Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Minutes of the 85th
Meeting of PCSC held on 31st July, 2019 Page 1
SOUTHERN REGIONAL POWER COMMITTEE BENGALURU
Minutes of the 85th Meeting of Protection Coordination Sub-Committee (PCSC – 85) of SRPC held on 31st July, 2019
1. Introduction
The 85th meeting of Protection Coordination Sub-Committee (PCSC-85) of SRPC was held on 31st July, 2019 at SRPC Secretariat, Bengaluru. The list of participants is enclosed at Annexure-I. MS (I/c) SRPC welcomed Members and Participants to the meeting and briefed them on the following points: Apprised PCSC forum that Protection Audit of 400/220/132kV Jamalamadugu SS of APTRANSCO was completed successfully during 17-18th July 2019.
The protection Management System (PMS) project is in the final phase of completion and requested all constituents to extend all support in this regard.
Informed constituents that Nominations have been obtained from majority constituents for Conduction of Protection Audit of various 220 kV & above Stations in Southern Region. He requested all constituents to suggest modifications in Protection Audit formats (used for Protection Audit) to modify the same at par with present practices.
2. Confirmation of Minutes of 84th PCSC meeting held on 26th - 27th July 2019
The minutes of the 84th meeting of PCSC were circulated vide SRPC letter No. SRPC/SE-III/ PCSC-84/ 2019/4335- 4371 dated 11.07.2019. No comments had been received from any of the Constituents. The minutes of the 84th meeting of PCSC were confirmed.
3. Details of Grid Disturbances (GD’s), Grid Incidents (GI’s), and Line Trippings
due to Auto- Reclose (A/R) failure/ non-operation & PLCC mal-operation
The trippings due to GD’s, GI’s, A/R failure/ non-operation, and PLCC mal-operation that had occurred during May, 2019 – July, 2019 were discussed in the Meeting. The deliberations and recommendations of the PCSC forum are enclosed at Annexure–II for needful action please. The details of the tripping events including relevant PMU plots presented by SRLDC in the meeting are also enclosed at Annexure-III for kind reference.
4. Status of implementation of pending PCSC Recommendations (P-REC)
The status of implementation of pending PCSC recommendations was discussed in the meeting. The updated status of the same as on 19.08.2019 is enclosed at Annexure–IV. The Constituents were asked to take steps to comply with the same, and requested to submit the status of their compliance latest by 28.08.2019.
5. Remedial measures/ Action taken for the tripping incidents of the transmission
elements under forced outage (PRM)
The tripping incidents of the transmission elements under forced outage for which the constituents have to furnish remedial measures taken, were circulated via mail dated 01.08.2019 (Annexure-V). The Constituents were requested to take appropriate action and
Minutes of the 85th
Meeting of PCSC held on 31st July, 2019 Page 2
furnish specific remedial measures/action taken covering one or the other items from the following indicative list in time so as to forward the same to Central Electricity Authority: Brief details of line patrolling carried out (with tower location) Brief details of RoW maintenance (by proper Tree-cutting) resorted to De-capped insulators replacement DC earth fault removal PLCC cards replacement Relay settings modification Steps taken to put A/R or CB into service after they have been locked-out Faulty equipment replacement Reference to OEM in case of equipment failure Brief Details of tests carried out to ascertain the healthiness of various equipment (Power Transformer/ Reactors/ Surge Arrestors/ Circuit Breakers/ CT's/ PT's/CVT's) like Insulation Resistance (IR) test, Winding Resistance test, Capacitance test, Tan delta test, DGA test, Leakage current test, CRM/ DCRM test, etc. Any other appropriate remedial measure It was observed that many utilities default furnishing of remedial measures for tripping. It is requested to take prompt and definite measures and ensure that Remedial measures are intimated on regular basis. 6. Certificate on Healthiness of Batteries
As per MoP/ CEA direction given in pursuant to recommendations of the Enquiry Committee (NEW Grid Disturbance on 30th & 31st July, 2012), RPC’s are required to obtain from their respective Constituents a monthly certificate for healthiness of batteries installed at 220 KV & above voltage level Substations (for power supply to Relays, RTUs and PLCC equipment) and furnish the same to CEA/ MoP. With reference to above, the Constituents were requested to submit the certificate on healthiness of batteries on monthly basis (i.e. status for a month shall be sent by the 7th day of the following month) to SRPC as per the format given below:
Sl. No.
Station Application Battery Battery Charger Remarks
Station Name
Code
Type
(PS/ SS)
Protection/
Communication
Details
Status (Healthy/ Unhealthy)
Details
Status (Healthy/ Unhealthy)
Brief Details of unhealthy battery banks and/ or DC leakage along with proposed time-lines for rectifying the same shall be mentioned.
1 Station-A
Protection (Bank-1)
Protection (Bank-2)
Communication (Bank-1)
Communication (Bank-2)
2 Station-B
…
… … …
Note: 1. Code is the short name of the Station 2. PS – Power Station; SS – Substation
The sought status for the month of June, 2019 had been received from all constituents.
Minutes of the 85th
Meeting of PCSC held on 31st July, 2019 Page 3
7. General Guidelines regarding Line Differential Protection for transmission
lines
The draft protection standards prepared by national Reliability Council for electricity mentions reliability criterions for transmission line having voltages at 220kV and above as:
“High speed Duplicated Main Protection (Main-I and Main-II) shall be provided and at least one of them being carrier aided non-switched four zone distance protection. The other protection may be a phase segregated current differential (this may require digital communication) or a carrier aided non-switched distance protection. Wherever Optical Ground Wire (OPGW) or separate optic fibre laid for the Communication is available, Main-I and Main-II protection shall be the line differential protection with distance protection as backup (built-in Main relay or standalone). For very short line (less than 10 km), line differential protection with distance protection as backup (built-in Main relay or standalone) shall be provided mandatorily as Main-I and Main-II). “
The general guidelines to be followed for Line Differential Protection was discussed in the meeting. During the discussion, SR constituents had brought out the following facts with regard to Line Protection. Transmission lines which are the most vital link in power transmission run through open atmosphere and the probability of occurring faults in them is very high compared to any other power system equipment. Operation of a standard Protection system in the event of fault is envisaged not only to selectively isolate the faulty element but also to maintain reliability of supply in the system. The capability of zone- segregated distance protection in achieving the same is a well-established fact and hence is being used in protection of transmission lines.
But when the length of protected transmission line is short (less than 10km) due to the limitations imposed in accurate setting of Zone -1 (primary zone of distance protection) by R/X value of relay, distance protection is seen to overreach for a fault on adjacent transmission line and cause unwarranted tripping. Line differential protection devoid of such overreach issues is important under such circumstances. Wherever Line differential protection is to be used as main protection (Main-1 and Main-II), distance protection has to be invariably provided to cater to function as back up protection for adjacent transmission line.
SR constituents were of the opinion that Line differential protection is required as Main protection only in case of short length of transmission line. Also in radial single circuit line less than 10km, distance protection will function reliably without any overreach. Line differential protection not only mandates laying of separate fibre optic, but is also much expensive compared to distance protection.
Hence, the guidelines for Line Differential Protection for transmission lines having voltages at 220kV and above recommended by PCSC-85 and communicated to NPC vide SRPC letter dated 01.08.2019 are:
“High speed Duplicated Main Protection (Main-I and Main-II) shall be provided using carrier aided non-switched four zone distance protection.
For very short line (10 km or shorter), except radial single circuit line, phase segregated current differential protection (this may require digital communication) with distance protection as backup (built-in Main relay or standalone) shall be provided mandatorily in Main-I and Main-II.
Wherever Optical Ground Wire (OPGW) or separate optic fibre laid for the Communication is available, Main-I and Main-II protection may be line differential protection with distance
Minutes of the 85th
Meeting of PCSC held on 31st July, 2019 Page 4
protection as backup (built in Main relay or standalone).
Whenever differential protection is provided it should be provided both in Main-I and Main-II otherwise it will not serve the intended purpose.
However, in all Critical links recommended by PCSC forum of RPC (to be decided on case to case basis), utility shall provide line differential protection irrespective of length of line.”
For transmission lines having voltages at 132 kV and below, the general protection guidelines suggested by National Reliability Council for electricity are:
“There should be at least one carrier aided non-switched four zone distance protection scheme. In addition to this, another non-switched/switched distance scheme or directional over current and earth fault relays should be provided as back up.”
Providing Line Differential Protection for these lines shall be at the discretion of utility. 8. Status regarding Protection Management System (PMS) project
The Protection Management System Project (PMS) for Southern Region implemented by M/s PRDC is nearing completion. During the review meeting held on 24.06.2019, PRDC demonstrated the following features of PSCT. Load flow analysis, Fault simulation of Renewable generators modelled using the actual
field data. Unified Power Flow controller block developed for use in PSCT modelling was
demonstrated on IEEE 6 bus system along-with the voltage and Power flow control capability of UPFCs on the test system.
Functioning of 3 winding phase shifting transformer modelled as available at KTPS station of TSGENCO.
Improvement done in MVAR compensation functionality of PSCT. Provision for globally changing voltage and location of MVAR compensation has been
made, accordingly the software calculates the amount of compensation required. Transient stability analysis of Renewable generators and plotting of related curves.
Apart from the above PRDC also submitted the Protection SLDs of all Substations visited during 2nd Phase of data collection in January 2019. The same has been circulated among constituents for verification. PRDC also submitted statewise excel sheet containing element information of all elements modelled in SR MDB case vide mail dated 26.06.2019. As decided by Monitoring committee, letter regarding “Resolution of Issues pertaining to PMS
Project under Milestone-5 and Milestone-9” was addressed to PRDC. PRDC had submitted their
action plan regarding pending activities of Milestone 5, 7, 9 & 10 vide reply dated 4th
July 2019.
Further SRPC had sought time extension for PMS project from PSDF vide SRPC letter dated 22.07.2019. The constituents were requested to inform the network updates along-with the supporting
documents through DMNS application. The updated version of PSCT software, PSCT manual, PSCT bus breaker model (PSCT case file) for SR region and excel sheet containing statewise element details have been uploaded in the ftp link provided by PRDC to SR constituents. Constituents were requested to make use of the same by downloading from the ftp link.
9. Over Voltage (OVR) Grading
New Over Voltage Relay (OVR) Gradings for 400 kV and 765 kV Transmission Lines of Southern
Minutes of the 85th
Meeting of PCSC held on 31st July, 2019 Page 5
Region had been issued vide SRPC letter No. SRPC/SE-III/OVR/2019/4074-4107 dated 03.07.2019. New gradings had been issued only for lines with configuration changes, for remaining lines previous OVR gradings shall prevail. Confirmation with respect to implementation of the same have been received from following utilities:
APGENCO (Thermal & Hydel), NTPC (RMGDM), CEPL, NTPL, APTRANSCO and KPTCL.
All the remaining constituents were requested to take steps to implement the new OVR gradings provided, with immediate effect and inform confirmation in this regard urgently.
APTRANSCO and KPTCL informed that configuration changes in their network. SRPC shall be providing revised OVR gradings for the substations with configuration changes.
10. Maintenance & Support (AMC) renewal of PSSE Licenses
In 2012, POWERGRID had coordinated one-time capacity building exercise for various stakeholders, under which 35 No. of PSSE Licenses were distributed among SR utilities. The maintenance and support for supplied licenses was for a period of 6 years, which had ended on 30th November 2018. The communication regarding renewal of the maintenance and support for the above Licenses received from M/s Seimens and Budgetary Offer had been communicated to constituents vide mail dated 12.06.2019 and 14.06.2019 respectively.
Meanwhile SRLDC had informed that the matter is being pursued by SRLDC in association with NLDC. Hence the matter would be further coordinated by SRLDC. 11. Nominations of Nodal Officers for Conduction of Protection Audit of various 220
kV & above Stations in Southern Region
As per the discussions of PCSC-80 conduction of protection audit of various 220 kV & above Stations in Southern Region was approved in 35th SRPC meeting. Nominations in this regard were sought from all Utilities vide SRPC letter No. SRPC/SE-III/ PA/ 2019/3589-3618 dated 19.06.2019. Based on consolidation of responses received in this regard nominations have been received from all constituents except NLCIL. NLCIL was requested to urgently furnish the nomination for charting the schedule for audit.
12. Instances of SPS Operation
Based on the information furnished by SRLDC, it is informed that the following SPS operations took place in SR during June 2019:
Sl. No. Date
Time, hrs
Reason Actual Load Relief obatined, MW
TN KA TS
AP KL
Total
1
05.06.2019
18:53
Talcher- Kolar SPS: HVDC Talcher-Kolar Pole-1 tripped. SPS trip signal-1 operated since power loss was more than 500MW but less than 1000MW.
200 35
0 -
15
3 -
703
2 05.06.201
9 19:01
Talcher- Kolar SPS: HVDC Talcher - Kolar Pole-2 tripped. SPS trip signal-1 did not operate since power loss after pole tripping was less than
-- -- --
-- --
--
Minutes of the 85th
Meeting of PCSC held on 31st July, 2019 Page 6
500MW.
3 08.06.2019
12:10
Talcher- Kolar SPS: HVDC Talcher-Kolar Pole-1 tripped. SPS Trip Signal-1 operated since power loss was more than 500 MW and less than 1000 MW.
276 35
0 -
21
9 -
845
4 12.06.201
9 12:24
Talcher- Kolar SPS: HVDC talcher-Kolar Pole-2 tripped. Since power loss immediately after tripping of pole-2 was around 400 MW, hence SPS did not operate (power loss <500MW).
-- -- --
-- --
--
5
04.06.2019 11:36
SPS at Kudankulam Nuclear Power Station Unit#1: KKNPP Unit#1 tripped. SPS operated at KKNPP. However ,SPS signal not transmitted towards loads
-- -- --
-- --
--
13. Network Configuration Changes
The following Network configuration changes occurred in the month of June 2019.
Erection of 220 kV D/C line from 400 kV SS Sattenapally to 220 kV SS Guntur in Guntur District (95.59 Ckm) was commissioned on 29.06.2019 by APTRANSCO.
400 kV/220 kV Bus Reactor of Jammalamadugu SS in Kadapa District (80 MVAR) was commissioned on 03.06.2019 by APTRANSCO.
220 kV line on Multi Circuit towers for making LILO of Both circuits of existing 220 kV Waddekothapalli I&II Bhongir DC line at 400/220 kv SS Janagaon (104.06 Ckm) was commissioned on 12.06.2019 by TSTRANSCO.
400 kV Quad Moose DC line from Julurupadu I&II to Janagaon SS (174.72 Ckm) was commissioned on 26.06.2019 by TSTRANSCO.
220 kV DC line from proposed 220 kV Rampur I & II SS to proposed 220/11 kV Rajeshwarrao Peta Substation (72 Ckm) was commissioned on 28.06.2019 by TSTRANSCO.
220/11 kV Rajeshwarrao peta I & II SS (120 MVA) in Jagtiyal District was commissioned on 28.06.2019 by TSTRANSCO.
8th 220/11 Kv, 50 MVA PTR at Medigadda SS in Jayashankar Bhoopalpally District (existing 7x50 MVA) was commissioned on 17.06.2019 by TSTRANSCO.
6th & 7th 220/11 kV, 50 MVA PTRs (2 x 50 MVA) at Annararam SS in Peddapalli District (Existing 5x50 MVA) was commissioned on 18.06.2019 by TSTRANSCO.
2x50 + 1x80 MVA, 220/11 kV PTRs at Bheemghanpur SS in Jayashankar Bhoopalpally district (existing 1x31.5+2x50 MVA) was commissioned on 07.06.2019 by TSTRANSCO.
14. Date and Venue of Next PCSC Meeting
The date of 86th meeting of PCSC will be intimated in Agenda for PCSC-86.
*****
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 1/52
Grid Occurrences - 85
I. Details of Grid Disturbances:
Sl. No.
Details of Event Date &Time Reason Remarks Category
1
Complete outage of 220kV 220/110kV Palakkad Substation of KSEB
04-06-2019 at 14:02hrs
Testing of Bus Coupler CT was being carried out during which LBB trip got initiated and resulting in tripping of Bus-2. This resulted in the tripping all the connected elements at 220kV Palakkad Bus-2 leading to complete loss of supply
Load loss – 268 MW
GD-1
SLD: The SLD of 220/ 110 kV Palakkad SS of KSEBL is attached at the end.
Bus configuration and arrangement: Double Bus with Bus coupler Arrangement
Antecedent conditions: Bus - 1 was in dead conditions Bus -2 connected elements:220kV Palakkad – Palakkad PG line-1, 220kV 220kV Palakkad –
Palakkad PG line-2, 220kV Palakkad – Palakkad PG line-3, 220kV Madakathara – Palakkad line, 220/ 110 kV 200MVA Transformer 1, 220/ 110 kV 200MVA Transformer 2, 220/ 110 kV 200MVA Transformer 3.
Bus coupler was in open condition.
Tripping of 220kV Palakkad – Palakkad PG line-1,2 & 3: Palakkad (KSEBL) end:
As per FIR/ DR/ EL/ TR line tripped at 08:32:51.686 hr. on operation of LBB protection of Bus-2. Palakkad PG (PGCIL-Sr-2) end:
As per FIR/ TR line did not trip at Palakkad PG end.
220kV Palakkad PG
220kV Palakkad
110kV Palakkad
220kV Madakathara
Connectivity diagram of 220/ 110kV Palakkad SS of KSEBL
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 2/52
Tripping of 220kV Palakkad – Madakkathara line : Palakkad (KSEBL) end:
As per FIR/ DR/ EL/ TR line tripped at 08:32:51.686 hr. on operation of LBB protection of Bus-2. Madakathara (KSEBL) end:
As per FIR/ TR line did not trip at Palakkad PG end. Tripping of 220/ 110kV Palakkad SS:
As per FIR/ DR/ EL/ TR 220kV Bus-2 tripped at 08:32:51.686 hr. on operation of Bus-2 LBB protection. The operation of Bus-2 LBB tripped all elements connected to Bus-2 ( i.e, 220kV Palakkad – Palakkad PG line-1, 220kV Palakkad – Palakkad PG line-2, 220kV Palakkad – Palakkad PG line-3, 220kV Madakathara – Palakkad line, 220/ 110 kV 200MVA Transformer 1, 220/ 110 kV 200MVA Transformer 2, 220/ 110 kV 200MVA Transformer 3 ). Total load loss reported during the event is 268MW.
KSEBL informed that The high impedance BBP at 220kV Palakkad substation was replaced with new low impedance GE make numerical bus bar protection and commissioned on 30.05.2019. At the time of commissioning the 220 KV Bus coupler was not in service. On 04.06.2019, relay team carried out pre commissioning testing on bus coupler CT after putting BBP selector switch to out of service.
While carrying out CT secondary injection, the relay team had injected current in O/C and E/F core first. This had led to operation of earth fault protection and master trip relay in bus coupler panel. Trip relay operation triggered LBB initiation in numerical bus bar protection. When relay team injected current in CT core connected to bus bar relay without resetting master trip relay, LBB trip was initiated. As all element were connected to same bus, all were tripped.
Deliberations:
In the antecedent condition, 220kV Bus-1 at Palakkad SS was under shutdown, Buscoupler was in open condition and all elements were connected to 220kV Bus-2. On 04.06.2019, relay team of KSEBL were carrying out pre commissioning testing on bus coupler CT after putting BBP selector switch to out of service.
Initially the relay team had injected current in O/C and E/F core of Bus coupler CT. This had led to operation of earth fault protection and master trip relay in bus coupler panel. Trip relay operation triggered LBB initiation in numerical bus bar protection. The relay then reset only the trip relay but not the lockout relay. Hence LBB initiation was high. Subsequently relay team injected current in CT core connected to bus bar relay. Presence of current alongwith LBB initiation led to operation of LBB protection for Bus-2 and tripped all elements connected to Bus-2. Total load loss reported during the event was 268MW.
Remedial Measures Taken: KSEBL vide mail dated 29.07.2019 informed that: Warning stickers were provided and other precautionary steps were taken to avoid this in
future. GPS connection was corrected and found OK.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 3/52
2
Complete outage of 220kV Pothenkode Substation of KSEB
04-07-2019 at 01:18 hrs
Triggering incident was failure of suspension insulator of 220kV Pothenkode – Trivendrum ckt-2. Bus bar protection of Bus-1 and Bus -2 operated resulting in tripping of all connected elements.
Load loss – 300 MW
GD-1
SLD: The SLD of 220/ 110 kV Pothencode SS of KSEBL is attached at the end.
Bus configuration and arrangement: Double Bus with Bus coupler arrangement [ Bus 1 extension also available so there are 3 buses]
Antecedent conditions: Bus-1 connected elements: 220kV Pothencode – Edamon line 1, 220kV Pothencode –
Trivandrum line – 1 & 3, 220/ 110kV 200MVA Transformer 1& 3. Bus-2 connected elements:220kV Pothencode – New Kattakada line 1 & 2, 220kV
Pothencode – Edamon line 2, 220kV Pothencode – Trivandrum line – 2 & 4, 220/ 110kV 200MVA Transformer 2
Bus coupler in closed condition
Tripping of 220kV Pothencode Trivandrum Line -1,2& 4: Pothencode (KSEBL) end:
As per FIR/ DR/ EL/ TR line tripped at 01:17:29.751 hr. on operation of Bus Bar Protection. Trivandrum (PGCIL-SR-2) end:
As per FIR/ EL/ TR line tripped at 01:17 hr. on receipt of DT from remote end.
KSEBL informed that suspension insulators connecting fly bus and 220 kV bus isolator unit totally exploded leaving the conductor hanging freely from fly bus assembly
Connectivity diagram of 220/ 110kV Pothencode SS of KSEBL
220kV Pothencode
110kV Pothencode
220kV Trivandrum
220kV New Kattakada
220kV Edamon
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 4/52
Tripping of 220/ 110kV Pothencode SS:
As per FIR/ DR/ EL/ TR all connected elements of 220kV/ 110kV Pothencode SS tripped at 01:17:29.751 hr. on operation of Bus Bar Protection.
KSEBL informed vide mail dated 29.07.2019 that Busbar protection was operated in 220 kV Substation, Pothencode on 04-07-2019 at 01.17 Hrs. This is due to failure of B phase string of fly bus of 220 kV TVPC #2 feeder. Busbar protection on Zone 2 operated. All feeders and transformers connected to Zone B (Bus2) tripped immediately. Trip in Zone B (Bus2) was found in order. Differential current in Central unit was vanished by 55ms.
All feeders and transformers connected to Zone A(Bus 1) were tripped just after Zone2 except 200MVA transformer#3. Internal trips were initiated after 20ms (EMPC1, PGCIL1), 50ms(PGCIL3) and 73ms(Transformer 1&3). The reason of these trippings could not be identified. Bus coupler current was found very low by 55ms.
Breaker failure initiated in both Zone A and Zone B simultaneously. Simultaneous occurrence of breaker failure in both buses is also to be investigated. The currents in Bus coupler became low value after 55ms. Therefore, there is no reason for breaker failure. GPS connectivity was found lost in the relay due to fault in GPS card.
Therefore, detailed study is required for finding reasons and for rectifying the issues stated above.
Deliberations:
In the antecedent condition both Bus 1 & 2 were in service and buscoupler was in closed condition.
The triggering incidence for complete outage of 220/ 110kV pothencode SS was failure of suspension insulator (connecting to fly bus) of 220kV Pothenkode – Trivendrum ckt-2. Busbar protection for Bus-2 (Zone-2) operated and tripped all feeders and transformers connected to Zone B (Bus2) immediately. Operation of BBP for bus-2 is in order.
But 90msec after tripping of Bus-2, BBP for Bus-1 (Zone-A) also operated tripping all elements except 220/ 110kV transformer -1, (which was later handtripped) connected to Bus-1. Operation of BBP for Bus-1 is not in order.
KSEBL informed that on inspection it was found that Buscoupler current was very low after 55mec to tripping of Bus-2 hence, operation of BBP for Bus-1 needs further detailed inspection. Also Breaker failure was initiated simultaneously in both Zone A and Zone B and needs further investigation.
PCSC forum suggested checking of DC leakages in the substation and DC- AC mixing which might have led to tripping of Bus-1.
Remedial Measures Taken: KSEBL vide mail dated 29.07.2019 informed that:
Non tripping of Transformer 3 was rectified during the time of restoration. Steps have been taken to replace faulty GPS card in the relay to get GPS connectivity. Detailed testing of busbar system in Pothencode 220kV SS is planned to carry out in the
month of August to study the reasons for extended trippings, breaker failure etc and to take corrective action.
Recommendations:
KSEBL is recommended to investigate the non-operation of zone selective Busbar Operation at 220/ 110kV Pothencode SS and submit detailed report regarding reasons for the same alongwith remedial measures taken.
KSEBL is recommended to ensure time synchronization of relays at 220/ 110kV Pothencode SS.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 5/52
3 Complete outage of 220kV Malaparamba SS of KSEB
29-05-2019 at 01:12 hrs
Triggering incident was R-phase to Earth fault in 220kV MalaparambaAreakode line due to insulator decapping . 220kV Malaparamba Substation was being radially fed from 220kV Areakode
Load loss – 150 MW
GD-1
SLD: The SLD of 220/ 110 kV Malaparamba SS of KSEBL is attached at the end.
Bus configuration and arrangement: Double bus configuration
Antecedent conditions: Bus-1 connected elements: 220/ 110kV 100MVA Transformer 2 Bus-2 connected elements: 220kV Malaparamba – Areakode line, 220/ 110kV 100MVA
Transformer 1 220kV Malaparamba – Madakathara line was under LC.
Tripping of 220kV MalaparambaAreakode line: Malaparamba (KSEBL) end:
As per FIR/ DR/ TR line tripped at 1:12:03.376 hr. on R-E fault due to operation of DPR Z1 protection. A/R was attempted but line tripped on persisting fault due to decapping of insulator at location number 4 (23.59 km).
Areakode (KSEBL) end:
As per FIR/ DR/ TR line tripped at 1:12:03.376 hr. on R-E fault due to operation of DPR Z2 CAT protection (46.27 km). A/R was attempted but line tripped on persisting fault.
Tripping of 220kV Malaparamba SS:
As per FIR/ TR there was complete loss of supply at 220/ 110kV Malaparamba SS due to tripping of incoming 220kV Malaparamba-Areakode line on operation of distance protection.
KSEBL informed that there are two 220kV feeders at 220kV Substation Malaparamba. One feeder is from Areacode (2MRAR) and other from Madakathara (2MDMR). 2MDMR feeder from Madakathara was under permit for transgrid work. 2MRAR feeder from Areacode tripped on 29-05-2019 at 01-12hrs due de capping of insulator. Thus 220kV supply failed and hence supply
Connectivity diagram of 220/ 110kV Malaparamba SS of KSEBL
220kV Malaparamba
110kV Malaparamba
220kV Madakathara
220kV Areakode
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 6/52
interrupted for 1MRML1&2, 1MRPT, 1MRME and 110/11kV Transformer No1.
No interruption occurred in 1MRKU1&2 and 110/11kV Transformer No 2 since this supply were through 110kV bus 2 from shornur side. As per the concurrence with LD Kalamassery, feeding to Malappuram substation re arranged from Areacode through 110kV substation Kizhissery, then 110kV bus1&2 at Malaparamba tied and supply restored on all 110kV bays from Shornur side at 1.55hrs on 29-05-2019.
Deliberations:
In the antecedent condition, 220kV Malaparamba – Madakkathara line was under LC for transgrid works and both Buses 1 & 2 was in service.
The triggering incidence was R-E fault on 220kV Malaparamba – Areakode line due to insulator decapping at 1:12:03.376 hr. The line attempted auto-reclosure, but since the fault was persisting in nature line tripped in 3-ph. Hence, the supply to 220kV bus was lost and it resultedin outage of 220kV Bus 1 & 2. But 110kV Bus-2 was fed from 110kV Shornur SS, so there was not complete loss of supply at the station.
KSEBL had informed that feeding to malaparamba substation was re arranged from Areacode through 110kV Kizhissery SS, and 110kV bus 1 & 2 at Malaparamba were tied and supply restored on all 110kV bays from Shornur side at 1.55hrs on 29-05-2019.
Remedial Measures Taken: KSEBL informed that after the tripping, measure has been taken to ensure reliable supply to
220kV Malaparamba SS through 220kV Madakkathara – Malaparamba lines 1 &2.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 7/52
4
Tripping of 220kV Sedam-RTPS line-1&2 and 220kV Sedam-Tandur line
14-06-2019 at 02:00 hrs
Tripped on Directional Earth Fault indications in Main-2 relay at Tandur end for fault at Raichur end. Sedam end details not furnished.
GI-1
SLD: The SLD of 220/ 110 kV Sedam SS of KPTCL is attached at the end.
Bus configuration and arrangement: Double bus configuration Bus 1- 220kV Sedam – Humnabad line-1, 220kV Sedam – RTPS line-2, 100 MVA
Tranformer-1, 220kV Sedam– Shree cements line, 220kV Sedam – Tandur line. Bus 2- 220kV Sedam –Shahapur line, 220kV Sedam – Humnabad line-2, 220kV Sedam
Orient cements line , 220kV Sedam RTPS line-1, 220kV Sedam - cleanmax solar line
Tripping of 220kV Sedam – RTPS line-1: Sedam ( KPTCL) end:
As per FIR/ TR line did not trip at Sedam end. RTPS (KPCL) end:
As per FIR/ EL line tripped at 01:59:47.906 hr. on operation of DPR Z3 protection (Tz3=750msec) Tripping of 220kV Sedam – RTPS line-2: Sedam ( KPTCL) end:
As per FIR/ TR line detected B-E fault in Z-1 due to operation of Distance protection (1.38kA) but did not trip due to mechanical problem with the line CB at Sedam end.
RTPS (KPCL) end:
As per FIR/ EL line tripped at 01:59:47.103 hr. on operation of DPR Z1 protection (9.05 kA; 13.1 km)
Tripping of 220kV Sedam – Tandur line: Sedam ( KPTCL) end:
As per FIR/ TR line did not trip at Sedam end. Tandur (TSTRANSCO) end:
Sedam RTPS
Humnabad
Shree cements
Orient cements
Shahpur
Tandur Clean Max solar
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 8/52
As per FIR/ DR/ EL/ TR line tripped at 02:00:06.353 hr. on operation of Directional Earth fault protection. (Td=2.8msec)
Deliberations:
In the antecedent condition 220kV Sedam-Shahapur line was under LC due to line fault and the station was under single bus operation.
At 01:59:47 hr. B-E fault occurred on 220kV Sedam – RTPS line-2. The fault was detected in Z-1 at both ends. RTPS end tripped immediately but Sedam end breaker did not open due to CB mechanical problem. A/ R was not in service for the line.
Hence fault was cleared by operation of protection at remote end. 220kV Sedam – Humnabad line- 1 & 2, 220kV Sedam – Tandur line tripped at remote end on DEF operation. 220kV Sedam RTPS line-1 tripped at RTPS end on operation of DPR Z3. All remaining lines were radially fed from Sedam end. Hence no protection operated at remote end. This has led to complete outage of 220kV Sedam SS.
Remedial Measures Taken: KPTCL vide mail dated 30.07.2019 informed that:
The Circuit Breaker of RTPS-1 &2 lines which was due for replacement has been replaced on 24th and 25th July 2019.
The control cables required for Bus Bar Protection work has been arranged, the work is expected to be completed by August end.
Recommendations: KPTCL is recommended to enable A/R on all lines emanating from 220kV Sedam SS. KPTCL is recommended to commission BBP at 220kV Sedam SS immediately.
II. Details of Grid Incidents:
Sl. No. Details of Event Date &Time Reason Categor
y
1 Tripping of 400/230kV MANALI ICT-3
13-05-2019 at 2:42 hrs
ICT-3 got tripped on the activation of HV REF protection. During test charging of 110 kV Manali-ETPS -1 , the 110 kV ETPS -1 got tripped on the activation of Back up relay and Distance relay failed to act
GI-2
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 9/52
MANALI (TANTRANSCO) end:
As per FIR/ DR/ EL/ TR ICT-3 tripped on HV side at 02:42:54.570 hr. due to operation of HV REF protection.
TANTRANSCO in their TR informed that during test charging of 110 kV Manali- ETPS -1, the line got tripped on the activation of Back up O/C protection and Distance relay failed to act. The earth conductor of line got cut and fell on 110 kV Manali- TPL # Line conductor. 110 kV Manali- TPL line got tripped on Distance relay activation with Z-1 trip. Both ICTs kept feeding the fault upto 1.1 secs. During this time the ICT-3 got tripped on the activation of HV REF protection. But 400/110 kV, 200 MVA, ICT-1 was in service and hence no interruption to the 110 kV Loads. Deliberations:
In the antecedent condition 110kV Manali –ETPS line -1 was out of service. During testcharging of 110kV Manali –ETPS line -1 from Manali end, B-E fault occurred on the line. But SOTF did not pick for the fault. During this time, 400/230kV ICT-3 at Manali tripped on operation of HV REF protection(Differential current is present in REF protection DR for 3 cycles). The operation of ICT REF protection for through fault needs review.
The fault wascleared by operation of Overcurrent protection of the line after 1.1 sec.
When enquired about non-operation of SOTF protection of 110kV Manali –ETPS line -1, TANTRANSCO informed that the distance relay at Manali end was configured from Bus PT and it was changed to line PT after the fault.
After 1.3sec after the fault, earth conductor of 110kV Manali –ETPS line -1 got cut and fell on 110 kV Manali -TPL line conductor creating Y-E fault. The fault was cleared by tripping of 110kV Manali – TPL line due to operation of distance protection.
Remedial Measures Taken: TANTRANSCO informed that the operation of ICT HV REF protection for through fault has been
sent to Relay OEM (M/s. NR Ltd) for analysis.
Recommendations: TANTRANCO is recommended to sort out the malfunctioning of ICT Ref protection in
consultation with OEM and submit a detailed report regarding the same in 1 month time. TANTRANSCO is recommended to ensure proper labelling of all digital signals in Disturbance
recorders of lines and ICTs at Manali SS.
2 Tripping of 400kV Madurai-Udumalpet line
16-05-2019 at 18:54 hrs
400kV Udumalpet Madurai line tripped only at Udumalpet end on line under frequency protection operation due to suspected R-ph CVT problem.
GI-2
Madurai (PGCIL –SR-2) end:
As per FIR line did not trip at Madurai end. Udumalpet (PGCIL –SR-2) end:
As per FIR/ DR/ EL/ TR line tripped at 18:54:44.201 hr. on operation of under frequency protection.
As per DR R-ph voltage is observed to be 76.256kV.
PGCIL-SR-2 informed in TR that Underfrequency relay operated due to suspected CVT problem. Deliberations:
400kV Madurai-Udumalpet line tripped at 18:54:44.201 hr. on operation of
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 10/52
underfrequencyprotection. R-ph voltage waveform was observed to be distorted in line DR. PGCIL –SR-2 informed that underfrequency protection was enabled on the line as part of Neyveli islanding scheme. On analysis, R-ph CVT was found to be proper, but cable from CVT to relay was found to have leakages and this led to spurious underfrequency operation.
Remedial Measures Taken: PGCIL (SR-2) informed that R-ph CVT cable has been replaced after the incidence.
3 Tripping of 400kV Kurnool-Srisailam line
17-05-2019 at 14:10 hrs
line tripped only at Srisailam end on Zone-3 distance protection operation during Y phase to B phase fault in 220kV NarnoorSomayajulapalli line-1
GI-2
Kurnool (APTRANSCO) end:
As per FIR line did not trip at Kurnool end. Srisailam LB (TSGENCO) end:
As per FIR/ EL/ TR line tripped at 14:10 hr on R-B-E fault due to operation of DPR, Z3.
As per EL line picked up in Zone-3 for R-B-E fault at 14:09:44.417 hr.
Deliberations:
In the antecedent conditions, 220kV NarnoorSomayajulapalli line-1 was idle charged from Somayajulapalli end. While testcharging the line it tripped on Y-B fault due to operation of DPR Z1 protection. 400kV Kurnool-Srisailam line tripped from Srisailam end at 14:09:44.417 hr on operation of DPR Z3 protection for Y-B fault on 220kV NarnoorSomayajulapalli line-1. TSGENCO informed that the tripping was due to wrong PSL logic in Micom P442 relay which issues trip without any time delay for 2ph and 3ph faults occuring in any zone.
Remedial Measures Taken: TSGENCO vide mail dated 29.05.2019 and 25.07.2019 had informed that the setting of Z3 time
delay for 400kV Kurnool – Srisailam line is 1.5sec. But the line is tripping instantaneously without any time delay in Zone-3 for LL faults occurring in Kurnool line. In Micom P-442 PSL logic 2Ph fault signal was programmed to the trip relay without any time delay. This signal will issue the trip whenever a two phase fault occurred in the system without waiting the time delay. (In this case Rph to B pH fault occurred i.e 2PH fault occurred in the system). For rectification of Zone-3 fault without any time delay, DR was sent to GEC ALSTOM (OEM) and informed to change the PSL logic.
PSL Logic of Micom P442 relay for 400kV Kurnool Srisailam line
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 11/52
Recommendations: TSGENCO is recommended to modify the PSL logic (Srisailam end to trip for faults occurring in
Zone-2 and Zone-3 with respective time delays except for PUR scheme if adopted ) in 1 month time to avoid occurrence of any such unwarranted trippings in future.
APTRANSCO to ensure time synchronization of relays at 220kV Somayajulapalli SS.
4 Tripping of 220kV Ambewadi-Ponda line
18-05-2019 at 12:13 hrs
B phase to Earth fault in the line. Line tripped on Zone 3 distance protection operation at Ambewadi end
GI-1
Ambewadi (KPTCL) end:
As per FIR/ DR / EL/ TR line tripped at 12:12:09.118 hr. on B-E fault due to operation of DPR Z3. (45.9km; Ir- 0.22 kA, Iy – 0.24 kA, Ib – 0.57 kA; T Z3 = 1 sec)
Ponda (GED) end:
The line being radial did not trip at Ponda end.
KPTCL informed vide mail dated 30.07.2019 that : At Ambewadi: At 14.10.14.420: M-I relay which picked up when B phase voltage dipped to 106kV, fault current 70A IN reached 335A dropped out after 120msec as fault was no longer persisting. However, Main-II relay (Siemens make) which picked up with Zone-3, BN fault (Fault current 350A, 45.9km) issued trip command after set zone-3 time delay of 1 second. Nature of Fault: Suspected high resistive transient fault in the line.
Deliberations:
220kV Ambewadi-Ponda line tripped from Ambewadi end, at 12:12:09.118 hr. on B-E fault due
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 12/52
to operation of directional earth fault protection. PTCL informed that Main-1 and Main-2 relays at Ambewadi are Seimens 7SA522 and Micom P442. Micom relay picked up and dropped for the fault. But in Seimens relay zone pick up was used to provide directionality feature for Overcurrent and DEF protections.
Also Zone settings were also high which led to pickup of relay in Zone-3 and DEF operated after 1 sec.
Remedial Measures Taken: KPTCL informed vide mail dated 30.07.2019 that : The healthiness of Siemens make new Main-II relay is checked once again after the incident and
the relay is found to be working satisfactory for all fault conditions. The reach of Zone-3 has been reduced to avoid such unnecessary trippings in future. DEF protection has been normalized in Seimens relay and has been made independent of Zone
pick up. To provide directionality feature to OCR protection Zone-5 has been used.
5 Tripping of 400/220 kV ICT-3 at Nelamangala substation
19-05-2019 at 16:11 hrs
As per FIR, ICT-3 got tripped on operation of High Set Over current trip on 400kV side
GI-2
Connectivity diagram of 400/ 220kV Neelamangala SS of KPTCL: Neelamangala (KPTCL) end:
As per FIR/ DR ICT-3 tripped on both sides at 16:55:13.114 hr. on operation of High Set O/C operation.
KPTCL vide mail dated 30.07.2019 informed that 220kV DB Pura was radially fed from Nelamangala SS through Nelamangala-DB Pura D/c line. At 16.11Hrs 220kV Nelamangala-DB Pura line-1& 2 tripped on operation of M-I&M-II,Zone-1 due to snapping of earth wire near Nelamangala switchyard. Tripping of both the incoming lines to DB Pura resulted in complete outage of the SubStation.Along with this, 500MVA ICT-3 tripped at Nelamangala on HV side OC High set element.
Also, Nelamangala-Magadi line tripped on SOTF O/c pick up. Deliberations:
In the antecedent conditions 400/ 220kV ICT-1 & 2 were connected in parallel at Bus-1. Bus coupler was in open condition. Bus 1 & Bus-2 was connected through 220kV DB pura line -1 & 2
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 13/52
to reduce shortcircuit level at Neelamangala bus.
The triggering incidence was B-E fault on 220kV Neelamangala DB Pura line-1 and 2 at 16:10:53 hr. due to snapping of the earth wire during heavy rain. The line tripped due to operation of DPR Z1 protection. A/R was disabled on the line. KPTCL informed that auto-reclosure will be made available for the line immediately after retrofitting works are completed at D.B. Pura SS.
Delayed clearance of the fault was due to the fact that the fault started as high resistance fault and subsequently was picked up in zone-1. Tripping of both the incoming lines to DB Pura resulted in complete outage of the Sub Station.
During this time 400/220 kV ICT-3 at Nelamangala substation tripped on operation of HV High Set O/C protection.
At 16:10:54 hr. 220kV Nelamangala-Magadi line tripped on B-E fault due to operation of SOTF protection. When enquired about reason for SOTF protection, KPTCL informed that the logic implemented in relay did not include breaker status, hence it operated based only on the fault current.
Remedial Measures Taken: KPTCL vide mail dated 30.07.2019 informed that:
The line fault was attended. ICT-3 high set setting is revised to 5 Amp from existing 4.3A; Time delay of 100msec is
also provided to the high set. SOTF logic reviewed in Magadi line distance relay (breaker status also included in logic).
Recommendations:
KPTCL is recommended to enable auto-reclosure on all lines emanating from 400/ 220kv Neelamangala SS and to ensure time synchronization of relays at Neelamangala SS.
6 Tripping of 400/220 kV ICT-2 at Ghani substation
21-05-2019 at 15:13 hrs
ICT-2 tripped on LV Earth fault protection. 400kV Ghani-Narnoor line-1 had tripped on B-phase to earth fault.
GI-2
Tripping of 400kV Ghani-Narnoor line-1 : Ghani (APTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped in 3-ph at 15:13:28.605 hr. on B-E fault due to operation of
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 14/52
DPR Z1. The Main CB was already open and line was connected though Tie CB only. Tie CB did not attempt A/R.
Narnoor (APTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped in B-phat 15:13:28.627 hr. on B-E fault due to operation of DPR Z2, CAT. A/R was successful but line tripped in 3-ph at 15:13:29.715 hr. on persisting fault due to operation of DPR 2 (since no carrier received, tripped with TZ2 delay).
