1
EarthTEC concludes four years of successful works at Thredbo When a section of the Alpine Way in Thredbo collapsed following a major slip failure, a strong but flexible and free-draining retaining wall was re- quired. Gabions and the Terramesh rein- forced earth wall system was select- ed as the most suitable solution. The preferred design comprised a series of terraced walls similar to those installed by our crews at the Olympic Archery Facility, Haslams Creek. The two lower terraces were Terramesh type walls. However, limited space above the Alpine Way required the use of gravity walls and soil nail anchors in these sections. Access was extremely difficult, particularly during the work areas close to the former lodge locations at Carinya and Bimbadeen, where deeper excavations were required to achieve satisfactory foundation condi- tions. The gabion walls were combined with extensive drainage subsoil works to collect and discharge ground water. The initial sections of work were completed prior to the ski season which was a major challenge, given the significant increase in scope generated by the poor foundation conditions encountered. To achieve on-time completion, a night shift using additional crews working under lights was added to the projects program. Subsequent sections of work were tendered and won over the next four summers including a large Perma- crib wall below Bobuck Lane. In to- tal, over 12,000m3 of gabion work was completed by our crews. The work at Thredbo represents one of the largest gabion projects constructed in the southern hemi- sphere has established the bench- mark for most large-scale commer- cial grade gabion works completed since. Please contact our Sydney head office to meet with an EarthTEC representative in your state to discuss your project: E [email protected] T +61 2 9420 8610 F +61 2 9420 8650 RETAINING WALLS REF No. E/RW-814N Client: Haskins Contractors Location: Thredbo, NSW Project: Alpine Way Restoration The completed works is the largest gabion project in the Southern Hemisphere. ISO 4801:2001 ISO 9001:2000 ISO 14001:2004 RETAINING WALLS REINFORCED EARTH EROSION CONTROL ROCKFALL PROTECTION BARRIER SYSTEMS www.earthtec.com.au

EarthTEC concludes four years of successful works at Thredboearthtec.com.au/wp-content/uploads/2013/07/Thredbo.pdf · EarthTEC concludes four years of successful works at Thredbo

  • Upload
    voxuyen

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

EarthTEC concludes four years of successful works at Thredbo

When a section of the Alpine Way in

Thredbo collapsed following a major

slip failure, a strong but flexible and

free-draining retaining wall was re-

quired.

Gabions and the Terramesh rein-

forced earth wall system was select-

ed as the most suitable solution.

The preferred design comprised a

series of terraced walls similar to

those installed by our crews at the

Olympic Archery Facility, Haslams

Creek.

The two lower terraces were

Terramesh type walls. However,

limited space above the Alpine Way

required the use of gravity walls and

soil nail anchors in these sections.

Access was extremely difficult,

particularly during the work areas

close to the former lodge locations at

Carinya and Bimbadeen, where

deeper excavations were required to

achieve satisfactory foundation condi-

tions.

The gabion walls were combined

with extensive drainage subsoil

works to collect and discharge

ground water.

The initial sections of work were

completed prior to the ski season

which was a major challenge, given

the significant increase in scope

generated by the poor foundation

conditions encountered.

To achieve on-time completion, a

night shift using additional crews

working under lights was added to

the projects program.

Subsequent sections of work were

tendered and won over the next four

summers including a large Perma-

crib wall below Bobuck Lane. In to-

tal, over 12,000m3 of gabion work

was completed by our crews.

The work at Thredbo represents

one of the largest gabion projects

constructed in the southern hemi-

sphere has established the bench-

mark for most large-scale commer-

cial grade gabion works completed

since.

Please contact our Sydney head

office to meet with an EarthTEC

representative in your state to

discuss your project:

E [email protected]

T +61 2 9420 8610

F +61 2 9420 8650

RETAINING WALLS REF No. E/RW-814N

Client: Haskins Contractors

Location: Thredbo, NSW

Project: Alpine Way Restoration

The completed works is the largest gabion project

in the Southern Hemisphere.

ISO 4801:2001

ISO 9001:2000 ISO 14001:2004

RETAINING WALLS REINFORCED EARTH EROSION CONTROL ROCKFALL PROTECTION BARRIER SYSTEMS

w w w . e a r t h t e c . c o m . a u