34
OPERATIONS MANAGEMENT DONNER COMPANY SUBMITTED TO PROF. JANAT SHAH PREPARED BY: ABHISHEK PRASAD 0511147 BURJOR DADACHANJI 0511160 ROHIT GOEL 0511178 VISHAL AGGRAWAL 0511196 JAYARAMA HOLLA 0512005

Donner Report

Embed Size (px)

Citation preview

Page 1: Donner Report

   

OPERATIONS MANAGEMENT

DONNER COMPANY

SUBMITTED TO

PROF. JANAT SHAH

PREPARED BY:

ABHISHEK PRASAD 0511147

BURJOR DADACHANJI 0511160

ROHIT GOEL 0511178

VISHAL AGGRAWAL 0511196

JAYARAMA HOLLA 0512005

Page 2: Donner Report

Donner Company

TABLE OF CONTENTS

INTRODUCTION....................................................................................................................3

CASE FACTS........................................................................................................................3

PROBLEMS AND REASONS..................................................................................................8

CASE ANALYSIS.................................................................................................................11

DATA ANALYSIS............................................................................................................13

RECOMMENDATIONS.........................................................................................................17

APPENDIX.......................................................................................................................21

Exhibit A.....................................................................................................................22

Exhibit B.....................................................................................................................24

Group 07 2

Page 3: Donner Report

Donner Company

INTRODUCTION

The Donner Company manufactures printed circuit boards for a variety

of electronics manufacturers based on the specifications provided by

them. It started operations in 1985, and is run by engineers who have

substantial experience in the electronics industry.

There are 750 printed circuit board manufacturers in the US market,

classified as captive or contract manufacturers. The industry has

shown phenomenal growth as electronics increasingly becomes a vital

part of all aspects of life.

The Donner Company is believed to be more adept than its

competitors in creating prototypes of new designs and

anticipating/resolving any problems that might be associated with

these designs.

CASE FACTS

Manufacturing Process Flow

Donner produces “solder mark over bare copper” (SMOBC) boards.

This process has three broad stages:

1. Preparation Stage

Master artwork received from the customer –

used to produce negative image

Group 07 3

Page 4: Donner Report

Donner Company

Individual image repeated to maximize panel

utilization (panel size 12” by 18”) – typically 8 images per

panel

Double sided copper-clad glass epoxy sheets –

36” by 48” sheared into 12” by 18” panels

Location holes punched – used in aligning,

drilling, imaging and routing

2. Image Transfer Stage

Approximately 500 holes per circuit board –

drilled manually or using CNC drill (worth $80000) – drilling

process needs the operator in both cases

Panel is processed through copper immersion

bath – metallization – deposits thin layer of copper on

drilled holes

Panels are washed, scrubbed and coated with

photo-resist (DFPR)

Film of the artwork is placed on the panel and

it is exposed to UV light

DFPR machines wash away un-exposed DFPR

leaving conducting copper surface bare where conductors

are desired

Conductors are electroplated – bare areas and

metallized holes are covered by an additional layer of

copper

Exposed DFPR – stripped off the panel – un-

electroplated copper is etched off – circuit pattern

protected by tin coating

Tin coating chemically stripped off – leaving

the desired circuit pattern on both sides of the board

Group 07 4

Page 5: Donner Report

Donner Company

3. Fabrication Stage

Protective epoxy coating over circuit traces – solder-mask

silk-screening

Through holes – covered with solder

Individual boards separated from panel – reduced to

desired size and shape using the CNC or a punch press

Boards are inspected, tested, packaged and shipped – one

senior Donner employee assigned to this final step

Figure 1: Manufacturing Process Flow

Group 07 5

Page 6: Donner Report

Donner Company

The normal flow described above could be modified based on specific

requirements of customers. Sometimes additional steps may also be

involved.

Special racks are used between process operations to hold up to 20

panels in order to reduce handling damage

Supervision Process

Supervision responsibilities are shared by three people:

Diane Schnabs – expediter

Bruce Altmeyer – design engineer

David Flaherty – shop supervisor

Figure 2: Flow of Information

Group 07 6

Page 7: Donner Report

Donner Company

The expediter:

Keep track of orders in process. Investigated delays, fixed problems,

kept customers informed. Took charge of rush orders.

The design engineer:

Inspect artwork, find design errors, and create processing strategy.

The shop supervisor:

In charge of manufacturing, supervised 22 production employees,

worked with the blue-print.