Tripping of 400/ 220kV ICT-2 Ghani : Ghani (APTRANSCO) end:
As per FIR/ DR/ EL ICT-2 tripped on both sides at 15:13:29.776 hr. due to operation of LV DEF protection. ( Td= 1.15 sec)
Deliberations:
The triggering incidence for the tripping was B-E fault at 15:13:28 hr. on 400kV Ghani-Narnoor line-1. In antecedent condition Main CB was already open and Tie CB issued 3-ph trip (did not attempt A/R) on operation of distance protection Z1. Narnoor end attempted autoreclosure on operation of DPR Z2 CAT. But since the fault was persisting in nature subsequently tripped in 3-ph. But during 3-ph tripping since no carrier was received from Ghani end (since Ghani end already open)Narnoor end tripped with a Zone-2 delay of 350msec.
During this fault, 400/ 220kV ICT-2 at Ghani SS tripped due to operation of LV DEF protection. APTRANSCO informed that the self reset contact of ICT DEF relay got latched and hence it did not reset inspite of fault current reducing to zero. This led to tripping of ICT.
Remedial Measures Taken: APTRANSCO informed that the reset contact of DEF protection relay has been replaced with
new contact.
Recommendations: APTRANSCO is recommended to send a detailed report regarding non-availability of Main CB
(Main CB was already in tripped condition in antecedent condition) during the tripping and non-attempt of auto-reclosure by Tie CB at Ghani end.
7 Tripping of 400/220 kV ICT-3at Mamidapalli
21-05-2019 at 20:43 hrs
ICT tripped on PRV-1 indications due to ingress of moisture into the relay
GI-2
Mamidapalli (TSTRANSCO) end:
As per FIR/ EL ICT-3 tripped on PRV-1 indications due to ingress of moisture into the relay.
Remedial Measures Taken:
TSTRANSCO informed that they cleaned the moisture and charged the ICT.
Recommendations: TSTRANSCO is recommended to ensure proper sealing of PRV by providing suitable canopy to
prevent spurious operation of the same due to ingress of moisture.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 15/52
8 Tripping of 765/400kV ICT-1 and 2 at Kurnool substation
21-05-2019 at 18:11 hrs
ICT 1 and 2 got tripped due to maloperation of Bucholz relays during the charging of 400KV Kurnool-Nanoor line 1 which tripped on SOTF
GI-2
765/400kV ICT – 1 Kurnool (PGCIL –Sr-I) end:
As per FIR/ DR/ EL TR ICT-1 tripped at 18:11:18.757 hr. on operation ofBucholz relay during the charging of 400KV Kurnool-Nanoor line1 which tripped on SOTF during charging.
As per EL ICT-1 tripped at 18:11:18.777 hr. on operation of IOX protection. 765/400kV ICT – 2 Kurnool (PGCIL –Sr-I) end:
As per FIR/ DR/ EL TR ICT-2 tripped at 18:11:18.758 hr. on operation of Bucholz relay during the charging of 400KV Kurnool-Nanoor line1 which tripped on SOTF during charging.
Deliberations:
In the antecedent condition, 400KV Kurnool-Nanoor line 1 was under shutdown. While testcharging the line from Kurnool end at 18:11:18 hr.line tripped on 3ph-E fault due to operation of SOTF protection.
But during the incidence, 765/400kV ICT-1 and 2 at Kurnool SS tripped due to operation of Buchholz relay. The operation of Buchholz relay for ICT through fault needs investigation.
Remedial Measures taken: PGCIL-SR-1 informed vide mail dated 28.07.2019 that ICTs fed the through fault current on
account of fault in 400kV Kurnool-Narnoor line-1 & tripped on operation of Buchholz Relay. Line Fault Current Ia - 34.90kA (RMS), Ib - 33.66kA (RMS), Ic - 41.99kA (RMS). ICT1 also got tripped due to high through fault. Reasons for momentary operation of Buchholz Relay for through fault may be due to
i. Vibration of pipe connected between the Conservator & Main Tank. ii. Operation of Trip contact for oil surge during the through fault.
Cedapse, Italy make Buchholz relay of Model number- EE3-MA at Kurnool SS are mal operated for the through faults . Informed to OEM to take corrective modification. Awaiting for OEM response. OEM planned to visit the Kurnool SS for rectification in 1st week of August-2019.
Recommendation: PGCIL (SR-I) is recommended to submit a detailed report regarding operation of Buchholz relay
of 765/ 400kV ICT 1& 2 during through fault after consultation with OEM along-with the remedial measures taken to prevent occurrence of any such incidence in future.
9 Tripping of 220KV Sabarigiri-Theni line
23-05-2019 at 16:12 hrs
Line tripped on operation of DEF at Theni end
GI-1
Theni (TANTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 16:11:51.111 hr. on R-E fault due to operation of DEF protection ( Td= 3.1ec ( if calculated from earlier IN pick up ); 0.97kA)
Sabarigiri (KSEBL) end:
As per FIR/ DR/ EL/ TR line tripped at 16:11:51.111 hr. on R-E fault due to operation of DPR Z2 protection. (100.3km, Td = 625msec)
Deliberations:
220KV Sabarigiri-Theni line tripped at 16:11:51.111 hr. on R-E fault due to operation of DEF protection at Theni end and DPR Z2 protection at Sabarigiri end. KSEBL informed that due to the high resistance nature of fault, it was detected after some delay in Zone-2 hence the tripping was after 625msec after the fault.
Recommendations: KSEBL is recommended to configure in DR and EL the pick up and operation of relevant distance
protection zones in the event of distance protection operation.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 16/52
10 Tripping of 400kV Sigareni-Sundilla line-2
24-05-2019 at 18:21 hrs
Line tripped to operation of OV Stg-1 protection operation at Sundila end and DT received at Singareni end. Difference in phase voltages is observed at Sundilla end DR (Vr-262kV, Vy-240kV and Vb-214kV).
GI-2
Singareni (STPP) end:
As per DR/ EL line tripped at 18:21:57.612 hr. on receipt of DT from Sundilla end. Sundilla (TSTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 18:21:52.847 hr. on operation of OVR Stg.-1 protection. ( TOV – 8sec; Vr- 262kV, Vy-240.079kV, Vb-214.42kV).
OVR grading (2019) at 400kV Sundilla SS :
Remedial Measures taken: TSTRANSCO informed that the CVT’s and relays has been checked by OEM and everything has
been found normal. Also new OVR grading has been adopted at 400kV Sundilla SS.
11 Tripping of 400kV Hoody-Yelahanka line-1
25-05-2019 at 20:41 hrs
Line tripped at Hoody end only and was holding from Yelahanka.
GI-2
Hoody (KPTCL) end:
As per FIR/ DR/ EL/ TR line tripped at 20:37:32.242 on operation of DPR Z1 or SOTF/TOR.
As per EL distance B-ph pickup observed. But as per DR no fault current but instantaneous voltage 0 in all 3-phases for a short time.
Yelahanka (PGCIL-SR-2) end:
As per FIR/ TR line did not trip at Yelahanka end.
KPTCL vide mail dated 30.07.2019 informed that at 20.37.32.201: Main-I relay operated in Zone-1. Fault duration: 3.336ms; Sudden dip in voltage observed in all the three phases for about 40msec; M-II has not operated during the moment.
At Yelahanka: Line was holding from Yelahanka end
Reason: Suspected momentary problem in secondary voltage circuit of M-II relay
Deliberations:
400kV Hoody-Yelahanka line-1 tripped only at Hoody end at 20:37:32.242 hr. on operation of SOTF protection. The Main-1 relay (Micom P444) picked up for momentary voltage problem and issued trip.
Recommendations: KPTCL is recommended to check the spurious operation of SOTF protection at Hoody SS and
submit a report to SRPC regarding the same .
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 17/52
12 Tripping of 400/220 kV ICT-1at Guttur Substation
26-05-2019 at 10:00 hrs
LV side of 400kV/220kV 315MVA ICT#1 Guttur got tripped due to CB lockout (B phase)because of low SF6 gas in the CB
GI-2
Guttur (KPTCL) end:
As per FIR/ DR/ EL/ TR ICT-1 tripped on LV side at 10:00:51.355 hr. on operation of CB lockout trip due to low SF6 gas pressure in B-ph CB.
KPTCL vide mail dated 30.07.2019 informed that220kV side CB of ICT-1 was replaced by CGL make new CB recently.SF6 leakage was observed in B phase limb, hence, operating personnel attempted to recharge the pressure in the cylinder. The cylinder used for recharge was having lower pressure hence, when connected to breaker pressure flowed from CB to cylinder and CB tripped on low SF6 gas pressure.
Remedial Measures Taken: KPTCL vide mail dated 30.07.2019 informed that SF6 gas leakage problem in the breaker is
attended by the OEM.However small leakage still persists .The issue is referred to the OEM and OEM is yet to depute their personnel.
Recommendations: KPTCL is recommended to submit a report to SRPC after the CB pressure leakage problem is
attended by OEM. KPTCL to ensure that during recharging of Circuit breakers, cylinders with Non-return valve only
are used to prevent sudden pressure drop in Circuit breakers.
13 Tripping of 400kV NPS Nellore line-1 & 2
27-05-2019 at 17:42 hrs
400kV NPS Nellore-PG line-2 tripped at NPS end due to suspected maloperation of group B protection and DT was sent to Nellore-PG end. 400kV NPS Nellore-PG line-1 got tripped due to operation of SPS
GI-2
Tripping of 400kV NPS Nellore line-1 : Nellore PG(PGCIL-Sr-1) end:
As per FIR/ DR/ EL/ TR line tripped at 17:42:39.572 hr. on receipt of DT due to SPS operation on tripping of 400kV NPS Nellore line-2.
Nellore PS (PGCIL-Sr-1) end:
As per FIR/ DR/ EL/ TR line tripped at 17:42:39.527 hr. due to SPS operation on tripping of 400kV NPS Nellore line-2.
Tripping of 400kV NPS Nellore line-2 : Nellore PG(PGCIL-Sr-1) end:
As per FIR/ DR/ EL/ TR line tripped at 17:42:34.423 hr. on receipt of DT from Nellore PS end. Nellore PS (PGCIL-Sr-1) end:
As per FIR/ DR/ EL/ TR line tripped at 17:42:34.401 hr. due to operation of Group B trip relay.
Deliberations:
400kV NPS Nellore line-2 tripped due to maloperation of Group B (86B) trip relayat Nellore PS end and DT was sent to Nellore PG end. Consequently 400kV NPS Nellore line-1 tripped on SPS operation. Operation of protection system is stated to be in order.
Remedial Measure Taken: PGCIL (Sr-1) vide mail dated 28.07.2019 informed that 400kV NPS Nellore Line-2 tripped due to
86B trip relay maloperation. 86 B trip relay replaced with spare relay and line taken into service.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 18/52
14 Tripping of 230kV Theni-Sabarigiri line
29-05-2019 at 18:39 hrs
3 phase to earth fault occurred in line. Tripped on ground over current protection 67N at Sabarigiri and Zone-2 at Theni end.
GI-1
Theni (TANTRASCO) end:
As per FIR/ DR/ EL/ TR line tripped at 18:38:45.979 hr. on R-Y-B fault due to operation of DPR Z2 protection. (96.998 km; 3.05kA; TZ2 = 350msec)
Sabarigiri (KSEBL) end:
As per FIR/ DR/ EL/ TR line tripped at 18:39:20.987 hr. on R-Y-B fault due to operation of DPR Z1 protection (16.6 km; Ir-6.55 kA, Iy-7.16 kA, Ib- 6.67kA; TZ1 = 100msec).
Deliberations:
230kV Theni-Sabarigiri line tripped on R-Y-B fault due to operation of distance protection. Sabarigiri end, fault was detected in Zone-1 and carrier was sent but Theni end did not receive the carrier and hence tripped only after Zone-2 time delay. TANTRANSCO requested KSEBL to replace the PLCC panel at their end so as to ensure same make PLCC at both ends.
Recommendations: For the subject line, the following shall be carried out by TANTRANSCO in coordination with
KSEBL: (i) End-to-end testing for DT/ permissive & other signals may be ensured by testing at both the
ends. (ii) Healthiness of PLCC system components ( hardware and software) at both the ends shall be
checked and faulty components shall be repaired/ replaced .
15 Tripping of 400/220 kV ICT-1 and 400kV RTPS-RAICHUR PG line-2
29-05-2019 at 12:43 hrs
Due to spurious operation of Tie breaker LBB, 400/220 kV ICT-1 and 400kV RTPS-Raichur PG 2 got tripped at RTPS end and DT was sent to Raichur PG end
GI-2
Tripping of 400/220 kV ICT-1 Raichur TPS (KPCL):
As per FIR/ DR/ EL/ TR ICT-1 tripped at 12:43 hr. on operation of Tie CB LBB protection. Tripping of 400kV RTPS – Raichur PG line -2: RTPS (KPCL):
As per FIR/ DR/ EL/ TR line tripped at 12:43 hr. on operation of Tie CB LBB protection and DT was sent to Raichur PG end.
Raichur PG (PGCIL- SR-1) end:
As per FIR/ DR/ EL/ TR line tripped at 12:43:39.954 hr. on receipt of DT from remote end. Deliberations:
Tripping of 400kV RTPS – Raichur PG line -2 and 400/ 220kV ICT-1 at Raichur was due to maloperation of Tie CB LBB protection. KPCL informed that the contact multiplier relay of Tie LBB was MVAJHM53 type which had been retrofitted with MVAJM25 relay. The retrofitted relay maloperated and caused tripping of 400/220 kV ICT-1 and 400kV RTPS-RAICHUR PG line-2.
Remedial Measures Taken: KPCL informed that the Tie CB LBB trip at RTPS was recently retrofitted from VAJHM53 with
MVAJM25 on 02.05.2019. The faulty trip relay MVAJM25 replaced with spare relay and the contacts used for DT has been incorporated in the LBB relay.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 19/52
16
Tripping of 400kV Tumkur-Bidadi line-1&2, 400kV Tumkur-Cuddapah line-2, 400kV Tumkur-Pavagada line-2
29-05-2019 at 6:11 hrs
Lines tripped due to Y-N & Y-B phase to earth fault
GI-2
Tripping of 400kV Tumkur – Bidadi line 1: Tumkur (PGCIL –SR-2) end:
As per FIR/ TR line did not trip at Tumkur end. Bidadi (PGCIL –SR-2) end:
As per FIR/ DR/ EL/ TR line tripped at 06:11:03.304 hr. on Y-B fault due to operation of DPR Z2 CAT.
Tripping of 400kV Tumkur – Bidadi line 2: Tumkur (PGCIL –SR-2) end:
As per FIR/ DR/ EL/ TR line tripped at 06:11:03.293 hr. on operation of DPR Z1. Bidadi (PGCIL –SR-2) end:
As per FIR/ DR/ EL/ TR line tripped at 06:11:03.308 hr. on Y-B fault due to operation of DPR Z2 CAT.
Tripping of 400kV Tumkur – Cuddapah line 2: Tumkur (PGCIL –SR-2) end:
As per FIR/ DR/ EL/ TR line tripped in Y ph at06:11:02.038 hr. on Y-E fault due to operation of DPR Z1 protection. A/R was attempted but subsequently line tripped in 3-ph due to persisting fault.
Cuddapah (PGCIL-SR-1) end:
As per FIR/ DR/ EL/ TR line tripped in Y ph at 06:11:02.009 hr. on Y-E fault due to operation of DPR Z2 CAT protection. A/R was attempted but subsequently line tripped in 3-ph due to persisting fault. (248.5 km; FC:2.71 kA)
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 20/52
Tripping of 400kV Tumkur – Pavagada line 2: Tumkur (PGCIL –SR-2) end:
As per FIR/ DR/ EL/ TR line tripped at 06:11:03.292 hr. on Y-B-E fault due to operation of DPR Z1 protection. The fault was due to B-ph LA failure at Tumkur end.
Pavagada (PGCIL –SR-2) end:
As per FIR/ DR/ EL/ TR line tripped at 06:11:03.298 hr. on Y-B-E fault due to operation of DPR Z2 CAT protection.
Deliberations:
The triggering incidence was Y-E fault on 400kV Tumkur – Cuddapah line 2, the line attempted A/R but tripped due to persisting fault. During same time B-ph LA of 400kV Tumkur – Pavagada line 2 failed at Tumkur end and it was detected as Y-B-E fault and the line tripped. At the same time another Y-B fault was detected in 400kV Tumkur – Bidadi line 2 and it tripped on operation of Distance protection. But 400kV Tumkur – Bidadi line 1 also tripped at Bidadi end on Z2 CAT.
PGCIL (SR-2) informed that Main 2 relay (GE P444) at Tumkur end of 400kV Tumkur – Bidadi line 1 maloperated (due to problem with relay software) and sent carrier to Bidadi end. Hence, Bidadi end tripped immediately (Z2 CAT).
Remedial Measures Taken: PGCIL (SR-2) informed that the failed LAof 400kV Tumkur – Pavagada line 2 was replaced and
line taken back into service. The maloperated relay software was upgraded to new version (D4.7 ) by OEM.
Recommendations:
PGCIL (SR-2) is recommended to submit Equipment failure report to CEA regarding the failed LA.
17
400 kV Ghani – Narnoor line-1, 400 KV Jamalamadugu-Kurnool line-1, 765/400 kV ICT-1&2 at Kurnool
30-05-2019 at 00:48 hrs
Triggering incident was Y-ph to B-ph fault in the 400kV NarnoorJammalamadugu line-1 & 2 due to falling of Y-ph CVT jumper on B-ph during heavy wind. At the same time, 400kV GhaniNarnoor tripped only at Ghani end on operation of Zone-1 distance protection. 765/400 kV ICT-1 & 2 at Kurnool PG also got tripped on HV side Directional Overcurrent (DOC) protection.
GI-2
Tripping of 400kV Ghani – Narnoor line-1:
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 21/52
Ghani (APTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 00:48:13.076 hr. on Y-B fault due to operation of DPR Z1 protection (19.7 km). [ Iy=758A, Ib=769A]
Narnoor (APTRANSCO) end:
As per FIR line did not trip at Narnoor end. Tripping of 400kV Jamalamadugu – Narnoor line-1: Jamalamadugu (APTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 00:47:55.948 hr. on Y-B fault due to operation of DPR, Z2 CAT protection. (89.7 km)
Narnoor (APTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 00:48:13.079 hr. on Y-B fault due to operation of DPR Z1 protection. The fault was due to Y-Phase CVT jumper cut and fallen on B-Phase Jumper.
In DR Y ph voltage is not present for 600msec. and SOTF/ TOR signal also raised at 00:48:13.054 hr.
Tripping of 400kV Jamalamadugu – Narnoor line-2: Jamalamadugu (APTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 00:47:55.950 hr. on Y-B fault due to operation of DPR, Z2 CAT protection. (94.7 km)
Narnoor (APTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 00:47:55.934 hr. on Y-B fault due to operation of DPR Z1 protection. The fault was due to Y-Phase CVT jumper cut and fallen on B-Phase Jumper. (0.93 km)
Tripping of 765/ 400kV ICT-1 Kurnool:
As per FIR/ DR/ EL/ TR ICT-2 tripped at 00:47:55.991 hr. on Y-B fault due to operation of DOC ( Highset, If < 5kA)
Tripping of 765/ 400kV ICT-2 Kurnool:
As per FIR/ DR/ EL/ TR ICT-2 tripped at 00:47:55.9922 hr. on Y-B fault due to operation of DOC ( Highset, If <5kA)
PGCIL (SR-1 ) vide mail dated 28.07.2019 informed that 1500MVA ICT-1&2 at Kurnool tripped on operation of Bucholz-1 operation. ICTs fed the through fault current on account of fault in 400kV Ghani-Narnoor line & Jammalamadugu-Narnoor-1&2 & tripped on operation of Buchholz Relay. Line Fault Current Ib - 4.90kA (RMS), Ic - 3.99kA (RMS).
Reasons for momentary operation of Buchholz Relay for through fault may be due to i. Vibration of pipe connected between the Conservator & Main Tank. ii. Operation of Trip contact for oil surge during the through fault.
Cedapse, Italy make Buchholz relay of Model number- EE3-MA at Kurnool SS are mal operated for the through faults . Informed to OEM to take corrective modification. Awaiting for OEM response. OEM planned to visit the Kurnool SS for rectification in 1st week of August-2019.
Deliberations:
The triggering incidence was Y-Phase CVT jumper cut and falling on B-Phase Jumper creating Y-B fault on 400kV NarnoorJamalamadugu lines 1 & 2 tripping them on operation of Distance protection. The fault was also detected by 400kV Ghani – Narnoor line at Ghani end in Z1 and it tripped. APTRANSCO informed that Seimens 7SA522 relay at Ghani end only operated in Zone-1. The other main relay did not operate. The issue has been referred to OEM and the relay is yet to be tested.
765/ 400kV ICT 1 & 2 at Kurnool SS also tripped for the fault due to operation of Buccholz relay
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 22/52
and the same has also been referred to OEM by PGCIL (SR-1) Recommendations:
APTRANSCO is recommended to sort out the issues with their distance protection relay (7SA522) which maloperated and caused unwarranted tripping of 400kV Ghani – Narnoor line-1. The time synchronization of relays at Ghani end also shall be ensured.
PGCIL (Sr-1) is recommended to submit a detailed report regarding operation of ICT Buchholz relay for through fault conditions along-with remedial measures suggested by OEM.
18 Tripping of 765/400kV ICT-2 at Kurnool
02-06-2019 at 17:41 hrs
ICT-2 got tripped on operation of Back up directional over current due to through fault (Y-B phase fault).
GI-2
Tripping of 765 KV Kurnool - NPS line-1: Kurnool PG (PGCIL-SR-1) end:
As per FIR/ DR/ EL/ TR line tripped in 3-ph at 17:41:23.865 hr. on R-E fault due to operation of DPR Z1. The fault was due to jumper dislocation near isolators due to heavy gale winds. A/R not attempted due to PLCC channel failure.
Nellore PS (PGCIL-SR-1) end:
As per FIR/ DR/ EL/ TR line tripped in 3-ph at 17:41:24.421 hr. on R-E fault due to operation of DPR Z2 (TZ2-0.5 sec). Line tripped in Z-2 time due to non-receipt of carrier due to PLCC channel failure.
Tripping of 765 KV Kurnool - NPS line-2: Kurnool PG (PGCIL-SR-1) end:
As per FIR/ DR/ EL/ TR line tripped at 17:41:15.815 hr. due to operation of OVR Stg.1 and DT was sent to other end.
Nellore PS (PGCIL-SR-1) end:
As per FIR/ DR/ EL/ TR line did not trip since DT was not received due to PLCC channel failure. Tripping of 765/ 400kV ICT-2 Kurnool (PGCIL –SR-1):
As per FIR/ DR/ EL/ TR ICT-2 tripped at 17:41:23.816 hr. on R-Y fault due to operation of HV side Back up protection.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 23/52
PGCIL (Sr-1) vide mail dated 28.07.2019 informed that 1500MVA ICT-2 at Kurnool tripped on DOC due to through fault in 765kV lines which were tripped at same time. Fault due to heavy swing of jumpers and connector damage on heavy gale & rain at Kurnool SS and this caused tripping of 765kV lines also. All damaged connectors were replaced and jumper tightening checked and all elements taken into service.
Deliberations:
At 17:41 hr. 765kV Raichur – Kurnool line tripped on another Y-E fault on operation of distance protection. The line auto-reclosed successfully. But after 2sec, subsequent B-E fault occurred on the line and it tripped in 3-ph.
Simultaneously 765 KV Kurnool - NPS line-1 tripped on Y-E fault due to jumper dislocation near isolators due to heavy gale winds on operation of distance protection. A/r was not attempted due to PLCC channel failure. Subsequently 765 KV Kurnool - NPS line-2 tripped on operation of Overvolatage Stg.-1 protection at Kurnool end. Nellore PS end did not trip since DT was not received due to PLCC channel failure. At the same time 765/ 400kV ICT-2 at Kurnool also tripped on operation of HV side High set O/C protection.
Remedial Measures Taken: PGCIL (SR-1) informed that the terminal connector quality at 765kV Maheshwaram SS is found
to be inadequate and the same has already been replaced. Healthiness of PLCC channel of 765 KV Kurnool - NPS line-1& 2 has been restored.
Recommendations: PGCIL (SR-1) is requested to check the operation of ICT HV side High set O/C protection for
through fault and submit a report regarding the same.
19 Tripping of 400kV JSW-Guttur line
02-06-2019 at 18:17 hrs
Line tripped due to OV St-1 protection operation at JSW end and DT was sent to Guttur end. At Guttur end B ph voltage was observed to be lesser comparing to R ph and Y ph(Vr-249kV, Vy-255kV and Vb-230kV).
GI-2
JSWEL end:
As per FIR/ DR/ EL/ TR line tripped at 18:16:19.203 hr. on operation of OVR stg.-1 protection and DT sent to Guttur end. (Vr= 249kV, Vy=250kV, Vb=230kV, Tov=6sec) [ As per OVR-2018, Grading is F i.e, 110%, 6sec]
Guttur (KPTCL) end:
As per FIR/ DR/ EL/ TR line tripped at 18:09:52.543 hr. on receipt of DT .At the same time OVR stg.-1 protection operated atGutturand DT sent to JSWEL end. (Vr= 251kV, Vy=245kV, Vb=245kV, Tov=12sec) [ As per OVR 2019, Grading is D i.e, 110%, 8sec)
OVR grading (2018 ) at 400kV JSWEL end:
OVR grading (2019 ) at 400kV Guttur end:
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 24/52
Remedial Measures Taken: KPTCL vide mail dated 30.07.2019 informed that from the Guttur end DR, R phase voltage was
found to be more when compared to Y&B phases. Due to higher ratio error, R phase CVT of JSWEL line at Guttur was tagged for replacement. The suspected CVT has been replaced by new CVT on 25.07.2019.
Recommendations: JSWEL is recommended to monitor the B-ph CVT of 400kV JSWEL-Guttur line (due to lower B-ph
voltage compared to other two phases). The same shall be replaced if the issue persists.
20 Tripping of 220kV Idukki-Udumalpet line
05-06-2019 at 15:13 hrs
Triggering incident was R-Y-Earth fault in the line. Carrier aided protection not operated at Udumalpet end.
GI-1
Idukki (KSEBL) end:
As per FIR/ DR/ EL/ TR line tripped at 15:10:09.260 hr. on R-B-E fault due to operation of DPR Z1 protection (I a = 2 . 4 9 6 k A , I b = 3 5 4 . 6 A , I c = 8 . 6 7 2 k A ; 8.962 km)
As per FIR carrier was sent to Udumalpet end. Udumalpet (TANTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 15:06:37.918 hr. on R-B-E fault due to operation of DPR Z2 protection. ( Line tripped with a delay of 350msec)
Recommendations: For the subject line, the following shall be carried out by TANTRANSCO in coordination with
KSEBL: (iii) End-to-end testing for DT/ permissive & other signals may be ensured by testing at both the
ends. (iv) Healthiness of PLCC system components ( hardware and software) at both the ends shall be
checked and faulty components shall be repaired/ replaced .
21 Tripping of 400kV JSW -Guttur line and 400 kV Kaiga - Guttur line-2
05-06-2019 at 18:27 hrs
Y-phase to earth fault occurred in 400kV Kaiga-Guttur line-2. A/r was successful at Guttur end. At Kaiga end A/r was not attempted and breakers got tripped due to operation of Pole discrepancy (1.65 Sec). 400kV JSW-Guttur line tripped on operation of over-voltage at Guttur and direct trip was received at JSW. From DR of Guttur, it is observed that there was swell in R & Y phase voltage for few cycles
GI-2
Tripping of 400kV JSW -Guttur line: JSWEL end:
As per FIR/ DR/EL/ TR line tripped at 18:27:13.103 hr. on receipt of DT from Guttur end. Guttur end:
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 25/52
As per FIR/ DR/EL/ TR line tripped at 18:28:24.670 hr. on operation of OVR stg. 1 (Vr = 259.160 kV, Vy= 152.718 kV, Vb= 254.238 kV; Tov = 5 sec)[ Grading not followed. Grading issued was D = 110%, 8sec].
Tripping of 400kV Kaiga – Guttur line-2: Kaiga (NPCIL) end:
As per FIR/ DR/ TR line tripped at 18:27:08.314 hr. on Y-E fault due to operation of DPR Z1 protection (132.8 km) and Pole discrepancy operation.
As per EL line tripped at 18:27:06.951 hr.on Y-E fault due to operation of DPR Z1 protection and Pole discrepancy operation.
As per EL OVR stg.-1 operated at 18:27:11.488 hr. [ Grading – F; 110% 6 sec]
Guttur (KPTCL) end:
As per FIR/ DR/ EL/ TR line tripped in Y-ph 18:27:08.347 hr. on Y-E fault due to operation of DPR Z1 protection. The line successfully auto-reclosed but subsequently tripped at 18:27:14.592 hr. due to DT receipt from OVR operation at Kaiga end.
Deliberation:
As per the tripping files 400kV KaigaGuttur line-2 tripped in Y-phat 18:27:08.314 hr. on Y-E fault due to operation of DPR Z1 protection. Tie CB (02C) tripped in 3-ph but Main CB tripped only in Y-ph. After 80msec, Main CB (02B) B-ph also opened.
Due to non-opening of R-ph CB PD operated and tripped the line 1.7 sec after the fault.6 secs after the fault, OVR stg.1 protection also operated. Since OVR pick up not indicated, grading could not be verified.
OVR Grading(2018) at 400kV Kaiga end:
OVR Grading(2019) at 400kV Guttur end:
Remedial Measures Taken: KPTCL vide mail dated 30.07.2019 informed that from the Guttur end DR, R phase voltage was
found to be more when compared to Y&B phases. Due to higher ratio error, R phase CVT of JSWEL line at Guttur was tagged for replacement. The suspected CVT has been replaced by new CVT on 25.07.2019.
Recommendations: NPCIL (KGS) is recommended to identify the issue related to unsuccessful A/R attempt of 400kV
Kaiga – Guttur line and non-opening of R-pole CB. It is recommended to check the healthiness of all breakers including breaker timing.
Time synchronization of DR and EL at Kaiga end shall be ensured.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 26/52
22 Tripping of 400kV Dhoni-Munirabad line
06-06-2019 at 02:01 hrs
Line got tripped at Dhoni end. From DR Zone-3 start, PSB and A/r block was observed.
GI-2
Tripping of 400kV Narendra – Guttur Line -1: Guttur (KPTCL) end:
As per FIR/ DR/EL/ TR line tripped at 02:00:57.875 hr. on R-Y fault due to operation of DPR Z1 protection. ( Ir=7.9kA, Iy=9.01kA, 31.6 km)
Narendra (PGCIL –Sr-2) end:
As per FIR/ EL/ TR line tripped at 02:00:57.895 hr. on R-Y fault due to operation of DPR Z1 protection. The fault was due to tower collapse.
As per DR line tripped at 02:00:59.061 hr. on R-Y fault due to operation of DPR Z1 protection. Tripping of 400kV Narendra – Guttur Line -2: Guttur (KPTCL) end:
As per FIR/ TR line tripped on R-Y fault due to operation of DPR Z1 protection. Narendra (PGCIL –Sr-2) end:
As per FIR/ EL/ TR line tripped at 02:02:57.895 hr. on R-Y fault due to operation of DPR Z1 protection. The fault was due to tower collapse.
Tripping of 400kV Dhoni-Munirabad line: Dhoni (KPTCL) end:
As per FIR/ EL/ TR line tripped at 02:01:02.313 hr. on operation of PSB protection. (Tpsb=2 sec) Munirabad (KPTCL) end:
As per FIR/ TR line did not trip at Munirabad end. Deliberations:
KPTCL vide mail dated 30.07.2019 informed that 400kV Guttur-Narendra 1 &2 lines tripped at both the ends on Distance protection at 2.01Hrs as 04 nos of towers collapsed near Medleri village (Tower no:362). M-I & M-II relays of 400kV Dhoni-Munirabad line at Doni have sensed this fault in Zone-3 at 02.00.57.866 hr.However both the relays have dropped after 100msec after clearance of fault in Narendra- Guttur lines. After 2 seconds of the above fault, 400kVDoni-Munirabad line tripped at Doni end on suspected PSB mal operation in Main-1 Siemens relay.The line was holding from Munirabad end.
Remedial Measures Taken: KPTCL vide mail dated 30.07.2019 informed that PSB mal operation is suspected in Main-I
Siemens relay.The issue is referred to the OEM.
Recommendations: KPTCL is recommended to submit a report regarding PSB maloperation along-with the RM
suggested by OEM. Proper legends shall be ensured for digital signals at Doni end.
23 Tripping of 400kV N.P.Kunta-Hindupur line-2
09-06-2019 at 18:14 hrs
R-phase to earth fault occurred in line. Line tripped due to operation of over-voltage stg-2. Voltage swell was observed in DR (R-phase to earth voltage-462kV)
GI-2
NPKunta (PGCIL-SR-1) end:
As per FIR/ DR/EL/ TR line tripped at 18:14:42.854 hr. on operation of OVR stg-2 protection. Hindupur (APTRANSCO) end:
As per DR/ EL/ TR line tripped at 18:14:42 hr. on operation of OVR Stg.-2 Deliberations:
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 27/52
The triggering incidence for the tripping was R-E fault on 400kV N.P.Kunta-Hindupur line-2. During the fault, at NPKunta end Main CB tripped in 3-ph and Tie CB tripped only in R-ph. Tie CB only attempted Auto-reclosure. During A/R deadtime OVR stg.-2 operated (after 200msec to fault) and line tripped in 3-ph.
24 Tripping of 400kV Vemagiri-Vijayawada line-3
10-06-2019 at 9:18 hrs
line tripped due to mal-operation of line Reactor Differential relay at Vijayawada end and DT was received at Vemagiri end
GI-2
Vemagiri PG (PGCIL-SR-1) end:
As per FIR/ DR/EL/ TR line tripped at 09:18:04.868 hr. on receipt of DT from Vijayawada end. Vijayawada (APTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 09:18:04.827 hr. on operation of line reactor differential protection.
Remedial Measures Taken: APTRANSCO informed that line reactor differential was found faulty and the relay has been
taken out of service. Faulty relay replaced on 15.06.2019.
25
Tripping of 400kV KTPS-VII - Julurupadu Line-2 & tripping of 400/220kV ICT-1&2 at Julurupadu substation
10-06-2019 at 8:22 hrs
Y-phase to earth fault occurred in 400kV KTPS-VII -Julurupadu Line-2. Operation of over-voltage stg-2 resulted in tripping of line. 400/220kV ICT-1&2 at Julurupadu on operation of over flux protection.
GI-2
Tripping of 400kV KTPS-VII - Julurupadu line-2: KTPS VII (TSGENCO ) end:
As per FIR/ DR/ EL/ TR line tripped at 08:21:54.939 hr. on operation of OVR Stg.-1 protection. (Tov= 7 sec).
Julurupadu (TSTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 08:21:54.961 hr. on receipt of DT from KTPS end. Tripping of 400/220kV ICT-1 at Julurupadu:
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 28/52
As per FIR/ DR/ EL/ TR ICT-1 tripped on both sides at 08:22:09.016 hr. on operation of Overflux protection.
Tripping of 400/220kV ICT-2 at Julurupadu:
As per FIR/ DR/ EL/ TR ICT-2 tripped on both sides at 08:25:35.975 hr. on operation of Overflux protection.
Tripping of 400kV Julurupadu – Suryapet line-1: Julurupadu (TSTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 08:22:04.002 hr. on operation of OVR stg.-1 protection and DT was sent to Suryapet end. (Tov=6sec)
Suryapet (TSTRANSCO) end:
As per FIR line tripped at 08:22hr. on receipt of DT from remote end. Deliberations:
In the antecedent condition, 400kV KTPS-VII - Julurupadu line -1 was under outage for attending hotspots. 400kV SuryapetJulurupadu 2 was under outage to contain overvoltage. At 08:21 hr. 400kV KTPS-VII - Julurupadu line-2 tripped at KTPS end on OVR stg.-1 operation and at Julurupadu on DT receipt. Subsequently OVR appeared at Manuguru end and tripped 400kV Manuguru – Julurupadu line 2. Then due to overvoltage at Julurupadu, 400kV Julurupadu – Suryapet line-1 tripped. Then both ICT’s at Julurupadu tripped on Overflux protection.
The SCADA plot of 400kV Bus voltage of Julurupadu showed the Bus voltage as very high (478kV).
OVR Grading 2019 at 400kV Julurupadu SS:
OVR Grading 2019 at 400kV KTPS SS:
Recommendations:
TSTRANSCO is recommended to check the v/f settings of ICT-2 at Julurupadu since ICT-1 & 2 tripped at different time ( 3mins difference).
DGA analysis of ICT-2 shall be carried out to ensure healthiness of ICT owing to very high voltage and the tap position of ICT-2 also to be checked.
26 Tripping of 400kV Vemagiri-GMR line-1&2
14-06-2019 at 09:33 hrs
Line-1 tripped on Y-Phase to earth fault due to Y-Phase LA failure at Vemagiri end. Line-2 tripped at GMR end only
GI-2
Tripping of 400kV Vemagiri-GMR line-1: Vemagiri (APTRANSCO) end:
As per FIR/ EL/ TR line tripped at 09:33 hr. on Y-E fault due to LA blast as a result of operation of
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 29/52
DPR Z1. (24.465 kA)
As per FIR line attempted A/R but tripped due to persisting fault. GMR end:
No tripping files furnished Tripping of 400kV Vemagiri-GMR line-2: Vemagiri (APTRANSCO) end:
As per FIR/ DR/ EL/ TR line did not trip at Vemagiri end GMR end:
No tripping files furnished.
As per SRLDC report line tripped at GMR end on SOTF /TOR trip. Recommendations:
APTRANSCO is recommended to submit Equipment failure report (LA failure) to CEA. GMR is recommended to submit a report regarding tripping of 400kV Vemagiri-GMR line-2 at
GMR end along-with the related tripping files.
27 Tripping of 400/220kV ICT-2 at Hoody substation
16-06-2019 at 19:20 hrs
ICT-2 got tripped on operation of over-flux protection
GI-2
Hoody (KPTCL) end:
As per FIR / DR/ EL/ TR ICT-2 tripped at 19:19:09.170 hr. on operation of HV side Overflux protection operation.
KPTCL informed that B-ph voltage was high due to neutral floating due to loose wiring in voltage circuit.
Remedial Measures Taken:
KPTCL vide mail dated 30.07.2019 informed that:
Loose wire found in voltage circuit rectified. The Over Flux settings have been revised as follows:
v/f setting for alarm: 1.1 time Vnominal, Time delay 20 seconds; v/f trip setting : v/f is 1.2 time Vnominal;Time delay 10 seconds
Recommendations: KPTCL is recommended to adopt v/f settings as per manufacture suggested curve.
v/f setting for alarm: 1.1 time Vnominal; Time delay 10 seconds; v/f trip setting : v/f is 1.2 time Vnominal;Time delay 60 seconds
28 Multiple tripping at 220kV Nunna substation
16-06-2019 at 06:16 hrs
Triggering incident was failure R phase CT of 220/132kV transformer (connected to 220kV Bus-2) in 220kV Nunna station. Bus-2 bus bar protection operated resulting in tripping of elements connected to 220kV Bus-2. 2.63 Seconds later a 2nd fault occurred in Bus-1 due to fault getting extended from Bus-2 CT failure which inturn resulted in tripping of elements connected to 220kV Bus-1
GI-1
Tripping of 220kV Nunna SS
As per FIR/ DR/ EL/ TR Bus-2 at Nunna SS tripped at 04:19:59.735 hr. on operation of Bus Bar Protection due to B-ph CT blast.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 30/52
Tripping of 400/ 220kV ICT-1 at Vijayawada (PGCIL-SR-1):
As per FIR/ DR/ EL/ TR 400/ 220kV ICT-1 tripped at 06:15:51.550 hr. due to operation of BBP at 220kV Nunna SS.
Tripping of 400/ 220kV ICT-2 at Vijayawada (PGCIL-SR-1):
As per FIR/ DR/ EL/ TR 400/ 220kV ICT-2 tripped at 06:15:51.550 hr. due to operation of BBP at 220kV Nunna SS.
Tripping of 400/ 220kV ICT-3 at Vijayawada (PGCIL-SR-1):
As per FIR/ DR/ EL/ TR 400/ 220kV ICT-3 tripped at 06:15:51.366 hr. due to operation of BBP at 220kV Nunna SS.
Tripping of 400kV KTPS – Nunna line: KTPS (TSGENCO) end:
As per FIR line did not trip at KTPS end. Nunna (APTRANSCO) end:
As per FIR line tripped at 06:16 hr. on operation of Bus Bar protection at 220kV Nunna SS.
Tripping of 220kV Gunadala SS
As per FIR 220kV Nunna – Gunadala lines 1 & 2 tripped at Nunna end due to operation of BBP at Nunna. This led to complete loss of supply to 220kV Gunadala SS.
Deliberations:
Bus configuration : Double Bus with Bus coupler.
The triggering incidence for complete outage of 220kV Nunna SS was failure of B phase CT of 220/132kV transformer (connected to 220kV Bus-2) in 220kV Nunna station. This resulted in operation of Busbar protection for Bus-2.
After 2.63sec, R-ph fault occurred in Bus-1 and led to operation of Busbar protection for Bus-1.
Recommendations: APTRANSCO is recommended to submit Equipment Failure Report regarding the failed CT to
CEA. APTRANSCO to sort out time synchronization issues in 220kV Nunna SS.
29
Tripping of 400kV Hiriyur-Nelamangala line-1 and 400kV Gooty-Nelamangala line
22-06-2019 at 04:06hrs
400kV Hiryur-Nelamangala line-1 : 'Y' phase bushing of Hiriyur line-1 reactor failed at Nelamangala end resuting in a R-Y phase fault. Direct trip was sent to Hiryur. 400kV Gooty-Nelamangalaline : Line tripped at Nelamangala end only due to mal-operation of Main-2 distance protection relay (THR).
GI-2
Tripping of 400kV Hiriyur-Nelamangala line-1: Hiriyur (PGCIL-SR-2) end:
As per FIR/ DR/ EL/ TR line tripped at 04:06:01.594 hr. on R-Y fault due to operation of DPR Z2 CAT protection. (Ir= 2.73 kA, Iy= 2.143 kA, 135.2 km)
Neelamangala (KPTCL) end:
As per FIR/ DR/ EL/ TR line tripped at 04:06:33.612 hr. on operation of reactor protection (Ir -
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 31/52
24.78 kA, Iy-25.27kA, Ib - 0.55 kA; 0.2 km). 400kV Hiriyur-Nelamangala line-1 reactor Y phase bushing failed triggering fire which caused line R and Y phase fault.
Tripping of 400kV Gooty – Neelamangala line: Gooty (PGCIL-Sr-1) end:
As per FIR line did not trip at Gooty end. Neelamangala (KPTCL) end:
As per FIR/ DR/ EL/ TR line tripped at 04:06 hr. on operation of DPR Reverse Zone.
Deliberations:
KPTCL vide mail dated 30.07.2019 informed that Y' phase bushing of 400kV Hiriyur-Nelamangala line-1 reactor failed followed with fire. This led to tripping of the line on operation of distance protection. Along with this, 400kV Nelamangala-Gooty line tripped at Nelamangala end due to suspected mal operation of Main-2 THR relay.
Remedial Measures Taken: KPTCL vide mail dated 30.07.2019 informed that action has been taken to replace the Main-2
THR relay at Neelamangala end by commissioning new CRP mounted in bay KIOSK under R&M works. Presently the work of Mysore-1 and Bidadi-1lines have been taken up. Cable laying work is under progress. After completing the above bays Gooty bay will be taken up.
