Upload
trinhdan
View
214
Download
0
Embed Size (px)
Citation preview
Document of
The World Bank
Report No: ICR2282
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IDA-43410, IDA-44860 and TF-92655)
ON TWO CREDITS
IN THE AMOUNT OF SDR 26.3 MILLION
(US$ 40 MILLION EQUIVALENT)
AND
IN THE AMOUNT OF SDR 30.7 MILLION
(US$ 50 MILLION EQUIVALENT)
AND A SUPPLEMENTAL FINANCING GRANT
(US$ 10 MILLION)
TO THE
THE REPUBLIC OF MADAGASCAR
FOR A
POVERTY REDUCTION SUPPORT CREDIT SERIES
June 22, 2012
Poverty Reduction and Economic Management 1
Africa Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
CURRENCY EQUIVALENTS
(Exchange Rate Effective as of May 31, 2012)
Currency Unit = Malagasy Ariary (MGA)
1.00 MGA = US$ 0.000477
US$ 1.00 = 2,096 MGA
FISCAL YEAR
January1-December 31
ABBREVIATIONS AND ACRONYMS
ACT Artemisinin-based Combined Therapies
ADB African Development Bank
ARMP Regulatory Agency for Public Procurement
CBM Central Bank of Madagascar
CAS Country Assistance Strategy
CDE Expenditures Control (Contrôle des dépenses engages)
CHD Hospital at district level
CSB Basic Health Center
DGWS Directorate General of Water and Sanitation
DHS Demographic Household Survey
EC European Commission
EFA National Education for All
EITI Extractive Industry Transparency Initiative
EU European Union
FAF Fer Acid Folic
FDI Foreign Direct Investment
FDL Local Development Fund
GDP Gross Domestic Product
GNI Gross National Product
GoM Government of Madagascar
ICRR Implementation Completion and Results Report
INSTAT National Statistics Institute
MAP Madagascar Action Plan
MDGs Millennium Development Goals
MDRI Multilateral Debt Relief Initiative
MEFB Ministry of Finance and Budget
ONN National Office for Nutrition
PAP Priority Action Plan
PDSS Health Sector Development Program
PRSP Poverty Reduction Support Credit
SIGFP Integrated Financial Management System
CNN National Nutrition Council
DGWS Directorate General of Water and Sanitation
INSTAT National Institute for Statistics
OMNIS National Office of Mines and Strategic Industries
PGDI Governance and Institutional Development Project
PARP EU's Budget Support Program
PFM Public Finance Management
PRSC Poverty Reduction Support Credit
CPIA Country Policy and Institutional Assessment
PEFA Public Expenditure and Financial Accountability
M&E Monitoring and Evaluation
Vice President: Makhtar Diop
Country Director: Haleh Z. Bridi
Sector Manager: John Panzer
Task Team Leader: Maria Teresa Benito-Spinetto
ICR Team Leader: Maria Teresa Benito-Spinetto
MADAGASCAR
IMPLEMENTATION COMPLETION AND RESULTS REPORT
POVERTY REDUCTION SUPPORT CREDITS 4-5
CONTENTS
Data Sheet
A. Basic Information
B. Key Dates
C. Ratings Summary
D. Sector and Theme Codes
E. Bank Staff
F. Results Framework Analysis
G. Ratings of Program Performance in ISRs
H. Restructuring
1. Program Context, Development Objectives and Design ............................................ 1
2. Key Factors Affecting Implementation and Outcomes .............................................. 6
3. Assessment of Outcomes .......................................................................................... 14
4. Assessment of Risk to Development Outcome ......................................................... 19
5. Assessment of Bank and Borrower Performance ..................................................... 20
6. Lessons Learned........................................................................................................ 20
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners........... 22
Annex 1 Bank Lending and Implementation Support/Supervision Processes.............. 23
Annex 2. Beneficiary Survey Results ........................................................................... 25
Annex 3. Stakeholder Workshop Report and Results ................................................... 26
Annex 4. Summary of Borrower's ICR and/or Comments on Draft ICR ..................... 27
Annex 5. Comments of Cofinanciers and Other Partners/Stakeholders ....................... 28
Annex 6. List of Supporting Documents ...................................................................... 29
Annex 7. Program Development Objectives Results Matrix……………………….... 30
Annex 8. Summary PEFA Indicators………………………………………………… 36
MAP
A. Basic Information
Program 1
Country Madagascar Program Name
Fourth Poverty
Reduction Support
Credit
Program ID P099420 L/C/TF Number(s) IDA-43410,TF-56900
ICR Date 05/25/2012 ICR Type Core ICR
Lending Instrument DPL Borrower REPUBLIC OF
MADAGASCAR
Original Total
Commitment XDR 26.30M Disbursed Amount XDR 26.30M
Implementing Agencies
Ministry of Economy Finance and Budget
Cofinanciers and Other External Partners
Program 2
Country Madagascar Program Name Fifth Poverty Reduction
Support Credit
Program ID1 P105135 L/C/TF Number(s) IDA-44860
ICR Date 05/25/2012 ICR Type Core ICR
Lending Instrument DPL Borrower REPUBLIC OF
MADAGASCAR
Original Total
Commitment XDR 30.70M Disbursed Amount XDR 30.70M
Implementing Agencies
Ministry of Finance Economy and Budget
Cofinanciers and Other External Partners
1 A Supplemental Financing Grant was approved by the Board in August 13, 2008 in the
amount of US$10 million.
B. Key Dates
Fourth Poverty Reduction Support Credit - P099420
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 03/28/2007 Effectiveness: 08/30/2007 08/30/2007
Appraisal: 05/08/2007 Restructuring(s):
Approval: 07/31/2007 Mid-term Review:
Closing: 07/31/2008 07/31/2008
Fifth Poverty Reduction Support Credit - P105135
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 02/06/2008 Effectiveness: 07/30/2008
Appraisal: 05/09/2008 Restructuring(s):
Approval: 06/26/2008 Mid-term Review:
Closing: 07/31/2009 07/31/2009
C. Ratings Summary
C.1 Performance Rating by ICR
Overall Program Rating
Outcomes Unsatisfactory
Risk to Development Outcome High
Bank Performance Moderately Unsatisfactory
Borrower Performance Unsatisfactory
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Overall Program Rating
Bank Ratings Borrower Ratings
Quality at Entry Moderately
Satisfactory Government: Not applicable
Quality of Supervision: Moderately
Unsatisfactory
Implementing
Agency/Agencies: Not applicable
Overall Bank
Performance
Moderately
Unsatisfactory
Overall Borrower
Performance Unsatisfactory
C.3 Quality at Entry and Implementation Performance Indicators
Fourth Poverty Reduction Support Credit - P099420
Implementation
Performance Indicators
QAG Assessments
(if any) Rating:
Potential Problem
Program at any time
(Yes/No):
No Quality at Entry
(QEA) None
Problem Program at any
time (Yes/No): No
Quality of
Supervision (QSA) None
DO rating before
Closing/Inactive status Satisfactory
Fifth Poverty Reduction Support Credit - P105135
Implementation
Performance Indicators
QAG Assessments
(if any) Rating:
Potential Problem
Program at any time
(Yes/No):
No Quality at Entry
(QEA) None
Problem Program at any
time (Yes/No): No
Quality of
Supervision (QSA) None
DO rating before
Closing/Inactive status Satisfactory
D. Sector and Theme Codes
Fourth Poverty Reduction Support Credit - P099420
Original Actual
Sector Code (as % of total Bank financing)
Central government administration 50 Ibid.
General education sector 10 Ibid.
General water, sanitation and flood protection sector 10 Ibid.
Health 20 Ibid.
Sub-national government administration 10 Ibid.
Theme Code (as % of total Bank financing)
Education for all 17 Ibid.
Health system performance 17 Ibid.
Other accountability/anti-corruption 16 Ibid.
Public expenditure, financial management and
procurement 33
Ibid.
Rural services and infrastructure 17 Ibid.
Fifth Poverty Reduction Support Credit - P105135
Original Actual
Sector Code (as % of total Bank financing)
Central government administration 56 Ibid.
General education sector 11 Ibid.
General water, sanitation and flood protection sector 11 Ibid.
Health 22 Ibid.
Theme Code (as % of total Bank financing)
Education for all 17 Ibid.
Health system performance 17 Ibid.
Other accountability/anti-corruption 17 Ibid.
Public expenditure, financial management and
procurement 33
Ibid.
Rural services and infrastructure 16 Ibid.
