Drilling Efficiency

• Veritas Associates, Inc• For Conoco Indonesia• By Paul Baumgardner

Page 2: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

About This Program• This program was developed by the drilling

personnel of Global Marine UK Drilling Co. as a consequence of GM UK being awarded a five well turnkey job for Fina Oil and a four well incentive alliance drilling program, both in the UK North Sea.

• The program was developed with the idea that working efficiently would reduce the time and costs of drilling the wells without compromising safety or causing damage to the drilling equipment.

Page 3: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Drilling Efficiency Overview

• The Concept Consists of the Following:• Morning Meetings

• Meetings are not more that 20 minutes• Should involve drilling contractor supervisors, all

Operator representatives and third party personnel that will be involved in the drilling program for that day

• Meetings should be a daily program

Page 4: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Drilling Efficiency Overview Continued

• Tool Box Meetings• Crew level meetings, i.e. driller and drill crew,

crane operator and roustabout crew, mechanic/chief engineer and maintenance crew.

• Checklists• Needs to cover the activities of that day.• Needs to cover all aspects of the job.• Needs to assign a person responsible.• Allows the responsible person to sign off that

the job has been done.

Page 5: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Drilling Efficiency Overview Continued

• Written Instructions

• Write instructions for all critical procedures.

• Must be short and cover routine as well as non-routine jobs.

• Involves the input of the operator, drilling contractor supervisors and third party personnel as appropriate.

Page 6: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Sample – Written Instructions Now that the 26” hole has been drilled, it is time to run the 20” casing. All tools, etc. required for this operation have been

prepared in accordance with the checklist for “Running 20” Casing”. The casing has been measured ahead of time and a running list will be made out. The casing running list, usually made out by the operator’s drilling supervisor or engineer, is basically a list defining the correct order in which the casing is to be ran.

The first joint to be picked up is the shoe joint. The bottom 10’ –15’ is painted white to aid visibility when entering the 30” housing. A rotating ring is attached to this joint, about 10-12 feet from the bottom, for guide ropes.

When the shoe joint is picked up, water is pumped into it to test the integrity of the shoe. The shoe is basically a non return valve. When the shoe joint is confirmed to be in good working order and is lowered through the rotary, the guide ropes can be secured from the rotating ring to the guide lines. These guide ropes act as a guide for entering the 30” housing. Now all of the remaining intermediate joints can be ran. After these joints have been ran, it is time to pick up the 18 3/4 “ wellhead housing. Depending on the operator, the housing may already be made up and standing in the derrick, or the running tool will have been installed on deck.

Before picking up the wellhead housing it is good practice to count the joints of casing remaining on deck to confirm the total joints ran reflects the the running list. With the wellhead resting on the rotary table, a third party engineer will check operation of the running tool. With the running tool checked and reinstalled, the complete casing string is ran on drill pipe (landing string). Prior to stabbing the 30” housing, the compensator should be unlocked and put in mid stroke. The ROV should be present on the seabed to aid in stabbing. The last stand of the landing string will have a crossover from the pipe connection to a 2A” weco union fitted on top. The landing string will have been “spaced” out so that the wellhead when landed in the 30” will have approximately 10-20 feet of pipe sticking up above the rotary. Once the wellhead is landed, a 20,000 lbs. over pull will be taken to ensure engagement of the latch ring that connects the wellhead to the 30” housing.

Satisfied that the latch has connected, a circulating line from the mud pumps/cement line can be rigged up. All of the equipment required for the cement job will have been checked according to the checklist “Cement 20” casing”

Once the circulating line has been hooked up, it is customary to to pump at least the volume of the casing using either the rig mud pump or the cement pump. When pumping is complete, the cement unit will be lined up to the circulating line, etc., etc., etc.

Page 7: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Drilling Efficiency Overview Continued

• Critical Path Planning

• Needs to be done for all rig activities.

• Best to use Gantt charts or pert charts.

• Best to use Microsoft Project Manager.

• Identification of tools and equipment to facilitate the drilling program, i.e. rotating mousehole, step on slips, automatic driller, iron roughneck, E-Z torque, etc.

Page 8: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Overview Continued

• Identifying Constraints in the drilling process

• Identification of the limitations of the drilling process, i.e. tools, equipment, personnel, training, shorebase management, third party equipment and services, etc.

• Problem identification and problem solving

Page 9: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Some Grade School Management Concepts

• Develop Clear Objectives.

• Clearly Communicate the Importance of Achieving the Objectives.

• Make a plan to achieve the objectives.