Recommendations:
KPTCL is recommended to submit equipment failure report to CEA regarding the reactor bushing failure and also to sort out time synchronization issues of 400kV Hiriyur-Nelamangala line.
30 Tripping of 400/220kV ICT-1&2 at Munirabad substation
24-06-2019 at 20:50 hrs
400/220kV ICT-1&2 at Munirabad end got tripped due to operation of High set of backup earth fault relay during failure of Y phase CT in 220kV Munirabad-Kalyani steel feeder at Kalyani steel end
GI-2
Tripping of 220kV Munirabad – Kalyani steel line: Munirabad (PGCIL –SR-1) end:
As per FIR/ DR/ EL line tripped at 20:50:55.835 hr. on Y-B-E fault due to operation of DPR Z1 protection (13.6 kA). The Y-E fault was due to failure of Y-ph CT in 220kV Munirabad-Kalyani steel line at Kalyani steel end and B-E fault was due to failure of B-ph PT.
As per EL, LBB of 220kVMunirabad-Kalyani steel line operated at 20:50:55.924 but immediately it got reset.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 32/52
Tripping of 400/220kV ICT-1 at Munirabad:
As per FIR/ DR/ EL / TR ICT-1 tripped at 20:50:55.758 hr. on operation of High set back up E/F protection (5.2 kA).
Tripping of 400/220kV ICT-2 at Munirabad:
As per FIR/ DR/ EL / TR ICT-1 tripped at 20:50:55.734 hr. on operation of High set back up E/F protection (5.3 kA).
Remedial Measures Taken: KPTCL vide mail dated 30.07.2019 informed that 220kV Kalyani Steel line distance relay settings
have been reviewed and revised consequent to the tripping.
Recommendations: KPTCL is recommended to submit equipment failure report to CEA regarding the CT and PT
failure.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 33/52
31
Tripping of HVDC Talcher-Kolar Pole-1
31-05-2019at 18:30
hrs
Pole 1 tripped on Line fault. Pole-1 restarted three times and went into RVO mode. The fourth fault caused tripping of the pole. Pole-2 went to ground return mode. Remarks: SPS Trip Signal-1 and Trip Signal-2 operated at Kolar end since total power loss was ~1700 MW
Kolar (PGCIL-SR-2) end:
As per FIR/ DR/ EL/ TR Pole-1 tripped at 18:30:22.418 hr. on operation of DC line differential Protection.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 34/52
Tripping of HVDC Talcher-Kolar Pole-1&2
05-06-2019 at 19:01 hrs
HVDC Talcher-Kolar Pole-1 tripped on receipt of ESOF (Emergency Switch On to Fault) signal at Kolar from Talcher end. Pole-2 went to metallic return mode with a power flow of 900MW at Kolar end. Subsequently at 19:02 Hrs, HVDC Talcher-Kolar Pole -2 also tripped due to operation of undervoltage protection at Kolar end. Remarks: After tripping of Pole-1 SPS Trip Signal-1 operated leading to total load relief of 700MW.
Tripping of HVDC Talcher-Kolar Pole-1 at 18:53 hr: Kolar (PGCIL-SR-2) end:
As per FIR/ DR/ EL/ TR Pole-1 tripped at 18:53:23:471 hr. on operation of ESOF (Emergency switch off ) signal from Talcher end. Tripping of Pole-1 initiated TK SPS-1 leading to load relief of 700MW.
As per TR the 400kV converter transformer isolator (B-ph) had opened under load, following which the operator at Talcher had initiated manual ESOF.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 35/52
Tripping of HVDC Talcher-Kolar Pole-1 at 19:01 hr: Kolar (PGCIL-SR-2) end:
In the antecedent condition HVDC Pole-1 was out of service and Pole-2 was in Monopolar Metallic Return mode with a power of 900W.
As per FIR/ DR/ EL/ TR Pole-2 tripped at 19:01:50:242 hr. on operation of Undervoltage protection due to loss of incoming NTPC lines 1- 4.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 36/52
Tripping of HVDC Talcher-Kolar Pole-1
08-06-2019 at 12:10 hrs
Pole 1 tripped on receipt of ‘ESOF” from other side at 12:10 Hrs. Pole-2 shifted to metallic return mode of operation. Remarks: SPS Trip Signal-1 operated at Kolar end leading to total load relief of 700MW.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 37/52
Kolar (PGCIL-SR-2) end:
As per FIR/ DR/ EL/ TR Pole-1 tripped at 12:10:07.856 hr. on operation of ESOF (Emergency switch off ) signal from Talcher end. Tripping of Pole-1 initiated TK SPS-1 leading to load relief of 700MW.
Tripping of HVDC Talcher-Kolar Pole-2
12-06-2019 at 12:24 hrs
While carrying out the switching operation of charger-2 to Charger-3 for enabling maintenance by OEM, Pole -2 got tripped due to suspected over voltage in 24V system. After tripping of Pole-2, Pole-1 continued to operate in metallic return mode Remarks: SPS at Kolar did not operate since total power loss after tripping of Pole-2 was less than 500 MW
Kolar (PGCIL-SR-2) end:
As per FIR/ DR/ EL/ TR Pole-2 tripped at 12:24:05:397 hr. on operation of ESOF signal due to power supply fault in 24V DC system.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 38/52
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 39/52
Remedial Measure Taken: PGCIL (SR-2) informed that the power supply fault was due to battery changeover switch
problem and the same will be rectified in next opportunity shutdown.
32
220kV Lower Sileru-KTPS line
01-06-2019 at 00:00 hrs
R-phase to ground fault. Auto-reclose was successful at Lower sileru end. A/r is not enabled at KTPS
GI-1
KTPS (TSGENCO) end:
As per FIR line tripped at 00 hr. on R-E fault due to operation of DPR Z1. (84.1 km)
As per DR/ EL/ TR line tripped at 13:28:07.947 hr. on R-E fault due to operation of DPR Z1. (84.1 km)
Lower Sileru (APGENCO) end:
As per FIR/ TR line tripped at 00 hr. on R-E fault due to operation of DPR Z1 and auto-reclosed.
220kV Lower Sileru-KTPS line
02-06-2019 at 15:30 hrs
R-phase to earth fault occurred in line. Auto-reclose was successful at Lower sileru end. A/r is not enabled at KTPS.
GI-1
KTPS (TSGENCO) end:
As per FIR/ DR/ EL/ TR line tripped at 15:24:21.280 hr. on R-E fault due to operation of DPR Z1. (99.69 km)
Lower Sileru (APGENCO) end:
As per FIR/ TR line auto-reclosed successfully on R-E fault due to operation of DPR Z1.
220kV Lower Sileru-KTPS line
09-06-2019 at 11:58 hrs
B-phase to earth fault occurred in line. Zone-2 operated at KTPS and Earth fault at Lower sileru. Suspected high resistance fault.
GI-1
KTPS (TSGENCO) end:
As per FIR/ DR/ EL/ TR line tripped at 11:58:27.534 hr. on B-E fault due to operation of DPR Z2. (48.69 km; TZ2= 350msec)
Lower Sileru (APGENCO) end:
As per FIR/ TR line tripped at 11:58 hr. on B-E fault due to operation of Directional E/F
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 40/52
Protection.
220kV Lower Sileru-KTPS line
12-06-2019 at 14:23 hrs
Y-phase to earth fault occurred in line. Auto-reclose was successful at Lower Sileru end. A/r is not enabled at KTPS
GI-1
KTPS (TSGENCO) end:
As per FIR/ DR/ EL/ TR line tripped at 14:23:07.593 hr. on Y-E fault due to operation of DPR Z1 protection. (84.18km)
Lower Sileru (APGENCO) end:
As per FIR/ TR line tripped at 14:23hr. on Y-E fault due to operation of DPR Z1 Protection and auto-reclosed.
TSGENCO informed vide mail dated 30.09.2019 that in view of phasing out of the units, the implementation of the scheme in 220 KV generating stations is under discussions regarding relay settings & mapping
Recommendations: ATRANSCO in coordination with TSTRANSCO to ensure frequent patrolling and proper
maintenance of ROW by attending all tree clearance issues.
III. Details of Trippings due to Failure or Non-operation of Auto-Reclose:
Sl. No. Element Date & Time Reason
1 Tripping of 400kV Ghani-Narnoor line-1
21-05-2019 at 15:11 hrs
B-phase to earth fault occurred in line. Auto-reclose was not successful as fault was persistent in nature. Fault was cleared in zone-2 time during A/r attempt
Ghani (APTRANSCO) end:
Asper FIR/ DR/ EL line tripped in 3-ph on B-E fault on operation of DPR Z1. Narnoor (APTRANSCO) end:
As per FIR/ DR/ EL line tripped in B-ph on B-E fault due to operation of DPR Z2 CAT protection and attempted A/R. (14.63kA; 16.86kA) But since the fault was persisting line tripped in 3-ph after auto-reclosure due to operation of SOTF operation. During SOTF operation since fault was detected in Z2 and no carrier was received from remote end line tripped after Z2 delay of 350msec.
Deliberations:
The reason for the tripping was B-E fault at 15:13:28 hr. on 400kV Ghani-Narnoor line-1. In antecedent condition at Ghani end Main CB was already open and Tie CB issued 3-ph trip (did not attempt A/R) on operation of distance protection Z1. Narnoor end attempted autoreclosure on operation of DPR Z2 CAT. But since the fault was persisting in nature subsequently tripped in 3-ph. But during 3-ph tripping since no carrier was received from Ghani end (since Ghani end already open) Narnoor end tripped with a Zone-2 delay of 350msec.
Recommendations: APTRANSCO is recommended to send a detailed report regarding non-availability of Main CB
(Main CB was already in tripped condition in antecedent condition) during the tripping and non-attempt of auto-reclosure by Tie CB at Ghani end.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 41/52
2 Tripping of 400 kV Kudgi PG (Narendra-New) - Tumkur line - 2
21-05-2019 at 15:30 hrs
Y-phase to earth fault occurred in line. Auto-reclose was successful at Tumkur. At Kudgi end Auto-reclose was not attempted
Narendra-New (PGCIL-SR-2) end:
As per FIR/ DR/ EL/ TR line tripped in Y-ph at 15.30.03.360 hr. on Y-E fault due to operation of DPR Z2 CAT protection, but after 800msec tripped in 3-ph. [subsequentlyOVR appeared and line tripped at 15:30.08.141 hr. on OVR operation?]
Tumkur (PGCIL-SR-2) end:
As per FIR/ DR/ EL/ TR line tripped in Y-ph on Y-E fault due to operation of DPR Z1 operation and auto-reclosed successfully. [121.6 km]
PGCIL (SR-2) informed that the delay in goose signal communication between Main-2 relay and BCU at Kudgi PG end led to the tripping of the line. Due to the delay, the same was understood as subsequent fault and relay issued 3-ph trip command.
3 Tripping of 400kV Talarichevu - Jamalamadugu ckt-1
21-05-2019 17:51 hrs
B -ph to ground fault in the line. Auto reclose operated at Talarichevu end but tripped on persistent fault. Auto reclose not attempted at Jamalamadugu end
Talarichevu (APTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped in B-ph at 17:59:55.960 hr. B-E fault due to operation of DPR Z1 operation and auto-reclosed. But subsequently line tripped in 3-ph on SOTF operation due to persisting fault.
Jamalamadugu (APTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped in B-ph at 17.59.52.449 hr. B-E fault due to operation of DPR Z1 operation but after 300msec tripped in 3-ph due to A/R configuration problem in BCU (15.7 km; 7.13 kA).
Remedial Measures Taken: APTRANSCO informed that non-attempt of A/R at Jamalamadugu SS was due to A/R
configuration problem in BCU and the same has been rectified.
4 Tripping of 400kV Talarichevu - Jamalamadugu ckt-1
22-05-2019 at 19:21 hrs
R phase to Earth fault in the line. At Jammalamadugu end A/r operated and line tripped due to persistent fault. Main CB A/r not attempted at Talarichevu
Talarichevu (APTRANSCO) end:
As per FIR/ DR/ EL line tripped in R-ph at 19:19:48.512 hr. on R-E fault due to operation of DPR Z1 operation. Main CB A/R not successful and it tripped in 3-ph after 500msec but Tie CB reclosed and tripped due to persisting fault.
Jamalamadugu (APTRANSCO) end:
As per FIR/ DR/ EL line tripped in R-ph at 19:46:03.161 hr. on R-E fault due to operation of DPR, Z1 and auto-reclosed but subsequently tripped in 3-ph due to persisting fault.
Recommendations:
APTRANSCO is recommended to submit a report regarding non-attempt of A/R by Main CB at Talarichevu end of 400kV Talarichevu - Jamalamadugu ckt-1.
e
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 42/52
5 Tripping of 400 kV Kudgi PG (Narendra-New) –Tumkurline-2
23-05-2019 at 22:05 hrs
Y-phase to earth fault occurred in line. Auto-reclose was successful at Tumkur end. At Kudgi(PG) end A/r was not attempted due to A/r block
Kudgi PG(Narendra-New) (PGCIL-SR-2) end:
As per FIR/ DR/ EL/ TR line tripped in Y-ph at 22:05:09.260 hr. on Y-E fault due to operation of DPR Z1. But immediately tripped in 3-ph (22:05:09.349 hr.) due to A/R lockout. After 4 secs, OVR Stg.-1 operated and sent DT to other end (Tov= 4 sec; Vr = 240.4 kV, Vy= 144.96kV, Vb=236.62 kV). [ Grading - I, 109%, 4sec]
Tumkur (PGCIL-SR-2) end:
As per FIR/ DR/ EL/ TR line tripped in Y-ph at 22:05:09.352 hr. on Y-E fault and auto-reclosed successfully. Later line tripped in 3-ph on receipt of DT from Kudgi end.
OVR Grading 2018 for Kudgi PG:
PGCIL (SR-2) informed that the reason for non-attempt of A/R at Kudgi PG end was due to carrier fail alarm which issued A/R lockout.
Remedial Measures Taken: PGCIL (SR-2) informed that healthiness of carrier communication has been ensured after the
incidence.
6 400 KV Thiruvelam – Palavadi line-1
28-05-2019 at 18:04 hrs
B-phase to earth fault. A/r attempt could not be validated.
Thiruvalem (TANTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped in 3-ph at 18:02:45.019 hr. on receipt of DTT from other end. A/R started in B-ph for B-E fault on operation of DPR Z2 CAT (179.8 km, 3.168kA) but immediately line tripped in 3-ph due to DT receipt.
Palavadi (TANTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped in B-ph at 18:04:39.553 hr. on B-E fault but did not reclose and subsequently tripped in 3-ph.
TANTRANSCO informed that due to breaker unhealthy feedback (no spring charge due to station supply failure) 3 phase trip extended
TANTRANSCO informed that non-attempt of A/R at Palvadi end was due to failure of AC station supply.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 43/52
Recommendations: TANTRANSCO is recommended to check sending of DT from Palvadi end during 3-ph trip at
Palvadi. The time synchronization issues between Thiruvalem and Palvadi shall also be rectified.
7 Tripping of 400kV Pugalur-Karaikudi line-1
31-05-2019 at 17:44 hrs
R-phase to earth fault occurred in line. Auto-reclose was successful at Karaikudi, At Pugalur end there was 3-phase trip
Pugalur (PGCIL-SR-2) end:
As per FIR/ DR/ EL/ TR line tripped in R-ph at 17:44:52.684 hr. on R-E fault due to operation of DPR Z1. A/R attempted but not successful and after 300msec line tripped in 3-ph.
PGCIL-SR-2 informed that A/R was unsuccessful due to low CB air pressure. Karaikudi (PGCIL-SR-2) end:
As per FIR/ DR/ EL/ TR line tripped in R-ph at 17:44:42.369 hr. on R-E fault due to operation of DPR Z1 and auto-reclosed successfully (43.8 km).
Recommendations: PGCIL (SR-2) is recommended to ensure proper condition monitoring of their CB’s such as
sufficient air pressure.
8 Tripping of 400kV Ramagundam-Ghanapur line
02-06-2019 at 13:23 hrs
R-phase to earth fault occurred in line. Auto-reclose was successful at Ghanapur and A/r was not attempted at Ramagundam due to DT receive
Ramagundam (NTPC) end:
As per FIR/ DR/ EL/ TR line tripped in R-ph on R-E fault due to operation of DPR Z1. A/R started but unsuccessful due to receipt of DT at 13:24:31.473 hr. [PLCC DT increment indicated]
Ghanapur (PGCIL-SR-1) end:
As per FIR/ DR/ EL/ TR line tripped in R-ph on R-E fault due to operation of DPR Z1 and autoreclosedsuccessfully.(3.03kA)[No PLCC DT increment]
Remedial Measures Taken: PGCIL (SR-1) vide mail dated 28.07.2019 informed that the fault was due to agrifire. Pamphlets
distributed to farmers and informed all locals not to put fire under the line. DT received at RDM end due to BPL make PLCC problems and same is being replaced with new PLCC panels at both ends. New PLCC panels received at site and will be commissioned by month end.
9 Tripping of 400kV Kalikiri-RYTPP line-2
02-06-2019 at 19:15 hrs
B-phase to earth fault occurred in line. Auto-reclose was successful at Kalikiri and A/r not attempted at RYTPP due to A/r lockout
Kalikiri (APTRANSCO ) end:
As per FIR/ DR/ EL/ TR line tripped in B-ph on B-E fault due to operation of DPR Z2 CAT and autoreclosed successfully ( 168 km).
RYTPP (APGENCO) end:
As per FIR/ DR/ EL/ TR line tripped in B-ph at 19:15:40;426 hr. on B-E fault due to operation of DPR Z1. A/R started but unsuccessful dueto A/R lockout signal after 400msec to A/R start.
APGENCO informed that the non-attempt of A/R at RYTPP was due to Goose signal problem. The goose communication hanged and BCU issued lockout due to non updating of CB status by BCU.
Remedial Measures Taken:
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 44/52
APGENCO informed that BCU was restarted and goose communication issue was resolved.
10 Tripping of 400kV VTPS-SURYAPET line-1
02-06-2019 at 13:15 hrs
B-phase to earth fault occurred in line. Auto-reclose was successful at Suryapet end. 2nd fault during reclaim time resulted in three phase trip. At VTPS end A/r was not attempted
VTS – IV (APGENCO) end:
As per FIR/ DR/ EL/ TR line tripped in 3-ph on B-E fault due to operation of DPR Z1. A/R started but immediately line tripped in 3-ph.
Suryapet (TSTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped in B-ph on B-E fault due to operation of DPR Z1 and autoreclosed successfully (3.7kA; 60.02 km). But subsequently line tripped due to second fault in reclaim time.
Remedial Measures Taken: APGENCO informed that A/R was unsuccessful at VTS-IV end due to problem with A/R logic. The
logic was modified on 24.06.2019 and A/R is put into service.
11 Tripping of 765 KV Kurnool - NPS line-1
02-06-2019 at 17:41 hrs
R-phase to earth fault occurred in line. A/r not attempted due to PLCC channel fail.
Kurnool PG (PGCIL-SR-1) end:
As per FIR/ DR/ EL/ TR line tripped in 3-ph on R-E fault due to operation of DPR Z1. The fault was due to jumper dislocation near isolators due to heavy gale winds.A/R not attempted due to PLCC channel failure.
Nellore PS (PGCIL-SR-1) end:
As per FIR/ DR/ EL/ TR line tripped in 3-ph on R-E fault due to operation of DPR Z2 (TZ2-0.5 sec). Line tripped in Z-2 time due to non-receipt of carrier due to PLCC channel failure.
Remedial Measures Taken: PGCIL (SR-1) vide mail dated 28.07.2019 informed that all jumper connections at Kurnool SS
checked and PLCC channel restored by adjusting the levels and line taken into service.
12 Tripping of 400KV-Maheshwaram PG-Mahbubnagar line-1
06-06-2019 at 19:18 hrs
Y phase to Earth fault in the line. A/r not operated at Mahbubnagar
Maheshwaram PG (PGCIL – SR-1) end:
As per FIR/ DR/ TR line tripped in Y phase on Y-E fault due to operation of DPR Z2 CAT and autoreclsoed successfully (117.8 km; 1.04 kA).
Mehaboobnagar (TSTRANSCO) end:
As per FIR/ DR line tripped in 3-ph on Y-E fault due to operation of DPR Z1 and did not attempt A/R.
TSTRANSCO informed that LC will be availed shortly to check non-attempt of A/R at Mehaboobnagar end.
Recommendations: TSTRANSCO is recommended to submit a report regarding non-attempt of A/R at
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 45/52
Mehaboobnagar with Remedial measures taken.
13 Tripping of 400 kV JSW -Guttur line
08-06-2019 at 13:13hrs
B-phase to earth fault occurred in line. A/r was not successful as fault was persistent. A/r not attempted at Guttur.
JSWEL end:
As per FIR/ DR/ EL/ TR line tripped in Y phase at 12:58:51.492 hr. on Y-E fault due to operation of DPR Z2 CAT and autoreclsoed successfully. On reclosure since the fault was persisting in nature, line tripped in 3-ph at 12:58:53.082 hr. with Z2 time delay.
Guttur (KPTCL) end:
As per FIR/ DR/ EL/ TR line tripped in 3-ph on Y-E fault due to operation of DPR Z1 and did not attempt A/R.
KPTCL vide mail dated 30.07.2019 informed that Upon detailed investigation regarding A/R block, problem in Auto Reclosure Selector Switch was observed (for M-I selection). Now A/R priority switch is changed to M-II position and found to be working satisfactory. Action has already been taken to replace the AR priority switch.
Remedial Measures Taken: KPTCL informed that non-attempt of A/R at Guttur end was due to PLCC problem that issued
A/R block. The same has been attended and rectified.
14 Tripping of 400kV Kaiga-Guttur line-2
16-06-2019 at 19:20 hrs
R-phase to earth fault. Auto-reclose attempt at Guttur end was not successful as fault was persistent in nature. Attempt for A/r could not be established from Kaiga end EL
Kaiga (NPCIL) end: As per FIR/ EL/ TR line tripped in 3-ph at 02:53:09.667 hr. on R-E fault due to operation of DPR
Z1 protection. A/R was started but immediately Tie CB issued A/R lockout and tripped. Main CB tripped only after 2 sec i.e, may be due to PD operation.
Guttur (KPTCL) end: As per FIR/ DR/ EL/ TR line tripped in R-ph at 02:53:11.652 hr. on R-E fault due to operation of
DPR Z2 CAT protection. Line autoreclosed but subsequently tripped due to Dt receipt from Kaiga.
Remedial Measures Taken: KPTCL informed that the reason for persisting fault was Insulator flashed over at tower location
231. Line has been charged after attending the line fault.
Recommendations: NPCIL (KGS) is recommended to identify the issue related to unsuccessful A/R attempt of 400kV
Kaiga – Guttur line. It is recommended to check the healthiness of all breakers including breaker timing.
Time synchronization of DR and EL at Kaiga end shall be ensured.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 46/52
IV. Details of Trippings due to PLCC mal-operation:
Sl. No. Element Date & Time Reason
1 Tripping of 400kV Julurupadu-Managuru line -2
20-05-2019 at 15:57 hrs
Line tripped at Julurupadu end only on direct trip receive
Julurupadu (TSTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 15:57:50.167 hr. on receipt of DT. [D/T receipt in EL] Manuguru (TSGENCO) end:
As per FIR/ DR line was holding from Manuguru end. Remedial Measures Taken: TSGENCO vide mail dated 30.09.2019 informed that without any disturbance in the line, DT
signal was generated from FOTE panel(BTPS end) and sent to other end(Julurupadu end) . The panel was checked but no discrepancy was found. In order to avoid unnecessary trippings, a letter was addressed to M/s BHEL requesting to depute the service engineer from GE to check the healthiness and configuration of the newly commissioned FOTE panel at BTPS.
2 Tripping of 400kV Khammam-Mamidapally line-1
27-05-2019 at 18:16 hrs
Line tripped only at Mamidapally end due to suspected PLCC maloperation
Khammam (PGCIL-SR-1) end:
As per FIR/ DR/ EL/ TR line was holding from Khammam end. [ PLCC D/T increment not indicated] Mamidapalli (TSTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 18:16:22.374 hr. on receipt of DT . [D/T receipt signal in EL]
Recommendations: For the subject line, the following shall be carried out by TSTRANSCO in coordination with
PGCIL(SR-I): (i)End-to-end testing for DT/ permissive & other signals may be ensured by testing at both the ends. (ii)Healthiness of PLCC system components ( hardware and software) at both the ends shall be checked and faulty components shall be repaired/ replaced .
3 Tripping of 765 kV Raichur- Kurnool line- 2
02-06-2019 at 17:41 hrs
Line tripped on operation of Over voltage stage-1 at Kurnool end. Direct trip was not sent to Raichur due to failure of PLCC channel at Kurnool and line was holding from Raichur.
Raichur PG (PGCIL-SR-1) end:
As per FIR/ DR/ EL/ TR line was holding from Raichur end. Kurnool (PGCIl-SR-1) end:
As per FIR/ DR/ EL/ TR line tripped at 17:41:16.686 hr. on operation of OVR stg.-1 and DT was sent to other end. Line tripped at Kurnool end only .DT not received at Raichur end due to failure of PLCC channel at Kurnool end.
Remedial Measures Taken: PGCIL(SR-1) informed vide mail dated 28.07.2019 that PLCC channel restored by adjusting the
levels and line taken into service.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 47/52
4
Tripping of 400kV Warangal-Bhoopalapalli line-1 &BoopalppalliChandlapur line-1
08-06-2019 at 1:35 hrs
400kV Warangal-Bhoopalapalli line-1 line tripped only at Boopalappalli end on OV st-1 protection operation and DT was not sent to Warangal end due to failure of both PLCC channels. 400kV BoopalppalliChandlapur line-1 tripped at Boopalpalli end due to DT Receive
Trippping of 400kV Warangal-Bhoopalapalli line-1: Warangal (PGCIL-SR-1) end:
As per FIR line was holding from Warangal end. Bhoopalapalli (TSGENCO) end:
As per FIR/ DR/ EL/ TR line tripped at 01:35:33.243 hr. on operation of OVR Stg.1 but DT was sent to remote end [PLCC D/T increment mentioned].
Trippping of 400kV Bhoopalapalli - Chandlapur line-1: Bhoopalapalli (TSGENCO) end:
As per FIR/ DR/ EL/ TR line tripped at 01:35:34.270 hr. on receipt of DT from other end. [ DT receipt signal in EL]
Chandlapur (TSTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped at 01:35:34.279 hr. on operation of OVR Stg.1 and DT was sent to Bhoopalapalli end.
TSGENCO informed that Unit-2 (600MW) tripped on flame failure on 08/06/2019@01:34Hrs, then Warangal-2 feeder on overvoltage stage-1@01:35Hrs and Chandlapur-2 feeder tripped @ 1:35Hrs on DT CH-1/CH-2 received from Chandlapur. It is also observed that PLCC counter incremented in PLCC panel but PGCIL/Warangal end CB not tripped.
TSGENCO vide mail dated 30.07.2019 informed that TSGENCO is coordinating with TSTRANSCO for testing of End-to-End communication for DT/ permissive & other signals; checking of Healthiness of PLCC system components and also for replacing of faulty components.
Recommendations: For the subject line, the following shall be carried out by TSTRANSCO in coordination with
TSGENCO (i)End-to-end testing for DT/ permissive & other signals may be ensured by testing at both the ends. (ii)Healthiness of PLCC system components ( hardware and software) at both the ends shall be checked and faulty components shall be repaired/ replaced .
6 Tripping of 400kV Kayathar-Kanarpatty line-1 & 2
10-06-2019 at 12:22 hrs
Line-1 & 2 tripped at Kanarpatty end due to spurious DT sent from kayathar end. Feeder did not trip at Kayathar end
Kayathar (TANTRANSCO) end:
As per FIR/ DR/ TR line was holding from Kayathar end, but sent spurious DT to Kannarpatti end. [ PLCC DT increment indicated]
Kannarpatti (TANTRANSCO) end:
As per FIR/ DR/ EL/ TR line tripped on receipt of DT from other end. [ PLCC DT increment indicated]
Remedial Measures taken: TANTRANSCO informed that the spurious sending of DT was due to PLCC panel problem at
Kayathar (NSD570D). The same has been informed to OEM for Corrective measures.
Recommendations:
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 48/52
TANTRANSCO is recommended to submit a report regarding the problem with PLCC panel at Kayathar along-with Remedial Measures suggested by OEM.
7 Tripping of 400kV Ramadugu-Singareni line
11-06-2019 at 08:24 hrs
Line tripped due to Direct Trip receive at Ramadugu end
Ramadugu (TSTRANSCO) end:
As per FIR/ DR/ EL line tripped at 08:24:53.669 hr. on receipt of DT from other end. [ PLCC DT increment indicated]
Singareni (STPP) end:
No tripping files furnished.
Recommendations: Singareni STPP is recommended to submit a detailed report regarding sending of DT from
singareni end that resulted in tripping of 400kV Ramadugu-Singareni line.
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 49/52
1.1 The SLD of 220/ 110 kV Palakkad SS of KSEBL
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 50/52
The SLD of 220/ 110 kV Pothencode SS of KSEBL
1.2 The SLD of 220/ 110 kV Pothencode SS of KSEBL
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 51/52
1.3 The SLD of 220/ 110 kV Malaparamba SS of KSEBL
Annexure-II
Grid Occurrences discussed in the 85thMeeting of PCSC scheduled held on 31st July, 2019 52/52
1.4 The SLD of 220/ 110 kV Sedam SS of KPTCL
Annexure-II
85.I.1. Complete outage of 220kV/110kV Palakkad Substation of KSEB on 04-06-2019 at 14:02 hrs
• Triggering Incident: Testing of Bus Coupler CT was being carried out duringwhich LBB trip got initiated and resulting in tripping of Bus-2.
• All elements were connected to Bus-2• Load Loss-268 MW
3
Double Main with Bus Coupler
Annexure-III
Page 3 of 81
PMU Plots
4
Remedial Actions Furnished
• Warning stickers were provided and other precautionary steps were taken to avoid similar incidents in future.
Bus DR: DR Trigger time-14:02:50.911 hrs
BC_TRIP
BUS1 BB OP
BUS2 BB OP
SCADA PlotDR
Annexure-III
Page 4 of 81
85.I.2. Complete outage of 220kV Pothenkode Substation of KSEB on 04-07-2019 at 01:18 hrs
• Triggering Incident: Failure of suspension insulator (connecting to fly bus) of220kV Pothenkode – Trivendrum ckt-2
• Bus bar protection of Bus-1 and Bus -2 operated• Load Loss- 300MW
5
Annexure-III
Page 5 of 81
85.I.3. Complete outage of 220kV Malaparamba SS of KSEB on 29-05-2019 at 01:12 hrs
• Triggering Incident: R-phase to Earth fault in 220kV Malaparamba Areakodeline due to insulator decapping.
• 220kV Malaparamba Substation was being radially fed from 220kV Areakode• Load Loss-268 MW
6
Annexure-III
Page 6 of 81
DR Analysis
7
PMU Plots
220kV Malaparamba Areakode line
Malaparamba End Areakode End
DR Trigger Time: 01:12:02.376 hrs
Rph fault
R pole open
DR Trigger Time: non readable
Annexure-III
Page 7 of 81
85.II.1. Tripping of 400/230kV MANALI ICT-3 on 13-05-2019 at 2:42 hrs
• During test charging of 110 kV Manali-ETPS -1 , line got tripped on the activation of Back
up relay and Distance relay failed to act.
• ICT-3 got tripped on the activation of HV REF protection.
• After 400ms, Earth wire of 110 kV Manali ETPS -1 got cut and fell on Y ph conductor of 110
kV Manali TPL line resulting in Y ph to Earth fault. 9
TN Reply
Annexure-III
Page 9 of 81
10
DR Analysis
400/110 kV ICT-3 at Manali
DR Trigger Time: 02:42:54.559 hrs
HV REF operated
110 kV Manali ETPS -1
Manali ETPSDR Trigger Time: 02:42:54.510hrs
Distance Forward Pickup
IfaultR=7.34kA
IfaultY=7.298kA
IfaultB=7.421kA
Fault current persistent for 1.1sec
3ph trip
Digital signals in DR are not mapped properly.
DR Trigger Time: 02:42:54.509hrs
Distance Forward Pickup
After 1.1 sec 50/51 operated
DR Trigger Time:NA
ETPS end was in open condition.
110 kV Manali TPL
Manali TPLDR Trigger Time: 02:45:56.045hrs
YN fault (Ifault Y=8.404kA)
Carrier Sent
Distance Forward Pickup
3ph Trip
DR Trigger Time: NA
Line is radial
DR
DR
DR
DR
Annexure-III
Page 10 of 81
PMU Plots
First fault was cleared in 1160ms and
the Second fault got cleared in 80ms.
Points for Review
(1). Non operation of SOTF-distance protection of 110 kV Manali ETPS -1 at
Manali end.
(2). Tripping of 400/110 kV ICT-3 at Manali on REF protection during fault in
110kV line.
(3). 110kV line DR labelling is not proper.
11
Annexure-III
Page 11 of 81
85.II.2. Tripping of 400kV Madurai-Udumalpet line on 16-05-2019 at 18:54 hrs
• 400kV Udumalpet Madurai line tripped only at Udumalpet end on line
under frequency protection operation.
• Suspected R-ph CVT problem.
• Findings and Remedial actions taken shall be furnished.
12
Annexure-III
Page 12 of 81
85.II.3. Tripping of 400kV Kurnool-Srisailam line on 17-05-2019 at 14:10 hrs
• Triggering incident: Y phase to B phase fault in 220kV Narnoor Somayajulapalli line-1.
• 400kV Kurnool Srisailam line tripped only at Srisailam end on Zone-3 distance protection
operation.
TSGENCO reply to SRLDC Email
Points for Review
• Zone-3 distance protection operation at Srisailam without time delay
Annexure-III
Page 13 of 81
PMU Plots
220kV Narnoor Somayajulapalli line-1.Narnoor End Somayajulapalli End
Line was under idle charged condition from
Somayajulapalli end during antecedent
DR Trigger Time: 15:10:31.901 hrs
YN fault
Zone-1DR
400kV Kurnool-Srisailam line.Kurnool End Srisailam End
Line didn’t trip at Kurnool end DR Trigger Time: DR not Furnished. Zone-3
distance operation observed from EL.
14
EL
Annexure-III
Page 14 of 81
85.II.4. Tripping of 220kV Ambewadi-Ponda line on 18-05-2019 at 12:13 hrs
• Triggering incident: BN Fault in the line.
• Line tripped on Zone 3 distance protection operation at Ambewadi end
PMU Plots
15
DR EL Remedial Actions Furnished by KPTCL
The healthiness of Siemens make new Main-II relay is checked once again after the incident and the relay is found to be working satisfactory for all fault conditions.
M-I relay which picked up when B phase voltage dipped to 106kV, fault current 70A IN reached 335A dropped out after 120msec
Annexure-III
Page 15 of 81
85.II.5. Tripping of 400kV/220kV Neelamangala ICT#3 on 19-05-2019 at 16:10hrs and complete loss of 220kV Anchepalya and 220kV Magadi SS of
KPTCL on 19-05-2019 at 16:33hrs
• Triggering incident: BN fault in 220kV Neelamangala DB Pura line-1 and 2 at 16:10hrs due
to snapping of the earth wire during heavy rain.
• ICT-3 got tripped on operation of HV side High Set Over current trip
• 220kV Neelamangala Magadi line tripped on SOTF due to subsequent fault
• At 16:31hrs, 220kV Neelamanagala Anchepalya tripped at Neelamangala end on SOTF due
to BN fault.
• Load loss-80MW 16
Annexure-III
Page 16 of 81
17
220 kV DBPura Neelamangala-1
Tripping at 16:10hrs:
220kV Neelamangala End 220kV DBPura End
DR Trigger Time: 16:06:17.219 hrs
BN fault
280ms delay
SOF
86 operated
DR NA
220 kV DBPura Neelamangala-2
220kV Neelamangala End 220kV DBPura End
DR Trigger Time: 16:09:05.849 hrs
BN fault
100ms current persistent
240ms breaker opening
86 operated
DR NA
220 kV Magadi Neelamangala
220kV Neelamangala End 220kV Magadi End
DR Trigger Time: 16:12:50.987 hrs
BN fault
Ibfault=2.53A (Secondary current)
80ms delay
SOF
86 operated
DR NA
400/220 kV ICT-3 at Neelamangala
DR Trigger Time: 16:55:12.114 hrs
BN fault
Ibfault=3.07A (Secondary current)
132ms delay
HS OC/EF
DR is not time synchronised with GPS
Tripping at 16:31hrs:
220 kV Anchepalya Neelamangala
220kV Neelamangala End 220kV Anchepalya End
DR Trigger Time: 16:31:20.512 hrs
BN fault
80ms delay
SOF
86 operated
DR NA
DR
DR
DR
DR
DR
Annexure-III
Page 17 of 81
18
PMU Plots
Points for Review:
Remedial Actions Furnished:
(1). High set element of 400kV/220kV ICT- 3 at
Neelamangala will be increased to 5A with time delay of
100ms.
(2). For 220kV lines, SOTF overcurrent pickup will be revised
to 8kA from 2kA to avoid undesired tripping.
(1). Reason for delayed fault clearance.(2). Tripping of 400kV/220kV ICT- 3 at Neelamangala for a through line fault.(3). Status of A/r for 220kV Neelamangala connected lines.(4). Tripping of 220kV Neelamangala lines on SOTF operation
Annexure-III
Page 18 of 81
85.II.6. Tripping of 400kV Ghani Narnoor line-1 and 400/220 kV ICT-2 at Ghani on 21-05-2019 at 15:13hrs
• Triggering Incident: BN fault in 400kV Ghani-Narnoor line-1
• ICT#2 tripped on LV Earth fault protection.
19
DR Analysis
400kV /220 kV ICT-2 at GhaniDR Trigger Time: 15:13:28.624 hrs
IN1>1 Start
IN1>1 TripDR
Time of operation
Annexure-III
Page 19 of 81
DR Analysis
Points for Review:
20
400kV Ghani Narnoor line-1
Ghani End Narnoor End
DR Trigger Time: 15:13:28.606 hrs
Zone-1 Trip
Carrier sent
A/r not attempted. All 3 phases tie
breakers got opened.
DR Trigger Time: 15:13:28.630 hrs
Zone 2
Carrier Receive
A/r operated
Zone-2 start
SOTF Trip Zone-2
Current persistent for around 250ms.
Remarks:
Status of main breakers at Ghani
end needs review
Status of tie breakers at Narnoor
end needs review
(1). Non operation of A/r at Ghani end for 400kV Ghani Narnoor line-1.
(2). Tripping of ICT on LV Earth fault protection during line fault.
(3). Opening of tie breaker before main breaker at Narnoor end during A/r.
PMU Plots
DR
DR
Annexure-III
Page 20 of 81
85.II.7. Tripping of 400/220 kV ICT-3 at Mamidapalli on 21-05-2019 at 20:43 hrs
• ICT tripped on PRV-1 indications due to ingress of moisture into the
relay.
• Findings and remedial actions taken shall be furnished.
21
Annexure-III
Page 21 of 81
85.II.8. Tripping of 765/400kV ICT-1 and 2 at Kurnool substation on 21-05-2019 at 18:11 hrs
• Triggering incident : During test charging of 400KV Kurnool-Nanoor line 1
ICT 1 and 2 got tripped due to maloperation of Bucholz relays.
• Line tripped on SOTF.
765/400kV ICT-1 at Kurnool
DR Trigger Time: 18:11:18.757 hrs
BCZ_ TR_Y, Three phase Group A and B
operated
DR
22
765/400kV ICT-2 at Kurnool
DR Trigger Time: 18:11:18.754 hrs
Digital signals not available
DR
• Remedial Actions: Informed OEM for corrective action
Annexure-III
Page 22 of 81
85.II.9. Tripping of 220KV Sabarigiri-Theni line on 23-05-2019 at 16:12 hrs
• Triggering incident: RN fault in the line
• Line tripped on operation of DEF at Theni end
• At Sabarigi end, distance protection operated
Observations from DR
Sabarigiri End Theni End
DR Trigger Time: 16:12:23.394 hrs
21 distance fwd pickup
Trip in 625ms, Fault distance=100KM
DR Trigger Time: 16:11:48.990 hrs
IN>1 Start
IN>1 Trip
DR
DR
Points for Review
23
• What protection operated at Sabarigiri end?
• Tree clearance issues?
Line length=107KM
Annexure-III
Page 23 of 81
85.II.10. Tripping of 400kV Sigareni-Sundilla line-2 on 24-05-2019 at 18:21 hrs
• Line tripped to operation of OV Stg-1
protection operation at Sundila end
• DT received at Singareni end.
• Difference in phase voltages observed
at Sundilla end.
24
Observations from DR
Sigareni End Sundilla End
DR Trigger Time: 18:21:57.616hrs
DT Receive
DR Trigger Time: 18:21:44.838hrs
Vr-262kV, Vy-240kV and Vb-214kV
OV St-1 Start
OV St-1 Trip -observed from EL
DR DR
DR in cfg and dat
Annexure-III
Page 24 of 81
85.II.11. Tripping of 400kV Hoody-Yelahanka line-1 on 25-05-2019 at 20:41 hrs
• Line tripped at Hoody end only and was holding from Yelahanka.
• No fault was observed from DR
25
Observations from DR
Hoody End Yelahanka End
DR Trigger Time: 20:37:32.201hrs
Dist fwd
Z1
SOTF Enable
SOTF/TOR Trip
All pole dead
DR Trigger Time: NA
Line didn’t trip at Yelahanka end
DR
Type of Main-1 and 2 . DR of other main
Annexure-III
Page 25 of 81
85.II.12. Tripping of 400/220 kV ICT-1 at Guttur on 26-05-2019 at 10:00 hrs
• LV side of 400kV/220kV 315MVA ICT#1 Guttur got tripped due to CB
lockout (B phase)because of low SF6 gas in the CB
• Findings and remedial actions taken may be furnished.
• Similar incident happened on 13-May-2019 at 00:51hrs
26
Extracts from Minutes of 84th PCSC held on 27-06-2019
Annexure-III
Page 26 of 81
85.II.13. Tripping of 400kV NPS Nellore line-1 & 2 on 27-05-2019 at 17:42 hrs
• 400kV NPS Nellore-PG line-2 tripped at NPS end due to suspected maloperationof group B protection
• DT was sent to Nellore-PG end. • 400kV NPS Nellore-PG line-1 got tripped due to operation of SPS.
• Antecedent Flow=1100MW each
27
Implemented SPS logic:• In case of tripping of one 400kV Nellore – Nellore PS line and loading on other circuit:
• Recommended setting is 105 % of 2524Amp =2652 Amp
• (In steps of 10 A) Setting is = 2650 Amp and Time Delay=5 sec
Remedial action taken: 86 B trip relay replaced with spare relay and line taken into service.
Annexure-III
Page 27 of 81
85.II.14. Tripping of 230kV Theni-Sabarigiri line on 29-05-2019 at 18:39 hrs
• Triggering Incident: 3 phase to earth fault occurred in line.