E. Bank Staff
Fourth Poverty Reduction Support Credit - P099420
Positions At ICR At Approval
Vice President: Makhtar Diop Obiageli Katryn Ezekwesili
Country Director: Haleh Z. Bridi Ritva S. Reinikka
Sector Manager: John Panzer Laura Frigenti
Task Team Leader: Alain W. D'Hoore Stefano Paternostro
ICR Team Leader: Maria Teresa Benito-Spinetto
ICR Primary Author: Maria Teresa Benito-Spinetto
Fifth Poverty Reduction Suport Credit - P105135
Positions At ICR At Approval
Vice President: Makhtar Diop Obiageli Katryn Ezekwesili
Country Director: Haleh Z. Bridi Dirk Reinermann (Acting)
Sector Manager: John Panzer John Panzer and Lynne D.
Sherburne-Benz
Task Team Leader: Alain W. D'Hoore Jacques Morisset and Stefano
Paternostro
ICR Team Leader: Maria Teresa Benito-Spinetto
ICR Primary Author: Maria Teresa Benito-Spinetto
F. Results Framework Analysis
Program Development Objectives (from Program Document)
In line with the Country Assistance Strategy for Madagascar, a series of single tranche
Poverty Reduction Support Credits (PRSCs), provided in the form of budget support, was
envisaged to support implementation of key components of the second-generation
Madagascar PRSP called the Madagascar Action Plan (MAP). The focus of the series
was centered on: (i) governance and budget management reform and (ii) improved
systems for service delivery in education, health, nutrition, water and sanitation.
Revised Program Development Objectives (as approved by original approving
authority)
Program Development Objectives were not revised.
(a) PDO Indicator(s)
Indicator Baseline
Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : Number of PEFA budget preparation and execution indicators (indicators 1
through 17) rated "B" and above.
Value
(quantitative or
Qualitative)
9 13 NA
Date achieved 03/31/2006 12/31/2010 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target not met. The 2011 PEFA that would have allowed assessment for this
indicator did not take place. (The last available PEFA dates from 2009). A
2011 review of PFM issues suggests limited progress on the Public Finance
Management reform agenda since March 2009.
Indicator 2 :
Number of public institutions (ministries at central government level)
executing their annual budgets through the integrated financial management
system (SIGFP).
Value
(quantitative or
Qualitative)
5 All All
Date achieved 03/31/2006 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target met.
Indicator Baseline
Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 3 : Number of PEFA budget reporting (indicators 22 through 25) rated "B" and
above.
Value
(quantitative or
Qualitative)
0 3 NA
Date achieved 03/31/2006 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target not met. See comment for Indicator 1.
Indicator 4 : Number of PEFA indicators measuring the internal/external control
mechanisms (indicators 20, 21, 26 through 28) rated “B” and above.
Value
(quantitative or
Qualitative)
0 4 NA
Date achieved 03/31/2006 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target not met. See comment for Indicator 1.
Indicator 5 :
Percentage of reviewed procurement processes in selected public institutions
that conform to the new procurement regulations (Ministries of Education,
Health, Transport, and Agriculture used as reference points).
Value
(quantitative or
Qualitative)
5% 80% 50%
Date achieved 03/31/2006 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target not met, but some improvement occurred.
Indicator 6 : National Anti-Corruption Perception Index of (i) households and (ii) civil
service employees.
Value
(quantitative or
Qualitative)
(i) 2.2
(ii) 3.0 10% increase 2.6
Date achieved 03/31/2006 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target not met. (Available data for 2010 does not distinguish by target).
Indicator 7 : Share of annual central budget transferred to local governments.
Value
(quantitative or
Qualitative)
1.4 2.7 1.9
Date achieved 03/31/2006 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target not met.
Indicator Baseline
Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 8 : Primary net enrollment rate.
Value
(quantitative or
Qualitative)
80%
90% 87.7%
Date achieved 03/31/2006 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target not met, despite some improvement. (The baseline and target indicators
were revised in PRSC-5 for the series as a whole based on the availability of
better data.)
Indicator 9 : Primary school completion.
Value
(quantitative or
Qualitative)
50% 74% 63%
Date achieved 03/31/2006 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target not met. (The baseline and target indicators were revised in PRSC-5 for
the series based on the availability of better data. )
Indicator 10 : Repetition rate.
Value
(quantitative or
Qualitative)
19% 14% 19%
Date achieved 03/31/2006 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target not met. (The baseline and target indicators were revised in PRSC-5 for
the series based on the availability of better data.)
Indicator 11 : Skilled birth attendance in (i) CSB, (ii) CHD1 and (iii) in all public CHD2.
Value
(quantitative or
Qualitative)
(i) 18.8
(ii) 1.4
(iii) 2.1
(i) 20.8
(ii) 3.4
(iii) 4.0
(i) 24.9
(ii) 3.4
(iii) 3.4
Date achieved 03/31/2006 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target met. Although skill birth attendance at all public CHD2 was not met,
overall birth attendance surpassed the target.
Indicator 12 : Consultation rate for treatment in CSB (number of curative outpatient
visits/total population).
Value
(quantitative or
Qualitative)
44.4 Not specified 31.2
Date achieved 03/31/2006 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target not met. (The baseline was revised from 32.4 to 44.4 due to the
availability of better data)
Indicator Baseline
Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 13 : Availability of medicines in CSB for each of the following: (i) Chloroquine,
(ii) FAF, (iii) Cotrimoxazole, (iv) Paracetamol and Vitamin A.
Value
(quantitative or
Qualitative)
(i) 96.6%
(ii) 89.3%
(iii) 95.7%
(iv) 92.2%
(v) 93.4%
(i) >95%
(ii) >95%
(iii) >95%
(iv) >95%
(v) >95%
(i) ACT:99.0%
(ii) 88.3%
(iii) 96.7%
(iv) 96.6%
(v) 95.3%
Date achieved 03/31/2006 12/31/2010 2011
Comments
(incl. % of
achievement)
Target met for all sub-indicators except FAF (Fer Acid Folic). Note that
Chloroquine no longer exists due to policy change in malaria treatment.
Equivalent treatment was replaced by ACT (Artemisinin-based Combined
Therapies).
Indicator 14 : Child underweight rate.
Value
(quantitative or
Qualitative)
42% Decreased by 10%
of baseline 30%
Date achieved 06/30/2004 12/31/2010 12/31/2011
Comments
(incl. % of
achievement)
Target met. Baseline data is based on the 2003/04 Demographic Household
Survey (DHS) and 2011 is based on the Anthropometric and Child
Development Survey.
Indicator 15 : Percentage of the rural population with access to safe drinking water.
Value
(quantitative or
Qualitative)
31% 37% 38.5%
Date achieved 03/31/2006 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target met. Data for 2010 based on the 2010 DHS.
Indicator 16 : Percentage of the rural population with access to sanitation.
Value
(quantitative or
Qualitative)
46% 51% 41.5%
Date achieved 03/31/2006 12/31/2010 12/31/2010
Comments
(incl. % of
achievement)
Target not met. Data for 2010, based in the 2010 HS, refers to access to
latrines/toilets. (The baseline indicator was revised slightly in PRSC-5 to 46%
due to better data availability).
G. Ratings of Program Performance in ISRs
Fourth Poverty Reduction Support Credit - P099420
No. Date ISR
Archived DO IP
Actual
Disbursements
(USD millions)
1 06/28/2008 Satisfactory Satisfactory 40.87
Fifth Poverty Reduction Support Credit - P105135
No. Date ISR
Archived DO IP
Actual
Disbursements
(USD millions)
1 08/25/2008 Satisfactory Satisfactory 48.55
H. Restructuring (if any) Not applicable.
1
Context of the Preparation of the Implementation Completion and Results Report
The PRSCs were originally designed as a three single-tranche credit series. The first two
operations, PRSC-4 and PRSC-5, were approved by the World Bank Board, respectively
on July 31, 2007 and June 26, 2008. However, due to the emergence of a political crisis
in Madagascar in early 2009, and OP 7.30 coming into effect2, the preparation of PRSC-6,
planned for mid-2009 was suspended, and the series was discontinued. Section 2.2
expands on the political situation in 2009 and following years.
The ICR for this PRSC series was delayed on account of expectations that PRSC-6 would
take place once the political situation was resolved. However, the political crisis
continued to be in effect for longer than expected and finally PRSC-6 was discontinued
and an ICR prepared.
1. Program Context, Development Objectives, and Design
1.1 Context at Appraisal
a. Macroeconomic situation at appraisal
Madagascar is one of the poorest countries in Sub-Sahara Africa, with a GNI per capita
of US$340 in 2007. Following the 2002 political crisis—a crisis that had lasted almost a
year and seen a 12.5 percent drop in real GDP, GDP had rebounded to its pre-crisis level
by 2004, and overall growth was set on a pace of close to 5 percent a year over 2005-06
with an estimated growth of 6.5 percent for 2007. Inflation continued to decline in 2006
aided by tight monetary policy, low prices, and a decline in world oil prices during the
second half of the year. Fiscal policy was been consolidated with the overall
macroeconomic situation remaining stable.
