Upload
hanyalramady
View
219
Download
0
Embed Size (px)
DESCRIPTION
wayleve
Citation preview
OMD DEPARTMENT
OPERATIONS DIVISION
DAMAGE PREVENTION UNIT
Way leave NO EDD/ 2010/2016 Contractor Name& Phone NoBlock No 575 A.Karim Al JahromiRoad No. 7552 17821000Starting Date
30/05/2016Contact Date
Service Representative Name AQEEL FATEEL (36052803)Site Meeting Contractor signature
HANY 39955944
According to the site- meeting held with the Contractor’s Representative, the following ticked condition should be considered.
1 OMD Must be informed about Starting Date
2 Trial holes must be made of Contractor and checked by OMD inspector before Excavation.
3 “Code of Practice. “Should be applied.
4 A clearance to one meter is required
5 OMD should be called on 17875555 to inspect clearance before backfilling.
6 All affected M/H covers &gully gratings should be adjusted to the road level.
7 The system be demolished and rebuilt in accordance with MOWPW’S Standard Details Drawing &
Specification for Sewerage & Drainage Civil Engineering.
8 Concrete Protection of 150 mm is required.
9 Any Crossing of OMD services must be reported to at any time.
10 A copy of the W.L, P.P, and the site – meeting log must always be kept with the Forman on site.
11 the Contractor must immediately inform OMD on about any old & new damages found.
12 OMD Plant should not be moved without prior permission from OMD.
13 Any Contractor intends to work at night contact OMD on not later than 1.00 pm same day
14 For any emergency work, the contractor should contact OMD on before Commencing work.
15 Any Contractor working on any OMD system should obtain a “Permit to Work” which is” issued by
OMD‘s Operations Division on weekly basis.
16 Any Contractor intends to pump ground water into any of OMD system should obtain a “pumping permit”
Which is issued by OMD’s operation Division on weekly basis.
Further Comments: