Upload
march
View
52
Download
0
Embed Size (px)
DESCRIPTION
Earned Value Analysis. Earned Value Analysis compares the Current Project status with the Baseline Plan Earned Value for a task = (budgeted cost of task)x(% completion of task) Task Progress Conventions Estimated by a knowledgeable unbiased assessor - PowerPoint PPT Presentation
Citation preview
Earned Value Analysis
Earned Value Analysis compares the Current Project status with the Baseline Plan
Earned Value for a task =
(budgeted cost of task)x(% completion of task)Task Progress Conventions
Estimated by a knowledgeable unbiased assessor X% complete when task started and other (1-X)%
when task finished. Usually 50-50 or 0-100
Earned Value for the entire project is the summation of earned values for all tasks
04/21/23 Ardavan Asef-Vaziri 7-1
PV, EV, and AC
PV: Planned Value, baseline cost of scheduled work. Also known as Budgeted Cost of Work Scheduled (BCWS)
AC: Actual cost of work performed. Also shown by (ACWP)
EV: Earned Value, budgeted cost of work performed. Also shown by (BCWP)
04/21/23 Ardavan Asef-Vaziri 7-2
Control System Example 1
Week 2: Task expenses = 460 worker-hours
370
380
390
400
410
420
430
440
450
460
470
1 2 3 4
Week
Cos
t (i
n w
ork
er-h
ours
)
WeekPlanned Cost
(BCWS) Actual Cost
Cumulative Actual Cost
(ACWP)
1 400 420 4202 400 460 880
Is the task “out of control”?
Actual
Planned
04/21/23 Ardavan Asef-Vaziri 7-3
Control System Example 1
Week 3: Task expenses = 500 worker-hrs
WeekPlanned cost
(worker-hours)Actual cost
(worker-hours)Cumulative cost (worker-hours)
1 400 420 4202 400 460 8803 400 500 1380
Again, is the task “out of control”?
0
100
200
300
400
500
600
1 2 3 4
Week
Wor
ker-
hour
s
Actual
Planned
04/21/23 Ardavan Asef-Vaziri 7-4
Controlling Projects
Key decisions in controlling performance in project management: What is the optimal review frequency? What are appropriate acceptance levels at each review stage?
“Both over-managed and under-managed development processes result in lengthy design lead time and high development costs.”
R.H. Ahmadi, R. Wang. 1999. Managing Development Risk in Product Design Processes. Operations Research 47, 235-246
04/21/23 Ardavan Asef-Vaziri 7-5
6
Types of System Variation
Common cause variation: “in-control” or normal variation
Special cause variation: variation caused by forces that are outside the system
Treating common cause variation as if it were special cause variation is called “tampering”
Tampering always degrades the performance of a system – W.E. Deming
04/21/23 Ardavan Asef-Vaziri 7-6
7
Performance Metrics for Example 1
PV: Planned Value, baseline cost of scheduled work. AC: Actual cost of work performed. EV: Earned Value, budgeted cost of work performed. PWC: percentage of work completed.