Growth in 2006 was led by the tertiary sector. Tourist arrivals increased 14 percent and
growth was strong in public sector, transport, and telecommunications. The primary
sector, on the other hand, grew only 2.3 percent due to rain shortfalls and low world
prices for key agricultural exports, such as vanilla. The secondary sector grew at a
moderate 4 percent, paced by solid gains in construction and mining, the latter related to
a large ilmenite mining investment in the Fort Dauphin area. Early estimates at the time
projected a healthy 6.5 percent growth in GDP for 2007 due to the launch of another
large mining investment project of around US$2.5 billion (or 45 percent of GDP) to be
undertaken over three years (2007-2009). This optimistic outlook was in spite of the six
tropical storms/cyclones that hit Madagascar in early 2007 when more than 300,000
people were affected by deteriorating food security, increasing health risks, and
substantial damage to public infrastructure and crops.
2 Refer to OP/BP 7.30 for more information on Bank‟s policy on “Dealing with the facto
governments”.
2
In 2006, inflation slowed down from its previous high levels over 2004-05, owing to
tighter monetary policy, lower rice prices, and a decline in oil prices later in the year.
However, the declining trend started to reverse in the early months of 2007 due to the
floods and increasing import prices, especially rice and petroleum. The exchange rate of
the ariary was broadly stable in 2005, but it began to rise against the U.S. dollar in the
last quarter of 2006 and the first months of 2007, with a nominal appreciation of 10
percent in the beginning of the year, reflecting an improved export performance and
greater foreign direct investment (FDI) linked to the mining project. FDI increased from
1.7 percent of GDP in 2005 to 4 percent in 2006. Stronger exports, greater FDI inflows,
and temporarily declining world petroleum prices contributed to an improvement in the
balance of payments, with the overall current account deficit improving from -
10.9 percent of GDP in 2005 to -8.8 percent in 2006. Foreign reserves were maintained at
three months of imports at year end 2006. The Central Bank of Madagascar (BCM)
guidelines for intervention in the foreign exchange market, aimed at achieving its foreign
assets objectives and dampening sharp swings that would create uncertainty, were
broadly followed.
Fiscal policy had two key objectives: reducing macroeconomic imbalances and avoiding
crowding out the private sector. Total spending was kept in line with domestic revenue
and concessional external financing, allowing domestic financing of the budget to be held
at a minimum. In 2006, the tax revenue to GDP ratio was still a low 10.7 percent.
Persistent problems in revenue collection hindered the Government's ability to implement
its ambitious poverty reduction strategy, with mid-year expenditure cuts implemented in
2006 to maintain overall fiscal discipline. The domestic fiscal balance improved from
-2.2 percent to -2.0 percent of GDP, and the overall fiscal balance (excluding grants)
from -10.1 percent to -10.5 percent of GDP.3 As a result, bank credit to the government
declined in the context of a modest pace of overall credit and monetary expansion. A
tight statutory limit on central bank financing of the budget deficit was strictly observed
and steps were taken to develop the Treasury bill market. Consolidated Government debt
owed to the BCM was converted into marketable securities. The Government was also
implementing a customs reform program and, with support from the IMF and World
Bank, was designing a comprehensive reform of tax and customs administration.
b. Alignment of PRSC program with Government, Bank and donor strategies
This PRSC series was approved shortly after the re-election of President Ravalomanana,
in December 2006, and the launch of the Madagascar Action Plan (MAP), the
government‟s Poverty Reduction Strategy. The series was designed to support
implementation of this strategy, and was consistent with the Bank's Country Assistance
Strategy (CAS) discussed at the Board of Executive Directors meeting on April 3, 2007.
The MAP‟s objective was to promote rapid and sustainable development over the next
five years in line with the Government's national vision document (Madagascar
3 The overall deficit, including grants, increased drastically from -4.3 percent to 37.5
percent of GDP due to a onetime MDRI.
3
Naturally) and the UN Millennium Development Goals (MDGs). To attain this objective,
the MAP presented eight key commitments: (i) responsible governance; (ii) connected
infrastructure; (iii) educational transformation; (iv) rural development and a green
revolution; (v) health, family planning, and the fight against HIV/AIDS; (vi) high-growth
economy; (vii) cherish the environment; and (viii) national solidarity.
The PRSC program for this series focused explicitly on improving governance, budget
management, and service delivery, and it included specific policy actions in these areas.
In parallel, Bank support aimed at directly enhancing Madagascar's growth potential
through its significant portfolio of ongoing IDA investment projects in infrastructure,
environment, mining, rural development, the Integrated Growth Poles project, the
Irrigation and Watershed Management project, and the Regional Telecommunications
project. Overall, the 2007 CAS devoted significant IDA resources to operations designed
to continue investment and policy dialogue on the growth agenda.
In line with the Government‟s request and consistent with the Paris Declaration on
harmonization, Bank assistance to Madagascar was aligned with financial and technical
support from other donors to provide a package of coordinated support around the MAP.
A partnership agreement (“Cadre de Partenariat”) was signed between the Government
and key donors providing part of their assistance through budget support (the European
Commission (EC), France (Agence Française de Développement and the French Co-
operation), the African Development Bank, and the World Bank) to provide a framework
and lay out procedures and modalities for a multi-donor approach to budgetary support.
This Budget Group initiated joint-donor missions already since October 2004 to review
implementation of the PRSP/MAP and supervise their respective budget support
operations.
In addition, the Bank collaborated and coordinated activities with the IMF. The staff of
the two institutions conducted regular joint assessments of the PRSP/MAP
implementation and worked closely together on such areas as: (i) analysis and reforms in
public financial management; (ii) other governance reforms, including customs and tax
reform; (iii) trade; and (iv) financial sector reforms. Joint policy advice was given on
budgetary procedures, including expenditure execution and the functioning of internal
and external controls.
1.2 Original Program Development Objectives (PDO) and Key Indicators (as
approved)
The original PDOs were stated as follows:
In line with the Country Assistance Strategy for Madagascar, a series of single-tranche
Poverty Reduction Support Credits (PRSCs), provided in the form of budget support, is
envisaged to support implementation of key components of the second-generation
Madagascar PRSP called the Madagascar Action Plan (MAP). The focus of the series is
centered on: (i) governance and budget management reform and (ii) improved systems
for service delivery in education, health, nutrition, water, and sanitation.
The original Key Outcome Indicators are shown in Table 1 below.
4
Table 1: Expected Key Outcome Indicators
Area Key Monitoring Indicator
A. PUBLIC FINANCE MANAGEMENT
Budget preparation and execution 1. Number of PEFA budget preparation and
execution indicators (indicators 1 through
17) rated “B” and above increased from 9
to 13.
2. Execution of annual budgets through the
integrated financial management system
(SIGFP) by all public institutions
(ministries at central government level).
Budgetary reporting 3. Number of PEFA budget reporting
indicators (indicators 22 through 25) rated
“B” and above increased from 0 to 3.
Internal and external controls 4. Number of PEFA indicators measuring
internal and external control mechanisms
(indicators 20, 21, 26 through 28) rated “B”
and above increased from 0 to 4.
Public procurement 5. Reviewed procurement processes in
selected public institutions assessed as
conforming to the new procurement
regulations increased to at least 80%
(Ministries of Education, Health,
Transport, and Agriculture are used as
reference points).
B. GOVERNANCE
Reduction of corruption 6. National Anti-Corruption Perception
Index of (i) households and (ii) civil
service employees increased by 10 percent
over its 2005 value.
Decentralization 7. Share of annual central budget
transferred to local governments increased
to 2.7 percent.
BASIC SERVICE DELIVERY
Education 8. Primary school net enrollment rate
increased from baseline.
9. Primary school completion rate
increased from baseline.
10. Reduced repetition rate over baseline.
Health 11. Skilled birth attendance increased to
20.8% in CSB, 3.4% in CHD1and 4.0% in
all the public CHD2.
12. Consultation rate for treatment
increased in CSB (number of curative
outpatient visits/total population).
5
13. Availability of medicines in CSB
increased to more than 95% for each of the
following: Chloroquine, FAF,
Cotrimoxazole, Paracetamol and Vitamin
A.
Nutrition 14. Child underweight rate (MDG
indicator) by reduced 10% from baseline.
Water and sanitation 15. Rural population with access to safe
drinking water increased to 37%.
16. Rural population with access to
sanitation increased to 51%.
1.3 Revised PDO, Key Indicators, and Reasons/Justification
The PDO and key indicators were not revised.