• Zone-2 at Theni end.
28
220kV Sabarigiri Edamon-2 and 3 were under outage during antecedent.
Observations from DR
Sabarigiri End Theni End
DR Trigger Time: 18:39:20.887 hrs
Distance Fwd
Relay Trip
DR Trigger Time: 18:38:45.628 hrs
Distance Fwd
Zone 2, Fault distance=97.44KM
DR DR
Points for Review
• Tree clearance issues?
Line length=107KM
Annexure-III
Page 28 of 81
85.II.15. Tripping of 400/220 kV ICT-1 and 400kV RTPS-RAICHUR PG line-2 on 29-05-2019 at 12:43 hrs
• Due to spurious operation of Tie breaker LBB at , 400/220 kV ICT-1 and
400kV RTPS-Raichur PG 2 got tripped at RTPS end and DT was sent to
Raichur PG end
29
Points for Review
Spurious operation of Tie breaker LBB
Annexure-III
Page 29 of 81
85.II.16. Tripping of 400kV Tumkur-Bidadi line-1&2, 400kV Tumkur-Cuddapahline-2, 400kV Tumkur-Pavagada line-2 on 29-05-2019 at 6:11 hrs
• Triggering incident: B phase LA failure at Tumkur end of 400kV Tumkur-Pavagada line-2 .
• 400kV Tumkur-Bidadi line-1&2 also got tripped.
• YN fault occurred at 6:11:02 hrs in 400kV Tumkur-Cuddapah line.
• A/r attempt was not successful as fault was persistent in nature.30
Annexure-III
Page 30 of 81
31
Observations from DR
Tumkur End Cuddapah End
DR Trigger Time: 06:11:02.005 hrs
Zone-1, YN fault
Carrier sent
A/r operated, TOR
DR Trigger Time: 06:11:01.419hrs
Zone 2, Carrier receive
A/r operated, SOTF/TORDRDR
400kV Tumkur-Cuddapah line-2
400kV Tumkur-Pavagada line-2
Tumkur End Pavagada End
DR Trigger Time: 06:11:03.276 hrs
Zone-1, YBN fault
Carrier sent
DR Trigger Time: 06:11:01.419hrs
Zone 2, Carrier receive
DR DR
400kV Tumkur-Bidadi line-1
Tumkur End Bidadi End
DR Trigger Time: NA
Line didn’t trip at Tumkur end
DR Trigger Time: 06:11:02.019 hrs
Zone 2 start, Carrier receive
3 ph trip DR
Annexure-III
Page 31 of 81
32
PMU plots
400kV Tumkur-Bidadi line-2
Tumkur End Bidadi End
DR Trigger Time: 06:11:02.756 hrs
M2 trip
M2 operated
DR Trigger Time: 06:11:02.018 hrs
Zone 2 start, Carrier receive
Carrier receiveDR DR
Points for Review
• Tripping of 400kV Tumkur-Bidadi line-1&2
Annexure-III
Page 32 of 81
85.II.17. Tripping of 400 kV Ghani – Narnoor line-1, 400 KV Jamalamadugu-Kurnool line-1, 765/400 kV ICT-1&2 at Kurnool on 30-05-2019 at 00:48 hrs
• Triggering incident: Y-ph to B-ph fault in the 400kV Narnoor Jammalamadugu line-1& 2 due to falling of Y-ph CVT jumper on B-ph during heavy wind.
• 765/400 kV ICT-1 and 2 at Kurnool PG also got tripped on HV side DirectionalOvercurrent (DOC)
• 400kV Ghani Narnoor tripped only at Ghani end on operation of Zone-1 33
Annexure-III
Page 33 of 81
34
Observations from DR
PMU Plots
400kV Narnoor Jammalamadugu-1
Narnoor End Jammalamadugu End
DR Trigger Time: 00.48.13.000.000 hrs
Y-ph to B-ph fault
I(y-ph)=15.41kA, I(b-ph)=15.40kA
Zone-1
Carrier sent
86 operated
DR Trigger Time: 00:47:55.448 hrs
Y-ph to B-ph fault
Zone 2 Pickup
86 operated
From EL:
CARRIER RECEIVED CH-2 at 00:48:13.077 hrs
DR DR
Annexure-III
Page 34 of 81
35
Observations from DR
400kV Narnoor Jammalamadugu-2
Narnoor End Jammalamadugu End (Main-1 and Main-2)
DR Trigger Time: 00:47:55.934hrs
Y-ph to B-ph fault
I(y-ph)=29.7kA, I(b-ph)=30.05kA
Zone-1
Carrier sent
86 operated
DR Trigger Time:
00:47:55.450 hrs
Distance pickup
DT Receive
86 operated
DR Trigger Time:
00:47:55.903 hrs
Zone 2 Pickup
Carrier Receive
86 operated
From EL:
CARRIER RECEIVED CH-2 at 00:47:55.937 hrs
DT RECEIVED CH-2 at 00:47:55.968 hrs
400kV Narnoor Ghani-1
Narnoor End Ghani End
Line didn’t trip at Narnoor end DR Trigger Time: 00:48:13.083 hrs
Zone 2 Pickup
86 operated
From EL:
21M2_PROT,ZONE-1 PROTECTION,OPERATED at
00:48:13.071hrs
DR
DR
DR DR
Annexure-III
Page 35 of 81
36
Observations from DR
765/400 kV ICT-1 at Kurnool PG
DR Trigger Time: 00:47:55.991 hrs
Y-ph to B-ph fault
I(y-ph)=2.26kA, I(b-ph)=3.83kA
HV side DoC operated
765/400 kV ICT-2 at Kurnool PG
DR Trigger Time: 00:47:55.306hrs
Y-ph to B-ph fault
I(y-ph)=2.3kA, I(b-ph)=3.89kA
HV side DoC operated
Points for Review
(1). Tripping of 400kV Narnoor Ghani line at Ghani end.
(2). Tripping of 765/400 kV ICT-1 and 2 at Kurnool PG for a through line fault.
DR DR
Annexure-III
Page 36 of 81
85.II.18. Tripping of 765/400kV ICT-2 at Kurnool on 02-06-2019 at 17:41 hrs
• Triggering Incident: RN fault in 765kV Kurnool NPS-1
• YN fault in 765kV Kurnool Raichur-1
• ICT-2 got tripped on operation of HV side high set directional over
current during through fault (R-Y phase fault).
37
Annexure-III
Page 37 of 81
38
765/400 kV ICT-2 at Kurnool PG
DR Trigger Time: 17:41:23.789hrs
R-ph fault, subsequent Y-ph fault
HV side high set DoC operated
Observations from DR
765kV Kurnool NPS-1
Kurnool End NPS End
DR Trigger Time: 17:41:23.700 hrs
R phase fault (Ifault=10.8kA)
Zone-1, Carrier sent
A/r not operated
DR Trigger Time: 17:41:18.550 hrs
R phase fault (Ifault=1.73kA)
Zone-2
Carrier not received
765kV Kurnool Raichur-1
Kurnool End Raichur End
DR Trigger Time: 17:41:23.789 hrs
Y phase fault(Ifault=4.4927 kA)
Zone 2, carrier receive
A/r operated
After 2s, B phase fault(Ifault=4.3014 kA)
3 phase trip
DR Trigger Time: 17:41:23.713 hrs
Y phase fault
Zone 1, carrier sent
A/r operated
After 2s, B phase fault
3 phase trip
DR
DR DR
DR
DR
Annexure-III
Page 38 of 81
39
PMU Plots
Points for Review
(1). Tripping of 765/400 kV ICT-1 at Kurnool PG for a through line fault(2). Non operation of A/r at Kurnool end for 765kV Kurnool NPS line-1(3). Failure of carrier aided protection at NPS end for 765kV Kurnool NPS line-1
Annexure-III
Page 39 of 81
85.II.19. Tripping of JSW-Guttur line on 02-06-2019 at 18:17 hrs
• Line tripped due to OV St-1 protection operation at JSW end
• DT was sent to Guttur end.
• At JSW end, B ph voltage was observed to be lesser comparing to R ph
and Y ph.
Observations from DR
JSW End Guttur End
Trigger time-18:16:19.204 hrs
OV st-1 Trip
(Vr-249kV, Vy-255kV and Vb-230kV)
Trigger time-18:09:52.544 hrs
DT Receive
251kV , 245kV and 245kV
DR not time synchronised with GPSDR
DR
40
Remedial Actions Furnished by KPTCL:
The suspected R phase CVT has been replaced by new CVT on 25.07.2019
Annexure-III
Page 40 of 81
85.II.20. Tripping of 220kV Idukki-Udumalpet line on 05-06-2019 at 15:13 hrs
• Triggering incident: R-Y-Earth fault in the line.• Carrier aided protection not operated at Udumalpet end.
41
Observations from DRIdukki End Udumalpet End
DR Trigger Time: 15:10:08.673 hrs
R-Y-Earth fault
Zone-1
Carrier sent
DR Trigger Time:15:06:37.563 hrs
R-Y-Earth fault
(Ifault=2.8kA, 3.1kA)
Zone-2
DR DR
PMU Plot
Annexure-III
Page 41 of 81
85.II.21. Tripping of 400kV JSW -Guttur line and 400 kV Kaiga - Guttur line-2 on 05-06-2019 at 18:27 hrs
• Triggering Incident: Y-phase to earth fault occurred in 400kV Kaiga-
Guttur line-2.
• A/r was successful at Guttur end.
• At Kaiga end A/r was not attempted and breakers got tripped due to
operation of Pole discrepancy (1.65 Sec).
• 400kV JSW-Guttur line tripped on operation of over-voltage at Guttur
and DT received at JSW.42
Annexure-III
Page 42 of 81
Observations from DR
Kaiga End Guttur End
DR Trigger Time: 18:27:08.310 hrs
YN fault
Zone-1
Y ph open at 40ms. B ph opened at 100ms. R pole
open at 1700ms.
DR Trigger Time: 18:27:08.315 hrs
YN fault(Ifault=6.081kA)
Zone-1
A/r operated successfully
DR DR
Points for Review
• Non successful operation of A/r at Kaiga end.
• From DR of Guttur, it is observed that there was swell in R & Y phase voltage for
few cycles43
400 kV Kaiga - Guttur line-2
400kV JSW-Guttur line
JSW End Guttur End
DR Trigger Time: 18:27:13.103 hrs
DT Receive
Vr-239kV, Vy-243kV and Vb-221kV
DR Trigger Time: 18:28:19.670hrs
OV st-1 pickup
Vr-259kV, Vy-152kV and Vb-254kVDR DR
Annexure-III
Page 43 of 81
44
Observations from Kaiga EL
• Fault was sensed in Zone-1 (18:27:05.295 hrs-from EL)• At 18:27:05.298 hrs (from EL), Y phase protection• At 18:27:05.397 hrs (from EL), B phase Breaker open• At 18:27:06.951 hrs(from EL), Pole discrepancy of CB02B operated (Suspected non-opening of R-
ph breaker-from DR)• At 18:27:11.488 hrs (from EL), OV relay operated
PMU Plots
Remedial Actions Furnished by KPTCL:
The suspected R phase CVT has been replaced by new CVT on 25.07.2019
Annexure-III
Page 44 of 81
Observations from DR
Kaiga End Guttur End
DR Trigger: 01:49:21.620 hrs
Z1 operated, R-ph fault
A/r operated
After 300ms subsequent fault occurred
LBB operated, DT sent
DR Trigger: 01:49:21.625 hrs
R ph fault, Z2 operated, CAT
A/r operated
DT Received
DR
Observations from Kaiga EL
• Fault was sensed in Zone-1 (01:49:19.576 hrs-from EL)• LBB of main breaker(CB02B) of the line operated due to struck breaker condition(01:49:19.817 hrs-
from EL) of B-ph• At 01:49:21.285 hrs(from EL), Pole discrepancy of CB02B operated (Suspected non-opening of B-ph
breaker-from DR)
Annexure-III
Page 46 of 81
85.II.22. Tripping of 400kV Dhoni-Munirabad line on 06-06-2019 at 02:01 hrs
• Line got tripped at Dhoni end.
• From DR Zone-3 start, PSB and A/r block
was observed.
48
Observations from DR
Dhoni End Munirabad End
Main-1
DR Trigger Time:
02:00:57.884 hrs
Relay pickup
Main-2
DR Trigger Time: 02:00:57.002 hrs
Relay pickup
DR Trigger Time: 02:01:02.002 hrs
Tie breakers open
Line didn’t trip at Munirabad end
EL
400 kV Dhoni - Munirabad line-2
DR
Dhoni end DR digital signal labelling is not proper
400kV Guttur-Narendra ine-1&2 got tripped due to collapse of 04 nostowers resulting in a R-Y phase to earth fault.
DRDR
Annexure-III
Page 48 of 81
49
PMU Plot
• PSB mal operation is suspected in Main-I Siemens relay.• The issue is referred to the OEM.
Remedial Actions Furnished by KPTCL:
Annexure-III
Page 49 of 81
NP Kunta End Hindupur End
DR Trigger Time: 18:14:42.609 hrs
Zone-1.
Main CB R, Y & B poles got tripped
Tie CB R-pole tripped which was followed by tripping
of Y and B pole (260ms later) due to operation of
over-voltage Stg-2 protection
Vr-462kV
DR Trigger Time: 18:14:42.126 hrs
Carrier receive
OV St-2
DT Send
85.II.23. Tripping of 400kV N.P.Kunta-Hindpur line-2 on 09-06-2019 at 18:14 hrs
• Triggering incident: R-phase to
earth fault occurred in line
• Line tripped due to operation
of over-voltage stg-2.
DR
50
Line reactor is at Hindupur end
PSCAD Study Results
DR
Annexure-III
Page 50 of 81
85.II.24. Tripping of 400kV Vemagiri-Vijayawada line-3 on 10-06-2019 at 9:18 hrs
• Line tripped due to maloperation of Line Reactor Differential relay at
Vijayawada end
• DT was received at Vemagiri end.
51
Vemagiri End Vijayawada End
DR Trigger Time: 09:18:04.335 hrs
DT Receive
DR Trigger Time: 09:18:04.341 hrs
Tie and Main breakers open
From EL, LR operation permitted
Observations from DR
ELDR
Remedial Actions Furnished by PGCIL: Line Reactor differential relay found faulty and relay taken out of service, line charged. Faulty L/R differential relay at Vijayawada end replaced with MiCOM-P643 relay.
Annexure-III
Page 51 of 81
85.II.25. Multiple Tripping in 400kV Julurupadusubstation on 10-06-2019 at 8:22 hrs
• Triggering incident:
• 400kV lines tripped due to operation of over-voltage stg-1.
• 400/220kV ICT-1&2 at Julurupadu on operation of over flux protection.
52
Annexure-III
Page 52 of 81
53
KTPS-VII End Julurupadu End
DR Trigger Time: 08:21:54.949 hrs
OV St-1 operated
DR Trigger Time: 08:21:54.966 hrs
Trip Bus-1
DT Receive
Observations from DR
400kV KTPS-VII - Julurupadu Line-2.
400kV Julurpadu - Suryapet Line-1.
Julurpadu End Suryapet End
DR Trigger Time: 08:21:54.993 hrs
OV St-1 operated
Vr-250kV, Vy-252kV and Vb-251kV
DR Not submitted
DR DR
DR
Annexure-III
Page 53 of 81
54
Julurpadu End
DR Trigger Time: 08:25:35.990 hrs
V/f operated
Group B operated
Observations from DR
400kV/220kV Julurpadu-ICT-1.
400kV/220kV Julurpadu-ICT-2
Julurpadu End
DR Trigger Time: 08:25:35.990 hrs
V/f operated
Group B operatedDR
DR
SCADA Plot
DR
Annexure-III
Page 54 of 81
85.II.26. Tripping of 220kV Sedam-RTPS line-1&2 and 220kV Sedam-Tandur line on 14-06-2019 at 02:00 hrs
• Triggering incident: R phase to Earth fault in 220kV Sedam RTPS line-2.
• At Sedam end, breaker didn’t open
• Fault was cleared by tripping of remote end feeders.
55
Annexure-III
Page 55 of 81
Observations from DR:
220kV Sedam RTPS line-1
Sedam End RTPS End
DR Trigger time: NA
DR and EL not submitted.
Line didn’t trip at Sedam end
DR Trigger time: NA
DR not submitted.
From EL, Zone-3 operation was
observed.
220kV Sedam RTPS line-2
56
Sedam End RTPS End
DR Trigger time: NA
Line didn’t trip at Sedam end due to
mechanical problem in breaker.
DR Trigger time: 01:59:47.095 hrs
BN fault (Ifault-B=3.646kA)
Zone-1
Carrier sent
220kV Sedam Tandur line-1
Sedam End Tandur End
DR Trigger time: NA
Line didn’t trip at Sedam end
DR Trigger time: 02:00:03.533 hrs
EF pickup.
From EL, DEF operated in 2820ms
Annexure-III
Page 56 of 81
PMU PlotsPoints for Review
(1). Status of A/r of 220kV Sedam RTPS line-2 at both the ends(2). Non opening of breaker at Sedam end for 220kV Sedam RTPS line-2.(3). Absence of LBB protection at 220kV Sedam end.(4). DR of 220kV Sedam RTPS line-1 at RTPS end not submitted.(5). DR of 220kV Sedam RTPS line-2 at Sedam end not submitted.
57
Remedial Actions Furnished by KPTCL:
• The Circuit Breaker of RTPS-1 &2 lines which was due for replacement has been replaced on 24th and 25th July 2019.7.2019
• The control cables required for Bus Bar Protection work has been arranged, the work is expected to be completed shortly.
Annexure-III
Page 57 of 81
85.II.27. Tripping of 400kV Vemagiri-GMR line-1&2 on 14-06-2019 at 09:33 hrs
• Triggering incident: Y-Phase LA failure at Vemagiri end of 400kV
Vemagiri-GMR line-1 .
• Line-2 tripped at GMR end only on SOTF
DR
59
Observations from DR:
400kV Vemagiri-GMR line-1
Vemagiri End GMR End
DR Trigger time: NA
DR not submitted.
From EL, Zone-1, carrier send and A/r
operated were observed.
DR Trigger time: 09:33:17.028hrs
Y phase fault
Carrier received
A/r operation couldn’t be validated
DR
Annexure-III
Page 59 of 81
60
400kV Vemagiri-GMR line-2
Vemagiri End GMR End
DR Trigger time: NA
Line didn’t trip at Vemagiri
end
DR Trigger time: 09:33:17.036hrs
SoTF/ToR trip
Points for Review
(1). Tripping of 400kV Vemagiri GMR line-2 at GMR end on SOTF operation
DR
Annexure-III
Page 60 of 81
85.II.28. Tripping of 400/220kV ICT-2 at Hoody substation on 16-06-2019 at 19:20 hrs
• ICT-2 got tripped on operation
of HV over-flux protection
• V/f =1.211, 0.508sec
ELDR
61
Remedial Actions Furnished by KPTCL:
1). Loose wire found in voltage circuit rectified.
2).The Over Flux settings have been revised as follows:
v/f setting for alarm: 1.1 time V nominal, Time delay 20 seconds;
v/f trip setting : v/f is 1.2 time V nominal;Time delay 10 seconds;
SCADA Plot
Annexure-III
Page 61 of 81
85.II.29. Multiple tripping at 220kV Nunna substation on 16-06-2019 at 06:16 hrs
• Triggering incident: failure HV side B phase CT of 220/132kV transformer-1
(connected to 220kV Bus-2) in 220kV Nunna station.
• Bus-1 and Bus-2 BBP operated.62
Annexure-III
Page 62 of 81
63
PMU Plots
DR Analysis
DR Trigger time: 04:19:59.735 hrsBN faultTrip 87BB Zone 2
EL Analysis
ELDR
Annexure-III
Page 63 of 81
85.II.30. Tripping of 400kV Hiryur-Nelamangala-1 and 400kV Gooty-Nelamangala on 22-06-2019 at 04:06hrs
• Triggering incident: 'Y' phase bushing of Hiriyur line-1 reactor failed at
Nelamangala: R-Y phase fault.
• 400kV Gooty-Nelamangala line : Line tripped at Nelamangala end only
due to mal-operation of Main-2 distance protection relay
• No delayed fault clearance
64
Remedial Actions Furnished by KPTCL
Action has been taken to replace the same by commissioning new CRP mounted in bay KIOSK under R&M works.
Annexure-III
Page 64 of 81
65
PMU Plots
Observations from DR:
Hiryur End Nelamangala End
DR Trigger time: 04:06:35.840 hrs
RY fault
M1 operated
A/r lockout
DR Trigger time: 04:06:36.143 hrs
Distance relay pickup
Main 2 trip DR
400kV Hiryur-Nelamangala-1
DR
Gooty End Nelamangala End
DR Trigger time: NA
Line didn’t trip at Gooty end
DR Trigger time: 03:48:34.697 hrs
Distance relay pickup
Main 2 trip
400kV Gooty-Nelamangala
DR
Annexure-III
Page 65 of 81
85.II.31. Tripping of 400/220kV ICT-1&2 at Munirabadsubstation on 24-06-2019 at 20:50 hrs
• Triggering incident: failure of Y phase CT in 220kV Munirabad-Kalyani steel
feeder at Kalyani steel end
• Line got tripped on operation Zone-1. However zone-1 operation was
observed after 280ms after occurrence of fault.
• ICTs tripped due to operation of High set of backup earth fault relay (ICT-1 :
6.63kA, ICT-2 : 5.1KA)
66
At Munirabad end, ICT DOC high set settings are 400kV side: 4kA & 220kV side 5.0kA
Annexure-III
Page 66 of 81
Munirabad End Kalyani Steel End
DR Trigger time: 20:50:55.210 hrs
YN fault, subsequently YBN fault
Zone 2 pickup
Zone-1operated, Carrier sent
Fault current persistent for ~250ms.
DR Trigger time: NA
67
PMU Plots
DR
Observations from DR:220kV Munirabad- Kalyani Steel
400/220kV ICT-1
Munirabad
400/220kV ICT-2
Munirabad
DR Trigger time:
20:50:55.209 hrs
3 PH GR-A OPTD
Ifault=6.63kA
persistent for
~200ms.
DR Trigger time:
20:50:55.209 hrs
IV B/U PROT OPTD
Ifault=5.2863 kA
persistent for ~125ms.
Observations from DR:
220kV Kalyani Steel line distance relay settings have been reviewed and
revised consequent to the tripping.
Remedial Actions Furnished by KPTCL:
DR DR
Annexure-III
Page 67 of 81
85.II.32. Tripping of HVDC Talcher-Kolar Pole-1&2
Sl. No.Details of Event Date & Time Reason Remarks
1Tripping of HVDC Talcher-
Kolar Pole-131-05-2019 at 18:30 hrs
Pole 1 tripped on Line fault. Pole-1 restarted three times and
went into RVO mode. The fourth fault caused tripping of the
pole. Pole-2 went to ground return mode.
SPS Trip Signal-1 and
Trip Signal-2 operated
at Kolar end since total
power loss was ~1700
MW
2Tripping of HVDC Talcher-
Kolar Pole-1&205-06-2019 at 19:01 hrs
HVDC Talcher-Kolar Pole-1 tripped on receipt of ESOF
(Emergency Switch On to Fault) signal at Kolar from Talcher
end. Pole-2 went to metallic return mode with a power flow
of 900MW at Kolar end. Subsequently at 19:02 Hrs, HVDC
Talcher-Kolar Pole -2 also tripped due to operation of under
voltage protection at Kolar end
After tripping of Pole-1
SPS Trip Signal-1
operated leading to
total load relief of
700MW.
3Tripping of HVDC Talcher-
Kolar Pole-108-06-2019 at 12:10 hrs
Pole 1 tripped on receipt of ‘ESOF” from other side at 12:10
Hrs. Pole-2 shifted to metallic return mode of operation
SPS Trip Signal-1
operated at Kolar end
leading to total load
relief of 700MW.
4Tripping of HVDC Talcher-
Kolar Pole-212-06-2019 at 12:24 hrs
While carrying out the switching operation of charger-2 to
Charger-3 for enabling maintenance by OEM, Pole -2 got
tripped due to suspected over voltage in 24V system. After
tripping of Pole-2, Pole-1 continued to operate in metallic
return mode
SPS at Kolar did not
operate since total
power loss after
tripping of Pole-2 was
less than 500 MW
68
Annexure-III
Page 68 of 81
85.II.33. Frequent Tripping of 220kV Lower Sileru-KTPS
Sl.
No. Details of Event Date & Time ReasonFault
LocationDR
1220kV Lower
Sileru-KTPS line
01-06-2019 at
00:00 hrs
R-phase to ground fault. Auto-reclose
was successful at Lower sileru end. A/r
is not enabled at KTPS
95.6KM from
Lower Sileru
end.
2220kV Lower
Sileru-KTPS line
02-06-2019 at
15:30 hrs
R-phase to earth fault occurred in line.
Auto-reclose was successful at Lower
sileru end. A/r is not enabled at KTPS.
51KM from
Lower
Sileru end.
3220kV Lower
Sileru-KTPS line
09-06-2019 at
11:58 hrs
B-phase to earth fault occurred in line.
Zone-2 operated at KTPS and Earth fault
at Lower sileru. Suspected high
resistance fault.
119 KM
from
Lower
Sileru end.
4220kV Lower
Sileru-KTPS line
12-06-2019 at
14:23 hrs
Y-phase to earth fault occurred in line.
Auto-reclose was successful at Lower
Sileru end. A/r is not enabled at KTPS
76KM from
Lower
Sileru end.
69
DR
DR
DR
DR
Line Length= 114 KM
DR
DR
DR
DR
Annexure-III
Page 69 of 81
Sno. Name of the Element
Date and Time
Reason DR EL
1
Tripping of
400kV Ghani-
Narnoor line-1
21-05-2019 at
15:11 hrs
B-phase to earth fault occurred in line. Auto-reclose was
not successful as fault was persistent in nature. Fault was
cleared in zone-2 time during A/r attempt
2
Tripping of
400 kV Kudgi
PG - Tumkur
line - 2
21-05-2019 at
15:30 hrs
Y-phase to earth fault occurred in line. Auto-reclose was
successful at Tumkur. At Kudgi end Auto-reclose was not
attempted
3
Tripping of
400kV
Talarichevu -
Jamalamadugu
ckt-1
21-05-2019
17:51 hrs
B -ph to ground fault in the line.. Auto reclose operated at
Talarichevu end but tripped on persistent fault. Auto
reclose not attempted at Jamalamadugu end
4
Tripping of
400kV
Talarichevu -
Jamalamadugu
ckt-1
22-05-2019 at
19:21 hrs
R phase to Earth fault in the line. At Jammalamadugu end
A/r operated and line tripped due to persistent fault. Main
CB A/r not attempted at Talarichevu
Failure or Non-Operation of Auto Reclose During Transient Fault
72
Annexure-III
Page 72 of 81
Sno. Name of the Element
Date and Time
Reason DR EL
5
Tripping of
400 kV Kudgi
PG – Tumkur
line-2
23-05-2019
at 22:05 hrs
Y-phase to earth fault occurred in
line. Auto-reclose was successful
at Tumkur end. At Kudgi(PG) end
A/r was not attempted due to A/r
block
6
400 KV
Thiruvelam –
Palavadi line-
1
28-05-2019
at 18:04 hrs
B-phase to earth fault. A/r attempt
could not be validated.
7
Tripping of
400kV
Pugalur-
Karaikudi
line-1
31-05-2019
at 17:44 hrs
R-phase to earth fault occurred in
line. Auto-reclose was successful
at Karaikudi, At Pugalur end there
was 3-phase trip
8
Tripping of
400kV
Ramagundam
-Ghanapur
line
02-06-2019
at 13:23 hrs
R-phase to earth fault occurred in
line. Auto-reclose was successful
at Ghanapur and A/r was not
attempted at Ramagundam due to
DT receive
Failure or Non-Operation of Auto Reclose During Transient Fault
73
Annexure-III
Page 73 of 81
Sno. Name of the Element
Date and Time
Reason DR EL
9
Tripping of
400kV Kalikiri-
RYTPP line-2
02-06-2019
at 19:15 hrs
B-phase to earth fault occurred in line.
Auto-reclose was successful at Kalikiri
and A/r not attempted at RYTPP due to
A/r lockout
10
Tripping of
400kV VTPS-
SURYAPET
line-1
02-06-2019
at 13:15 hrs
B-phase to earth fault occurred in line.
Auto-reclose was successful at
Suryapet end. 2nd fault during reclaim
time resulted in three phase trip. At
VTPS end A/r was not attempted
11
Tripping of
765 KV
Kurnool - NPS
line-1
02-06-2019
at 17:41 hrs
R-phase to earth fault occurred in line.
A/r not attempted due to PLCC
channel fail.
12
Tripping of
400KV-
Maheshwara
m PG-
Mahbubnagar
line-1
06-06-2019
at 19:18 hrs
Y phase to Earth fault in the line. A/r
not operated at Mahbubnagar
Item no 2.18
Failure or Non-Operation of Auto Reclose During Transient Fault
74
Annexure-III
Page 74 of 81
Sno. Name of the Element
Date and Time
Reason DR EL
13
Tripping of
400 kV JSW -
Guttur line
08-06-2019
at 13:13 hrs
B-phase to earth fault occurred in
line. A/r was not successful as fault
was persistent. A/r not attempted at
Guttur.
14
Tripping of
400kV Kaiga-
Guttur line-2
18-06-2019
at 15:03 hrs
R-phase to earth fault. Auto-reclose
attempt at Guttur end was not
successful as fault was persistent in
nature. Attempt for A/r could not be
established from Kaiga end EL
Failure or Non-Operation of Auto Reclose During Transient Fault
75
Annexure-III
Page 75 of 81
Sno. Name of the Element
Date and Time
Reason DR EL
1
Tripping of 400kV
Julurupadu-
Managuru line -2
20-05-2019
at 15:57 hrs
Line tripped at Julurupadu end only on
direct trip receive
2
Tripping of 400kV
Khammam
Mamidapally line-
1
27-05-2019
at 18:16 hrs
Line tripped only at Mamidapally end
due to suspected PLCC maloperation
3
Tripping of 765 kV
Raichur- Kurnool
line- 2
02-06-2019
at 17:41 hrs
Line tripped on operation of Over
voltage stage-1 at Kurnool end. Direct
trip was not sent to Raichur due to
failure of PLCC channel at Kurnool and
line was holding from Raichur.
4Tripping of 765 KV
KURNOOL - NPS 2
02-06-2019
at 17:41 hrs
Line tripped on operation of over
voltage stage-1 protection at Kurnool.
Direct trip was not sent to NPS due to
PLCC channel fail
Tripping at One End/ PLCC Mal-operation
77
NA
Annexure-III
Page 77 of 81
Sno. Name of the Element
Date and Time
Reason DR EL
5
Tripping of 400kV
Warangal-
Bhoopalapalli line-1
& Boopalppalli
Chandlapur line-1
08-06-2019
at 1:35 hrs
400kV Warangal-Bhoopalapalli line-
1 line tripped only at Boopalappalli
end on OV st-1 protection operation
and DT was not sent to Warangal end
due to failure of both PLCC channels.
400kV Boopalppalli Chandlapur line-1
tripped at Boopalpalli end due to DT
Receive
6
Tripping of 400kV
Kayathar-Kanarpatty
line-1 & 2
10-06-2019
at 12:22 hrs
Line-1 & 2 tripped at Kanarpatty end
due to spurious DT sent from
kayathar end. Feeder did not trip at
Kayathar end
7
Tripping of 400kV
Ramadugu-
Singareni line
11-06-2019
at 08:24 hrs
Line tripped due to Direct Trip receive
at Ramadugu end
Tripping at One End/ PLCC Mal-operation
78
NANA
NA NA
NANA
Annexure-III
Page 78 of 81
Meeting
No /
Index
Details of Event Date & Time Reason PCSC Recommendations Utility responsible for
Implementation
Status of Implementation of PCSC Recommendations Remarks Latest Status
(To be filled up by the Constituent)
PGCIL (SR-I) mail received on 27-04-2016:
1. The firmware of REL670 is being upgraded. ------- Completed.
2. The recording of events in msec interval is being taken up with OEM. Henceforth,
for analysis purpose, we will provide larm list which has msec time stamp. --------
Completed.
3. End to end testing of PLCC code transmision and tuning of channels carried out. ----
--- Completed.
4. Procurement of differential protection for 400kV NPS-NLR D/C and 400kV RCR-
RTPS-D/C is under tendering. The legends modified in Event/alarm list. Provision of
diff. relay for all short lines emanating from NPS is being taken up with our
corporate.
----- Pending.
PGCIL(SR-I) RVMD 14-07-2016:
4. The proposal for procurement of Line differential Protections for 400kV Raichur -
RTPS-1 & 2 and 400kV Nellore - NPS - 1 & 2 lines has been approved and tender is
30-12-2015 at
06:02hrs
50/I/2 1.PGCIL (SR-I) to furnish Action Taken Report on the
findings of OEM on relay mal-operation at NPS end
on 400 kV NPS – NCC line to PCSC forum.
2. PGCIL (SR-I) to appropriately configure Station
Event Logger at NPS to record events at msec interval.
3. PGCIL (SR-I) to carry out PLCC end-to-end testing
in coordination with TPCIL for 400 kV NPS –TPCIL
line.
4.PGCIL (SR-I), MEPL, SEL, TPCIL & NCC to take
steps to provide line differential protection at their
respective ends on all 400 kV lines (except Gooty line)
emanating from Nellore Pooling Station, and furnish
an action plan to implement the same.
Status of Pending Implementation of PCSC Recommendations as on 19.08.2019 (up to 85th Meeting)
KPTCL Mail dated 27-05-2015:
1. KPTCL has taken action to provide bus bar protection to 220kV buses. --- Pending
2. Over current relay Settings of ICTs to be reviewed by PGCIL.
--- Pending
3. --- Pending
KPTCL Mail dated 29-07-2015:
1. Initial Tendering stage. --- Pending
2. --- Pending
3. --- Pending
KPTCL Mail dated on 23-01-2016:
1. Detailed estimate prepared for taking up the work. CEE, Transmission Zone,
Gulbarga will take up necessary procurement and further execution. --- Pending
2. --- Pending with PGCIL (SR-I).
3. --- Pending
PGCIL (SR-I) Mail dated 14.07.2016:
2. Relay settings of all the stations in SRTS-1 were derived as per Ramakrishna
Commettee recomendations and implemented" --- Completed.
KPTCL Mail dated 16.12.2017:
1) & 3). DPR is approved. Tender is to be called by CEE,TZ Kalaburgi --- Pending
Review Meeting dated 19.12.2017:
1. KPTCL informed that Tenders for providing BBP would be called in Jan-Feb,
2018; Supply of the same is targeted by September, 2018; Erection & Commissioning
is targeted by January, 2019
--- Pending
3. PGCIL (SR-I) informed that time-synchronization of 220 kV side is in place. ---
Completed.
KPTCL mail dated 19.12.2018:
1. DPR preapared for the work of providing Bus Bar Protection to 220kV buses at
Guddadahally is approved. Tender is to be invited by CEE,TZ .
Review Meeting dated 20.12.2018:
1. Tender would be floated in January 2019. Works would be completed in 6 months
16-07-201434/I/6 400/220 kV ICT-1 & 2 at
Munirabad
As reported directional over current relay of ICT’s
operated due to snapping of line jumper in 220kV
Lingapur line.
1. Bus bar protection shall be provided by asset
owner ( i.e KPTCL).
2. Settings for main distance protection &
Overcurrent protection shall be examined and
reviewed.
3. Time synchronization of the Substation shall be
ensured.
KPTCL/
PGCIL (SR-I)
Pending
(with KPTCL)
Multi-Utilities
Complete outage of TPCIL
power station
PendingPGCIL (SR-I),
MEPL, SEL, TPCIL,
NCC
Running units at Thermal Powertech power Station
tripped due to tripping of 400kV Nellore pooling
station (NPS)-TPCIL line and 400kV Nellore pooling
station (NPS)-NCC line
Annexure-IV
Page 1 of 48
PGCIL (SR-I) Mail dated 15.12.2017:
4. LDP relays procurement is under process. Procurement will be completed by Feb-
2018. TPCIL has to give written confirmation for LDP relay procurement. For want
of written confirmation from TPCIL, PGCIL approving authority has withheld the
LDP proposal.
Review Meeting dated 19.12.2017:
4. PGCIL (SR-I) informed that they are waiting for written confirmation from TPCIL
to complete procurement of LDP relays. To this, PCSC forum asked TPCIL to submit
written confirmation to PGCIL (SR-I) by 29.12.2017. PGCIL (SR-I) assured that
with receipt of above confirmation from TPCIL by Dec, 2017, they would be able to
complete the work by FEbruary, 2018.
APTRANSCO informed that they would be able to implement LDP from their &
APGENCO side by April, 2018.
In this regard, PCSC forum made it clear that the recommendation is about providing
LDP as both Main-I & Main-II relays on all stated lines in Nellore Complex, ans
PGCIL (SR-I) mail dated 20.06.2018:
PGCI(SR1) procuring LDP relays for retrofitting of Main-1&2 distance relays.
Tenders are invited from bidders & tender floated. Technical bid opening in this
week.
PGCIL (SR-I) mail dated 10.12.2018:
PO placed on M/s GE & TD India Ltd on 24.09.2018. Supply of relays will be
completed by Jan'2019 and commissioning by Mar'19.
PGCIL (SR-I) mail dated 07.06.2019:
4. PGCIL-SR1: LDP relays (Main-1) commissioned in 400kV NPS-TPCIL-1 Line
during opportunity shutdown. NPS-NCC D/C & NPS-TPCIl D/C lines LDP relay
retrofitting planned in June & July -2019.
In 154th OCC meeting SRLDC/SRPC has advised to re-schedule LDP
commissioning tentatively to Sep/Oct’2019.57/II/9 Tripping of 400 kV Nellore
(PG) - NPS line-1, 400 kV
Krishnapatnam-Nellore (AP)
lines -1&2 and 400kV NPS -
MEPL line
18-07-2016
at 19:05 hrs
APTRANSCO mail dated on 20-12-2016:
Issue was addressed to the concerned for necessary action.
APTRANSCO mail dated on 24-05-2017:
Meeting was conducted and the relays procurement for all the loctions is under
progress.
APTRANSCO mail dated on 20-10-2017 & 22.11.2017:
Relays procurement for all the locations is under progress.
APTRANSCO Mail dated 15.12.2017:
Technical bids opened. PQ evaluation under progress . Price bids expected to open in
next week.
PGCIL (SR-I) Mail dated 15.12.2017:
LDP relays procurement is under process. Procurement will be completed by Feb-
2018. TPCIL has to give written confirmation for LDP relay procurement. For want
of written confirmation from TPCIL, PGCIL approving authority has withheld the
LDP proposal.
Review Meeting dated 19.12.2017:
PGCIL (SR-I) informed that they are waiting for written confirmation from TPCIL to
complete procurement of LDP relays. To this, PCSC forum asked TPCIL to submit
written confirmation to PGCIL (SR-I) by 29.12.2017. PGCIL (SR-I) assured that
with receipt of above confirmation from TPCIL by Dec, 2017, they would be able to
complete the work by FEbruary, 2018.
APTRANSCO informed that they would be able to implement LDP from their &
APGENCO side by April, 2018.
In this regard, PCSC forum made it clear that the recommendation is about providing
LDP as both Main-I & Main-II relays on all stated lines in Nellore Complex, ans
asked all stakeholders to ensure & comply with the same.
Triggering incident was snapping of Y phase conductor
in 400kV Nellore (PG) - NPS line-1. Distance relay at
Krishnapatnam end over-reached in Zone-1, and
resulted in tripping of 400kV Krishnapatnam – Nellore
(AP) lines - 1&2 from Krishnapatnam end. Distance
relay at MEPL over-reached and resulted in tripping of
MEPL-NPS line from MEPL end.
PGCIL (SR-I), TPCIL, MEPL, SEL, SGPL,
APTRANSCO, APGENCO and SDSTPS to
implement line differential protection on all 400 kV
transmission lines (of length less than 50 km)
emanating from Nellore PS, Nellore (PG) SS, and
Nellore (AP) SS. [It may be noted here that the cut-off
length of 50 km has been specified with a view to
exclude only long transmission lines].
APGENCO/
PGCIL(SR-I)/
TPCIL/MEPL/SEL/
SGPL/ APTRANSCO
Pending
30-12-2015 at
06:02hrs
50/I/2 1.PGCIL (SR-I) to furnish Action Taken Report on the
findings of OEM on relay mal-operation at NPS end
on 400 kV NPS – NCC line to PCSC forum.
2. PGCIL (SR-I) to appropriately configure Station
Event Logger at NPS to record events at msec interval.
3. PGCIL (SR-I) to carry out PLCC end-to-end testing
in coordination with TPCIL for 400 kV NPS –TPCIL
line.
4.PGCIL (SR-I), MEPL, SEL, TPCIL & NCC to take
steps to provide line differential protection at their
respective ends on all 400 kV lines (except Gooty line)
emanating from Nellore Pooling Station, and furnish
an action plan to implement the same.
Complete outage of TPCIL
power station
PendingPGCIL (SR-I),
MEPL, SEL, TPCIL,
NCC
Running units at Thermal Powertech power Station
tripped due to tripping of 400kV Nellore pooling
station (NPS)-TPCIL line and 400kV Nellore pooling
station (NPS)-NCC line
Annexure-IV
Page 2 of 48
APTRANSCO Mail Dated 24.04.2018:
ABB make LDP relays inspection is completed. SNEIDER make LDP relays
inspection yet to be completed. Delivery of relays expected in the 1st weak of May-
2018.
APTRANSCO Mail Dated 24.05.2018:
SNEIDER make LDP relays inspection yet to be completed.Delivery of relays
expected in the month of june 2018.
PGCIL (SR-I) mail dated 20.06.2018:
PGCI(SR1) procuring LDP relays for retrofitting of Main-1&2 distance relays.
Tenders are invited from bidders & tender floated. Technical bid opening in this
week.
APTRANSCO Mail Dated 26.06.2018:
ABB make LDP relays are delivered. Schneider make LDP relays inspection to be
offered by the company.
APTRANSCO Mail Dated 25.07.2018:APTRANSCO Mail Dated 25.09.2018:
ABB make LDP relays for Main-1 protection were delivered earlier and schneider
make LDP relays for Main-2 protection are delivered in this week.
APTRANSCO Mail Dated 18.12.2018:
ABB & SCHNEIDER Relays are drawn and available at site. To be commissioned
in coordination with the Alstom (Area) engineers who implemented SAS.
PGCIL (SR-I) mail dated 10.12.2018:
PGCIL(SR-1): PO placed on M/s GE & TD India Ltd on 24.09.2018. Supply of
relays will be completed by Jan'2019 and commissioning by Mar'19
APTRANSCO MAIL DATED 22.01.2019:
The relays are yet to be commissioned.
APTRANSCO mail dated 15.03.2019:
Commissioning of LDP relays scheduled in the month of April 2019.
APTRANSCO mail dated 13.05.2019:
Schnider make P546 LDP relays commissioned in place of Main-1 relays at Nellore
end for 400KV Krishnapatnam feeder on 26/03/19 and for feeder-2 on 27/03/19.
