DRAFT ENVIRONMENTAL MANAGEMENT
PROGRAMME
HALFWAY HOUSE RESIDENTIAL ESTATE
Portion 30, 31 and the remaining extent of Portion 29 of Holding 74
Halfway House Estate Agricultural Holdings
Gaut:002/16-17/E0246
Prepared for
JANUARY 2017
2
LIST OFACRONYMS
BAR Basic Assessment Report
DW&S Department of Environmental Affairs
EA Environmental Authorisation
EIA Environmental Impact Assessment
EAP Environmental Assessment Practitioner
EIR Environmental Impact Assessment Report
ECO Environmental Control Officer
EMPr Environmental Management Programme
EMS Environmental Management System
GDARD Gauteng Department of Agriculture and Rural Development
HIA Heritage Impact Assessment
HSRA Health and Safety Risk Assessment
I&AP Interested and Affected Parties
LOS Level of Service
NCR Non Conformance Report
NHBRC Nation Home Builders Registration Council
OHS Occupation Health and Safety
PM Post Meridian
QMS Quality Management System
SAHRA South African Heritage Resource Agency
SHE Safety Health and Environment
TES Traffic Engineering Services
WUL Water Use License
3
TABLE OF CONTENTS
1.0 INTRODUCTION AND BACKGROUND ................................................................................................... 5
1.1 Details of the applicant .................................................................................................................... 5
1.2 Details of the EAP ........................................................................................................................... 6
2.0 ENVIRONMENTAL MANAGEMENT PROGRAMME (EMPR) .................................................................. 7
2.1 Purpose of the EMPr ........................................................................................................................ 7
2.2 Objectives of the EMPr .................................................................................................................... 7
2.3 Applicable Documentation .............................................................................................................. 7
2.4 Scope of the EMPr ........................................................................................................................... 7
2.5 Structure of the EMPr ...................................................................................................................... 8
2.6 EMPr as a live document ................................................................................................................. 8
2.6.1 Plan .......................................................................................................................................... 9
2.6.2 Do ............................................................................................................................................. 9
2.6.3 Check ........................................................................................................................................ 9
2.6.4 Act .......................................................................................................................................... 10
3.0 MANAGMENT AND MONITORING PROCEDURES .......................................................................... 10
3.1 Organisational Structure and Responsibility ................................................................................. 10
3.2 The Developer ................................................................................................................................ 11
3.3 The Engineer .................................................................................................................................. 11
3.4 The Contractor (including sub-contractors) .................................................................................. 11
3.5 Environmental Control Officer ....................................................................................................... 12
3.6 Occupational Health and Safety Officer ........................................................................................ 12
3.7 Safety, Health and Environmental (SHE) Officer ........................................................................... 13
3.8 Training and Environmental Awareness ........................................................................................ 13
3.9 Monitoring ..................................................................................................................................... 14
3.10 Reporting Procedures .................................................................................................................... 14
3.10.1 Documentation ...................................................................................................................... 14
3.10.2 Environmental Register ......................................................................................................... 15
3.10.3 Non-Conformance Report...................................................................................................... 15
3.10.4 Environmental Emergency Response .................................................................................... 16
3.10.5 Method Statements ............................................................................................................... 17
3.10.6 Public Communication and Liaison with I&APs ..................................................................... 18
4
4.0 COMPLIANCE WITH ENVIRONMENTAL SPECIFICATION .................................................................... 18
5.0 CONFORMANCE WITH THE APPLICABLE ISO STANDARDS ENVIRONMENTAL MANGEMENT SYSTEM
19
6.0 ENVIRONMENTAL CODE OF CONDUCT .............................................................................................. 20
7.0 ENVIRONMENTAL GUIDELINES, STANDARDS AND PERMITS ............................................................. 20
8.0 DETAILED ENVIRONMENTAL MANAGEMENT PROGRAMME ............................................................ 22
8.1 CATERGORY A: PRE-CONSTRUCTION PHASE .................................................................................. 24
8.2 CATERGORY B: CONSTRUCTION PHASE ......................................................................................... 27
8.3 Post Construction Phase-Rehabilitation/Maintenance ................................................................. 32
9.0 CONCLUSION ...................................................................................................................................... 34
LIST OF FIGURES
Figure 1: Locality Map ...................................................................................................................................... 5
Figure 2: Proposed layout .................................................................................. Error! Bookmark not defined.
Figure 3: Deming Cycle of Continuing Improvement ....................................................................................... 9
Figure 4: Project Organisational Structure .................................................................................................... 10
Figure 5: ISO EMS Cycle of Continuous Improvement ................................................................................... 19
LIST OF TABLES
Table 1: Details of the applicant ...................................................................................................................... 5
Table 2: Details of the applicant ...................................................................................................................... 6
Table 3: Phases of the Project Life-Cycle ......................................................................................................... 8
Table 4: Fines that may be Implemented .......................................................... Error! Bookmark not defined.
Table 5: Environmental Code of Conduct ...................................................................................................... 20
Table 6: Applicable Legislation ...................................................................................................................... 20
5
1.0 INTRODUCTION AND BACKGROUND
The applicant, M&T Development (Pty) Ltd, proposes to establish a residential township to be known as
Vorna Valley Extension 106. The subject property is located on the Remaining Extent of Portion 29, Portion
30 and Portion 31 of Holding 74 Halfway House Estate Agricultural Holdings sandwiched between
Langevelt Road and Pretorius Road, and north of Bel Aire Estate. The development is close to the Mall of
Africa and Waterfall Office Park development to the south of Allandale Road, as well as various Blue Chip
Office Developments developed along the N1 Highway.
The Environmental Management Programme (EMPr) will serve as a management tool to ensure that
adverse impacts of the construction of the project are prevented while enhancing the positive
benefits which, in turn, will support the operation phases of the project.
Figure 1: Locality Map
1.1 Details of the applicant
Table 1: Details of the applicant
Aspect Details
Project applicant: M & T Development PTY LTD
Trading name M&T Development
Contact person: Cobus Cronje
Physical address: 340 Witch-Hazel Street, Highveld X70, Centurion
Postal address: P O Box 39727, Faerie Glen
Postal code: 0043 Cell: 076 412 5852
Telephone: 012 676 8592 Fax: 086 623 5451
6
1.2 Details of the EAP
Table 2: Details of the applicant
Aspect Details
Name Nali Sustainability Solutions (Pty) Ltd
Representative Mr Pirate Ncube
Physical Address 65 Country Club Drive, Irene Farm Villages, Centurion
Postal Address P Bag X1, Stand 1829, Irene Farm Villages, Centurion, 0045
Other contact details Tel: 0824517120; Fax: 086 694 1178
Email: [email protected] or [email protected]
Expertise/experience Vast experience in environmental and land use management. More than 22
years’ experience in spatial planning, environmental planning and
management encompassing Strategic Environmental Assessments,
Environmental Impact Assessments and reviews, Environmental Management
Plans, and Environmental Compliance Monitoring as well as Project
Management. Served/s in various decision making bodies including the DFA
Tribunal, Environmental Advisory Committee, MEC Appeals Advisory Panel.