1.4 Original Policy Areas Supported by the Program (as approved)
The PRSC series supported three policy areas:
(i) Public Finance Reform:
Public finance reform was aimed at establishing an efficient and effective
government budget process by: (i) advancing on the public finance reform
started in 2005 and already in process of implementation, along with specific
steps identified in the rolling working plan for 2007-09; (ii) enhancing budget
formulation; (iii) improving budget execution and quality of public
procurement; (iv) strengthening controls on public finance management; (v)
improving debt management; (vi) improving revenue generation and
management; and (vii) improving budget transparency.
(ii) Governance:
Governance reforms included actions to improve decentralization and reduce
corruption. In the area of decentralization, the Government‟s reform program
supported by this PRSC series was expected to lead to a higher share of
resources available to the local governments. In the area of fighting corruption,
the reform program was expected to improve the perception of corruption
among the population and civil servants, and reduce opportunities for
corruption in extractive and natural resource industries.
(iii) Basic Service Delivery:
Basic service delivery was concentrated on education, health, nutrition, and
water and sanitation. Support in these areas was aimed at strengthening the
institutional systems and improving access and quality of services.
6
The reforms supported under the above policy areas were expected to increase fiscal
discipline, streamline and consolidate government budget practices, improve
transparency, and sustain efforts to upgrade the overall institutional setting for service
delivery. These reforms were expected to produce higher growth rates and faster poverty
reduction.
1.5 Revised Policy Areas
Not applicable.
1.6 Other Significant Changes
Supplemental Financing Grant under OP 8.6.4 A supplemental financing grant in the
amount of US$10 million was approved by the Board on August 13, 2008 in response to
the evolving risks of food crisis facing Madagascar. Since the beginning of 2008, when
international rice prices rose sharply, domestic prices had risen only moderately due to
the availability of locally produced rice.5 However, rice needs during the post-harvest
October-to-December period needed to be met through imports. At the time of PRSC-5
preparation, it was difficult to anticipate import needs. After PRSC-5 approval, it was
estimated that import needs for the rest of the year would be large (100 to 150 thousand
tons) and domestic prices could rise by more than 50 percent if international prices
remained at high levels. In addition, Madagascar faced the impacts of cyclones and the
oil price shock. Under this scenario, the Government worked with development partners
in preparing a coordinated response, and the Bank responded with this grant.
2. Key Factors Affecting Implementation and Outcomes
2.1 Program Performance
*The prior actions for the first and second operations in this series were met before the
respective Board approvals. However, many of these actions were reversed or their
implementation discontinued.
PRSC-4
Prior actions from Legal
Agreement/Program Document
Status
Public Finance Reform
The Borrower has satisfactorily
implemented the Priority Action
Plan for FY 2006.
Met in 2006. Assessed satisfactory by the
joint donor review of November 2006 and
March 2007. The PAP was no longer
4 See World Bank Report No.44743-MG (P113224).
5 The welfare of a majority of the population is highly sensitive to the price of rice, which
both is the main agricultural crop (rice production contributes around 10 percent of GDP)
and accounts for a large share of the consumption basket for the population.
7
implemented after March 2009.
The Borrower has allocated
adequate resources to PRSP/MAP
priority sectors in its Budget for
2007.
Met in 2007. The budget for 2007
allocated 18.1 % to education, 16.3% to
infrastructure, and 9% to health, which was
consistent with the MAP priorities. (See
current allocations under PRSC-5 status.)
All sector ministries have
submitted budget execution reports
based on an economic
classification to the Ministry of
Finance and Budget (MEFB)
within four weeks after the end of
the reference period (every four
months).
Met in 2007 and still currently submitted
every 4 months.
Procurement Audits are carried out
by or under the oversight of the
Regulatory Agency for Public
Procurement (ARMP) in at least 3
key ministries (education, health,
transport) to assess compliance
with new rules and regulations
Met in 2007 for the ministries of education,
health and transport. Procurement audits
have not been conducted since 2009.
Governance
The Borrower has adopted new
regulations on fiscal
decentralization to be reflected by
the 2007 Budget Law.
Met in 2007. The 2007 Budget Law
increased the share of certain taxes (impôt
synthétique, impôt foncier) in favor of the
communes. Formally the prior action was
fulfilled, but the adopted regulations fell
well short of the originally envisaged scope
of the reform due in part to difficulties in
conceptualizing and operationalizing a
broader revision of the fiscal
decentralization framework. In 2008, the
Government instituted a local development
fund (FDL)6
. As the Bank and EU
decentralization project did not
materialized, the FDL has not been able to
channel block grants to communes to
finance basic social and economic
infrastructure. However, since the
beginning of the crisis in early 2009, the
FDL has remained operational and has been
able to make limited transfers to communes
financed from domestic resources. The
6 The FDL was created with two main objectives: (i) strengthen commune capacity, and
(ii) transfer funds to communes for small social services/economic infrastructure.
8
percent of the budget allocated to FDL was
less than 2% in 2011.
The Borrower has developed
conflict-of-interest regulations.
Met in 2007. Government initiated the
process to develop conflict of interest
regulations for the civil service. A decree
was drafted and implementation was to
start in July-August 2007 in 4 pilot
ministries. However, it was never
implemented.
Basic Service Delivery
Implementation of the National
Education for All Initiative Plan
(EFA) is on track.
Met by 2006. The EFA plan was
implemented and is broadly on track. The
program is in the third phase and a new
EFA strategy is under preparation.
The Borrower has prepared and
validated the Health Sector
Development Program (PDSS).
Met by 2007, when the Ministry of Health
completed the elaboration of the PDSS and
it was validated by the Cabinet. The PDSS
is still the reference document for the
health sector today.
The Borrower has elaborated,
validated, and implemented the
recommendations of a nutrition
sector institutional assessment.
Met in 2007. The institutional assessment
of the National Office of Nutrition (ONN)
was completed in early March 2007 and
validated with the Prime Ministry. A decree
formalizing the main institutional changes
was issued on May 2007 (decree No. 397).
Although the institutional arrangement is
still in place, it lacks financing.
The Borrower and its main partners
have implemented the
recommendations of 2006 joint
donor/Government sector review in
the program budget 2007-2009.
Met by 2007. However, the program
budget only worked adequately until 2009.
PRSC-5
Public Finance Reform
The Borrower has satisfactorily
implemented the Priority Action
Plan (PAP) for FY2007.
Met as of October 2007. The joint donor
mission in October 2007 and the 2007
implementation status report confirmed
satisfactory implementation of the PAP.
Same in October and December 2008 for
the implementation of the PAP of 2008.
The PAP was no longer implemented after
March 2009.
The Borrower has allocated
adequate resources to MAP priority
sectors in its budget for 2008.
Met. The budget for 2008 continued to
allocate significant resources to priority
sectors (8% for health, 18.5% for
education, 11.5% for public works and
2.5% for transport). Budget allocations to
9
health, education and transport as percent
of GDP were significantly lower in 2010
and despite increasing for education and
health in 2011, resources are still
substantially insufficient to meet the
nation‟s needs (see section 3.2.3). The table
below shows committed expenditures as
shares of GDP in three priority sectors.
2009 2010 2011
Health
9.3%
5.7%
8.8%
Education
22.6%
17.0%
19.2%
Transport
1.4 %
0.5 %
0.3%
Source: Ministry of Finance and Budget.
All sector ministries have reconciled
their budget execution status with
the Ministry of Finance and Budget
at least every 2 months.
Met as of May 2008. Since the beginning of
February 2008 to 2009, the budget
execution status between key sector
ministries (health, education, transport,
public works, environment and agriculture)
and the Ministry of Finance was reconciled
and discussed on a monthly basis by using
the SIGFP. The practice appears to have
been discontinued since 2009.
The Borrower has published on the
website of the ARMP the results of
all public tendering processes of the
central Government with a contract
value above US$50,000.
Met. From December 2007 to March 2009,
all major central Government tendering
processes were published on the website of
ARMP. Although the system is still in
existence, the information it reports does
not appear to be reliable.7
The Borrower has started
implementing the recommendations
of the independent audit of the
commitment control (CDE) in: (i)
fully integrating the CDE into the
integrated financial management
system (SIGFP) and (ii) reducing
the current transaction time
Met. The CDE began to systematically use
the SIGFP in the second half of 2007 and
results indicated a significant improvement
of service standards. The CDE is currently
integrated in the SIGFP, and the visa takes
24 hours instead of 3 to 5 days.
7 According to the website, for example, the Ministry of Sports tendered equipment for a total of
30 billion ariary in 2010, even as its overall annual budget was only 3.3 billion ariary. See World
Bank, PER, “Madagascar: La Politique Budgétaire après Deux Ans de Crise Politique et
Comment l‟Investissement Public peut Contribuer à la Croissance du Pays”, September 2011.
10
necessary for the CDE visa by at
least 20%.
