Downstream Monitor - MEA Week 15

Embed Size (px)

Citation preview

  • 8/11/2019 Downstream Monitor - MEA Week 15

    1/22

    For analysis and commentary on these and other stories, plus the latest downstream developments, see inside

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    16 April 2014

    Week 15

    Issue 152

    News Analysis

    Intelligence

    Published by

    NewsBase

    COMMENTARY 2

    Iran ratchets up exports rhetoric 2

    Oman: action on graft releases

    contracting energy 4

    Infrastructure works on

    the way for Kenya 6

    Russian roulette points the

    barrel at TANAP 7

    POLICY 8

    Egypt strikes energy security

    deal with Kuwait 8

    Zambia seeks financiers

    to fund oil imports 9

    COMPANIES 9

    ABB takes Zirku power contract 9

    Sasol earnings rise by 26%, whiledoubts are raised about SA future 10

    REFINING 11

    Abadan to produce Euro IV fuel 11

    Construction to begin on

    Egyptian refinery 11

    FUELS 12

    Basra NGL advances as Technip gets

    FEED contract 12

    OGC plans LPG plant in Salalah 12

    PIPELINES 13

    Transnet suffers yet another setback 13

    TERMINALS & SHIPPING 13

    Libya crude oil exports set

    to resume this week 13

    TENDERS 14

    KNPC floats new refinery tenders 14

    NEWS IN BRIEF 15

    CONFERENCES 19

    SPECIAL REPORT 21

    NEWS THIS WEEK

    Iran: bullish sentimentIrans deputy petroleum minister this week toldNewsBasethat the country is keen to establisheffective and stable interaction on the globalmarket, and responded bullishly to questions aboutsanctions.

    He said that Iran was exporting 1 million bpddespite IEA reports estimating it at 1.65 millionbpd. (Page 2)

    Majedi outlined ambitious plans for Iran LNG tocome online during 2015. (Page 3)

    Swift action reaps rewardsAs corruption arraignments swept through thesultanates leading state oil and gas companies inlate 2013, progress on major projects wasinevitably slowed. However, the dramaticculmination of the resulting criminal trials in thefirst three months of this year has precipitated asurge in contracting activity along the downstreamvalue chain, from refineries to speciality chemicals.

    The conclusion of corruption trials has promptedkey petrochemicals project awards. (Page 4)

    NewsBase

    Downstream Monitor

    MEA

  • 8/11/2019 Downstream Monitor - MEA Week 15

    2/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 2

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    Iran is slowly ratcheting up rhetoric

    designed to smooth its return as a fully-

    fledged player to global oil and gas

    export markets, although experts believethat it could be three-five years before

    this actually happens,NewsBasehas

    learnt from comments made at an oil and

    gas conference taking place in Dubai this

    week.

    Iran is projecting an increase in oil

    production to 5 million barrels per day in

    2018. Global crude oil supplies will rise

    to 113 million bpd in 2014, Irans

    deputy petroleum minister in charge of

    international affairs, Ali Majedi, told the

    Middle East Petroleum and GasConference, organised by Singapores

    Conference Connection Group, in Dubai

    April 14.

    Iran is currently exporting around 1

    million bpd to global markets, he said, to

    countries thought to include Far Eastern

    players like Japan, Korea, Taiwan and

    India, and is trying to make its first

    tentative steps into LNG production.

    However, the International Energy

    Agency (IEA) recently reported Iranian

    exports at around 1.65 million bpd in

    February and predicted similar levels

    during Marchexceeding significantly

    the 1 million bpd limit set out in the

    agreement with the P5+1 signed on

    November 24, 2014.

    Majedi also told the conference that

    Iran now had the worlds largest gas

    reserves.

    BPs 2013 Statistical Review of World

    Energy said Irans proved natural gas

    reserves stood at 33.6 trillion cubic

    metres at the end of 2012, while the total

    reserves of Russia, until recently seen as

    the worlds largest owner of gas reserves,

    were 32.9 tcm.

    Coming to the table

    Iran seeks an effective and stable

    interaction with the worlds key oil and

    gas players, including NOCs and IOCs,

    and a diversified market. This would be

    a win-win interaction, Majedi said. He

    also called for a fair multilateral co-

    operative strategy and a non-political

    trade and investment framework.

    I strongly believe that security of

    energy supply should be respected by all

    countries of the world. Iran is the worldsbiggest cumulative oil and gas [reserves]

    holder, based in a geopolitical and

    strategic location. It has a 1,800 km

    shoreline on the Persian Gulf and the

    Oman Sea. Iran holds the worlds fourth-

    largest oil reserves at 11% [of the total].

    He said profitability of projects would

    be a hallmark of investor experience

    when the green light was finally received

    for international participation in Irans

    projects market. However, he added that

    Iran has not accepted [EU and US]

    sanctions, as progress in a number of

    domestic fields demonstrated.

    He said that consumer loss was

    caused by a political approach to the

    oil and gas industry.

    Commenting on the current European

    situation in light of the Ukraine crisis, hesaid 33% of Europes gas was onshore,

    while of the rest, 23% was provided by

    Russia, 22% by Norway and 11% by

    Algeria.

    Qatar, Nigeria and Libya also played a

    role in supplying European gas markets,

    a lucrative area on which Iran has long-

    term designs, given prices as high at

    US$14-15 per million British thermal

    units (mBtus) on the continent.

    Gas export plansIran plans to increase its gas exports

    through a comprehensive and coherent

    programme Irans domestic market is

    saturated, he said. Majedi added that

    Iran LNG would come online in 2015,

    without giving further details. It would

    be possible to assign 100% to foreign

    investors through Build Own Operate

    [BOO] or Build Operate Transfer [BOT]

    [frameworks], he said.

    According to Iran LNGs website, EPC

    contractors have been assigned to

    packages for LNG storage tanks and

    harbour and jetties, but process, utilities

    and offsite areas, including loading

    facilities, and liquefaction unit work

    appears not yet to be awarded.

    Iran, which on paper once had the

    potential to match Qatar as a global

    player, has remained frozen out of the

    gas market because sanctions have led to

    a failure to attract international EPC

    players to install the complex technology

    required to develop its assets.

    COMMENTARY

    Iran ratchets up exports rhetoric

    Irans deputy petroleum minister this week toldNewsBasethat the country is keen toestablish effective and stable interaction on the global market, and responded bullishly

    to questions about sanctions

    y Peter Shaw-Smith

    He said that Iran was exporting 1 million bpd despite IEA reports pegging it at 1.65 million bpdMajedi outlined ambitious plans for Iran LNG to come online during 2015He set out details of US$255 billion of investment plans, most of it aimed at the up- and downstream sectors

    Majedi set out detai ls of

    US$255 bil li on worth of

    investment in Irans oil

    and gas sectors due to take

    place in 2011-15

  • 8/11/2019 Downstream Monitor - MEA Week 15

    3/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 3

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    On the question of Iranian pipeline

    exports to the UAE, Majedi said: We

    are ready to renegotiate and co-operate,

    he said. Asked if in addition Iran might

    supply gas for domestic use in Oman or

    LNG export, he said: Maybe both.

    Of course we will try to compete with

    Russia, he said. There is competition in

    the world. If Iran wants to export more

    gas, each economy in the world can[choose from whom it wants to buy]. We

    are trying to find countries where we can

    get market [share]. We are trying to find

    another customer for export of gas after

    2015, he said, referring to an existing

    deal with Pakistan.

    Investment expectations

    Majedi set out details of US$255 billion

    worth of investment in Irans oil and gas

    sectors due to take place in 2011-15. The

    bulk of this will be in the upstream,midstream and downstream oil sector.

    Arabian Oil and Gas reported March 4

    that Iran had allocated US$255 billion

    for its oil and gas industries, of which

    US$155 billion is for the upstream

    sector. By September 2013, US$42

    billion of this money had already been

    invested, leaving US$113 billion to be

    invested before 2016, the publication

    said.

    Wind of changeTehran has publically mooted its

    consideration of a new contractual model

    for upstream projects, to allow for

    alignment of government and contractor

    take. Majedi said this would mean an

    integrated operation for exploration,

    development and production. We are

    looking to maximise incentives for

    investors in low and high-risk areas.

    In December 2013, Irans Petroleum

    Minister Bijan Namdar Zangeneh said at

    an OPEC conference in Vienna thatmember countries would welcome

    Irans return to world crude oil markets.