• Successfully implement the plan.• “A goal without a plan is but a dream”

Page 10: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Some Common Goals of the Operator and Contractor

• Safety

• Downtime Control

• Good Food

• Clean Rig

Page 11: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Some not so Common Goals

• Operator - Drill the well on or under budget.• Contractor - Operate the rig under budget.• Operator - Drill the well as fast as possible.• Contractor - Keep the rig on contract as long

as possible.• Operator - Find a suitable rig for the lowest

dayrate possible.• Contractor - Find a job for the rig with the

highest dayrate possible.

Page 12: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Drilling Efficiency

• Unfortunately, contract drilling is one of the few industries in which the service provider does not consistently identify with the client’s objectives. Contractors usually do not develop a plan to meet the client’s objectives.

• Contractors need to:• Identify the client’s objectives.• Establish a goal to meet the client’s objectives.• Formulate a plan to meet the client’s objectives.• Execute the plan to achieve the client’s objectives.

Page 13: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Good Plans / Bad Plans• If the goal is to meet or beat the drilling time curve,

a bad plan to achieve this goal would be:• Run the mud pumps to 130 SPM

• Run the mud pumps to 4800 PSI

• Run the maximum weight on the bit by running the drill pipe in compression.

• Run the blocks up and down as fast as possible while tripping or making a connection.

• Move the rig with a full load of liquid mud, casing, drill pipe in the derrick, etc.

• Compromise safety by getting in a hurry.

• Cause damage to the rig equipment by exceeding the equipment limitations.

Page 14: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Good Plans / Bad Plans

• A Bad Plan Will:

• Compromise safety for speed.

• Will also eventually cause damage to the rig equipment resulting in expensive mechanical downtime.

• This is not what we want to accomplish.

Page 15: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Do We Really Need a Learning Curve?

• NO – We can do it: “The First Time - On Time - Every Time”.

Page 16: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Critical Path Planning

• Identify the critical path.• Do good task analysis.• The drilling program should be a planned project.• It is not a daily episode, waiting on a crisis.• Managing the past or planning the future.• What is a poorly planned round trip?• What is a well planned round trip?

Page 17: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Task Analysis

• Start / Start• Task 1• Task 2• Task 3• Finish / Finish• Task 1• Task 2• Task 3

Page 18: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Task Analysis

• Finish / Start• Task 1• Task 2• Task 3• Lead Time• Task 1• Task 2• Task 3

Page 19: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Task Analysis

• Lag Time

• Task 1

• Task 2

• Task 3

Page 20: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

ID Task Name Duration1 START - START 0 days

2 Task 1 1 day

3 Task 2 3 days

4 Task3 1.5 days

56 FINISH - FINSIH 0 days

7 Task 1 3.5 days

8 Task 2 3 days

9 Task3 1.49 days

1011 FINISH - START 0 days

12 Task 1 1 day

13 Task 2 2 days

14 Task3 2 days

1516 LEAD TIME 0 days

17 Task 1 2 days

18 Task 2 3 days

19 Task3 1.5 days

START - START A TASK CANNOT START UNTIL ANOTHER TASK STARTS

FINSIH - FINISH A TASK CANNOT FINISH UNTIL ANOTHER TASK ENDS

FINISH - START A TASK CANNOT START UNTIL ANOTHER TASK ENDS

LEAD TIMEA TASK STARTSWHILE THE PROCEEDING TASK TASK IS BEING DONE

3 4 5 6 7M T W T F

Task Relations Using Microsoft Project Manager

Page 21: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Critical Path Planning

• Drilling a Well is a Project

• We Recommend Using Microsoft Project Manager.

• And, Using a Gantt Chart for Following the Critical Path.

• What is a Critical Path?• A critical path is the linking of tasks that must be done on

a Finish/Start or a Lead Time Relation.

Page 22: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

ID Task Name Duration

1 OVERALL DRILLING GOM JACKUP 38.13 days

2 Phase 1 - Move In & Rig Up 3.38 days

3 Tow to Location 24 hrs

4 Position Rig on Location 6 hrs

5 Jack to 5' Airgap 5 hrs

6 Preload Rig 24 hrs

7 Dump Preload 4 hrs

8 Jack to Final Air Gap 3 hrs

9 Skid Rig Into Drilling Posiion 3 hrs

10 Rig Up Prep to Spud 12 hrs

11 End of Phase 1 0 days

12 Phase 2 - Drive Pipe 1 day

13 Rig Up Hammer 3 hrs

14 Drive Pipe to Refusal or (xxx' BML) 12 hrs

15 Rig Down Hammer 3 hrs

16 Install Diverter 4 hrs

17 Test Diverter 2 hrs

18 End of Phase 2 0 days

19 Phase 3 - Conductor Hole 2.63 days

20 Pick up 17 1/2" x 26" Drilling Assembly 6 hrs

21 Trip in Hole & Tag Mud Line 1 hr

22 Wash Out Inside Drive Pipe 2 hrs

23 Drill Conductor Hole to +/- 1000 Ft 10 hrs

24 Circulate Out 2 hrs

25 Wiper Trip 3 hrs

26 Circulate Out 2 hrs

31 1 2 3 4 5 6 7 8 9

Sample Gantt Chart Page Using Microsoft Project Manager

Page 23: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

ID Task Name

1 Drilling - Semisubmersible 2 Move onto Location3 Tow to New Location4 Position Rig5 Run Anchors6 Deballast Rig7 Tension Anchors8 Phase 1 - 36" Hole / 30" Casing9 Make up Pilot Hole BHA

