Drop wall (100mm) Cost break down and Total from BOQ I. CONCRETING WORKS A.) Material Cost of RMC (¾” agg., 6”-8” slump @ 28days): Batch cost / m3 - 1650 (including sand and gravel) Cement / m3 - 2340 (13 bags /m3) B.) Labor / m3 - 645 (Crane and bucket method) Total Labor & materials / m3 - 4635 / m3 Total Volume - 130m3 Total amount - 602,550 II. FORMWORKS A.) Material Cost / m2- 152.6 B.) Labor / m2 - 232.2 Total Labor & materials / m2 - 384.8 / m2 Total Volume - 2,572 m2 Total amount - 989,705.60 III. REBAR WORKS A.) Material Cost / kg - 32 B.) Labor / kg - 6.45

Drop Wall and Ret Wall sample estimate

Embed Size (px)

DESCRIPTION

Engineering

Citation preview

Drop wall (100mm) Cost break down and Total from BOQ

I. CONCRETING WORKSA.) Material Cost of RMC( agg., 6-8 slump @ 28days):Batch cost / m3-1650 (including sand and gravel) Cement / m3-2340 (13 bags /m3)B.) Labor / m3-645 (Crane and bucket method)Total Labor & materials / m3-4635 / m3Total Volume-130m3Total amount-602,550

II. FORMWORKSA.) Material Cost / m2-152.6B.) Labor / m2 -232.2Total Labor & materials / m2-384.8 / m2Total Volume-2,572 m2Total amount-989,705.60

III.REBAR WORKSA.) Material Cost / kg -32B.) Labor / kg-6.45Total Labor & materials / kg-38.45 / kgTotal Volume-14,300 kgTotal amount-549,835

Total Cost=2,142,087.6 (as per BOQ)

Total Cost / Area= 2,142,087.6 / 2752m2=778.38 / m2(considering both sides)Or1,556.76 / m2 (considering one side only)Retaining wall (200mm) Cost break down and Total from BOQ

I. CONCRETING WORKSA.) Material Cost of RMC( agg., 6-8 slump @ 28days):Batch cost / m3-1650 (including sand and gravel) Cement / m3-2340 (13 bags /m3)B.) Labor / m3-645 (Crane and bucket method)Total Labor & materials / m3-4635 / m3Total Volume-104.61m3Total amount-484,867.35

II. FORMWORKSA.) Material Cost / m2 -414B.) Labor / m2 -232.2Total Labor & materials / m2-646.2 / m2Total Area-1006.00 m2Total amount-650,077.2

III.REBAR WORKSA.) Material Cost / kg -32B.) Labor / kg-6.45Total Labor & materials / kg-38.45 / kgTotal kg-15,971.78 kgTotal amount-614,114.94

Total Cost=1,749,059.49(as per BOQ)

Total Cost / Area= 1,749,059.49 / 1006 m2=1738.63 / m2(considering both sides)Or3477.25 / m2 (considering one side only)