Upload
aamir-sayeed
View
214
Download
0
Embed Size (px)
Citation preview
8/11/2019 Downstream Monitor - MEA Week 15
1/22
For analysis and commentary on these and other stories, plus the latest downstream developments, see inside
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
16 April 2014
Week 15
Issue 152
News Analysis
Intelligence
Published by
NewsBase
COMMENTARY 2
Iran ratchets up exports rhetoric 2
Oman: action on graft releases
contracting energy 4
Infrastructure works on
the way for Kenya 6
Russian roulette points the
barrel at TANAP 7
POLICY 8
Egypt strikes energy security
deal with Kuwait 8
Zambia seeks financiers
to fund oil imports 9
COMPANIES 9
ABB takes Zirku power contract 9
Sasol earnings rise by 26%, whiledoubts are raised about SA future 10
REFINING 11
Abadan to produce Euro IV fuel 11
Construction to begin on
Egyptian refinery 11
FUELS 12
Basra NGL advances as Technip gets
FEED contract 12
OGC plans LPG plant in Salalah 12
PIPELINES 13
Transnet suffers yet another setback 13
TERMINALS & SHIPPING 13
Libya crude oil exports set
to resume this week 13
TENDERS 14
KNPC floats new refinery tenders 14
NEWS IN BRIEF 15
CONFERENCES 19
SPECIAL REPORT 21
NEWS THIS WEEK
Iran: bullish sentimentIrans deputy petroleum minister this week toldNewsBasethat the country is keen to establisheffective and stable interaction on the globalmarket, and responded bullishly to questions aboutsanctions.
He said that Iran was exporting 1 million bpddespite IEA reports estimating it at 1.65 millionbpd. (Page 2)
Majedi outlined ambitious plans for Iran LNG tocome online during 2015. (Page 3)
Swift action reaps rewardsAs corruption arraignments swept through thesultanates leading state oil and gas companies inlate 2013, progress on major projects wasinevitably slowed. However, the dramaticculmination of the resulting criminal trials in thefirst three months of this year has precipitated asurge in contracting activity along the downstreamvalue chain, from refineries to speciality chemicals.
The conclusion of corruption trials has promptedkey petrochemicals project awards. (Page 4)
NewsBase
Downstream Monitor
MEA
8/11/2019 Downstream Monitor - MEA Week 15
2/22
Downstream Monitor MEA 16 April 2014, Week 15 page 2
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
Iran is slowly ratcheting up rhetoric
designed to smooth its return as a fully-
fledged player to global oil and gas
export markets, although experts believethat it could be three-five years before
this actually happens,NewsBasehas
learnt from comments made at an oil and
gas conference taking place in Dubai this
week.
Iran is projecting an increase in oil
production to 5 million barrels per day in
2018. Global crude oil supplies will rise
to 113 million bpd in 2014, Irans
deputy petroleum minister in charge of
international affairs, Ali Majedi, told the
Middle East Petroleum and GasConference, organised by Singapores
Conference Connection Group, in Dubai
April 14.
Iran is currently exporting around 1
million bpd to global markets, he said, to
countries thought to include Far Eastern
players like Japan, Korea, Taiwan and
India, and is trying to make its first
tentative steps into LNG production.
However, the International Energy
Agency (IEA) recently reported Iranian
exports at around 1.65 million bpd in
February and predicted similar levels
during Marchexceeding significantly
the 1 million bpd limit set out in the
agreement with the P5+1 signed on
November 24, 2014.
Majedi also told the conference that
Iran now had the worlds largest gas
reserves.
BPs 2013 Statistical Review of World
Energy said Irans proved natural gas
reserves stood at 33.6 trillion cubic
metres at the end of 2012, while the total
reserves of Russia, until recently seen as
the worlds largest owner of gas reserves,
were 32.9 tcm.
Coming to the table
Iran seeks an effective and stable
interaction with the worlds key oil and
gas players, including NOCs and IOCs,
and a diversified market. This would be
a win-win interaction, Majedi said. He
also called for a fair multilateral co-
operative strategy and a non-political
trade and investment framework.
I strongly believe that security of
energy supply should be respected by all
countries of the world. Iran is the worldsbiggest cumulative oil and gas [reserves]
holder, based in a geopolitical and
strategic location. It has a 1,800 km
shoreline on the Persian Gulf and the
Oman Sea. Iran holds the worlds fourth-
largest oil reserves at 11% [of the total].
He said profitability of projects would
be a hallmark of investor experience
when the green light was finally received
for international participation in Irans
projects market. However, he added that
Iran has not accepted [EU and US]
sanctions, as progress in a number of
domestic fields demonstrated.
He said that consumer loss was
caused by a political approach to the
oil and gas industry.
Commenting on the current European
situation in light of the Ukraine crisis, hesaid 33% of Europes gas was onshore,
while of the rest, 23% was provided by
Russia, 22% by Norway and 11% by
Algeria.
Qatar, Nigeria and Libya also played a
role in supplying European gas markets,
a lucrative area on which Iran has long-
term designs, given prices as high at
US$14-15 per million British thermal
units (mBtus) on the continent.
Gas export plansIran plans to increase its gas exports
through a comprehensive and coherent
programme Irans domestic market is
saturated, he said. Majedi added that
Iran LNG would come online in 2015,
without giving further details. It would
be possible to assign 100% to foreign
investors through Build Own Operate
[BOO] or Build Operate Transfer [BOT]
[frameworks], he said.
According to Iran LNGs website, EPC
contractors have been assigned to
packages for LNG storage tanks and
harbour and jetties, but process, utilities
and offsite areas, including loading
facilities, and liquefaction unit work
appears not yet to be awarded.
Iran, which on paper once had the
potential to match Qatar as a global
player, has remained frozen out of the
gas market because sanctions have led to
a failure to attract international EPC
players to install the complex technology
required to develop its assets.
COMMENTARY
Iran ratchets up exports rhetoric
Irans deputy petroleum minister this week toldNewsBasethat the country is keen toestablish effective and stable interaction on the global market, and responded bullishly
to questions about sanctions
y Peter Shaw-Smith
He said that Iran was exporting 1 million bpd despite IEA reports pegging it at 1.65 million bpdMajedi outlined ambitious plans for Iran LNG to come online during 2015He set out details of US$255 billion of investment plans, most of it aimed at the up- and downstream sectors
Majedi set out detai ls of
US$255 bil li on worth of
investment in Irans oil
and gas sectors due to take
place in 2011-15
8/11/2019 Downstream Monitor - MEA Week 15
3/22
Downstream Monitor MEA 16 April 2014, Week 15 page 3
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
On the question of Iranian pipeline
exports to the UAE, Majedi said: We
are ready to renegotiate and co-operate,
he said. Asked if in addition Iran might
supply gas for domestic use in Oman or
LNG export, he said: Maybe both.
Of course we will try to compete with
Russia, he said. There is competition in
the world. If Iran wants to export more
gas, each economy in the world can[choose from whom it wants to buy]. We
are trying to find countries where we can
get market [share]. We are trying to find
another customer for export of gas after
2015, he said, referring to an existing
deal with Pakistan.
Investment expectations
Majedi set out details of US$255 billion
worth of investment in Irans oil and gas
sectors due to take place in 2011-15. The
bulk of this will be in the upstream,midstream and downstream oil sector.
Arabian Oil and Gas reported March 4
that Iran had allocated US$255 billion
for its oil and gas industries, of which
US$155 billion is for the upstream
sector. By September 2013, US$42
billion of this money had already been
invested, leaving US$113 billion to be
invested before 2016, the publication
said.
Wind of changeTehran has publically mooted its
consideration of a new contractual model
for upstream projects, to allow for
alignment of government and contractor
take. Majedi said this would mean an
integrated operation for exploration,
development and production. We are
looking to maximise incentives for
investors in low and high-risk areas.
In December 2013, Irans Petroleum
Minister Bijan Namdar Zangeneh said at
an OPEC conference in Vienna thatmember countries would welcome
Irans return to world crude oil markets.