Qualified Town Planner (honours) with Masters in Real Estate and an MBA.
Figure 2: Layout plan
7
2.0 ENVIRONMENTAL MANAGEMENT PROGRAMME (EMPR)
2.1 Purpose of the EMPr
An Environmental Management Programme (EMPr) provides management mechanisms/methods
for the prevention of undue or reasonably avoidable adverse environmental impacts and for the
enhancement of the positive environmental benefits of a development. The EMPr derives from the
provisions of the National Environmental Management Act (Act No. 107 of 1998, (NEMA)(as
amended), and bestows a ‘Duty of Care’ on those who cause, have caused or may in future cause
pollution or degradation of the environment as per Section 28 (1) of NEMA.
2.2 Objectives of the EMPr
The EMPr provides recommendedmeasures and guidelines for environmental monitoring
throughout the construction and the operational phase of the activity. The specific objectives for
this EMPr include, among others:
Provision of the details of the applicant;
The outline of the legal requirements;
Identifies the regulatory and policy stipulations applicable to the activity;
The mitigation measures for construction associated impacts and key measures to be
implemented in the operational phase of the project;
Specification of roles and responsibilities of parties in the implementation of this EMPr;
Identifying construction activities that might have detrimental impacts on the environment;
To identify measures that could optimize beneficial impacts;
To establish a method of monitoring and auditing environmental management practices during
all phases of development;
Mechanisms for monitoring compliance with the EMPr and reporting thereon;
Specifying time periods within which the measures contemplated in the Environmental
Management Programme must be implemented.
2.3 Applicable Documentation
Some of the documentation required to undertake the Project and that will be read in conjunction
with the EMPr are listed below:
Environmental Authorisation from the Gauteng Department of Agriculture and Rural
Development (GDARD).
Environmental Impact Assessment for the proposed Vorna Valley Extension 106.
All other approvals required for the activity.
2.4 Scope of the EMPr
In accordance with the requirements of the National Environmental Management Act (NEMA)
Environmental Impact Assessment (EIA) Regulations, 2014, and the requirements of the GDARD this
EMPr is to be implemented by the Developer/applicant as well as any employee, contractor, agent
8
or sub-contractor appointed to act on behalf of the Developer in the execution of the Project, in
order to ensure environmental compliance onsite. Thus the specifications outlined in this EMPr are
applicable to all activities undertaken by the Developer as well as appointed contractors and all
persons involved in the execution of the works.
An Environmental Code of Conduct has also been developed that provides a simplified set of rules
that should be adhered to by all persons involved with the project at all times. This is to be
displayed at strategic points to ensure constant environmental awareness.
The effectiveness of the EMPr depends on the level of compliance with conditions and measures
in the EMPr by the applicant. It is further assumed that compliance with the EMPr will be
monitored and audited as set out in this EMPr and contractual clauses.
2.5 Structure of the EMPr
There are three main phases in the EMPr that provide proposed mitigations and management
measures in Table1.
Table 3: Phases of the Project Life-Cycle
Category Phase Description
Category A Pre-Construction
This section provides guidelines on pre-construction activities including site establishment and clearance; environmental induction and training & awareness.
Category B Construction This section will provide guidelines on construction ethods and considerations
Category C Rehabilitation This section of the EMPr provides management principles for the rehabilitation phase of the Development. This will include best practice, procedures and responsibilities as required for various associated activities.
Relevant environmental legislation pertaining to the development is listed in the next section. The
applicant shall be responsible for ensuring compliance with the laws and conditions by any person
acting on its behalf.
However, the EMPr is a dynamic document which will be updated on a continuous basis to ensure
environmental best practices. Any amendments to be made, must be submitted to to the GDARD
for approval in accordance with the Regulations.
2.6 EMPr as a live document
The approach adopted for this EMPr is derived from the Deming Cycle (Figure 3), a cycle of
continuous improvement that entails the reiterative actions of plan, do, check, act, and then return
to the planning phase.
9
Figure 2: Deming Cycle of Continuing Improvement
2.6.1 Plan Project-specific planning for the proposed project involves consideration of the legal triggers, the
specifics of the proposed development, and the nature of the receiving environment. This provides
a starting point for targeted environmental management objectives. Environmental performance
indicators are then determined with measurable targets prescribed to monitor the environmental
performance of the project. Achieving the targets depends on compliance with this EMPr and the
legislative requirements that underpin it.
2.6.2 Do
Throughout the development’s life-span, the developer will be required to develop and maintain a
Quality Management System–designed to ensure that best management practices are implemented
on day-to-day management. Such a QMS should at least include the following information:
Location and extent of associated infrastructure;
Associated activities such as the transportation of people and equipment;
Resources and experience required(staffing);
Materials and equipment to be used;
Management actions;
Human resources used;
Construction-monitoring activities;
Emergency/disaster incident and reaction procedures; and
Rehabilitation procedures for the impacted environment.
These topics will be cross-linked into the contracts related to the development of the project.
2.6.3 Check
A system of assessing monitoring results has been developed to check the environmental
management performance. Continuous assessment facilitates proactive management of the
environmental issues. Mitigation measures can then be successfully implemented on an ongoing
basis to keep environmental indicators within their target thresholds. Moreover, the assessment
system also enables the assessment of the efficiency of the EMPr. Regular auditing of
environmental performance is prescribed to prove and preserve accountability.
10
2.6.4 Act
The assessments and monitoring of the results and findings of the regular audits must be
documented within a reporting system. Precautionary mitigation measures and corrective actions
will be prescribed and instructions will be given in order to implement these in the field. The
findings of monitoring and auditing programmes can also be used to update the EMPr. Although the
EMPr is a project-specific document, it is dynamic and should be updated regularly to address the
changing circumstances of the scheme.
3.0 MANAGMENT AND MONITORING PROCEDURES
3.1 Organisational Structure and Responsibility
The figure below provides an indication of the organizational and team structure for the Project.
Figure 3: Project Organisational Structure
11
3.2 The Developer
The Developer is ultimately responsible for ensuring compliance with the environmental
specification and upholding the environmental commitment to 100% compliance with all
National, Provincial and local legislation that relates to management of this environment. Briefly,
the Developer will:
Appoint specialist and assembly construction team;
May on the recommendation of the Engineer and/or Environmental Officer order the
Contractor to suspend any or all works on site if the Contractor or his Sub-
Contractor/Supplier fails to comply with the said specifications; and
Maintain control of all activities pertaining to the project.
