Upload
hoangthien
View
228
Download
7
Embed Size (px)
Citation preview
The Association of Cost Engineers
ACOSTE CONFERENCE 2012
www.acoste.org
Earned Value Project Control
Steve Wake Chairman APM Planning Monitoring and Control SIG
Company Logo
What is Earned Value Management (EVM)?
• Definition: – “a project control process based on a structured approach to
planning, cost collection and performance measurement. It facilitates the integration of project scope, time and cost objectives and the establishment of a baseline plan for performance measurement”
– APM Body of Knowledge 5th edition
• Comprises: – Definition and authorisation of scope of work – Development of a baseline against which cost, schedule and
technical performance can be measured – Objective performance measurement – Variance analysis and corrective action reporting – Disciplined and timely incorporation of baseline changes
3 © APM 2008. Reproduced under licence from APM
Why use Earned Value Management?
• Helps management by: – Enabling an objective measure of project status – Providing basis for estimating final cost – Predicting when the project will be complete – Supporting effective management of resources – Providing a means of managing and controlling change
• Also provides – Verifiable status reports – Clear objective analysis – Considered reasoning – Accountability in the decision-making process – Awareness of impact on the schedule and cost – Visibility of results
4 © APM 2008. Reproduced under licence from APM
What does EVM require?
6
Time/Schedule
Cost/Budget Quality
Scope
WBS OBS
Baselined Plan
Performance measurement and analysis
Controlled Change
Four key data elements
BCWS Budgeted Cost of Work Scheduled
Planned Value (PV)
ACWP Actual Cost of Work Performed
Actual Cost (AC)
BCWP Budgeted Cost of Work Performed
Earned Value (EV)
EAC Estimate at Completion
7 © APM 2008. Reproduced under licence from APM
9
Time ‘now’
Actual Cost (ACWP)
9 9 TIME
CO
ST
Planned budget (BCWS)
© APM 2008. Reproduced under licence from APM
10
Earned value (BCWP)
Time ‘now’
Actual Cost (ACWP)
10 10 TIME
CO
ST
Planned budget (BCWS)
© APM 2008. Reproduced under licence from APM
EVM Process
12
1. Definition of scope
6. Risk Management
5. Change Management
2. Planning 4. Analysis, review, action
3. Data Collection
Definition of Scope
• Concerned with: – Defining the work to be done – WBS – Assigning work to parts of the project organisation – OBS – Aligning and combining the WBS and OBS – RAM
• Key activities: – Review the project requirements and establish key deliverables – Develop a Work Breakdown Structure (WBS) – Develop an Organisation Breakdown Structure (OBS) – Generate a Responsibility Assignment Matrix (RAM), identifying
control accounts – Produce a Work Breakdown Structure Dictionary (WBSD) down
to work packages and planning packages – Determine and agree flowdown of EVM into subcontracts
14 © APM 2008. Reproduced under licence from APM
Requirements and key deliverables
• Statement of Works – A narrative description of products or services to be delivered by
the project
• Defines the project scope • Includes:
– Overall requirements – Deliverables
• Forms the basis for allocating: – Work – Budget – Schedule
15 © APM 2008. Reproduced under licence from APM
Work Breakdown Structure
16
Project Scope
Component 2.1
High-level work
element 2
Component 2.2
Component 1.1
High-level work
element 1
Component 1.2
WBS Dictionary
• Purpose – Describe the entire scope of the work to be undertaken by the
project
• For each element of the WBS, should contain – Contract number – WBS number and title – WBSD issue number and date – Contract paragraph number – Statement of work
17 © APM 2008. Reproduced under licence from APM
Organisation Breakdown Structure
18
Project Organisation
Team Manager
2.1
Function/Department
2
Team Manager
2.2
Team Manager
1.1
Function/Department
1
Team Manager
1.2
Control Account
Control Account
Control Account
Control Account
Responsibility Assignment Matrix (RAM)
19
Project Organisation
Team Manager
2.1
Function/Department 2
Team Manager
2.2
Team Manager
1.1
Function/Department 1
Team Manager
1.2
Project Scope
Component 2.1
High-level work
element 2
Component 2.2
Component 1.1
High-level work
element 1
Component 1.2
© APM 2008. Reproduced under licence from APM
Subcontract Management
• Requirements for EVM need to be reflected in any subcontracts
• Subcontractors plans should be represented within the project plans/schedules
• Decision needs to be taken about the level of detail to incorporate in the project plans/schedules – Not too much detail – Not insufficient detail
20 © APM 2008. Reproduced under licence from APM
Planning
• Concerned with: – Establishing a baseline for performance measurement