Order Processing

Figure 3: Order Processing Flow

Key steps involved:

Group 07 7

Page 8: Donner Report

Donner Company

Estimating labor and material costs – preparing a bid for the

customer

Orders less than 1000 boards – 3 weeks, larger orders – 5 weeks

Material specification and factory order created

Supervisor receives the blueprint (4 days after the bid is

finalized)

Scheduling decisions, labor estimates, made after material

arrived

Ticketing used to track orders as they moved through processing

Facilities and Layout

Machines installed prudently to ensure longevity and isolation of

corrosive elements

No outside capital – most of the companies funds invested

Full utilization of space in existing plant

PROBLEMS AND REASONS

Problem Statement - Difficulty in manufacturing two products with

different production requirements in a single facility.

Product Related

Special boards require additional steps

Company concentrating more on small order sizes and has a lower

delivery time (3 weeks) vis-à-vis its competitor. Small order delivery

cannot be delayed to prevent revenue target constraint

Group 07 8

Page 9: Donner Report

Donner Company

Customer Related

Normal work flows interrupted by several customer orders each

week; all having specific requirements

Delays due to artwork modifications to be received from the

customer

1 to 9 design changes a week – One fourth of delays caused by

these requests from the customers. Also involve rework in case they

want to revert to original design

Production Related

Workflow interrupted 6 to 12 times per day

1. To secure more work from the upstream process

2. To seek advice on a problem (Should assistant manufacturing

supervisors spend more than 10% of their time instructing

and monitoring employees?)

3. Average delay in shipping completed orders is 5.2 days (As

calculated further down in the report )

Daily at least 2 – 3 slow orders (non-rush orders) delayed and need

to be expedited

Around 3 rush orders a week

Rework required in rush orders needing rework in one or two

operations

Estimated order completion time is a standard rate and not based

on capacity utilization as of time order received

No raw material storage maintained, and procurement initiated with

purchasing agent only after order received. (Materials received

same day or next day for rush orders. Otherwise it took “several”

days)

Group 07 9

Page 10: Donner Report

Donner Company

Most orders reached manufacturing only 4 days after the bid had

been accepted

Scheduling decision takes place only after raw materials arrive

Prioritization of orders based on work in process at critical points

and the manufacturing manager’s assessment of the sale’s

possibilities of these orders being held up

Production bottlenecks shifting based on processes utilized, order

sizes and differences in designs for different client orders. No

pattern available to forecast where the pile-up would take place

Movement of resources from a particular process to meet

bottlenecks, which are occupied by the time the order, is expedited

to that original process

Quality Related

Customer rejection rates up from 1% to 3%

Returns due to

a) Damaged or out of tolerance (10%)

b) Process missed out (90%)

Leading to reprocessing and reshipping costs

Method improvements not implemented due to output pressure

No overall coordination on increasing efficiency of process as a

whole

Quality inspection standards seem to be too stringent

Quality checks being duplicated (both at beginning and end) as well

as informal worker examination

Pre-shipment rejection rate = 7% (1% total losses & 6% process

missed)

Shipments are 9 days late on average

Layout related

Group 07 10

Page 11: Donner Report

Donner Company

Production layout with a view to:

1. Minimized installation costs

2. Preserved equipment life

3. Isolated the diverse operating environments

Production facilities have been designed primarily around process

layout

Constant interruptions due to need for walking from one section to

another

Group 07 11

Page 12: Donner Report

Donner Company

CASE ANALYSIS

Analysis of September Standard Production data

On an average 3 orders of size 96 are processed per day

Manpower utilization

No. of

peopl

e

Utilizatio

n Hrs

Asst.

Supervisor 4 0.9 576

New Workers 8 0.5 640

Others 10 1

160

0

Total 22

281

6

Capacity utilization

Refer to exhibit A for the details.

Overall capacity utilization is 56%.

Bottleneck processes are

Drilling – Manual (4 in number)

– Capacity utilization of 104%

– Cycle time: 80 min/panel

Drilling CNC

– Capacity utilization of 127%

– Cycle time: 16 min/panel

(Usage is more than 8Hrs/day)

Group 07 12

Page 13: Donner Report

Donner Company

In addition electroplating has a very high capacity utilization of

82%.

It can also be found that on an average 20 orders are being reworked/

month at an average order size of 360 boards. This totals to an

average time spent in rework = 379 hrs.