Governance
The Borrower has started reviewing
the hydrocarbon law to include the
separation of National Office for
Mines and Strategic Industries
(OMNIS) regulatory and
commercial functions.
Met. A first draft was prepared and
discussed through a participatory process.
As a result, the new law was expected to be
submitted to Parliament in early 2009, but
never was.
Basic Service Delivery
The implementation by the
Borrower of the National Education
for All (EFA) plan is on track.
Met. The EFA plan was implemented and is
broadly on track. The program is in the
third phase and a new EFA strategy is
under preparation.
The Borrower has updated and
validated a health mapping at all
levels of the health system.
Met. The updating of the health map was
completed before May 2008 and
implemented.
The Borrower has caused: (i) the
national coordinator of the National
Office for Nutrition (ONN) to
submit to the permanent office of
the National Nutrition Council
(CNN) the ONN financial accounts
certified by an external independent
auditor recruited by competitive
bidding and (ii) the permanent
office of the CNN to validate the
ONN‟s accounting and financial
procedures manual.
Met. The independent audit and the
elaboration of manuals were completed and
validated by the CNN permanent office in
April 2008.
The Borrower has issued the decree
for the creation of the Directorate
General of Water and Sanitation
(DGWS) and, through its ministry
in charge of water, has started
recruitment of at least 30 of the 60
new DGWS staff members.
Met. The decree was issued in November
2007. The DGWS was created and its
director general was recruited. The
recruitment process for all 60 new staff
members was launched in January 2008 as
planned. The DGWS was changed to a
ministry in mid-2008 and recruitment was
carried out.
PRSC-6 indicative triggers for what was intended to be the third PRSC of this series, as
presented in PRSC-5 Prior Actions Table is shown below. Even though the operation
was not presented to the Board, several of these triggers were carried out as of February
2009 and a few remain in place today.
Public Finance Reform
The Borrower has satisfactorily
implemented the PAP for FY2006.
Carried out as of February 2009. The joint
donor missions in October and December
2008 confirmed the satisfactory
implementation of the PAP. However, the
11
PAP was not implemented after March
2009.
Develop standardized budget
execution reports and distribute
them internally to all sector
ministries and cabinet on a monthly
basis.
Carried out as of February 2009. A
standardized report on the Ministry of
Finance website has been available to the
public since August 2008. After March
2009, the website8
continues to show
standardized reports on quarterly budgetary
commitments, albeit with gaps in coverage.
Continue to strengthen the capacity
of ARMP and of the procurement
units in key sector ministries,
including (i) training of
procurement auditors and the
creation of a pool of auditors and
(ii) carrying out procurement audits
in the following three Government
institutions: FER, SAMVA, and
OMH.
Not carried out.
Develop standardized monthly
reports for financial controls based
on the SIGFP, including (i) the total
number of rejections of
approvals/visas and (ii) the main
reasons for rejections by the General
Directorate for Financial Controls
(Direction Générale du Contrôle
Financier).
Carried out as of February 2009. Currently,
internal controls can effectively contain
spending commitments within the limits of
budgetary authorizations. The devolution of
financial controls coupled with a high level
of computerization and clear and well-
known procedures strengthen the controls
in place. However, discretionary control
mechanisms remain concentrated at the
different steps of the administrative
process, which undermines the potential for
effective control.
Governance
Submit revised hydrocarbon law to
Parliament.
Not carried out.
Budget allocation in the 2009
Budget Law to the Local
Development Fund (EPA-FDL)
increased by 15 percent compared to
the level in the 2008 Budget Law.
Carried out as of February 2009. The
budgeted allocation to the FDL funded on
internal resources increased 38% between
2008 and 2009. However, for reasons
explained before, the percentage of the
budget allocated to it has sharply decreased
since the beginning of the crisis. The FDL
allocation in the 2011 finance law was 1.14
8 http://www.mefb.gov.mg/index.php?option=com_content&view=article&id=465&Itemid=186
12
billion ariary (including FDL current
expenditures and EPA transfers), compared
to 28.3 billion ariary in 2008 (including
27.9 billion ariary for EPA transfer).
Basic Service Delivery
Implementation of national EFA
Plan is on track.
Carried out. The EFA plan was
implemented and is on track. The program
is in the third phase and a new EFA
strategy is now under preparation.
Design and start implementing in
pilot areas incentive- and
performance-based mechanisms for
redeployment of medical personnel
in rural areas.
Partly carried out as of February 2009.
During 2008, a series of incentives aimed at
encouraging the redeployment of health
personnel were implemented. The piloting
of performance based mechanisms started
in January 2009 in the regions of Alaotra
Managoro and Anosy where 70% of the
needed personnel were deployed. This
activity was part of the Sustainable Health
System Development Project. However,
the evaluation of the pilot could not be
carried out due to the political crisis.
The new ONN HR policy is
operational in accordance with the
2007 implementation decree.
Carried out by February 2009. The ONN
HR policy is still operational.
All the 60 new DGWS staff
members are recruited and 50 of
them are deployed to the regions.
Carried out as of February 2009. All 60
new staff were recruited and most of them
deployed to the regions.
2.2 Major Factors Affecting Implementation
Over the early implementation of the program supported under PRSC-4 and PRSC-5,
major factors affecting implementation included donor coordination, the effects of shocks,
capacity issues, and complementarities between PFM reforms and social sector policy
implementation.
Bank coordination with other donors through the common framework of budget
support was a positive element in the implementation of PRSC-4 and PRSC-5. The
joint donor status reports on PAP implementation provided inputs to the status of various
reforms supported by the series. During the joint supervision missions, common areas of
support with the EU‟s program of budget support (Programme d‟Appui Budgétaire à la
Réduction de la Pauvreté, or PARP) included the public-sector reform agenda, education
and health. There were also synergies with other donors on areas supported by the series.
Madagascar’s vulnerability to external shocks affected implementation of this series,
in particular, cyclones and variations in global commodity prices, such as oil and
rice, and the global financial crisis. These risks were identified in PRSC-4 and PRSC-5,
and some measures were taken to mitigate their impact. To reduce vulnerabilities to
13
climate shocks, for example, the Bank supported the Government in finalizing a Risk and
Social Protection review that paved the way for risk prevention and mitigating strategies.
There were also steps taken to investigate the feasibility of specific options to mitigate
shocks, such as weather risk insurance. The Bank also supported Government efforts to
protect vulnerable groups affected by food price increases.
Capacity constraints were a negative element in the implementation of PRSC-4 and
PRSC-5. Although the Government undertook efforts to improve internal capacity,
significant weaknesses at the sectoral and local levels remained. To mitigate the impact,
the Government, in coordination with the donors, prepared a capacity building strategy as
a key element of the MAP. The donor community designed a range of technical
assistance grants and training initiatives designed to enhance capacity. These efforts were
enhanced through round tables for public expenditure management reforms and the
Budget Support Group.
Delays in implementing public finance and structural reforms in strategic sectors
were a challenge and an identified risk for improving service delivery. The
unpredictability of budget execution, capacity weaknesses in applying the program
budget structure, and poor monitoring and evaluation (M&E) negatively impacted service
delivery in priority sectors. The PAP implementation was identified as critical to ensuring
real impact on service delivery and poverty reduction. The political crisis in early 2009
was the main impediment to the full implementation of the series and progress on its
objectives. Given Madagascar‟s recent history, political risks to implementation of both
PRSC-4 and PRSC-5 had been identified in the program documents. At appraisal of
PRSC-4 and PRSC-5, however, the political situation in Madagascar appeared to be
stable, having been solidified by the transparent and peaceful national elections in
December 2006 and municipal elections in December 2007. The coup d'etat of March
2009 forced President Marc Ravalomanana into exile and put into power the elected
Mayor of Antananarivo, who took the title of President of the High Authority (HAT).
This unconstitutional access to power was rejected by the international community. The
causes of the 2009 crisis were multiple and complex, and include governance issues in
the policy process and conduct of officials at the highest level of the Government, with
significant issues coming to the forefront already by late 2008 and forming part of the
triggers for the subsequent crisis and entrenched and widespread poverty, and limited
progress in sustained, inclusive economic growth.
The onset of the crisis, the change in government and several donors’ decisions to
suspend their respective programs effectively led to the interruption of the reform
program supported by the PRSCs. For the planned PRSC-6, although many of its
triggers were met by February 2009, the onset of the crisis triggered the application of OP
7.30, and its processing was suspended. In this context also, the broader agenda
supported by the PRSCs, including in PFM reform and service delivery has been
interrupted. The political crisis translated into a sharp contraction in spending, with donor
aid falling sharply, a fall in domestic revenues related in part to a decline in GDP, and the
adjustment of overall expenditures to maintain macroeconomic balance, even as the
relative allocation of funds to current spending on priority social sectors was broadly
maintained. On the structural front, since 2009, in particular, the PAP was not
implemented in its form, and the political crisis undermined the vision created for the
social sectors. It also created greater uncertainty in the modes of governance. In particular,
14
at the “last segment” of the value chain in education and health care, service delivery is
currently underfunded, inefficient, and insufficient.