He said Iran was planning to bring its oil
production back to 4 million bpd when
international sanctions were lifted.
I noted in a statement that we [will]
return to the market in the shortest
possible time, and naturally, we expect
OPEC [member countries] to co-operate
with us. OPEC welcomed our return at
its highest level, which was exactly what
I expected them to do, he was quoted as
saying by the Ministry of Petroleums
monthly publication.
He added that the cartels historic
background also shows that when a
member exits the market [because of]
problems and makes a second coming,
member states have always shown their
maximum co-operation for that memberto take back its share.
Great expectations
On the sidelines of the conference, an
industry executive toldNewsBasethat
the interim agreement between Iran and
the P5+1 would come up for
reassessment on July 20, after
implementation of the November accord,
due to be in force for six months, was
delayed. He said it would be five years
at least before Iran would start to seemajor investment in its oil and gas
industry and a return to a pre-sanctions
situation. The source also quoted an
Iranian national as saying that Iran would
try to move towards oil exports at around
1.5-1.6 million bpd, with perhaps slight
increases going forward, but that it was
unlikely that a major change would come
about in the next 12 months. Everybody
going to Iran, investment coming up,
thats not on the cards [in the next three-
five years], he said.
As if to underline what he saw as the
merely temporary nature of the Irans
current predicament, Majedi sought to
lay stress on the long-term dynamics in
hydrocarbons markets, and the role that
players like his country could enjoy. He
said global natural gas use, some of it
unconventional, was predicted to rise by
65% in the next 25 years, with China,
India and the US the worlds main oil
consumers in 2040. About US$19
trillion in investments are required, he
saidlofty aims indeed.
COMMENTARY
8/11/2019 Downstream Monitor - MEA Week 15
4/22
Downstream Monitor MEA 16 April 2014, Week 15 page 4
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
In late February, Ahmed al-Wahaibi,former CEO of government-owned
Oman Oil Co. (OOC) was jailed for a
shocking 23 years for accepting bribes in
relation to the signature of a
petrochemicals project agreement in
2012. Joining him behind bars a few days
later was Adel al-Kindi, previously CEO
of Oman Oil Refineries & Petroleum
Industries Co. (ORPIC), convicted of
involvement in graft surrounding
contract awards for work on the Sohar
refinerythe firms largest asset and acrucial one for broader downstream
development schemes in the country.
With the highest echelons of the
governments two flagship downstream
hydrocarbons companies and their
private sector partners forced to turn their
eyes to the past, it is little wonder that the
focus was diverted from major future
projects on their slates, thus holding up
investments worth billions of dollars.
However, as these and other trials in an
unprecedentedly wide-ranging
crackdown on high-level corruption inpublic institutions reached their
conclusions during the first quarter of
2014, an apparent release of pent-up
energy has ensuedwith a flurry of vital
contracts on refining and petrochemicals
schemes moving to the tendering,
bidding or award stage.
Petchems push
Petrochemicals have become central to
Muscats strategy of economic
diversification, both sectoral andgeographicalwith plans to develop the
industry not only at the established
industrial nerve centre of Sohar but also
at the southern port of Salalah and, from
a greenfield base at Duqm, on the central
Al-Wusta coast.
Should all the planned projects come
to fruition, Oman would become a world-
scale producer alongside fellow Gulf
giants Qatar and Saudi Arabia, driven by
similar aims of reducing dependence on
raw hydrocarbon exports and translating
hydrocarbon wealth into job creation forrapidly increasing local populations.
Compared to these Gulf Co-operation
Council (GCC) oil and gas
heavyweights, the sultanate is a relative
minnow.
Oil production stands at around
920,000 barrels per day according to the
latest BP energy statistics, compared
with 2 million bpd from Qatar and 11.5
million bpd from Saudi Arabia, while the
gas contrast is even starkerwith proven
reserves of around 33.5 trillion cubic feet(949 billion cubic metres), dwarfed by
Dohas 885.1 tcf (25 trillion cubic
metres) and Riyadhs 290.8 tcf (8.2 tcm).
Omans advantage
However, Omans crucial advantage lies
in its location, allowing the import and
export of products to key Asian markets
without passing through the Strait of
Hormuz and thus without the risk of
being affected by political uncertainty
involving Iranwhich has in the past
threatened to close the waterway inprotest at international sanctions on its
hydrocarbons industry.
Pure import-export refineries and
downstream facilities such as that
planned at Duqm are thus economically
viable.
An upstream investment programme is
also well under way to stem oil output
decline and to boost gas production, with
the biggest projectKhazzannow
entering the construction phase.
COMMENTARY
Oman: action on graft releases
contracting energyAs corruption arraignments swept through the sultanates leading state oil and gas
companies in late 2013, progress on major projects was inevitably slowed. However, with
the cases now over, there has been a recent surge in contracting activity
y Clare Dunkley
The conclusion of corruption trials has prompted key petrochemicals project awardsBoth major Sohar downstream complexes have appointed project managersThe award of the Duqm refinery FEED is a clear sign that the port zone development is back on track
8/11/2019 Downstream Monitor - MEA Week 15
5/22
Downstream Monitor MEA 16 April 2014, Week 15 page 5
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
This follows the signature of a final
gas sales agreement in December 2013.
The US$16 billion development of tight
gas reserves at the Khazzan field in
central Block 61 by BP, and due to
deliver 1 billion cubic feet (28 million
cubic metres) per day by 2018,
equivalent to around 33% of national
output.
Industrial hub
At the heart both of new developments
and of the criminal investigations
remains the well-established industrial
hub of Sohar, home to the sultanates
largest refinery and petrochemicals
facilities, the management of which were
combined in 2011 under the ORPICumbrella.
The refinery is being expanded under a
US$2.1 billion engineering, procurement
and construction (EPC) contract awarded
in November 2013 to a joint venture (JV)
of South Koreas Daelim Industrial and
the UKs Petrofac, which will raise
output to 187,000 bpd from 116,000 bpd
and thereby feed both ORPICs existing
340,000 bpd polypropylene (PP) plant
currently running at only around 60% of
capacityand supply additional facilitiesplanned by ORPIC and OOC.
The largest of theseand indeed the
largest ever in Omanis the estimated
US$3.6 billion Liwa Plastics scheme to
build a steam cracker and downstream
units, to be the first in the country to
manufacture polyethylene (PE) and its
derivatives and to have capacity of 1
million tonnes per year (tpy) on
completion in 2018.
Output will comprise high-density
polyethylene (HDPE), linear low-density
polyethylene (LLDPE), PP, methyl
tertiary butyl ether (MTBE) and butane-
1, with feedstock sourced partly from the
refinery and partly from the central
Fahud gas field. After formal launch in
mid-2013, little was heard of the project
above the noise of the corruption
crackdown. However, shortly after Al-
Kindi learned his fate, his successors
awarded the project management
consultancy (PMC) and front-end
engineering and design (FEED) contracts
to Engineers India Ltd (EIL) and CB&I
of the US respectively, with
prequalification for the EPC contracts
expected to be launched by the end of theyear in order to return the project to
schedule. A tender for the financial
advisory mandate was floated in late
March, with a May 6 deadline.
Even more mired in the graft morass
was the other major new petrochemicals
venture planned at Sohara polyester
chemicals complex to be developed
under an agreement between OOC and
South Koreas LG International signed in
2012corruption in the negotiation of
which led to the imprisonment of both
Al-Wahaibi and the vice-CEO of LG.
However, far from being abandoned in
light of such tainted beginnings, this
scheme too seems to have been
galvanised by the trials end, with
Australia Worley Parsons selected for
the PMC in March.
The estimated US$850 million plant
will produce 1.1 million tpy of purified
terephthalic acid (PTA) and 500,000 tpy
of polyethylene terephthalate (PET), used
primarily in packaging, and like Liwa
will be fed by ORPICs refinery indicative of the close and overlapping
ties between the various state
hydrocarbons companies.