Also 660 hrs are spent in labor movement and 24 hrs is wasted in

plating operation. An average of 139.2 hrs are lost when rush orders (3

per week) are loaded on to the process.

Wait time analysis (Based on data for September)

Average Order Size 1000 boards/order

Average delay 8 days

Average Order processing time 4 weeks

(1000 boards/order)

Expected Time in the system (Ws) 36 days (7*4+8)

Total processing time 1531.7 Hrs

(5761 boards)

Average processing time 3.4 Days* (266 Hrs)

(For 1000 boards)

Lead time before start of manufacturing 7 days

(4 days for the order to reach the shop floor and 3 days for procuring

raw material)

Average delay in shipping (per Order) ** 5.2 days

Expected time waiting in the Line (Wq) 20.4 days (36 - 3.4 – 7

– 5.2)

*Elapsed time (in days)

Group 07 13

Page 14: Donner Report

Donner Company

Total available man hours 2816 Hrs

(Per month)

Total available man hours 140.8 Hrs

(Per Day)

Capacity Utilization 56%

Utilized Man Hours (per day) 78.85 Hrs.

Average processing time 3.4 days (266/78.85)

**Average orders shipped /day = 288. No. of orders shipped per day is

calculated using exhibit no. 5. Average delay in shipping is calculated

by taking the weighted average of the individual order delays.

DATA ANALYSIS

Standard labor time calculations

Order size 1

Group 07 14

Page 15: Donner Report

Donner Company

Group 07 15

 

Standard

Production time Total Standard Production time

  Set up Run Set up Run Min Hrs

Artwork Generation 29 0

29 -

29.00

0.48

Inspect & Shear 20 0.5

20

0.06

20.06

0.33

Punch Tooling

Holes 10 0.5

10

0.06

10.06

0.17

             

Drill – Manual 15 0.08

15

40.00

55.00

0.92

Drill – CNC 240 0.004 - - - -

Materialization 10 0.75

10

0.09

10.09

0.17

DFPR            

Panel Prep 5 0.2

5

0.03

5.03

0.08

Laminate & Expose 20 2

20

0.25

20.25

0.34

Develop 20 0.2

20

0.03

20.03

0.33

Electroplate 25 8.5

25

1.06

26.06

0.43

Strip DFPR 5 0.2

5

0.03

5.03

0.08

Etch & Tin Strip 10 0.2

10

0.03

10.03

0.17

             

Soldermask 45 1.5

45

0.19

45.19

0.75

Solder dip 30 0.5

30

0.06

30.06

0.50

Profile – punch

press 50 1

50

1.00

51.00

0.85

Profile - CNC router 150 0.5 - - - -

Inspect, Test, pack 45 1.5

45

1.50

46.50

0.78

Page 16: Donner Report

Donner Company

Total: 6.39 hours

Order Size 8 boards

 

Standard

Production time Total Standard Production time

  Set up Run Set up Run Min Hrs

Artwork Generation 29 0

29 - 29.00

0.48

Inspect & Shear 20 0.5

20 0.50 20.50

0.34

Punch Tooling

Holes 10 0.5

10 0.50 10.50

0.18

Drill – Manual 15 0.08

15 320.00

335.00

5.58

Drill – CNC 240 0.004 - - - -

Materialization 10 0.75

10 0.75 10.75

0.18

DFPR

Panel Prep 5 0.2

5 0.20 5.20

0.09

Laminate & Expose 20 2

20 2.00 22.00

0.37

Develop 20 0.2

20 0.20 20.20

0.34

Electroplate 25 8.5

25 8.50 33.50

0.56

Strip DFPR 5 0.2

5 0.20 5.20

0.09

Etch & Tin Strip 10 0.2

10 0.20 10.20

0.17

Soldermask 45 1.5

45 1.50 46.50

0.78

Solder dip 30 0.5 0.50 30.50

Group 07 16

Page 17: Donner Report

Donner Company

 

Standard

Production time Total Standard Production time

  Set up Run Set up Run Min Hrs

30 0.51

Profile - punch

press 50 1

50 8.00 58.00

0.97

Profile - CNC router 150 0.5

- - - -

Inspect, Test, pack 45 1.5

45 12.00 57.00

0.95

Total: 11.57 hours

Group 07 17

Page 18: Donner Report

Donner Company

Order Size 200

 