    He said Iran was planning to bring its oil

    production back to 4 million bpd when

    international sanctions were lifted.

    I noted in a statement that we [will]

    return to the market in the shortest

    possible time, and naturally, we expect

    OPEC [member countries] to co-operate

    with us. OPEC welcomed our return at

    its highest level, which was exactly what

    I expected them to do, he was quoted as

    saying by the Ministry of Petroleums

    monthly publication.

    He added that the cartels historic

    background also shows that when a

    member exits the market [because of]

    problems and makes a second coming,

    member states have always shown their

    maximum co-operation for that memberto take back its share.

    Great expectations

    On the sidelines of the conference, an

    industry executive toldNewsBasethat

    the interim agreement between Iran and

    the P5+1 would come up for

    reassessment on July 20, after

    implementation of the November accord,

    due to be in force for six months, was

    delayed. He said it would be five years

    at least before Iran would start to seemajor investment in its oil and gas

    industry and a return to a pre-sanctions

    situation. The source also quoted an

    Iranian national as saying that Iran would

    try to move towards oil exports at around

    1.5-1.6 million bpd, with perhaps slight

    increases going forward, but that it was

    unlikely that a major change would come

    about in the next 12 months. Everybody

    going to Iran, investment coming up,

    thats not on the cards [in the next three-

    five years], he said.

    As if to underline what he saw as the

    merely temporary nature of the Irans

    current predicament, Majedi sought to

    lay stress on the long-term dynamics in

    hydrocarbons markets, and the role that

    players like his country could enjoy. He

    said global natural gas use, some of it

    unconventional, was predicted to rise by

    65% in the next 25 years, with China,

    India and the US the worlds main oil

    consumers in 2040. About US$19

    trillion in investments are required, he

    saidlofty aims indeed.

    COMMENTARY

  • 8/11/2019 Downstream Monitor - MEA Week 15

    4/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 4

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    In late February, Ahmed al-Wahaibi,former CEO of government-owned

    Oman Oil Co. (OOC) was jailed for a

    shocking 23 years for accepting bribes in

    relation to the signature of a

    petrochemicals project agreement in

    2012. Joining him behind bars a few days

    later was Adel al-Kindi, previously CEO

    of Oman Oil Refineries & Petroleum

    Industries Co. (ORPIC), convicted of

    involvement in graft surrounding

    contract awards for work on the Sohar

    refinerythe firms largest asset and acrucial one for broader downstream

    development schemes in the country.

    With the highest echelons of the

    governments two flagship downstream

    hydrocarbons companies and their

    private sector partners forced to turn their

    eyes to the past, it is little wonder that the

    focus was diverted from major future

    projects on their slates, thus holding up

    investments worth billions of dollars.

    However, as these and other trials in an

    unprecedentedly wide-ranging

    crackdown on high-level corruption inpublic institutions reached their

    conclusions during the first quarter of

    2014, an apparent release of pent-up

    energy has ensuedwith a flurry of vital

    contracts on refining and petrochemicals

    schemes moving to the tendering,

    bidding or award stage.

    Petchems push

    Petrochemicals have become central to

    Muscats strategy of economic

    diversification, both sectoral andgeographicalwith plans to develop the

    industry not only at the established

    industrial nerve centre of Sohar but also

    at the southern port of Salalah and, from

    a greenfield base at Duqm, on the central

    Al-Wusta coast.

    Should all the planned projects come

    to fruition, Oman would become a world-

    scale producer alongside fellow Gulf

    giants Qatar and Saudi Arabia, driven by

    similar aims of reducing dependence on

    raw hydrocarbon exports and translating

    hydrocarbon wealth into job creation forrapidly increasing local populations.

    Compared to these Gulf Co-operation

    Council (GCC) oil and gas

    heavyweights, the sultanate is a relative

    minnow.

    Oil production stands at around

    920,000 barrels per day according to the

    latest BP energy statistics, compared

    with 2 million bpd from Qatar and 11.5

    million bpd from Saudi Arabia, while the

    gas contrast is even starkerwith proven

    reserves of around 33.5 trillion cubic feet(949 billion cubic metres), dwarfed by

    Dohas 885.1 tcf (25 trillion cubic

    metres) and Riyadhs 290.8 tcf (8.2 tcm).

    Omans advantage

    However, Omans crucial advantage lies

    in its location, allowing the import and

    export of products to key Asian markets

    without passing through the Strait of

    Hormuz and thus without the risk of

    being affected by political uncertainty

    involving Iranwhich has in the past

    threatened to close the waterway inprotest at international sanctions on its

    hydrocarbons industry.

    Pure import-export refineries and

    downstream facilities such as that

    planned at Duqm are thus economically

    viable.

    An upstream investment programme is

    also well under way to stem oil output

    decline and to boost gas production, with

    the biggest projectKhazzannow

    entering the construction phase.

    COMMENTARY

    Oman: action on graft releases

    contracting energyAs corruption arraignments swept through the sultanates leading state oil and gas

    companies in late 2013, progress on major projects was inevitably slowed. However, with

    the cases now over, there has been a recent surge in contracting activity

    y Clare Dunkley

    The conclusion of corruption trials has prompted key petrochemicals project awardsBoth major Sohar downstream complexes have appointed project managersThe award of the Duqm refinery FEED is a clear sign that the port zone development is back on track

  • 8/11/2019 Downstream Monitor - MEA Week 15

    5/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 5

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    This follows the signature of a final

    gas sales agreement in December 2013.

    The US$16 billion development of tight

    gas reserves at the Khazzan field in

    central Block 61 by BP, and due to

    deliver 1 billion cubic feet (28 million

    cubic metres) per day by 2018,

    equivalent to around 33% of national

    output.

    Industrial hub

    At the heart both of new developments

    and of the criminal investigations

    remains the well-established industrial

    hub of Sohar, home to the sultanates

    largest refinery and petrochemicals

    facilities, the management of which were

    combined in 2011 under the ORPICumbrella.

    The refinery is being expanded under a

    US$2.1 billion engineering, procurement

    and construction (EPC) contract awarded

    in November 2013 to a joint venture (JV)

    of South Koreas Daelim Industrial and

    the UKs Petrofac, which will raise

    output to 187,000 bpd from 116,000 bpd

    and thereby feed both ORPICs existing

    340,000 bpd polypropylene (PP) plant

    currently running at only around 60% of

    capacityand supply additional facilitiesplanned by ORPIC and OOC.

    The largest of theseand indeed the

    largest ever in Omanis the estimated

    US$3.6 billion Liwa Plastics scheme to

    build a steam cracker and downstream

    units, to be the first in the country to

    manufacture polyethylene (PE) and its

    derivatives and to have capacity of 1

    million tonnes per year (tpy) on

    completion in 2018.

    Output will comprise high-density

    polyethylene (HDPE), linear low-density

    polyethylene (LLDPE), PP, methyl

    tertiary butyl ether (MTBE) and butane-

    1, with feedstock sourced partly from the

    refinery and partly from the central

    Fahud gas field. After formal launch in

    mid-2013, little was heard of the project

    above the noise of the corruption

    crackdown. However, shortly after Al-

    Kindi learned his fate, his successors

    awarded the project management

    consultancy (PMC) and front-end

    engineering and design (FEED) contracts

    to Engineers India Ltd (EIL) and CB&I

    of the US respectively, with

    prequalification for the EPC contracts

    expected to be launched by the end of theyear in order to return the project to

    schedule. A tender for the financial

    advisory mandate was floated in late

    March, with a May 6 deadline.

    Even more mired in the graft morass

    was the other major new petrochemicals

    venture planned at Sohara polyester

    chemicals complex to be developed

    under an agreement between OOC and

    South Koreas LG International signed in

    2012corruption in the negotiation of

    which led to the imprisonment of both

    Al-Wahaibi and the vice-CEO of LG.

    However, far from being abandoned in

    light of such tainted beginnings, this

    scheme too seems to have been

    galvanised by the trials end, with

    Australia Worley Parsons selected for

    the PMC in March.

    The estimated US$850 million plant

    will produce 1.1 million tpy of purified

    terephthalic acid (PTA) and 500,000 tpy

    of polyethylene terephthalate (PET), used

    primarily in packaging, and like Liwa

    will be fed by ORPICs refinery indicative of the close and overlapping

    ties between the various state

    hydrocarbons companies.