encompassing: • A plan of logically scheduled activities • Agreed and assigned budgets and resources • Defined objective achievement measures
• Key activities: – Identify master milestones and deliverables – Develop activities with logical dependencies and durations – Group activities into work packages and planning packages – Apply resources to activities – Distribute the budget to work packages and planning packages – Determine the earned value type for the work packages – Establish performance measurement baseline
22 © APM 2008. Reproduced under licence from APM
Work packages, planning packages and activities
23
Task Name Year 1 Year 2
Control Account 1
- Work Package 1
- Activity 1 - Activity 2 - Activity 3 - Milestone 1 - Work Package 2
- Activity 4 - Activity 5 - Activity 6 - Milestone 2 - Planning Package 1
© APM 2008. Reproduced under licence from APM
Work packages - attributes
• Defined scope of work • Measure of achievement • Traceability up through the WBS • Budget • Assignment of responsibility • Start and finish dates
• If any work cannot be defined with the detail above, then it should be identified as a planning package within the control account
24 © APM 2008. Reproduced under licence from APM
Schedules
• Definition – The timing and sequence of tasks within a project, as well as the
project duration. The schedule consists mainly of tasks, dependencies among tasks, durations, constraints, resources and time-oriented project information
• Key points – Form the basis for assessing actual progress – Should include contractual milestones – Need to identify activities on the critical path – Permits the integrated planning of project resources with the cost
and schedule objectives of the project
• The plans of any subcontractor should detail an appropriate number of activities/milestones, and these should be integrated into the project schedule
25 © APM 2008. Reproduced under licence from APM
Setting Budget
26
Contract Price
Contract Budget Baseline
Performance Measurement Baseline
Distributed Budget
Control Account Budget
Work Packages
Margin
Management Reserve
Undistributed Budget
Planning Packages
© APM 2008. Reproduced under licence from APM
Objective Measures of Progress
• Applies to work packages that are planned to be or are actually in progress
• Earning method may be objective or subjective • Objective – measurement is straightforward and can be
automated • Subjective – manual assessment will be necessary • Short work packages make assessment easier, but avoid
arbitrary breaks in job planning and scheduling
27 © APM 2008. Reproduced under licence from APM
Earned Value Techniques
• To be agreed for each work package
• Milestones complete • Percentage complete • Equivalent units • Formula method • Level of effort • Apportioned effort
• Earned value for materials?
28 © APM 2008. Reproduced under licence from APM
Baselining the Project
• The plan is baselined (frozen) when it is sufficiently developed and stable
• Becomes the agreed Performance Measurement Baseline (PMB)
• PMB forms the basis for measurement • Should include all elements of the project • Should only be changed through a formal approval
process
29 © APM 2008. Reproduced under licence from APM
Data Collection
• Concerned with: – Ensuring that complete and accurate cost information is
collected in a timely manner to enable the transfer of actual cost information into the earned value management system
• Key activities: – Ensure that procedures are in place to protect the integrity of
bookings to work packages/control accounts, and that the correct booking/charge numbers are available
– Use the estimated actuals process as required to ensure that there are no variances due to payment lag
– Verify actual costs to ensure only valid costs are booked to valid booking/charge numbers
31 © APM 2008. Reproduced under licence from APM
Measuring costs and committed costs
• Actual cost of work performed (ACWP) include: – Labour costs (direct and indirect costs) – Direct expenses – Materials costs – Subcontractor costs for work done
• ACWP should be: – Collected at a level that will identify cost elements and factors
contributing to cost variance – Recorded in a manner consistent with the budget and include all
expenditure
• Ensure that BCWS, BCWP and ACWP are created in the same time frame
32 © APM 2008. Reproduced under licence from APM
Analysis Review and Action
• Concerned with: – The evaluation of the measured performance as compared to
the baseline plan
• Key activities: – Update control accounts with achievement, in line with the
calendar – Update schedule status and schedule forecasts, in line with the
calendar – Determine estimate to completion as required – Integrate whole project, to determine impact of critical path – Analyse variances to baseline, and focus on problem areas – Take corrective action as required