2.3 Monitoring and Evaluation (M&E) Design, Implementation, and Utilization
The design of the indicators to monitor PDO progress was partly adequate and
envisaged adaptation to the detailed results framework for the MAP that was finalized in
2008. Prior actions for PRSC-4 and PRSC-5 and indicative triggers for PRSC-6 were
selected with Government on the basis of (i) their importance in contributing a key
constraint to the implementation of the intended reform and (ii) their alignment with
MAP objectives. Indicators in the Policy Matrix were also consistent with the MAP.
Despite the ambitious set of indicators, the PRSC was more conservative than the MAP
in foreseeing outcomes because the MAP presented a very ambitious progression path,
predicated on a large increase of external financing that did not fully materialize. PDO
indicators were based on data expected to be available. Without the data, gaps were
created in the M&E process. For example, the last PEFA took place in 2009 and
indicators related to it became very difficult to monitor and evaluate after 2010.
M&E was implemented in an environment already known for weak monitoring
capacity and data that needed quality improvements. The Bank supported efforts to
improve these, such as through an Institutional Development Fund grant on statistical
capacity-building and through a PRSP Trust Fund for M&E of the MAP. The Bank also
provided support through the PGDI Madagascar Second Governance and Institutional
Development Project (P103950) that aimed at improving ministry level monitoring
systems, developing the National Statistics Institute (INSTAT), and contributing to the
funding of the 1993 Population and Housing Census.9 Despite these efforts, M&E
implementation was inadequate. Several activities, such as the roll-out of the MAP M&E
system and the Population and Housing Census, were never carried out after suspension
of development assistance in March 2009.
2.4 Expected Next Phase/Follow-up Operation (if any)
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
The PRSC objectives and design were fully relevant, and remain so today. An
extensive program of analytical and advisory activities (AAA) informed the PRSC design.
Key monitoring indicators were mostly chosen from the Government‟s Action Plan
Matrix in coordination with the Government and donors. The monitoring and evaluation
of this series was adapted to the monitoring system of the MAP. The Government
developed in close collaboration with partners, including the Bank, the detailed results
framework for the MAP and designed the proper institutional setting to monitor its
implementation.
9 The latest Madagascar Population and Housing Census is dated 1993.
15
The PRSC objectives are still relevant to Madagascar despite the political crisis that
put a halt to its implementation. The three-year crisis has imposed a high cost on one of
the world‟s poorest populations. As a result, Madagascar is gradually sinking into a state
of increased fragility, including a rise in poverty and a continued deterioration in
governance. Health and education are close to an emergency situation because the
delivery system for public services risks paralysis despite humanitarian aid, which,
bypassing public institutions is showing its limits. The infrastructure is in an alarming
state of falling into disrepair. Furthermore, Madagascar remains prone to exogenous
shocks (financial crisis, food or oil prices) and extreme climate risks (hurricanes,
drought), which further aggravate the vulnerability of the poor in a country where the
Government has only limited capacity to respond. Therefore, improving governance and
public sector management, and service delivery in key areas are still at the core of
Madagascar needs.
3.2 Achievement of Program Development Objectives
Program Development Objectives Results Matrix in Annex 7 presents a summary of the
achievements under this PRSC series relative to baselines and targets. Detailed indicators
provide evidence of progress towards achieving the PDOs.
3.2.1. Public finance reform (unsatisfactory)
In the area of public finance management, substantial improvement of the whole budget
process was achieved by 2008, a trend captured by the PEFA indicators comparing the
situation in 2006 and 2008 (see Annex 8). Despite these improvements, however, most of
the target indicators were not met as of 2011 (see Annex 7). A rapid assessment of the
PFM was done in 2011. It concluded that the PFM did not worsen significantly during the
political crisis, but the need for improving the system is urgent.
In the area of budget execution, the overall process was streamlined through the
introduction of the modern computerized SIGFP. As a consequence, all central public
institutions (ministries and central government level) now execute their annual budgets
through SIGFP. However, budget execution rates, which improved significantly between
2006 and 2008, deteriorated in recent years. The closest available measure of execution
rates for 2011 is presented in the Analysis of the Finance Act of 2012, which shows a
comparison between the Finance Act of 2011 budgeted amounts and expected realization
for 2011. These data show that, in most cases, the expected realization rate is
significantly off the projected amounts, except for staff costs, interest payable, and other
net treasury operations. The differences are most notable in non-tax revenues, grants, and
capital expenditures where expected realization is only 60%, 63%, and 51% of the
budgeted amounts, respectively, reflecting in part low donor‟s disbursements relative to
budget forecasts. This said, the execution of domestically-financed capital expenditure
also fell short of budget plans.
In the area of revenue generation, improvements from 2006 to 2009 resulted from
substantial administrative and policy reforms, such as the consolidation of the tax and
16
custom reforms, which led to an unprecedented increase in tax collection in 2008.10
The
Government was able to maintain the tax share at 10.7 percent of GDP in 2009 and 2010
and even increased it slightly to 10.9 percent of GDP in 2011, with a continued effort in
tax collection compensating for the decline in economic activity. The Government has
continued to pursue macroeconomic stability and fiscal sustainability, with public
investment having born the burden of adjustment to lower revenues and donor resources
since the beginning of the political crisis.
Internal control systems operate with significant deficiencies, particularly for
commitment controls. Controls continue to appear inadequate for the execution of civil
service payroll, for ensuring compliance of non-salary expenditure execution with
procurement rules and regulations, and in the verification of the actual delivery of goods
and services. However, limited information is currently available for assessing recent
trends and practices.
In the area of improving budget transparency, efforts included the previously
mentioned introduction of a SIGFP, which allowed the production of regular reports as
well as reformed public procurement. However, the absence of an effective control
system on the use of public funds remains a concern. Reporting and control processes on
use of funds in Treasury accounts (“comptes des dépôts”) remain insufficient. A
significant fraction of non-tax revenues and public funds managed by autonomous public
agencies are not included in the budget. To improve transparency of the public
procurement process, the ARMP set up a website to provide information about open
tenders and about the results of the tendering process. However, the information now
often appears outdated and its quality varies. The application of the new procurement
code was becoming more common, but due to a lack of training, local entities (communes,
regions, independent public agencies) do not systematically use it. Cases of misuse of
public funds are rarely reported due to weak and insufficient controls. The same is true
for corruption cases in public procurement.
3.2.2. Governance (unsatisfactory)
In the area of reduction of corruption, the PRSC program assisted the Government in its
efforts to consolidate the regulatory framework, but the political crisis took a heavy toll
on governance indicators. Between 2002 and 2009, most governance indicators were
improving, and Madagascar was doing better than the African average on most accounts.
Transparency International‟s Corruption Index for 2007, which the Government used to
assess the effectiveness of anti-corruption efforts, gave Madagascar a rating of 3.2,
ranking 95th
out of 179 countries. This was an improvement over the rating of 2.8 in 2005.
10 The Government also included a number of reforms in the 2008 Budget law, including the
merging of personal and corporate income taxes and the reduction of the top rate from 30 percent
to 25 percent, removing taxes on dividends and excise taxes on sugar and flour, raising the VAT
threshold and increasing its rate by 2 percentage points, removing small taxes, and eliminating
some special treatments.
17
Furthermore, the index for 2009 improved to 3.4 before rapidly deteriorating during the
ongoing crisis. From 2008 to 2011, Madagascar fell from 85th
to 100th
in the world on
Transparency International‟s Corruption Perception Index, earning a rating of 3.0 in 2010
and 2.6 in 2011. Similarly, the Bank‟s Country Policy and Institutional Assessment index
(CPIA) declined from 3.7 in 2008 to 3.4 in 2010 with the indicator on Transparency,
Accountability and Corruption in the Public Sector falling from 3.5 to 2.5.
In the area of reducing opportunities of corruption in natural resource industries, the
forestry sector has seen a surge in illegal logging of precious timber. This has risked
destroying the progress made in two decades of efforts to preserve the island‟s unique
biodiversity.
In the mining sector, where sound governance institutions have been adopted since the
late 1990s, transparent governance is at risk of being undermined. A transparent permit
management system was designed to encourage prudent exploitation and valuation of
Madagascar‟s mining potential, but implementation has been weak, with limited gains in
transparency and indications of political interference, including in the redistribution of
mining revenues among affected communes. Madagascar was accepted as an Extractive
Industry Transparency Initiative (EITI) candidate in February 2008, but it was suspended
from the EITI process in October 2011 due to a non-conducive environment for effective
multi-stakeholder dialogue.
