Gopal Prasad Sigdel, Joint secretary, Ministry of Physical Planning and Transport
NepalNew Delhi ,Aug 1-2, 2018
Status
of
DryPorts
Development
in Nepal
1
Kathmandu
NEPALArea : 147,181 Sq. Km.Population: 27.8 Mill. GDP Per capita : US$ 865
CHINA
2
Rasuwa (Rasuwa)
Yari (Humla)
Olangchungola Kimathanka (Taplejung)
(Sankhuwasabha)
Nechung(Mustang) NORTH
Riwu
Lizi
Pulan
Larke(Gorkha)
Mugu(Mugu)
Hyazimang
Dodhara Chadani (Kanchanpur)
ICD (Under Construction) (First Phase)
Second Phase(MOU)
Third Phase(MOU)
Inland ClearanceDepots(ICDs) Under Operation
Integrated Check Posts (ICPs)Proposed
Thhhhhiiiird
CFS/ICD
Major Trade & Transit Points of Nepal
Survey Designing Stage
Nepal Intermodal Transport Development Board, Kathamndu, Nepal, Phone: +977-1-4440936, 4439664, Email: [email protected]
Rasuwa (Rasuwa)
Olangchungola (Taplejung)
Yari (Humla)
Kimathanka(Sankhuwasabha)
Nechung(Mustang) NORTH
Riwu
Lizi
Pulan
Larke(Gorkha)
Mugu(Mugu)
Hyazimang
Dodhara Chadani (Kanchanpur)
Existing Railway Connectivity
Proposed Railway Connectivity
CFS/ICD
Status of Railway Connectivity
Nepal Intermodal Transport Development Board, Kathamndu, Nepal, Phone: +977-1-4440936, 4439664, Email: [email protected]
TRANSPORT INFRASTRUCTURE(2016)
ROADS LENGTH
STRATEGIC ROAD NETWORK 12498 KM
LOCAL ROAD NETWORK 57632 KM
RAILWAYS
JAYNAGAR(INDIA)-JANAKPUR 51 KM
RAXAUL(INDIA)- BIRGUNJ ICD 5 KM
AIRFIELDS
INTERNATIONAL 1 NO
DOMESTIC 48 NOS
DRY PORTS
ROAD BASED 4 NOS
RAIL BASED 1 NO
ROADS CONNECTING DRY PORTSDRY PORTS ROADS LENGTH CONNECTING STATUS AND FUTURE PLANS
BIRGUNJ ICD 29Km E/W HIGHWAYPathalaiya
6 Lane road under construction ICD under Operation
BIRATNAGAR ICD 31KM E/W HIGHWAYItahari
6 Lane Road under construction ICD under consideration
KAKARBHITTA ICD 1 KM E/W HIGHWAYKakadbhitta
Under Operation
BHAIRAHAWA ICD 24 KM E/W HIGHWAYButwal
6 Lane Road under construction
TATOPANI ICD 114 KM Kathmandu UNDER CONSTRUCTION
RASUAWAGADI 84 KM Galchhi PrithviHighway
UNDER CONSTRUCTION
DODHARA CHANDINI
9 KM Mahendranagar E/W HIGHWAY
UNDER CONSTRUCTION
KOROLLA 110 KM Jomsom Planned
KATHMANDU CHOBHAR
9 KM Kathmandu UNDER CONSTRUCTION
FOREIGN TRADE SITUATIONStatus of Nepal as perDoing Business Report 2015
Export Cost per container US$ 2545
Export Time 40 days
Import cost per container US$ 2650
Import Time 39 days
Stream Share of Total Trade(2016/17)
Export 6.9 %Import 93.09%
100%India 64.92%
Overseas 35.08%100%
4Source: WB & GON
Transport Infrastructure (2016)
8
Roads
Local Roads (57,632 Km) Strategic Roads (12,473 Km)
Railways
Jayanagar (India) - Janakpur (Nepal)(51 KM)
Raxaul (India) – Birgunj (Nepal) (5 KM)
Airfields
48 Nos. (registered)Dryports
Road based (3+1) Rail based(1)
DRY PORTS (RAIL BASED)
Dry Ports (Roadbased)
10
BIRATNAGAR BHAIRAHAWA
TATOPANIKAKARBHITTA
Dry Ports (Roadbased)
• BIRATNAGARBHAIRAHAWA
Dry Ports (Roadbased)
TATOPANIKAKARHITTA
13
DRY PORTS
BhairahawaBirgunj
Kakarbhitta Biratnagar
Tatopani (Under Construction)
UNESCAP
20
Future Dryports
15
• Under Construction:- Tatopani ICD
- Source: PR China (Turn Key)- Connectivity: Asian Highway 42 (AH42)
(Construction period is extended due to earthquake)
• Proposed:– Rasuwa: (Assistance : PRChina)
- Detail Design is about tofinalize.- Construction contract will be awarded soon.
– CFS/ICD at Kathmandu Valley (Assistance: WB):- Awaiting for Construction Tender Process.
– Korola (Mustang):- Pre-feasibility study has been completed.
– Dodhara Chadani (Kanchanpur)- AH2:- Feasibility study is ongoing.
Tatopani Dry Port (UnderConstruction)
23
Rescue Project
Rasuwa Dry PortLayout Design
Admin Building 5000 Sq.M
Warehouse 750 Sq.M.
Appraisal Shed 2nos.Total 2080 Sq.M.
Parking Area for 350 trucks
Kathmandu CFS/ICD (Google View)
18
Korola (Mustang)
19
Dodhara Chadani (Kanchanpur)
20
Challenges• Geological status of Roads and
Infrastructure• International Recognition of Dry ports• Transshipment facility and additional Port
Connectivity• International Guidelines for leasing out of
ports• Road carriage act and Regulation• Rail carriage act and regulation• Dry Port Management issues
(Managerial/Technical/Awareness)• Reduction in Import/Export Process 30
Way Forward:
• Cost of logistics and transit transportation forlandlocked countries is > 15% than coastal countries
• UNESCAP needs to address capacityactivities for managerial, technical and
buildingawareness
issues regarding dry port taking in mind of itsimportance
• Should conduct national levelactivities also
• International agency should focus on bringing outtransshipment,guidelines related to
Registration of LOCODE, Locate dryport leasing,port on the
international shipping map, etc.
• Ratification of Intergovernmental Agreement on Dryports
31