Upload
ngokhuong
View
233
Download
3
Embed Size (px)
Citation preview
Engineering And Construction Contract Specifications
[CVE449]
FIDIC CONTRACTS
Dr. Ahmed Elyamany
Objectives
� By the end of this lecture, you will:
1. Define FIDIC Contracts
2. CONDITIONS OF CONTRACT
3. FEATURES AND ADVANTAGES
4. TENDERING PROCEDURES
2
4. TENDERING PROCEDURES
Dr. Ahmed Elyamany
What is FIDIC ?
� An international federation of consulting engineers, founded in 1913 with its headquarters located in Lausanne, Switzerland, whose objective is to promote the common interests of the member associations and disseminate information to its members for the development of consulting industry.
3 Dr. Ahmed Elyamany
What does FIDIC do?
� Arrange seminars and conferences and prepare standard documents, in the furtherance of its goals.
4 Dr. Ahmed Elyamany
FIDIC CONTRACTS
� Conditions of Contract for Construction (Red Book)
� Conditions of Contract for Plant and Design-Build (Yellow Book)
� Conditions of Contract for EPC/Turnkey Projects(Silver Book)
� Short Form of Contract ( Green Book)� Short Form of Contract ( Green Book)
� CLIENT/CONSULTANT MODEL SERVICES AGREEMENT
5 Dr. Ahmed Elyamany
The New Red Book
� For Construction of major building or engineering projects in general
� Employer’s Responsibility for Design
� Unit Price Contract/Remeasurement (monthly payment)
� Administration of Contract by Engineer� Administration of Contract by Engineer
� Pro-contractor in terms of risk allocation
6 Dr. Ahmed Elyamany
The New Yellow Book
� For provision of mechanical and electrical plant, and for design and execution of building or engineering projects
� Contractor’s Responsibility for Design(design extent?)
� Lump-sum, with adjustments (stage/milestone or monthly payment)
� Administration of Contract by Engineer
� Pro-contractor in terms of risk allocation
7 Dr. Ahmed Elyamany
The Silver Book
� For provision on a turnkey basis of a process or power plant, etc.
� Contractor’s Total Responsibility for Design
� Normally fixed Lump-sum, with few adjustments (stage/milestone or monthly payment)
� Administration of Contract by Employer’s Representative
� Pro-employer in terms of risk allocation
8 Dr. Ahmed Elyamany
The Green Book
� For Building or Engineering Works of Small Capital Value or containing mostly simple or repetitive work
� Contractor’s or Employer’s Responsibility for Design
� Lump-sum, with adjustments (monthly payment)
� Administration of Contract by Employer’s Representative � Administration of Contract by Employer’s Representative
� Pro-contractor in terms of risk allocation
9 Dr. Ahmed Elyamany
published 1999CONDITIONS OF CONTRACT
Guide
published 2001
Dr. Ahmed Elyamany10
STRAIGHTFORWARD
PROJECT ?EMPLOYER DESIGN ?
CONTRACTOR DESIGN
fixed price - lump sum
no
no
yesyes
WHICH BOOK TO USE?