3.3 The Engineer
The Engineer will:
Enforce the environmental specifications on site;
Monitor compliance with the requirements of the specification;
Assess the Contractor’s environmental performance in consultation with the Environmental
Officer from which a brief monthly statement of environmental performance is drawn up for
record purposes and to be reported to project meetings; and
Ensure the documentation, in conjunction with the Contractor, the state of the site prior to
construction activities commencing. This documentation will be in the form of photographs
or video record.
3.4 The Contractor (including sub-contractors)
The Contractor is required to:
Be fully conversant with the EMPr and all conditions of the EA, WUL ,etc.;
Provide information on previous environmental management experience and company
environmental policy in terms of the relevant forms contained in the Contract Document.
Supply method statements timeously for all activities requiring special attention as specified
and / or requested by the Developer, Environmental Officer and/or Engineer during the
duration of the Contract.
Be conversant with the requirements of this environmental specification/ EMPr. Brief all his/
her staff about the requirements of the environmental specification;
Comply with requirements of the Environmental Officer in terms of this specification and the
project specification, as applicable, within the time period specified.
Ensure any Sub-Contractors/Suppliers who are utilized within the context of the contract
comply with the environmental requirements of the project, in terms of the specifications.
The Contractor will be held responsible for non-compliance on their behalf.
Bear the cost of any delays, with no extension of time granted, should he or his Sub-
Contractors/Suppliers contravene the said specifications such that the Engineer orders a
12
suspension of work. The suspension will be enforced until such time as the offending
party(ies), procedure, or equipment is corrected.
Bear the costs of any damages / compensation resulting from non-adherence to the said
specifications or written site instructions.
Comply with all applicable legislation.
Ensure that he informs the Engineer timeously of any foreseeable activities which will
require input from the Environmental Officer.
The Contractor will conduct all activities in a manner that minimizes disturbance to the
natural environment as well as directly affected residents and the public in general.
3.5 Environmental Control Officer
The ECO will:
Be fully conversant with the EMPr;
Be familiar with the recommendations and mitigation measures of the associated EMPr for
the project;
Monitor the implementation of the EMPr during the construction and rehabilitation phases;
Ensure site protection measures are implemented on site;
Monitor that the Principal Contractor, sub-contractors, construction teams and the
Developer are in compliance with the EMPr at all times during the construction and
rehabilitation phases of the project;
Monitor all site activities monthly for compliance.
Conduct monthly audits of the site according to the EMPr, and report findings to the
Developer/Contractor;
Attend monthly site meetings;
Recommend corrective action for any environmental non-compliance at the site;
Compile a monthly report highlighting any non-compliance issues as well as progress and
compliance with the EMPr prescriptions. These monthly reports are to be submitted to the
Developer and GDARD; and
Conduct once-off training with the Contract or on the EMPr and general environmental
awareness.
It must be noted that the responsibility of the ECO is to monitor compliance and give advice on
the implementation of the EMPr and not to enforce compliance. Ensuring compliance is the
responsibility of the Developer and the SHE Officer.
3.6 Occupational Health and Safety Officer
The OHS Officer will be responsible for undertaking of the following:
Compilation of a comprehensive project Health and Safety Risk Assessment(HSRA)
Compilation of health and safety specifications based on risks identified;
Reviewing and approval of health and safety plan(s) submitted by appointed Principal
Contractor(s);
13
Conducting monthly health and safety inspections and compiling monthly OHS reports;
Conducting monthly health and safety audits with audit reports;
Assisting the Developer/Contractor in the investigation of major accident/incidents;
Monitoring of site activities for compliance to the Occupational Health and Safety Act
(OHSA)and Regulations;
Establishment and monitoring of project health and safety file;
Monitoring the Principal Contractor(s’) health and safety performance; and
Preparation of project close-out reports and submission of project files to the Client.
3.7 Safety, Health and Environmental (SHE) Officer
The Safety, Health and Environmental Officer will:
Be fully conversant with the EMPr;
Be fully conversant with all relevant environmental legislation applicable to the project, and
ensure compliance with them;
Compilation of Method Statements together with the Principal Contractor that will specify
how potential environmental impacts in line with the requirements of the EMPr will be
managed, and, where relevant environmental best practice and how they will practically
ensure that the objectives of the EMPr are achieved;
Convey the contents of this EMPr to the construction site staff and discuss the contents in
detail with the Contractor;
Undertake regular and comprehensive inspection of the site and surrounding areas in order
to monitor compliance with the EMPr;
Take appropriate action if the specifications contained in the EMPr are not followed;
Monitor and verify that environmental impacts are kept to a minimum, as far as possible;
Order the removal from the construction site of any person(s) and/or equipment in
contravention of the specifications of the EMPr;
Report any non-compliance or remedial measures that need to be applied to the appropriate
environmental authorities, in line with the requirements of the EMPr;
Submitting a report at each site meeting which will document all incidents that have
occurred during the period before the site meeting;
Ensuring that the list of transgressions issued by the ECO is available on request; and
Maintain an environmental register which keeps a record of all incidents which occur on the
site during construction. These incidents include:
Public involvement/complaints.
Health and safety incidents.
Incidents involving hazardous materials stored on site.
Non-compliance incidents.
3.8 Training and Environmental Awareness
It is important to ensure that the Contractor has the appropriate level of environmental
awareness and competence to ensure continued environmental due diligence and ongoing
14
minimisation of environmental harm. Training needs should be identified based on the available
and existing capacity of site personnel (including the Contractors and Sub-contractors) to
undertake the required EMPr management actions and monitoring activities. It is vital that all
personnel are adequately trained to perform their designated tasks to an acceptable standard.
The environmental training is aimed at:
Promoting environmental awareness;
Informing the Contractor of all environmental procedures, policies and programmes
applicable;
Providing generic training on the implementation of environmental management
specifications; and
Providing job-specific environmental training in order to understand the key environmental
features of the construction site and the surrounding environment.
Training will be done in a verbal format. The training will be a once-off event; however the
Contractor should make provision for weekly training or Toolbox Talks. In addition to training,
general environmental awareness must be fostered among the project’s workforce to encourage
the implementation of environmentally sound practices throughout its duration. This ensures that
environmental accidents are minimised and environmental compliance maximized.
3.9 Monitoring
A monitoring programme will be in place not only to ensure compliance with the EMPr through
the contract/work instruction specifications, but also to monitor any environmental issues and
impacts which have not been accounted for in the EMPr that are, or could result in significant
environmental impacts for which corrective actions required. The applicant will cause and or carry
out the internal audits.
