Drakenstein’s Maintenance and Asset Management Approach
Presented by Deon Louw 10 September 2013Jointly prepared by Gavin Barbier & Deon Louw
Pulse2013 Optimizing the Worlds Infrastructure
Content
• Background• Challenges & Requirements• Project Implementation Planning• Project Implementation• Early Results• Future Plans
Pulse2013 Optimizing the Worlds Infrastructure
Background
Pulse2013 Optimizing the Worlds Infrastructure
Background (…1)
Drakenstein
Pulse2013 Optimizing the Worlds Infrastructure
Background (… 2)
• Drakenstein did not have any Asset Register of note and therefore no Asset Maintenance
• With the new Municipal Finance Management Act, it became compulsory to have a formal Asset Register
• Had various attempts at creating a formal asset register, but never had a Asset Management Software system automatically updating the Asset Register
• Had various stand alone systems such as GIS, SCADA, Call Centre Management, Accounting Systems – none of them integrated.
• No proper maintenance philosophy and maintenance planning systems
Pulse2013 Optimizing the Worlds Infrastructure
Challenges & Requirements
Pulse2013 Optimizing the Worlds Infrastructure
Challenges at Drakenstein
• Siloed information in various systems• Difficulty in correlating data from various systems• Asset register only used for financial evaluation of asset
register• No or little preventive maintenance on assets (Run to
failure) • No visibility maintenance costs per asset
– Cost of Material/Stocked Items– Cost of Labour– Cost of Services
• Difficult to do maintenance budgeting based on current history
• Reduced budgets, needed to do Risk Analysis in order to spend limited funds wisely
Pulse2013 Optimizing the Worlds Infrastructure
Drakenstein’s Requirement
– Keep Asset Register current (constant verification and updating)
– Optimisation of Operational Resources– Unified Process of Managing Assets and Work– Integrate Data Sources: Spatial, SCADA, Financial and
Human Resources– Using SCADA data to generate maintenance plans on
Meters based on the amount of trips have occurred– Improved communication with clients
Pulse2013 Optimizing the Worlds Infrastructure
Process Impact on Asset Register
Asset Register
CAPEX
Maintenance
Service Strategy
Condition Assessment
Operations
Financial Accounting
Asset Disposal
Supply Chain
Pulse2013 Optimizing the Worlds Infrastructure
Unified Business Process for all Work
• Drakenstein’s Flow Trough Business Process– Work Initiators:
• Call Centre• Help Desk: Service Request• CAPEX • Planned Maintenance • Unplanned Maintenance
– Work Planning– Scheduling– Assigning & Dispatching– Field Force Management– Feedback– Closeout– Analysis
Pulse2013 Optimizing the Worlds Infrastructure
Project Implementation Planning
Pulse2013 Optimizing the Worlds Infrastructure
Service Management Process
Client Call Create Service Request
Classify Request
Create Work OrderWork Planning
Pulse2013 Optimizing the Worlds Infrastructure
Helpdesk: Client Calls
• Other Feeds:– E-mail– Self Service Application
Pulse2013 Optimizing the Worlds Infrastructure
Changes on Account Holder Contact Details
• Maximo can be used to update the caller’s Contact details• On saving the SR an e-Mail will be sent to the accounts
department notifying them of the change• The accounts department will contact the person to confirm
the details and physically do the change on the financial system
Old Contact Details New Contact Details
Pulse2013 Optimizing the Worlds Infrastructure
Location Identification
• Search Map
Pulse2013 Optimizing the Worlds Infrastructure
Verify duplicate Service Requests
Pulse2013 Optimizing the Worlds Infrastructure
Work Order reference SR for Auto status updates
Pulse2013 Optimizing the Worlds Infrastructure
CAPEX Process
• Functions:• CAPEX Cost Centre• Budgeting• GIS Integration• Compatible Unit Estimator• Standard Job Plans• Standard Project Templates• Supply Chain Integration• Outages Planning• Maximo Scheduler • Customer Notifications• Crew Management• Workflow signoffs
Master Plan Project Definition
Field Estimating
Office Estimating
Work Package Development Notifications
Work Planning
Pulse2013 Optimizing the Worlds Infrastructure
Preventive Maintenance
• Functions:• Meters (SCADA)• Calendar• Standard Job Plans• Master PM’s• PM Sequencing• Supply Chain
Integration• Outages Planning• Maximo Scheduler • Customer Notifications• Crew Management• Workflow signoffs
Preventive Maintenance
Launching Conditions
Job Plans & Procedures
PM PredictionsNotifications
Preventive Maintenance Generation
Work Planning
Pulse2013 Optimizing the Worlds Infrastructure
Corrective & Emergency Maintenance
• Functions:• DMS Integration• SCADA Integration• Condition Monitoring
• Infrared Cameras• Online Monitoring• High/Low Alarm Levels• High/Low Action Levels• Colour conditions
• GIS Integration• Incident Classification• Work Prioritisation• Standard Work Templates
Smart Feeds Incident Reporting
TrendingActions Launching
Prioritisation Work Planning
Pulse2013 Optimizing the Worlds Infrastructure
Planning to Execution
• Functions:• Job Plans• Resource selection
• Material• Labour• Tool• Services
• Planning Tools• Dispatching Tools• Mobility Tools
Work Planning Material, Resource Planning