10 RIH & Tag Seabed & POOH11 Drill Pilot Hole12 POOH w/ Pilot Hole BHA13 Make up 36" BHA & RIH14 Drill 36" Hole15 Circulate & Condition16 POOH to Seabed-Wait 1 hr17 RIH-Displace Hole18 POOH w/ 36" Drlg Assembly19 Rig up to run Conductor Casing20 Run Conductor & PGB21 Cement Conductor (inc. WOC)22 Run Pin Connector23 Make up 26" BHA24 Trip in Hole25 Drill Shoe 26 End of Phase 1

Fri Dec 31 Sat Jan 1 Sun Jan 2 Mon Jan 3 Tue Jan 4 Wed Jan 5 Thu Jan 6 Fri Jan 7 Sat Jan 8 Sun Jan 9

Sample Gantt Chart Page for Semisubmersible

Page 24: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Critical Path Planning

• If a task has a Finish/Finish or a Start/Start Relation, then it should be on a checklist.

Page 25: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Planning Meeting• A planning meeting should be held daily.• It should be only 15 - 20 minutes long.• Who Should Attend?

• Contractor Supervisors

• Operator Supervisors

• Third Party Personnel as Appropriate

• What Should Be Discussed?• Critical path planning

• Checklists

• Narratives (Written Plans)

• Review Potential Problems and Discuss Safety

Page 26: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Bad Trip - No Planning• Drilling• Mix Slug• Pump Slug• Pull Out of Hole

• Call Drilling Supt for Bit Info • Bring Bit to Floor• Bring Pliers & Jets to Floor• Install Jets• Call Drilling Sup for BHA Info• Drilling Supt Calls Shorebase• Shorebase Calls Directional Co.• Shorebase Calls Rig• Bring Subs to Floor• Rig Down Old BHA• Pick up New BHA• Double Handle BHA• RIH

• Total = 22.75 Hours

Page 27: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

•Good Trip - Well Planned• Drilling• Mix Slug• Pump Slug• Pull Out of Hole

• Call Drilling Supt for Bit Info • Bring Bit to Floor• Bring Pliers & Jets to Floor• Install Jets• Call Drilling Supt for BHA Info• Drilling Supt Calls Shorebase• Shorebase Calls Directional Co.• Shorebase Calls Rig• Bring Subs to Floor• Rig Down Old BHA• Pick up New BHA• RIH

• Total = 13 Hours

Page 28: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Bad Trip Using Microsoft Project Manager

ID Task Name Duration1 Drilling 1 hr

2 Mix Slug 1 hr

3 Pump Slug 0.5 hrs

4 Pull Out Of Hole 4 hrs

5 Call Drilling Sup For Bit Info 0.25 hrs

6 Bring Bit To Floor 0.5 hrs

7 Bring Pliers & Jets To Floor 0.5 hrs

8 Install Jets 0.5 hrs

9 Call Drilling Sup For BHA Info 0.5 hrs

10 Drilling Sup Calls Shorebase 1 hr

11 Shorebase Calls Directional Co 1 hr

12 Shorebase Calls Rig 0.5 hrs

13 Bring Subs To Drill Floor 1 hr

14 Rig Down Old BHA 2 hrs

15 Pick Up New Bit 0.5 hrs

16 Pick Up New BHA 2 hrs

1 2 3 4 5 6 7 8 9 10 11 12

Page 29: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

ID Task Name Duration

1 Drilling 6 hrs

2 Mix Slug 1 hr

3 Pump Slug 0.5 hrs

4 Pill Out Of Hole 4 hrs

5 Call Drilling Sup For Bit Info 0.25 hrs

6 Bring Bit To Floor 0.5 hrs

7 Bring Pliers & Jets To Floor 0.5 hrs

8 Install Jets 0.5 hrs

9 Call Drilling Sup For BHA Info 0.5 hrs

10 Drilling Sup Calls Shorebase 1 hr

11 Shorebase Calls Directional Co 1 hr

12 Shorebase Calls Rig 0.5 hrs

13 Bring Subs To Drill Floor 1 hr

14 Rig Down Old BHA 2 hrs

15 Pick Up New Bit 0.5 hrs

16 Pick Up New BHA 2 hrs

17 RIH 4 hrs

18 Total 13 Hrs 0 days

4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9Mon May 1

Good Trip Planning Using Microsoft Project Manager

Page 30: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

•Good Trip / Bad Trip Costs• No. of Hours - Good Planning Bad Planning• Mix Slug 00.0 1.00• Pump Slug 00.5 0.50• Pull Out of Hole 4.00 4.00