OOCs subsidiary Takamul Investment
is planning a complementary 100,000 tpy
purified isophthalic acid (PIA) plant in
partnership with ORPICwhich will
provide metaxyelene feedstockwhile
the PIA will be combined with PTA from
OOCs facility to produce PET. Design
work is expected to be completed by the
end of 2014.
Diversification
As in Saudi Arabia, Oman is pursuing
geographical as well as general economic
diversification, spreading economic
activity and wealth beyond Muscat and
Sohar through developing new hubs such
as Duqm and Salalah, both designated
special economic zones (SEZs).
While Salalah is already home to
several petrochemicals plants, Duqms
development as a major port and
industrial area is being carried out from
scratch, with a refinery and
petrochemicals complex as the
centrepiece and OOCs priority project
among the many in the zone in which the
firm is investing. The state company is
implementing the estimated US$15billion scheme in 50:50 JV with Abu
Dhabis International Petroleum
Investment Co. (IPIC)the latter
providing the necessary crude from the
emirates Habshan oil processing hub.
The project itself has escaped censure
during the corruption debacle but
officials from the Transport &
Communications Ministry and Athens-
based Consolidated Contractors were
jailed in March for improper payments
during the award of contracts relating tothe portwhich will handle the
refinerys raw materials and exports
while the conclusion of Al-Wahaibis
case has again coincided with renewed
OOC-related activity. In late March,
Foster Wheeler of the US was awarded
the FEED contract for the estimated
US$6 billion, 230,000 bpd import-export
refinery, envisaged as a first phase to be
followed at an unspecified later date by a
US$9 billion second phase adding
petrochemicals production. Frances
Credit Agricole was selected as financial
adviser to the project company, Duqm
Refinery & Petrochemical Industries, in
2013. On a smaller scale, further
petrochemicals development at Salalah,
led by Takamul, is well under way, with
a US$500 million caustic soda and
ethylene dichloride plant under
construction and plans recently
announced for an ammonia facility,
valued at several hundred million dollars,
to add value to the output from the
operational Salalah Methanol plant.
COMMENTARY
The revolutions that tore
through the Arab wor ld in
2011 barely touched
poli tically quiescent Oman,
bar l imited protests in
major citi es demanding,
among other things, an
end to high-l evel
corruption
8/11/2019 Downstream Monitor - MEA Week 15
6/22
Downstream Monitor MEA 16 April 2014, Week 15 page 6
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
The revolutions that tore through the
Arab world in 2011 barely touched
politically quiescent Oman, bar limited
protests in major cities demanding,
among other things, an end to high-level
corruption.
Frightened into action by such unusual
demonstrations of dissent, Muscat acted
swiftly to strengthen anti-graft
mechanisms, re-constituting the State
Financial and Administrative Audit
Institution with a remit to present
evidence of illegalities to the Office of
the Prosecutor General.
As these moves have proven more than
mere window-dressing, the damage
wreaked by unrest elsewhere in the
region to the ability of many states to
attract foreign direct investment may
have precisely the opposite effect in the
sultanate by increasing transparency at
the same time as ensuring popular calm,
boding well for Muscats ambitious
downstream plans.
Kenya is preparing for a regional oil rush
that it hopes will transform its economy
and bring down high fuel prices.
The country is investing in new import
and export infrastructure and co-
operating with neighbours over possible
new refinery projects that will make the
region more self-sufficient in higher-
value oil products.
Meanwhile, Kenya continues to attract
interest from local and international
explorers and developers, keen to win a
slice of the countrys newly discovered
oil wealth. Kenyas government has
already starting relocating the Kipevu oil
terminal in Mombasa to allow more and
bigger tankers to berth, Kenya Ports
Authority (KPA) said last week. The new
terminal will cost US$120 million and,
once complete, will have the capacity for
two large vessels at the same time, each
carrying 100,000 tonnes (733,000
barrels) of crude oil.
Once complete, in 2018, it should helpreduce fuel prices in Kenya by solving
perennial capacity constraints in the
handling of petroleum products.
The sector has been experiencing
shortages of petroleum oils occasioned
by lack of adequate storage capacity in
the industry, according to KPAs
chairman, Danson Mungatana. The
situation has caused delays for vessels
and inadvertent ship congestion, which in
turn raises prices of oil in the country.
Refining
Kenya is also teaming up with Uganda
and Rwanda to help ease a crippling lack
of refining capacity in the region, with
plans to build a joint refinery in Uganda.
The proposed refinery is expected to be
built in the Hoima district, because of its
sparse population and the proximity to
Ugandas oilfields. It will be jointly
owned by the public, with a 40% stake,
and the private sector, with a 60% stake,
according to Reuters reports.
The proposed plant would have a
capacity of around 60,000 barrels per
day, dwarfing Kenya Petroleum
Refineries 35,000 bpd plant in Kipevu,
which is currently the only refinery in the
region and is on the verge of closing.
Kenya does plan to build another US$2.8
billion refinery on its northern coast but
has made little progress thus far.
Privately owned National Oil Ethiopia
is also keen to get in on the act, with its
CEO, Tadesse Tilahun, saying last weekthat it wants to part-finance a refinery
with other various partners.
Africas demand for refined products
is growing hugely because of its
economic growth. The crude findings are
also increasing. That is the opportunity,
he said. We want to [build] a refinery.
We have already discussed this in
principle with our shareholders, who are
very much committed.
Africa faces challenges, though, in
supplying more of its own refined
petroleum products. Funding for oil-
related infrastructure is still tough and
foreign refiners and traders continue to
flood the market with US$80 billion
worth of imports, said Tadesse. Existing
pipelines also tend to run to the coast
either for the export of crude or to import
transport fuel produced at coastal
refineries.
That has to change, he says.
Refineries are now needed inland so
that Africa can supply itself.
Pipelines
In another sign of increased co-operation
with neighbouring states, Kenya and
Uganda have reportedly agreed to build a
crude oil export pipeline that will
incorporate a special heating system to
keep the waxy crude found in Kenya
liquid and flowing.
The 1,380-km long pipeline would be
the longest such link in the world.
On the Kenyan side, the pipelinewould probably run mostly underground,
stretching 850 km from the Lokichar
Basin to the coast, according to a report
last month by Tullow Oil, which has
drilled seven wells in the area, finding
600 million barrels of oil.
Ugandas section is expected to run
from the Lake Albert rift basin to link up
with the Kenyan pipeline, with another
link from South Sudan to Lamu.
COMMENTARY
Infrastructure works onthe way for Kenyay Helen Castell
8/11/2019 Downstream Monitor - MEA Week 15
7/22
Downstream Monitor MEA 16 April 2014, Week 15 page 7
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
Uganda and Kenya are now at the
heart of an emerging power house in
future global oil supply markets and this
has created some high-potential
synergies for accelerated oil production
and inter-governmental [co-operation] in
the region, said Tullows CEO, Aidan
Heavey.
Farm Tower
Kenya is also attracting more interest
from energy companies. London-listed
minnow Tower Resources agreed last
week to farm in to the onshore Block 2B,
acquiring a 15% participating interest
from Taipan Resources Kenya-based
subsidiary, Lion Petroleum.
Taipan will remain operator of the
block with a 30% interest. Tower is
paying US$4.5 million in cash for the
stake plus 9 million of its own shares and
will make an additional payment of
US$1 million conditional upon the
spudding of a second well in the block.
Home-grown companies are also
getting into better shape, with Kenyan oil
marketer KenolKobil reporting last week
that it booked a profit in 2013 as its
exchange rate losses were reduced and
cost-cutting paid off.
The company made a 564 million
shilling (US$6.51 million) pre-tax profit
in 2013, compared with a 8.9 billion
shilling (US$102.6 million) loss the
previous year. It also forecasts stronger
sales this year.
Nearly 15 years on since it was first
mooted, a European Union (EU) energy
policy objective the Southern Gas
Corridor has never appeared more
necessary.