ABB make RED670 relays yet to be commissined in place of Main-2 relays.
PGCIL (SR-I) mail dated 07.06.2019:
PGCIL-SR1: LDP relays (Main-1) commissioned in 400kV NPS-TPCIL-1 Line
during opportunity shutdown. NPS-NCC D/C & NPS-TPCIl D/C lines LDP relay
retrofitting planned in June & July -2019.
In 154th OCC meeting SRLDC/SRPC has advised to re-schedule LDP
commissioning tentatively to Sep/Oct’2019.
APTRANSCO mail dated 19.06.2019:
ABB make RED670 relays testing is under process and will be commissioned in
place of Main-2 relays for Krishnapatnam-1&2 feeders by 30.06.2019 at 400KV
Manubolu SS.
APTRANSCO mail dated 30.07.2019:
ABB make RED670 type LDP relays commissioned in place of Main-2 relays at
Nellore end for 400KV Krishnapatnam feeder-1 on 17/07/19 and for feeder-2 on
15/07/19. The 400KV Krishanapatnam line-2 main-2 relay is in service in
Differential mode. But due to non availability of suitable patch cards, Main-1 of KP-
1 & Main-1&2 of KP-2 feeders are not in differential mode but in Distance mode.
The diffential mode of operation will be kept in service by after purchasing suitable
patch cards.
57/II/9 Tripping of 400 kV Nellore
(PG) - NPS line-1, 400 kV
Krishnapatnam-Nellore (AP)
lines -1&2 and 400kV NPS -
MEPL line
18-07-2016
at 19:05 hrs
Triggering incident was snapping of Y phase conductor
in 400kV Nellore (PG) - NPS line-1. Distance relay at
Krishnapatnam end over-reached in Zone-1, and
resulted in tripping of 400kV Krishnapatnam – Nellore
(AP) lines - 1&2 from Krishnapatnam end. Distance
relay at MEPL over-reached and resulted in tripping of
MEPL-NPS line from MEPL end.
PGCIL (SR-I), TPCIL, MEPL, SEL, SGPL,
APTRANSCO, APGENCO and SDSTPS to
implement line differential protection on all 400 kV
transmission lines (of length less than 50 km)
emanating from Nellore PS, Nellore (PG) SS, and
Nellore (AP) SS. [It may be noted here that the cut-off
length of 50 km has been specified with a view to
exclude only long transmission lines].
APGENCO/
PGCIL(SR-I)/
TPCIL/MEPL/SEL/
SGPL/ APTRANSCO
Pending
Annexure-IV
Page 3 of 48
NTPC mail dated 07.12.2017:
1. High set DEFR on 220 KV lines is disabled ----Completed
2. ---- Pending
Review Meeting dated 19.12.2017:
TSTRANSCO informed that the works are under progress, and are targeted to be
completed in 3 months time.
TSTRANSCO MAIL DATED 20.01.2018:
Line Differential Protection will be provided within 3 months i.e., by end of March,
2018.
TSTRANSCO MAIL DATED 20.04.2018:
Line Differential Protection relays are under procurement and will be provided by end
of May, 2018.
TSTRANSCO MAIL DATED 17.05.2018:
Line Differential relays will be supplied to site by manufacturer by end of May, 2018
and erection will be completed by end of June, 2018.
TSTRANSCO MAIL DATED 12.10.2018:
Inspection of the relays is completed and the relays are received at stores. Relays are
to be drawn and commissioned. Work is expected to be completed by end of
TSTRANSCO MAIL DATED 22.01.2019:
Relays will be commissioned by end of February, 2019.
TSTRANSCO MAIL DATED 22.01.2019:
Replacement of porcelain insulators with Polymer insulator for 4 Km radius ( in
Chennai area) from NCTPS.2 in 400kV SVCM & Alamathy feeders were completed.
TSTRANSCO mail dated 22.06.2019:
2. Relay erection work is under progress and will be completed by end of July, 2019.
11-06-2017
at 19:46hrs
Triggering incident was failure of 220 kV
B-phase LA in ICT-3 LV extension feeder (220KV
line-2) at Malayalapalli substation
1. NTPC to disable high-set of DEFR on the 220 kV
lines emanating from their Ramagundam STPS.
2. NTPC/ TSTRANSCO to provide Line Differential
Protection (with or without pilot) on 220 kV
Ramagundam – Malayalapalli lines – 1 & 2 & 3.
66/ II/ 10 Tripping of 400/ 220 kV
ICT’s – 3 & 4 at
Ramagundam STPS
NTPC-Ramagundam/
TSTRANSCO
Pending
Annexure-IV
Page 4 of 48
69/I/2 Complete outage of 400kV
TPCIL station
30-10-2017 at
21:37 hrs
400kV TPCIL - Nellore line-1 got tripped at TPCIL
end during failure of LA of Station Transformer-2 at
TPCIL. Running Units at TPCIL got tripped due to loss
of evacuating line. 400kV TPCIL - Nellore PS line-2
was under emergency shutdown
1. TPCIL to configure DEF protection such that it
remains in blocked condition as long as Distance
Protection is active, and becomes active only when
distance protection does not pickup.
2.PGCIL (SR-I) to ensure healthiness of Carrier
communication, and the set PUP mode of carrier aided
scheme operates reliably on TPCIL lines 1 & 2.
TPCIL/
PGCIL (SR-I)
Review Meeting dated 19.12.2017:
PGCIL (SR-I) informed that they are waiting for written confirmation from TPCIL to
complete procurement of LDP relays. To this, PCSC forum asked TPCIL to submit
written confirmation to PGCIL (SR-I) by 29.12.2017. PGCIL (SR-I) assured that
with receipt of above confirmation from TPCIL by Dec, 2017, they would be able to
complete the work by February, 2018.
APTRANSCO informed that they would be able to implement LDP from their &
APGENCO side by April, 2018.
In this regard, PCSC forum made it clear that the recommendation is about providing
LDP as both Main-I & Main-II relays on all stated lines in Nellore Complex, ans
asked all stakeholders to ensure & comply with the same.
PGCIL (SR-I) mail dated 20.06.2018:
2. PGCI(SR1) procuring LDP relays for retrofitting of Main-1&2 distance relays.
Tenders are invited from bidders & tender floated. Technical bid opening in this
week.
PGCIL (SR-I) mail dated 10.12.2018:
2. PO placed on M/s GE & TD India Ltd on 24.09.2018. Supply of relays will be
completed by Jan'2019 and commissioning by Mar'19.
Review Meeting on 20.12.2018 & 27.06.2019:
Pending
APTRANSCO maild ated 30.01.2018:
1. Pending...
2.A/R scheme on 400kV Kurnool (PGCIL) feeder-2 will be checked after getting LC.
APTRANSCO maild ated 24.04.2018 & 24.05.2018 & 26.06.2018:
1. Pending...
2. B Ph auxilary trip relay is found defective. The same is to be replaced by M/S
PGCIL. Ii) PD relay event is configured in the EL as per the recommendation.
PGCIL (SR-I) mail dated 20.06.2018:
1. ---Pending
2. PGCIl(SR-1): B-Ph auxiliary relay problem rectified at Narnoor end by replacing
relay contact. ---Completed
APTRANSCO Mail Dated 18.12.2018:
1) Bays and lines pertains to PGCIL .
2) ---Completed.
PGCIL (SR-I) mail dated 20.12.2018:
1) PO placed on M/s GE & TD India Ltd on 24.09.2018. Supply of relays will be
completed by Jan'2019.
APTRANSCO MAIL DATED 22.01.2019:
Pending [with PGCIL (SR-I)]
PGCIL (SR-I) mail dated 07.06.2019:
PGCIL(SR-1):
This issue of retrofitiing of distance relays with LDP relays in Kurnool(PG) –
Kurnool(AP) D/C lines has been discussed with our management. Our management is
seeking approval for the same. You are requested to takeup this LDP issue in next
TCC meeting.
69/III/3 02-10-2017 at
02:03 hrs
1) PGCIL (SR-I) and APTRANSCO to provide for
Line Differential Protection as both the Main
protections on 400 kV Kurnool (AP) – Kurnool (PG)
lines 1 & 2 lines.
2) APTRANSCO to furnish an action taken report
w.r.t. resolving A/R non-operation at Kurnool-AP end
for the subject trippings and configure EL for capturing
PDR operation at their 400 kV Kurnool-AP SS.
Line tripped on B-ph to ground fault. A/R was
unsuccessful at both Kurnool (AP) and Kurnool (PG)
ends.
APTRANSCO/
PGCIL (SR-I)
Tripping of 400 kV
Kurnool(PG) – Kurnool(AP)
line-2
Pending [with
PGCIL (SR-I)]
Annexure-IV
Page 5 of 48
APTRANSCO maild ated 15.12.2017:
APTRANSCO would extend support and requirements if any ,for the rectification
proposed by KPTCL.
Review Meeting dated 19.12.2017:
It was noted that the original Gooty - Lingapur line got LILOed at BTPS, Alipura,
and Ragulapadu. It was also noted that Phase Discrepancy is being observed in
Ragulapadu - Alipira section only. When enquired about the same, KPTCL informed
that they would examine the issue in detail, and would inform the action lan proposed
by next PCSC-71 meeting. On this, APTRANSCO was also asked to render all help
required from their side to KPTCL.
APTRANSCO maild dated 30.01.2018:
APTransco world extend required support .
APTRANSCO maild dated 24.04.2018 & 24.05.2018 & 26.06.2018:
AP Transco would extend required support for attending, phase discrepancy issue in
ragulapadu-Alipura line by KPTCL.
APTRANSCO Mail Dated 25.07.2018:
To be attended by KPTCL as discussed in 75th PCSC meeting.
KPTCL mail dated 19.12.2018:
Phase mis match issue is to be sorted out jointly by KPTCL/ APTRANSCO/ KPCL.
Review Meeting on 20.12.2018:
PCSC forum decided that concrete action in this respect to be initiated in 2 months by
KPTCL alongwith APTRANSCO.
APTRANSCO MAIL DATED 22.01.2019:
Pending [with KPTCL ]
Review Meeting on 27.06.2019:
KPTCL informed that the work is expected to be completed by August 2019.
Line tripped on B-Ph to earth fault. A/R was successful
at Regulapadu and breakers at Alipura end got tripped.
69/III/7 Tripping of 220 kV
Ragulapadu – Alipura line
12-10-2017 at
01:30 hrs
KPTCL and APTRANSCO to sort out issues relating
to incongruence in denoting R, Y, B phases of the
electric supply on their respective sides.
APTRANSCO/ KPTCL
Tripping of 230 kV
Thiruvalam - Chittoor line
76/II/9 1) TANTRANSCO Mail dated 29.08.2018 & 11.09.2018:
Material supplied and work to be taken up ---Pending
2) APTRANSCO Mail dated 24.09.2018:
The static relays were replaced with Numerical relay on all 220 kV feeders at 220 kV
SS chittoor.---Completed
TANTRANSCO Mail dated 11.12.2018:
Due to space constraint, the equipments could not be erected.
Review Meeting on 20.12.2018:
In view of Tiruvalam being inter-state sustation, TANTRANSCO was asked to
prvodie double-bus operation at their 230 kV Tiruvalam SS.
APTRANSCO MAIL DATED 22.01.2019:
Pending [with TANTRANSCO]
TANTRANSCO MAIL DATED 23.01.2019 & 19.03.2019:
Feasibility for providing hybrid breaker / shifting of bays will be studied & action
will be taken. Time upto Sep 2019
TANTRANSCO MAIL DATED 13.06.2019:
1. Bus segregation will be ensured by providing bus coupler bay by extending the
existing Bus.Time line 31.12.2019.
TANTRANSCO mail dated 18.07.2019 & 26.07.2019:
1. Bus segregation will be ensured by providing bus coupler bay by extending the
existing Bus.Time line 31.12.2019.
Pending [with
TANTRANSCO]
TANTRANSCO/
APTRANSCO
13-06-2018 at
18:55hrs
Y-phase to earth fault occurred in line. At 230 kV
Tiruvalam end, breaker was under lockout leading to
operation of LBB protection.
1) TANTRANSCO to provide double-bus operation at
their 230 kV Thiruvalam SS.
2) APTRANSCO to replace the existing static relays
with suitable numerical relays for various line
protections at their 220 kV Chittoor SS.
Pending
[with KPTCL ]
Annexure-IV
Page 6 of 48
KPTCL mail dated 19.12.2018:
3). Nagzari-Bidnal PLCC link is healthy --- Completed.
1.--- Pending
2. --- Pending
Review Meeting on 20.12.2018:
1. & 3. Completed
2. Pending
KPCL mail dated 24-12-2018:
1) --- Completed
2) Proposal will be taken up for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850 shortly, after availing
necessary admnistrative approval...Pending
3) Completed
KPCL mail dated 23.01.2019:
1. Completed
2. Letter addressed to site to take up the proposal for replacement of PZ1000 line
distance relays.KPCL mail dated 23.03.2019:
1). COMPLETED
2) Proposal will be taken up for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850. Prepration of
specification is under progress.
3) COMPLETED
KPCL mail dated 13.05.2019:
1) & 3) Completed
2) Budgetary offer obtained for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850. Preparation of estimation
and specification is under progress.
KPCL mail dated 25.06.2019:
1) & 3) Completed
2) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval of
NLDC for DPR is awaited. Further, availing administrative approval for issue of NIT
for replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 and preparation of estimation and specification is
under progress.
Review Meeting on 27.06.2019:KPCL mail dated 16.07.2019:
1) & 3) Completed
2) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval of
NLDC for DPR is awaited. However, administrative approval for issue of NIT for
replacement of existing PZ1000 relays with new version Numerical Line protection
relays having IEC61850 obtained. Preparation of technical specification is under
progress.
1. SLDC/KPTCL to be pro-active in issuing necessary
directions that help in expeditious restoration of the
tripped lines based on the prevailing conditions and
grid security.
2.KPCL to implement A/R enabled on all 220 kV lines
emanating from their 220 kV Nagjheri PH, with the
help of KPTCL, by December, 2018. In the event of
non-amenability of the existing PZ1000 relays in
providing A/R feature, KPCL shall take steps to
retrofit them with suitable relays that support A/R.
3. KPTCL to restore PLCC carrier communication on
220 kV Nagjheri – Bidnal line at the earliest
220kV lines connected to Nagjheri PH got tripped due
to successive transient faults. Running Units #3 and #4
at Nagjheri got tripped on over frequency protection
operation due to loss of evacuating lines resulting in
complete outage of 220 kV Nagjheri. 220 kV Nagjheri
being the only source to 220kV Ambewadi station,
since 220kV Ambewadi Narendra line 1&2 were under
shutdown during antecedent condition, tripping of
Units at 220 kV Nagjheri resulted in the loss of supply
to 220 kV Ambewadi SS.
17-09-2018 at
14:37hrs
Complete outage of 220 kV
Nagjheri PH and 220/110 kV
Ambewadi Substation.
78/I/2 PendingKPCL/ KPTCL
Annexure-IV
Page 7 of 48
Review Meeting on 20.12.2018:
1. KPTCL I formed that SPS scheme finalisation shall be completed in one month
time --- Pending
KPCL mail dated 24-12-2018:
2) Time delay of operation is not changed. However, the external NCT is used for
REF protection against earlier internal NCT for REF, to avoid tripping due to
malopration --- Completed.
KPCL mail dated 23.01.2019:
1) It shall be reviewd and Implemented by KPCL in coordination with KPTCL.
2)....Completed.
KPCL mail dated 23.01.2019:
1) It shall be reviewd and Implemented by KPTCL in coordination with KPCL.
KPCL mail dated 10.05.2019 & 25.06.2019:
1) Letter addressed to KPTCL RT dated: 25.03.2019 for review and implementation
of SPS at NPH. Reply is awaited.
Review Meeting on 27.06.2019:
1. KPTCL informed that Nagjheri SPS has to be studied in the event of configuration
changes and outcome of the same will be intimated soon .KPCL mail dated 16.07.2019:
1) Letter addressed to KPTCL RT dated: 25.03.2019 for review and implementation
of SPS at NPH. Reply from KPTCL is awaited.
2)Completed.
TANTRANSCO Mail dated 11.12.2018:
1. TANTRANSCO: Estimate sanctioned for replacement of defective isolator status
feedback. Work under progress. ......Pending
2.Earth value of 110kV earthmat has been improved & 230kV side earthmat work
under progress. Lightning mask earthing renovation under execution............Pending
3.......Pending
APTRANSCO Mail Dated 18.12.2018:
Relays settings reviewed and need to be revised due to change of line length DR &
EL's of Main-1 (P444) relay configured properly. Main-2 (D60) relay to be
configured.
Review Meeting on 20.12.2018:
1 & 2). TANTRANSCO informed that Work will be completed by March 2019.
3. APTRANSCO informed that work will be completed by February 2019.
APTRANSCO MAIL DATED 22.01.2019:
Collecting the details of adjacent feeders connected to Gummadipudi for computing
revised relay settings.
TANTRANSCO MAIL DATED 23.01.2019:
Isolator status will be ensured by March 2019
79/I/2
Multiple trippings at 220kV
Nagjheri PH
Triggering incident was B-phase fault at 230kV
Gummidipoondi Substation due to which 230kV Bus-1
Bus-bar protection operated. 230kV Gummidipoondi
Station was under single bus operation, hence
operation of Bus-bar protection resulted in tripping of
all connected elements.
31-08-2018
at 11:49 hrs
KPTCL/ KPCL1)KPTCL to examine the reasons for tripping of more
than one Unit (Units – 3 & 6) on SPS operation at
Nagjheri PH during subject trippings, and furnish a
report on the same along with remedial action taken to
PCSC forum.
2)KPCL to employ a suitable time delay of 50 – 60
msec in operation of REF protection for the GT of Unit-
2 at their Nagjheri PH.
Triggering incident was B-E fault in 220 kV Nagjheri -
Ambewadi line-1. As per the information received,
after tripping of 220 kV Naghjeri - Ambewadi line-1,
220 kV Naghjeri Ambewadi line#2 got overloaded.
This resulted in the tripping of Nagjheri Generating
Units #3 and 6 on SPS operation. At the same time,
Unit #2 got tripped on REF operation.
Pending
1) TANTRANSCO to take steps to implement multi-
bus, multi-zone operation (Double-bus operation) at
their 230 kV Gummidipooindi SS by December,
22018.
2) TANTRANSCO to check if the Gummidipoondi
substation is adequately protected from lightning-
strokes by providing requisite no. of lightning masts
and/ or earth-wire caging.
3) APTRANSCO was asked to verify & correct the
settings employed for distance protection at Sullurpeta
and configure DR’s & EL’s of all Protection Relays at
their Supllurpet SS properly for recording only the
mandated protections & digital signals.
Pending [with
TANTRANSCO]
78/II/16
TANTRANSCO/
APTRANSCO
05-10-2018 at
00:42 hrs
Complete outage of 230/ 110
kV Gummidipoondi
Substation
Annexure-IV
Page 8 of 48
APTRANSCO mail dated 15.03.2019:
3. Revised relay settings were implemented on 16/02/2019 ---Completed
TANTRANSCO MAIL DATED 19.03.2019:
New 230kV isolators have been allotted for replacement of defective isolators. Hence
time line requested upto June.2019.
TANTRANSCO MAIL DATED 13.06.2019:
1. New 230kV isolators have been allotted for replacement of defective isolators.
Hence time line requested upto Sep.2019.
Review Meeting on 27.06.2019:
1. New 230kV isolators have been allotted for replacement of defective isolators.
Hence time line requested upto Sep.2019.
2. & 3. Completed
TANTRANSCO mail dated 18.07.2019 & 26.07.2019:
1. 1New 230kV isolators have been allotted for replacement of defective isolators.
Hence time line requested upto Sep.2019
81/IV/3 Tripping of 400 kV
Warangal - Bhoopalapalli
line-2
15-12-2018 at
20:42 hrs
Line tripped at Bhoopalapalli end only and was holding
from warangal s/s. FIR, DR and EL of Bhoopalapally
were not furnished.
For the line under consideration, the following shall be
carried out by TSGENCO in coordination with PGCIL
(SR-I):
(i) End-to-end communication for DT/ permissive &
other signals may be ensured by testing at both the
ends.
(ii) Healthiness of PLCC system components
(hardware and software) at both ends shall be checked
and faulty components shall be repaired/ replaced.
TSGENCO/ PGCIL (SR-
I)
PGCIL (SR-I) mail dated 07.06.2019:
PGCIL-SR1: Presently WGL-Bhopalapalli-2 line PLCC Ch-1 is unhealthy same was
informed to TSGENCO for rectification. The Ch-1 is out of service from last 50 days
onwards. Both ends PLCC belongs to TSGENCO
TSGENCO mail dated 24.06.2019:
TSGENCO is cordinating with TSTRANSCO for testing of End-to-End
communication for DT/permissive & other signals; checking of Healthiness of PLCC
system components and also for replacing of faulty components .
Review Meeting on 27.06.2019:
TSGENCO informed that PLCC has to be replaced and will be done by December
2019.
Pending [with
TSGENCO]
83/I/1 Complete outage of 230kV
Veeranam substation of
TANTRANSCO
11-03-2019
at 00:55Hrs
Triggering incident was Y-phase CT blast in 230kV
Tirunelvelli (Abhishekpatty) – Veeranam Ckt-1.
230kV Trirunelvelli – Veeranam Ckt-1 and 2 tripped.
Two faults were observed from the PMU plot. During
the second fault, delayed fault clearance of 400ms was
observed. As reported, other connected feeders 230kV
Veeranam – Kodikur ckt-1&2 and 230kV Veeranam –
Kayathar tripped on Zone -2 protection.
1. TANTRANSCO is recommended to submit action
plan to provide Multi-Bus operation/ Hybrid breakers
at 230kV Veeranam SS with clear timelines.
2. TANTRANSCO to revise the distance zone settings
at Tiruneveli SS for 230kV Veeranam – Tirunelveli
line to overcome the problem of relay overreach and
share the same with SRPC.
3. TANTRANSCO to take definite measures ensure
the time synchronization of relays at Tirunelveli end.
4. TANTRANSCO to submit equipment failure report
of the failed CT to CEA.
TANTRANSCO TANTRANSCO MAIL DATED 13.06.2019:
1.Provision of bus coupler breaker is not feasible due to space constaint.
2&3. Tirunelveli end maintained by PGCIL.
4. Report will be sent.
Review meeting on 27.06.2019:
1.Provision of bus coupler breaker is not feasible due to space constaint.
2. Will be informed
3. Time synchronisation will be ensured.
4. Report will be sent.
TANTRANSCO mail dated 19.07.2019:
1.Provision of bus coupler breaker is not feasible due to space constaint.
2&3. Tirunelveli end maintained by PGCIL.
4. Report sent to CEA.
Pending[PGCIL-
SR-II]
79/I/2 Triggering incident was B-phase fault at 230kV
Gummidipoondi Substation due to which 230kV Bus-1
Bus-bar protection operated. 230kV Gummidipoondi
Station was under single bus operation, hence
operation of Bus-bar protection resulted in tripping of
all connected elements.
1) TANTRANSCO to take steps to implement multi-
bus, multi-zone operation (Double-bus operation) at
their 230 kV Gummidipooindi SS by December,
22018.
2) TANTRANSCO to check if the Gummidipoondi
substation is adequately protected from lightning-
strokes by providing requisite no. of lightning masts
and/ or earth-wire caging.
3) APTRANSCO was asked to verify & correct the
settings employed for distance protection at Sullurpeta
and configure DR’s & EL’s of all Protection Relays at
their Supllurpet SS properly for recording only the
mandated protections & digital signals.
Pending [with
TANTRANSCO]
TANTRANSCO/
APTRANSCO
05-10-2018 at
00:42 hrs
Complete outage of 230/ 110
kV Gummidipoondi
Substation
Annexure-IV
Page 9 of 48
83/I/6 Complete outage of 220kV
Hubli substation of KPTCL
and 220kV
Nagjheri Power station of
KPCL
10-04-2019
at 18:09Hrs
Y and B-phase earth isolator switch blades of 220kV
Hubli-Bidnal ckt-1, got closed due to failure of locking
mechanism during heavy wind and rain
conditionsresulting in bus fault. Bus bar protection
operated and all connected elements tripped. There was
complete loss of supply at 220kV Hubli station since
the station was on single bus operation. At thesame
time, 220kV Nagjheri-Ambewadi ckt-1 and 220kV
Nagjheri – Bidnal tripped on overcurrent
protection. Since 220kV Nagjheri – Ambewadi ckt-2
and 220kV Nagjheri-Kodasalli ckt-1 &2 wereunder
shutdown in the antecedent due to maintenance,
running units #1,4,5 and 6 tripped due to
loss of evacuating lines. This resulted in complete loss
of supply at 220kv Nagjheri station.
1. KPTCL is recommended to revise the SPS at
Nagjheri, (to accommodate a new condition with high
flow and low time delay) in consultation with SRPC
and SRLDC.
2. KPCL in coordination with KPTCL is recommended
to provide at least one main protection as carrier aided
three zone distance protection on the 220kV lines
emanating from Nagjheri GS.
KPTCL/ KPCL KPCL mail dated 25.06.2019:
2) Carrier aided protection is enabled on all 220kV lines emanating from NPH
___Completed
Review Meeting on 27.06.2019:
1. KPTCL informed that Nagjheri SPS has to be studied in the event of configuration
changes and outcome of the same will be intimated soon
KPCL mail dated 16.07.2019:
1. under progress
2. Completed
Pending
83/II/9 Tripping of 400 kV
GUTTUR - NARENDRA -1
10-03-2019 at
18:03hrs
Line tripped on operation of overvoltage stage-1
protection at Guttur end and DT received at Narendra
end. Voltages at Guttur end: Vr-254kV, Vy-252kV,
Vb-246kV. As per voltage grading, 400kV Guttur
Narendra line-2 should trip first.
PGCIL (SR-II) to submit action plan regarding
replacement of CT’s for 400Kv Guttur Narendra line -
1 at Guttur end. PGCIL (SR-II) to sort out the time
sync issues in DR and EL at Narendra end.
PGCIL (SR-II)/ KPTCL PGCIL (SR-I) mail dated 07.06.2019:
Line belongs to PGCIL(SR-2)
Review meeting on 27.06.2019:
PGCIL(SR-II) informed that R & Y ph CVT replaced on 25.05.2019. Time
syncronisation has to be attended by KPTCL.
Pending
23-03-2019 at
04:41 hrs
24-03-2019 at
02:32 hrs
25-03-2019 at
01:19 hrs
84/I/1 Complete outage of 230kV
NCTPS Generating Station
of TANGEDCO
18-05-2019 at
04:39 hr.
Triggering incident was Y phase to Earth fault in 220
kV NCTPS Tondiarpet line-2. Due to mal-operation of
LBB protection (of Tondiarpet line-2) at NCTPS end,
all the connected elements of bus zone-3 got tripped.
Due to loss of evacuating lines, running units at
NCTPS unit#1 and 2 got tripped.
1.TANTRANSCO may take immediate measures to
attend the problem in LBB wiring that is extending trip
during A/R within one month.
2. TANTRANSCO is recommended to send a detailed
report regarding the A/R status (availability
/enabling)on all lines emanating from 230kV NCTPS
GS and enable A/R in all lines emanating from 230kV
NCTPS GS.
3.TANGEDCO in coordination with TANTRANSCO
may take definite measures to ensure time
synchronization of all relays with GPS signal at
NCTPS end and remote ends at the earliest.
4. It was also suggested that possibility of backing
down of generation, in the event of unavailability of
many feeders, in particular when radial feeders only
are in service, may be looked at.
TANGEDCO/
TANTRANSCO
TANTRANSCO mail dated 26.07.2019:
1 & 2.Inbuilt LBB function will be enabled in the new distance relays.
3. will be ensured.
4.230kV Kilpauk was operated radially for avoid overloading in the adjacent feeders
due to cable fault in the area.Normally all feeders are operated as grid feeders.
Pending
Pending [ with
APGENCO]
Tripping of 400kV
Krishnapatnam – Nellore ckt-
1
Feeder tripped due to severe tracking on line insulator
stacks.
1. APGENCO to inform PCSC forum the following:
Status of A/R in 400kV Krishnapattnam – Nellore
line-1 at Krishnapattanam end, if A/R is not enabled
APGENCO shall implement 1-ph ‘lead-follow’ A/R
scheme at Krishnapattanam.
The reason for tripping of Unit-2, along with the line
tripping on 24.03.2019.
2. APGENCO in consultation with APTRANSCO to
explore the possibility of providing Line Differential
Protection (LDP) for the line.
3. APTRANSCO is recommended to replace the
insulators of the line with polymer insulators.
83/II/17 APGENCO/
APTRANSCO
APTRANSCO mail dated 19.06.2019:
3. Line Insulator stacks were replaced with SRC insulators at location Nos.4,5,6 for
Krishanpatnam-1 on 26/03/2019 and Krishanpatnam-2 on 27/03/2019.--------------
Completed.
Review Meeting on 27.06.2019:
1. APGENCO representative did not attend the meeting. APGENCO is requested to
furnish the status at the earliest.
Annexure-IV
Page 10 of 48
84/I/2 Complete outage of 230kV
NCTPS Generating Station
of TANGEDCO
19-05-2019 at
22:44 hr.
230kV lines connected to NCTPS got tripped due to
fault in lines. Running units#1,2 and 3 at 230kV
NCTPS also got tripped due to loss of evacuating lines.
1. TANGEDCO in coordination with TANTRANSCO
to take definite measures to ensure time
synchronization of all relays with GPS signal at
NCTPS end and remote ends at the earliest.
2.The PCSC noted frequent jumper cut/conductor snap
instances in the area, of late; accordingly, it was
suggested to have adequate condition monitoring and
preventive maintenance measures.
3.TANTRANSCO to communicate
(i) the schedule of replacement of balance porcelain
insulators with polymer insulators in evacuation lines
from NCTPS.
(ii) schedule of insulator washing
4.NCTPS /TANGEDCO to inform regarding house
load operation capability of Generators at NCTPS.
TANGEDCO/
TANTRANSCO
TANTRANSCO mail dated 26.07.2019:
2& 3.wedge connector have been provided in order to avoid jumbercut.
4. Replacement of porcelain insulators by polymer insulatos in all 230kV & 400kV
feeders in North Chennai area has been completed
Pending
84/II/4 Tripping of 230kV Sulurupet-
Gumudipoondi line
11-04-2019 at
16:05 hr.
Triggering incident was B-N fault in 230kV
Gummudipoondi-NCTPS line. 230kV Sulurupet -
Gummudipoondi line tripped on operation of zone-2
distance protection at Sulurpet end and reverse zone
protection at Gummudipoondi end.
1.TANTRANSCO to check the resistive and reactive
reach settings of 230kV Gummudipoondi-NCTPS line
at Gummidipoondi end.
2. APTRANSCO to ensure time synchronization of
DR and EL at Sulurupet end. Also in coordination with
TANTRANSCO sort out the time synchronization
issue in 230kV Sulurupet-Gumudipoondi line.
3. TANTRANSCO to check the SOTF settings at
Gummidipoondi end for 230kV Gummudipoondi-
NCTPS line .
TANTRANSCO/
APTRANSCO
APTRANSCO mail dated 30.07.2019:
2. GPS not available at 220KV Sullurpet SS.Manually set the timing on 29/07/2019 -
- Completed
TANTRANSCO mail dated 26.07.2019:
1. & 3. Will be reviewed
Pending [ with
TANTRANSCO]
84/II/19 Tripping of 400/220 kV ICT-
1 atCuddapah
03-05-2019 at
23:39 hr.
ICT-1 Tripped on operation of APTRANSCO 220 kV
Bus Bar relay (96 trip relay). Fault reported in 220 kV
Cudappah-Renigunta line
1. PGCIL (SR-I) to submit the high set settings of
ICT’s at Cuddapah. Since the static relay in which
high set is enabled has no provision to provide time
delay, ICT high set shall be enabled from numeric
relay and sufficient time delay shall be provided for
highset operation.
2.APTRANSCO to check the Busbar operation at 220
kV Cuddapah SS and submit a report regarding the
same.
3. PGCIl (SR-I) to inform the methodology adopted for
calculating high set settings of ICT’s. Also due to
changes in system configuration at Cuddapah in recent
future revision of set points shall be taken up.
PGCIL (SR-I)/
APTRANSCO
APTRANSCO mail dated 30.07.2019:
2. The 220KV GE make B90 type Bus Bar relays tested on 23/07/19 and found
healthy. The report submitted vide mail dated 29.07.2019 - Completed
Pending [ with
PGCIL (Sr-1)
84/II/22 Tripping of 400kV
Khammam-Mamidapalli line-
1
09-05-2019 at
02:40 hr.
Line tripped on mal-operation of Reactor differential
protection and DT sent to Khammam.
TSTRANSCO in coordination with PGCIL (SR-I) to
ensure time synchronization of relays at Mamidapalli
end with Khammam end in 6 months’ time.
TSTRANSCO/ PGCIL
(SR-I)
Yet to be informed Pending
Annexure-IV
Page 11 of 48
84/II/29 Frequent tripping of 220 kV
KTPS –Lower Sileru line
01-05-2019 at
16:04 hr.
04-05-2019 at
14:48 hr.
05-05-2019 at
11:29 hr.
06-05-2019 at
13:14 hr.
09-05-2019
at13:58 hr.
12-05-2019
at11:10 hr.
15-05-2019
at21:05 hr.
26-05-2019
at15:36 hr.
29-05-2019
at21:26 hr.
B-N FAULT
B-N FAULT
B-N FAULT
B-N FAULT
R-N FAULT
R-B FAULT
R-B FAULT
B-N FAULT
R-B FAULT
It was noted that no representative of APGENCO
attended the meeting.
For the subject line, the following shall be carried out
by TSGENCO in co-ordination with APGENCO:
(i) End-to-end communication for DT/ permissive &
other signals may be ensured by testing at boththe
ends.
(ii) Healthiness of PLCC system components
(hardware and software) at both ends shall be checked
and faulty components shall be repaired/ replaced.
APGENCO in coordination with TSGENCO to
ensure frequent patrolling and proper maintenance of
ROW by attending all tree clearance issues.
APGENCO/
TSGENCO
Yet to be informed Pending
85/II/3 Tripping of 400kV Kurnool-
Srisailam line
17-05-2019 at
14:10 hrs
line tripped only at Srisailam end on Zone-3 distance
protection operation during Y phase to B phase fault in
220kV NarnoorSomayajulapalli line-1
1. TSGENCO is recommended to modify the PSL
logic (Srisailam end to trip for faults occurring in Zone-
2 and Zone-3 with respective time delays except for
PUR scheme if adopted ) in 1 month time to avoid
occurrence of any such unwarranted trippings in future.
2. APTRANSCO to ensure time synchronization of
relays at 220kV Somayajulapalli SS.
TSGENCO/
APTRANSCO
Yet to be informed Pending
85/II/14 Tripping of 230kV Theni-
Sabarigiri line
29-05-2019 at
18:39 hrs
3 phase to earth fault occurred in line. Tripped on
ground over current protection 67N at Sabarigiri and
Zone-2 at Theni end.
For the subject line, the following shall be carried out
by TANTRANSCO in coordination with KSEBL:
(i) End-to-end testing for DT/ permissive & other
signals may be ensured by testing at both the ends.
(ii) Healthiness of PLCC system components (
hardware and software) at both the ends shall be
checked and faulty components shall be repaired/
replaced .
TANTRANSCO/
KSEBL
Yet to be informed Pending
85/II/17 400 kV Ghani – Narnoor line-
1, 400 KV Jamalamadugu-
Kurnool line-1, 765/400 kV
ICT-1&2 at Kurnool
30-05-2019 at
00:48 hrs
Triggering incident was Y-ph to B-ph fault in the
400kV NarnoorJammalamadugu line-1 & 2 due to
falling of Y-ph CVT jumper on B-ph during heavy
wind. At the same time, 400kV GhaniNarnoor tripped
only at Ghani end on operation of Zone-1 distance
protection. 765/400 kV ICT-1 & 2 at Kurnool PG also
got tripped on HV side Directional Overcurrent (DOC)
protection.
1. APTRANSCO is recommended to sort out the issues
with their distance protection relay (7SA522) which
maloperated and caused unwarranted tripping of
400kV Ghani – Narnoor line-1. The time
synchronization of relays at Ghani end also shall be
ensured.
2.PGCIL (Sr-1) is recommended to submit a detailed
report regarding operation of ICT Buchholz relay for
through fault conditions along-with remedial measures
suggested by OEM.
APTRANSCO/ PGCIL
(SR-1)
Yet to be informed Pending
85/II/20 Tripping of 220kV Idukki-
Udumalpet line
05-06-2019 at
15:13 hrs
Triggering incident was R-Y-Earth fault in the
line. Carrier aided protection not operated at
Udumalpet end.
For the subject line, the following shall be carried out
by TANTRANSCO in coordination with KSEBL:
(iii) End-to-end testing for DT/ permissive & other
signals may be ensured by testing at both the ends.
(iv) Healthiness of PLCC system components (
hardware and software) at both the ends shall be
checked and faulty components shall be repaired/
replaced .
KSEBL/
TANTRANSCO
Yet to be informed Pending
85/II/26 Tripping of 400kV Vemagiri-
GMR line-1&2
14-06-2019 at
09:33 hrs
Line-1 tripped on Y-Phase to earth fault due to Y-
Phase LA failure at Vemagiri end. Line-2 tripped at
GMR end only
1. APTRANSCO is recommended to submit
Equipment failure report (LA failure) to CEA.
2.GMR is recommended to submit a report regarding
tripping of 400kV Vemagiri-GMR line-2 at GMR end
along-with the related tripping files.
APTRANSCO/ GMR Yet to be informed Pending
Annexure-IV
Page 12 of 48
02-06-2019
at 15:30 hrs
R-phase to earth fault occurred in line. Auto-reclose
was successful at Lower sileru end. A/r is not enabled
at KTPS.
02-06-2019 at
15:30 hrs
R-phase to earth fault occurred in line. Auto-reclose
was successful at Lower sileru end. A/r is not enabled
at KTPS.
09-06-2019 at
11:58 hrs
B-phase to earth fault occurred in line. Zone-2
operated at KTPS and Earth fault at Lower sileru.
Suspected high resistance fault.
12-06-2019 at
14:23 hrs
Y-phase to earth fault occurred in line. Auto-reclose
was successful at Lower Sileru end. A/r is not enabled
at KTPS
85/IV/2 Tripping of 400kV
Khammam-Mamidapally line-
1
27-05-2019 at
18:16 hrs
Line tripped only at Mamidapally end due to suspected
PLCC maloperation
For the subject line, the following shall be carried out
by TSTRANSCO in coordination with PGCIL(SR-I):
(i)End-to-end testing for DT/ permissive & other
signals may be ensured by testing at both the ends.
(ii)Healthiness of PLCC system components (
hardware and software) at both the ends shall be
checked and faulty components shall be repaired/
replaced .
TSTRANSCO/ PGCIL
(SR-I)
Yet to be informed Pending
85/IV/5 Tripping of 400kV Warangal-
Bhoopalapalli line-1
&BoopalppalliChandlapur
line-1
08-06-2019 at
1:35 hrs
400kV Warangal-Bhoopalapalli line-1 line tripped
only at Boopalappalli end on OV st-1 protection
operation and DT was not sent to Warangal end due to
failure of both PLCC channels. 400kV
BoopalppalliChandlapur line-1 tripped at Boopalpalli
end due to DT Receive
For the subject line, the following shall be carried out
by TSTRANSCO in coordination with TSGENCO
(i)End-to-end testing for DT/ permissive & other
signals may be ensured by testing at both the ends.
(ii)Healthiness of PLCC system components (
hardware and software) at both the ends shall be
checked and faulty components shall be repaired/
replaced .
TSGENCO/
TSTRANSCO
Yet to be informed Pending
Andhra Pradesh
ATRANSCO in coordination with TSTRANSCO to
ensure frequent patrolling and proper maintenance of
ROW by attending all tree clearance issues.
APTRANSCO/
TSTRANSCO
Yet to be informed Pending85/II/32 220kV Lower Sileru-KTPS
line
Annexure-IV
Page 13 of 48
57/II/9 Tripping of 400 kV Nellore
(PG) - NPS line-1, 400 kV
Krishnapatnam-Nellore (AP)
lines -1&2 and 400kV NPS -
MEPL line
18-07-2016
at 19:05 hrs
Triggering incident was snapping of Y phase conductor
in 400kV Nellore (PG) - NPS line-1. Distance relay at
Krishnapatnam end over-reached in Zone-1, and
resulted in tripping of 400kV Krishnapatnam – Nellore
(AP) lines - 1&2 from Krishnapatnam end. Distance
APGENCO to furnish a report on the remedial action
implemented w.r.t. overreaching of Krishnapatnam end
distance relays during the tripping of 400 kV Nellore
(PG) - NPS line-1
APGENCO Review Meeting dated 19.12.2017:
It was noted that no APGENCO representative had come to attend the meeting.
APGENCO Mail dated 19.12.2017:
Procurement of relays is under progress
Pending
82/III/8 Tripping of 400kV VTPS-
SURYAPET-1
10-02-2019
at 13:20 hrs
B-phase to earth fault occurred in line. Auto-reclose
was successful at Suryapet and breakers got tripped at
VTPS end
It was noted that no representative of APGENCO
attended PCSC-82 meeting. APGENCO to furnish a
detailed report on tripping event bringing out reasons
for A/R non-operation at VTPS end along with
remedial action taken to PCSC forum.
APGENCO Review Meeting on 27.06.2019:
1. APGENCO representative did not attend the meeting. APGENCO is requested to
furnish the status at the earliest.
Pending
82/III/9 Tripping of 400kV VTPS-
SURYAPET-1
15-02-2019
at 14:36 hrs
B-phase to earth fault occurred in line. Auto-reclose
was successful at Suryapet and breakers got tripped at
VTPS end
It was noted that no representative of APGENCO
attended PCSC-82 meeting. APGENCO to furnish a
detailed report on tripping event bringing out reasons
for A/R non-operation at VTPS end along with
remedial action taken to PCSC forum.
APGENCO Review Meeting on 27.06.2019:
1. APGENCO representative did not attend the meeting. APGENCO is requested to
furnish the status at the earliest.
Pending
83/II/20 Tripping of 220kV VTS-
Talapalli ckt-3 and
Generating Units#1,2,3,4,5
& 6 at VTS.
01-04-2019 at
22:58hrs
220kV VTS – Talapalli ckt-4 was under maintenance.
While restoring the feeder, 220kV VTS – Talapalli ckt-
3 tripped on Zone-1 distance protection due to B-N
fault. At the same tine VTS unit# 1 & 2 tripped on
Loss of fuel and Generators 3,4,5&6 tripped on
Generator Negative phase sequence protection.
1. APGENCO is recommended to revise the time
delay of Negative Phase sequence protection operation
in consultation with OEM.
2. APGENCO is also recommended to look into the
Overcurrent Protection settings of Buscoupler, so as to
reduce its time delay of operation in case of faults on
Transfer Bus.
APGENCO Review Meeting on 27.06.2019:
1. APGENCO representative did not attend the meeting. APGENCO is requested to
furnish the status at the earliest.
