Dudley Creek Work Notice Stage 4 Petrie Street works overview 8 June 2016 Dudley Creek Project - Overview The Dudley Creek flood remediation works have progressed after extensive consultation with the community, where several options were considered. These options took into account the impact on residents and the environment, as well as reducing the flood risk in the Flockton area. The Stapletons Road option that was chosen had the added advantage of enhancing the landscape in the longer term, with an improved overall quality of trees, and improved walkways and access to the waterway. For more information, visit www.ccc.govt.nz/floodmitigation and click on Avon Catchment ’, and Dudley Creek’. And pages 15-21 in the Christchurch City Council consultation document, http://resources.ccc.govt.nz/haveyoursay/ dudleycreekconsulationbooklet.pdf or contact the Council on 03 941 8999. Image 1: Stage 4 Petrie Street works Stage 4 Petrie Street works are due to start this month, with bypass works to follow in August. See more information and timeline of works overleaf. There is a road closure associated with this work from July 2016-January 2017

Dudley Creek Work Notice 8 June 2016 Stage 4 Petrie … · Dudley Creek Work Notice Stage 4 Petrie Street works overview 8 June 2016 Dudley Creek Project -Overview The Dudley Creek

Embed Size (px)

Citation preview

Dudley Creek Work Notice

Stage 4 Petrie Street works overview

8 June 2016

Dudley Creek Project - Overview

The Dudley Creek flood remediation works have progressed after extensive consultation with the community, where

several options were considered. These options took into account the impact on residents and the environment, as

well as reducing the flood risk in the Flockton area.

The Stapletons Road option that was chosen had the added advantage of enhancing the landscape in the longer

term, with an improved overall quality of trees, and improved walkways and access to the waterway.

For more information, visit www.ccc.govt.nz/floodmitigation and click on ‘Avon Catchment’, and ‘Dudley Creek’.

And pages 15-21 in the Christchurch City Council consultation document, http://resources.ccc.govt.nz/haveyoursay/

dudleycreekconsulationbooklet.pdf or contact the Council on 03 941 8999.

Image 1: Stage 4 Petrie Street works

Stage 4 Petrie Street works are due to start this month, with bypass works to follow in August.

See more information and timeline of works overleaf.

There is a road closure

associated with this work

from July 2016-January 2017

Need more information? Contact Downer on 0800 033 747 or

email [email protected]

What we are doing

This month Downer will begin preparing the Stage 4 Petrie Street site for the localised widening of Dudley

Creek between Stapletons Road and Petrie Street. This involves the demolition of 71 Petrie Street and

70/70A Stapletons Road, and replacing the Petrie Street culvert.

As a separate package of work, we will also be constructing a large intake structure at the Petrie Street site,

that when connected to the underground piped bypass will help increase the capacity for floodwater in

Dudley Creek. You will get a separate notice about these works later this month.

See indicative timeline of works below, and general impact information overleaf.

Stage 4 Petrie Street works timeline

Works are subject to favourable weather and on-site conditions, these dates are indicative only.

You will be updated as work progresses, please check your mailbox.

7 - 15th June

Site establishment and asbestos removal at

71 Petrie Street and 70/70A Stapletons Road.

16 - 24th June

Demolition and disestablishment of 71 Petrie

Street and 70/70A Stapletons Road. July 2016 until January 2017

Petrie Street road closure outside 74 Petrie

Street. Affected residents will be contacted

soon.

July

Service diversions of the Chorus/Enable/

Vodafone cables from outside 62 to 74 Petrie

Street. This work will take about 3 weeks.

Tree removals (approximately 20) within the

Petrie Street worksite and on private property.

Installation of

the Petrie

Street sheet

piling. These

works will be

undertaken

during normal

working hours,

7am-6pm.

Precondition surveys of private properties are

currently being undertaken along the bypass route.

Removal of sheet piles will be in October.

Please expect increased levels of vibration, and

noise from the dewatering pumps during this

time.

Late July / early August

An example of sheet pile installation

Petrie Street

culvert

works.

Removing the

old culvert and

constructing

the new

culvert.

There will be increased noise, dust and vibration

levels associated with this work.

Late July until October

New box culvert installation on Warden Street

July and August

Ground stabilisation works, also known as in

situ mass stabilisation (IMS). This work will take 1-2

months.

This work involves a large digger excavating a 3

metre wide strip along the full length of the worksite,

blending, circulating, and kneading the soil and

mixing it with cement. When completed the 3 metre

by 4 metre block will be a homogenous mixture of

cement and existing soils. This will act as

underground wall, and help stabilise the ground and

stop it from slumping toward the creek.

Timeline continues overleaf

Need more information? Contact Downer on 0800 033 747 or

email [email protected]

August

Bypass and intake works expected to start. You

will get another notice about these works later this

month.

August

Private property work. Property owners will be

contacted individually.

Winter 2017

Petrie Street road reconstruction. You will get

another notice about these works closer to the time.

Stage 4 Petrie Street works timeline continued

Works are subject to favourable weather and on-site conditions, these dates are indicative only.

September

Once ground improvements are finished, we will

start the landscaping between Petrie Street and

Stapletons Road. This work includes: creating new

fresh plains, creek works, planting, and a new path.

See image 1 on page 1.

Stage 1 running from Slater St to Chancellor

Street is now completed with new fresh plains,

rock edge and planting.

Downer are pleased to be working on this exciting project. Our experienced team are keen to

become part of your community. Over the coming weeks you can expect to see Downer staff,

introducing:

Alex Mowe

Project Manager Chiara Tucker

Stakeholder

Coordinator

Dean Ewen

Project Engineer

Harry Brand

Project Engineer

Jake Richmond

Site Supervisor

Tom Harding-Ilott

Site Engineer

General information

There will be increased noise, dust and

vibration levels associated with these

work.

The work area will be fenced off. Safety is

our number one priority. Safety is your

responsibility too. Stay clear and stay alert -

keep children and pets at a safe distance

from the worksites.

Works have no planned impact on current

power, telecommunication, water or gas

services. However, the network is still fragile

so please be prepared in case there is an

unexpected service cut off.

Our standard work hours are Monday to

Friday between the hours of 7.00am and

6.00pm. On occasions we may have to work

on a Saturday to complete essential work.

You will be updated as work progresses,

please check your mailbox.