plant and/or high
unforeseen risks
fixed price - lump sum
little employer involvement
no major unforeseen risks no
DISCUSS IN DETAIL
Employer ’s requirements
with the Contractor, and
negotiate a modified
FIDIC contract
no yesyes
11 Dr. Ahmed Elyamany
FEATURES AND ADVANTAGES
� BALANCED
� Fair apportioning of risks, rights and obligations between the parties
� WELL TRIED
� Long case history for earlier contracts
� ACCEPTEDACCEPTED
� Known and recognized; in wide use for international contracts
� SUPPORTED
� Recommended or required by development banks,
� EFFECTIVE
� Clear and complete conditions; time limits; provisions for attribution
12 Dr. Ahmed Elyamany
Key points: CONSTRUCTION
� Employer designs
� Engineer, working for the Employer
� Bill of Quantities� Bill of Quantities
� Payments based upon measurements
� Certification of payments by Engineer
13 Dr. Ahmed Elyamany
Key points: PLANT & DESIGN-BUILD
� Contractor designs
� Engineer, working for the Employer
� Lump sum pricing� Lump sum pricing
� Payments according to progress
� Certification of payments by Engineer
14 Dr. Ahmed Elyamany
Key points: EPC/TURNKEY PROJECTS
� Contractor designs and takes full responsibility
� Employer may appoint a Representative
� Fixed price, to cover risks taken on by Contractor� Fixed price, to cover risks taken on by Contractor
� Payments according to progress
15 Dr. Ahmed Elyamany
Key points: SHORT FORM
� Simple projects
� Design by either party
� Employer may appoint a Representative� Employer may appoint a Representative
� Valuation as appropriate; to be agreed
� Payments according to value of Works executed and Materials and Plant delivered to site
16 Dr. Ahmed Elyamany
Key points: CLIENT/CONSULTANT
� Agreed Scope of Services: Appendix A (the agreed scope of services)
� Normal, Additional and Exceptional Services
� Normal Services priced as agreed
� Additional and Exceptional Services at rates agreed
� Payment schedule as agreed
17 Dr. Ahmed Elyamany
USE OF FIDIC CONTRACTS
� Match contract and project
� Decide the form of contract early
� Appoint Dispute Arbitration Board early� Appoint Dispute Arbitration Board early
� preparation of the contract should be done by professionals
� Do not touch the General Conditions
18 Dr. Ahmed Elyamany
PRINCIPLES OF PROCUREMENT
� Effectiveness
� Economy
� Efficiency
� Accountability
� Transparency / confidentiality� Transparency / confidentiality
� Strong competition
� Publicity, wide participation
� Fair and equal conditions
� Standard procedures
� Standard documentation
19 Dr. Ahmed Elyamany
PROCUREMENT CATEGORIES
� Goods
� Works
VersusVersus
� Consultant services
20 Dr. Ahmed Elyamany
TENDERING PROCEDURES
� Development bank / public procurement procedures
� Open tendering / International Competitive Bidding
� Local tendering / National Competitive Bidding� Local tendering / National Competitive Bidding
� Restricted tendering / Limited Bidding
� Two stage tendering
21 Dr. Ahmed Elyamany
SELECTION PROCEDURES/CRITERIA
� Criteria defined and published in advance
� Economically most advantageous offer
� Quality based selection for intellectual services� Quality based selection for intellectual services
� Quality and cost based selection
22 Dr. Ahmed Elyamany
PROCUREMENT STEPS
� Preparation
� Publication
� Pre-qualification / short-listing
� Invitation
� (Submission)� (Submission)
� Evaluation
� Award, contracting
� Supervision, contract administration
� Lessons learned
23 Dr. Ahmed Elyamany
PREPARATION OF PROCUREMENT
� Determination of needs and objectives
� Determination of constraints
� Identification of parties
� Planning, budgeting, financing
� Contract type
� Selection procedure� Selection procedure
� Requirements / Specifications / Bills of Quantities / Terms of Reference
� Pre-qualification and evaluation criteria
� Particular conditions
� Tender documents
� Publicity
24 Dr. Ahmed Elyamany
CONTRACT ADMINISTRATION
� Supervision
� Implementation of rule
� Quality and quantity
� Invoice verification
� Payments� Payments
� Extensions, variation orders, modifications
� Termination
� Disputes and their resolution
25 Dr. Ahmed Elyamany
RISKS IN PROCUREMENT
� Wrong goods, works, services
� Bad value for money
� Fraud� Fraud
� Corruption
26 Dr. Ahmed Elyamany
Questions?Questions?
Contact:
Dr. Ahmed Elyamany
0109-4100-824
http://drahmedelyamany.weebly.com
27 Dr. Ahmed Elyamany