DAILY CONSTRUCTION REPORT (Contractor : AL MUSAIRIE) DATE: 01-Sep-2015
Contract No. GC - 13 111100
CIVIL / STRUCTURAL MANPOWER DETAILS OF FIRST SHIFT ( FROM 0430 HRS TO 1130 HRS)
Sr. Staf Sr. Supervisor Foreman Chargehand Skilled Labour Operators / Drivers Unskilled Labour Subcontractor
4 13 2 4 38 15 29 0CIVIL / STRUCTURAL MANPOWER DETAILS OF SECOND SHIFT ( FROM 1500 HRS TO 0100 HRS)
Sr. Staf Sr. Supervisor Foreman Chargehand Skilled Labour Operators / Drivers Unskilled Labour Subcontractor
0 4 0 0 10 4 20 0
1 Temporary works (Milestone 1)Work Completed
2 Gate Security Building (Milestone 2)
3 Canopy Area
Foundation excavation is going on.
Preparation for foundation blinding at canopy B
Installation of dewatering pump & laying of flat hose
4 Boundary Fence
Activity PROGRESS FENCE MATERIAL RECEIVED AT SITE DETAILS Total Qty. Unit Todate Remarks Items Unit
Survey / Setting Out 946 nos 565 Line Post Nos
Surface Preparation 946 nos 400 Gate Post Nos
Contract Title : EPIC for Security Buildings and Boundary & Landscaping Works
Casting of GSB foundations(100% Completed)
Casting of Column necks(100% Completed)
Anti termite application @ GSB finished.
Backfilling & compaction 100% Completed
Shuttering preparation for grade beam blinding 100% Completed
Blinding concrete pouring 100% Completed
Removal of interlock in paving area.(100% Completed)
FDT Test 946 nos 400 Straining Post Nos
Shuttering 946 nos 400 Corner PostBlinding Concrete 946 nos 437 Fabric Roll
Screed 946 nos 313 Bracing Nos
Fence Post / Shutter Installation 946 nos 186 Tie Bar Nos
Fence Post Concreting 946 nos 181
Concrete Protection 946 nos 24Screening of excavated material in progress
5 Ground Improvement
6 Delivery of Selected Fill Material
Received Till 27-Aug-2015 Qty Rece. in tonne Qty Rece. in Trip Remarks
4856 134 D.Trucks
On Going activityA Gate Security Building (Milestone 2)
Preparation for grade beam
B Canopy AreaContinouos Excavation in Canopy areaContinouos Installation of dewatering pump & laying of flat hose
C Boundary FenceSetting-out of line postsFill material laying & compaction of line post for blindingShuttering of line post for fence foundations Casting of fence post foundations - 24 nos this afternoonScreening of excavated material in progress Removal of shuttering of fence post & blinding in progress Curing in progress
D Ground Improvement
Curing in progress
Curing in progress
Site grading in progress (1650 meters out of 2910 meters)
Site grading in progress
DAILY CONSTRUCTION REPORT (Contractor : AL MUSAIRIE) DATE: 01-Sep-2015
MANPOWER DETAILS OF FIRST SHIFT ( FROM 0430 HRS TO 1130 HRS)
TOTAL
105MANPOWER DETAILS OF SECOND SHIFT ( FROM 1500 HRS TO 0100 HRS)
TOTAL
38
Work Completed
Foundation excavation is going on. 2555 m3 total, 49.2x7.5x2.2x2nos----56.4x7.5x2.2x1NosPreparation for foundation blinding at canopy B
Installation of dewatering pump & laying of flat hose
Boundary Fence
FENCE MATERIAL RECEIVED AT SITE DETAILS Total Qty. Todate Remarks
877 473
16 0
53 45
60 50
106
actual 1004 meter(pt1-4,pt 8-9,pt9-10)
On Going activityGate Security Building (Milestone 2)Preparation for grade beam
Canopy AreaContinouos Excavation in Canopy areaContinouos Installation of dewatering pump & laying of flat hose Boundary FenceSetting-out of line postsFill material laying & compaction of line post for blinding
Screening of excavated material in progress Removal of shuttering of fence post & blinding in progress Curing in progress Ground Improvement
Site grading in progress