• Call Drilling Supt for Bit Info 00.0 0.25

• Bring Bit to Floor 0.00 0.50• Bring Pliers & Jets to Floor 0.00 0.50• Install Jets 0.00 0.50• Call Drilling Supt for BHA Info 0.00 0.50• Drilling Supt Calls Shorebase 0.00 1.00• Shorebase Calls Directional Co. 0.00 1.00• Shorebase Calls Rig 0.00 0.50• Bring Subs to Floor 0.00 1.00• Rig Down Old BHA 2.00 2.00• Pick up New BHA 0.50 0.50• Double Handle BHA 0.00 3.00• RIH 4.00 4.00

• Total = 13.0 Hrs 22.75 Hrs• At 100,000/Day Spread Cost = $54,166 $94,791• The bad trip cost was $40,625

Page 31: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Good Task / Bad Task Relationship

• Just as we have a good trip/bad trip situation, we also have a good cementing operation/bad cementing operation, good nipple up/bad nipple up, etc.

• We can reduce the time for any project by changing the task relationships or by not doing the task at all.

Page 32: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Checklists

• What is a checklist task and what is a critical path task?• A critical path task is a task that must be done

in sequence. It must be done as a lead time relation or a finish/start relation.

• A checklist item is a task that must be done but can be taken off the critical path and made into a finish/finish or a start/start relation.

Page 33: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Checklists

• Checklists• Should be job specific• Should be rig specific• Are basic outlines• Should address potential problems• Should be a live system, i.e. readily changeable

Page 34: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Jackup Drilling Rig Equipment and Procedures Checklist

Operation: Tripping

OPERATOR:

WELL:

RIG:

DATE:

ITEM

CHECKS

ASSIGNED

INITIALS

Pre - Trip Equipment Checks

The following are to be completed prior to tripping drill pipe.

Person or title

When completed

Tongs

Check and replace tong dies as necessary

Check for spare tong dies

Check jaws

Check and repair/replace retainer bolts/pins as required.

Iron Roughneck

Check & replace worn/slick dies

Inspect hydraulic/hoses/couplings for leaks and damage

Check operation

Spinning wrench

Check operation

Check and replace worn dies

Check hydraulic hoses/couplings for leaks & damage.

D.P. Elevators

Check & repair worn retainer bolts on ears.

D.C. Elevators

Check & repair worn retainer bolts on ears

Check & repair retainer bolts

Link arms and link ears

Check for excessive wear and cracks

Traveling block hook & bail

Check for cracks and excessive wear

Master bushing and slips

Check fit and check for wear.

Checklist

Sample Portion

Page 35: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Checklists

• Pre-operations start-up• Prepare to spud• Drive Pipe• Drill conductor hole• Run conductor casing• Cement conductor casing• Grout conductor casing (Top Job)• Grout conductor (With BOP Installed)

Page 36: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Checklists• Install Diverter System• Drill surface hole (17 1/2)• Under-ream surface hole• Run surface casing• Cement surface casing• Install wellhead• Nipple up BOP’s• Test BOP’s• Drill intermediate hole (12 1/4)

Page 37: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Checklists

• Establish shut in procedure

• Establish kill procedure

• Logging operations

• Run intermediate casing (9 5/8)

• Cement intermediate casing

• Install casing spool

• Install and nipple up BOP’s

Page 38: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Checklists

• Drill production hole (8 1/2)

• Run production casing

• Run production liner

• Cement casing

• Cement liner

• Set P&A plugs

• Cut and retrieve casings

Page 39: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner

Review of Drilling Efficiency • Drilling Efficiency is:

• Controlling costs by working efficiently (Reducing the time it takes to drill a well).

• Critical path planning.• Using Checklists.• Holding a daily planning meeting.• Holding toolbox meetings.• Using narrative (written) instructions.• Identifying tools and equipment to facilitate the drilling program,

i.e. rotating mousehole, auto driller etc.• Identify Constraints, i.e. solids control equipment, rig power,

pumps, etc. rig crews, shorebase management, training, etc.• Utilizing constructive criticism, i.e. “Report Card” with feedback.

Page 40: Drilling Efficiency Veritas Associates, Inc For Conoco Indonesia By Paul Baumgardner