview 11 May Colas Rail Limited DB Schenker Rail (UK) Limited – interview 22 April Department for Transport – interview 21 May DP World Direct Rail Services Limited (DRS) East Coast Main Line Company Limited – interview 20 April East Midlands Trains Limited First Capital Connect Limited First/Keolis Transpennine Limited (TPE) First ScotRail Limited Freightliner Group Limited – interview 4 May GB Railfreight Limited Grand Central Railway Company Limited – interview 13 May Hull Trains Company Limited – interview 14 May Hutchison Ports (UK) Limited London Eastern Railway Limited (NXEA) London TravelWatch – letter dated 31 March and interview 19 April MDS Transmodal Limited Network Rail Infrastructure Limited – interview 29 April Northern Rail Limited – interview 30 April Passenger Focus – interview 14 May Rail Freight Group – letter dated 17 March Renaissance Trains South Yorkshire PTE Transport Scotland - letter dated 12 April and interview 30 April Transport for London Tyne & Wear PTE (Nexus) West Coast Railway Company Limited West Coast Trains Limited (Virgin Trains) West Yorkshire PTE XC Trains Limited (CrossCountry)
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 61
62 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
Annex C – summary of recommendations
Paragraph
number
Issue Recommendation
2.14 Strategic Capacity Network Rail should: (a) develop and publish a clear and transparent policy on how it will integrate its strategic planning vision with its timetable development activity – this should probably be included in Network Rail’s network statement; and (b) appoint a ‘controlling mind’ who ensures that the access planning process is carried out in a way that is consistent with the strategic needs of the industry and its customers.
2.23 ECML RUS (a) Network Rail to ensure that there is better alignment between the access planning and RUS processes; (b) funders are encouraged to support an approach which gives better alignment between the access planning and franchising processes; and (c) ORR to clarify the relationship between RUSs and decisions on the allocation of capacity and set these out in its criteria and procedures document.
2.34 Structure & culture Network Rail to: (a) ensure that internal communications are improved between teams working on the access planning activity and that it has in place clear guidelines and processes; (b) continue with its work on introducing updated guidance on stakeholder engagement; and (c) review its project management arrangements for timetable development to ensure that they are rigorous and include the appointment of a dedicated project manager and a senior responsible officer.
2.51 Timetabling & resources
The timetabling process should be accorded more priority within Network Rail, properly resourced and conducted in line with rigorous project planning disciplines. Network Rail should produce and publish a clear process which would accurately reflect the requirements of the network code.
2.66 Stakeholder engagement
Recommendation: Network Rail and ORR to continue with the work of improving stakeholder engagement. The industry generally to ensure that the passenger representative bodies are included at an appropriate stage.
2.74 ORR’s role ORR will continue to work with the industry to find ways of improving, simplifying and streamlining industry processes, including its own.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 63
2.79 Timescales ORR will ensure that rigorous project planning disciplines are applied to all future projects of a similar nature, including the setting of clear timescales and milestones.
2.90 Setting deadlines ORR will develop and introduce arrangements, in certain specified circumstances, for a cut-off date, and these will be set out in its criteria and procedures document.
2.98 Remits ORR to ensure that: (a) it provides Network Rail with clear and unambiguous instructions/remits; (b) strong project management arrangements are in place, both in Network Rail and within its own organisation; and (c) interested stakeholders understand how the timetable development process will work, and their role in it.
2.104 Attendance at industry meetings
ORR will in future: (a) attend initial meetings of industry stakeholders to explain its position and to set out what it hopes to achieve from the project; and (b) consider attending other meetings throughout a particular project as an observer on a case by case basis.
2.109 Project management arrangements
ORR will ensure that: (a) both ORR and Network Rail establish suitable project management arrangements at the outset of any project, including the early publication of a project plan detailing timescales, milestones and resources; and (b) the sole point of contact, together with others involved in a particular piece of work, is clearly detailed at the outset.
2.116 ORR’s timetabling & resources
No change to ORR’s current position, although ORR will work with Network Rail to ensure that it has suitable arrangements in place so that it can provide high quality professional advice and assessments.
2.121 Publication policy ORR will review its policy on the publication of material and provide further clarifying guidance as necessary in its criteria and procedures document.
2.131 Protecting the interests of open access operators
ORR will ensure that journey times are given more recognition in any similar exercise (this has already been noted as an issue for the WCML capacity exercise).
2.151 Funders’ role Funders are encouraged to support the policy of improved alignment between the access planning and franchising processes, and to be actively engaged in the establishment of an industry best practice statement.
64 Doc # 378117.05 August 2010 • OFFICE of RAIL REGULATION
2.159 Train operators’ role
Train operators should: (a) be clear about their requirements for timetable development and ensure that these are communicated to Network Rail in a timely and constructive way; and (b) maintain adequate processes to ensure that they are able to respond and contribute as necessary to the access planning process.
2.162 Rules of the plan Network Rail to investigate the optimum use of route capability, including a review of the ROTP and taking into account both infrastructure and rolling stock, so as to maximise the benefit of commercial train services whilst delivering a timetable that can be operated day in and day out on the ECML and to agree a plan, with affected train operators, by the end of September 2010, for developing potential improvements to feed into ECML timetables at the earliest practical opportunity.
2.164 Application forms ORR will review its application forms to ensure that the relevant questions are clear, and remind the industry of the need to give clear and concise information.
2.167 MOIRA ORR is currently reviewing the ‘not primarily abstractive’ test as part of its review of access policy, and is expecting to publish conclusions shortly.
OFFICE of RAIL REGULATION• August 2010 Doc # 378117.05 65