    Erection All Risk Insurance

  • 7/24/2019 EAR Insurance Presentation

    2/19

    Project Insurance

    Insured Parties

    Principal Employer

    Manufacturer

    Contractor Sub-contractor& Insurer

    Any one or more of the following

  • 7/24/2019 EAR Insurance Presentation

    3/19

    Erection All Risk

    Basic concept

    Comprehensive cover against all the risk

    involved in the

    Storage

    Erection

    Testing and

    Commissioning

    of machinery & plant pertaining to various

    Industries

  • 7/24/2019 EAR Insurance Presentation

    4/19

    Erection All Risk

    CoverSudden and unforeseen loss or damage due to

    Fire, lightning, explosion, aircraft damage Riot, strike, malicious act Flood, inundation, storm, cyclone and allied perils Landslide, subsidence and rockslide Burglary and theft Faults in erection Human errors, negligence, lack of skill Short circuiting, arcing, excess voltage Collapse, damage due to foreign objects, impact damages Earthquake (optional)Terrorism (optional)Any other sudden, unforeseen damages not explicitlyexcluded

  • 7/24/2019 EAR Insurance Presentation

    5/19

    Erection All Risk

    Interest

    Joint interest:

    The policy can be taken jointly bythe owner / principal covering the

    interests of all other parties

    Interest of Financial institution:

    Insured must specify clearly ifinterest of Financial Institution orBank is required to be covered

  • 7/24/2019 EAR Insurance Presentation

    6/19

    Erection All Risk

    Period of cover

    Erection period according to the contract requirement

    Testing period - Normally 1 month but may be more than a month

    depending on actualrequirement

    Maintenance period begins from the day testing of the plant is declared

    completed upto the periodbased on requirement

  • 7/24/2019 EAR Insurance Presentation

    7/19

    Erection All Risk

    Insured Period

    Taken into use

    Works Testing Maintenance

    EAR Operational

    Commencementof Works

    Provisional AcceptanceCertificate

    Final Acceptance

  • 7/24/2019 EAR Insurance Presentation

    8/19

    Erection All Risk

    Sum insured

    Completely erected value of the propertyinclusive of

    Freights

    Customs duty

    Erection cost

  • 7/24/2019 EAR Insurance Presentation

    9/19

    Erection All Risk

    Exclusion

    Types:

    General Market Exclusions

    Trade Risks

    Risks more exactly the Subject matter

    of Other Insurance

  • 7/24/2019 EAR Insurance Presentation

    10/19

    Erection All Risk

    General Market Exclusions

    War Invasion Riot Strike Civil

    Commotion etc

    Nuclear Reaction Nuclear Radiation

    or Radioactive Contamination

    Insureds Contribution Deductible

    Wilful Act or Wilful Negligence of

    the Insured

    Cessation of Work

  • 7/24/2019 EAR Insurance Presentation

    11/19

    Erection All Risk

    Trade risk

    Defective Material or Bad workmanship

    Wear Tear Corrosion Oxidation Deterioration

    Normal Maintenance or Making Good

    Disappearance or Shortage (Inventory Losses)

    Risks more exactly the Subject matter of Other Insurance

    Design Defects

    Loss of files, drawings, cash, cheques etc,.

    Consequential Loss

  • 7/24/2019 EAR Insurance Presentation

    12/19

    Erection All Risk

    Add-on covers

    Third party liability

    Cross liability

    Cost of removal of debris,

    Express freight,overtime charges,

    Air freight,

    Custom duty

    Escalation

    Owners surrounding property

    Storage risk at Fabricators Premises

  • 7/24/2019 EAR Insurance Presentation

    13/19

    Project Insurance

    IMPORTANT ADD-ONS:

    Third-party exposure to nearby structures by excavationand foundation work and to traffic

    Third Party Liability

  • 7/24/2019 EAR Insurance Presentation

    14/19

    Project Insurance

    Add-on covers

    The cost of debris removalfollowing an accident to the

    Extent that it is necessary

    Before repairs may be put

    In hand

    Removal of Debris

  • 7/24/2019 EAR Insurance Presentation

    15/19

    Project Insurance

    Add-on covers

    The integration of an oldhotel into the new projectrepresented a high exposureof the Principals existing property

    Surrounding Property

  • 7/24/2019 EAR Insurance Presentation

    16/19

    Erection All Risk

    Physical Hazards

    Pre-erection and storage:

    Fire

    Theft

    Water Damage

    AOG Perils

    Material Handling Equipments

    Improper StorageActs of god

  • 7/24/2019 EAR Insurance Presentation

    17/19

    Erection All Risk

    Physical Hazards

    Construction & erection:

    Working at Heights

    Heavy Lifts

    Handling of Over Dimensioned Items & Electrical Equipments

    Civil Construction Requirements

    Fire & AOG Perils

    Theft

  • 7/24/2019 EAR Insurance Presentation

    18/19

    Erection All Risk

    Physical Hazards

    Testing & commissioning:

    Failure of Controls & Safety Device

    Chemical Leakages

    Controls & Instrument Failure

    Failure of Material under Pressure

    Human Error & Negligence

    Explosion.

    ErectionErrors

  • 7/24/2019 EAR Insurance Presentation

    19/19

    Erection All Risk

    Basis of settlement

    Partial loss:

    The cost of repairs necessary to restore the items to theircondition immediately before the occurrence of the damage

    less salvage, OR

    Total loss:

    The actual value of the items immediately before theoccurrence of the loss less salvage;

    However, only to the extent the costs claimed has to be borne

    by the Insured and to the extent they are included in the

    Sum Insured