As part of the contract or work instruction, Before the Wind Investment will stipulate the period
and frequency of monitoring required. This will be determined from applicable permits and
authorisations from authorities. The Project Manager will ensure that monitoring is carried out.
3.10 Reporting Procedures
3.10.1 Documentation
The following documentation must be kept on site in order to record compliance with the EMPr:
An Environmental File which includes:
Copy of the EMPr;
Copy of the Environmental Authorisation;
Copy of all other licenses/permits;
Copy of all rehabilitation plans;
Copy of the Storm Water Management Plan;
Copy of relevant legislation;
15
Environmental Policy of the Main Contractor;
Environmental Method statements compiled by the Contractor;
Non-conformance Reports;
Environmental register, which shall include:
Communications Register–including records of Complaints, and, minutes and attendance
registers of all environmental meetings.
Monitoring Results–including environmental monitoring reports, register of audits, Non-
Conformance Reports (NCR).
Incident book – including copies of notification of Emergencies and Incidents, this
must be accompanied by a photographic record.
Waste manifests.
Waste Documentation such as Sewerage Disposal Receipts;
Material Safety Data Sheets for all hazardous substances;
Dust suppression register;
Water Quality Monitoring reports (if necessary);
Written Corrective Action Instructions; and
Notification of Emergencies and Incidents.
3.10.2 Environmental Register
The Developer will put in place an Environmental Register. The contractor will ensure that the
following information is recorded for all complaints/incidents:
Nature of complaint/incident.
Causes of complaint/incident.
Party/parties responsible for causing complaint/incident.
Immediate actions undertaken to stop/reduce/contain the causes of the complaint/incident.
Additional corrective or remedial action taken and/or to be taken to address and to prevent
reoccurrence of the complaint/incident.
Time frames and the parties responsible for the implementation of the corrective or remedial
actions.
Procedures to be undertaken and/or penalties to be applied if corrective or remedial actions
are not implemented.
Copies of all correspondence received regarding complaints/incidents.
The above records will form an integral part of the Contractors’ Records. These records will be
kept with the EMPr, and will be made available for scrutiny if so requested by the Developer.
3.10.3 Non-Conformance Report
A Non-Conformance Report (NCR) will be issued to the Contractor as a final step towards
rectifying a failure in complying with a requirement of the EMPr. This will be issued by the ECO to
the Contractor in writing. Preceding the issuing of an NCR, the Contractor must be given an
16
opportunity to rectify the issue.
Should the ECO assess an incident or issue and find it to be significant (e.g. non-repairable
damage to the environment), it will be reported to the relevant authorities and immediately
escalated to the level of a NCR. The following information should be recorded in the NCR:
Details of non-conformance;
Any plant or equipment involved;
Any chemicals or hazardous substances involved;
Work procedures not followed;
Any other physical aspects.
Nature of the risk.
Actions agreed to by all parties following consultation to address the non-conformance in
terms of specific control measures and should take the hierarchy of controls into account.
Agreed timeframe by which the actions documented in the NCR must be carried out.
ECO should verify that the agreed actions have taken place by the agreed completion date,
when completed satisfactorily; the ECO and Contractor should sign the Close-Out portion of
the Non- Conformance Form and file it with the contract documentation.
3.10.4 Environmental Emergency Response
The Contractor’s environmental emergency procedures must ensure appropriate responses to
unexpected / accidental actions/incidents that could cause environmental impacts. Such incidents
may include:
Accidental discharges to water (i.e. into the watercourse) and land;
Accidental spillage of hazardous substances (typically oil, petrol, and diesel);
Accidental toxic emissions into the air; and
Specific environmental and ecosystem effects from accidental releases or incidents.
The Environmental Emergency Response Plan is separate to the Health and Safety Plan as it is
aimed at responding specifically to environmental incidents and must ensure and include the
following:
Construction employees shall be adequately trained in terms of incidents and emergency
situations;
Details of the organization and responsibilities, accountability and liability of personnel;
A list of key personnel and contact numbers;
Details of emergency services (e.g. the fire department / on-site fire detail, spill clean-up
services) shall be listed;
Internal and external communication plans, including prescribed reporting procedures;
Actions to be taken in the event of different types of emergencies;
Incident recording, progress reporting and remediation measures to be implemented; and
Information on hazardous materials, including the potential impact associated with each,
and measures to be taken in the event of accidental release.
17
The Contractor and their sub-contractor(s) must comply with the environmental emergency
preparedness and incident and accident-reporting requirements as per the relevant legal
requirements.
3.10.5 Method Statements
It is a statutory requirement to ensure the wellbeing of employees and the environment. To allow
the mitigation measures in this document to be implemented, task-specific method statements
should be developed for each set of tasks.
A Method Statement details how and when a process will be carried out, detailing possible
dangers/risks, and the methods of control required.
Type of construction activity;
Timing and location of the activity;
Construction procedures;
Materials and equipment to be used;
Transportation of the equipment to/from site;
How equipment/material will be moved while on site;
Location and extent of construction site office and storage areas;
Identification of impacts that might result from the construction activity;
Methodology and/or specifications for impact prevention/containment;
Methodology for environmental monitoring;
Emergency/disaster incident and reaction procedures (required to be demonstrated); and
Rehabilitation procedures and continued maintenance of the impacted environment.
The Contractor will be accountable for all actions taken inn on-compliance of the approved
Method Statements. The Contractor shall keep all the Method Statements and subsequent
revisions on file, copies of which must be distributed to all relevant personnel for
implementation. The following is a list of Method Statements that may be required:
Bunding;
Blasting
Construction site and office/yard establishment;
Cement mixing/concrete batching/bentonite mixing;
Dust management;
Environmental awareness course(s);
Environmental monitoring;
Erosion control;
Fire, hazardous and/or poisonous substances;
Fuels and fuel spills (may form part of the item above);
Storage, handling and decanting of diesel (may form part of the item above);
Personnel, public and animal safety;
18
Rehabilitation of modified environment(s);
Solid and liquid waste management;
Sources of materials (including MSDSs);
Top-soil management;
Stormwater Management.
3.10.6 Public Communication and Liaison with I&APs
The Developer must ensure that the adjacent landowners are informed and updated throughout
the construction phases.
Sufficient signage should be erected around the site (including at the entrance), informing the
public of the construction activities taking place. The sign boards should include the following
information:
The name of the Contractor.
The name and contact details of the site representative to be contacted in the event of
emergencies or complaint registration.
