Upload
evangeline-morrison
View
214
Download
0
Tags:
Embed Size (px)
Citation preview
DREAM November Meeting
Agenda
• Introduction and Expectations• Path to becoming a Resource Node – ERCOT• Registration process for non-modeled resources – ERCOT• Distribution Switching 101• Reliability Discussion – DERs (December)• Modeling DERs at the Transmission Bus• FIS / Screening Study Exemption for DERs• Definition Update• Resource Optionality and Switching between LZ and Nodal
Prices
Expectations
• Understand and differentiate registration processes for resource nodes and un-registered resources
• Identify bottlenecks for establishing a resource node for a DER
• Understand complications associated with DER registration and distribution switching
• Document task force positions on LZ/Nodal switching
Distribution Switching 101
Feeder A Feeder B Feeder C
Main 1 Main 2
Feeder D Feeder F Feeder G
T BKR 1
Transmission Line 1
Transmission Line 2
Transformer 1138/13.8kV
Transformer 2138/13.8kV
Fault duty rated disconnect switch
Fault duty rated disconnect switch
T BKR 2
SubstationFence
Residential Service
Commercial, Light Industrial, Residential Service
DERville Substation
Field switching between feeders
Field switching between substations
ODER YODER
Modeling DERs at the transmission bus
DER
• Establishing a Logical Resource Node for a DER enables participation in SCED dispatch, ancillary service markets, and CRR markets.
• The resource’s electrical identity on the grid can be represented by an equivalent circuit, and shift factor relative to the transmission bus
• A DER with many parallel paths back to a substation still has a shift factor of 1, relative to the T/D transformer, assuming it is truly “radial” to that transformer
• Downtown networks with tied secondary lines are notable exceptions
Mapping a DER to the Transmission Load
• DERs can be modeled at the transmission bus
• Shift factors relative to constraints can accurately represent the resource at the transmission bus
• Switching between substations may physically move the resource connection relative to it’s DER mapping
• CIM nodes must be logically adjusted to account for DER output and apparent load.
Sub 1 Sub 2
DER1
CIM Load
Distribution switching is not currently modeled by ERCOT
Potential Solution for Distribution Switching impact on resource location
The ability to switch load (and distribution connected resources) is typically limited by physical and electrical distance in between transmission substations.
Sub 1
Sub 1
Sub 1
Sub 1
Sub 130 Mi 40 Mi 20 Mi
25 Mi
Load / DER
Load / DER Load / DER
Voltage and Thermal Constraints Limit D Switching
Resource switching may be limited to immediately neighboring circuits / stations
Potential Solution for Distribution Switching impact on resource location
If the resource can only switch between two substations that have a shift factor +/- 2% (shift factor cut-off), then the resource may be modeled at either substation without material impact. Station outages may require that a DER QSE notify ERCOT of the change for accurate representation.
Sub 1
Sub 1
Sub 1
Sub 1
Sub 130 Mi 40 Mi 20 Mi
25 Mi
Load / DER
Load / DER Load / DER
Voltage and Thermal Constraints Limit D Switching
Resource switching may be limited to immediately neighboring circuits / stations
Potential Exemptions for FIS Studes
• Do TDSP interconnection studies obviate the need for further ERCOT study?
• Does the 10MW Exemption allow a bypass of ERCOT/ FIS studies?
• If the DER Nameplate rating < Station Transformer minimum load, then the DER may not inject to the grid
Behind the meter, LZ Pricing
Battery Solar Panel
Inverter
Load
Meter
Load ZoneChargingPricing
Load Zone Pricing
Load Zone Pricing
Load Zone Pricing
Net apparent load invoiced by interval
Behind the meter, LZ/Nodal Pricing
Battery Solar Panel
Inverter
Load
Meter
NodalChargingPricing
Nodal / Solar Charging Pricing
Load Zone Pricing
Nodal Pricing
Logical load invoiced by interval
Sub Meter
Logical Load may be defined as Meter – Sub Meter
Load Zone/Nodal Optionality
• Wholesale and Load Zone prices may diverge when constraints bind
• Resources and Loads may get inconsistent pricing at the same electrical bus
This issue exists at traditional generators, where station service load pays load zone pricing and the generator is paid wholesale pricing
Electrically equivalent location
Nodal and Load Zone Price Divergence
• If a customer site is in a load pocket within a load zone, nodal prices may be very high, while load zone prices are relatively low.
• If a customer site is in a generation pocket within a load zone, LZ pricing may be very high, while nodal prices are very low
Issues with Optionality
• The ability to switch between nodal and load zone pricing, on an interval, hourly, or daily basis enables the customer to optimize charging, discharging, and LZ/Nodal Pricing
• Provides an unprecedented opportunity to manage load zone / nodal risk
Examples: Day (hour, week, month)1
Optimizing LZ/NP, the resource would:– Switch batteries to full
charging mode– Switch solar production
to self serve (Load Zone hedge)
– Potentially reduce Load
NP : -$25
Note: Assumes sub-metering on the battery and solar array are independent and switchable (Potentially Post-ITC Scenario, ITC for batteries requires 70% solar charging)
LZ: $30
Examples: Day (hour, week, month) 2
Optimizing LZ/NP, the resource would:– Switch batteries to full
dis-charging mode– Switch solar production
to nodal pricing– Potentially increase
charging load to discharge to a nodal price
NP : $30
Note: Assumes sub-metering on the battery and solar array are independent and switchable
LZ: $18
Pros/Cons
• Creates increased value for the solar/storage combination behind the meter
• Enables unprecedented optionality for a Resource to optimize LZ/Nodal pricing
• Potentially sends differing/conflicting pricing signals to a single electrical location
Alternatives
• Establish a Resource Node for the Solar/Battery combination
• Charge and Sell wholesale• Procure CRRs from the Resource Node to the
Load Zone when LZ pricing is desired
Next Meeting
• Discuss potential rules for aggregations• Review year-to-date findings• Prepare a summary for TAC direction in
January• DER Reliability Discussion – Current DR Concentration– Can existing DR aggregate output currently exceed
Reg Down, SCED Down on a 5, 10, 15 min basis?