    OOCs subsidiary Takamul Investment

    is planning a complementary 100,000 tpy

    purified isophthalic acid (PIA) plant in

    partnership with ORPICwhich will

    provide metaxyelene feedstockwhile

    the PIA will be combined with PTA from

    OOCs facility to produce PET. Design

    work is expected to be completed by the

    end of 2014.

    Diversification

    As in Saudi Arabia, Oman is pursuing

    geographical as well as general economic

    diversification, spreading economic

    activity and wealth beyond Muscat and

    Sohar through developing new hubs such

    as Duqm and Salalah, both designated

    special economic zones (SEZs).

    While Salalah is already home to

    several petrochemicals plants, Duqms

    development as a major port and

    industrial area is being carried out from

    scratch, with a refinery and

    petrochemicals complex as the

    centrepiece and OOCs priority project

    among the many in the zone in which the

    firm is investing. The state company is

    implementing the estimated US$15billion scheme in 50:50 JV with Abu

    Dhabis International Petroleum

    Investment Co. (IPIC)the latter

    providing the necessary crude from the

    emirates Habshan oil processing hub.

    The project itself has escaped censure

    during the corruption debacle but

    officials from the Transport &

    Communications Ministry and Athens-

    based Consolidated Contractors were

    jailed in March for improper payments

    during the award of contracts relating tothe portwhich will handle the

    refinerys raw materials and exports

    while the conclusion of Al-Wahaibis

    case has again coincided with renewed

    OOC-related activity. In late March,

    Foster Wheeler of the US was awarded

    the FEED contract for the estimated

    US$6 billion, 230,000 bpd import-export

    refinery, envisaged as a first phase to be

    followed at an unspecified later date by a

    US$9 billion second phase adding

    petrochemicals production. Frances

    Credit Agricole was selected as financial

    adviser to the project company, Duqm

    Refinery & Petrochemical Industries, in

    2013. On a smaller scale, further

    petrochemicals development at Salalah,

    led by Takamul, is well under way, with

    a US$500 million caustic soda and

    ethylene dichloride plant under

    construction and plans recently

    announced for an ammonia facility,

    valued at several hundred million dollars,

    to add value to the output from the

    operational Salalah Methanol plant.

    COMMENTARY

    The revolutions that tore

    through the Arab wor ld in

    2011 barely touched

    poli tically quiescent Oman,

    bar l imited protests in

    major citi es demanding,

    among other things, an

    end to high-l evel

    corruption

  • 8/11/2019 Downstream Monitor - MEA Week 15

    6/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 6

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    The revolutions that tore through the

    Arab world in 2011 barely touched

    politically quiescent Oman, bar limited

    protests in major cities demanding,

    among other things, an end to high-level

    corruption.

    Frightened into action by such unusual

    demonstrations of dissent, Muscat acted

    swiftly to strengthen anti-graft

    mechanisms, re-constituting the State

    Financial and Administrative Audit

    Institution with a remit to present

    evidence of illegalities to the Office of

    the Prosecutor General.

    As these moves have proven more than

    mere window-dressing, the damage

    wreaked by unrest elsewhere in the

    region to the ability of many states to

    attract foreign direct investment may

    have precisely the opposite effect in the

    sultanate by increasing transparency at

    the same time as ensuring popular calm,

    boding well for Muscats ambitious

    downstream plans.

    Kenya is preparing for a regional oil rush

    that it hopes will transform its economy

    and bring down high fuel prices.

    The country is investing in new import

    and export infrastructure and co-

    operating with neighbours over possible

    new refinery projects that will make the

    region more self-sufficient in higher-

    value oil products.

    Meanwhile, Kenya continues to attract

    interest from local and international

    explorers and developers, keen to win a

    slice of the countrys newly discovered

    oil wealth. Kenyas government has

    already starting relocating the Kipevu oil

    terminal in Mombasa to allow more and

    bigger tankers to berth, Kenya Ports

    Authority (KPA) said last week. The new

    terminal will cost US$120 million and,

    once complete, will have the capacity for

    two large vessels at the same time, each

    carrying 100,000 tonnes (733,000

    barrels) of crude oil.

    Once complete, in 2018, it should helpreduce fuel prices in Kenya by solving

    perennial capacity constraints in the

    handling of petroleum products.

    The sector has been experiencing

    shortages of petroleum oils occasioned

    by lack of adequate storage capacity in

    the industry, according to KPAs

    chairman, Danson Mungatana. The

    situation has caused delays for vessels

    and inadvertent ship congestion, which in

    turn raises prices of oil in the country.

    Refining

    Kenya is also teaming up with Uganda

    and Rwanda to help ease a crippling lack

    of refining capacity in the region, with

    plans to build a joint refinery in Uganda.

    The proposed refinery is expected to be

    built in the Hoima district, because of its

    sparse population and the proximity to

    Ugandas oilfields. It will be jointly

    owned by the public, with a 40% stake,

    and the private sector, with a 60% stake,

    according to Reuters reports.

    The proposed plant would have a

    capacity of around 60,000 barrels per

    day, dwarfing Kenya Petroleum

    Refineries 35,000 bpd plant in Kipevu,

    which is currently the only refinery in the

    region and is on the verge of closing.

    Kenya does plan to build another US$2.8

    billion refinery on its northern coast but

    has made little progress thus far.

    Privately owned National Oil Ethiopia

    is also keen to get in on the act, with its

    CEO, Tadesse Tilahun, saying last weekthat it wants to part-finance a refinery

    with other various partners.

    Africas demand for refined products

    is growing hugely because of its

    economic growth. The crude findings are

    also increasing. That is the opportunity,

    he said. We want to [build] a refinery.

    We have already discussed this in

    principle with our shareholders, who are

    very much committed.

    Africa faces challenges, though, in

    supplying more of its own refined

    petroleum products. Funding for oil-

    related infrastructure is still tough and

    foreign refiners and traders continue to

    flood the market with US$80 billion

    worth of imports, said Tadesse. Existing

    pipelines also tend to run to the coast

    either for the export of crude or to import

    transport fuel produced at coastal

    refineries.

    That has to change, he says.

    Refineries are now needed inland so

    that Africa can supply itself.

    Pipelines

    In another sign of increased co-operation

    with neighbouring states, Kenya and

    Uganda have reportedly agreed to build a

    crude oil export pipeline that will

    incorporate a special heating system to

    keep the waxy crude found in Kenya

    liquid and flowing.

    The 1,380-km long pipeline would be

    the longest such link in the world.

    On the Kenyan side, the pipelinewould probably run mostly underground,

    stretching 850 km from the Lokichar

    Basin to the coast, according to a report

    last month by Tullow Oil, which has

    drilled seven wells in the area, finding

    600 million barrels of oil.

    Ugandas section is expected to run

    from the Lake Albert rift basin to link up

    with the Kenyan pipeline, with another

    link from South Sudan to Lamu.

    COMMENTARY

    Infrastructure works onthe way for Kenyay Helen Castell

  • 8/11/2019 Downstream Monitor - MEA Week 15

    7/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 7

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    Uganda and Kenya are now at the

    heart of an emerging power house in

    future global oil supply markets and this

    has created some high-potential

    synergies for accelerated oil production

    and inter-governmental [co-operation] in

    the region, said Tullows CEO, Aidan

    Heavey.

    Farm Tower

    Kenya is also attracting more interest

    from energy companies. London-listed

    minnow Tower Resources agreed last

    week to farm in to the onshore Block 2B,

    acquiring a 15% participating interest

    from Taipan Resources Kenya-based

    subsidiary, Lion Petroleum.

    Taipan will remain operator of the

    block with a 30% interest. Tower is

    paying US$4.5 million in cash for the

    stake plus 9 million of its own shares and

    will make an additional payment of

    US$1 million conditional upon the

    spudding of a second well in the block.

    Home-grown companies are also

    getting into better shape, with Kenyan oil

    marketer KenolKobil reporting last week

    that it booked a profit in 2013 as its

    exchange rate losses were reduced and

    cost-cutting paid off.

    The company made a 564 million

    shilling (US$6.51 million) pre-tax profit

    in 2013, compared with a 8.9 billion

    shilling (US$102.6 million) loss the

    previous year. It also forecasts stronger

    sales this year.

    Nearly 15 years on since it was first

    mooted, a European Union (EU) energy

    policy objective the Southern Gas

    Corridor has never appeared more

    necessary.

    Two months on from Russias

    annexation of Crimea and with Russian

    troops massing on Ukraines eastern

    borders, Russian President Vladimir

    Putin last week gave his clearest message

    yet that he is prepared to use the ultimate

    weapon if he does not get what he

    wantsnamely to cut supplies of

    Russian gas flowing to Europe via transit

    lines through Ukraine.

    While Putins warning referred directly

    only to the cutting of supplies to Ukraine

    in the event of further violation of

    payment for gas supplied it also noted the

    risk that Ukraine may siphon off gas

    being transited to Europe, warning of the

    possible need then to cut those supplies

    too.

    Although not explicitly stated, the

    message to Europe was clear: intervene

    in our dispute with Ukraine and face gas

    cuts. It comes as no surprise then that

    those EU policy makers have suddenly

    rekindled interest in the EUs long-

    mooted plan to create the Southern Gas

    Corridor allowing the export of gas from

    the Caspian and Middle East through

    Turkey.

    Until last year, the EU was banking on

    the development of the multinational

    Nabucco pipeline running from Eastern

    Turkey through Bulgaria, Romania and

    Hungary to Austriaand in its later

    incarnation, on to Germany and Poland.

    Over a decade in the planning,

    Nabucco never overcame the major

    obstacle of how to ensure the viability of

    a 31 billion cubic metre per year pipeline

    being developed by a consortium none of

    whose members own any upstream gas,

    and which has only a conditional promise

    of 16 bcm per year of supplies.

    Lack of progress

    Most observers concluded that

    Azerbaijans announcement in late 2011

    that it wanted to develop its own gas

    pipeline in partnership with Turkeythe

    Trans Anatolian Gas Pipeline (TANAP)

    saved the EU the embarrassment of

    having to admit that the project it had

    been backing was unlikely ever to be

    realised in the form it had envisioned.

    So far however, plans for TANAP are

    proving scarcely any smoother.

    Over a year ago, it was announced that

    TANAP would be developed by a

    consortium in which the State Oil

    Company of Azerbaijan Republic

    (SOCAR) would take a 51% stake,

    Turkey would 20%, with the remaining

    29% being divided between the three

    other members of the consortium

    developing the Shah Deniz gas field

    which will supply the 16 bcm of gas

    committed to TANAP: BP (12%), Statoil

    (12%) and Total (5%).

    COMMENTARY

    Russian roulette points

    the barrel at TANAPContinuing Russian aggression in Ukraine has rekindled Europe interest in a Southern

    Gas Corridor. But with TANAP now the only game in town, can Azerbaijan and Turkey

    actually deliver, and at what price?

    y David OByrne

    TANAP last year beat off competition from Nabucco to pipe gas from the Caspian to EuropeHowever, little progress has been made, and due diligence is only now being carried out by Botas and BPStatoil and Total have made it clear they will play no part in TANAP and may withdraw from Shah Deniz

  • 8/11/2019 Downstream Monitor - MEA Week 15

    8/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 8

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    Now with both Statoil and Total

    having confirmed they will play no part

    in TANAP, Statoil having reduced its

    stake in Shah Deniz from 25.5% to 10%

    and Total apparently intent on selling allof its 10% take, the structure of the

    TANAP consortium is no clearer.

    Indeed if statements made at a

    conference in Turkey last week by the

    remaining three participants are anything

    to go by, the process of finalising the

    three party consortium is proving

    problematic.

    Speaking in Ankara, Saltuk Duzyol the

    newly appointed CEO of the TANAP

    project company announced that

    construction would start in April 2015,however he subsequently conceded that

    while it is now decided that SOCAR will

    take a 58% stake it is still unclear when

    the equity split will be concluded.

    Uncertainty

    Duzyol suggested that the cause of the

    delay lies with Turkeys state gas

    importer Botas conducting due diligence

    prior to confirming its stake, now

    expected to be 30%.

    A senior Botas official was also unableto suggest when the consortium structure

    may be concluded.

    At the same time Bud Fackrell, head of

    BP Turkey confirmed that BP too is

    conducting due diligence on its planned

    12% stake in TANAP and expressed his

    hope that the process can be completed

    this yearhardly an encouraging

    suggestion given the planned start date.

    Previously Fackrell and others associated

    with the TANAP project have stated that

    the final agreement on the consortiumneed not be taken before investment

    starts.

    Certainly, with the project planned to

    be financed solely by the equity partners,

    there is no need for the lengthy process

    of securing and finalising lines of credit.

    This has apparently allowed the TANAP

    project company to open a tender for the

    supply of pipe, with 18 companies pre-

    qualifying, to prepare an engineering,

    procurement and construction (EPC)

    tender to be held this month and to

    prepare documentation for a tender for

    supply of compressors, also expected to

    be issued soon.

    However, the prospect of due diligence

    by two members of a three party

    consortium continuing until just a few

    months before construction starts is far

    from normal, the more so given that

    project cost has yet to be finalised and is

    expected to substantially exceed the

    US$7 billion initial estimate.

    While SOCAR does have substantial

    financial muscle, it has yet to finalise theUS$3.5 billion financing required for its

    10 million tonne per year STAR refinery

    project following the sudden pull out

    earlier this year of the European Bank for

    Reconstruction and Development

    (EBRD) and the International Finance

    Corp. (IFC) which were to contribute

    US$500 million between them.

    If SOCAR is unable to secure finances

    for STAR, it may have to use its own

    resources, and look elsewhere for funds

    for TANAPa project which in theoryshould have had no trouble in securing

    funds from international development

    lenders even before the Russian

    occupation of Crimea and the sudden

    urgent need to realise the long-mooted

    Southern Gas Corridor.

    Egypt will receive additional supplies of

    crude oil from Kuwait, along with an

    increase in petroleum products.

    The two countries reached a deal last

    week whereby Kuwait Petroleum Corp.

    (KPC) will boost its crude deliveries to

    Egypt by 20,000 barrels per day to

    85,000 bpd, from the current rate of

    65,000 bpd.

    The Kuwaiti news agency, KUNA,

    reported that the new contracts would run

    for three years.

    The deal also calls for an increase in

    diesel and jet fuel deliveries to 1.5

    million tonnes per year, up from 860,000

    tonnes per year.

    Egypt is facing a serious energy crunch

    as demand for petroleum products and

    natural gas moves beyond the

    governments ability to keep the market

    supplied.

    COMMENTARY

    POLICY

    Egypt strikes energy securitydeal with Kuwait

  • 8/11/2019 Downstream Monitor - MEA Week 15

    9/22

  • 8/11/2019 Downstream Monitor - MEA Week 15

    10/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 10

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    Zirku handles output from ZADCOs

    three fieldsUpper Zakum, thought to

    be the worlds fourth largest, and the

    smaller Umm al-Dalkh and Satah fields.

    In early April 2013, a team of South

    Koreas Daewoo Shipbuilding & Marine

    Engineering and UK/UAE joint venture

    Petrofac Emirates was awarded the

    US$3.7 billion EPC contract for the

    onshore portion of the full-field

    expansion project at Upper Zakum,

    covering an oil processing plant and

    associated facilities, aimed at boosting

    production from 550,000 bpd to 750,000

    bpd by 2017: the US$800 million

    offshore elements engineering

    procurement and construction (EPC)

    contract was awarded to a consortium ofthe local National Petroleum

    Construction Co. (NPCC) and Frances

    Technip in July 2012.

    The Upper Zakum expansion forms an

    important part of Abu Dhabis broader

    drive to increase crude capacity to 3.8

    million bpd by 2017/18, with the

    increment mainly being delivered from

    offshore.

    ZADCO is considering undertaking a

    further expansion to produce 1 million

    bpd: no timeframe has yet been set, but

    some certainty around the concession

    agreement was reached in January with

    the extension of the contract with Japans

    Inpex, which holds a 12% stake, to 2041

    in line with those of partners Abu

    Dhabi National Oil Co. (ADNOC) with

    60% and the US ExxonMobil with 28%.

    Fellow ADNOC-owned offshore

    operator Abu Dhabi Marine Operating

    Co. (ADMA-OPCO) is also undertaking

    expansion at its major fields to raise

    output by 300,000 bpd to 1 million bpd:

    in 2013, NPCC won the main EPC

    contract for the development of the Umm

    al-Lulu asset while South Koreas

    Hyundai Engineering & Construction

    was selected for the largest package on

    the Satah al-Razboot field.Bids have been under evaluation since

    January for the full-field development of

    the companys Nasr field.

    South Africas petrochemicals giant

    Sasol has reported a 25% hike in its first

    quarter headline earnings, helped by a

    weaker rand currency and higher

    chemical prices.

    In a statement the company said: This

    achievement was on the back of a strong

    operational performance from our global

    businesses, coupled with a 19% weaker

    average rand/US dollar exchange and

    improved chemical prices.

    However, some analysts in South

    Africa are beginning to question whether

    with the successful commissioning of itsUS$29 billion gas-to-liquid (GTL)

    project at Lake Charles, Louisiana, the

    company is still committed to operations

    in South Africa.

    The US project uses unique technology

    to convert ethylene into higher value

    chemical products to be used in the

    manufacture of consumer products such

    as food packaging.

    It is currently in start-up and the first

    products have already been produced.

    The plant is expected to be fully

    operational by mid-2014.

    However, critics say that Sasol, which

    started in 1955 with taxpayers cash, has

    gambled hugely on this single project in

    Louisiana.

    Sasol was the target of a possible

    windfall tax in 2006.

    However, it managed to negotiate

    away that tax, partly by promising to

    build a coal-to-liquid (CTL) plant

    Mafuthawhich was to be aimed at the

    local fuel market.

    But Mafutha has failed to materialise

    and in its stead Sasol built its GTL

    facility at Lake Charles.

    Local news agency Business Day

    reported on April 6: The argument that

    Sasol is quietly lightening its exposure to

    South Africa is bolstered by its failure to

    capitalise on Mozambican gas fields, as

    well as its stated desire to become lessreliant on coalwith its dirty image

    and impending carbon tax implications.

    In response, Sasol said last week that it

    is adamant that it has no plans to cut its

    ties to South Africa. Spokesman Alex

    Anderson said that 66% of Sasols total

    assets will reside in sub-Saharan Africa

    (SSA) and its primary listing will remain

    on the Johannesburg Stock Exchange

    (JSE).

    COMPANIES

    Sasol earnings rise by 26%, whiledoubts are raised about SA future

  • 8/11/2019 Downstream Monitor - MEA Week 15

    11/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 11

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    Irans 390,000 barrel per day Abadan

    Refinery is set to produce Euro IV gradegasoline in the coming Iranian calendar

    year.

    In an interview with the Shana news

    agency Saeed Mahjoubi, a senior official

    with the National Iranian Oil Refining

    and Distribution Co. (NIORDC), said

    that a number of old units will now be

    deactivated at the site, with new units to

    come online in their place.

    Abadan, which meets 25% of Irans

    demand for gasoline and fuel oil, was

    closed for maintenance between March10 and April 10, a move that is estimated

    to have cut the countrys fuel exports by

    around 50%.

    Currently, Abadan produces Euro II

    standard fuel, which is well below the

    Euro V grade commonly used by

    consumers in the European Union (EU).Increasingly, this has become a key

    market for Middle Eastern refiners keen

    to diversify their economies away from a

    reliance on crude exports.

    While the upgrade to Euro IV still falls

    short of EU requirements, it does raise

    the possibility of a future renovation in

    order to supply European customers,

    should Tehran have its exports sanctions

    fully lifted later this year.The Abadan refinery was completed in

    1912 and is the oldest refinery in the

    Middle East, despite having to be rebuilt

    after being destroyed during the 1980-

    1988 Iran-Iraq war.

    In May 2011, an explosion occurred

    during a visit to Abadan by then

    president Mahmoud Ahmadinejad for the

    inauguration of a new gasoline

    production unit. Reports said that four

    people were killed and around 20 others

    were injured.In September that year, a fire also

    injured four people. On March 30, Shana

    said that another fire had occurred at the

    facility, although no injuries or

    substantial damage were reported.

    The Egyptian Refining Co. (ERC) is to

    begin construction this month on its

    long-delayed refinery project, which is

    designed to alleviate some of Egypts

    growing domestic demand for petroleum

    products and thus reduce Egypts

    mounting costs of importing fuels.

    Fuel shortages in Egypt have served to

    exacerbate the countrys social and

    political problems.

    The US$3.7 billion project will be built

    at the existing Mostorod PetroleumComplex (MPC) site, which is operated

    by the Cairo Oil Refinery Co. (CORC)

    and located 20 km north of the capital.

    The 145,000 barrel per day CORC

    refinery, which came on-stream in 1973,

    produces light and middle distillates and

    LPG and it will supply the ERC plant

    with 67% of its production for further

    processing. ERC was formed in 2007

    with a plan to upgrade the CORC

    refinery and produce lighter products and

    more diesel. The new facility includes an

    80,000 bpd vacuum distillation unit and a

    40,000 bpd hydrocracker, a 25,000 bpd

    delayed coker, a 23,000 bpd naphtha

    hydrotreater and a 32,000 bpd distillate

    hydrotreater.

    The project is expected to come into

    operation in 2017. The plant will produce

    Euro V grade diesel, International Air

    Transport Association (IATA)

    specification jet fuel, fuel oil, LPG,

    kerosene, reformate, naphtha, sulphur

    and coke, and its entire production will

    be sold to key shareholder the Egyptian

    General Petroleum Co. (EGPC) at

    international prices under a 25-year

    contract.

    The sulphur and coke will be marketed

    to industrial users and suppliers. EGPC

    has provided US$1.1 billion in equity for

    the project and US$2.6 billion in

    financing has been arranged by a numberof international institutions. Project

    consultants include Worley Parsons,

    KBC and Societe Generale. Egypts

    largest refinery is the 146,300 bpd El-

    Nasr plant, originally built in 1913 and

    upgraded during 1967-74. In 2000, the

    Ministry of Petroleum signed an

    agreement with China to build a new

    US$2 billion at the El-Nasr site with a

    capacity up to 150,000 bpd, but work has

    yet to begin.

    REFINING

    Abadan to produce Euro IV fuel

    Construction to begin

    on Egyptian refinery

  • 8/11/2019 Downstream Monitor - MEA Week 15

    12/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 12

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    The Basra Gas Co. (BGC) Train 1

    project at North Rumaila in southern Iraq

    moved a step further forward with the

    announcement that Technip, in

    partnership with China HuanQiu

    Contracting & Engineering Corp.

    (HQCEC), has been awarded the front-

    end engineering design (FEED) contract.

    BGC is a joint venture between Iraqs

    South Gas Co. (SOC) with a 51% share,

    Shell with 44%, and Mitsubishi with 5%.

    The project is the first of the new

    greenfield associated gas processing

    facilities that it is hoped will significantly

    minimise gas flaring in Iraq and make

    more energy resources available for

    power and domestic use. The natural gas

    liquid (NGL) train will have a nominal

    feed gas capacity of 530 million cubic

    feet (15 million cubic metres) per day.

    The standalone facilities will produce

    LPG as well as NGLs and condensate for

    domestic markets. It is scheduled to be

    completed by the end of 2014.

    Vaseem Khan, President of Technip

    Middle East said: This award reflects

    Technips strengthened position in the

    Middle East market We are proud to

    bring our specific technological edge and

    licensed innovative solutions to the

    downstream industry.

    The project began operations in May

    2013, marking a milestone in the

    countrys fragile post-war recovery.

    BGC is one of the largest gas-

    capturing projects in the world and once

    complete, will gather and process

    associated gas from three major oilfields

    in southern Iraq. The gas captured by

    BGC from Rumaila, the first stage of

    West Qurna and Zubair will be used to

    generate electricity in Iraq. But the

    project will also have the option to build

    a plant to produce LNG for export once

    domestic energy needs are met.

    Total planned investment is US$13

    billion, with the possibility of an

    additional US$4 billion for an LNG

    export plant, according to the

    International Energy Agency (IEA).

    Shell said that BGC would rehabilitate

    and upgrade existing facilities as well as

    build new assets which would increase

    production capacity from the current 400

    million cubic feet (11 million cubic

    metres) per day to 2 billion cubic feet (57

    million cubic metres).

    The Oman Gas Co. (OGC) has signed a

    memorandum of understanding (MoU)

    with the Salalah Free Zone (SFZ) and the

    Port of Salalah for the construction of a

    LPG processing plant that will be located

    in the SFZ with export facilities at the

    port.

    The LPG will enable the high recovery

    of propane, butane and condensates from

    the natural gas that flows through OGCs

    southern gas grid. The estimated cost of

    the project was not disclosed.OGC, which is wholly owned by the

    Oman Oil Co. (OOC), is Omans natural

    gas transport utility and supplies gas to

    domestic power generation stations and

    water desalination plants, as well as

    fertilizer and methanol to petrochemical,

    steel and cement plants, and refineries.

    The plan calls for an LPG extraction

    plant to be located in the free zone. LPG

    and condensate storage facilities and a

    jetty will be constructed at Salalah port.

    The scope of work includes construction

    of new gas and liquids pipelines in the

    Salalah region.

    The plant, which will provide a supply

    of domestic gas for the region, is due to

    come into operation in 2018.

    The plant is to be state-of-the-art and

    will adhere strictly to health, safety and

    environment standards, officials said

    during the MoU signing ceremony. The

    project also will create a number of jobs

    for local residents.

    The CEO of the Salalah Free Zone,

    Awadh Salim Al Shanfari said the

    agreement to construct this vital project

    in the Salalah region comes from the

    strategic goal of exploiting the naturalresources to create projects which will

    add value and broaden the horizons for

    other industries that are located

    downstream of the LPG value chain, the

    Oman Tribune reported.

    He said the project would also create

    opportunities for small and medium

    enterprises (SMEs).

    FUELS

    Basra NGL advances as

    Technip gets FEED contract

    OGC plans LPG plant in Salalah

  • 8/11/2019 Downstream Monitor - MEA Week 15

    13/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 13

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    The construction of South Africas New

    Multi-Product Pipeline (NMPP) is now

    over four years behind schedule and is

    not likely to be completed until April

    2015.

    The string of setbacks faced by the

    project, operated by Transnet Pipelines,

    has already led to cost escalations which

    are currently being investigated by the

    South African national energy regulator

    (NERSA) and are sure to lead to future

    fuel tariff increases. According to

    NERSA, the investigation will only be

    completed in 2015.

    So far, the company has already

    admitted to underestimating the

    complexity of the project, justifying the

    delays with the negotiation of the rights

    of passage with about 900 landowners,

    which it said was extremely time-

    consuming. In an interview to the South

    African Black Business Quarterly

    (BBQ), CEO Sharla Pillay said: The

    lessonwe understated the magnitude

    and complexity of the NMPP project.

    There was an over-reliance on external

    service providers for expertise and skills

    which were lacking in-house.

    Transnets General Manager Lennie

    Moodley has also acknowledged the

    challenges ahead, but is confident that

    the company has entered a new era and

    has the opportunity to unblock supply

    chain inefficiencies, broadening its focus

    into Africa. There are opportunities for

    securing maintenance and strategic

    planning contracts while working with

    others in the logistics industry to more

    effectively delivery services to

    customers, he told BBQ.

    Meanwhile, NERSA is concerned

    whether the pipeline will represent value

    for money.

    According to Rod Crompton,

    responsible for petroleum pipelines at

    NERSA, the regulator is concerned

    whether the usual approachwhereby

    regulators can exclude the portion of an

    asset not prudently acquired from a tariff

    application, so that users pay a tariff

    consistent with the costshould be

    applied to the pipeline project, as it

    would severely impact Transnets

    investment programme.

    The 55-km pipeline from Durban to

    Johannesburg will have a 70-year design

    life and a capacity to transport 93-grade

    and 95-grade unleaded petrol, low-

    sulphur diesel, ultra-low sulphur diesel

    and jet fuel.

    Crude oil exports from one of the four

    terminals that have been under the

    control of a rebel militia group in eastern

    Libya are expected to resume this week.

    Media reports say Sarir crude will be

    loaded at Libyas eastern-most terminal,

    Marsa al-Harigah, near Tobruk.

    The terminal, with a capacity to ship

    110,000 barrels per day, and the terminal

    at Zueitina were turned over to Libyan

    army control late last week following an

    agreement between the Libyan

    government and the rebels. This should

    lead to the four terminals being returned

    to government control.

    The rebels had formed themselves into

    the Cyrenaica Political Bureau and

    demanded that eastern Libya be given

    more autonomy and more control over

    oil revenues. Originally organised to

    protect the countrys energy facilities, the

    rebel group threatened to establish a new

    state if the government in Tripoli did not

    make efforts to put the country on a

    better political course. Events came to a

    head in March when the rebels attempted

    to export crude using a rogue tanker that

    managed to evade Libyan authorities.

    However, this was later seized by the US

    Navy and returned to one of the Libyan

    ports under government control.

    Libyas state-owned National Oil

    Corp. (NOC) last week lifted the force

    majeure declaration imposed at Marsa al-

    Harigah after it was seized by rebels in

    mid-2013.

    It is not clear when exports might

    resume from Zueitina, which has a

    70,000 bpd capacity, or when the export

    terminals of Es Sider and Ras Lanuf,

    with a combined capacity of 560,000 bpd

    will be turned over to government

    control.

    The blockade of the terminals, which

    has lasted more than nine months, has

    resulted in serious financial losses for

    Tripoli, which has had to revert to

    dipping into its financial reserves in

    order to keep the government working.

    Revenue losses are estimated to be

    US$14 billion or more.

    PIPELINES

    Transnet suffers yet

    another setback

    TERMINALS & SHIPPING

    Libya crude oil exports setto resume this week

  • 8/11/2019 Downstream Monitor - MEA Week 15

    14/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 14

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    Production and exports in recent

    months is reported to have fallen to

    around 200,000 bpd and less.

    Prior to the blockade of terminals and

    onshore oil fields and infrastructure,

    Libya was producing 1.2 million bpd and

    exporting most of it.

    Premier resignation

    While there are signs of progress from

    Libyas east, trouble continues at the

    heart of government. Libyan Prime

    Minister Abdullah al-Thinni, who

    replaced Ali Zeidan, announced plans to

    resign last week after an attack on his

    family.

    A militia is believed to have attacked

    al-Thinnis family, although they were

    not harmed. The premier condemned the

    cowardly attack, during which his car

    was reportedly stolen.

    Once the General National Congress

    (GNC) has chosen a replacement, al-

    Thinni will step down, he said.

    More than a decade after the project was

    first mooted, state-owned downstreamoperator Kuwait National Petroleum Co.

    (KNPC) in mid-April finally tendered

    two of the five main engineering,

    procurement and construction (EPC)

    contracts covering storage and marine

    works on its US$14 billion new refinery

    project (NRP), a 615,000 barrel per day

    facility to be built at Al-Zour in the south

    of the country.

    The launch of the bidding process

    follows the award in February of the

    main EPC contracts on KNPCs other

    flagship scheme, the Clean Fuels Project

    (CFP) to expand and upgrade existing

    refining capacity at Mina Abdullah and

    Mina al-Ahmadi.

    Bids for both NRP contracts are due on

    September 14. Four prequalifiers are

    looking at the tank farm packagethe

    UKs Petrofac with South Koreas

    Hyundai Heavy Industries (HHI), Italys

    Saipem with Indias Essar and separately

    Daelim Industrial and Daewoo

    Engineering & Construction, both of

    South Korea.A similarly Korean-dominated shortlist

    of five prospective bidders are eligible to

    bid for the marine works package

    Petrofac with HHI, Hyundai Engineering

    & Construction with Saipem and South

    Koreas SK Engineering & Construction,

    Daewoo and the US McDermott.

    Several interested companies have

    reached this stage and beyond before.

    When the contracts were first awarded in

    2008 before being cancelled in light oftrenchant criticisms of both the bidding

    process and the projects economics by

    the always-suspicious National Assembly

    (parliament), Daewoo won the tank

    farms job and HHI was selected for the

    marine works.

    The three remaining packages, on

    which no details of prequalifiers has been

    released more than a year after the

    submission of applications, cover the

    atmospheric residue desulphurisation

    units, hydrogen compression and

    recovery units and offsites and utilities

    won in 2008 respectively by Japans JGC

    Corp. with South Koreas GS

    Engineering & Construction, SK and the

    US Fluor.

    According to the ambitious schedule

    set out by KNPC late last year,so far,

    to general surprise, adhered tothe

    bidding and awards process for all five

    contracts will be completed by the end of

    the year.

    Other aspects of the NRP have been

    put in place recently, likewiseengendering hope of timely progress: in

    early March, Van Oord of the

    Netherlands won the 186.4 million dinar(US$663.3 million) site preparation

    contract for dredging and reclamation of

    the designated 16.2 million square metre

    plot, unusually winning against

    competition from a significantly lower

    bid by fellow Dutch firm Boskalis

    Westminster.

    Meanwhile KNPCs upstream

    counterpart Kuwait Oil Co. (KOC)

    issued a tender the same month for

    construction of a 350-km pipeline to

    supply the new refinery with crude

    feedstock from its Lower Fars heavy oil

    project, with bids due on May 6.

    The refinerys output will primarily

    supply low-sulphur fuel oil to the

    countrys existing and planned power

    plants, as the government works to

    eliminate highly controversialin light

    of the countrys energy riches chronic

    summer power shortages. Completion is

    due in 2019.

    Future integration with a

    petrochemicals complex is also under

    discussion between KNPC and sister firmPetrochemical Industries Co. (PIC),

    which under initial proposals would see

    the refinery supply naphtha and LPG to a

    mixed-feedstock cracker with

    commodities and derivatives units, with

    PIC providing hydrogen and pygas in

    return. Fluor and Foster Wheeler, also of

    the US, are carrying out studies on the

    estimated US$7-10 billion project.

    TERMINALS & SHIPPING

    TENDERS

    KNPC floats new refinery tenders

  • 8/11/2019 Downstream Monitor - MEA Week 15

    15/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 15

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    The following news items are sourced

    from local and international news

    sources. NewsBase is not responsible for

    the contents of the stories and gives no

    warranty for their factual accuracy.

    POLICY

    Israeli gas holdspromise of betterties with neighboursIsraels drive to export its new-found

    natural gas could help to rebuild strained

    ties with old regional allies Egypt and

    Turkey, but could deprive Europe of a

    precious alternative to Russian gas.

    Israel has in recent months alreadysigned energy deals with Jordan and the

    Palestinian Authority, though relations

    with the Palestinians are at a low ebb,

    and now needs to expand its export

    horizons to cash in on its huge energy

    discoveries.

    If all goes well, the latest developments

    could see first pipelines being laid

    between Israel and Turkey as soon as

    2015, and gas cooperation between Israel

    and Egypt is also emerging, which would

    allow export access to Asias majormarkets.

    A growing population and soaring

    demand have left Egypts own liquefied

    natural gas export (LNG) plants in need

    of new supply, as domestic shortages eat

    into seaborne exports through the Suez

    Canal to the worlds most lucrative

    market in Asia.

    This has put Israels previous plans to

    pump its gas reserves into a future export

    plant in Cyprus on the back burner,

    dealing a major blow to the indebted

    Mediterranean islands ambitions to

    become a global player in the gas market.

    A Cypriot LNG export plant was due to

    deliver at least 5 million tonnes a year to

    Europe and Asia, allowing Europe to

    reduce its growing dependency on

    Russia, which has become of particular

    concern since the crisis in Ukraine cast a

    Cold War chill over East-West relations.

    Israels new plans throw Cypriot

    developments into doubt as investors

    would require more gas than Cyprus has

    on offer to make returns on multibillion-

    dollar investments.

    If Israel has really ditched Cyprus as a

    partner to develop the regions gas

    resources, then we (Cyprus) really do

    have to find quite a lot more gas if we

    want to become a viable exporter, and

    that would inevitably throw our plans

    back by several years, said one source

    involved in developing Cypruss gas

    reserves.

    The possibility of sanctions on Russias

    energy sector in response to Moscows

    annexation of Crimea and troop build-up

    along Ukraines eastern border have

    underscored Europes acute need to

    diversify its oil and gas sources.

    Israel plans to export gas by pipeline and

    through several floating LNG productionplants, which cool gas to liquid form, so

    they can ship it to the worlds largest

    markets.

    At stake for Israel is a US$150 billion tax

    take should export deals be agreed by a

    consortium operating its gasfields. Its

    strategic re-alignment effectively places

    a tantalisingly close new gas province

    out of Europes reach.

    Ultimately Egypt and Turkey need

    energy, and the fact that we have it is

    creating a regional convergence ofinterests, an Israeli diplomatic source

    told Reuters.

    REUTERS, Apri l 14, 2014

    REFINING

    SK firms wincombined US$7.2bnin Kuwait ordersFive South Korean companies have won

    a combined US$7.2 billion in orders

    from Kuwait National Petroleum

    Company to expand capacity and

    improve environmental standards at two

    oil refineries.

    The contracts, which stem from US$12

    billion in bids approved in February for

    the state-run companys Clean Fuels

    Project, highlight efforts by South

    Korean builders to shore up margins via

    joint bids with other local or foreign

    firms for major overseas construction

    projects. Korean companies are

    increasingly forming consortiums with

    established overseas companies and that

    is helping them to win better value

    contracts, said Yun Sok-mo, an analyst at

    Samsung Securities.

    Overseas plant orders won by South

    Korean builders during the first quarter

    rose by 42.1 percent from a year ago,

    according to the Ministry of Trade,

    Industry and Energy in a report earlier

    this month.

    The ministry said prospects for further

    growth in overseas orders looked good

    given expectations for continued global

    economic recovery and growing demand

    for energy-related work.

    Daewoo Engineering & Construction Co

    Ltd said in statement on Monday that it

    won an order for the Mina Abdullahrefinery in Kuwait as part of a joint

    venture with Hyundai Heavy Industries

    Co Ltd and Fluor Corp.

    The order is worth US$1.13 billion each

    for the three companies, according to

    Daewoo.

    Samsung Engineering Co Ltd, in a

    regulatory filing on Monday, said it got a

    separate US$1.62 billion order for the

    Mina Abdullah refinery as part of a joint

    venture with Petrofac Ltd and Chicago

    Bridge & Iron Company NVGS Engineering & Construction Corp

    and unlisted SK Engineering &

    Construction Co Ltd also said they got an

    order for refinery work in Kuwait as part

    of a joint venture with Japans JGC Corp.

    The third order, for the Mina Al-Ahmadi

    refinery, is worth around US$1.66 billion

    for each of the three companies,

    according to GS Engineering and SK

    Engineering.

    REUTERS, Apri l 14, 2014

    Imports, notrefineries, to meetAfricas fuel needsAfricas dependency on fuel imports is

    likely to grow as its refining projects

    struggle to get off the ground, a Vitol

    director told a Reuters Africa Summit.

    Dozens of new refining projects have

    been announced in Africa, but they are

    unlikely to be built unless they are either

    gigantic or with guaranteed crude supply

    in a landlocked location.

    NEWS IN BRIEF

  • 8/11/2019 Downstream Monitor - MEA Week 15

    16/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 16

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    Micro refineries in waterborne locations

    are not a viable way to get a return on

    capital. You have to go big, and today

    big means a 300,000 to 500,000 barrel

    per day complex refinery and US$5-$15

    billion of capital, Chris Bake, director

    of origination and investments, told

    Reuters in a telephone interview. To

    deploy that is challenging, he added.

    Bake added that he expected one large

    refinery to be built in West Africa but

    that it could take five to seven years,

    while new plants in east Africa were less

    certain given strong competition from the

    Middle East.

    Vitol, the worlds top oil trader with over

    US$300 billion in annual revenues, seeks

    to meet African demand in competitionwith other traders such as Glencore and

    Trafigura and with large Asian refiners.

    Vitol estimates that Africas fuel demand

    amounts to 3.71 million barrels per day

    in 2014, worth about US$440 million a

    day, based on ICE gasoil futures prices.

    That is close to a 3 percent increase from

    the 2013 estimate.

    Bake said the most exciting market in

    Africa was gasoil, with growth expected

    to be in the high single digits as power

    demand booms. Demand for liquefiedpetroleum gas will also rise quickly

    across North Africa and Nigeria as

    consumers spend more and move to

    cities, he added.

    A small number of refining projects in

    landlocked locations could succeed,

    possibly in Uganda, Chad or South

    Sudan, Bake added, as they are sheltered

    from competing supplies of giant Asian

    refineries. Vitol is leading a consortium

    to bid for a US$2.5 billion refinery in

    Uganda. The winner is expected to be

    announced in July. Vitol will also seek to

    supply African countries with gas for

    power production and is already working

    to develop gas fields offshore Ghana to

    supply its local market. Africa is a

    power-hungry continent, and we are

    looking at domestic gas opportunities,

    said Chris Joly, director of exploration

    and production, in the same interview.

    He added that the firm, which pumps

    around 10,000 barrels per day, would

    look for exploration and production

    opportunities that complement its

    existing assets and trading contracts.

    Vitol has invested in an African chain of

    petrol service stations, Vivo Energy, in

    partnership with Shell and Helios

    Investments Partners. Vitol also has an

    oil product storage terminal in Mombasa,

    Kenya.

    Were not doing upstream for the sake

    of doing upstream. Its more about

    integration with the wider Vitol

    business, Joly said.

    Unlike traders Glencore and Mercuria,

    Vitol has held off bidding for Shells

    assets in Nigeria, Africas top oil

    producer, citing high entry costs and stiff

    competition from local players, who have

    access to low borrowing rates.

    But Joly said Vitol would keep looking atopportunities.

    Nigerias too important to ignore, so we

    are taking a cautious and long-term view.

    There will be opportunities down the

    road. We are talking and looking, he

    said. Vitol, a regular buyer of South

    Sudans Dar grade crude, is also in talks

    with the government there on oil

    infrastructure projects, Bake said,

    without giving details.

    Like others, weve talked to the

    government about ways to help improvethe infrastructure to give them

    incremental security of supply. Were

    still working on options with them.

    REUTERS, Apri l 10, 2014

    Ethiopian marketersays Africa needs torefine its oilEthiopias leading private oil marketer

    plans to expand into neighbouring east

    African economies and is interested in

    part financing a refinery aftercommercial discoveries in the region.

    Tadesse Tilahun, CEO of National Oil

    Ethiopia, said untapped crude deposits in

    Kenya and Uganda handed governments

    and investors the opportunity to construct

    a refinery able to compete with cheap

    imports from India, the Gulf and beyond.

    Doing so would help African countries

    extract more value from their resources

    and cut their import bills, Tadesse said.

    Africas demand for refined products is

    growing hugely because of its economic

    growth. The crude findings are also

    increasing. That is the opportunity,

    Tadesse said in Addis Ababa as part of

    the Reuters Africa Summit.

    We want to (build) a refinery. We have

    already discussed this in principle with

    our shareholders, who are very much

    committed.

    National Oils (NOC) shareholders

    include Saudi billionaire Mohammed

    Hussein Al Amoudi, whose investment

    portfolio in construction, gold, hotels and

    energy has helped amass an estimated

    fortune of over US$15 billion, according

    to Forbes.

    Tadesse said other private and public

    investors would need to come on board.

    Eastern Uganda has become the latestfrontier in the global hydrocarbon hunt

    after gas finds off Tanzania and

    Mozambique and oil discoveries in

    Uganda and Kenya.

    Even so, Sub-Saharan Africa faces

    headwinds supplying more of its own

    refined petroleum products. Regional

    cooperation and funding for oil-related

    infrastructure are proving slow, while

    foreign oil refiners and traders are

    flooding the US$80 billion market with

    imports. Existing pipelines also tended torun to the coast, Tadesse said, either for

    the export of crude or the import of

    refined products from small-scale

    refineries found near ports.

    That has to change, Tadesse said.

    Refineries are now needed inland so

    that Africa can supply itself.

    Tadesse acknowledged the price tag was

    problematic for many African countries.

    Oil production in Uganda has been

    delayed in part due to a row between the

    government and investors over the size -

    and thus cost - of a refinery in the

    country.

    It would be in our own interest, for all

    countries in this area, to have a common

    refinery, a joint facility, where we can

    take our own product, Tadesse said.

    Kenya plans - but has made little

    progress towards - a new US$2.8 billion

    refinery on its northern coast. Industry

    experts say Ugandan and Kenyan oil

    exports could reach 500,000 barrels per

    dayoil Tadesse would rather see stay

    in the region.

    NEWS IN BRIEF

  • 8/11/2019 Downstream Monitor - MEA Week 15

    17/22

  • 8/11/2019 Downstream Monitor - MEA Week 15

    18/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 18

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    Around the world, oil & gas, refining and

    petrochemical companies are becoming

    increasingly concerned by how the

    development of unconventional resources

    is changing the energy landscape. Our

    business is facing new and

    unprecedented challenges globally and

    from all directions, warned Al-Mady.

    Cheap and abundant resources have

    been our primary competitive advantage.

    Within five years, what used to be a

    phenomenon known only to specialists,

    what is now called drilling technologies,

    brought an avalanche of unforeseen

    reserves.

    With forecasts predicting that the GCC

    will enter into a new growth phase

    characterised by massive capacityexpansions combined with significant

    product diversification, there is an

    imminent need to invest in the means that

    ensure such projects remain competitive,

    even in the face of the shale revolution.

    That is of course, not to say that the GCC

    has failed to innovate. With a likely gas

    shortage approaching as early as 2015,

    the regions petrochemicals companies

    have certainly seized the opportunity to

    innovate, albeit because of challenging

    circumstances.As much as 34 million tons of additional

    petrochemical capacity may come online

    by 2018, but constraints in the supply of

    ethane throughout the GCC have

    encouraged companies to shift to the

    utilisation of heavier feed-stocks such as

    propane, butane and naphtha.

    By 2020, approximately 35% of the

    incremental feedstock for petrochemical

    production will be derived from refining

    operations. Within refinery streams,

    naphtha will account for the largest

    feedstock demand. Such a move has

    come at a higher cost, but has also

    produced a more balanced base

    petrochemicals products mix. In turn this

    has allowed for the production of new

    sets of secondary and tertiary products.

    The successful diversification of the

    regions petrochemical product slate has

    been heralded as one of the major

    triumphs of innovation in the region. But

    other factors, such as coals-to-chemicals

    technology in China, have also meant

    that the comparative cost advantages

    once enjoyed by the Middle East are

    fading in Eastern markets as well.

    ARAB IAN OIL AND GAS, Apri l15, 2014

    PIPELINES

    Iraq hopes tocomplete pipeline toraise exports in 2014Iraqi Oil Minister Abdul Kareem Luaibi

    said on Wednesday his country hoped to

    complete construction of a 200 km (124

    miles)oil pipeline to raise exports toTurkey to more than 1 million barrels per

    day (bpd) this year.

    We are building a pipeline in Iraq,

    Luaibi was speaking to Reuters on the

    sidelines of an oil and gas conference in

    the Turkish capital Ankara. I believe the

    daily oil flow will exceed one million

    barrels a day when that line is completed.

    I hope it happens this year.

    REUTERS, Apri l 9, 2014

    TERMINALS &SHIPPING

    Mombasa oilterminal relocationKenyas government said Saturday it has

    begun the process of relocating

    Mombasa-based Kipevu oil terminal to

    create additional capacity at a cost of

    U.S. $120 million dollars. Kenya Ports

    Authority chairman Danson Mungatana

    said the new terminal, expected to be

    completed in 2018 and will reduce fuel

    pump prices in the East African nation.

    Preliminary design of the new facility

    has been undertaken and the relocationagreed upon by all stake holders. The

    detailed design will cost 1.7 million

    dollars while construction of the facility

    will cost about 120 million dollars,said

    Mungatana.

    The KPA chairman who was speaking

    during the official launch of the Kenya

    Oil and Gas Association in Nairobi said

    the new terminal will have capacity for

    two large vessels each carrying 100,000

    tons of crude oil. Kenyan oil firms have

    previously cited the high cost of refinedpetroleum products to losses incurred as

    a result of refining at the Kenya

    Petroleum Refineries Limited (KPRL)

    facility in Kipevu. Analysts say this will

    enable the refinery to play a key role in

    reducing the price of fuel in the East

    African country to the benefit of

    consumers affected by the high cost of

    living.

    CW, Ap ril 6, 2014

    NEWS IN BRIEF

  • 8/11/2019 Downstream Monitor - MEA Week 15

    19/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 19

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    CONFERENCES

  • 8/11/2019 Downstream Monitor - MEA Week 15

    20/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 20

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    CONFERENCES

  • 8/11/2019 Downstream Monitor - MEA Week 15

    21/22

    Downstream Monitor MEA 16 April 2014, Week 15 page 21

    Copyright 2014 NewsBase Ltd.

    www.newsbase.com Edited by Ian Simm

    All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All

    reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents

    SPECIAL REPORT

  • 8/11/2019 Downstream Monitor - MEA Week 15

    22/22