4.0 COMPLIANCE WITH ENVIRONMENTAL SPECIFICATION
The EMPr forms part of the Contract Documentation and is thus a legally binding document. It is
also necessary for the Contractor to make provisions as part of their budgets for the
implementation of the EMPr. In terms of the Act an individual responsible for environmental
damage is responsible for the costs for rectification and the preventative measures to reduce or
prevent additional pollution and/or environmental damage from occurring. This is referred to as
the Polluter Pays Principle. Section 28 of the NEMA embodies the polluter pays principle.
The Contract is deemed not to have complied with the Environmental Specification/EMPr if:
There is evidence of contravention of clauses within the boundaries of the site, site
extensions and haul / access roads;
Environmental damage ensues due to negligence;
The Contractor ignores or fails to comply with corrective or other instructions issued by
the Developer, ECO or Engineer within a specified time; and
The Contract or fail stores pond adequately to complaints from the public.
Application of a penalty clause may apply for incidents of non-compliance. Failure to rectify the
offense within one (1) working week of the issue of the warning or a repeat offence may result in
a fine being issued by the Environmental Officer.
The Developer is responsible for the implementation of the EMPr and for compliance monitoring of
the EMPr. The EMPr will be made binding on all contractors (including sub-contractors) operating
on the site and will be included with the Contract. Non-Compliance with, or any deviation from, the
conditions set out in this document constitutes a failure incompliance.
19
5.0 CONFORMANCE WITH THE APPLICABLE ISO STANDARDS ENVIRONMENTAL MANGEMENT SYSTEM
The ISO Environmental Management System (EMS) is the internationally recognised standard for
the environmental management of organisations. It prescribes controls for those activities that
have an effect on the environment. These include the use of natural resources, handling and
treatment of waste, energy consumption, water resource management and so forth.
All the requirements in ISO standards are intended to be incorporated into any EMS. The extent of
the application will depend on factors such as the environmental policy of the organisation, the
nature of its activities, products and services, the location and the conditions in which it functions.
The ISO family addresses various aspects of environmental management. It provides practical
tools for companies and organisations looking to identify and control their environmental impact
and constantly improve their environmental performance. The aim of the ISO standard is to
achieve continuous improvement through the cycle outlined in Figure 5.
Although not prescribed for the proposed activity, the Standards provide a set of tools that can
assist the applicant in meeting non-prescribed environmental obligattions.
Figure 4: ISO EMS Cycle of Continuous Improvement
20
6.0 ENVIRONMENTAL CODE OF CONDUCT
One of the objectives of the EMPr is to ensure that the workforce, contractors, sub-contractors
and construction staff have an understanding of environmental issues and potential impacts that
may arise from site activities. This environmental code of conduct provides the basic rules that
should be strictly adhered to. It is the responsibility of the Contractor to ensure that site
personnel understands and adhere to the Code of Conduct.
Table 4: Environmental Code of Conduct
ENVIRONMENTAL CODE OF CONDUCT
ALL PERSONS ARE OBLIGED TO KEEP TO THE RULES OF THIS CODE OF CONDUCT Ignorance, negligence, recklessness or a general lack of commitment resulting in environmental degradation or pollution shall not be tolerated! ENVIRONMENTAL RULES
Only use authorised accesses;
Do not litter;
Dispose solid waste to the correct waste containers provided;
Prevent pollution;
Use the toilet facilities provided;
Do not dispose contaminated waste water into the storm water or the environment
Immediately report any spillage from containers, plant or vehicles;
Do not burn or bury any waste on the site and;
Do not trespass onto private properties;
Do not waste electricity, water or consumables;
Strictly leave all animals alone. Never tease, catch or set devices to trap or kill any animal.
Never damage or remove any trees, shrubs or branches unless it forms part of working instructions and authorization has been received where necessary;
Do not deface, draw or cut lettering or any other markings on trees, rocks or buildings in the area;
Know the firefighting procedure and locations of firefighting equipment; and
Know the environmental incident procedures.
7.0 ENVIRONMENTAL GUIDELINES, STANDARDS AND PERMITS
The following is asummary of the environmentall legislation applicable to the proposed project
Table 5: Applicable Legislation
Legislation Sections Relates to
The Constitution (No 108
of1996)
Chapter 2 Bill of Rights.
Section 24 Environmental rights.
National Environmental
Management Act (No 107
Section 2 Defines the strategic environmental
management goals and objectives of the
21
of 1998 [as amended]) government. Applies through-out the Republic
to the actions of all organs of state that may
significantly affect the environment.
Section 24 Provides for the prohibition, restriction and
control of activities which are likely to have a
detrimental effect on the environment.
Section 28 The developer has a general duty to care for
the environment and to institute such
measures as may be needed to demonstrate
such care.
Environment Conservation
Act (No 73 of 1989) and
Regulations
Sections 19 and
19 A
Prevention of littering by employees and
subcontractors during construction and the
maintenance phases of the proposed project
National Heritage
Resources Act (No 25 of
1999) and Regulations
Section 32 No person may, without a permit issued by
the responsible heritage resources authority
destroy, damage, excavate, alter, deface or
otherwise disturb any archaeological or
paleontological site.
Section 34 No person may, without a permit issued by
SAHRA or a provincial heritage resources
authority destroy, damage, alter, exhume,
remove from its original position or
otherwise disturb any grave or burial ground
older than 60 years which is situated outside
a formal cemetery administered by a local
authority. Grave is widely defined in the Act
to include the contents, headstone or other
marker of such a place, and any other
structure on or associated with such place.
Section 35 This section provides for Heritage Impact
Assessments (HIAs), which are not already
covered under the ECA. Where they are
covered under the ECA the provincial heritage
resources authorities must be notified of a
proposed project and must be consulted
during the HIA process. The Heritage Impact
Assessment (HIA) will be approved by the
authorising body of the provincial directorate
of environmental affairs, which is required to
take the provincial heritage resources
authorities' comments into account prior to
22
making a decision on the HIA.
National Environmental
Management
Biodiversity Act (Act No.
10 of 2004)
Provide for the protection of species and
ecosystems that warrant national protection
and the sustainable use of indigenous
biological resources.
Occupational Health
and Safety Act
(No 85 of 1993)
Section 8 Control of dust
Section 9 Control of noise
Occupational Health
and Safety Act-Major
Hazard
InstallationRegulations
(GN R692, July 2001)
Sections 5 and 6 Control of offensive odours
National Water Act (No
36 of 1998) and
Regulations
Section 19 General duties of employers to their
employees
Section 20 General duties of employers and self
employed persons to persons other than
their employees
National Road TrafficAct
(No 93 of 1996)
Road safety.
Town Planning and
Townships Ordinance
15 of 1986
Town Planning.
SANS 10103 (Noise
Regulations)
The measurement and rating of
environmental noise with respect to
annoyance and to speech communication.
8.0 DETAILED ENVIRONMENTAL MANAGEMENT PROGRAMME
The EMPr specifies the minimum requirements to be implemented by the Developer as per the
scope of works and scope of the environmental authorisation, in order to minimise and manage
the potential environmental impacts and ensure sound environmental management practices. It
also provides the framework for environmental monitoring throughout the construction and
operational phases.
The provisions of this EMPr are binding on the Developer during the life of the project. The EMPr
must be binding on Cavaleros Group or any authority to which responsibility for the construction
activities has been delegated to, until such time that the Gauteng Department of Agriculture and
Rural Development (GDARD) or applicable environmental authority has formally absolved the
Developer from its responsibilities in terms of this EMPr.
23
It is essential that the EMPr requirements be carefully studied, understood, implemented, and
adhered to at all time. To simplify the EMPr requirements, each aspect related to the EMPr has
been addressed in the table below. Each action within the EMPr is supported by the priority of
when the specific action will need to be implemented. Each of these aspects is briefly described
below for ease of reference.
Environmental Measures, Actions and Controls
This section indicates the actions required to either prevent and/or minimise the potential
impacts on the environment that is associated with the project.
Responsibility
This section indicates the party responsible for implementing the environmental measures and
action plans laid out in the EMPr.
Monitoring Frequency
This section indicates when the actions for that specific aspect must be implemented and/or
monitored.
24
8.1 CATERGORY A: PRE-CONSTRUCTION PHASE
Objective or requirement
Control measure Responsibility
DESIGN AND PLANNING
STORMWATER DESIGN
To prevent and restrict erosion, siltation and groundwater pollution
Stormwater outlets shall be correctly designed to prevent soil erosion and stormwater related damage to the soil. Construction guidelines shall be provided for the prevention and restriction of erosion and siltation.
Suitably qualified specialist
A detailed storm water management plan must be approved by the City of Johannesburg prior construction activities commencing.
Engineer
INFRASTRUCTURE
Infrastructure requirements must be in accordance with the City of Johannesburg Metropolitan Municipality requirements.
Engineer
FLORAL BIODIVERSITY AND ECOLOGICAL HEALTH
To insure that the species introduced to the area, are compatible with the current and future quality of the ecological processes.
The landscape development plan and the Master plan for the proposed development shall be submitted to the local government for approval. It is important that all the plant positions, quantities and coverage per m² be indicated on a plan.
Landscape Architect
The proposed planting materials for the areas to be landscaped shall be non-invasive, and preferably indigenous and /or endemic.
Landscape Architect
OTHER DESIGN REQUIREMENTS
To prevent the extreme change in micro climate temperatures
Where open parking bays are involved, one tree for every two parking bays shall be indicated on the Landscape Development Plan
Landscape Architect
To insure stability of structures
More detailed foundation investigation shall be done for structures that are sensitive to ground water movement, or which will extent heavy loads.
Engineer
Light pollution The generation of light by night events, security lighting and other lighting shall be effectively designed so as not to spill unnecessary outward into the oncoming traffic, or into the yards of the neighbouring properties or open spaces
Landscape Architect
Architect,
Contractor
Visual impact The architecture of the proposed development shall be in line with the character of the area. Architects
25
Objective or requirement
Control measure Responsibility
The existing trees shall be incorporated in the design and the natural theme that the development should take on.
Architects and Landscape Architects
As many of the loose rocks that originate from the excavation exercises and other construction works should be re-utilised and incorporated into the natural and formal landscaping of the proposed development.
Contractor and Landscape Architects
EROSION AND SILTATION
To prevent the unnecessary loss of soil through bad management.
All surface run-offs shall be managed in such a way so as to ensure erosion of soil does not occur. All surfaces that are susceptible to erosion shall be covered with a suitable vegetative cover as soon as construction is completed
Engineer
Contractor
COMPACTION
To prevent the compaction of valuable soils due to traffic and equipment.
Designated routes shall be determined for the construction vehicles and designated areas for storage of equipment. All areas that are compacted by machinery shall be ripped prior to them being rehabilitated with topsoil and grass seed.
Contractor
Clearly mark the site access point and routes on site to be used by construction vehicles and pedestrians.
Provide an access map to all contractors whom in turn must provide copies to the construction workers.
Instruct all drivers to use access point and determined route.
ECO,
Site Supervisor
Fence off areas which are off limits to vehicles Site Supervisor
Excavate only where necessary
Mark out the areas to be excavated Site Supervisor
TOPSOIL
To prevent the loss of valuable topsoil.
The top layer of all areas to be excavated for the purpose of construction must be stripped and stockpiled in areas where this material will not be damaged, removed or compacted. This stockpiled material shall be used for the rehabilitation of the site and for landscaping purposes.
Contractor
When the stripping of topsoil takes place, the grass component shall be included in the stripped topsoil. The soil will contain a natural grass seed mixture that may assist in the re-growth of grass once the soil is used for back filling and landscaping.
Contractor
WASTE STORAGE
26
Objective or requirement
Control measure Responsibility
To control the temporary storage of waste.
No waste materials shall at any stage be disposed of in the open veld or adjacent properties Temporary waste storage points on site shall be determined. These storage points shall be accessible by waste removal trucks and these points should not be located in areas highly visible from the properties of the surrounding land-owners/tenants/in areas where the wind direction will carry bad odours across the properties of adjacent tenants or landowners.
Contractor
ECO
Avoid, reuse or recycle material where possible and correctly dispose of unusable wastes
Coordinate with other trades on site and nearby businesses for potential reuse or ‘waste exchange’
ECO
GENERAL
WASTE GENERATION AND WATER, AIR AND NOISE POLLUTION
Best practice to minimise environmental impacts and ensure efficient management
Coordinate with other trades working on site regarding: site management, timing of works and waste management (recycling and reuse potential).
Project Manager
Plan the site before starting – for access, deliveries, construction areas, washout area, waste, stockpiles, and chemicals storage.
Environmental Control Officer
Solid waste disposal Solid waste shall be disposed of in a manner approved by the Department of Water and Sanitation.
Contractor
GEOLOGY AND SOILS
To prevent the damaging of the existing soils and geology.
The top layer of all areas to be excavated for the purposes of construction shall be stripped and stockpiled in areas where this material will not be damaged, removed or compacted.
Contractor
All surfaces that are susceptible to erosion, shall be protected either by cladding with biodegradable material or with the top layer of soil being seeded with grass seed/planted with a suitable groundcover.
Contractor
No waste material shall at any stage be disposed of on the site. All solid waste must be removed and transported to a recognised waste disposal site on a weekly basis.