Two months on from Russias
annexation of Crimea and with Russian
troops massing on Ukraines eastern
borders, Russian President Vladimir
Putin last week gave his clearest message
yet that he is prepared to use the ultimate
weapon if he does not get what he
wantsnamely to cut supplies of
Russian gas flowing to Europe via transit
lines through Ukraine.
While Putins warning referred directly
only to the cutting of supplies to Ukraine
in the event of further violation of
payment for gas supplied it also noted the
risk that Ukraine may siphon off gas
being transited to Europe, warning of the
possible need then to cut those supplies
too.
Although not explicitly stated, the
message to Europe was clear: intervene
in our dispute with Ukraine and face gas
cuts. It comes as no surprise then that
those EU policy makers have suddenly
rekindled interest in the EUs long-
mooted plan to create the Southern Gas
Corridor allowing the export of gas from
the Caspian and Middle East through
Turkey.
Until last year, the EU was banking on
the development of the multinational
Nabucco pipeline running from Eastern
Turkey through Bulgaria, Romania and
Hungary to Austriaand in its later
incarnation, on to Germany and Poland.
Over a decade in the planning,
Nabucco never overcame the major
obstacle of how to ensure the viability of
a 31 billion cubic metre per year pipeline
being developed by a consortium none of
whose members own any upstream gas,
and which has only a conditional promise
of 16 bcm per year of supplies.
Lack of progress
Most observers concluded that
Azerbaijans announcement in late 2011
that it wanted to develop its own gas
pipeline in partnership with Turkeythe
Trans Anatolian Gas Pipeline (TANAP)
saved the EU the embarrassment of
having to admit that the project it had
been backing was unlikely ever to be
realised in the form it had envisioned.
So far however, plans for TANAP are
proving scarcely any smoother.
Over a year ago, it was announced that
TANAP would be developed by a
consortium in which the State Oil
Company of Azerbaijan Republic
(SOCAR) would take a 51% stake,
Turkey would 20%, with the remaining
29% being divided between the three
other members of the consortium
developing the Shah Deniz gas field
which will supply the 16 bcm of gas
committed to TANAP: BP (12%), Statoil
(12%) and Total (5%).
COMMENTARY
Russian roulette points
the barrel at TANAPContinuing Russian aggression in Ukraine has rekindled Europe interest in a Southern
Gas Corridor. But with TANAP now the only game in town, can Azerbaijan and Turkey
actually deliver, and at what price?
y David OByrne
TANAP last year beat off competition from Nabucco to pipe gas from the Caspian to EuropeHowever, little progress has been made, and due diligence is only now being carried out by Botas and BPStatoil and Total have made it clear they will play no part in TANAP and may withdraw from Shah Deniz
8/11/2019 Downstream Monitor - MEA Week 15
8/22
Downstream Monitor MEA 16 April 2014, Week 15 page 8
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
Now with both Statoil and Total
having confirmed they will play no part
in TANAP, Statoil having reduced its
stake in Shah Deniz from 25.5% to 10%
and Total apparently intent on selling allof its 10% take, the structure of the
TANAP consortium is no clearer.
Indeed if statements made at a
conference in Turkey last week by the
remaining three participants are anything
to go by, the process of finalising the
three party consortium is proving
problematic.
Speaking in Ankara, Saltuk Duzyol the
newly appointed CEO of the TANAP
project company announced that
construction would start in April 2015,however he subsequently conceded that
while it is now decided that SOCAR will
take a 58% stake it is still unclear when
the equity split will be concluded.
Uncertainty
Duzyol suggested that the cause of the
delay lies with Turkeys state gas
importer Botas conducting due diligence
prior to confirming its stake, now
expected to be 30%.
A senior Botas official was also unableto suggest when the consortium structure
may be concluded.
At the same time Bud Fackrell, head of
BP Turkey confirmed that BP too is
conducting due diligence on its planned
12% stake in TANAP and expressed his
hope that the process can be completed
this yearhardly an encouraging
suggestion given the planned start date.
Previously Fackrell and others associated
with the TANAP project have stated that
the final agreement on the consortiumneed not be taken before investment
starts.
Certainly, with the project planned to
be financed solely by the equity partners,
there is no need for the lengthy process
of securing and finalising lines of credit.
This has apparently allowed the TANAP
project company to open a tender for the
supply of pipe, with 18 companies pre-
qualifying, to prepare an engineering,
procurement and construction (EPC)
tender to be held this month and to
prepare documentation for a tender for
supply of compressors, also expected to
be issued soon.
However, the prospect of due diligence
by two members of a three party
consortium continuing until just a few
months before construction starts is far
from normal, the more so given that
project cost has yet to be finalised and is
expected to substantially exceed the
US$7 billion initial estimate.
While SOCAR does have substantial
financial muscle, it has yet to finalise theUS$3.5 billion financing required for its
10 million tonne per year STAR refinery
project following the sudden pull out
earlier this year of the European Bank for
Reconstruction and Development
(EBRD) and the International Finance
Corp. (IFC) which were to contribute
US$500 million between them.
If SOCAR is unable to secure finances
for STAR, it may have to use its own
resources, and look elsewhere for funds
for TANAPa project which in theoryshould have had no trouble in securing
funds from international development
lenders even before the Russian
occupation of Crimea and the sudden
urgent need to realise the long-mooted
Southern Gas Corridor.
Egypt will receive additional supplies of
crude oil from Kuwait, along with an
increase in petroleum products.
The two countries reached a deal last
week whereby Kuwait Petroleum Corp.
(KPC) will boost its crude deliveries to
Egypt by 20,000 barrels per day to
85,000 bpd, from the current rate of
65,000 bpd.
The Kuwaiti news agency, KUNA,
reported that the new contracts would run
for three years.
The deal also calls for an increase in
diesel and jet fuel deliveries to 1.5
million tonnes per year, up from 860,000
tonnes per year.
Egypt is facing a serious energy crunch
as demand for petroleum products and
natural gas moves beyond the
governments ability to keep the market
supplied.
COMMENTARY
POLICY
Egypt strikes energy securitydeal with Kuwait
8/11/2019 Downstream Monitor - MEA Week 15
9/22
8/11/2019 Downstream Monitor - MEA Week 15
10/22
Downstream Monitor MEA 16 April 2014, Week 15 page 10
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
Zirku handles output from ZADCOs
three fieldsUpper Zakum, thought to
be the worlds fourth largest, and the
smaller Umm al-Dalkh and Satah fields.
In early April 2013, a team of South
Koreas Daewoo Shipbuilding & Marine
Engineering and UK/UAE joint venture
Petrofac Emirates was awarded the
US$3.7 billion EPC contract for the
onshore portion of the full-field
expansion project at Upper Zakum,
covering an oil processing plant and
associated facilities, aimed at boosting
production from 550,000 bpd to 750,000
bpd by 2017: the US$800 million
offshore elements engineering
procurement and construction (EPC)
contract was awarded to a consortium ofthe local National Petroleum
Construction Co. (NPCC) and Frances
Technip in July 2012.
The Upper Zakum expansion forms an
important part of Abu Dhabis broader
drive to increase crude capacity to 3.8
million bpd by 2017/18, with the
increment mainly being delivered from
offshore.
ZADCO is considering undertaking a
further expansion to produce 1 million
bpd: no timeframe has yet been set, but
some certainty around the concession
agreement was reached in January with
the extension of the contract with Japans
Inpex, which holds a 12% stake, to 2041
in line with those of partners Abu
Dhabi National Oil Co. (ADNOC) with
60% and the US ExxonMobil with 28%.
Fellow ADNOC-owned offshore
operator Abu Dhabi Marine Operating
Co. (ADMA-OPCO) is also undertaking
expansion at its major fields to raise
output by 300,000 bpd to 1 million bpd:
in 2013, NPCC won the main EPC
contract for the development of the Umm
al-Lulu asset while South Koreas
Hyundai Engineering & Construction
was selected for the largest package on
the Satah al-Razboot field.Bids have been under evaluation since
January for the full-field development of
the companys Nasr field.
South Africas petrochemicals giant
Sasol has reported a 25% hike in its first
quarter headline earnings, helped by a
weaker rand currency and higher
chemical prices.
In a statement the company said: This
achievement was on the back of a strong
operational performance from our global
businesses, coupled with a 19% weaker
average rand/US dollar exchange and
improved chemical prices.
However, some analysts in South
Africa are beginning to question whether
with the successful commissioning of itsUS$29 billion gas-to-liquid (GTL)
project at Lake Charles, Louisiana, the
company is still committed to operations
in South Africa.
The US project uses unique technology
to convert ethylene into higher value
chemical products to be used in the
manufacture of consumer products such
as food packaging.
It is currently in start-up and the first
products have already been produced.
The plant is expected to be fully
operational by mid-2014.
However, critics say that Sasol, which
started in 1955 with taxpayers cash, has
gambled hugely on this single project in
Louisiana.
Sasol was the target of a possible
windfall tax in 2006.
However, it managed to negotiate
away that tax, partly by promising to
build a coal-to-liquid (CTL) plant
Mafuthawhich was to be aimed at the
local fuel market.
But Mafutha has failed to materialise
and in its stead Sasol built its GTL
facility at Lake Charles.
Local news agency Business Day
reported on April 6: The argument that
Sasol is quietly lightening its exposure to
South Africa is bolstered by its failure to
capitalise on Mozambican gas fields, as
well as its stated desire to become lessreliant on coalwith its dirty image
and impending carbon tax implications.
In response, Sasol said last week that it
is adamant that it has no plans to cut its
ties to South Africa. Spokesman Alex
Anderson said that 66% of Sasols total
assets will reside in sub-Saharan Africa
(SSA) and its primary listing will remain
on the Johannesburg Stock Exchange
(JSE).
COMPANIES
Sasol earnings rise by 26%, whiledoubts are raised about SA future
8/11/2019 Downstream Monitor - MEA Week 15
11/22
Downstream Monitor MEA 16 April 2014, Week 15 page 11
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
Irans 390,000 barrel per day Abadan
Refinery is set to produce Euro IV gradegasoline in the coming Iranian calendar
year.
In an interview with the Shana news
agency Saeed Mahjoubi, a senior official
with the National Iranian Oil Refining
and Distribution Co. (NIORDC), said
that a number of old units will now be
deactivated at the site, with new units to
come online in their place.
Abadan, which meets 25% of Irans
demand for gasoline and fuel oil, was
closed for maintenance between March10 and April 10, a move that is estimated
to have cut the countrys fuel exports by
around 50%.
Currently, Abadan produces Euro II
standard fuel, which is well below the
Euro V grade commonly used by
consumers in the European Union (EU).Increasingly, this has become a key
market for Middle Eastern refiners keen
to diversify their economies away from a
reliance on crude exports.
While the upgrade to Euro IV still falls
short of EU requirements, it does raise
the possibility of a future renovation in
order to supply European customers,
should Tehran have its exports sanctions
fully lifted later this year.The Abadan refinery was completed in
1912 and is the oldest refinery in the
Middle East, despite having to be rebuilt
after being destroyed during the 1980-
1988 Iran-Iraq war.
In May 2011, an explosion occurred
during a visit to Abadan by then
president Mahmoud Ahmadinejad for the
inauguration of a new gasoline
production unit. Reports said that four
people were killed and around 20 others
were injured.In September that year, a fire also
injured four people. On March 30, Shana
said that another fire had occurred at the
facility, although no injuries or
substantial damage were reported.
The Egyptian Refining Co. (ERC) is to
begin construction this month on its
long-delayed refinery project, which is
designed to alleviate some of Egypts
growing domestic demand for petroleum
products and thus reduce Egypts
mounting costs of importing fuels.
Fuel shortages in Egypt have served to
exacerbate the countrys social and
political problems.
The US$3.7 billion project will be built
at the existing Mostorod PetroleumComplex (MPC) site, which is operated
by the Cairo Oil Refinery Co. (CORC)
and located 20 km north of the capital.
The 145,000 barrel per day CORC
refinery, which came on-stream in 1973,
produces light and middle distillates and
LPG and it will supply the ERC plant
with 67% of its production for further
processing. ERC was formed in 2007
with a plan to upgrade the CORC
refinery and produce lighter products and
more diesel. The new facility includes an
80,000 bpd vacuum distillation unit and a
40,000 bpd hydrocracker, a 25,000 bpd
delayed coker, a 23,000 bpd naphtha
hydrotreater and a 32,000 bpd distillate
hydrotreater.
The project is expected to come into
operation in 2017. The plant will produce
Euro V grade diesel, International Air
Transport Association (IATA)
specification jet fuel, fuel oil, LPG,
kerosene, reformate, naphtha, sulphur
and coke, and its entire production will
be sold to key shareholder the Egyptian
General Petroleum Co. (EGPC) at
international prices under a 25-year
contract.
The sulphur and coke will be marketed
to industrial users and suppliers. EGPC
has provided US$1.1 billion in equity for
the project and US$2.6 billion in
financing has been arranged by a numberof international institutions. Project
consultants include Worley Parsons,
KBC and Societe Generale. Egypts
largest refinery is the 146,300 bpd El-
Nasr plant, originally built in 1913 and
upgraded during 1967-74. In 2000, the
Ministry of Petroleum signed an
agreement with China to build a new
US$2 billion at the El-Nasr site with a
capacity up to 150,000 bpd, but work has
yet to begin.
REFINING
Abadan to produce Euro IV fuel
Construction to begin
on Egyptian refinery
8/11/2019 Downstream Monitor - MEA Week 15
12/22
Downstream Monitor MEA 16 April 2014, Week 15 page 12
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
The Basra Gas Co. (BGC) Train 1
project at North Rumaila in southern Iraq
moved a step further forward with the
announcement that Technip, in
partnership with China HuanQiu
Contracting & Engineering Corp.
(HQCEC), has been awarded the front-
end engineering design (FEED) contract.
BGC is a joint venture between Iraqs
South Gas Co. (SOC) with a 51% share,
Shell with 44%, and Mitsubishi with 5%.
The project is the first of the new
greenfield associated gas processing
facilities that it is hoped will significantly
minimise gas flaring in Iraq and make
more energy resources available for
power and domestic use. The natural gas
liquid (NGL) train will have a nominal
feed gas capacity of 530 million cubic
feet (15 million cubic metres) per day.
The standalone facilities will produce
LPG as well as NGLs and condensate for
domestic markets. It is scheduled to be
completed by the end of 2014.
Vaseem Khan, President of Technip
Middle East said: This award reflects
Technips strengthened position in the
Middle East market We are proud to
bring our specific technological edge and
licensed innovative solutions to the
downstream industry.
The project began operations in May
2013, marking a milestone in the
countrys fragile post-war recovery.
BGC is one of the largest gas-
capturing projects in the world and once
complete, will gather and process
associated gas from three major oilfields
in southern Iraq. The gas captured by
BGC from Rumaila, the first stage of
West Qurna and Zubair will be used to
generate electricity in Iraq. But the
project will also have the option to build
a plant to produce LNG for export once
domestic energy needs are met.
Total planned investment is US$13
billion, with the possibility of an
additional US$4 billion for an LNG
export plant, according to the
International Energy Agency (IEA).
Shell said that BGC would rehabilitate
and upgrade existing facilities as well as
build new assets which would increase
production capacity from the current 400
million cubic feet (11 million cubic
metres) per day to 2 billion cubic feet (57
million cubic metres).
The Oman Gas Co. (OGC) has signed a
memorandum of understanding (MoU)
with the Salalah Free Zone (SFZ) and the
Port of Salalah for the construction of a
LPG processing plant that will be located
in the SFZ with export facilities at the
port.
The LPG will enable the high recovery
of propane, butane and condensates from
the natural gas that flows through OGCs
southern gas grid. The estimated cost of
the project was not disclosed.OGC, which is wholly owned by the
Oman Oil Co. (OOC), is Omans natural
gas transport utility and supplies gas to
domestic power generation stations and
water desalination plants, as well as
fertilizer and methanol to petrochemical,
steel and cement plants, and refineries.
The plan calls for an LPG extraction
plant to be located in the free zone. LPG
and condensate storage facilities and a
jetty will be constructed at Salalah port.
The scope of work includes construction
of new gas and liquids pipelines in the
Salalah region.
The plant, which will provide a supply
of domestic gas for the region, is due to
come into operation in 2018.
The plant is to be state-of-the-art and
will adhere strictly to health, safety and
environment standards, officials said
during the MoU signing ceremony. The
project also will create a number of jobs
for local residents.
The CEO of the Salalah Free Zone,
Awadh Salim Al Shanfari said the
agreement to construct this vital project
in the Salalah region comes from the
strategic goal of exploiting the naturalresources to create projects which will
add value and broaden the horizons for
other industries that are located
downstream of the LPG value chain, the
Oman Tribune reported.
He said the project would also create
opportunities for small and medium
enterprises (SMEs).
FUELS
Basra NGL advances as
Technip gets FEED contract
OGC plans LPG plant in Salalah
8/11/2019 Downstream Monitor - MEA Week 15
13/22
Downstream Monitor MEA 16 April 2014, Week 15 page 13
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
The construction of South Africas New
Multi-Product Pipeline (NMPP) is now
over four years behind schedule and is
not likely to be completed until April
2015.
The string of setbacks faced by the
project, operated by Transnet Pipelines,
has already led to cost escalations which
are currently being investigated by the
South African national energy regulator
(NERSA) and are sure to lead to future
fuel tariff increases. According to
NERSA, the investigation will only be
completed in 2015.
So far, the company has already
admitted to underestimating the
complexity of the project, justifying the
delays with the negotiation of the rights
of passage with about 900 landowners,
which it said was extremely time-
consuming. In an interview to the South
African Black Business Quarterly
(BBQ), CEO Sharla Pillay said: The
lessonwe understated the magnitude
and complexity of the NMPP project.
There was an over-reliance on external
service providers for expertise and skills
which were lacking in-house.
Transnets General Manager Lennie
Moodley has also acknowledged the
challenges ahead, but is confident that
the company has entered a new era and
has the opportunity to unblock supply
chain inefficiencies, broadening its focus
into Africa. There are opportunities for
securing maintenance and strategic
planning contracts while working with
others in the logistics industry to more
effectively delivery services to
customers, he told BBQ.
Meanwhile, NERSA is concerned
whether the pipeline will represent value
for money.
According to Rod Crompton,
responsible for petroleum pipelines at
NERSA, the regulator is concerned
whether the usual approachwhereby
regulators can exclude the portion of an
asset not prudently acquired from a tariff
application, so that users pay a tariff
consistent with the costshould be
applied to the pipeline project, as it
would severely impact Transnets
investment programme.
The 55-km pipeline from Durban to
Johannesburg will have a 70-year design
life and a capacity to transport 93-grade
and 95-grade unleaded petrol, low-
sulphur diesel, ultra-low sulphur diesel
and jet fuel.
Crude oil exports from one of the four
terminals that have been under the
control of a rebel militia group in eastern
Libya are expected to resume this week.
Media reports say Sarir crude will be
loaded at Libyas eastern-most terminal,
Marsa al-Harigah, near Tobruk.
The terminal, with a capacity to ship
110,000 barrels per day, and the terminal
at Zueitina were turned over to Libyan
army control late last week following an
agreement between the Libyan
government and the rebels. This should
lead to the four terminals being returned
to government control.
The rebels had formed themselves into
the Cyrenaica Political Bureau and
demanded that eastern Libya be given
more autonomy and more control over
oil revenues. Originally organised to
protect the countrys energy facilities, the
rebel group threatened to establish a new
state if the government in Tripoli did not
make efforts to put the country on a
better political course. Events came to a
head in March when the rebels attempted
to export crude using a rogue tanker that
managed to evade Libyan authorities.
However, this was later seized by the US
Navy and returned to one of the Libyan
ports under government control.
Libyas state-owned National Oil
Corp. (NOC) last week lifted the force
majeure declaration imposed at Marsa al-
Harigah after it was seized by rebels in
mid-2013.
It is not clear when exports might
resume from Zueitina, which has a
70,000 bpd capacity, or when the export
terminals of Es Sider and Ras Lanuf,
with a combined capacity of 560,000 bpd
will be turned over to government
control.
The blockade of the terminals, which
has lasted more than nine months, has
resulted in serious financial losses for
Tripoli, which has had to revert to
dipping into its financial reserves in
order to keep the government working.
Revenue losses are estimated to be
US$14 billion or more.
PIPELINES
Transnet suffers yet
another setback
TERMINALS & SHIPPING
Libya crude oil exports setto resume this week
8/11/2019 Downstream Monitor - MEA Week 15
14/22
Downstream Monitor MEA 16 April 2014, Week 15 page 14
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
Production and exports in recent
months is reported to have fallen to
around 200,000 bpd and less.
Prior to the blockade of terminals and
onshore oil fields and infrastructure,
Libya was producing 1.2 million bpd and
exporting most of it.
Premier resignation
While there are signs of progress from
Libyas east, trouble continues at the
heart of government. Libyan Prime
Minister Abdullah al-Thinni, who
replaced Ali Zeidan, announced plans to
resign last week after an attack on his
family.
A militia is believed to have attacked
al-Thinnis family, although they were
not harmed. The premier condemned the
cowardly attack, during which his car
was reportedly stolen.
Once the General National Congress
(GNC) has chosen a replacement, al-
Thinni will step down, he said.
More than a decade after the project was
first mooted, state-owned downstreamoperator Kuwait National Petroleum Co.
(KNPC) in mid-April finally tendered
two of the five main engineering,
procurement and construction (EPC)
contracts covering storage and marine
works on its US$14 billion new refinery
project (NRP), a 615,000 barrel per day
facility to be built at Al-Zour in the south
of the country.
The launch of the bidding process
follows the award in February of the
main EPC contracts on KNPCs other
flagship scheme, the Clean Fuels Project
(CFP) to expand and upgrade existing
refining capacity at Mina Abdullah and
Mina al-Ahmadi.
Bids for both NRP contracts are due on
September 14. Four prequalifiers are
looking at the tank farm packagethe
UKs Petrofac with South Koreas
Hyundai Heavy Industries (HHI), Italys
Saipem with Indias Essar and separately
Daelim Industrial and Daewoo
Engineering & Construction, both of
South Korea.A similarly Korean-dominated shortlist
of five prospective bidders are eligible to
bid for the marine works package
Petrofac with HHI, Hyundai Engineering
& Construction with Saipem and South
Koreas SK Engineering & Construction,
Daewoo and the US McDermott.
Several interested companies have
reached this stage and beyond before.
When the contracts were first awarded in
2008 before being cancelled in light oftrenchant criticisms of both the bidding
process and the projects economics by
the always-suspicious National Assembly
(parliament), Daewoo won the tank
farms job and HHI was selected for the
marine works.
The three remaining packages, on
which no details of prequalifiers has been
released more than a year after the
submission of applications, cover the
atmospheric residue desulphurisation
units, hydrogen compression and
recovery units and offsites and utilities
won in 2008 respectively by Japans JGC
Corp. with South Koreas GS
Engineering & Construction, SK and the
US Fluor.
According to the ambitious schedule
set out by KNPC late last year,so far,
to general surprise, adhered tothe
bidding and awards process for all five
contracts will be completed by the end of
the year.
Other aspects of the NRP have been
put in place recently, likewiseengendering hope of timely progress: in
early March, Van Oord of the
Netherlands won the 186.4 million dinar(US$663.3 million) site preparation
contract for dredging and reclamation of
the designated 16.2 million square metre
plot, unusually winning against
competition from a significantly lower
bid by fellow Dutch firm Boskalis
Westminster.
Meanwhile KNPCs upstream
counterpart Kuwait Oil Co. (KOC)
issued a tender the same month for
construction of a 350-km pipeline to
supply the new refinery with crude
feedstock from its Lower Fars heavy oil
project, with bids due on May 6.
The refinerys output will primarily
supply low-sulphur fuel oil to the
countrys existing and planned power
plants, as the government works to
eliminate highly controversialin light
of the countrys energy riches chronic
summer power shortages. Completion is
due in 2019.
Future integration with a
petrochemicals complex is also under
discussion between KNPC and sister firmPetrochemical Industries Co. (PIC),
which under initial proposals would see
the refinery supply naphtha and LPG to a
mixed-feedstock cracker with
commodities and derivatives units, with
PIC providing hydrogen and pygas in
return. Fluor and Foster Wheeler, also of
the US, are carrying out studies on the
estimated US$7-10 billion project.
TERMINALS & SHIPPING
TENDERS
KNPC floats new refinery tenders
8/11/2019 Downstream Monitor - MEA Week 15
15/22
Downstream Monitor MEA 16 April 2014, Week 15 page 15
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
The following news items are sourced
from local and international news
sources. NewsBase is not responsible for
the contents of the stories and gives no
warranty for their factual accuracy.
POLICY
Israeli gas holdspromise of betterties with neighboursIsraels drive to export its new-found
natural gas could help to rebuild strained
ties with old regional allies Egypt and
Turkey, but could deprive Europe of a
precious alternative to Russian gas.
Israel has in recent months alreadysigned energy deals with Jordan and the
Palestinian Authority, though relations
with the Palestinians are at a low ebb,
and now needs to expand its export
horizons to cash in on its huge energy
discoveries.
If all goes well, the latest developments
could see first pipelines being laid
between Israel and Turkey as soon as
2015, and gas cooperation between Israel
and Egypt is also emerging, which would
allow export access to Asias majormarkets.
A growing population and soaring
demand have left Egypts own liquefied
natural gas export (LNG) plants in need
of new supply, as domestic shortages eat
into seaborne exports through the Suez
Canal to the worlds most lucrative
market in Asia.
This has put Israels previous plans to
pump its gas reserves into a future export
plant in Cyprus on the back burner,
dealing a major blow to the indebted
Mediterranean islands ambitions to
become a global player in the gas market.
A Cypriot LNG export plant was due to
deliver at least 5 million tonnes a year to
Europe and Asia, allowing Europe to
reduce its growing dependency on
Russia, which has become of particular
concern since the crisis in Ukraine cast a
Cold War chill over East-West relations.
Israels new plans throw Cypriot
developments into doubt as investors
would require more gas than Cyprus has
on offer to make returns on multibillion-
dollar investments.
If Israel has really ditched Cyprus as a
partner to develop the regions gas
resources, then we (Cyprus) really do
have to find quite a lot more gas if we
want to become a viable exporter, and
that would inevitably throw our plans
back by several years, said one source
involved in developing Cypruss gas
reserves.
The possibility of sanctions on Russias
energy sector in response to Moscows
annexation of Crimea and troop build-up
along Ukraines eastern border have
underscored Europes acute need to
diversify its oil and gas sources.
Israel plans to export gas by pipeline and
through several floating LNG productionplants, which cool gas to liquid form, so
they can ship it to the worlds largest
markets.
At stake for Israel is a US$150 billion tax
take should export deals be agreed by a
consortium operating its gasfields. Its
strategic re-alignment effectively places
a tantalisingly close new gas province
out of Europes reach.
Ultimately Egypt and Turkey need
energy, and the fact that we have it is
creating a regional convergence ofinterests, an Israeli diplomatic source
told Reuters.
REUTERS, Apri l 14, 2014
REFINING
SK firms wincombined US$7.2bnin Kuwait ordersFive South Korean companies have won
a combined US$7.2 billion in orders
from Kuwait National Petroleum
Company to expand capacity and
improve environmental standards at two
oil refineries.
The contracts, which stem from US$12
billion in bids approved in February for
the state-run companys Clean Fuels
Project, highlight efforts by South
Korean builders to shore up margins via
joint bids with other local or foreign
firms for major overseas construction
projects. Korean companies are
increasingly forming consortiums with
established overseas companies and that
is helping them to win better value
contracts, said Yun Sok-mo, an analyst at
Samsung Securities.
Overseas plant orders won by South
Korean builders during the first quarter
rose by 42.1 percent from a year ago,
according to the Ministry of Trade,
Industry and Energy in a report earlier
this month.
The ministry said prospects for further
growth in overseas orders looked good
given expectations for continued global
economic recovery and growing demand
for energy-related work.
Daewoo Engineering & Construction Co
Ltd said in statement on Monday that it
won an order for the Mina Abdullahrefinery in Kuwait as part of a joint
venture with Hyundai Heavy Industries
Co Ltd and Fluor Corp.
The order is worth US$1.13 billion each
for the three companies, according to
Daewoo.
Samsung Engineering Co Ltd, in a
regulatory filing on Monday, said it got a
separate US$1.62 billion order for the
Mina Abdullah refinery as part of a joint
venture with Petrofac Ltd and Chicago
Bridge & Iron Company NVGS Engineering & Construction Corp
and unlisted SK Engineering &
Construction Co Ltd also said they got an
order for refinery work in Kuwait as part
of a joint venture with Japans JGC Corp.
The third order, for the Mina Al-Ahmadi
refinery, is worth around US$1.66 billion
for each of the three companies,
according to GS Engineering and SK
Engineering.
REUTERS, Apri l 14, 2014
Imports, notrefineries, to meetAfricas fuel needsAfricas dependency on fuel imports is
likely to grow as its refining projects
struggle to get off the ground, a Vitol
director told a Reuters Africa Summit.
Dozens of new refining projects have
been announced in Africa, but they are
unlikely to be built unless they are either
gigantic or with guaranteed crude supply
in a landlocked location.
NEWS IN BRIEF
8/11/2019 Downstream Monitor - MEA Week 15
16/22
Downstream Monitor MEA 16 April 2014, Week 15 page 16
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
Micro refineries in waterborne locations
are not a viable way to get a return on
capital. You have to go big, and today
big means a 300,000 to 500,000 barrel
per day complex refinery and US$5-$15
billion of capital, Chris Bake, director
of origination and investments, told
Reuters in a telephone interview. To
deploy that is challenging, he added.
Bake added that he expected one large
refinery to be built in West Africa but
that it could take five to seven years,
while new plants in east Africa were less
certain given strong competition from the
Middle East.
Vitol, the worlds top oil trader with over
US$300 billion in annual revenues, seeks
to meet African demand in competitionwith other traders such as Glencore and
Trafigura and with large Asian refiners.
Vitol estimates that Africas fuel demand
amounts to 3.71 million barrels per day
in 2014, worth about US$440 million a
day, based on ICE gasoil futures prices.
That is close to a 3 percent increase from
the 2013 estimate.
Bake said the most exciting market in
Africa was gasoil, with growth expected
to be in the high single digits as power
demand booms. Demand for liquefiedpetroleum gas will also rise quickly
across North Africa and Nigeria as
consumers spend more and move to
cities, he added.
A small number of refining projects in
landlocked locations could succeed,
possibly in Uganda, Chad or South
Sudan, Bake added, as they are sheltered
from competing supplies of giant Asian
refineries. Vitol is leading a consortium
to bid for a US$2.5 billion refinery in
Uganda. The winner is expected to be
announced in July. Vitol will also seek to
supply African countries with gas for
power production and is already working
to develop gas fields offshore Ghana to
supply its local market. Africa is a
power-hungry continent, and we are
looking at domestic gas opportunities,
said Chris Joly, director of exploration
and production, in the same interview.
He added that the firm, which pumps
around 10,000 barrels per day, would
look for exploration and production
opportunities that complement its
existing assets and trading contracts.