Pending
83/III/8 Tripping of 400 kV VTPS -
Nellore
24-03-2019 at
12:46hrs
Feeder tripped on Y -N Fault. Auto reclose operated at
Nellore end but not operated at VTPS end.
APGENCO is recommended to submit a detailed
report regarding the reason for A/R being kept
disabled and the Remedial Measure taken for the same.
APGENCO Review Meeting on 27.06.2019:
1. APGENCO representative did not attend the meeting. APGENCO is requested to
furnish the status at the earliest.
Pending
84/II/9 Tripping of 220kV Bus 2 and
connected elements at 220kV
Gazuawaka Substation.
17-04-2019 at 5:40 hr.Triggering incident was Y-phase to earth fault in
220kV Gazuwaka Bus-2. This resulted in tripping of
220 kV elements and 400/220 kV ICT-2
1. APTRANSCO to submit a detailed report
regarding the subject tripping at 220 kV Gazuawaka
Substation along with the remedial measures taken.
2. For all lines emanating from Gazuwaka SS, RTV
coating shall be taken up.
APTRANSCO APTRANSCO mail dated 30.07.2019:
1. The report submitted vide mail dated 29.07.2019 -- Completed
2. Pending
Pending
85/II/6 Tripping of 400/220 kV ICT-
2 at Ghani substation
21-05-2019 at
15:13 hrs
ICT-2 tripped on LV Earth fault protection. 400kV
Ghani-Narnoor line-1 had tripped on B-phase to earth
fault.
APTRANSCO is recommended to send a detailed
report regarding non-availability of Main CB (Main
CB was already in tripped condition in antecedent
condition) during the tripping and non-attempt of auto-
reclosure by Tie CB at Ghani end.
APTRANSCO Yet to be informed Pending
85/II/27 Multiple tripping at 220kV
Nunna substation
16-06-2019 at
06:16 hrs
Triggering incident was failure R phase CT of
220/132kV transformer (connected to 220kV Bus-2) in
220kV Nunna station. Bus-2 bus bar protection
operated resulting in tripping of elements connected to
220kV Bus-2. 2.63 Seconds later a 2nd fault occurred
in Bus-1 due to fault getting extended from Bus-2 CT
failure which inturn resulted in tripping of elements
connected to 220kV Bus-1
1.APTRANSCO is recommended to submit Equipment
Failure Report regarding the failed CT to CEA.
2.APTRANSCO to sort out time synchronization
issues in 220kV Nunna SS.
APTRANSCO Yet to be informed Pending
Annexure-IV
Page 14 of 48
85/III/1 Tripping of 400kV Ghani-
Narnoor line-1
21-05-2019 at
15:11 hrs
B-phase to earth fault occurred in line. Auto-reclose
was not successful as fault was persistent in nature.
Fault was cleared in zone-2 time during A/r attempt
APTRANSCO is recommended to send a detailed
report regarding non-availability of Main CB (Main
CB was already in tripped condition in antecedent
condition) during the tripping and non-attempt of auto-
reclosure by Tie CB at Ghani end.
APTRANSCO Yet to be informed Pending
85/III/4 Tripping of 400kV
Talarichevu - Jamalamadugu
ckt-1
22-05-2019 at
19:21 hrs
R phase to Earth fault in the line. At Jammalamadugu
end A/r operated and line tripped due to persistent
fault. Main CB A/r not attempted at Talarichevu
APTRANSCO is recommended to submit a report
regarding non-attempt of A/R by Main CB at
Talarichevu end of 400kV Talarichevu -
Jamalamadugu ckt-1.
APTRANSCO Yet to be informed Pending
Annexure-IV
Page 15 of 48
82/II/1 Tripping of 400kV KTPS VI-
KTPS VII
05-01-2019
at 10:17hrs
Line tripped at KTPS VI end due to suspected mal-
operation of over-voltage protection. Line was in
service from KTPS VII., BUS CVT secondary R
PHASE got grounded at KTPS VI
1) TSGENCO to configure OVR_start and
OVR_tripin EL at KTPS-VI end and sent a report after
completion of works related to DT communication
channel between KTPS-VI and KTPS-VII
TSGENCO TSGENCO mail dated 24.06.2019:
The issue is referred to M/s BHEL ( EPC vendor ) and the study on feasibility for
providing the communication with the existing available system is under process and
will be completed during the availability of next shutdown.
Review meeting on 27.06.2019:
TSGENCO informed that the recommendations will be completed in September 2019
Pending
83/III/6 Tripping of 400kV Julurpadu
- Manuguru line-2
14-03-2019 at
06:10:00
Triggering incident was R-ph fault in the line. At
Julurpadu end, fault was sensed in Zone-2 and carrier
was received but due to DT Receive from manuguru
end, A/r not operated and line got tripped. FIR, DR and
EL of Manuguru end are not available.
It was noted that no representative of TSGENCO
attended the meeting. TSGENCO is recommended to
submit a report on the tripping and to furnish
equipment failure report to CEA.
TSGENCO TSGENCO mail dated 24.06.2019:
FIR, DR and EL was uploaded in SRLDC website.Trip Report was also submitted.
Review meeting on 27.06.2019:
TSGENCO informed that Equipment failure report will be sent to CEA.
Pending
84/II/28 Frequent tripping of 220 kV
KTPS –Nunna line
05-04-2019 at
12:55 hr. B-N
FAULT
15-04-2019 at
13:20 hr. Y-N
FAULT
16-04-2019 at
14:04 hr. B-N
FAULT
22-04-2019 at
14:13 hr. R-N
FAULT
23-04-2019 at
13:31 hr. R-N
FAULT
04-05-2019 at
14:40 hr. B-N
FAULT
09-05-2019 at
14:31 hr. B-N
FAULT
05-05-2019 at
13:03 hr. B-N
In 155thOCC meeting of SRPC, APTRANSCO
informed that the tripping was due to clearance issues
in the ROW caused by mango tree. It was cleared and
issue was rectified. However, frequent tripping of line
is still persistent.
1. TSGENCO to check the non-operation of carrier
aided trip, when fault is detected at KTPS end in Z-2
and carrier is also received, and submit a report
regarding the same.
2. TSGENCO and APTRANSCO to ensure that
ROW is cleared periodically.
3.APTRANSCO & TSGENCO may consider raising
the height of towers if the line is planned to be used in
future.
4.TSGENCO to consider replacement of old
pneumatic CB’s at KTPS if 220kV KTPS- Nunna line
is planned to be used in future.
TSGENCO Yet to be informed Pending
Telangana
Annexure-IV
Page 16 of 48
74/II/8 Tripping of 400/220 kV ICT-
2 at Gajwel
11-04-2018 at
5:50 hrs
400/220 kV ICT-2 at Gajwel tripped on mal-operation
of Buchholtz relay.
1). TSTRANSCO was asked to keep the ICT and its
mechanical protections under observation for detecting
any slippages.
2). TSTRANSCO was also asked to configure
capturing of mechanical protections of ICT’s in the
respective relay’s/ station’s event logger.
TSTRANSCO TSTRANSCO mail dated 20.06.2018:
1. Mechanical protections of ICTs is under observation. --- Completed
2.New relays are available at site and will be commissioned by 2nd week of August-
2018. The mechanical protection of ICTs will be configured in the new relays ----
Pending
TSTRANSCO MAIL DATED 20.10.2018:
2. New relays will be commissioned by end of November-2018 and the Over Voltage
settings will be implemented after commissioning in new relays ----Pending
TSTRANSCO MAIL DATED 06.12.2018:
2. New relays will be commissioned by end of January-2019 and the mechanical
protections of ICTs will be configured in the new relays ----Pending
Pending
84/II/1 Tripping of 400kV Srisailam-
Dindi line-1 and 400kV
Mamidapalli-Dindi line-1
06-04-2019 at
17:39 hr.
400kV Mamidapally Dindi line-1 tripped on R-phase
to earth fault. 400kV Srisailam-Dindi line-1 tripped on
operation of cable differential protection at Srisailam
and direct trip was sent to Dindi.
1.TSTRANSCO to ensure time synchronization of DR
and EL at Mamidapalli end and Dindi end. Also in
coordination with TSGENCO sort out the time
synchronization issue in 400kV Srisailam – Dindi line-
1. 2.TSTRANSCO to ensure that A/R dead-time
is maintained as 1 sec uniformly at all Stations.
TSTRANSCO Yet to be informed Pending
84/II/14 Tripping of 400/220 kV ICT-
2 and 3 at Dichipalli
Substation
22-04-2019 at
17:22 hr.
ICT#2 and 3 got tripped on suspected mal-operation of
LV earth fault relay during fault in 220 kV Dichpally-
Medaram feeder
1 .TSTRANSCO to ensure directional settings for ICT
earth fault protection and to ensure coordination
between line and ICT DEF protection.
2.TSTRANSCO to investigate the reason for non-
operation of LBB protection of 220 kVDichpally-
Medaram line while breaker lockout at Dichipalli SS
occurred.
3. TSTRANSCO to perform condition monitoring of
CB’s regularly to ensure sufficient air pressure for
proper CB operation.
TSTRANSCO Yet to be informed Pending
84/II/27 Multiple tripping at 220 kV
Ghanapur station
27-05-2019 at
02:04 hr.
Triggering incident was failure of B-phase CT of bus
coupler of Bus-2. Bus bar protection of 220 kV Bus-2
operated resulting in tripping of all elements connected
to Bus-2.
1.TSTRANSCO is recommended to submit
Equipment failure report to CEA regarding the blast
CT.
2.TSTRANSCO to inform if any old CTs exist in
Ghanapur SS and ensure healthiness of the same to
TSTRANSCO Yet to be informed Pending
84/III/4 Tripping of 400kV
Uravakonda - Veltoor ckt-1
13-04-2019 at
18:36 hr.
Y-phase to ground fault. Auto reclose didnot operate at
Veltoor end due to maloperation of STUB protection
1. TSTRANSCO to submit a report regarding the error
in PSL logic that led to the subject tripping along with
Remedial Measures taken.
2. TSTRANSCO to submit a report after checking mal-
operation of STUB protection on P444 relay.
TSTRANSCO Yet to be informed Pending
85/II/7 Tripping of 400/220 kV ICT-
3at Mamidapalli
21-05-2019 at
20:43 hrs
ICT tripped on PRV-1 indications due to ingress of
moisture into the relay
TSTRANSCO is recommended to ensure proper
sealing of PRV by providing suitable canopy to
prevent spurious operation of the same due to ingress
of moisture.
TSTRANSCO Yet to be informed Pending
85/II/25 Tripping of 400kV KTPS-
VII - Julurupadu Line-2 &
tripping of 400/220kV ICT-
1&2 at Julurupadu substation
10-06-2019 at
8:22 hrs
Y-phase to earth fault occurred in 400kV KTPS-VII -
Julurupadu Line-2. Operation of over-voltage stg-2
resulted in tripping of line. 400/220kV ICT-1&2 at
Julurupadu on operation of over flux protection.
1.TSTRANSCO is recommended to check the v/f
settings of ICT-2 at Julurupadu since ICT-1 & 2
tripped at different time ( 3mins difference).
2.DGA analysis of ICT-2 shall be carried out to ensure
healthiness of ICT owing to very high voltage and the
tap position of ICT-2 also to be checked.
TSTRANSCO Yet to be informed Pending
Annexure-IV
Page 17 of 48
85/III/12 Tripping of 400KV-
Maheshwaram PG-
Mahbubnagar line-1
06-06-2019 at
19:18 hrs
Y phase to Earth fault in the line. A/r not operated at
Mahbubnagar
TSTRANSCO is recommended to submit a report
regarding non-attempt of A/R at Mehaboobnagar with
Remedial measures taken
TSTRANSCO Yet to be informed Pending
Annexure-IV
Page 18 of 48
Mail received on 21-10-2015:
1) Anti-pumping contactors of all the nine 220KV Lines are in circuit and tested
periodically during AOH works of lines along with other protections.
2) Completed.
3) Possibility to use both the 220kV buses as main bus under normal operation is
under review.
Mail recieved on 23-11-2015:
1) Completed
3) Two bus operation for 220kV buses : In place of existing CT switching relays,
High speed manual heavy duty change over switch of sufficient current capacity will
be retrofitted to all feeders at 220kV station and same will be operated manually
during changeover of feeder by one bus to the other and this arrangement may Status received vide KPCL mail dated 14.12.2017:
3) DPR for implementation of Two Bus operation for 220kV bus system has been
prepared and proposal is placed for funds from PSDF. After the approval of the DPR,
the work is proposed to be taken up.
Review Meeting dated 19.12.2017:
3) KPCL informed that DPR for implementation of Two Bus operation for 220kV bus
system has been prepared and proposal is placed for funds from PSDF. After the
approval of the DPR, the work is proposed to be taken up. Time frame requested for
is 2 yrs.
KPCL mail dated 19.12.2018:
3) Work proposed to be taken up under PSDF. Approval from Nodal agency is
awaited. However, arrangements have been made to issue NIT.
Review Meeting on 21.12.2018:
KPCL informed that Tender would be floated in 1 month and work would be
completed in 2 years.
KPCL mail dated 23.01.2019:
Tender would be floated in 1 month and work would be completed in 2 years.
KPCL mail dated 23.03.2019:
Arrangements have been made to issue NIT and Tender for the work proposed to be
floated during May- 2019.
KPCL mail dated 10.05.2019:
NIT will be issued during May- 2019.
KPCL mail dated 25.06.2019:
1. & 2. Completed
3) Preparation of technical specification is in progress. NIT will be issued during July-
2019.
Review meeting on 27.06.2019:
KPCL informed that timeline for completion of work is December 2019.
KPCL mail dated 16.07.2019:
1. & 2. Completed
3) Preparation of technical specification is in progress. NIT will be issued during July-
2019. timeline for completion of work is December 2019.
Karnataka
46/II/21 Trippings at 220kV Raichur
TPS
07-06-2015 at
01:35 hrs
1. KPCL to check the operation of anti-pumping relay
on 220 kV side and keep it in healthy condition.
2. KPCL to provide manual reset to the 220 kV side
master trip relay.
3. KPCL to use both the 220 kV buses as main buses
under normal operation, and should go for single bus
operation only during emergencies.
KPCL Pending
Annexure-IV
Page 19 of 48
Status received vide KPCL mail dated 10.07.2017:
1. (ii) Hot line water washing stopped and off line water washing is carried out
whenever the 400 KV Unit or line is under tripped condition / Shutdown condition. ---
Completed
1. (iii) Silicon coating for Unit#8 main & tie breakers carried out in Sep'16 and same
is under observation. Till today in order and good condition. For remaining breakers,
since it is big order, approval for the same is under process. --- Pending
2. Static / Electromechanical relays are existing in all 1 to 7 units. Breaker flash over
protection feature will be enabled (if available) in the numerical relays which will be
retrofitted in phased manner during R&M works.
Status received vide KPCL mail dated 14.12.2017:
1.(i) --- Pending
1. (ii) Hot line water washing stopped and off line water washing is carried out
whenever the 400 KV Unit or line is under tripped condition / Shutdown condition. ---
Completed
1. (iii) Silicon coating for Unit#8 main & tie breakers carried out in Sep'16 and same
is under observation. Till today in order and good condition. For remaining breakers,
since it is big order, approval for the same is under process --- PendingReview Meeting dated 19.12.2017:
1 (iii) As upgradation of 400kV switchyard equip's to be taken under PSDF funds,
Silicon rubber coating for breakers is deffered till then. --- Pending
2. Replacement by Num relay for Units - 5,6 & 7 completed in the month of Oct-
2017. Main-I is Seimens make and Main-II is ABB make. --- Pending
KPCL mail dated 19.01.2018:
2. Replacement of Numerical relays for Units-5, 6 & 7 have been completed.
Referred to OEM for providing the Breaker flashover protection for all the breakers.KPCL mail dated 23.03.2019:
1) (i) & (iii)- Arrangements have been made to issue NIT and Tender for the work
proposed to be floated during May- 2019.
2) Reply is awaiting from OEM to implement the Breaker flash over protection in the
Numerical relays in 400KV station. & Being discussed with other utilities.
It is requested to furnish Necessary logic and settings to implement the breaker
flashover protection
KPCL mail dated 10.05.2019:
1) (i) & (iii)- NIT floated on 01.03.2019
2) Reply is awaiting from OEM to implement the Breaker flash over protection in the
Numerical relays in 400KV station. & Being discussed with other utilities.
It is requested that SRPC may suggest/furnish reference of necessary logic and
settings to implement the breaker flashover protection.
KPCL mail dated 25.06.2019:
1) (i) & (iii)- NIT floated on 01.03.2019. Cover-I opened. Technical evaluation is in
progress. Approval from Nodal Agency is awaited.
2) Reply is awaiting from OEM to implement the Breaker flash over protection in the
Numerical relays in 400KV station. & Being discussed with other utilities.
It is requested that SRPC may suggest/furnish referenc of necessary logic and Review meeting on 27.06.2019:
SRPC informed that referenc of necessary logic and settings to implement the breaker
flashover protection will be shared soon.
KPCL mail dated 16.07.2019:
1) (i) & (iii)- NIT floated on 01.03.2019. Cover-I opened. Technical evaluation is in
progress. Approval from Nodal Agency for PSDF funds is awaited.
2) As confirmed during 84th PCSC meeting, SRPC may suggest/furnish referenc of
necessary logic and settings to implement the breaker flashover protection. reply in
this regard is awaited.
54/II/9 PendingKPCL 1.KPCL to undertake the following remedial measures
to avoid breaker flashovers:
(i) Replacing all porcelain insulators with composite
insulators
(ii) Carrying out hot-line water washing of all
insulators on regular basis.
(iii) Applying Room Temperature Vulcanizing (RTV)
Silicone high voltage insulator coatings to all bus-
connected ceramic insulators of equipment like CT,
PT, CB, Isolators etc.
2.KPCL to take steps to provide dedicated breaker
flashover protection to all breakers at Raichur TPS at
the earliest.
Y-ph Pole of Tie-breaker of Unit-4 at RTPS failed.
Unit-4 got tripped on operation of Generator
Differential, Reverse power & LBB protection.
Operation of LBB protection led to tripping of BUS-2
at RTPS
13-04-2016 at
21:12 hrs
Tripping of 400kV Raichur
TPS
Bus-2
Annexure-IV
Page 20 of 48
Status received vide KPCL mail dated 10.07.2017 & 14.12.2017:
Two Bus operation for 220kV bus is being carried out whenever required. However
scheme for tripping of one bus during LBB/fault and maintaining the other bus intact
by tripping B/C breaker will be taken up in R&M works.
Review Meeting dated 19.12.2017:
3) KPCL informed that DPR for implementation of Two Bus operation for 220kV bus
system has been prepared and proposal is placed for funds from PSDF. After the
approval of the DPR, the work is proposed to be taken up. Time frame requested is 2
yrs.
KPCL mail dated 20.12.2018 & 23.01.2019:
Work proposed to be taken up under PSDF. Approval from Nodal agency is awaited.
However, arrangements have been made to issue NIT.
KPCL mail dated 10.05.2019:
NIT will be issued during May- 2019.
KPCL mail dated 25.06.2019:
Preparation of technical specification is in progress.
NIT will be issued during June/July- 2019.
Review meeting on 27.06.2019:KPCL mail dated 16.07.2019:
NIT will be issued during July- 2019. Time line for completion of work is Dec-2020.
Timeline?15-04-2016 at
15:36 hrs
PendingKPCL In view of the availability of two buses along with
healthy bus-coupler at 220 kV RTPS, KPCL is
recommended to put in service the double-bus
operation at 220 kV RTPS by suitably distributing
loads within 15 days.
During testing of retrofitted distance protection in
400kV Raichur-2 feeder, LBB protection trip DC got
extended to Bus trip. This resulted in tripping of 220kV
bus at RTPS and all connected 220 kV elements. Unit-
4 which is connected to 400 kV Bus got tripped due to
tripping of Station Utility Transformer that is
connected 220 kV bus
Tripping of Units at 220 kV
Raichur TPS
54/II/13
Annexure-IV
Page 21 of 48
Status received vide KPCL mail dated 14.06.2017:
1. All logics checked and found normal. LBB timing checked and found 200msec as
per KPTCL MRT recommendation. - Completed
2. Work Under Progress ---- Pending
3. New GPS System commissioned along with new numerical and synchronised with
GPS system - Complied
4. Work Under Progress ---- Pending
Status received vide mail dated 14.12.2017:
1),3),4) Completed
2. Auto Start of DG set is taken up --- Pending
Review Meeting dated 19.12.2017:
2. KPCL informed that for AMF of DG, Scheme prepared & material procurement
under process. The AMF scheme will be implemented in January 2018. --- Pending
3. The GPS system commissioned on Nov 2016 & all the numarical relay time
synchronised with GPS ---- Completed
Status received vide mail dated 25.07.2018:
AMF panel procurement under progress.
KPCL mail dated 20.1.2.2018:
2. AMF scheme implementation is included in the work ''Replacement common
auxiliary panel with latest technology SCADA compatibility system'' . Availing Review Meeting on 21.12.2018:
KPCL informed that Tender for the work would be floated by January 2019 and work
would be completed in 1 year.
KPCL mail dated 23.01.2019:
1) Completed.
2) Tender for the work would be floated by February 2019 and work would be
completed in 1 year....Pending
3) Completed.
4) Tender for the work would be floated by Feb, 2019, and work would be completed
in 1 year....Pending
KPCL mail dated 23.03.2019:Review meeting on 27.06.2019:
.1 & 3) Completed.
4) Tender published on 21.06.2019 and time line in June 2020.
2. tender has to be issued. Timeline requested upto December 2020.
KPCL mail dated 16.07.2019:
1 & 3) Completed.
2 ) NIT will be issued during Aug-2019.
4) Tender published on 21.06.2019. Time line for completion of Work is Dec-2020.
Status received vide mail dated 25.07.2018:
Numerical Generator protection relay replacement proposed to be taken up alongwith
SCADA work.
KPCL mail dated 20.12.2018:
Will be taken up along with SCADA work. NIT to be issued on Jan-2019
Review Meeting on 21.12.2018:
KPCL informed that Tender for the work would be floated by March, 2019, and work
would be completed in 1 year.
KPCL mail dated 23.01.2019:
Tender for the work would be floated by February-2019 and work would be
completed in 1 year.
KPCL mail dated 23.03.2019:
Tender for the work proposed to be floated during May- 2019 after model code of
conduct and work would be completed in 1 year
KPCL mail dated 10.05.2019:
Tender will be floated during 3rd week of May- 2019.
KPCL mail dated 25.06.2019:
Tender published on 21.06.2019.
Review meeting on 27.06.2019:
06-10-2017 at
22:22 hrs
Tripping of 220 kV Kaiga-
Kadra line-1
PendingKPCL1) KPCL to check settings of LBB protection in all
relays from which it was implemented, and ensure that
their configuration, logic, and timing are in order at
their 220 kV Kadra PH.
2) KPCL to furnish details regarding the existing LT
auxiliary supply arrangement at their 220 kV Kadra
PH, and take steps to provide a suitable Auto-Main-
Fail (AMF) panel for DG set to effect its auto-starting
in case of failure of LT supply.
3) KPCL to ensure time-sync of all relays (DR’s &
EL’s) with GPS at their 220 kV Kadra PH.
4) KPCL to provide stand-alone Event Logger at their
220 kV Nagjheri PH.
LBB of 220kV Kodasalli breaker at Kadra end got
operated which resulted in tripping of Bus at Kadra
and in turn led to tripping of all elements
06-09-2016
at 14:40 hrs
Complete outage of 220 kV
Kadra power station of
KPCL
58/I/3
(GD)
PendingKPCLKPCL to take steps to replace the existing static
protection relays for Generator Units and Generating
Transformers (GT’s) with suitable Numerical relays at
their 220 kV Kadra PH.
While de-synchronising of Unit-2, B-phase pole of
GCB did not open and pole descrepancy relay
operated. Hence all 220KV lines CB hand tripped.
69/II/8
Annexure-IV
Page 22 of 48
KPCL mail dated 16.07.2019:
Tender published on 21.06.2019. Time line for completion of Work is Dec-2020.
72/I/4 Complete outage of 220kV
Sedam, Shahapur, Shahabad,
Kapanoor, Humnabad and
Halabarga Stations of
KPTCL
01-02-2018
at 17:46 hrs
High resistance fault occurred in 110kV Sedam-
Chittapur line near Sedam end. Line DEF operated and
backup OC protection of 100MVA transformer
operated at Sedam end. But line breaker and
transformer HV breaker didn’t open due to problem in
trip circuit. This resulted in cascade tripping of
upstream feeders and power supply was lost to six
220kV stations of KPTCL.
KPCL to disable GFC protection on all lines
emanating from their generating stations.
KPCL Review Meeting on 21.12.2018
KPCL informed that compliance w.r.t. Implementing the recommendation would be
furnished soon.
KPCL mail dated 23.03.2019:
'GFC protection will be disabled in all lines in coordination with M/s.KPTCL
KPCL mail dated 10.05.2019 & 25.06.2019:
Letter addressed to CE, RT, KPTCL dated: 10.04.2019 to disable GFC protection
in all 220kV lines . Reply is awaited.
KPCL mail dated 16.07.2019:
Letter addressed to CE, RT, KPTCL dated: 10.04.2019 to disable GFC protection
in all 220kV lines . Reply is awaited.
Pending
73/I/5 Complete outage of 220kV
Varahi power station
15-03-2018 at
22:36 hrs
There was Y-phase to ground fault on 220 kV Varahi -
Shimoga line-2. Consequent to persisting fault in ‘Y’
phase, the breaker failure protection operated resulting
in operation of 220KV bus bar protection at Varahi,
tripping all the connected lines and Varahi running
units.
KPCL to take steps to put double-bus operation into
service at their 220 kV Varahi PH.
KPCL Status received vide mail dated 25.07.2018:
Under Implementation.
KPCL mail dated 20.12.2018 & 23.01.2019 & 23.03.2019:
Retrofitting of 220kV Bus Isolators is under progress. Proposed to be in service after
April-2019
KPCL mail dated 10.05.2019:
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted. Remaining
bays will be completed after Concurrence of LC from LDC
KPCL mail dated 25.06.2019 & 16.07.2019:
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted. Remaining
bay will be completed after monsoon season i.e during November -2019
Pending
78/I/1 Complete Outage of 220 kV
Varahi UGPH.
24-08-2018 at
11:00 hrs
Due to suspected mal-operation of 220KV bus bar
protection at Varahi, all the connected lines and Varahi
running Units got tripped. (6 nos 220kV lines and 4
nos Varahi generating station running Units). This
resulted in complete outage of 220kV Varahi UGPH
1. KPCL to take steps to put double-bus operation into
service at their 220 kV Varahi UGPH by December,
2018.
2. KPCL to employ correct operational practices like
keeping DC fuses of B/C CB intact during bus
changeover works, disabling back-up protections of
B/C CB during bus changeover works & enabling
them with proper settings only when it is used as Main-
CB of the grid elements.
KPCL KPCL mail dated 20.12.2018 & 23.01.2019:
1. Retrofitting of 220kV Bus Isolators is under progress. Proposed to be in service
after April-2019 --- Pending
2. ---- Completed.
KPCL mail dated 23.03.2019:
1) Retrofitting of 220kV Bus Isolators is under progress. Proposed to be in service
after April-2019
KPCL mail dated 10.05.2019:
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted. Remaining
bays will be completed after Concurrence of LC from LDC.
KPCL mail dated 25.06.2019 & 16.07.2019:
4 Set of Isolators of VS1, VS2 & VM2 bay of North Bus were cmpleted. Remaining
bay will be completed after monsoon season i.e during November -2019
Pending
06-10-2017 at
22:22 hrs
Tripping of 220 kV Kaiga-
Kadra line-1
PendingKPCLKPCL to take steps to replace the existing static
protection relays for Generator Units and Generating
Transformers (GT’s) with suitable Numerical relays at
their 220 kV Kadra PH.
While de-synchronising of Unit-2, B-phase pole of
GCB did not open and pole descrepancy relay
operated. Hence all 220KV lines CB hand tripped.
69/II/8
Annexure-IV
Page 23 of 48
KPCL mail dated 10.03.2019:
1) Preparation of technical specification is completed. Tender will be floated during
3rd week of May- 2019 for control & protection system along with SCADA.
2) English Electric make static type relay is used for NPS protection system at Unit
no.2. The detailed report shall be furnished shortly.
KPCL mail dated 25.06.2019:
1) Preparation of technical specification is completed. Tender will be floated during
1st week of July 2019 for control & protection system along with SCADA.
2) Existing relays are English Electric Static type
@ GT -2 side, Unit breaker opened at 3MW, HV side current is
0.045A(CTR:200/1A), Since LBB setting I= 0.2A, t=0.2sec, Hence LBB is not
operated.
at the same time,@Generator-2 side ,current is 0.9A(CTR-4000/5A, I2s=7.5% of
secondary current i.e alarm=80% of I2s(i.e 0.3A pickup value), since R pole of
breaker closed condition till manual opening of all 4lines, Due to continous
current(>0.3A), However, NPS operated.
Review meeting on 27.06.2019:
1. Timeline for completion of work July 2020.
2. PCSC confirmed the correctness of NPS relay settings adopted at Kadra. --
Completed.
KPCL mail dated 16.07.2019:
1) Tender published on 21.06.2019. Time line for completion of Work is Dec-2020.
2) Completed.
Mail received on 28-04-2015:
1. In view of operating 220kV Ambewadi SS in split bus mode, action is being taken
up by KPTCL. Problem in the 220kV bus coupler breaker is attended and isolator
overhauling work is under progress. Spilt bus operation at Ambewadi will be made
possible at the earliest. --- Pending
2. ICT Protection system at Ambewadi and trippings occured at Supa GS during the
instance is checked up and remedial measures already furnished in this regard.
---- Completed
Mail recieved on 29-07-2015:KPTCL Mail dated 16.12.2017 & Review Meeting dated 19.12.2017:
1. Recommended works at Ambewadi have not been taken up due to various problems
faced due to poor response from the turn key agency M/s ERL. A site meeting is
planned during this month to discuss about further plan of action for attending SRPC
recommendations pertaining to the Sub station.
The issue was discussed in the review meeting. Considering the importance of the
substation and delay in executing the works, it was decided to escalate all pending
issues relating to Ambewadi SS to KPTCL top Management for early completion.
KPTCL mail dated 20.12.2018:Mail received on 28-04-2015:
Procurement of Bus bar and LBB protection is in the final tendering stage. 2. Action
is being taken to restore the carrier protection for 220kV Sedam-Tandoor line. AR
will be enabled.
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final tendering stage. KPTCL Mail dated 16.12.2017:
1 & 2) Replacement of Bus Bar Protection is included under R&U project. Awarded
to M/s GE Ltd. Panels have alredy been supplied by the Agency. The work will be
taken up on top priority.
Review Meeting dated 19.12.2017:
41/I/4 Pending
82/I/3
R-Phase to ground fault occurred on 220kV Sedam-
Shahpur line. Fault not cleared from Sedam end due to
stuck-breaker condition. While the Sedam- Sahapur
line tripped from Shahapur end in Zone-1, the other
220 kv lines from Sedam tripped at remote ends in
Zone-2. This caused complete outage of 220kV Sedam
substation.
GD-1 at 220kV Ambewadi
Station of KPTCL
1) KPCL to ensure that DR and EL for all events are
made available. If Static relays with no DR are present
in Station, standalone Disturbance recorder and Event
logger should be provided.
2) KPCL to investigate the operation of Negative
sequence relay and report to SRPC since the operation
of Negative sequence relay due to stuck breaker
condition is not proper as per protection philisophy
During de-synchronising of Kadra unit#2, R-pole
didn’t open due to struck breaker condition. Pole
Discrepancy operated. All the connected 220kV lines
at Kadra end were hand tripped.
04-02-2019 at
20:19 hrs
Complete Outage of 220kV
Kadra Power House of
KPCL & 220kV Karwar SS
of KPTCL
PendingKPCL
Complete outage at 220kV
Sedam Substation of KPTCL
(GD-1)
KPTCL
22-12-2014
at 21:22 hrs
40/I/1
1. Status? 1. KPTCL to provide Bus bar and LBB
protections for 220 kV bus at Sedam S/s.
2. KPTCL to implement A/R feature on 220 kV
Sedam-Tandur inter-state line.
27-01-2015 at
8.00 hrs
1. Till the completion of R&M works for bus bar and
LBB protection, KPTCL shall explore the possibility
of having split bus operation at Ambewadi and submit
the details of the same to PCSC forum.
2. KPTCL shall provide the details of the tripping of
Supa hydro station connected downstream from 110
kV bus.
PendingKPTCLTriggering incident was B-phase to earth fault in
220kV Ambewadi- Nagzari line-1. B-pole of breaker
did not open at Ambewadi end. LBB protection not
available at Ambewadi end. All elements tripped on
Zone-2 from remote ends.
Annexure-IV
Page 24 of 48
Mail received on 27-05-2015:
1. Bus Bar protection will be provded under R&U.
2. A/R yet to be enabled.
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final tendering stage.
2. Action is being taken to restore the carrier protection for 220kV Sedam-Tandoor
line. AR will be enabled after restoration of PLCC.
KPTCL Mail Recieved dated 22-11-2017:
Bus Bar Protection panel and required Wave traps are supplied under R&U. Wave
trap to be commisioned in Tandoor line and PLCC to be restored.Once PLCC is
restored AR will be enabled.
KPTCL Mail dated 16.12.2017:
1. Replacement of Bus Bar Protection is included under R&U project. Awarded to
M/s GE Ltd. Panels have alredy been supplied by the Agency. The work will be taken
up on top priority.
2. AR feature will be enabled during retrofitting of Main-2 relays.
Review Meeting dated 19.12.2017:
1 & 2) KPTCL informed that the works are under progress and are targeted to be
completed by February, 2018. Review meeting on 27.06.2019:
1. Timeline - September 2019
2. Completed
Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final tendering stage.
2. Action is being taken to restore the carrier protection for 220kV Sedam-Tandoor
line. AR will be enabled after restoration of PLCC.
KPTCL Mail Recieved dated 22-11-2017 & 16.12.2017:
1.Enabling the AR feature was discussed during PCSC meetings and since Ambewadi-
Ponda and Ambewadi-Xeldom lines are radial lines, it was decided that enabling AR
KPTCL mail dated 20.12.2018:
The protection issues pertaining to Ambewadi was appraised to the management
and proposal for construction of new GIS SUb stations has been approved by KPTCL
management. Further as per SRPC directions and in view of attending protection audit
recommendations pertaining to Ambewadi SS without linking with new Station
proposal, action has been taken to include the works in extended scope of R&U
project awarded to M/s GE T&D India Limited. Addition materials required are yet to
be supplied by M/s GE. work expecnted to be completed in 5 months.
Review meeting on 27.06.2019:
1. Since 220kV Ambewadi -Ponda line is radial, this recommendation is dropped.
2. Timeline will be in timated by KPTCL
12-03-2015 at
7:51 hrs
Complete outage of 220kV
Sedam substation of KPTCL
PendingKPTCL1. KPTCL shall provide A/R feature on Ambewadi –
Ponda 220 kV D/C inter-state line.
2. Till the completion of R&M works for bus bar and
LBB protection, KPTCL shall explore the possibility
of having split bus operation at Ambewadi and submit
the details of the same to PCSC forum.
Fault in 220kV Ambewadi-Nagjheri line-2Complete outage of 220 kV
Ambewadi substation of
KPTCL
42/I/1 PendingKPTCL
42/I/2
(GD)
1. KPTCL to provide Bus Bar protection and LBB
protection at Sedam S/s and furnish the status of their
implementation to PCSC forum.
2. KPTCL to implement A/R feature on 220 kV Sedam-
Tandur inter-state line.
Fault occurred in 220kV Sedam-Shahpur line15-02-2015
at 14:24 hrs
Annexure-IV
Page 25 of 48
KPTCL mail received on 23-01-2016:
Will be complied in a months time.
KPTCL Mail Recieved dated 22-11-2017:
Enabling the AR feature was discussed during PCSC meetings and since Ambewadi-
Ponda and Ambewadi-Xeldom lines are radial lines, it was decided that enabling AR
is not required. To clear the faults in the abovelines early, the timings of the Zone 2
was reduced to 150mS and the Back Up EFR timings have been reducedto 150mS.
KPTCL Mail dated 16.12.2017:
Enabling the AR feature was discussed during PCSC meetings and since Ambewadi-
Ponda and Ambewadi-Xeldom lines are radial lines, it was decided that enabling AR
is not required. To clear the faults in the abovelines early, the timings of the Zone 2
was reduced to 150mS and the Back Up EFR timings have been reduced to 150mS.
In view of the above, it is requested to drop the issue from this list.
Review Meeting dated 19.12.2017:
KPTCL informed that AR would be enabled at Ambewadi end for lines other than
Ponda and Xeldom lines during retrofitting of Back Up protection by Distance
protection relay at Ambewadi.
KPTCL mail dated 20.12.2018:
The protection issues pertaining to Ambewadi was appraised to the management
and proposal for construction of new GIS SUb stations has been approved by KPTCL
management. Further as per SRPC directions and in view of attending protection audit
recommendations pertaining to Ambewadi SS without linking with new Station
proposal, action has been taken to include the works in extended scope of R&U
project awarded to M/s GE T&D India Limited. Addition materials required are yet to
be supplied by M/s GE. work will be completed in 5 months
Review meeting on 27.06.2019:
1. Work order plced. Timeline requested December 2019.
220kV Ambewadi-Nagjheri line-2 tripped on B-phase
to earth fault. This resulted in loss of supply to 220kV
Ambewadi bus. 220kV Ambewadi-Ponda line-1&2
were hand tripped after deenergization of bus at
Ambewadi.
30-09-2015 at
10:41 hrs
Outage of 220kV Ambewadi
station in Karnataka
PendingKPTCL KPTCL to fast-track providing A/R on all 220 kV
lines emanating from Ambewadi SS to prevent Station
shut-down on temporary faults.
48/I/3 Status?
Annexure-IV
Page 26 of 48
KPTCL Mail received dated 25-04-2017:
Replacement of existing BBP by new BBP with 4 zone protection is being taken up
under R&U.
KPTCL Mail Recieved dated 22-11-2017:
GE Ltd has already supplied the necessary Bus Bar protection panels for replacement
of the existing static type BBP by new numerical BBP with 4 zone protection under
R&U project. The work of commissioning the same will be taken up shortly.
KPTCL Mail dated 16.12.2017:
Due to operational constraints two/ multi bus operation is not being implemented.
Review Meeting dated 19.12.2017:
It was noted that Shimoga SS is having required configuration for providing double-
bus operation. However, due to large no. of feeders (15 in no) with variable gneration
at certain remote ends like Varahi, the flows on these lines are bound to vary. As such
it is necessary to zero in on appropriate arrangement of feeders on different buses so
that bus-isolators of the feeders are not overloaded.
The issue was discussed. KPTCL was asked to try out multi-bus operation on trial
basis to arrive at suitable arrangement of feeders.
KPTCL mail dated 20.12.2018:
Bus sectionaliser breakers have to be provided for operating Shimoga in multi bus
mode. Estimates have to be prepared by CEE,TZ,Hassan. Work expected to be
completed in 1 year.
KPTCL Mail Recieved dated 22-11-2017:
1. The necessary Bus Bar protection panels are already supplied to Chikkodi under
R&U project. Presently R&U works at sub stations subjected to audit are taken up.
After completion of PAR works, the baove works are planned.
--- Pending
2. --- Pending
3. --- Pending
KPTCL mail dated 16.12.2017:
1.The necessary Bus Bar protection panels are already supplied to Chikkodi under
R&U project. Control cables have to be supplied. Presently R&U works at sub
stations subjected to audit are taken up. After completion of PAR works at 26 Sub
stations, remaining works will be taken up through M/s GE.
--- Pending.
2. --- Pending
3. --- Pending
Review Meeting dated 19.12.2017:
1. KPTCL informed that BBP would be provided by April, 2018.
---- PendingKPTCL mail dated 20.12.2018:
1). Bus Bar Protection work is included under R&U. work expected to be completed
in 3 months ---- Pending
2). Major equipment failure reports are being sent to CEA regularly ----
Completed.
Review Meeting on 27.06.2019:
1. Timeline for completion of work is September 2019
2. Completed
Tripping of 220 kV Chikkodi-
Mudshingi and 220 kV
Chikkodi-Talandage lines
01-07-2016 at
03:03 hrs
Pending52/I/3 Complete outage of 220 kV
Shimoga substation
KPTCLKPTCL to operate 220 kV Shimoga on multi-bus
operation under normal conditions, and put it on single-
bus operation only under emergency conditions.
KPTCL1.KPTCL to take steps to provide busbar protection at
their 220 kV Chikkodi inter-regional substation, and
furnish a time-line for the same.
2.KPTCL to review distance protection settings for
220 kV Chikkodi – Kudachi line.
3.KPTCL to furnish equipment failure report of the
current incident to PSE&TD Division of CEA with a
copy marked to SRPC.
Triggering incident was failure of B-ph PT of 220kV
Bus-2 (western bus) at 220KV Chikkodi substation.
220KV Chikodi- Belgaum-I line tripped on DEFR
(Inst), 220KV Chikkodi-Kudachi line tripped on
Distance protection and also 100MVA transformer-2
tripped on E/F protection.
57/II/1 Pending
220kV Bus Bar protection operated during failure of R
phase CT in DVG-2 line bay.
22-02-2016 at
15:03 hrs
Annexure-IV
Page 27 of 48
KPTCL mail received dated 25.04.2017:
Numerical BBP is being provided under R&M works.
KPTCL mail dated 20.12.2018:
1). The R&M work of 220kV Hoody SS is under progress and expected to be
comleted before the end of August 2019. Providing Bus Bar Protection to 220kV
buses is a part of R&M work at Hoody ----- Pending
62/II/5 Tripping of 220 kV South
Bus and connected elements
(220kV HSR, 220kV
Nagnathpura, 220 kV
Harohalli, 220 kV
Subramanyapura, 220 kV
20-01-2017 at
14:34 hrs
Triggering incident was fault in 66 kV Somanahalli -
Bannerghatta line and fault was cleared by operation of
Back-up OCR at Somanahalli end.
KPTCL to provide numerical Busbar Protection at
their 220 kV Somanahalli SS at the earliest.
KPTCL KPTCL mail received dated 25.04.2017:
Numerical BBP is being provided under R&M works
KPTCL Mail Recieved dated 22-11-2017:
Tesing & Commissioning of numerical BBP at Somanahalli is under progress. There
was some technical issue wth BBP scheme supplied to Somanahally which is being
Pending
74/I/2 Complete outage of 220 kV
Ambewadi station
02-04-2018 at
13:46hrs
Loss of supply occurred to 220 kV Ambewadi station
due to tripping of 220kV Nagzhari-Ambewadi line-2
(Source) from Nagzhari power station. After bus dead,
Ambewadi-Ponda lines – 1 & 2 were hand-tripped. In
antecedent conditions, 220kV Ambewadi - Nagjheri
ckt-1, 220kV Ambewadi-Narendra Ckt-1 &2 were out
of service.