Contractor, Construction workers
Temporary waste storage points on the site should be determined. These storage points should be accessible by waste removal trucks and these points should not be located in sensitive areas (rocky outcrop /areas highly visible from the properties of the surrounding land-owners/ in areas where the wind direction will carry bad odours across the properties
ECO, Contractor,
27
Objective or requirement
Control measure Responsibility
of adjacent landowners.
Avoid the clearing of the site camp (of specific phase) or paved surfaces with soap. Contractors, Construction workers
SOCIAL IMPACT
Crime, safety and security
The Developer must determine which security system should be utilised for the site. Entrance points of the construction road must be secured.
Contractors, Engineers, Project Manager
Pedestrian design should acknowledge disabled persons.
Care needs to be taken in planning pedestrian links to and on site, so as to have the correct slopes to accommodate the disabled. The change in levels, however, can create interest for the pedestrian on moving through the site.
Landscape Architect, Contractors, Engineers
Noise impact Site workers must comply with the Provincial noise requirements as outlined in Provincial Notice No. 5479 of 1999: Gauteng Noise Control Regulations
Contractor
To prevent the invasion of the area with invasive species.
Invasive alien species shall be eradicated as part of the rehabilitation programme. ECO Project Manager
8.2 CATERGORY B: CONSTRUCTION PHASE
Objective or requirement
Control measure Responsibility
SOCIAL AND SAFETY
To insure the safety of the public.
Although regarded as a normal practice, it is important to erect proper signs indicating the operations of heavy vehicles in the vicinity of dangerous crossings and access roads or even in the development site if necessary.
Project Manager
With the exception of the appointed security personnel, no other workers, friend or relatives will be allowed to sleep on the construction site (weekends included)
Project Manager
Construction vehicles and activities to avoid peak hour traffic times Project Manager
Presence of law enforcement officials at strategic places must be ensured Project Manager
Following actions would assist in management of safety along the road
Adequate road marking
Project Manager
28
Objective or requirement
Control measure Responsibility
Adequate roadside recovery areas
Allowance for pedestrians and cyclists where necessary
Clear sign boards should be erected at the entrance to the site to indicate that a construction site is being entered and that certain safety precautions should be followed (hard hats, boots, etc).
Project Manager, Site supervisor
A list with all the relevant emergency telephone numbers shall be pasted up in the site office (hospital, fire department, police, ambulance, etc.) for easy access in the event of an accident.
Site supervisor, Contractor
To prevent detrimental fire hazards.
Fires shall only be permitted in specially designated areas and under controlled circumstances.
Project Manager
A fire extinguisher should be accessible at the site camp and the personnel should receive training in the use of a fire extinguisher. Furthermore, a fire extinguisher must at all times be available wherever welding or similar activities take place and be present on all construction vehicles.
Site supervisor, Project Manager
Site demarcation Fencing is required during the construction phase to demarcate the boundaries of the construction site and work camp. The fence will ensure that access to and from the site will be restricted to staff only.
Project Manager
WASTE MANAGEMENT
To prevent unhygienic usage on the site and pollution of the natural assets.
Develop a central waste temporary holding site to be used during construction. (Near the access entrance) This site should comply with the following:
Skips for the containment and disposal of a waste that could cause soil and water pollution, i.e. paint, lubricants, etc.
Domestic waste should be contained in skips with lids to prevent wind littering.
Bunded areas for containment and holding of dry building waste.
Project Manager
One toilet for every 10 workers must be established. Project Manager
No french drain systems may be installed. Project Manager
No person is allowed to use any other area than chemical toilets. Project Manager
To prevent hazardous waste from contaminating natural assets
All hazardous waste (fuel, lubricants, chemicals, diesel, etc) shall be placed in specifically designed containers and properly sealed. Should any fuel storage tank be required on site, the Contractor shall ensure that he has complied with the necessary legal requirements for the erection of such tanks.
Site supervisor, Project Manager
29
Objective or requirement
Control measure Responsibility
All containers shall be collected on a weekly basis by certified chemical removal companies.
Site supervisor, Contractor
All chemical waste shall be disposed of at a certified waste disposal site and proof of this disposal shall be sent to the contractor and ECO.
Site supervisor, Contractor
Record keeping Keep records of waste reuse, recycling and disposal for future reference. Provide information to ECO.
Site supervisor, Project Manager
Avoid, reuse or recycle material where possible and correctly dispose of unusable wastes.
All waste must be removed to a recognised waste disposal site on a weekly basis. No waste materials may be disposed of on or adjacent to the site. The storage of solid waste on site, until such time that it may be disposed of, must be in the manner acceptable to the Local Authority.
Contractor
FUEL MANAGEMENT
To refuel machinery and vehicles without contaminating natural assets
Refuelling will take place in an area such designated, with sufficient surface sealing such as a plastic liner to prevent spillage and soil contamination. Where not approved by a provincial government department – refuelling will be done off-site.
Contractor
To store fuel without contaminating natural assets
Fuel storage shall be within the construction camp, and within a bunded area with at least 110% of the volume of the amount of fuel stored, as per agreement and approval of the ECO. No storage of any fuel will be allowed on site, other than what is approved by the applicable provincial government Departments.
Contractor
FAUNA AND FLORA
Landscaping When planting trees, care should be taken to avoid the incorrect positioning of trees and other plants, to prevent the roots of trees planted in close proximity to the line of water-bearing services from causing leaking in, or malfunctioning of the services.
Landscape contractor
The proposed planting materials for the areas to be landscaped should preferably be endemic and indigenous. No exotic invaders shall be planted in the formal landscaping.
Landscape contractor
All new indigenous trees and shrubs to be planted on the study area, shall be inspected for pests and diseases prior to them being planted. The inspection shall be carried out by the maintenance contractor at the property of the supplier and not on the study area.
Landscape contractor
30
Objective or requirement
Control measure Responsibility
All trees to be planted shall be in 201 containers with a height of approximately 1,8 metres and a main stem diameter of approximately 300 mm.
Loss of plants Aerate compacted soil and check and correct pH for soils affected by construction activities.
Landscape contractor
Make sure plant material will be matured enough and hardened off ready for planting. Water in plants immediately as planting proceeds. Apply mulch to conserve moisture
Landscape contractor
Plant according to the layout and planting techniques specified by the Landscape Architect in the Landscape Development plans for the site.
Landscape contractor
Spread of weeds Ensure that materials used for mulching and topsoil/ fertilisers are certified weed free. Collect certifications where available.
Landscape contractor
Control weed growth that appears during construction. Site supervisor
ACCESS
Appropriate access provided
No workers should be allowed to enter adjacent private properties without the consent of the legal owners.