Regarding decentralization, this PRSC series was expected to lead to a higher share of
resources available to the local governments. Initially, the share of the total budget
transferred to local government rose from 1.8 percent in 2007 to 2.3 percent in 2008;
however, it fell to 1.7 percent in 2009 and reached 1.9 percent in 2010. However, the
decentralization process which had already started in the 1990s has made little progress
over the last 20 years. Although decentralization is one of the seven challenges under the
governance agenda of the MAP, government commitment has been uneven.
3.2.3 Improving Service Delivery (unsatisfactory)
The public health service delivery system is increasingly under threat, with increasing
fragmentation of scarce donor resources, decreasing utilization of public health services
and growth of parallel service delivery systems. Despite improvements in such indicators
as the child underweight rate and skill birth attendance (see PDO Results in Annex 7), the
impact of the crisis in the health/nutrition sector is noticeable. Between 2008 and 2010-11,
other indicators showed worsening trends; for example, the prenatal consultation rate in
basic health centers decreased from 74 to 62 percent and the acute malnutrition rate
increased from 4.7 percent to 7.4 percent. Moreover, the poorest segment of the
population is now most likely to need these parallel systems, which inherently cost more.
Public delivery in education has also suffered. None of the indicators in the Annex 7 were
met, although some showed improvements, such as the primary enrollment rate and the
primary completion rate. However, the impact of the crisis in this sector is high. Lower
public funding for education has led many communities to hire and pay for teachers. It is
estimated that as many as two-thirds of primary school teachers are hired by the
18
community. Given the economic context and the absence of regulation, these trends are
becoming increasingly unsustainable and leading to higher dropout rates.
Regarding service delivery in water and sanitation, indicators show mixed results.
Among the rural population, access to safe drinking water was reported to have improved
from 31.6 percent in 2006 to 38.5 percent in 2010; meanwhile, sanitation access fell from
47 percent in 2006 41.5 percent in 2010.
3.3 Justification of Overall Outcome Rating
Rating: Unsatisfactory
Based on the achievements of the PDOs, the overall outcome of the PRSC series is rated
unsatisfactory. Ten of the sixteen indicators were not met, one was partly met, and only
four were met. The implementation of the reform was halted by the political situation and
the likelihood that most of the results would be achieved is nil until the political crisis is
resolved.
3.4 Overarching Themes, Other Outcomes, and Impacts
a. Poverty impacts, gender aspects, and social development
The series was expected to have contributed to reduced poverty incidence from 68.7
percent in 2005 to 64 percent in 2010, with significant distributional impacts. However,
poverty incidence was estimated to have increased by more than 9 percentage points
between 2005 and 2010, reaching 77 percent of households, one of the highest rate in
Africa (World Development Indicators, 2011). The poverty challenge differs across
regions and other dimensions. There are wide gaps among regions (from 57 percent to 77
percent) and between rural areas (74 percent) and urban areas (52 percent)11
. In addition,
income differences between the rich and the poor are large, especially in urban centers,
where the ratio between the highest and the lowest income groups may top 10. Under the
current circumstances, there are little chances that Madagascar would achieve most of the
MDGs by the deadline date of 2015.
b. Institutional change/strengthening
This PRSC series had a strong complementarily with the Governance and Institutional
Development Project I and II. Both PRSC-4 and PRSC-5 were implemented in close
collaboration with these projects which supported specific activities in the area of focus
of the PRSC series. Some progress was made in the institutional front. For example, the
management of the Tax Directorate and the large taxpayer doctorate underwent
restructuring and modernization to allow for more transparency on tax declaration and tax
collection.
11 Madagascar ISN, December 2011. Report No. 63863-MG.
19
c. Other unintended outcomes and impacts (positive or negative)
None observed.
3.5 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
Not applicable.
4. Assessment of Risk to Development Outcome
Rating: High
Political and economic developments since early 2009 have effectively pre-empted the
achievement of most of the PRSC program‟s development objectives for the medium
term.
5. Assessment of Bank and Borrower Performance
5.1 Bank Performance
a. Bank performance in ensuring quality at entry
Rating: Moderately satisfactory
The design of this PRSC series, the second PRSC series in Madagascar, focused on
critical issues facing the country and in line with the CAS and Madagascar‟s
development goals as stated in its MAP. It supported the Government in implementing a
comprehensive reform program in the areas of governance and service delivery. It was
built on an extensive program of analytical and advisory activities (AAA), which
underpinned the Bank‟s policy dialogue and programmatic lending. It also incorporated
lessons from PRSC1-3. These ensured quality at entry. However, the series‟ scope was
very broad, and it could have benefited from more focus. There also could have been
scope to improve some of the linkages between prior action, triggers and PDO indicators.
For example, the trigger „the borrower has satisfactorily implemented the Priority Action
Plan‟ was very broad and could have been further detailed. Conversely, other PFM
related triggers were very much focused: allocation of adequate resources to PRSP/MAP
priority sectors in the budget (although no clear link to PDO indicators), and timely
submission of budget execution reports on an economic classification (PEFA Indicators 5
and 24).
Furthermore, the ambitious set of indicators, although less ambitious than the PAP, could
have been more conservative. For example, the PDO indicators related to PFM, in
particular, indicators 1, 3 and 4, could have been less ambitious at least in terms of the
horizon to achieve outcomes. For example, some of the objectives set out for PFM
reforms expected to be achieved in 3-4 years exceeded, in some cases, the performance of
two Middle Income Countries (Brazil and Peru) with very strong public sector and PFM
capacities.
20
b. Quality of supervision
Rating: Moderately unsatisfactory
Supervision was carried out through consultations with the Government and other
development partners. During the appraisal of PRSC-5, the Bank assessed the
achievement of prior actions and indicators as of 2007. In the context of the preparation
of the concept note for PRSC-6, it also evaluated the achievements of triggers for PRSC-
6. The Bank prepared two Implementation Status and Results Reports (ISRs), the last one
on August 2008, which assessed progress with indicators as of the end of 2007. It also
conducted periodic reviews with the other partners in the context of joint missions on
budget support and relevant sector programs. After March 2009, however, there was no
formal supervision. Nevertheless, the Bank maintained a technical dialogue with the
Ministry of Finance and Budget and other relevant ministries.
c. Justification of rating for overall Bank performance
Ratings: Moderately unsatisfactory
Despite a moderately satisfactory quality at entry, the scope for bank supervision and
policy dialogue was sharply reduced since March 2009 as a result of the ongoing political
crisis.
5.2 Borrower Performance
Rating: Unsatisfactory
In the early years of design and implementation, the Madagascar Government led the
design of the PRSC series through a process of frequent Bank-Government dialogue.
This series was designed to conform to the budget cycle, which runs from January 1 to
December 31, and PRSC-5 was delivered by the second quarter of the calendar year, as
requested by the Ministry of Finance. The responsibility for implementing this PRSC
program rested with the Ministry of Finance and Budget. The Government took the lead
in monitoring progress, implementing and updating the program policy matrix, and
coordinating inputs from other relevant ministries. The Government initially showed
strong ownership of reforms and commitment to achieve development objectives. In the
context of the political crisis, donor disengagement, and ensuing economic and financial
developments, however, the specific reform agenda supported by the PRSCs is no longer
a core government priority. Despite initial strong commitment to the DPOs and efforts to
strengthen the institutional structure to implement the overall MAP, subsequent
developments in policy conduct and performance called for a rating of unsatisfactory.
6. Lessons Learned
Development Policy Lending can be effective instruments for the Bank and
other development partners to signal significant concerns about governance.
By late 2008 development partners‟ governance concerns escalated. As a result,
the IMF postponed its Board presentation that was scheduled for December, 2008.
21
Other partners (EU and Germany) who were on the verge to disburse their budget
support in December 2008 decided to discontinue their disbursements until the
Government would provide satisfactory explanations and remedies. The Bank also
signed the letter that started the discontinuation of the disbursements. This was a
strong and coordinated signal that development partners were able to use to convey
these concerns about worsening governance and issues of transparency in fiscal
policy and management.
Donor coordination for budget support remains essential. A partnership
agreement was signed in 2004 between the Government and the key budget
support donors, the European Union (EU), France (Agence Française de
Developpement and the French Co-operation), the African Development Bank
(ADB) and the World Bank, later joined by Germany. The goal was to provide a
better alignment with Government procedures and Paris declaration objectives.
This group based its support on a harmonized matrix that guided individual
interventions. This group also agreed, in close coordination with the IMF, to
suspend budget support in December 2008. However, several members have also
noted that discussions within such a coordination group could be strengthened to a
more technical substantive level than has been the case.