1). KPTCL to review operation of SPS at NPH for
proper functionality and changed network conditions
(reduction of generation with tripping of evacuating
lines) and put it into service at the earliest.
2). KPTCL to furnish equipment failure report of the
current incident (R-phase CT in Nagjheri – 1 bay at
KPTCL KPTCL mail dated 20.12.2018:
1). To be reviewed. Expected to be completed in 1 month.---- Pending
2), Being followed ----- Pending
Review meeting on 27.06.2019:
1. Nagjheri SPS shall be studied in view of changed system configuration
Pending
74/II15 Multiple Trippings at
400/220kV Guttur station
21-04-2018 at
12:50 hrs
Triggering incident was fault in 220 kV Davanagare -
Shimoga line. Bus bar protection operated at Guttur
resulting in tripping of all the connected elements. 220
kV Guttur was on single bus operation due to CVT
problem in Bus-2.
KPTCL to put double-bus operation at their 220 kV
Guttur substations by attending to Bus-2 CVT
problem.
KPTCL KPTCL mail dated 20.12.2018:
Bus-2 CVT problem is attended. However due to breaker replacement works, 220kV
side operated in single bus mode.
Review Meeting dated 20.12.2018:
KPTCL informed that double-bus operation at their 220 kV Guttur would be provided
within two months.
Pending
79/III/9 Tripping of 400 kV JSWEL
–Guttur line
29-09-2018
at 11:30 hrs
R-phase to earth fault occurred in line. Auto-reclose
was not attempted at JSWEL due to DT receive. At
Guttur end auto-reclose could not be validated with
DR/EL.
KPTCL to furnish a detailed report on tripping event
bringing out reasons for DT sending from Guttur end
to JSWEL on 400 kV Guttur - JSWEL line along with
remedial action taken to PCSC forum.
KPTCL Review Meeting on 21.12.2018:
KPTCL was aksed to furnish status of implementation of the recommendation given
at the earliest.
Review meeting on 27.06.2019:
Pending
80/II/7 Tripping of 400 kV JSWEL-
Guttur line
17-10-2018 at
02:04 Hrs
Triggering incident was R-phase to earth fault in line.
At Guttur end there was operation of pole discrepancy
and resulted on tripping of Y & B pole after a duration
of 2 seconds from the occurrence of fault. FIR, DR &
EL of Guttur end were not furnished.
KPTCL to examine the reasons for sending of DT from
Guttur end to JSWEL end, and furnish an action taken
report including remedial measures taken to rectify the
same.
KPTCL Review meeting on 27.06.2019:
report will be submitted by KPTCL
Pending
82/I/4 Complete Outage of 220kV
Ambewadi Station of
KPTCL
06-02-2019 at
14:51hrs
Fault occurred while test charging of 220kV
Ambewadi – Nagjheri Line -2 from Ambewadi end.
Suspected stuck breaker condition at Ambewadi end)
led to clearing of fault by tripping of remote end
breaker in Zone-2. LBB protection is not active at
220kV Ambewadi station.
KPTCL to investigate the reason for non-tripping of
220kV Ambewadi - Nagjheri line-2 on operation of
SOTF and submit a report regarding the same to
SRPC. Also KPTCL to take necessary measures in
order to ensure healthiness of breaker before
testcharging of any line.
KPTCL Review meeting on 27.06.2019:
report will be submitted by KPTCL
Pending
09-01-2017
at 23:06 hrs
KPTCL Pending1. KPTCL to provide Busbar protection at their 220
kV Hoody SS at the earliest.
2. KPTCL to furnish an Equipment Failure Report on
CT failure to CEA with a copy marked to SRPC.
Failure of R-phase CT of 220/ 66 kV transformer-2 at
220kV Hoody end resulted in a bus fault in 220kV Bus-
2. Fault was cleared by backup protection of ICT's
(220kV lines were being radially operated) due to
absence of busbar protection
62/II/3 Tripping of 220 kV Bus 2
and connected elements
(220kV HAL #1 and 2,
400/220 kV ICT- 1, 2 and
220/66 kV ICT-2) at
400/220 kV Hoody
substation of KPTCL (Load
loss : 590 MW)
Annexure-IV
Page 28 of 48
82/I/8 Complete outage of 220kV
Alipura substation
20-02-2019 at
12:45 hrs
As informed by KPTCL, Suspected delayed clearance
of fault in 220 kV BTPS-Lingapur line from BTPS end
resulted in tripping of lines from Alipura S/s.
1) KPTCL is recommended to furnish detailed report
regarding spurious operation of DEF at Alipur SSand
check the directionality of DEF on all lines.
2) KPTCL is requested to share the revised zone
settings for Distance protection at BTPS end.
KPTCL Review meeting on 27.06.2019:
report will be submitted by KPTCL
Pending
82/II/12 Tripping of 400kV Kaiga-
Guttur line-1&2
07-02-2019
at 11:49 hrs
Line-1 tripped due to insulator flashover. Line-2
tripped due to zone-3 operation at Kaiga and Direct
trip receive at Guttur
KPTCL is recommended to take necessary measures to
ensure that Main-I and Main-II at Guttur end shall be
of different types (make and model) coherent with the
general protection philosophy followed in SR region.
KPTCL Review meeting on 27.06.2019:
KPTCL informed that the recommendation has been included as part of R & M work.
Timeline will be informed
Pending
84/II/12 Tripping of 400kV DHONI
GUTTUR line- 1
18-04-2019 at
18:59 hr.
Triggering incident was failure of B-ph CB of 400kV
Dhoni-Guttur line at Dhoni end. This resulted in the
operation of LBB of bus-1 and DT was sent to Guttur
end
1. KPTCL to send equipment failure report,
corresponding to the failed CB at Dhoni SS, to CEA.
2. KPTCL to ensure time synchronization at Guttur
end.
KPTCL Yet to be informed Pending
84/II/16 Tripping of 400 kV
Nelamangala-Mysore line-2
01-05-2019 at 02:29 hr.Line tripped on operation of over voltage stg-2 at
Nelamangala end
KPTCL to ensure time synchronization of DR and
EL with GPS signal at Nelamangala end.
KPTCL Yet to be informed Pending
84/II/24 Tripping of 400/220 kV ICT-
1&3 at Hoody Substation
13-05-2019 at
15:35 hr.
ICT-3 tripped on operation of 59N neutral
displacement relay. ICT-1 tripped on OCR.
KPTCL to inform PCSC forum regarding the changes
implemented in Hoody ICT SPS and to ensure time
synchronization of relays at Hoody SS.
KPTCL Yet to be informed Pending
85/I/4 Tripping of 220kV Sedam-RTPS
line-1&2 and 220kV Sedam-
Tandur line
14-06-2019
at 02:00 hrs
Tripped on Directional Earth Fault indications in Main-
2 relay at Tandur end for fault at Raichur end. Sedam
end details not furnished.
1. KPTCL is recommended to enable A/R on all lines
emanating from 220kV Sedam SS.
2.KPTCL is recommended to commission BBP at
220kV Sedam SS immediately.
KPTCL Yet to be informed Pending
85/II/5 Tripping of 400/220 kV ICT-3 at
Nelamangala substation19-05-2019
at 16:11 hrs
As per FIR, ICT-3 got tripped on operation of High Set
Over current trip on 400kV side
1. KPTCL is recommended to enable auto-reclosure
on all lines emanating from 400/ 220kv Neelamangala
SS and to ensure time synchronization of relays at
Neelamangala SS.
KPTCL Yet to be informed Pending
85/II/11 Tripping of 400kV Hoody-
Yelahanka line-125-05-2019
at 20:41 hrs
Line tripped at Hoody end only and was holding from
Yelahanka.
KPTCL is recommended to check the spurious
operation of SOTF protection at Hoody SS and submit
a report to SRPC regarding the same .
KPTCL Yet to be informed Pending
Annexure-IV
Page 29 of 48
85/II/12 Tripping of 400/220 kV ICT-1at
Guttur Substation26-05-2019
at 10:00 hrs
LV side of 400kV/220kV 315MVA ICT#1 Guttur got
tripped due to CB lockout (B phase)because of low
SF6 gas in the CB
1. KPTCL is recommended to submit a report to SRPC
after the CB pressure leakage problem is attended by
OEM.
2.. KPTCL to ensure that during recharging of Circuit
breakers, cylinders with Non-return valve only are
used to prevent sudden pressure drop in Circuit
breakers.
KPTCL Yet to be informed Pending
85/II/22 Tripping of 400kV Dhoni-
Munirabad line06-06-2019
at 02:01 hrs
Line got tripped at Dhoni end. From DR Zone-3 start,
PSB and A/r block was observed.
KPTCL is recommended to submit a report regarding
PSB maloperation along-with the RM suggested by
OEM. Proper legends shall be ensured for digital
signals at Doni end.
KPTCL Yet to be informed Pending
85/II/27 Tripping of 400/220kV ICT-2 at
Hoody substation16-06-2019
at 19:20 hrs
ICT-2 got tripped on operation of over-flux protection KPTCL is recommended to adopt v/f settings as per
manufacture suggested curve.
v/f setting for alarm: 1.1 time Vnominal; Time delay
10 seconds;
v/f trip setting : v/f is 1.2 time Vnominal;Time delay
60 seconds
KPTCL Yet to be informed Pending
85/II/29 Tripping of 400kV Hiriyur-
Nelamangala line-1 and 400kV
Gooty-Nelamangala line
22-06-2019 at
04:06hrs
400kV Hiryur-Nelamangala line-1 : 'Y' phase bushing
of Hiriyur line-1 reactor failed at Nelamangala end
resuting in a R-Y phase fault. Direct trip was sent to
Hiryur.
400kV Gooty-Nelamangalaline : Line tripped at
Nelamangala end only due to mal-operation of Main-2
distance protection relay (THR).
KPTCL is recommended to submit equipment failure
report to CEA regarding the reactor bushing failure
and also to sort out time synchronization issues of
400kV Hiriyur-Nelamangala line.
KPTCL Yet to be informed Pending
85/II/30 Tripping of 400/220kV ICT-1&2
at Munirabad substation24-06-2019
at 20:50 hrs
400/220kV ICT-1&2 at Munirabad end got tripped due
to operation of High set of backup earth fault relay
during failure of Y phase CT in 220kV Munirabad-
Kalyani steel feeder at Kalyani steel end
KPTCL is recommended to submit equipment failure
report to CEA regarding the CT and PT failure.
KPTCL Yet to be informed Pending
Annexure-IV
Page 30 of 48
KPTCL Mail Recieved dated 22-11-2017:
1. coordination of KPCL has been requested for enabling AR lines terminated to
Nagajari.
2. AR will be enabled at Ambewadi end for lines other than Ponda and Xeldom lines
during retrofitting of Back Up protection by Distance protection relay at Ambewadi.
KPTCL Mail dadted 16.12.2017 & Review Meeting dated 19.12.2017:
1. KPTCL informed that Coordination of KPCL has been requested for enabling AR
lines terminated to Nagajari.
--- Pending
2. KPTCL informed that AR would be enabled at Ambewadi end for lines other than
Ponda and Xeldom lines during retrofitting of Back Up protection by Distance
protection relay at Ambewadi. -- Pending
KPTCL mail dated 20.12.2018:
2). Readiness from KPTCL for implementing AR is already confirmed to KPCL. KPCL mail dated 23.03.2019:
1) Proposal will be taken up for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850. Prepration of
specification is under progress.
KPCL mail dated 13.05.2019:
1) Budgetary offer obtained for replacement of existing PZ1000 relays with new
version Numerical Line protection relays having IEC61850. Preparation of estimation
and specification is under progress.
KPCL mail dated 25.05.2019 & 16.07.2019:
1) Replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 is included in PSDF Phase-II DPR. Approval of
NLDC for DPR is awaited. Further, availing administrative approval for issue of NIT
for replacement of existing PZ1000 relays with new version Numerical Line
protection relays having IEC61850 and preparation of estimation and specification is
under progress. Timeline for completion of work is July 2020.
Status informed during Special Meeting held on 03.06.2016:
1. KPTCL informed that the matter had been taken up with concerned Line Operation
and Maintenance wing to carry out corridor clearance and maintenance as per
schedule to avoid frequent line faults in this corridor. A letter had also been addressed
to Chief Engineer, Bhagalkot zone, to ensure lines in & around Kali complex are
maintained in healthy condition. --- Completed
2. KPTCL assurd that the final modified SPS would be implemented at Nagjheri PH
at the earliest. ------ Pending
3. KPCL informed that Nagjhari- Kodasalli Lines 1 & 2 had been kept in service
since 23.05.2016 @ 08.06hrs.
--- Completed
KPTCL Mail received dated 28-06-2016:
2. Modifications to be carried in Nagzari SPS logic is submitted to SRLDC/SRPC
for verification and approval
Status received vide KPCL mail dated 14.06.2017:
1. Will be reviewed in consultation with EE(RT), KPTCL, Hubli.
3. Both the lines are in charged condition.
KPTCL Mail Recieved dated 22-11-2017:
1) & 3) --- Completed
2). Proposed revision in existing SPS scheme is already submitted to SRLDC/SRPC.,
Yet to be discussed and approved by the SRPC forum. --- Pending
Complete outage of 220kV
Ambewadi Substation of
KPTCL
29.10.2015 at
14:34 hrs
220kV Nagjheri-Ambewadi line-1 tripped at 13:33 hrs
due to B phase to earth fault. Ambewadi was radially
fed from Nagjheri power station through 220kV
Nagjheri-Ambewadi line-2. Tripping of this line
caused 220kV Bus shut down at Ambewadi and
remaining lines and transformers were hand tripped
1. KPCL to provide A/R on all 220 kV lines emanating
from Nagjheri PH.
2. KPTCL to provide A/R on all 220 kV lines
emanating from Ambewadi SS.
KPCL/ KPTCL49/I/3
PendingKPCL/ KPTCL 1. To avoid tripping of transmission lines on transient
faults, KPCL/ KPTCL is recommended to carry out
periodic patrolling of lines, and ensure their proper
maintenance by carrying out jungle/ bushing clearance
and trimming of tree branches within the RoW of
transmission lines as per the SRPC transmission line
patrolling guidelines (available under the menu item
"All Uploads/ Operation/ Miscellaneous/ Transmission
Line Patrolling Protocol / Guidelines for Southern
Region" on SRPC website).
2. KPCL/ KPTCL to review operation of SPS at NPH
for functionality (reduction of generation with tripping
of evacuating lines) and healthiness.
3. KPCL to put 220 kV Kodasalli - Nagjheri D/C lines
into service if more than 200 MW generation from
Kali Complex (with Nagheri Contribution not less than
50 MW) is ensured on sustained basis.
220kV lines from Nagjheri power house started
tripping from 11:00 hrs due to fault in lines. The
sequence of tripping is shown in SOE list. At 12:33
hrs, 220kV Narendra-Ambewadi lines-1&2 got tripped
which resulted in loss of evacuation path to Nagjheri
station resulting in tripping of running Units and
complete outage at Nagjhheri power station. 220kV
Ambewadi station also got de-energized due to tripping
of source feeders i.e. 220kV Narendra-Ambewadi-1&2
and 220kV Nagjheri-Ambewadi-1&2.
22-02-2016 at
12:36 hrs
Complete outage of 220 kV
Nagjheri power station and
220 kV Ambewadi
substation of KPTCL
51/I/3
Pending
Annexure-IV
Page 31 of 48
KPTCL Mail dated 16.12.2017:
1) & 3). --- Completed.
2). Proposed revision in existing SPS scheme is already submitted to SRLDC/SRPC.,
yet to be discussed and approved by the SRPC forum --- Pending
Review Meeting dated 19.12.2017:
2. The SPS proposed by KPTCL was discussed and the PCSC forum suggested
certain changes for suitable incorporation. KPTCL agreed to look into the same and
assured that the modified SPS would be furnished by January, 2018.
Review Meeting on 21.12.2018:
2. KPTCL informed that Nagjheri SPS shall be finalised in 1 month.
KPCL mail dated 23.01.2019 & 23.03.2019:
1) .....Completed
2) It shall be reviewd and Implemented by KPCL in coordination with KPTCL.
3) .....Completed
KPCL mail dated 13.05.2019 & 25.06.2019
1. 3. Completed
2) Letter addressed to KPTCL RT dated: 25.03.2019 for review and implementation
of SPS at NPH. Reply is awaited.
Review meeting on 27.06.2019:
2. KPTCL informed that Naghjeri SPS need to be revisited in view of changes in KPCL mail dated 16.07.2019:
1 & 3) Completed.
2) Letter addressed to KPTCL RT dated: 25.03.2019 for review and implementation
of SPS at NPH. Reply from KPTCL is awaited.
PendingKPCL/ KPTCL 1. To avoid tripping of transmission lines on transient
faults, KPCL/ KPTCL is recommended to carry out
periodic patrolling of lines, and ensure their proper
maintenance by carrying out jungle/ bushing clearance
and trimming of tree branches within the RoW of
transmission lines as per the SRPC transmission line
patrolling guidelines (available under the menu item
"All Uploads/ Operation/ Miscellaneous/ Transmission
Line Patrolling Protocol / Guidelines for Southern
Region" on SRPC website).
2. KPCL/ KPTCL to review operation of SPS at NPH
for functionality (reduction of generation with tripping
of evacuating lines) and healthiness.
3. KPCL to put 220 kV Kodasalli - Nagjheri D/C lines
into service if more than 200 MW generation from
Kali Complex (with Nagheri Contribution not less than
50 MW) is ensured on sustained basis.
220kV lines from Nagjheri power house started
tripping from 11:00 hrs due to fault in lines. The
sequence of tripping is shown in SOE list. At 12:33
hrs, 220kV Narendra-Ambewadi lines-1&2 got tripped
which resulted in loss of evacuation path to Nagjheri
station resulting in tripping of running Units and
complete outage at Nagjhheri power station. 220kV
Ambewadi station also got de-energized due to tripping
of source feeders i.e. 220kV Narendra-Ambewadi-1&2
and 220kV Nagjheri-Ambewadi-1&2.
22-02-2016 at
12:36 hrs
Complete outage of 220 kV
Nagjheri power station and
220 kV Ambewadi
substation of KPTCL
51/I/3
Annexure-IV
Page 32 of 48
KPCL mail dated 23.01.2019 & 23.03.2019:
1) …Completed.
2) It shall be reviewd and Implemented by KPCL in coordination with KPTCL.
3) …Completed.
KPCL mail dated 10.05.2019 & 25.06.2019:
1. & 3. Completed
2) Letter addressed to KPTCL RT dated: 25.03.2019 for review and implementation
of SPS at NPH. Reply is awaited.
Review meeting on 27.06.2019:
2. KPTCL informed that Naghjeri SPS need to be revisited in view of changes in
system configuration.
KPCL mail dated 16.07.2019:
1 & 3) Completed.
2) Letter addressed to KPTCL RT dated: 25.03.2019 for review and implementation
of SPS at NPH. Reply from KPTCL is awaited.
Complete outage of 220kV
Ambewadi station of
KPTCL and 220kV Nagjheri
of KPCL
18-03-2016 at
14:40 hrs
Tamil Nadu
Ambewadi Narendra line-2 tripped on fault and 220kV
ambewadi Narendra line-1 tripped due to over-loading.
Running Units at Nagjheri also tripped during the event
due to tripping of evacuating lines
PendingKPCL/ KPTCL KPTCL Mail received dated 28-06-2016:
Modifications to be carried in Nagzari SPS logic is submitted to SRLDC/SRPC for
verification and approval
Status received vide KPCL mail dated 14.06.2017:
1. Tripped since there was evacuation problem and there were only two lines NA-1
and NA-2 ---- Completed
2. Will be reviewed in consultation with EE(RT), KPTCL, Hubli. --- Pending
3. Both the lines are in charged condition. --- Completed.
KPTCL Mail Recieved dated 22-11-2017:
2. Proposed revision in existing SPS scheme is already submitted to SRLDC/SRPC.,
yet to be discussed and approved by the SRPC forum. --- Pending
KPTCL Mail dated 16.12.2017:
1) & 3). --- Completed.
2). Proposed revision in existing SPS scheme is already submitted to SRLDC/SRPC.,
yet to be discussed and approved by the SRPC forum --- Pending
Review Meeting dated 19.12.2017:
2. The SPS proposed by KPTCL was discussed and the PCSC forum suggested
certain changes for suitable incorporation. KPTCL agreed to look into the same and
assured that the modified SPS would be furnished by January, 2018.
Review Meeting on 21.12.2018:
KPTCL informed that Nagjheri SPS shall be finalised in 1 month.
53/I/3 1. KPCL to furnish a report on the reasons for Unit-6
tripping at Nagjheri PH.
2. KPCL/ KPTCL to modify suitably the SPS at
Nagjheri Power House such that it would also factor in
the over loading of Ambewadi-Narendra lines.
3. KPCL to put 220 kV Kodasalli - Nagjheri D/C lines
into service if more than 200 MW generation from
Kali Complex (with Nagheri Contribution not less than
50 MW) is ensured on sustained basis.
Annexure-IV
Page 33 of 48
Mail dated 18.07.2019
2) Tender has been lodged two times. New indent was reaised on 06.07.19. and
tender floating is expected by August 2019. 3) Tender has been
lodged on 15.07.19 and new indent would be raised for the same shortly.
TANTRANSCO Mail received on 19-02-2016 and 24-03-2016:
Revision of Bus Bar Protection setting was carried out. The stabilizing voltage
setting was raised from 410 to 450 volts. After completing the necessary test, the bus
bar protection put in to service on 29.12.2015.
Mail Received on 27-04-2016 ,16-06-2016,25-07-2016 & 24-09-2016:
Revision of Bus Bar Protection setting was carried out. After completing the
necessary test, the bus bar protection put in to service on 29.12.2015.
Mail received on 10-11-2016 & 20.12.2016:
Provision of Bus Coupler bay arrangement was included in the Upgradation works
proposed and the same was sanctioned by MoP through PSDF.
Numerical relay allotted and being commissioned.
Mail received on 20-02-2017:
Numerical BBP relay was commissioned on 02.02.2017
Status received vide mail dated 12.04.2017 & 01.06.2017 & 15-06-2017:
Numerical BBP relay was commissioned on 02.02.2017.
Provision of Bus Coupler bay arrangement was included in the Upgradation works
proposed and the same was sanctioned by MoP through PSDF.
Status received vide mail dated 04.08.2017:
Numerical BBP relay was commissioned on 02.02.2017.
PendingTANTRANSCO
Status?
21-12-2015 at
6:28 hrs
50/I/3 Complete outage of 230kV
Mywadi station of
TANTRANSCO
TANGEDCO mail dated 15.04.2017:
1) New Relay is tested and ready for replacement.Now all 5 units are in service.The
relay will be replaced when lesser units are in service. --- Pending
2.a)Steps are taken to renovate & mordernization of all the control panel into
Numerical based control panels. --- Pending
2.b) Since 230 KV indoor switchyard has no spare space providing dual CT`s is not
fessible. -- Completed
3) Procurement of EL & DR is under progress. --- Pending
TANGEDCO mail dated 26.04.2017:
1) Check zone New Relay is replaced on 17.04.2017 -- Completed.
2. --- Pending
3. --- Pending
TANGEDCO mail dated 13.12.2017:
2).P & C wing gives clearance to TTPS to procure the Bus bar protection relays and
protection relays and SER / DR system vide
Lr.CE/P&C/SE/D/EEPC4/AEE3/F.TECH/D.27/17 Dated: 05.10.2017. To get
administrative approval budgetary offer has bar protection relay from various
companies ----Pending
3). SRPC vide Lr: SRPC/SE- III/CEA/2017/6450/DT:27.10.2017 gives features of
SER/DR. Budgetary offer will be called for SER / DR having above features. ---
Penidng
Review Meeting dated 19.12.2017:
2) & 3) The issue was discussed and TANGEDCO was asked to provide time-line for
implementing the recommendations.
Mail dated 29.01.2018:
Procurement work is under progress and will be completed by December 2018.
Review Meeting on 21.12.2018:
TANTRANSCO informed that Tender would be floated by January 2019 and
Procurement is expected by APril 2019. Works would be completed by December
2019.
Review meeting on 27.06.2019:
2. Tender issued. Timline- July 2020.
3. Tender has to be issued. Timline- July 2020.
PendingTANGEDCO1. TANGEDCO to replace existing Check-Zone relay
with a new one possessing required performance.
2. TANGEDCO to take steps to provide numerical
busbar protection at their 220 kV Tuticorin TPS.
TANGEDCO may also explore providing dual CT’s
(on either side) for all B/S breaakers at the time of
commissioning of numerical BBP, if there were no
space constraints.
3. TANGEDCO to take steps to provide for standalone
Event Logger (EL) and standalone Disturbance
Recorder (DR) with automatic downloading facility to
a centralized server.
Failure of Bus Section-I Y-ph CT resulted in operation
of bus-bar protection for Bus Sections -I & II. Running
Units#1, 4 and 5, 230 kV Kayathar, 230kV
Kudankulam, 230kV Sterlite, Station Transformer-1, 2
& 3 got tripped during the incident. Unit – 2 & 3 were
not in service.
25-01-2017 at
22:36 hrs
Tripping of running Units &
230kV feeders at Tuticorin
TPS of TANGEDCO
(Gen Loss: 640 MW)
62/II/7
Busbar protection got operated for a fault in 230kV
Mywadi-Anaikadavu line
TANTRANSCO to examine the feasibility of
providing two main-zone operation for bus bar
protection by exploring various alternatives like
replacing existing bus-coupler CB with a hybrid bus-
coupler CB that comes with inbuilt CT, replacing
existing BBP relay with another suitable relay that
supports two main-zone operation, and implement the
same.
Annexure-IV
Page 34 of 48
Status received vide mail dated 18-09-2017 & 31-20-2017:
Numerical BBP relay was commissioned on 02.02.2017. Provision of CT in Bus
Coupler bay is arranged and zone segregation will be provided.
Status received vid email dated 12-12-2017:
Numerical BBP relay was commissioned on 02.02.2017. Provision of CT in Bus
Coupler bay has been allotted. Zone segregation will be provided after commissioning
of CT.
Review Meeting dated 19.12.2017:
TANTRANSCO informed that the recommendation would be complied with by
March, 2018.
TANTRANSCO Mail received on 25-01-2018:
Provision of CT in Bus Coupler bay is arranged and zone segregation will be
provided. Timeline: March-2018.
Status received vid email dated 11-12-2018:
Civil work completed & CT will be commissioned after strengthening Bus .2
conductor jumpers.Awaiting Bus LC Time line before January 2019.
TANTRANSCO MAIL DATED 23.01.2019:
Erection under progress will be completed before 31.01.2019
TANTRANSCO MAIL DATED 19.03.2019:
Buscoupler bay will be commissioned by June 2019
TANTRANSCO MAIL DATED 13.06.2019:
Buscoupler bay configuation in BBP will be completed by June 2019. Bus
segregation will be ensured by 31.12.2019 after attending Isolator status feedback.
TANTRANSCO MAIL DATED 18.07.2019:
Buscoupler bay configuation in BBP will be completed by June 2019. Bus
segregation will be ensured by 31.12.2019 after attending Isolator status feedback.
Mail recieved on 25-07-2016 & 24-09-2016:
TANTRANSCO: Auto Transformer-2 HV side Bus isolator 'C'-phase support
insulator of 230kV Southern Bus was replaced and Bus Bar Protection scheme was
restored on 12.05.2016.
Status received vide mails received on 10-11-2016 & 20.12.2016 & 12.04.2017
& 01.06.2017 & 15-06-2017 & 04.08.2017 & 18.09.2017:
CT is not available in the Bus Coupler bay for zone segregation. CT latch relay is to
be provided for all bays for zone segregation.
Status received vide mails received on 31-10-2017 & 12-12-2017:
Numerical Bus bar protection panel allotted and will be commissioned with zone
segregation..
Review Meeting dated 19.12.2017:
TANTRANSCO informed that Numerical BBP would be commissioned by March,
2018.
TANTRANSCO MAIL DATED 22.05.2018 & 08.06.2018:
Numerical Busbar protection relay commissioned on 14.05.2018
TANTRANSCO MAIL DATED 23.07.2018:
Control & Status of isolator feedeback to be provided by replacement of Drive
Mechanism box.
TANTRANSCO MAIL DATED 29.08.2018:
Control & Status of isolator feedeback to be provided by replacement of Drive
Mechanism box.
TANTRANSCO MAIL DATED 11.09.2018:
Control & Status of isolator feedeback to be provided by replacement of Drive
Mechanism box. Timeline requested upto Dec 2018.
Status received vid email dated 11-12-2018:
1. TANTRANSCO: Estimate sanctioned for replacement of defective isolator status
feedback. Work under progress. Lightning mask work under progress will be
completed within three days.
Review Meeting on 21.12.2018:
TANTRANSCO informed that Double bus operation would be provided by March,
PendingTANTRANSCO21-12-2015 at
6:28 hrs
50/I/3 Complete outage of 230kV
Mywadi station of
TANTRANSCO
Pending55/I/1
(GD)
Complete outage of 230 kV
Gummidipoondi Station of
TANTRANSCO
12-05-2016 at
12:15 hrs
Flashover of Auto Transformer- 2 HV
B-phase Isolator supporting insulator of 230kV
Southern Bus occurred at Gummidipoondi station. At
the time of fault, Bus bar protection relay was not in
service for pre-commissioning testing of Auto
Transformer-2. All feeders got tripped due to operation
of zone-2 protection from remote ends.
Busbar protection got operated for a fault in 230kV
Mywadi-Anaikadavu line
TANTRANSCO to examine the feasibility of
providing two main-zone operation for bus bar
protection by exploring various alternatives like
replacing existing bus-coupler CB with a hybrid bus-
coupler CB that comes with inbuilt CT, replacing
existing BBP relay with another suitable relay that
supports two main-zone operation, and implement the
same.
TANTRANSCO TANTRANSCO to take steps to provide double-bus
operation at their 230 kV Gummidipoondi SS.
Annexure-IV
Page 35 of 48
TANTRANSCO MAIL DATED 19.03.2019:
New 230kV isolators have been allotted for replacement of defective isolators. Hence
time line requested upto June.2019.
TANTRANSCO MAIL DATED 13.06.2019 & 18.07.2019:
New 230kV isolators have been allotted for replacement of defective isolators. Hence
time line requested uptoSep.2019
Pending55/I/1
(GD)
Complete outage of 230 kV
Gummidipoondi Station of
TANTRANSCO
12-05-2016 at
12:15 hrs
Flashover of Auto Transformer- 2 HV
B-phase Isolator supporting insulator of 230kV
Southern Bus occurred at Gummidipoondi station. At
the time of fault, Bus bar protection relay was not in
service for pre-commissioning testing of Auto
Transformer-2. All feeders got tripped due to operation
of zone-2 protection from remote ends.
TANTRANSCO TANTRANSCO to take steps to provide double-bus
operation at their 230 kV Gummidipoondi SS.
Annexure-IV
Page 36 of 48
The issue was discussed in PCSC-58 meeting held on 18.10.2016, when PCSC forum
agreed to de-link the implementation of the Item from the scope of Protection Audit
Recommendations (PAR), and pursue it as part of PCSC Recommendations.
Status received vide mails dated 10.01.2017 & 12.04.2017 & 01.06.2017 &15-06-
2017 & 04.08.2017 & 18.09.2017 & 31-10-2017& 12-12-2017:
Different make Relays will be provided for Main-I & II relays at Sunguvarchatram
end in a phased manner.
TANTRANSCO MAIL DATED 22.05.2018:
TANTRANSCO informed that the recommended works of providing different make
Relays for Main-I & Main-II are targeted to be completed by September, 2018.
TANTRANSCO MAIL DATED 08.06.2018:
provision of Different make Relays for Main-I & Main-II will be completed by
September, 2018.
TANTRANSCO MAIL DATED 23.07.2018:
Different make Relays will be provided for Main-I & II relays at Sunguvarchatram
end in a phased manner. Timeline: September-2018.
TANTRANSCO MAIL DATED 29.08.2018 & 11.09.2018:
Different make Relays will be provided for Main-I & II relays at Sunguvarchatram
end in a phased manner. Timeline: September-2019.
TANTRANSCO MAIL DATED 11-12-2018:
Different make Relays will be provided for Main-I & II relays at Sunguvarchatram TANTRANSCO MAIL DATED 23.01.2019:
Different make Relays will be provided for Main-I & II relays at Sunguvarchatram
end in a phased manner. Timeline: September-2019.
TANTRANSCO MAIL DATED 13.06.2019 & 18.07.2019:
Different make Relays will be provided for Main-I & II relays at Sunguvarchatram
end in a phased manner. Timeline: September-2019
14-09-2016 at
11:13Hrs
Bus Bar Protection (Zone-2) of 230 kV Bus-B got
operated at Alamathy Station during fault in 230 kV
Alamathy-Korattur feeder.
58 Different type and Make of distance protection relays to be provided for Main-I & Main-II protection for 230kV feeders at 400 kV Sunguvarchathiram & 230 kV
Sunguvarchathiram Substation [Carry-Over from Protection Audit Recommendations]
TANTRANSCO Mail received on 10-11-2016 & 20.12.2016:
1. The Bus Bar Protection scheme will be tested for healthiness including the CT
circuits.
2. High impedance BBP relay will be replaced by Numerical relay.
Status received vide mails dated 10.01.2017 & 12.04.2017 & 01.06.2017 & 15-06-
2017:
1. The Bus Bar Protection scheme was tested for healthiness including the CT
circuits. AREVA make CTs in Alamathy SS are having different kneepoint voltage
for the cores. CT cores of higher knee point voltage has been choosen for BBP in
230kV Korattur, 230kV OPG-1 & 230kV OPG-2 feeders on 29.11.2016. ----
Completed.
2. High impedance BBP relay will be replaced by Numerical relay. --- Pending,
Status received vide mails dated 04.08.2017 & 18.09.2017 & 31-10-2017 & 12-
12-2017.
1. ---- Completed
2. High impedance BBP relay will be replaced by Numerical relay. --- Pending
Review Meeting dated 19.12.2017:
2) TANTRANSCO informed that Numerical BBP would be provided by April, 2018
--- Pending
TANTRANSCO mail received on 25-01-2018:
1. --- Complied.
2. High impedance BBP relay will be replaced by Numerical relay. Timeline: April-
2018.
TANTRANSCO MAIL DATED 22.05.2018 & 08.06.2018 & 23.07.2018:
2.Numerical BBP relay will be provided. Timeline: Sep-2018.
TANTRANSCO MAIL DATED 29.08.2018 & 11.09.2018:
1. Complied
2.Numerical BBP relay will be provided. Timeline: Sep-2018.
Pending1. TANTRANSCO to check the healthiness of BBP
relay by conducting stability test, and take appropriate
remedial action like increasing voltage settings,
ensuring the healthiness of CT’s, using CT’s with
similar characteristics (equal saturation effects &
equal winding resistances) etc. at their 230 kV
Alamathy SS.
2. TANTRANSCO to replace the existing high-
impedance BBP relay with its low-impedance/
numerical variant so as to accommodate variation in
CT characteristics at their 230 kV Alamathy SS.
58/II/17 Multiple tripping at 230 kV
Alamathy Station
TANTRANSCO Pending
Annexure-IV
Page 37 of 48
TANTRANSCO MAIL DATED 11-12-2018:
Numerical BBP relay to procured. Timeline: Sep-2019.
TANTRANSCO MAIL DATED 23.01.2019:
Numerical BBP relay to be procured. Timeline: Sep-2019.
TANTRANSCO MAIL DATED 19.03.2019 & 13.06.2019 & 18.07.2019:
Numerical BBP relay to be procured. Timeline: Sep-2019.
Review meeting on 27.06.2019:
Bus Bar Protection (Zone1) of 230kV Bus-A got
operated at Alamathy Station during fault in 230 kV
Alamathy-OPG-1 feeder.
TANTRANSCO Mail received on 10-11-2016 & 20.12.2016:
1. The Bus Bar Protection scheme will be tested for healthiness including the CT
circuits.
2. High impedance BBP relay will be replaced by Numerical relay.
Status received vide mails dated 10.01.2017 & 12.04.2017 & 01.06.2017 & 15-06-
2017:
1. The Bus Bar Protection scheme was tested for healthiness including the CT
circuits. AREVA make CTs in Alamathy SS are having different kneepoint voltage
for the cores. CT cores of higher knee point voltage has been choosen for BBP in
230kV Korattur, 230kV OPG-1 & 230kV OPG-2 feeders on 29.11.2016. ----
Completed.
2. High impedance BBP relay will be replaced by Numerical relay. --- Pending,
Status received vide mails dated 04.08.2017 & 18.09.2017 & 31-10-2017 & 12-
12-2017.
1. ---- Completed
2. High impedance BBP relay will be replaced by Numerical relay. --- Pending
Review Meeting dated 19.12.2017:
2) TANTRANSCO informed that Numerical BBP would be provided by April, 2018
--- Pending
TANTRANSCO mail received on 25-01-2018:
1. --- Complied.
2. High impedance BBP relay will be replaced by Numerical relay. Timeline: April-
2018.
TANTRANSCO MAIL DATED 22.05.2018 & 08.06.2018 & 23.07.2018:
2.Numerical BBP relay will be provided. Timeline: Sep-2018.
TANTRANSCO MAIL DATED 29.08.2018 & 11.09.2018:
1. Complied
2.Numerical BBP relay will be provided. Timeline: Sep-2018.
Pending
15-09-2016 at
22:14 hrs
1. TANTRANSCO to check the healthiness of BBP
relay by conducting stability test, and take appropriate
remedial action like increasing voltage settings,
ensuring the healthiness of CT’s, using CT’s with
similar characteristics (equal saturation effects &
equal winding resistances) etc. at their 230 kV
Alamathy SS.
2. TANTRANSCO to replace the existing high-
impedance BBP relay with its low-impedance/
numerical variant so as to accommodate variation in
CT characteristics at their 230 kV Alamathy SS.
58/II/17 Multiple tripping at 230 kV
Alamathy Station
Annexure-IV
Page 38 of 48
64/1/4 Complete outage of North
Chennai TPS STG-1
26-03-2017
at 23:14hrs
Tripping of evacuating lines due to fault led to tripping
of running Unit at NCTPS Stg-1
1. TANTRANSCO to take steps to complete insulator
replacement works on the 230 kV lines owned by them
in NCTPS area within 6 months.
2. TANTRANSCO to take steps to implement A/R on
all 230 kV lines emanating from NCTPS-I at the
earliest.
TANTRANSCO Status received vide mails dated 04.08.2017 & 18.09.2017 & 31-10-2017:
1. All the Porcelain insulators were replaced with Polymer insulators in 230kV
NCTPS-I - Tondiarpet feeders - 1 & 2.
---- Completed
2. AR will be implemented on all 230kV lines emanating from NCTPS-I. --- Pending
Status received vid email dated 12-12-2017:
1. Completed
2. The scheme needs modification to enable AR, since AR was not envisaged for this
station during commissioning. AR will be implemented on all 230kV lines emanating
from NCTPS-I within six months. --- Pending
Review Meeting dated 19.12.2017:
2) TANTRANSCO informed that A/R would be implemented on all 230 kV lines
emanating from NCTPS-I by June, 2018.
TANTRANSCO mail received on 25-01-2018:
1. Complied.
2. The scheme needs modification to enable AR, since AR was not envisaged for this
station during commissioning. AR will be implemented on all 230kV lines emanating
from NCTPS-I within six months. Timeline:June-2018.
Pending
TANTRANSCO MAIL DATED 22.05.2018:
2. The scheme needs modification to enable AR, since AR was not envisaged for this
station during commissioning. AR will be implemented on all 230kV lines emanating
from NCTPS-I Timeline:Sep -2018.
TANTRANSCO mail received on 08-06-2018:
1. Complied.
2. The scheme needs modification to enable AR, since AR was not envisaged for this TANTRANSCO MAIL DATED 11-12-2018:
2. Enabling AR pending for 3 feeders. ( Sriperumpudhur end breaker problem,
Tondiarpet & Alamathy feeder . static relay to be replaced. Timeline - 1 year
TANTRANSCO MAIL DATED 23.01.2019:
Enabling AR pending for 3 feeders. ( Sriperumpudhur end breaker problem,
Tondiarpet & Alamathy feeder . static relay to be replaced. Timeline -Sep 2019
TANTRANSCO MAIL DATED 19.03.2019 & 13.06.2019 & 18.07.2019:
Enabling AR pending for 3 feeders. ( Sriperumpudhur end breaker problem,
Tondiarpet & Alamathy feeder . static relay to be replaced. Timeline -Sep 2019
77/II/9 Multiple trippings at
400 kV Manali Substation
TANTRANSCO to refer the issue of selective tripping
of 400 kV side breakers, and non-tripping of 230 kV
side breakers due to operation of Densimeters on low
pressure in the instant case to their OEM, and share
OEM’s advice/ remedy in this regard.
TANTRANSCO mail dated 11.09.2018:
OEM will be referred
Review Meeting on 21.12.2018:
TANTRANSCO was asked to update the status.
TANTRANSCO MAIL DATED 23.01.2019, 19.03.2019 & 13.06.2019:
The issue was referred with OEM & reply awaited.
Review meeting on 27.06.2019:
OEM reply shall be communicated by end of July 2019
TANTRANSCO mail dated 18.07.2019:
The issue was referred with OEM & reply awaited
Pending
Annexure-IV
Page 39 of 48
79/I/3 Complete outage of 230 kV
Thiruvalam Substation
05-10-2018 at
14:32 hrs
Bus-1 got tripped at 230 kV Thiruvalam substation due
to spurious LBB relay (independent) operation of
230kV Thiruvalam Chittoor line. 230kV Thiruvalam
substation was under single bus operation; hence
operation of LBB protection resulted in tripping of all
connected elements resulting in the complete outage
TANTRANSCO to take steps to implement multi-bus,
multi-zone operation (Double-bus operation) at their
230 kV Thiruvalam SS by December, 2018.
TANTRANSCO TANTRANSCO MAIL DATED 11-12-2018:
Due to space constraint, the equipments could not be erected.
Review Meeting on 21.12.2018:
It was noted that the station was on a single (Main) bus and there was not even
transfer bus. In view of the importance of 230 kV Thiruvalam SS, TANTRANSCO
was asked to take steps to provide dobule-bus operation at their 230 kV Tiruvalam
SS.
TANTRANSCO MAIL DATED 23.01.2019 & 19.03.2019:
Feasibility for providing hybrid breaker / shifting of bays will be studied & action
will be taken. Time upto Sep 2019
TANTRANSCO MAIL DATED 13.06.2019 & 18.07.2019:
Bus segregation will be ensured by providing bus coupler bay by extending the
existing Bus.Time line 31.12.2019.
Pending
80/II/12 Tripping of all elements
connected to 230 kV
Anaikadavu SS
06-11-2018 at
21:35 Hrs
Triggering incident was failure of R-ph PT of 230 kV
Anaikadavu Bus-1. 230 kV Bus bar protection of bus-
1 operated resulting in tripping of all the connected
elements. 230 kV Anaikadavu was on single bus
operation due to failure of Bus-2 PT during antecedent
conditions.
