DAILY CONSTRUCTION REPORT (Contractor : AL MUSAIRIE) DATE: 01-Sep-2015 Contract No. GC - 13 111100 CIVIL / STRUCTURAL MANPOWER DETAILS OF FIRST SHIFT ( FROM 0430 HRS T Sr. Staf Sr. Supervisor Foreman Chargehand Skilled Labour Operators / Drivers Unskilled Labour Subcontractor 4 13 2 4 38 15 29 0 CIVIL / STRUCTURAL MANPOWER DETAILS OF SECOND SHIFT ( FROM 1500 HRS Sr. Staf Sr. Supervisor Foreman Chargehand Skilled Labour Operators / Drivers Unskilled Labour Subcontractor 0 4 0 0 10 4 20 0 1 Temporary works (Milestone 1) Work Completed 2 Gate Security Building (Milestone 2) 3 Canopy Area Foundation excavation is going on. Preparation for foundation blinding at canopy B Installation of dewatering pump & laying of flat hose 4 Boundary Fence Activity PROGRESS FENCE MATERIAL Total Qty. Unit Todate Remarks Items Unit Survey / Setting Out 946 nos 565 Line Post Nos Surface Preparation 946 nos 400 Gate Post Nos Contract Title : EPIC for Security Buildings and Boundary & Landscaping Works Casting of GSB foundations(100% Completed) Casting of Column necks(100% Completed) Anti termite application @ GSB finished. Backfilling & compaction 100% Completed Shuttering preparation for grade beam blinding 100% Completed Blinding concrete pouring 100% Completed Removal of interlock in paving area.(100% Completed)

DPR ESR SEP 01 2015

Embed Size (px)

Citation preview

Page 1: DPR ESR SEP 01 2015

DAILY CONSTRUCTION REPORT (Contractor : AL MUSAIRIE) DATE: 01-Sep-2015

Contract No. GC - 13 111100

CIVIL / STRUCTURAL MANPOWER DETAILS OF FIRST SHIFT ( FROM 0430 HRS TO 1130 HRS)

Sr. Staf Sr. Supervisor Foreman Chargehand Skilled Labour Operators / Drivers Unskilled Labour Subcontractor

4 13 2 4 38 15 29 0CIVIL / STRUCTURAL MANPOWER DETAILS OF SECOND SHIFT ( FROM 1500 HRS TO 0100 HRS)

Sr. Staf Sr. Supervisor Foreman Chargehand Skilled Labour Operators / Drivers Unskilled Labour Subcontractor

0 4 0 0 10 4 20 0

1 Temporary works (Milestone 1)Work Completed

2 Gate Security Building (Milestone 2)

3 Canopy Area

Foundation excavation is going on.

Preparation for foundation blinding at canopy B

Installation of dewatering pump & laying of flat hose

4 Boundary Fence

Activity PROGRESS FENCE MATERIAL RECEIVED AT SITE DETAILS Total Qty. Unit Todate Remarks Items Unit

Survey / Setting Out 946 nos 565 Line Post Nos

Surface Preparation 946 nos 400 Gate Post Nos

Contract Title : EPIC for Security Buildings and Boundary & Landscaping Works

Casting of GSB foundations(100% Completed)

Casting of Column necks(100% Completed)

Anti termite application @ GSB finished.

Backfilling & compaction 100% Completed

Shuttering preparation for grade beam blinding 100% Completed

Blinding concrete pouring 100% Completed

Removal of interlock in paving area.(100% Completed)

Page 2: DPR ESR SEP 01 2015

FDT Test 946 nos 400 Straining Post Nos

Shuttering 946 nos 400 Corner PostBlinding Concrete 946 nos 437 Fabric Roll

Screed 946 nos 313 Bracing Nos

Fence Post / Shutter Installation 946 nos 186 Tie Bar Nos

Fence Post Concreting 946 nos 181

Concrete Protection 946 nos 24Screening of excavated material in progress

5 Ground Improvement

6 Delivery of Selected Fill Material

Received Till 27-Aug-2015 Qty Rece. in tonne Qty Rece. in Trip Remarks

4856 134 D.Trucks

On Going activityA Gate Security Building (Milestone 2)

Preparation for grade beam

B Canopy AreaContinouos Excavation in Canopy areaContinouos Installation of dewatering pump & laying of flat hose

C Boundary FenceSetting-out of line postsFill material laying & compaction of line post for blindingShuttering of line post for fence foundations Casting of fence post foundations - 24 nos this afternoonScreening of excavated material in progress Removal of shuttering of fence post & blinding in progress Curing in progress

D Ground Improvement

Curing in progress

Curing in progress

Site grading in progress (1650 meters out of 2910 meters)

Page 3: DPR ESR SEP 01 2015

Site grading in progress

Page 4: DPR ESR SEP 01 2015

DAILY CONSTRUCTION REPORT (Contractor : AL MUSAIRIE) DATE: 01-Sep-2015

MANPOWER DETAILS OF FIRST SHIFT ( FROM 0430 HRS TO 1130 HRS)

TOTAL

105MANPOWER DETAILS OF SECOND SHIFT ( FROM 1500 HRS TO 0100 HRS)

TOTAL

38

Work Completed

Foundation excavation is going on. 2555 m3 total, 49.2x7.5x2.2x2nos----56.4x7.5x2.2x1NosPreparation for foundation blinding at canopy B

Installation of dewatering pump & laying of flat hose

Boundary Fence

FENCE MATERIAL RECEIVED AT SITE DETAILS Total Qty. Todate Remarks

877 473

16 0

Page 5: DPR ESR SEP 01 2015

53 45

60 50

106

actual 1004 meter(pt1-4,pt 8-9,pt9-10)

On Going activityGate Security Building (Milestone 2)Preparation for grade beam

Canopy AreaContinouos Excavation in Canopy areaContinouos Installation of dewatering pump & laying of flat hose Boundary FenceSetting-out of line postsFill material laying & compaction of line post for blinding

Screening of excavated material in progress Removal of shuttering of fence post & blinding in progress Curing in progress Ground Improvement

Page 6: DPR ESR SEP 01 2015

Site grading in progress