28
water resource specialists LAR BPWG DWR Erosion Screening Process Application to LAR May 17, 2016 water resource specialists

DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

LAR BPWGDWR Erosion Screening Process

Application to LARMay 17, 2016

water resource specialists

Page 2: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

Presentation Outline

• Review of Erosion Screening Process• Modifications for LAR Application• ESP LAR Results• Recommendations

Page 3: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP Background

• AECOM November 17, 2015 Presentation• General Purpose• Caveats and Limitations• Three Tiers or Steps • Cross Section Based• Total Erosion (Wind and Waves)

Page 4: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP Tier 1 Analysis

• Pass/Fail Analysis• Soil Erodibility• Levee Geometry• Fetch length• Historical Performance

Page 5: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP Tier 1 Levee Geometry

Page 6: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP Tier 2 Analysis

• Pass/Fail Analysis• Applied vs Critical Velocity• Applied vs Critical Shear (wind)• Field Reconnaissance

Page 7: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP Tier 2 Example (RM 8.5R)

10

15

20

25

30

35

40

45

50

55

60

6450 6500 6550 6600 6650 6700 6750 680

Elevation (ft NAVD88)

Station (ft)

American River RM 8.5Right levee

Max WSE (unsteady HEC‐RAS)

HEC‐RAS cross‐section

LiDAR

Min levee template (Max WSE+3 ft)

3H:1V

2H:1V

Page 8: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP Tier 2 Example (RM 8.5)

0

1

2

3

4

5

6

7

8

9

10

11

12

0

5

10

15

20

25

30

35

40

45

50

55

60

5500 5600 5700 5800 5900 6000 6100 6200 6300 6400 6500 6600 6700 6800

Velocity (ft/s)

Elevation (ft NAVD88)

Station (ft)

American River RM 8.5Max WSE (unsteady HEC‐RAS)

WSE (RMA2 160K)

Bed (HEC‐RAS)

Bed (RMA2)

Vel (HEC‐RAS)

Vel (RMA2 160K)

Page 9: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP Tier 3 Analysis

• Applied to Sites that fail Tiers 1 and 2• Horizontal Extent of Wind Wave Erosion• Horizontal Extent of Velocity Erosion• Assigns Priorities based on TE/LW

Page 10: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP Tier 3 Risk Categories

Page 11: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Modifications

• Separate Wind Wave/Velocity Erosion• Separate Levee/Bank Toe Erosion• Analyze encroachment into levee prism to

assign priorities

Page 12: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Nomenclature

Page 13: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Data Requirements

• Levee and River Geometry• 200-Year Hydrograph• 200-Year Velocities• Soil Types (levees/foundation)• Vegetation and Riprap Protection

Page 14: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Geometry

Page 15: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR 200-Year Hydrograph

0

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

180,000

144 168 192 216 240 264 288 312 336 360 384 408 432 456 480 504 528

Flow

 (cfs)

Time (hrs)

American River

RM 22

RM 13.22

RM 9.146

RM 7.631

RM 6.951

RM 3.913

1st Peak (160,000 cfs ) = 39 hrs

2nd Peak (115,000 cfs ) = 107 hrs (total)

Page 16: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Hydraulics (RM 3.5)

0

1

2

3

4

5

6

7

8

9

10

‐20

‐10

0

10

20

30

40

50

60

70

80

5400 5600 5800 6000 6200 6400 6600 6800 7000 7200 7400 7600 7800 8000

Velocity (ft/s)

Elevation (ft NAVD88)

Station (ft)

American River RM 3.5

Max WSE (unsteady HEC‐RAS)

WSE (RMA2 160K)

Bed (HEC‐RAS)

Bed (RMA2)

Vel (HEC‐RAS)

Vel (RMA2 160K)

Page 17: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Soils and Slope Cover

• Based primarily on field investigations• Supplemented by borings, maps showing

extent of bank protection

Page 18: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Tier 1 Results

• All sections failed soil erosion susceptibility and fetch tests

• All sections re-considered in Tier 2

Page 19: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Tier 2 Results

• Nearly all sites failed the wind wave erosion test

• All sites re-considered in Tier 3

Page 20: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Tier 3 Calculations

• Horizontal extent of erosion calculated at levee and bank toe

• Erosion only occurs when applied exceed critical Velocities

• Erodibility coefficient for soils (ft3/lb-hour)• Difference between Applied and Critical

Shear Stress• Duration of the particular flow

Page 21: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Levee Toe Erosion

Erosion (ft) Class

0 0.1 to 5 5.1 to 10 10.1 to 20 > 20

Number of Observations

35 0 4 5 5

Page 22: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Bank Toe Erosion

Erosion (ft) Class

0 0.1 to 5 5.1 to 10 10.1 to 20 > 20

Number of Observations

27 0 1 2 3

Page 23: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Risk Categories

• Based on erosion encroaching into levee template or prism

• High – encroaches into prism• Medium – close to prism• Low – distant from prism

Page 24: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Encroachment Example

Page 25: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Erosion Risks

Page 26: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR High Risk Sites

• Main risk is erosion into prism at levee toe• RM 1.75L to 2.25L• RM 2.65L to 2.85L• RM 3.75L to 4.25L• RM 8.2L to 9.5L• RM 7.0R to 8.5R

Page 27: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

ESP LAR Recommendations

• High Risk Levee Embankment: 4 miles• Lengths approximate• Critical velocities an issue• RM 7.0R to 8.5R: Levee erosion risk also

bank erosion occurs. • RM 7.0R to 8.5R: highest priority site for

BPWG from ESP

Page 28: DWR Erosion Screening Process Application to LAR · • AECOM November 17, 2015 Presentation • General Purpose • Caveats and Limitations • Three Tiers or Steps • Cross Section

water resource specialists

Questions?