Site supervisor
The access roads for the construction vehicles and pedestrians shall be predetermined prior to any construction. No other accesses shall be used.
ECO Site supervisor Contractor
Fence off areas which are off limits to vehicles. Failure to adhere will result in spot-fines and all damage will immediately be rehabilitated at the Contractor’s expense.
Site supervisor Contractor
GEOLOGY AND SOILS
Minimise dust from the site
Dust pollution could occur during the construction works, especially during the dry months. Regular and effective damping down of working areas (especially during the dry and windy periods) must be carried out to avoid dust pollution that will have a negative impact on the surrounding environment. When necessary, these working areas should be damped down in the mornings and afternoons.
Site supervisor and Contractor
To prevent the contamination of soils and water by the leaking and discharges of machinery.
No leaking vehicle shall be allowed on site. Before entering the site, the vehicles and equipment shall be inspected for leaks by a qualified mechanic/other suitably qualified person and the environmental officer. The mechanic/ the mechanic of the appointed contractor must supply the environmental officer with a letter of confirmation that the vehicles and equipment are leak proof.
Site supervisor and Project Manager
31
Objective or requirement
Control measure Responsibility
Inaccurate stockpiling can interfere with natural drainage, cause siltation & water pollution.
Stockpiling will only be done in designated places where it will not interfere with the natural drainage paths of the environment.
In order to minimize erosion and siltation and disturbance to existing vegetation, it is recommended that stockpiling be done/ equipment is stored in already disturbed/exposed areas.
Cover stockpiles and surround downhill sides with a sediment fence to stop materials washing away.
ECO Site supervisor
Prevention of topsoil loss
Remove vegetation only in areas designated during the planning stage.
Rehabilitation/ landscaping is to be done immediately after the involved works are completed
All compacted areas should be ripped prior to them being rehabilitated/landscaped
The top layer of all areas to be excavated must be stripped and stockpiled in areas where this material will not be damaged, removed or compacted. This stockpiled material should be used for the rehabilitation of the site and for landscaping purposes.
When the stripping of topsoil takes place, the grass component shall be included in the stripped topsoil. The soil will contain a natural grass seed mixture that may assist in the re-growth of grass once the soil is used for back filling and rehabilitation.
Strip topsoil at start of works and store in stockpiles no more than 2, 5 m high in designated materials storage area.
No vehicles are allowed to traverse the stockpiled topsoil areas.
ECO and Contractor
Erosion prevention Demolition and construction activities should preferably take place during the dry months. All surface run-offs shall be managed in such a way so as to ensure erosion of soil does not occur. All surfaces that are susceptible to erosion shall be covered with a suitable vegetative cover as soon as construction is completed. Or where erosion may potentially occur, dissipaters such as gravel beds or straw bales must be installed to prevent erosion.
Project Manager, Site Supervisor
Excavations Mark out the areas to be excavated to ensure that only necessary areas are excavated. Site Supervisor
Storm water management
Appropriate Storm water outlets shall be correctly designed to prevent any possible soil erosion Engineer
32
Objective or requirement
Control measure Responsibility
stormwater outlet
Infrastructure Roads and pavements to be swept (not hosed) daily as needed. No material to go into stormwater drains or gutters.
Site Supervisor
Storm water outlets shall be correctly designed to prevent any possible soil erosion. Engineer
8.3 Post Construction Phase-Rehabilitation/Maintenance
Objective or requirement
Control measure Responsibility
SITE CLEAN UP AND PREPARED FOR USE
STORMWATER POLLUTION
Prevent blockages by not allow any materials to wash into the stormwater system.
Remove erosion and sediment controls only if all bare soil is sealed, covered or re-vegetated.
Contractor
Sweep roadways clean and remove all debris from kerb and gutter areas. Do not wash into drains.
Contractor
Minimise waste Decontaminate and collect waste in storage area ready for off-site recycling or disposal Site worker
Arrange for final collection and removal of excess and waste materials Site supervisor
ENVIRONMENTAL CONTROL OFFICER
Close-out report Do last inspection on site and sign off that the EMP has been complied with or identify breaches. Submit to GDARD for approval.
ECO
STORMWATER POLLUTION
Do not allow any materials to wash into the stormwater system.
Remove erosion and sediment controls only if all bare soil is sealed, covered or re-vegetated.
Trained site worker
Sweep roadways clean and remove all debris from kerb and gutter areas. Do not wash into drains.
Site worker
WASTE MANAGEMENT
Prevent pollution and minimise waste
Decontaminate and collect waste in storage area ready for off-site recycling or disposal Site worker
Arrange for final collection and removal of excess and waste materials Site supervisor
ESTABLISHMENT STAGE
ESTABLISHING PLANTS
Re-vegetation to Agreed schedule for regular follow-up watering, weed control, mulch supplements and Landscape contractor
33
Objective or requirement
Control measure Responsibility
stabilise soil amenity pruning, if needed. Replace all plant failures within three-month period after planting.
MATERIALS FAILURE
Prevent structural damage and loss of site materials.
Inspect all structures monthly to detect any cracking or structural problems. Confer with specifier/designer if there are design problems. Rectify with materials to match, or other agreed solution.
Project Manager
DRAINAGE FAILURE
Stormwater Management plan
Inspect all site drainage works and repair any failures. Confer with design engineer and specifier to correct site problems
Project Manager Project Engineer
MATERIALS THEFT, DAMAGE
Check client’s insurance coverage for compensation to replace items. Replace and repair to specified standards. Recommend improved surveillance or security measures
Project Manager
OPERATIONAL PHASE
GENERAL
General cleanliness and pollution prevention
No waste material shall at any stage be disposed of in adjacent open spaces Body corporate
VISUAL IMPACT
Architectural character and visual acceptability of the development
Township establishment to be approved by the local authority to ensure
compatibility with planning instruments;
Architectural designs to be aligned with the character of the area;
Use of internally focussed lighting to prevent light pollution;
Use of open space to enhance internal quality of the environment.
Development to align with the provisions of spatial plans.
Use of trees to screen sensitive receptors is encouraged
Developer, Project Manager, Architect
34
9.0 CONCLUSION
The EMPr should be seen as a day-to-day management document which sets out the environmental
standards that are required to minimise the negative impacts and maximise the positive benefits of the
proposed development. The EMPr is a “live document”, and if continuously reviewed and managed
correctly can result in successful construction and operation of the development.
All attempts should be made to have this EMPr available, as part of any contractual documentation, so
that the contractors are made aware of the potential cost and timing implications needed to fulfil the
implementation of the EMPr, thus adequately costing for them.
Further, guidance should also be taken from conditions contained in the Environmental Authorisation, if
the project is granted approval, and that these GDARD conditions must be incorporated into the final
EMPr.