Standard

Production time Total Standard Production time

  Set up Run Set up Run Min Hrs

Artwork Generation 29 0

29 - 29.00

0.48

Inspect & Shear 20 0.5

20 12.50 32.50

0.54

Punch Tooling

Holes 10 0.5

10 12.50 22.50

0.38

Drill – Manual 15 0.08

15 8,000.00

8,015.00

133.58

Drill – CNC 240 0.004

- - - -

Materialization 10 0.75

10 18.75 28.75

0.48

DFPR

Panel Prep 5 0.2

5 5.00 10.00

0.17

Laminate & Expose 20 2

20 50.00 70.00

1.17

Develop 20 0.2

20 5.00 25.00

0.42

Electroplate 25 8.5

25 212.50

237.50

3.96

Strip DFPR 5 0.2

5 5.00 10.00

0.17

Etch & Tin Strip 10 0.2

10 5.00 15.00

0.25

Soldermask 45 1.5

45 37.50 82.50

1.38

Solder dip 30 0.5 12.50 42.50

Group 07 18

Page 19: Donner Report

Donner Company

 

Standard

Production time Total Standard Production time

  Set up Run Set up Run Min Hrs

30 0.71

Profile - punch

press 50 1

50 200.00

250.00

4.17

Profile - CNC router 150 0.5

- - - -

Inspect, Test, pack 45 1.5

45 300.00

345.00

5.75

Total Time: 153.59 hours – using Manual Drill and punch press

Total Time: 30.67 hours - using CNC drill and CNC router

RECOMMENDATIONS

Change in job scheduling

At present all the panels that belong to an order are processed

completely in a particular process before moving on to the next

process. This results in WIP buildup at each stage causing spikes in the

arrival pattern of job from the previous process. To smoothen this it is

recommended that the panels that have been processed should move

on to the next process without waiting for the entire order to be

processed. The timing worked out for an order of size 100 shows that

the existing method takes 20.87 hours for complete processing. When

the panels are allowed to move to the next operation then the process

time reduces to 11.32+3.2 = 14.52 hours. The time saved is 6.35

hours. In September on an average, there were 57 orders of size 100

and the total reduction in the processing time would have been 362

hours. That implies 25 more orders of size 100 could have been

Group 07 19

Page 20: Donner Report

Donner Company

processed with the same capacity, an improvement of 58%. This figure

of 58% has been calculated assuming that there is no interruption in

the flow once an order is loaded for processing.

A decrease in the throughput time from 20.87 hours to 14.52 hours

would also reduce, on an average, the number of times a loaded job is

removed to make way for the rush order, resulting in the loss of setup

time.

Change Layout of the machine assembly

There is lot of scope to reduce or eliminate the time wasted due to

labor and material movement between operations. At present the

machines have been arranged in a job shop layout. Due to the nature

of the processes involved there are layout constraints such as

processes that release acid vapors are located away from machining

operations to prevent corrosion of machines and machining operations

that produce dust are separated from processes requiring pure

atmosphere (imaging, plating and etching). A line-flow or hybrid layout

would help in cutting down the material and labor movement time. But

this would require installation of additional technology, such air

ventilation systems or air screens, to isolate the atmospheric air of

plating and etching processes.

With an extra 1800-sq. feet of factory space available in the near

future, it was considered that the company could look to develop

additional production facility to cater to rush and small volume orders.

However, the cost involved in setting up a new production facility may

be very high. Also, the utilization of certain processes would be very

low, thus making it uneconomical to duplicate such facilities.

Group 07 20

Page 21: Donner Report

Donner Company

Reducing Process Bottleneck

Drilling is the critical process. Installation of a second CNC machine

would reduce the machining time from 203 hours to 119 hours

(September production figures) but this may require a huge capital

expenditure. Alternatively, capacity of the manual drilling process can

be increased by adding 4 machines. This would result in machining

time reduction from 662 hours to 331 hours. The additional

requirement of 4 units of labor can be met by re-allocation of under-

utilized manpower from other processes. Improving capacity of the

drilling process would result in a reduction of the large average waiting

time (~20 days) before the order is scheduled on the production line.

Improve Inventory Planning

It has been acknowledged that scheduling has been delayed till raw

materials are received from the vendor. It may not be possible to stock

all raw materials, but key items should be stocked. Especially those

related to the start of the manufacturing process. Time may also be

saved in case of larger orders which use common core materials, if

Manufacturing is informed upfront and the procurement order initiated

with a return policy with the vendor.