Vitol has invested in an African chain of
petrol service stations, Vivo Energy, in
partnership with Shell and Helios
Investments Partners. Vitol also has an
oil product storage terminal in Mombasa,
Kenya.
Were not doing upstream for the sake
of doing upstream. Its more about
integration with the wider Vitol
business, Joly said.
Unlike traders Glencore and Mercuria,
Vitol has held off bidding for Shells
assets in Nigeria, Africas top oil
producer, citing high entry costs and stiff
competition from local players, who have
access to low borrowing rates.
But Joly said Vitol would keep looking atopportunities.
Nigerias too important to ignore, so we
are taking a cautious and long-term view.
There will be opportunities down the
road. We are talking and looking, he
said. Vitol, a regular buyer of South
Sudans Dar grade crude, is also in talks
with the government there on oil
infrastructure projects, Bake said,
without giving details.
Like others, weve talked to the
government about ways to help improvethe infrastructure to give them
incremental security of supply. Were
still working on options with them.
REUTERS, Apri l 10, 2014
Ethiopian marketersays Africa needs torefine its oilEthiopias leading private oil marketer
plans to expand into neighbouring east
African economies and is interested in
part financing a refinery aftercommercial discoveries in the region.
Tadesse Tilahun, CEO of National Oil
Ethiopia, said untapped crude deposits in
Kenya and Uganda handed governments
and investors the opportunity to construct
a refinery able to compete with cheap
imports from India, the Gulf and beyond.
Doing so would help African countries
extract more value from their resources
and cut their import bills, Tadesse said.
Africas demand for refined products is
growing hugely because of its economic
growth. The crude findings are also
increasing. That is the opportunity,
Tadesse said in Addis Ababa as part of
the Reuters Africa Summit.
We want to (build) a refinery. We have
already discussed this in principle with
our shareholders, who are very much
committed.
National Oils (NOC) shareholders
include Saudi billionaire Mohammed
Hussein Al Amoudi, whose investment
portfolio in construction, gold, hotels and
energy has helped amass an estimated
fortune of over US$15 billion, according
to Forbes.
Tadesse said other private and public
investors would need to come on board.
Eastern Uganda has become the latestfrontier in the global hydrocarbon hunt
after gas finds off Tanzania and
Mozambique and oil discoveries in
Uganda and Kenya.
Even so, Sub-Saharan Africa faces
headwinds supplying more of its own
refined petroleum products. Regional
cooperation and funding for oil-related
infrastructure are proving slow, while
foreign oil refiners and traders are
flooding the US$80 billion market with
imports. Existing pipelines also tended torun to the coast, Tadesse said, either for
the export of crude or the import of
refined products from small-scale
refineries found near ports.
That has to change, Tadesse said.
Refineries are now needed inland so
that Africa can supply itself.
Tadesse acknowledged the price tag was
problematic for many African countries.
Oil production in Uganda has been
delayed in part due to a row between the
government and investors over the size -
and thus cost - of a refinery in the
country.
It would be in our own interest, for all
countries in this area, to have a common
refinery, a joint facility, where we can
take our own product, Tadesse said.
Kenya plans - but has made little
progress towards - a new US$2.8 billion
refinery on its northern coast. Industry
experts say Ugandan and Kenyan oil
exports could reach 500,000 barrels per
dayoil Tadesse would rather see stay
in the region.
NEWS IN BRIEF
8/11/2019 Downstream Monitor - MEA Week 15
17/22
8/11/2019 Downstream Monitor - MEA Week 15
18/22
Downstream Monitor MEA 16 April 2014, Week 15 page 18
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
Around the world, oil & gas, refining and
petrochemical companies are becoming
increasingly concerned by how the
development of unconventional resources
is changing the energy landscape. Our
business is facing new and
unprecedented challenges globally and
from all directions, warned Al-Mady.
Cheap and abundant resources have
been our primary competitive advantage.
Within five years, what used to be a
phenomenon known only to specialists,
what is now called drilling technologies,
brought an avalanche of unforeseen
reserves.
With forecasts predicting that the GCC
will enter into a new growth phase
characterised by massive capacityexpansions combined with significant
product diversification, there is an
imminent need to invest in the means that
ensure such projects remain competitive,
even in the face of the shale revolution.
That is of course, not to say that the GCC
has failed to innovate. With a likely gas
shortage approaching as early as 2015,
the regions petrochemicals companies
have certainly seized the opportunity to
innovate, albeit because of challenging
circumstances.As much as 34 million tons of additional
petrochemical capacity may come online
by 2018, but constraints in the supply of
ethane throughout the GCC have
encouraged companies to shift to the
utilisation of heavier feed-stocks such as
propane, butane and naphtha.
By 2020, approximately 35% of the
incremental feedstock for petrochemical
production will be derived from refining
operations. Within refinery streams,
naphtha will account for the largest
feedstock demand. Such a move has
come at a higher cost, but has also
produced a more balanced base
petrochemicals products mix. In turn this
has allowed for the production of new
sets of secondary and tertiary products.
The successful diversification of the
regions petrochemical product slate has
been heralded as one of the major
triumphs of innovation in the region. But
other factors, such as coals-to-chemicals
technology in China, have also meant
that the comparative cost advantages
once enjoyed by the Middle East are
fading in Eastern markets as well.
ARAB IAN OIL AND GAS, Apri l15, 2014
PIPELINES
Iraq hopes tocomplete pipeline toraise exports in 2014Iraqi Oil Minister Abdul Kareem Luaibi
said on Wednesday his country hoped to
complete construction of a 200 km (124
miles)oil pipeline to raise exports toTurkey to more than 1 million barrels per
day (bpd) this year.
We are building a pipeline in Iraq,
Luaibi was speaking to Reuters on the
sidelines of an oil and gas conference in
the Turkish capital Ankara. I believe the
daily oil flow will exceed one million
barrels a day when that line is completed.
I hope it happens this year.
REUTERS, Apri l 9, 2014
TERMINALS &SHIPPING
Mombasa oilterminal relocationKenyas government said Saturday it has
begun the process of relocating
Mombasa-based Kipevu oil terminal to
create additional capacity at a cost of
U.S. $120 million dollars. Kenya Ports
Authority chairman Danson Mungatana
said the new terminal, expected to be
completed in 2018 and will reduce fuel
pump prices in the East African nation.
Preliminary design of the new facility
has been undertaken and the relocationagreed upon by all stake holders. The
detailed design will cost 1.7 million
dollars while construction of the facility
will cost about 120 million dollars,said
Mungatana.
The KPA chairman who was speaking
during the official launch of the Kenya
Oil and Gas Association in Nairobi said
the new terminal will have capacity for
two large vessels each carrying 100,000
tons of crude oil. Kenyan oil firms have
previously cited the high cost of refinedpetroleum products to losses incurred as
a result of refining at the Kenya
Petroleum Refineries Limited (KPRL)
facility in Kipevu. Analysts say this will
enable the refinery to play a key role in
reducing the price of fuel in the East
African country to the benefit of
consumers affected by the high cost of
living.
CW, Ap ril 6, 2014
NEWS IN BRIEF
8/11/2019 Downstream Monitor - MEA Week 15
19/22
Downstream Monitor MEA 16 April 2014, Week 15 page 19
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
CONFERENCES
8/11/2019 Downstream Monitor - MEA Week 15
20/22
Downstream Monitor MEA 16 April 2014, Week 15 page 20
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
CONFERENCES
8/11/2019 Downstream Monitor - MEA Week 15
21/22
Downstream Monitor MEA 16 April 2014, Week 15 page 21
Copyright 2014 NewsBase Ltd.
www.newsbase.com Edited by Ian Simm
All rights reserved. No part of this publication may be reproduced, redistributed, or otherwise copied without the written permission of the authors. This includes internal distribution. All
reasonable endeavours have been used to ensure the accuracy of the information contained in this publication. However, no warranty is given to the accuracy of its contents
SPECIAL REPORT
8/11/2019 Downstream Monitor - MEA Week 15
22/22