Approve Work
Crew SchedulingAssignmentDispatching
Field Force Management
CAPEX, Preventive Maintenance, Service Requests, Incidents
Pulse2013 Optimizing the Worlds Infrastructure
Project Implementation
Pulse2013 Optimizing the Worlds Infrastructure
P&S Optimization Achievement on Productivity
13% Personal
10% Clerical
15%Waiting for Jobs
22%Travel Time and Stores
10%Waiting for Instructions
30% Productive Work
Reduce from 70 % to 50%
50% Productive Work
60% Increase inProductivity
Before P&S Optimization
After P&S Optimization
Pulse2013 Optimizing the Worlds Infrastructure
Planning & Scheduling Optimization ROI
Impact of Improvement– Reduce time to complete jobs by 33 %– Increase Productivity (Labor wrench time) by 60 %
Effect Of Improvement – 3 techs at 30% = 90 % total productivity– 2 techs at 50% + 1 planner @ 0% = 100% total productivity– A planner can plan work for 15-40 technicians depending on industry and
complexity of maintenance work. Average ratio is 1-20– One planner /scheduler for 20 technicians (21 employees) will yield the
same output as 30 technicians without planners
Visual Planner allows Planners, Schedulers and Supervisors achieving a 20% time saving (One full day per week)
Pulse2013 Optimizing the Worlds Infrastructure
Work Management Focus Areas
Forecast Work
Identify ResourceGaps
Availability:• Assets• Location• Material• Tools
• Labor/Crews
Resource Leveling
Graphical UI
Labor and Crews
Graphical UI
Public Map Control
Route Optimization
Labor and Crews
Assign Emergency Work
Communication To Field
Technicians
CapacityPlanning
Schedule Compliance
ResourceOptimization Assignment Dispatching Real-time
Communication
Pulse2013 Optimizing the Worlds Infrastructure
Roles in Managing Work
• Defines and adjusts labor/crew availability along with resource leveling
• Capacity Planning
• Assigns work orders to resources
• Continuously optimizes the schedule as the operational environment changes
• Sequence and route work assignments based on geography
Scheduler/Planner
• Monitor field resources and work order progress and status
• Monitor the location of field resources compared to open orders
• Enter status and complete work orders on behalf of technicians who don't have mobile devices
• Sequence and route ongoing work assignments based on geography and optimization
Dispatcher
• Supervisor approves and assigns work on mobile devices
• Receive work orders in the field and provide real time status updates to dispatch
• Complete, edit and approve work orders on mobile devices along with viewing work on a map with optimal driving directions
• Notify dispatch of potentially dangerous situations, incomplete work
Field Technician
Pulse2013 Optimizing the Worlds Infrastructure
Scheduling: Resource Load and Availability
Pulse2013 Optimizing the Worlds Infrastructure
Planning: Resource Optimisation
Pulse2013 Optimizing the Worlds Infrastructure
Dispatching: Real-time monitoring
Pulse2013 Optimizing the Worlds Infrastructure
Mobile Interface
Pulse2013 Optimizing the Worlds Infrastructure
2 x Clicks
Pulse2013 Optimizing the Worlds Infrastructure
Location
Direction
Speed
Pulse2013 Optimizing the Worlds Infrastructure
Mobile Supported Devices
Pulse2013 Optimizing the Worlds Infrastructure
Service Request feedback from Work Order
• Completing the work order a message will appear notifying you that the Service Request will be Resolved
• The Client that reported the call will receive an SMS notification that the call has been resolved
Pulse2013 Optimizing the Worlds Infrastructure
Prepare for: Meter Management Lifecycle
Truck(Rolling Storeroom)
StockQuarantined
Meter Shop
Stock
Meter Random Sample TestMeter Shop
Storeroom or Staging Area
Stock
Vendor Marriage and Test Files
Status: Not Ready
Location: Meter Shop
A
ASN File
Meter
Shipment
Meter Receipt Meter Marriage
Premise
ActiveLeft in Open
Sync
StoreroomMeter Shop
Needs Test
Truck(Rolling Storeroom)
Needs TestNeeds Test
Meter Shop
Stock
Meter Inspection/Test
Meter Fails Test, Lost or Obsolete
RetiredLost
Obsolete
Meter End of LifecycleStoreroom or Metershop
Meter
Passes Test
Storeroom
Stock
A
Service Order
Service Order
Meter Installation
Meter RemovalMeter
Shipment
Pulse2013 Optimizing the Worlds Infrastructure
Early Results
Pulse2013 Optimizing the Worlds Infrastructure
The Value to Drakenstein
•• Unified solution for:
• Service Management• Work Management• Asset Management • Supply Chain Management
• For all asset groups • Infrastructure• Plant• Facilities • Transportation• IT assets
• Visualisation• GIS integration• Map Integration• Dashboards• Birt Reporting• Customer WEB UI
AssetManagement
WorkManagement
Supply ChainManagement
Service Management
Pulse2013 Optimizing the Worlds Infrastructure
Call Centre Dashboard Graphical View
Pulse2013 Optimizing the Worlds Infrastructure
Call Centre Dashboard List View
Pulse2013 Optimizing the Worlds Infrastructure
Custom Reporting
Pulse2013 Optimizing the Worlds Infrastructure
Future Plans
Pulse2013 Optimizing the Worlds Infrastructure
Future Planned Steps
• Role out to all other Engineering Service• Role out to other Directorates• Full integration of all software systems• Fault Predictive Software Installation
Pulse2013 Optimizing the Worlds Infrastructure
Questions?