Week PV AC PWC EV1 400 420 23% 3682 800 880 50% 8003 1,200 1,380 85% 13604 1,600 1,500 100% 1600
04/21/23 Ardavan Asef-Vaziri 7-7
Schedule Variance
Schedule variance: difference between value of work completed and value of scheduled work SV = EV – PV
04/21/23 Ardavan Asef-Vaziri 7-8
Week PV AC PWC EV SV1 400 420 23% 368 -322 800 880 50% 800 03 1,200 1,380 85% 1360 1604 1,600 1,500 100% 1600 0
Cost Variance
Cost variance: difference between value of work completed and actual expenditures CV = EV – AC
04/21/23 Ardavan Asef-Vaziri 7-9
Week PV AC PWC EV SV CV1 400 420 23% 368 -32 -522 800 880 50% 800 0 -803 1,200 1,380 85% 1360 160 -204 1,600 1,500 100% 1600 0 100
Total Variance
Total variance: Cost Variance–Schedule Variance
=(EV-AC)-(EV-PV) TV = PV – AC
04/21/23 Ardavan Asef-Vaziri 7-10
Week PV AC PWC EV SV CV TV1 400 420 23% 368 -32 -52 -202 800 880 50% 800 0 -80 -803 1,200 1,380 85% 1360 160 -20 -1804 1,600 1,500 100% 1600 0 100 100
Earned Value Chart
04/21/23 Ardavan Asef-Vaziri
TimeNow
Dol
lars
Schedulevariance
Costvariance
PV(baseline)
AC
EV
Actual cost
Value completed (Earned Value)
7-11
Earned Value Chart 2
04/21/23 Ardavan Asef-Vaziri
Time
Dol
lars
PVAC
EV
7-12
Earned Value Chart 3
04/21/23 Ardavan Asef-Vaziri
Time
Dol
lars
PV
AC
EV
7-13
Earned Value Chart 4
04/21/23 Ardavan Asef-Vaziri
Time
Dol
lars
PV
AC
EV
7-14
Earned Value Chart 5
04/21/23 Ardavan Asef-Vaziri
Time
Dol
lars
PV
AC
EV
7-15
Earned Value Chart 6
04/21/23 Ardavan Asef-Vaziri
Time
Dol
lars
PV
AC
EV
7-16
Control System Example 2
Progress report at the end of week #5:
Cumulative Percent of Work Completed:
Worker-Hours Charged to Project:
04/21/23 Ardavan Asef-Vaziri 7-17
Control System Example 2
We ekPlan 1 2 3 4 5 6 7 8 9 10 TotalTask A 6 6 6 8 10 36Task B 12 12 12 36Task C 10 10 12 12 12 56Scheduled work-hrs 6 6 6 20 22 22 10 12 12 12PV work-hrs 6 12 18 38 60 82 92 104 116 128
04/21/23 Ardavan Asef-Vaziri 7-18
Control System Example 2
We ekPlan 1 2 3 4 5 6 7 8 9 10 TotalTask A 6 6 6 8 10 36Task B 12 12 12 36Task C 10 10 12 12 12 56Scheduled work-hrs 6 6 6 20 22 22 10 12 12 12PV work-hrs 6 12 18 38 60 82 92 104 116 128Actual 1 2 3 4 5 6 7 8 9 10Task A 5 6 8 10 10Task B 15 10Task CActual work-hrs 5 6 8 25 20AC 5 11 19 44 64
04/21/23 Ardavan Asef-Vaziri 7-19
Control System Example 2
04/21/23 Ardavan Asef-Vaziri 7-20
We ekPlan 1 2 3 4 5 6 7 8 9 10 TotalTask A 6 6 6 8 10 36Task B 12 12 12 36Task C 10 10 12 12 12 56Scheduled work-hrs 6 6 6 20 22 22 10 12 12 12PV work-hrs 6 12 18 38 60 82 92 104 116 128Actual 1 2 3 4 5 6 7 8 9 10Task A 5 6 8 10 10Task B 15 10Task CActual work-hrs 5 6 8 25 20AC 5 11 19 44 64% work completed 1 2 3 4 5 6 7 8 9 10Task A 0.15 0.3 0.4 0.6 0.8Task B 0.25 0.65Task C% work completed 1 2 3 4 5 6 7 8 9 10Task A 5.4 10.8 14.4 21.6 28.8Task B 9 23.4Task CEV 5.4 10.8 14.4 30.6 52.2
SV -0.60 -1.20 -3.60 -7.40 -7.80CV 0.40 -0.20 -4.60 -13.40 -11.80
Schedule and Cost Indices
SPI: Schedule Performance Index SPI = EV / PV CPI: Cost Performance Index CPI = EV / AC
04/21/23 Ardavan Asef-Vaziri 7-21
We ekPlan 1 2 3 4 5 6 7 8 9 10PV work-hrs 6 12 18 38 60 82 92 104 116 128AC 5 11 19 44 64EV 5.4 10.8 14.4 30.6 52.2