34 © APM 2008. Reproduced under licence from APM
Schedule Status
• When updating schedule status, consider: – Activity actual start/finish dates – Estimate of the time remaining to complete the task – Estimated start and finish dates of future activities
• Schedule status is determined by comparing how much time the activity is ahead or behind the baseline schedule
• Aspects of schedule assessment: – Review of the critical path activities – Review of schedule against key milestone forecasts – Review of future resource requirements
35 © APM 2008. Reproduced under licence from APM
Calculating and Reporting Earned Value
• Schedule Variance (SV) – SV = BCWP – BCWS – SV% = (SV/BCWS) X 100
• Cost Variance (CV) – CV = BCWP – ACWP – CV% = (CV/BCWP) X100
• Variance at Completion (VAC) • VAC = BAC – EAC • VAC% - (VAC/BAC) X100
36 © APM 2008. Reproduced under licence from APM
Calculating and Reporting Earned Value
• Schedule Performance Index (SPI) – SPI = BCWP/BCWS
• Cost Performance Index (CPI) – CPI = BCWP/ACWP
37 © APM 2008. Reproduced under licence from APM
Reporting Graphs
38 TIME
CO
ST
Planned completion
Planned Budget
BAC
Planned budget (BCWS)
BAC Budget at completion BCWS Budgeted Cost of Work Scheduled
© APM 2008. Reproduced under licence from APM
Reporting Graphs
39 TIME
CO
ST
Planned completion
Planned Budget
BAC
Planned budget (BCWS)
Earned value (BCWP)
Time ‘now’
BAC Budget at completion BCWS Budgeted Cost of Work Scheduled OD Original Duration planned ATE Actual Time Expended ACWP Actual Cost of Work Performed BCWP Budget Cost of Work Performed
OD ATE
Actual Cost (ACWP)
© APM 2008. Reproduced under licence from APM
Reporting Graphs
40 TIME
CO
ST
Planned completion
Planned Budget
BAC
Planned budget (BCWS)
Actual Cost (ACWP)
Earned value (BCWP)
OD ATE
Time ‘now’
BAC Budget at completion BCWS Budgeted Cost of Work Scheduled OD Original Duration planned ATE Actual Time Expended ACWP Actual Cost of Work Performed BCWP Budget Cost of Work Performed EAC Estimate Cost at Completion ETC Estimate Time at Completion
Schedule Variance (time)
Schedule Variance (cost)
Cost variance
© APM 2008. Reproduced under licence from APM
Variance Thresholds
41
CPI > 1, SPI < 1 Under spent and late
CPI < 1, SPI > 1 Over spent and early
CPI > 1, SPI > 1 Under spent and early
CPI < 1, SPI < 1 Over spent and late
COST PERFORMANCE
INDEX (CPI)
SCHEDULE PERFORMANCE
INDEX (SPI)
1
1
© APM 2008. Reproduced under licence from APM
Performance Trend Charts
42
VARIANCE
Positive
Negative
TIME
Schedule Variance
Cost Variance
© APM 2008. Reproduced under licence from APM
Estimates at Completion
• EAC = ACWP Cumulative + ETC (Estimate to completion)
• Based on the best estimates of the costs still to be incurred
43 © APM 2008. Reproduced under licence from APM
Simple Tests of Reasonableness
• Current performance indicators (SPI and CPI) should be compared with the anticipated performance to achieve either the BAC or the EAC
• To complete performance index (TCPI) provides a means of doing this comparison
• TCPI (BAC) = BAC – BCWP BAC – ACWP
• TCPI (EAC) = BAC – BCWP
EAC – ACWP
44 © APM 2008. Reproduced under licence from APM
TCPI Period
1 2 3 4 5 BCWS 10 20 50 80 120 BCWP 10 10 20 60 100 ACWP 12 15 30 80 110
BAC 120 120 120 120 120 EAC 120 130 160 150 130
CPI 0.83 0.67 0.67 0.75 0.91
TCPI(BAC) 1.02 1.05 1.11 1.50 2.00 TCPI(EAC) 1.02 0.96 0.77 0.86 1.00
45 © APM 2008. Reproduced under licence from APM
Checking forecast costs and dates
• To extrapolate future cost assuming past performance:
• EAC = BAC / CPI
• ETC = (BAC – BCWP) CPI
• To extrapolate future dates assuming past performance:
• Forecast Completion = Original Completion / CPI
46 © APM 2008. Reproduced under licence from APM
47
Reporting Graphs
TIME
CO
ST
Planned completion
Planned Budget
BAC
Planned budget (BCWS)
EAC
Forecast project
time slip
Actual Cost (ACWP)
Earned value (BCWP)
OD ATE
Forecast cost
overrun Time ‘now’
BAC Budget at completion BCWS Budgeted Cost of Work Scheduled OD Original Duration planned ATE Actual Time Expended ACWP Actual Cost of Work Performed BCWP Budget Cost of Work Performed EAC Estimate Cost at Completion
Schedule Variance (time)
Schedule Variance (cost)
Cost variance
Forecast completion
© APM 2008. Reproduced under licence from APM
Change Management
• The change management process ensures change is assessed and incorporated into the project baseline in a timely and controlled manner
• Key activities: – Identify and raise necessary changes to the control account – Integrate, where applicable, change to associated risks – Ensure that all changes to the performance measurement
baseline (PMB) are reflected within the associated forecast plans – Ensure that changes are embodied within all elements of
management systems (toolset, documentation, reports etc) – Seek appropriate approval for change.