Changing Information Transmission

The orders are taking almost 4 days to reach manufacturing after the

bid is accepted. This means that there are bottlenecks in information

transmission which need to be resolved by the company.

Change in Quality Control Mechanism

Group 07 21

Page 22: Donner Report

Donner Company

Quality checks should focus more on operations required by a client

being missed out rather than on actual damages, scratched PCB’s etc.

There needs to also be a separate personnel assigned to Quality

Control to reduce rework caused by processing errors. This would also

reduce the duplication of quality checks in the current process. On an

average, there is an additional load of 20 orders of average size 360

per month.

Group 07 22

Page 23: Donner Report

Donner Company

APPENDIX

Group 07 23

Page 24: Donner Report

Donner Company

Exhibit A

 

Standard Production

TimeSeptember's Production September's Total Standard Production

Hrs Required Per day

Resources required per day

Resources allocated

Capacity Utilization

 Set up Run Order Board

Set up Run Min Hrs        

Artwork Generation 29 0 50 832

1,450 -

1,450.00

24.17

1.21 0.15 1 15%

Inspect & Shear 20 0.5 60 6,001

1,200

375.07

1,575.07

26.25

1.31 0.16 1 16%

Punch Tooling Holes 10 0.5 60

6,001

600

375.07

975.07

16.25

0.81 0.10 1 10%

                         

Drill - Manual 15 0.08 51 975

765

39,000.00

39,765.00

662.75

33.14 4.14 4 104%

Drill - CNC 240 0.004 9 5,026

2,160

10,052.08

12,212.08

203.53

10.18 1.27 1 127%

Materialization 10 0.75 60 6,001

600

562.60

1,162.60

19.38

0.97 0.12 1 12%

DFPR                        

Panel Prep 5 0.2 60 6,001

300

150.03

450.03

7.50

0.38 0.05 1 5%

Laminate & Expose 20 2 60 6,001

1,200

1,500.26

2,700.26

45.00

2.25 0.28 1 28%

Develop 20 0.2 60 6,001

1,200

150.03

1,350.03

22.50

1.13 0.14 1 14%

Electroplate 25 8.5 60 6,001

1,500

6,376.11

7,876.11

131.27

6.56 0.82 1 82%

Strip DFPR 5 0.2 60 6,001

300

150.03

450.03

7.50

0.38 0.05 1 5%

Etch & Tin Strip 10 0.2 60 6,001

600

150.03

750.03

12.50

0.63 0.08 1 8%

Group 07 24

Page 25: Donner Report

Donner Company

 

Standard Production

TimeSeptember's Production September's Total Standard Production

Hrs Required Per day

Resources required per day

Resources allocated

Capacity Utilization

 Set up Run Order Board

Set up Run Min Hrs        

                                                  

Soldermask 45 1.5 55 5,983

2,475

1,121.88

3,596.88

59.95

3.00 0.37 1 37%

Solder dip 30 0.5 55 5,983

1,650

373.96

2,023.96

33.73

1.69 0.21 1 21%

Profile - punch press 50 1 47

1,284

2,350

1,284.38

3,634.38

60.57

3.03 0.38 1 38%

Profile - CNC router 150 0.5 6 4,511

900

2,255.73

3,155.73

52.60

2.63 0.33 1 33%

Inspect, Test, pack 45 1.5 60 6,001

2,700

9,001.56

11,701.56

195.03

9.75 1.22 2 61%

Total 1,580.48

79.02 21

Average 3 orders per dayAverage 288 Boards per day

Group 07 25

Page 26: Donner Report

Donner Company

Exhibit B

DateDaily Order value

Cumulative order value

No of boards shipped

No of boards

produced

No of boards pending shipment

Sales 124800

0 237 237No of

boards5761

1 11118 11118 513 288 12Value per board $

21.66291

4 -1188 9930 0 288 3005 4057 13987 187 288 4006 1696 15683 78 288 6107 2226 17909 103 288 7958 8430 26339 389 288 694

11 2395 28734 111 288 872s12 -684 28050 0 288 116013 2560 30610 118 288 133014 5926 36536 274 288 134415 -147 36389 0 288 163218 3952 40341 182 288 173819 13216 53557 610 288 141620 10070 63627 465 288 123921 5561 69188 257 288 127022 2275 71463 105 288 145325 176 71639 8 288 173326 -1327 70312 0 288 202127 -7975 62337 0 288 230928 17939 80276 828 288 176929 44560 124836 2057 288 0

Group 07 26