SV -0.60 -1.20 -3.60 -7.40 -7.80CV 0.40 -0.20 -4.60 -13.40 -11.80SPI 0.900 0.900 0.800 0.805 0.870CPI 1.080 0.982 0.758 0.695 0.816
Budget and Estimate at Completion
04/21/23 Ardavan Asef-Vaziri 7-22
BAC: Budget At Completion EAC: Estimate At Completion ETC: Estimated to Completion
Updating Forecasts: Future is the same as actual
Assumes that the progress in future is the same as actual
04/21/23 Ardavan Asef-Vaziri 7-23
9.92649.156
9.156816.0
128
ACEACETC
EAC
CPI
BACEAC
Updating Forecasts: Future is the same as schedule (Example 2)
Assumes that the progress in future is the same as schedule
04/21/23 Ardavan Asef-Vaziri 7-24
8.65648.139
8.1398.11128
ACEACETC
EAC
CVBACEAC
TIME To Completion: (Example 2)
04/21/23 Ardavan Asef-Vaziri 7-25
Weeks5.655.11CompletionToTime
CompletionToTime
5.1187.0
10
nowp
p
pp
-TET
ET
SPI
TET
Assumes that the progress in future is the same as actual
Tp: Project duration
ETp: Estimated project duration
Tnow: Elapsed time
Updating Forecasts: Optimistic Viewpoint (Example 2)
04/21/23 Ardavan Asef-Vaziri 7-26
Weeks75.5575.10CompletionToTime
-CompletionToTime
75.10)75.0(10
7500.87
55
-Variance Time
nowp
p
pp
nownow
TET
ET
tVTET
.tV
SPI
TTtV
Assumes that the progress in future is the same as schedule
Example 3
Budgeted cost for finished task = $850K. Actual cost to date = $550K; Task is 70% complete, but was scheduled to be 80% complete by now. The project was scheduled for 12 months. It is now end of month 10.
AC = 550, PV = 0.8×850 = 680, EV = 0.7×850 = 595
Cost variance = EV – AC = +45
Schedule variance = EV – PV = -85
CPI = EV / AC = 1.082
SPI = EV / PV = 0.875
04/21/23 Ardavan Asef-Vaziri 7-27
Example 3
BAC= 850. AC = 550; % Complete = 70%, Scheduled % Complete = 80%. Scheduled Duration = 12 months, now = end of month 10. PV = 0.8×850 = 680, EV = 0.7×850 = 595
CV = EV – AC = +45, SV = EV – PV = -85
CPI = EV / AC = 1.082, SPI = EV / PV = 0.875
Estimated Remaining Cost = 850/1.082 -550= 236
Estimated Remaining Time = Tp/0.875 –Tnow= 12/0.875-10 = 13.71-10 = 3.71 months
Estimated Remaining Cost = 850-CV -AC= 850-(45) – 550 = 255
tV = Tnow - Tnow /0.875 =- 1.43
Estimated Remaining Time = Tp –tV – Tnow = = 12- (-1.43) – 10 = 3.43 months
04/21/23 Ardavan Asef-Vaziri 7-28
Critical Ratio
The critical ratio is the product of a schedule ratio and a cost ratio. Indicates when a task or process is becoming unacceptable, typically when the ratio drops below 1.
04/21/23 Ardavan Asef-Vaziri
cost actual
progress actualfor cost budgeted
progress scheduled
progress actual
04/21/23 Ardavan Asef-Vaziri 7-29
If both progress and budget are on the same curve, then it is
ACPV
EV
AC
EV
PV
EV
2
Monitoring the Critical Ratio
Although Task 1 is behind schedule, the cost is correspondingly below budget so everything is fine if lateness is no problem for this activity.
Task 2 is on budget but progress is lacking so too much money was spent than should have been spent; when the project is completed, it will probably go over budget.
04/21/23 Ardavan Asef-Vaziri04/21/23 Ardavan Asef-Vaziri 7-30
Critical Ratios With Control Limits
04/21/23 Ardavan Asef-Vaziri 7-31
Cost Control Chart
04/21/23 Ardavan Asef-Vaziri 7-32