49 © APM 2008. Reproduced under licence from APM
Maintaining Integrity
• Changes to past, present and future information should be embodied in the PMB in an orderly and and documented manner
• Approved project baseline is the time-phased budget against which progress and performance are measured and reported (BCWS)
• Current baseline must be traceable back to the original baseline
50
Contract Budget Baseline (CBB)
Performance Measurement Baseline (PMB)
Margin
Management Reserve
© APM 2008. Reproduced under licence from APM
When to Make Changes
• Conditions that do not warrant change: – There has been an overspend – There has been a delay
• Conditions that do warrant change: – An authorised change to the scope, cost or schedule of the
project – Changes to standard rates (e.g. labour, materials or overhead) – Work and budget transfer between control accounts
51 © APM 2008. Reproduced under licence from APM
How to Make Changes
• Baselines are updated by either: – Adding extra budget for additional work scope, and/or – Transferring management reserve into the budget baseline
• Additional budgets can be incorporated by: – Generating new work packages – Closing existing work pages and opening new work packages
• Additional budget must not be assigned to closed work packages
52 © APM 2008. Reproduced under licence from APM
Risk Management
• The integration of EVM and risk management should provide more realistic earned value assessments and give a better estimate of the project completion cost and timescale
• Key activities: – Risk identification – Risk assessment – Produce response strategy
54 © APM 2008. Reproduced under licence from APM
Benefits of Risk Management
• More realistic business and project planning • Actions being implemented in time to be effective • Greater certainty of achieving business goals and project
objectives • Appreciation of, and readiness to exploit, all beneficial
opportunities • Improved loss control • Improved control of project and business costs • Increased flexibility • Greater control over innovation and business
development • Fewer costly surprises
55 © APM 2008. Reproduced under licence from APM
Integrating Risk Management with EVM
• Estimating project activities (cost and schedule) • Establishing management reserve budget • Creating and controlling the budget and schedule for the
risk management process • Scheduling • Including risk management activities in project
performance analysis • Developing forecasts • Change management
56 © APM 2008. Reproduced under licence from APM
System Review
• Benefits – Confirm that an integrated project management system exists – Provide a fixed cut-off point to conclude the planning phase – Validate reliable performance data – Reduce risk – Ensure that experience from previous projects is captured – Put the focus on performance measurement
• Three main categories – Integrated baseline review (IBR) – Demonstration review – Surveillance
58 © APM 2008. Reproduced under licence from APM
EVM Reviews
59
Integrated Baseline Review
Assesses the content and
integrity of the Performance Management
Baseline
Surveillance To confirm that standards are being maintained
throughout the remainder of the project
Demonstration Review Assesses the EVM System against the EV guidelines.
• Organisation • Planning, scheduling,
budgeting • Accounting
• Analysis and management reports
• Revisions and data maintenance
© APM 2008. Reproduced under licence from APM
Steve Wake EVA booklet APM Guideline for EV PMI Practice standard
Foundation exan Practitioner exam Earned Schedule
EV Compass EV and Risk
60
Thanks
[email protected] 0788 764 4125
www.acoste.org
The Association of Cost Engineers
Company Logo