Upload
herbert-payne
View
216
Download
5
Embed Size (px)
Citation preview
Dounreay
Nuclear and Chemical Land Contamination
Background
Site on north coast of Scotland set up in 1955 as UK’s centre of fast reactor development
Last reactor ceased operation in 1994
Fuel reprocessing ended in 1996 Fuel fabrication ended in 2004 Construction, demolition and
waste management on going One of the most complex
nuclear clean up challenges in the world
Dounreay Site Restoration Ltd
DSRL are the site licence company responsible for the closure programme of the site
Site is owned by the Nuclear Decommissioning Authority (NDA) who contract DRSL to manage the site
Main Environmental Problems
65m deep shaft containing intermediate level waste is contaminating some groundwater
Fragments of irradiated nuclear fuel were discharged into the sea during reprocessing in 1960s and 70s
18,000 cubic metres of radiologically contaminated land, and 28,000 cubic metres of chemically contaminated land
Large amount of highly active waste and intermediate level waste in storage
Large amount of uranium and plutonium still on site
Site is threatened by coastal erosion
Shaft
Vertical shaft built in 1950s to construct a low active effluent discharge tunnel
In 1958 authorisation given for the disposal of unconditioned intermediate level radioactive wastes
Hydrogen explosion in the shaft in 1977 caused severe damage to superstructure - material consignments to the shaft ceased
Decision to empty shaft made in 1998
Shaft Clean-up First phase of decommissioning
completed in 2008 – Hydraulic Isolation Grouting of rock fissures reducing flow of
groundwater through shaft 400 boreholes drilled into rock and fine grout
injected under pressure Water volume reduced from 350m3/day to
12.7m3/day
Water level in shaft maintained below sea level by daily pumping of water
Reduces amount of water that can flow through the shaft and contaminate the rock on the seaward side
After grouting volume of pumped water reduced from 15m3/day to 1.3m3/day
Success of Hydraulic Isolation
Highly Commended at Ground Engineering Awards 2009
Received Ground Engineering Award and Exceptional Performance Award at the Construction News Specialists Awards 2009
Received Civil Engineering Award at British Construction Industry Awards 2009
“an extraordinarily innovative and complex project delivered with extreme care, confidence and total team collaboration. “
Future Shaft Clean-up Plans
Next stage involves removal, treatment and storage of waste
Concept designs for waste retrieval, treatment and storage facilities
In March 2010, DSRL announced a delay to the construction of these facilities
Retrieval of the waste is unique among nuclear decommissioning around the world
End State of Shaft
Initial Options: Near Field (1m radius):
Natural attenuation; removal of rock; chemical clean; passive out-diffusion; surface seal; local back-flush; local chemical back-flush
Far Field (1-300m radius): Natural attenuation; removal of
rock; flushing with water; flushing with chemicals; in-situ immobilisation
Decision will be assessed by BPEO process
End State of Site
“a restored site, with early release of land once decommissioning was complete “
Some contaminated ground will be remediated by the end of decommissioning in 2025-32
Other contamination will be left to decay naturally in the ground through to 2300
Estimated cost of decommissioning - £2.6bn
Thank you for listening
This case study highlights the need for safe nuclear waste management policies particularly for the new generation of nuclear power stations.