1) TANTRANSCO to adopt recommended OVR,
Stage-I and OVR, Stage-II protections at their 400 kV
Anaikadavu and 400 kV Rasipalayam stations, and to
ensure that OVR-I_START signal is configured for
triggering corresponding Event Logger (EL), and OVR-
I_TRIP is configured for triggering corresponding
Event Logger (EL) and Disturbance Recorder (DR).
2) TANTRANSCO to take steps to restore multi-bus,
multi-zone operation at their 230 kV Anaikadavu SS at
the earliest.
TANTRANSCO TANTRANSCO MAIL DATED 23.01.2019 & 19.03.2019:
1……Complied
2.Bus PT is to be supplied by the Turnkey contractor will be replaced by 31.03.2019
TANTRANSCO MAIL DATED 13.06.2019:
Bus PT is to be supplied by the Turnkey contractor
Review meeting on 27.06.2019:
Timeline requested upto December 2019.
TANTRANSCO mail dated 18.07.2019:
Bus PT is to be supplied by the Turnkey contracto
Pending
82/I/1 Complete outage of 400kV
Sriperumbudur station
28-01-2019
at 01:15 Hrs
Failure of ‘R-phase’ HV side Current transformer (CT)
of 315MVA 400/230kV ICT-3 at 400kV
Sriperumbudur substation (400kV TANTRANSCO
switchyard).
1) TANTRANSCO to ensure proper legends for DR
Digital signals and all required events(including CB
status, Type of protection operated) are captured in
Event logger.
2) TANTRANSCO to extend BBP trip from BusBar
relay to 86A (with source-1 DC) in addition to 86B
(with source-2 DC), or to provide Common trip relay
96 with redundant DC supply.
3) TANTRANSCO to inform the action plan with
timelines for providing Numerical BBP at
Sriperumbdur SS .
4) TANTRANSCO to check the healthiness of all
CT’s in the stationand submit a report regarding the
same to SRPC to prevent any such occurrence in
future.
TANTRANSCO TANTRANSCO MAIL DATED 13.06.2019:
1. At present Duobias relay avaiable I/O configuration could not be carried out.after
changing the relay Digital signals will be configured
2.COMPLIED
3.Provision of Numerical BBP relay covered under R&M work. Tender under
progress.
4.out of 30 CTs, 21 No CTs have been replaced with new one.
Review meeting on 27.06.2019:
1. , 3. Timeline requested upto July 2020.
2. Complied
4. Timeline requested upto September 2019.
TANTRANSCO mail dated 18.07.2019:
1. At present Duobias relay avaiable I/O configuration could not be carried out.after
changing the relay Digital signals will be configured
2.COMPLIED
3.Provision of Numerical BBP relay covered under R&M work. Tender under
progress.
4.out of 30 CTs, 21 No CTs have been replaced with new one.
Pending
83/I/7 Complete outage of
230kV/110kV KR Thoppur
Substation of
TANTRANSCO
11-04-2019
at 13:16Hrs
Triggering incident was failure of Y-ph CT of Bus
Coupler at 230kV KR Thoppur(Salem) SS. Bus bar
protection of Bus-1 and Bus-2 operated resulting in the
tripping of all the connected elements at 230kV KR
Thoppur SS. 400kV/230kV ICT#1 and 2 at Salem also
got tripped during this event.
1.TANTRANSCO informed that replacement of
mechanical relay by Numerical relay is under progress
and it is recommended to submit the action plan
regarding the same with proper time-lines.
2.TANTRANSCO is also recommended to send
equipment failure report to CEA regarding failure of
Bus coupler CT.
TANTRANSCO TANTRANSCO MAIL DATED 13.06.2019 & 18.07.2019:
1. Replacement of numerical relay under progress
2.Equipment failure report will be sent
Pending
Annexure-IV
Page 40 of 48
83/II/13 230kV Bus dead at 230/110
kV Pugalur
14-03-2019 at
13:24 hrs
Triggering incident was R-phase breaker failure in
230kV Pugalur end of Budansandhai feeder. LBB
operated resulting in tripping of all connected elements.
As reported, 230kV side was on single bus operation
since bus sectionalizer provision is not there. 110kV
side connected feeders did not trip.
TANTRANSCO is recommended to furnish
equipment failure report to CEA regarding failure of
CB.
TANTRANSCO TANTRANSCO MAIL DATED 13.06.2019 & 18.07.2019:
Equipment failure report will be sent
Pending
85/II/1 Tripping of 400/230kV
MANALI ICT-3
13-05-2019 at
2:42 hrs
ICT-3 got tripped on the activation of HV REF
protection. During test charging of 110 kV Manali-
ETPS -1 , the 110 kV ETPS -1 got tripped on the
activation of Back up relay and Distance relay failed to
act
1. TANTRANCO is recommended to sort out the
malfunctioning of ICT Ref protection in consultation
with OEM and submit a detailed report regarding the
same in 1 month time.
2. TANTRANSCO is recommended to ensure proper
labelling of all digital signals in Disturbance recorders
of lines and ICTs at Manali SS.
TANTRANSCO Yet to be informed Pending
85/III/6 400 KV Thiruvelam – Palavadi
line-1
28-05-2019 at 18:04
hrs
B-phase to earth fault. A/r attempt could not be validated. TANTRANSCO is recommended to check sending of DT from
Palvadi end during 3-ph trip at Palvadi. The time
synchronization issues between Thiruvalem and Palvadi shall
also be rectified.
TANTRANSCO Yet to be informed Pending
85/IV/6 Tripping of 400kV Kayathar-
Kanarpatty line-1 & 2
10-06-2019 at 12:22
hrs
Line-1 & 2 tripped at Kanarpatty end due to spurious DT sent
from kayathar end. Feeder did not trip at Kayathar end
TANTRANSCO is recommended to submit a report regarding
the problem with PLCC panel at Kayathar along-with
Remedial Measures suggested by OEM.
TANTRANSCO Yet to be informed Pending
Annexure-IV
Page 41 of 48
KSEB Mail received vide dated 17.01.2017:
1. 110 kV bus bar protection progressing ----Pending
2. Connection of 220kV earth mat and 110 kV plate earthing system completed.----
Completed
3. Redundancy of 110V DC system in progress. Complete independent redundancy is
not practical for the time being. 48 V DC redundancy was already there. ----
Pending
4. Instead of stand alone event logger, SCADA system of 110 kV feeder is expected
to be completed by the end of 2017. SCADA system of 220kV side will be taken up
Status received vide mail dated 12-12-2017:
1. Detailed engineering of the scheme has been completed. Material procurement is in
progress. ---Pending
2.,3. ---- Completed
4. The SOE and DR are available with time stamping from the numerical relays.
Hence stand alone event logger is not necessary ----- Completed
Status received vide mail dated 11-12-2018:
Work has been already tendered. It is expected that purchase process will completed
Status received vide mail dated 03.05.2019:
Sanction to issue purchase order in progress. Time Frame is January 2020 .
Review meeting on 27.06.2019.
1. BBP will be commissioned by December 2019.
2.,3.,4. Completed
79/I/1 Complete Outage of 220 kV
Idukki Power Station
01-10-2018 at
04:16 hrs
Triggering incident was R-Ph fault in 220kV Idukki-
Kalamassery line-2. R-phase pole of breaker didn’t
open at Idukki end. LBB of Bus-2 operated resulting in
tripping of all connected elements along with running
Unit#4 at Idukki and 50MVA station transformer. At
the same time, 220kV Idukki Kalamassery line-1 also
got tripped at Idukki end. Subsequently running Units 1
and 2 also tripped on Governor oil Low Pressure due to
loss of AC supply. This resulted in complete outage of
1). KSEBL to check & correct the LBB time setting
employed at their Idukki PH to 200 msec.
2). KSEBL o ensure that DR’s & EL’s of all
Protection Relays (PR’s) at their Idukki PH are
configured for recording all mandated protections &
signals.
KSEBL Status received vide mail dated 11-12-2018:
1) Present setting is 180ms.OEM(ABB) suggests that it will give around 200ms
delay as it is having inherent delay is of around 20ms(ie, 180ms +20ms
=200ms).With this setting the fault clearence is found after 220ms.So further revision
may be carried out after discussion.
2)Breaker status will be ready only after completing the GOOSE network as part of
renovation of all feeder panels and Idukki first stage units by June 2019 .
Pending
80/II/5 Multiple trippings at 220 kV
Madakathra station
15-10-2018 at
08:57 Hrs
Triggering incident was Y-phase to ground fault in
220kV Madakathra – Palakkad_KL (Ellapully) line
due to flashover of pilot insulator string. Auto-reclose
was successful at Madakathra end. At the same time
bus differential relay Zone-C mal-operated resulting in
tripping of all elements connected to the bus.
KSEBL to take steps to replace the existing static
(high impedance type) 220 kV BBP with numerical
Busbar protection at their 220 kV Madakathara SS.
KSEBL Status received vide mail dated 11-12-2018:
In progress
Status received vide mail dated 19.03.2019:
Status as on 18.03.2019: Estimate sanctioned by CE(Transmission North ) and have
prepared the technical specifications.Tendering procedures are yet to get started.
Status received vide mail dated 03.05.2019:
Pending
23-08-2016
at 11:20 hrs
Complete outage of 220 kV
Kalamassery Substation
Triggering incident was conductor snapping in 110 kV
Kalamassery- Kaloor feeder
1. Time-frame?58/I/1
(GD)
KSEB to take steps to provide the following at their
220/ 110 kV Kalamassery SS:
1. Busbar protection at 110 kV level
2. Connecting 220 kV and 110 kV sides on to a
common earthmat
3. Redundant DC supply for both protection (220 V)
and communication (48 V) applications
4. Stand-alone Event Logger
KSEB Pending
Kerala
PED
Annexure-IV
Page 42 of 48
82/I/5 Complete Outage of 220kV
Bhramapuram substation of
KSEB
08-02-2019 at
10:28 hrs
Complete outage of 220kV Brahmapuram SS occurred
due to suspected mal operation of Bus Bar protection.
1) KSEBL to furnish detailed report regarding the
healthiness of BBP operation at 220kV Brahmapuram
after testing of the same on 12th April 2019.
2) KSEBL to submit the action plan regarding
(i) Replacing of the Static High impedance BBP
(using CRM relays) with Numerical BBP.
(ii) Replacement of CRM relays and relays with no
Disturbance recording facilitites.
KSEBL Status received vide mail dated 03.05.2019:
1) Detailed report sent on 02.05.2019…..Completed.
2) As reported earlier in this regard, the permanent solution to this problem is to
replace the existing high impedance static relay with a low impedance numerical
relay. The station authorities have already initiated action to implement the same by
June 2020.
Pending
84/I/3 Complete outage of 220 kV
Edamon SS of KSEB
27-05-2019 at
12:30 hr.
Triggering incident was three phase to earth fault in
220 kV Edamon Bus 1 and 2. Bus 1 and 2 Bus bar
protection operated resulting in the tripping of all
connected elements.
1.KSEBL may develop proper operational code for
procedures to be followed while performing operations
in switchyard and sensitize their operators to reduce
operational errors. 2.ksEBL to ensure time
synchronization of relays at 220 kV Edamon SS.
KSEBL KSEBL mail dated 30.07.2019:
1. proper operrational code is avilalable in 220kV SS Edamon
2. All 220KV relays of Edamon substation are synchronized with GPS clock . Out of
this, 3 relays are having hardware issues with time synchronisation switch . This
problem will be resolved by August 2019 itself.
Pending
85/I/2 Complete outage of 220kV
Pothenkode Substation of
KSEB
04-07-2019
at 01:18 hrs
Triggering incident was failure of suspension insulator
of 220kV Pothenkode – Trivendrum ckt-2. Bus bar
protection of Bus-1 and Bus -2 operated resulting in
tripping of all connected elements.
1. KSEBL is recommended to investigate the non-
operation of zone selective Busbar Operation at 220/
110kV Pothencode SS and submit detailed report
regarding reasons for the same alongwith remedial
measures taken.
2. KSEBL is recommended to ensure time
synchronization of relays at 220/ 110kV Pothencode
SS.
KSEBL Yet to informed Pending
85/II/9 Tripping of 220KV Sabarigiri-
Theni line23-05-2019
at 16:12 hrs
Line tripped on operation of DEF at Theni end KSEBL is recommended to configure in DR and EL
the pick up and operation of relevant distance
protection zones in the event of distance protection
operation.
KSEBL Yet to informed Pending
82/II/6 Tripping of 400/220 kV ICT-
1 at Khammam
27-01-2019
at 14:33hrs
ICT-1 at Khammam tripped on operation of IV side
non directional Over-current high set during failure of
L.A in 220kV Khammam (Budhidampadu)-Suryapet
line-2
PGCIL (SR-I) to immediately take necessary actions
to raise the Highset pick up current setting as per
protection standards since unwarranted tripping of ICT
for fault on 220kV line compromises the reliability of
Power system. In any case the transformer protection
should not encroach into protection zone of nearby
protection element.
PGCIL (SR-I) Review meeting on 27.06.2019:
PGCIL (SR-I) informed that the ICT high set settings have been sent by mail
Pending
84/II/3 Tripping of 400kV KTPS-
Khammam line
11-04-2019 at 13:59 hr.Line tripped on operation of overvoltage stage-1
protection at KTPS end and DT received at Khammam
end. Phase voltages at KTPS end could not be verified
from the DR furnished.
PGCIL (SR-I) to ensure time synchronization of DR
and EL at Khammam end.
PGCIl (SR-I) Yet to be informed Pending
80/II/9 Tripping of 400/220 kV ICT-
2 at Bangalore (Somanahalli)
26-10-2018 at
12:10 Hrs
400/220 kV ICT-2 at Bengaluru (Sonamahalli) tripped
due to operation of LV side over flux protection which
in turn was due to suspected 220 kV CVT problem.
PGCIL (SR-II) to configure DR’s & EL’s all
protection relays at their 400/ 220 kV Somanahally SS
for all mandated protections and signals.
PGCIL (SR-II) Review meetinmg on 27.06.2019:
PGCIL (SR-II) was asked to furnish the status of implementation of the
recommendation at the earliest.
Pending
84/II/2 Tripping of 400kV
Somanahalli-Dharmapuri
line-2
07-04-2019 at
18:02 hr.
Line tripped on operation of over voltage stage-1
protection at Somanahalli. Somanahalli end DR: Vr-
240kV, Vy-253kV, Vb-241kV. Y-phase voltage was
higher than R and B phase
1. PGCIL (SR-II) to configure OVR start and OVR
trip signal in Event logger to facilitate verification of
adopted OVR grading.
2.PGCIL (SR-II) to ensure time synchronization of
DR and EL at Somanahalli end and Dharmapuri end.
PGCIL (SR-II) Yet to be informed Pending
84/II/15 Tripping of 400kV Bus-1
and connected elements at
400kV Bidadi substation
25-04-2019 at 08:01 hr.Triggering incident was failure of R-ph CB of bus
reactor at 400kV Bidadi. Bus bar protection of Bus-1
operated resulting in the tripping of all elements
connected to Bus-1
1. PGCIL (SR-II) was requested to send the
equipment failure report to CEA.
2.PGCIL (SR-II) is recommended to share the
feedback of OEM regarding decomposition of SF6 gas.
PGCIL (SR-II) Yet to be informed Pending
PGCIL (SR-I) & PGCIL (SR-II)
Annexure-IV
Page 43 of 48
85/II/8 Tripping of 765/400kV ICT-
1 and 2 at Kurnool
substation
21-05-2019 at
18:11 hrs
ICT 1 and 2 got tripped due to maloperation of
Bucholz relays during the charging of 400KV Kurnool-
Nanoor line 1 which tripped on SOTF
PGCIL (SR-I) is recommended to submit a detailed
report regarding operation of Buchholz relay of 765/
400kV ICT 1& 2 during through fault after
consultation with OEM along-with the remedial
measures taken to prevent occurrence of any such
incidence in future.
PGCIL (SR-I) Yet to be informed Pending
85/II/16 Tripping of 400kV Tumkur-
Bidadi line-1&2, 400kV
Tumkur-Cuddapah line-2,
400kV Tumkur-Pavagada
line-2
29-05-2019 at
6:11 hrs
Lines tripped due to Y-N & Y-B phase to earth fault PGCIL (SR-2) is recommended to submit Equipment
failure report to CEA regarding the failed LA.
PGCIL (SR-II) Yet to be informed Pending
85/II/18 Tripping of 765/400kV ICT-
2 at Kurnool
02-06-2019 at
17:41 hrs
ICT-2 got tripped on operation of Back up directional
over current due to through fault (Y-B phase fault).
PGCIL (SR-1) is requested to check the operation of
ICT HV side High set O/C protection for through fault
and submit a report regarding the same.
PGCIL (SR-I) Yet to be informed Pending
85/III/7 Tripping of 400kV Pugalur-
Karaikudi line-1
31-05-2019 at
17:44 hrs
R-phase to earth fault occurred in line. Auto-reclose
was successful at Karaikudi, At Pugalur end there was
3-phase trip
PGCIL (SR-2) is recommended to ensure proper
condition monitoring of their CB’s such as sufficient
air pressure.
PGCIL (SR-II) Yet to be informed Pending
Others
Annexure-IV
Page 44 of 48
69/I/1 Complete outage of 400kV
TPCIL station
25-10-2017 at
19:33 hrs
400 kV TPCIL-Nellore PS line-1 got tripped from
TPCIL end during fault in 400kV Nellore-Nellore PS
line-2. Running units at TPCIL got tripped due to loss
of evacuating line. 400kV Nellore PG - Nellore PS line-
2 and 400kV TPCIL - Nellore PS line-1 were under
shutdown.
TPCIL to configure DEF protection such that it
remains in blocked condition as long as Distance
Protection is active, and becomes active only when
distance protection does not pickup.
TPCIL Review Meeting on 21.12.2018:
It was noted that no TPCIL representatives had come to attend the meeting
Review meetinmg on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit status
regrading the recommendation at athe earliest.
Pending
Status revided vide MAPS mail dated 06.12.2016;
1. The settings given by M/s TANTRANSCO were adopted for Main –I & Main- II
relays for both the lines. The same settings were verified to be same. Subsequently
calibrated was done and no drift was observed. --- Completed
2. From May 2016 onwards, the DR, EL and trip report are being sent by mail to
SRLDC, Bengaluru by MAPS. --- Completed
B-phase CT failure occurred in 230 kV S.P.Koil -
MAPS line-1. Busbar protection got operated at
SP.Koil station. All elements except 230kV Oragadam
and 230kV Kalivandapattu got tripped at 230kV
S.P.Koil station. ‘Y’ phase CT and support insulators
also got damaged.
1.MAPS to furnish a detailed report on the tripping of
SP Koil – MAPS lines 1 & 2 at MAPS end with focus
on the correctness of the settings of Main-I & Main-II
relays (for primary & back-up protections) on both the
lines.
2.MAPS to take steps to provide down-loading facility
02-04-2016 at
17:08 hrs
54/I/1 Complete outage of 230 kV
S.P.Koil Station of
TANTRANSCO
PendingNPCIL (MAPS)
Annexure-IV
Page 45 of 48
78/II/2 Tripping of 400 kV Neyveli
TS2Exp -Pugalur line
01-08-2018
at 11:56 hrs
Triggering incident was failure of R-ph tension
insulator string/ flashover in 400 kV Bus-1 at NLC
TS2Exp end. Busbar protection had operated resulting
in tripping of all main breakers connected to 400kV
Bus-1 at Neyveli TS2 Exp. In 400kV NLC TS2Exp -
Pugalur line, fault was sensed in Zone-1, R-N at
Pugalur end resulting in a single phase trip. Direct Trip
was received at Pugalur end due to operation of over
voltage Stg-2 at NLC TS2Exp.
1. NLCIL to furnish a report along with a suitable
SLD on the tripping event explaining the observed
discrepancies [DPR, Z1 operation, instantaneous
operation of OVR-II operation], and remedial action
taken to attend the same.
2. NLCIL to configure DR’s & EL’s of all protection
relays at their NLC TS-IIExp station for all mandated
protections & signals.
NLCIL Review Meeting on 21.12.2018:
NLCIL was asked to furnish the status of implementation of the recommendation
given at the earliest.
Review meetinmg on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit status
regrading the recommendation at athe earliest.
Pending
79/II/8 Tripping of 400 kV NLC TS-
2 (Exp) – Pugalur line
10-09-2018 at
20:57 hrs
Line tripped on B-N fault. Auto-reclose was not
attempted at Pugalur end due to DT receipt from NLC
TS2Exp end. At NLC TS2Exp end, V>2 trip was
observed in DR. Analog voltages recorded in DR were
observed to be less than that required for O/V Stage-II
operation.
NLCIL to furnish a detailed report on tripping event
explaining the observed discrepancies , and proper
reasons for tripping of the line considering both the
Main-relays including remedial action taken w.r.t.
healthiness/ replacement of Main protection relays on
400 kV NLC TS2Exp–Pugalur line.
NLCIL Review Meeting on 21.12.2018:
NLCIL was asked to furnish the status of implementation of the recommendation
given at the earliest.
Review meetinmg on 27.06.2019:
it is requested to submit status regrading the recommendation at athe earliest.
Pending
80/II/17 Tripping of 400 kV Nellore
PS – SGPL line-1
14-11-2018 at
20:20 hrs
Y- ph to earth fault occurred in line due to snapping of
GIS to Air bushing conductor at SGPL switchyard.
The conductor got grounded such that the fault was
being fed by NPS bus and there was earth fault and
broken conductor start at SGPL end. NPS end got
tripped in Zone-2 due to non-receipt of carrier resulting
in a 3-ph trip at NPS. After 500ms, earth fault
occurred at SGPL end resulting in Zone-1 operation
and 3 phase trip. A/R was not attempted at SGPL end
SGPL to examine the reasons for no-operation / failure
of Auto-reclosure from their end for the subject
tripping, and furnish an action taken report detailing
remedial measures taken to PCSC forum.
SGPL Review meetinmg on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit status
regrading the recommendation at athe earliest.
Pending
80/III/6 Tripping of 400 kV Neyvelli
TS2 (Exp) - Pugalur line
07-11-2018 at
05:50 Hrs
400 kV Neyvelli TS2Exp - Pugalur tripped on
B-phase to ground fault due to DPR, Z1 operation.
Auto-reclose was successful at Pugalur end and the
line tripped at Neyveli TS2Exp end only. Auto-reclose
was not attempted at Neyveli TS-2(Exp) end
NLCIL to furnish a detailed report on the reasons for
A/R non-operation for the subject tripping at their
NLCTS2Exp station including remedial measures
taken to PCSC forum.
NLCIL Review meetinmg on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit status
regrading the recommendation at athe earliest.
Pending
83/III/1 Tripping of 220 kV
Kayamkulam –Punnapura-2
24-02-2019 at
03:05hrs
Line tripped on B-phase to earth fault. Auto-reclose
was successful at Punnapura. A/r was not attempted at
Kayamkulam and there was pole discrepancy operation
resulting in tripping of R and Y pole of CB.
It was noted that no representative of NTPC attended
the meeting.
NTPC (Kayamkulam) to furnish detailed report
regarding failure of Auto-reclosure at Kayamkulam
end for Kayamkulam –Punnapura line-2.
NTPC (KYKLM) Review meeting on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit status
regrading the recommendation at athe earliest.
NTPC mail dated 13.05.2019:
Trip report for Tripping of 220 kV Kayamkulam –Punnapura-2 submitted , but for
submitting detailed report for Auto-reclosure at Kayamkulam end not operating for
Kayamkulam –Punnapura line-2 , half day shutdown of Kayamkulam –Punnapura
line is required to check reason for failure . May please approve half day outage of
Kayamkulam –Punnapura line and intimate us atleast one day in advance.
Pending
83/III/2 Tripping of 220 kV
Kayamkulam –Punnapura-2
05-03-2019 at
00:30hrs
220kV Kayamkulam-Punnapura -2 tripped on Zone-1
distance protection due to R-N fault. Auto reclose
operated and successful at Punnapara end but didnot
operate at Kayamkulam end.
It was noted that no representative of NTPC attended
the meeting.
NTPC (Kayamkulam) to furnish detailed report
regarding failure of Auto-reclosure at Kayamkulam
end for Kayamkulam –Punnapura line-2.
NTPC (KYKLM) Review meeting on 27.06.2019:
No representative from the utility attended meeting and it is requested to submit status
regrading the recommendation at athe earliest.
NTPC mail dated 13.05.2019:
Trip report for Tripping of 220 kV Kayamkulam –Punnapura-2 submitted , but for
submitting detailed report for Auto-reclosure at Kayamkulam end not operating for
Kayamkulam –Punnapura line-2 , half day shutdown of Kayamkulam –Punnapura
line is required to check reason for failure . May please approve half day outage of
Kayamkulam –Punnapura line and intimate us atleast one day in advance.
Pending
Annexure-IV
Page 46 of 48
84/I/5 Complete outage of 400kV
NLC1
Expansion(NLC1EXP)
05-06-2019at 18:51 hr.Triggering incident was failure of Y-phase CT of GT-1 (Generator Transformer) at 400kV NLC1EXP. Bus-1 Bus bar protection operated resulting in the tripping of NLC1EXP U#1 and 400kV NLC1EXP- Nagapattinam line 1. NLCIL to check the healthiness of R & B ph CT of
Unit-1 at NLC TS1(Exp) and if found unhealthy
replace the same alongwith replacement of Y-ph CT.
CT replacement plan and timeframe shall be informed
to SRPC.
2.NLCIL in coordination with PGCIL(SR-II) to
resolve the time syncronisation issues in 230kV NLC
TS1(Exp) – Nagapattinam line.
3. NLCIL was also requested to investigate the reason
of unwarranted DT sent to NLC TS1 (Exp) end from
NLC TS2 end and resolve the same.
NLCIL NLCIL mail dated 09.07.2019:
AT TS2 Side Siemens 7SA52 & Micromho relay are used for distance protection.
During the incident Micromho has sensed the CT blast as a Zone-1 fault and tripped
the feeder. Adt signal was send to TS1 Exp end. The relay will be tested during the
next shut down.
Pending
84/II/7 Tripping of 400 kV
Dichipally–Ramagundam
line
20-04-2019 at
18:09 hr.
Y phase to Earth fault in the line. Line did not auto-
reclose at Ramagundam end
1. It was noted that no representative of NTPC
(Ramagundam) attended the meeting.
2. NTPC (Ramagundam) to submit a detailed report
regarding non-operation of A/R at Ramagundam end
and Remedial measures taken for the same
NTPC (RMGDM) Yet to be informed Pending
84/II/20 Tripping of 400kV Neyveli
TS2- Neyveli TS-I (EXP)
and 400/230 kV ICT-1
atNeyvli
07-05-2019 at 20:56 hr.400kV/230kV ICT-1 got tripped on Differential
protection due to failure of R phase bushing on the HV
side. For 400kV Neyveli TS2- Neyveli TS-I (EXP), R
pole breaker at TS1Expgot tripped. TS2 End breaker
tripped on trip command received from TS1 EXP
1. NLCIL to measure the earth resistance of Neyveli
TS-2 SS and submit the same to PCSC forum. NLCIL
to check the healthiness of LAs of ICTs and confirm
proper earthing.
2.It is also recommended to furnish a report on
adequacy of ground wire shielding of switchyard.
3. NLCIL to ensure Time synchronization of relays at
Neyveli TS-2 SS.
NLCIL NLCIL mail dated 09.07.2019:
1) The earth pit resistance of the ICT1 LA was measured as follows.
400 kV side was measured on29-03-19
Rphase - 0.61 ῼ , Y phase - 0.76ῼ , B phase - 0.58 ῼ
230 kV side was measured on 29-03-2019
Rphase - 0.47 ῼ , Y phase - 0.86ῼ , B phase - 0.68ῼ
The resistive leakage current for the LA's was also measured and the readings are as
follows.
400kV side was measured on 29-03-2019 and the values are as follows .
R phase - 73 μA , Y phase 90 μA , B phase - 92 μA .
230kV side was measured on 22-03-2019 and the values are as follows
R phase - 238 μA , Y phase - 330 μA , B phase 401 μA.
After the incident on 07-05-19 the resistive leaksge current was again measured on
13-05-2019 and the values are as follows.
400kV Side
R phase - 91 μA , Y phase - 116 μA , B phase - 105 μA
230 kV side
R phase - 297 μA , Y phase - 318 μA , B phase - 385 μA
2) Time synchronization of one series of relays completed. The time synchronization
of balance relays will be completed by August 2019.
Pending
84/III/12 Tripping of 400 kV Simhadri-
Kalpakka line-3
12-05-2019 at
18:33 hr.
R-phase to earth fault. Line did not attempt auto-
reclose
1. It was noted that no representative of NTPC
(Simhadri) attended the meeting.
2.NTPC (Simhadri) to submit a detailed report
regarding non-operation of A/R at Simhadri end and
Remedial measures taken for the same.
NTPC(Simhadri) Yet to be informed Pending
85/II/19 Tripping of 400kV JSW-
Guttur line
02-06-2019 at
18:17 hrs
Line tripped due to OV St-1 protection operation at
JSW end and DT was sent to Guttur end. At Guttur
end B ph voltage was observed to be lesser comparing
to R ph and Y ph(Vr-249kV, Vy-255kV and Vb-
230kV).
JSWEL is recommended to monitor the B-ph CVT of
400kV JSWEL-Guttur line (due to lower B-ph voltage
compared to other two phases). The same shall be
replaced if the issue persists.
JSWEL Yet to be informed Pending
85/II/21 Tripping of 400kV JSW -
Guttur line and 400 kV
Kaiga - Guttur line-2
05-06-2019 at
18:27 hrs
Y-phase to earth fault occurred in 400kV Kaiga-Guttur
line-2. A/r was successful at Guttur end. At Kaiga end
A/r was not attempted and breakers got tripped due to
operation of Pole discrepancy (1.65 Sec). 400kV JSW-
Guttur line tripped on operation of over-voltage at
Guttur and direct trip was received at JSW. From DR
of Guttur, it is observed that there was swell in R & Y
phase voltage for few cycles
1. NPCIL (KGS) is recommended to identify the issue
related to unsuccessful A/R attempt of 400kV Kaiga –
Guttur line and non-opening of R-pole CB. It is
recommended to check the healthiness of all breakers
including breaker timing.
2. Time synchronization of DR and EL at Kaiga end
shall be ensured.
NPCIL (KGS) Yet to be informed Pending
Annexure-IV
Page 47 of 48
85/III/14 Tripping of 400kV Kaiga-
Guttur line-2
16-06-2019 at
19:20 hrs
R-phase to earth fault. Auto-reclose attempt at Guttur
end was not successful as fault was persistent in
nature. Attempt for A/r could not be established from
Kaiga end EL
1. NPCIL (KGS) is recommended to identify the issue
related to unsuccessful A/R attempt of 400kV Kaiga –
Guttur line and non-opening of R-pole CB. It is
recommended to check the healthiness of all breakers
including breaker timing.
2. Time synchronization of DR and EL at Kaiga end
shall be ensured.
NPCIL (KGS) Yet to be informed Pending
85/IV/7 Tripping of 400kV
Ramadugu-Singareni line
11-06-2019 at
08:24 hrs
Line tripped due to Direct Trip receive at Ramadugu
end
Singareni STPP is recommended to submit a detailed
report regarding sending of DT from singareni end that
resulted in tripping of 400kV Ramadugu-Singareni
line.
Singareni TPP Yet to be informed Pending
Annexure-IV
Page 48 of 48
Sl.No. Element Name Outage date/time Revival date/time Reason for outage Sender/ Receiver Remedial Measures/ Actions taken Remarks
1 400KV-BPS-TUMKUR-2 17-03-2019/16:17:00 R-Y FAULT KPTCL To-be-discussed
2 400KV/220KV RAMAGUNDAM-ICT-2 05-04-2019/19:56:00 05-04-2019/23:26:00BUS BAR PROTECTION
OPERATEDNTPC To-be-discussed
3 220kV Dindi-Srisailam line-2 17-05-2019/11:44:00 17-05-2019/16:33:00 TRIPPED ON R-N FAULT
TSGENCO/ TSTRANSCO
[Pending with TSGENCO]
"TSTRANSCO:
It is 220kV Dindi-Srisailam-2 feeder.
A/R successful at Dindi end."
4 400KV-BTPS-HIRIYUR-2 02-06-2019/18:16:00 TRIPPED ON Y-N FAULT
KPCL/ KPTCL
[Pending with KPTCL]
"KPCL: Line tripped on Zone-2, ""C"" phase
to earth.
Remedial Measures: Line Charged on
03.06.2019 at 09:47Hrs from BTPS end
"
5 400KV-TALGUPPA-HASSAN-1 05-06-2019/23:59:00 06-06-2019/00:32:00R Phase distance protection
operatedKPTCL/ PGCIL (SR-II) To-be-discussed
6 132KV-KONAJE-MANJESWAR-1 06-06-2019/05:45:00 EARTH FAULT RELAY OPERATED KPTCL/ KSEBLKSEBL:
Feeder not trippped at Manjeswar end
7 400KV-KUDGI_PG-NARENDRA-1 07-06-2019/22:47:00 07-06-2019/23:00:00 Y-N FAULT PGCIL(SR-II) To-be-discussed
8 400KV-GUTTUR-JINDAL-1 11-06-2019/17:24:00 11-06-2019/19:00:00BUS BAR PROTECTION
OPERATEDKPTCL/ JSWEL To-be-discussed
9 400KV/220KV GUTTUR-ICT-2 11-06-2019/17:24:00 11-06-2019/19:04:00BUS BAR PROTECTION
OPERATEDKPTCL
On 11.06.19 at 17:23 hrs 400KV Kaiga-
Guttur-1(Line-1) tripped at Kaiga end on
receipt of DT from Guttur end. As per
KPTCL information, during ground fault
testing in bus bar panel at Guttur end, trip
command was extended to bus bar
protection and all connected elements
were tripped. Direct trip was extended to
Kaiga end CB. No event is recorded at
Kaiga end. Kaiga- Guttur-1 (Line-1) was
taken into service on 11.06.2019 at
20:13hrs vide CPCC-06/234 and SRLDC -
06/627.
Issue is belonging to KPTCL
10 400KV/220KV GUTTUR-ICT-1 11-06-2019/17:24:00 11-06-2019/18:10:00BUS BAR PROTECTION
OPERATEDKPTCL To-be-discussed
11 400KV-GUTTUR-HIRIYUR-2 11-06-2019/17:24:00 11-06-2019/18:42:00BUS BAR PROTECTION
OPERATEDKPTCL/ PGCIL (SR-II) To-be-discussed
Pending Remedial Measures/ Actions taken for the Critical Tripping Incidents (as on 01.08.2019)
Annexure-V
Page 1 of 4
12 400KV-KAIGA-GUTTUR-1 11-06-2019/17:24:00 11-06-2019/20:13:00BUS BAR PROTECTION
OPERATEDNPCIL (KGS)/ KPTCL To-be-discussed
13 400KV-DONI-GUTTUR-1 11-06-2019/17:24:00 11-06-2019/18:01:00BUS BAR PROTECTION
OPERATEDKPTCL To-be-discussed
14 400KV-GUTTUR-HIRIYUR-1 11-06-2019/17:24:00 11-06-2019/18:35:00BUS BAR PROTECTION
OPERATEDKPTCL/ PGCIL (Sr-II) To-be-discussed
15 400KV-NELAMANGALA-TALGUPPA-1 12-06-2019/18:24:00 12-06-2019/20:44:00 EMERGENCY WORK KPTCL To-be-discussed
16 400KV-GUTTUR-HIRIYUR-1 12-06-2019/17:00:00 12-06-2019/17:19:00 DT received from Guttur KPTCL/ PGCIL (SR-II) To-be-discussed
17 400KV-TALGUPPA-HASSAN-1 12-06-2019/14:38:00 12-06-2019/21:31:00 INSULATOR FLASH OVER KPTCL/ PGCIL (SR-II) To-be-discussed
18 400KV/220KV HOODY-ICT-2 16-06-2019/19:20:00 16-06-2019/20:51:00OVER FLUX PROTECTION RELAY
OPERATEDKPTCL To-be-discussed
19 400KV-KAIGA-GUTTUR-2 18-06-2019/02:53:00 R-N FAULT NPCIL(KGS)/ KPTCL To-be-discussed
20 220KV-AMBEWADI-XELDEM 23-06-2019/16:09:00 TRIPPED ON C-N FAULT KPTCL To-be-discussed
21 220KV-CHILLAKALLU-NARKETPALLI-1 25-06-2019/17:17:00 25-06-2019/17:34:00 TRIPPED ON R-N FAULT
APTRANSCO/ TSTRANSCO
[pending with TSTRANSCO/
TSGENCO]
APTRANSCO: Feeder tripped on R-Phase to
ground, Zone-2 fault. Line charged after
taking permission from SLDC. Fault
distance of 81.68KM falls in TSTRANSCO
juridiction.
TSTRANSCO: Line Patrolling done and no
fault found. Substation belongs to
TSGENCO
What protection operated at
Narketapalli? Status of A/R in
the line?
22 400KV-BHADRAVATHI-RAMAGUNDAM-1 26-06-2019/16:29:00 26-06-2019/18:35:00 RELAY MALOPERATION NTPC (RMGD)/ WR To-be-discussed
23 400KV-SALEM-DHARMAPURI-1 29-06-2019/15:43:00 29-06-2019/17:03:00 phase to phase fault PGCIL (SR-II) To-be-discussed
24 220KV-Talapalli-NAGARJUNASAGAR TS 30-06-2019/11:03:00 30-06-2019/11:36:00 TRIPPED ON B-N FAULTAPTRANSCO/ TSGENCO [
pending with TSGENCO]
APTRANSCO: Feeder not tripped at
Tallapalli end.
APTRANSCO: The feeder "Nagarjuna sagar-
AP" may be changed as "Tallapalli".
2.Feeder not tripped at Tallapalli end.No
carrier received from Nagarjuna Sagar -TS
end due to PLCC problem at TSGENCO
end.
25 132KV-KONAJE-MANJESWAR-1 07-07-2019/12:49:00 DISTANCE PROTECTION KPTCL/ KSEBLKSEBL: Supply failed at 110kV Manjeswar
substaion
Annexure-V
Page 2 of 4
26220KV-KOTHAGUDEM_TPS-
LOWER_SILERU-108-07-2019/10:45:00 08-07-2019/11:18:00 TRIPPED ON B-N FAULT TSGENCO/ APGENCO
TSGENCO: On 08.07.2019 at 10:45 hrs
220KV KTPS-Lower Sileru Feeder was
tripped on Distance Protection at a
distance of 49.31KMs from KTPS end. After
getting clearance from SLDC, line charged
at 11:18 Hrs. Line stood ok.
27 400KV/110KV SHOLINGANALLUR-ICT-1 09-07-2019/14:47:00 09-07-2019/20:25:00TRIPPED ON BUCCHOLZ RELAY
OPERATIONTANTRANSCO To-be-discussed
28400KV-CUDDAPAH-NAGARJUNASAGAR_PG-
112-07-2019/14:31:00 12-07-2019/15:10:00
TRIPPED DUE TO B-N LINE
FAULTPGCIL (SR-I) To-be-discussed
29 132KV-KONAJE-MANJESWAR-1 14-07-2019/10:25:00 14-07-2019/10:49:00 TRIPPED ON B-N FAULT KPTCL/ KSEBL To-be-discussed
30220KV-KOTHAGUDEM_TPS-
LOWER_SILERU-114-07-2019/13:39:00 14-07-2019/13:55:00 TRIPPED ON R-N FAULT TSGENCO/ APGENCO To-be-discussed
31 400KV-NEYVELI_TS_II-NEYVELI_TS1_EXP-1 17-07-2019/21:39:00 17-07-2019/23:26:00 POLE DISCREPANCY NLCIL To-be-discussed
32400KV-SRISAILAM_LEFT_BANK-
SATTENPALLI20-07-2019/07:44:00 20-07-2019/17:53:00 TRIPPED ON B-N FAULT TSGENCO/ APTRANSCO To-be-discussed
33 400KV-KAIGA-GUTTUR-2 22-07-2019/17:47:00TRIPPED DUE TO B-N LINE
FAULTNPCIL (KGS)/ KPTCL To-be-discussed
34220KV-KOTHAGUDEM_TPS_V-LOWER_SILE
..23-07-2019/11:48:00 23-07-2019/16:20:00
TRIPPED DUE TO B-N LINE
FAULTAPGENCO/ TSGENCO To-be-discussed
35 400KV-YELHANKA-NELAMANGALA-1 23-07-2019/12:09:00operation of gas chamber
protectionKPTCL/ PGCIL (Sr-2) To-be-discussed
36 400KV-HOODY-YELHANKA-1 23-07-2019/12:09:00operation of gas chamber
protectionKPTCL/ PGCIL (Sr-2) To-be-discussed
37 220KV-KADAKOLA-KANIYAMPETTA 23-07-2019/10:49:00 23-07-2019/12:26:00 RELAY MALOPERATION KSEBL/ KPTCL To-be-discussed
38 400KV-HINDUJA-KV_KOTA-1 23-07-2019/09:04:00 TRIPPED ON B-N FAULT HNPCL/ APTRANSCO To-be-discussed
39 400KV-DICHPALLY-NIZAMABAD-2 25-07-2019/14:19:00 25-07-2019/14:58:00 RELAY MALOPERATION TSTRANSCO/ PGCIL (SR-2) To-be-discussed
40400KV-SRISAILAM_LEFT_BANK-
SATTENPAL..26-07-2019/11:39:00 26-07-2019/13:19:00 MAL-OPERATION TSGENCO/ APTRANSCO To-be-discussed
41400KV/110KV SUNGAVARACHATRAM-ICT-
326-07-2019/14:07:00 26-07-2019/15:15:00 EXTERNAL PROTECTION TRIP TANTRANSCO To-be-discussed
42400KV/110KV SUNGAVARACHATRAM-ICT-
426-07-2019/14:10:00 26-07-2019/16:30:00 EXTERNAL PROTECTION TRIP TANTRANSCO To-be-discussed
43 220KV-THENI-MOOZIYAR-1 27-07-2019/12:24:00 27-07-2019/12:47:00TRIPPED ON SINGLE PHASE TO
GND FAULTKSEBL/ TANTRANSCO To-be-discussed
44 400KV/220KV TALGUPPA-ICT-2 27-07-2019/16:27:00 27-07-2019/17:16:00 MALFUNCTIONING OF OCR KPTCL To-be-discussed
Annexure-V
Page 3 of 4
45 132KV-KONAJE-MANJESWAR-1 28-07-2019/10:29:00 28-07-2019/14:26:00 DISTANCE PROTECTION KSEBL/ KPTCL To-be-discussed
46 230KV-NEYVELI_TS_II-KARAIKAL-1 29-07-2019/18:36:00 29-07-2019/20:18:00 TRIPPED ON R-N FAULT NLCIL/ PGCIL (SR-2) To-be-discussed
47 400KV-TIPPAPUR-JANAGAON-2 31-07-2019/19:00:00 31-07-2019/20:36:00 DT RECEIVED TSTRANSCO To-be-discussed
48 230KV-NEYVELI_TS_II-KARAIKAL-1 31-07-2019/07:08:00 31-07-2019/20:09:00 CVT Problem NLCIL/ PGCIL (SR-2) To-be-discussed
Annexure-V
Page 4 of 4