Broader monitoring of developments on the ground and more attention to
outcomes, as opposed to inputs, is needed. Although selected prior actions and
indicators were coordinated with the Government‟s Action Plan and MAP
objectives, their monitoring did not always provide a whole picture of real progress
on the ground, especially in regards to developments on the governance front.
While in social sectors, outcomes indicators were used to assess progress, in PFM,
too much emphasis was put on progress on inputs (such as PFM systems,
institutions, and legal texts) rather than outcomes. In particular, the indicators used
to evaluate progress on transparency and PFM focused too much on budget
preparation and not enough on execution and checks and balances.
Even when the range of systemic performance issues is broad, as it is in all
areas supported under the PRSC series, especially PFM, it remains important
to set as much as possible a few reasonable objectives aiming at gradual and
sustainable improvements. Related to this is the need for careful recurrent review
of existing analytical work when designing and implementing a reform program,
targeting more focused triggers and PDO indicators. For example, as noted above,
the PRSC series could have supported two or three selected and critical PFM
improvements rather than proposing such a broad coverage.
Supplemental financing may sent mixed signals to authorities when issues
emerge in the implementation of a PRSC-supported program. PRSC-5 was
approved as an instrument to support the Government's progress on the
implementation of its national strategy. Concurrently, another budget operation
was prepared in 2008 to help Madagascar deal with the international food crisis.
Although these two operations were distinct, they resulted in an increase in budget
support and may have been interpreted by the authorities as a seal of approval from
22
the Bank and the donor community even at a time when significant governance
concerns had emerged at the forefront.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners
a. Borrower/implementing agencies
b. Co-financiers
c. Other partners and stakeholders
Comments were received from donors and have been reflected in lessons learned.
23
Annex 1 Bank Lending and Implementation Support/Supervision Processes
(a) Task Team members
P099420 - Poverty Reduction Strategy Credit
Names Title Unit Responsibility/
Specialty
Lending
Norosoa Andrianaivo Language Program Assistant AFTED
Myrina D. McCullough Consultant AFTSP
Stefano Paternostro Lead Economist MNSED Task Team Leader
Francois Marie Maurice
Rakotoarimanana Sr Financial Management Specia AFTFM
Sylvain Auguste Rambeloson Senior Procurement Specialist AFTPC
Supervision
Noro Aina Andriamihaja Economist AFTP1
Sajitha Bashir Sector Leader LCSHD
Sofia U. Bettencourt Lead Operations Officer AFTEN
Mukesh Chawla Head HDNVP
Pierre Graftieaux Lead Transport Specialist AFTTR
Guenter Heidenhof Sector Manager MNSPR
Montserrat Meiro-Lorenzo Sr Public Health Spec. HDNHE
Jacques Morisset Lead Economist AFTP2
Suzanne F. Morris Senior Finance Officer CTRFC-
His
Christophe Prevost Sr Water & Sanitation Spec. LCSUW
Francois Marie Maurice
Rakotoarimanana Sr Financial Management Specia AFTFM
Patrice Joachim Nirina
Rakotoniaina Municipal Engineer AFTUW
Patrick Philippe
Ramanantoanina Senior Operations Officer LCSHE
Sylvain Auguste Rambeloson Senior Procurement Specialist AFTPC
Dieudonne Randriamanampisoa Senior Economist AFTPR
Herinjara Maria Ranohatra Team Assistant AFMMG
Ganesh Rasagam Senior Private Sector Developm AFTFE
Renaud Seligmann Manager AFTFM
Maryanne Sharp Senior Operations Officer LCSHH
Gilles Marie Veuillot Consultant AFTEG
P105135 - Madagascar Fifth Poverty Reduction Strategy Credit
Names Title Unit Responsibility/
Specialty
Lending
Supervision
Jacques Morisset Lead Economist AFTP2
(b) Staff Time and Cost
P099420 - Poverty Reduction Strategy Credit
24
Stage
Staff Time and Cost (Bank Budget Only)
No. of staff weeks USD Thousands (including
travel and consultant costs)
Lending
FY07 38 248.20
FY08 0.00
Total: 38 248.20
Supervision
FY07 0.00
FY08 0.00
Total: 0.00
P105135 - Madagascar Fifth Poverty Reduction Strategy Credit
Stage
Staff Time and Cost (Bank Budget Only)
No. of staff weeks USD Thousands (including
travel and consultant costs)
Lending
FY08 113 405.26
FY09 0.00
Total: 113 405.26
Supervision
Total: 0.00
25
Annex 2. Beneficiary Survey Results
None undertaken.
26
Annex 3. Stakeholder Workshop Report and Results None undertaken.
27
Annex 4. Summary of Borrower's ICR and/or Comments on Draft ICR
Based on the country‟s political circumstances and limited dialogue with the Ministry of
Finance, the team decided not to seek comments from the Borrower.
28
Annex 5. Comments of Cofinanciers and Other Partners/Stakeholders
Comments were received from donors and have been reflected in lessons learned.
29
Annex 6. List of Supporting Documents
World Bank
IDA Program Document, PRSC-4, Report No.39028, May 25, 2007.
IDA Program Document, PRSC-5, Report No. 43274-MG, May 29, 2008.
Food Price Crisis Response Trust Fund Program Document for a Proposed Supplemental
Financing Grant, Report No. 44743-MG, July 31, 2008.
Concept Note for PRSC 6, February 12, 2009 (Draft).
IDA Interim Strategy Note for the Republic of Madagascar, Report No. 63863-MG,
December 28, 2011.
Madagascar CPIA 2010 (draft), March 2011.
Madagascar: Governance and Development Effectiveness Review. A Political Econmy
Analysis of Governance in Madagascar. Report No. 54277-MG, July 2010.
Madagascar : “La Politique Budgétaire après Deux Ans de Crise Politique et Comment
l‟Investissement Public peut Contribuer à la Croissance du Pays ”, , September 2011.
Implementation Completion and Results Report for the First Governance and Institutional
Development Project, Report No 00001514, July 2010.
IMF
Republic of Madagascar: 2007 Article IV Consultation, IMF Country Report No. 07/236,
July 2007.
Other sources
“Mission d‟évaluation de la gestion des finances publiques malgaches du 26 Octobre au
16 novembre 2011”, Interim Report by Ibarhim Mamane, Decmber 2011.
“Évaluation de la mise en œuvre du système intégré de gestion des finances publiques
(SIGFP) malgaches”, Interim report by Michael Bitz, November 30, 2011.
30
Annex 7: Program Development Objectives Results
Baseline Value Original
Target
Value
(from
approval
documents)
Formally
Revised
Target
Values
Actual Value Achieved at
Completion of Target
Years
2007 2008 2009 2010 2011
A. PUBLIC FINANCE MANAGEMENT
Indicator 1: Number of PEFA budget preparation and execution indicators (indicators 1 through 17) rated “B” and above.
Value
(quantitative or
qualitative)
9 13 N.A. NA 10 9 9 NA NA
Date achieved 2006 2010
Comment
(incl. %
achievement)
Target not met. The 2011 PEFA that would have allowed assessment for this indicator did not take place. (The last
available PEFA dates from 2009). A 2011 review of PFM issues suggests limited progress on the Public Finance
Management reform agenda since March 2009.
Indicator 2: Number of public institutions (ministries at central government level) executing their budgets through the SIGFP.
Value
(quantitative or
qualitative)
5 All All 9 All All All All
Date achieved 2006 2010 2011
Comment
(incl. %
achievement)
Target met.
Indicator 3: Number of PEFA budget reporting indicators (indicators 22 through 25) rated “B” and above.
Value
(quantitative or
qualitative)
0 3 NA 1 0 0 NA NA
Date achieved 2006 2010
Comment
(incl. %
Target not met. See comment for Indicator 1.
31
Baseline Value Original
Target
Value
(from
approval
documents)
Formally
Revised
Target
Values
Actual Value Achieved at
Completion of Target
Years
2007 2008 2009 2010 2011
achievement)
Indicator 4: Number of PEFA indicators measuring the internal/external control mechanisms (indicators 20, 21, 26 through
28) rated “B” and above.
Value
(quantitative or
qualitative)
0 4 NA 0 0 0 NA NA
Date achieved 2006 2010
Comment
(incl. %
achievement)
Target not met. See comment for Indicator 1.
Indicator 5: Percentage of reviewed procurement processes in selected public institutions that conform to the new procurement
regulations (Ministries of Education, Health, Transport, and Agriculture used as reference points).
Value
(quantitative or
qualitative)
5% 80% 50% 28.1% 35% 40% 50% NA
Date achieved 2006 2010 2010
Comment
(incl. %
achievement)
Target not met, but some improvement occurred.
B. GOVERNANCE
Indicator 6: National Anti-Corruption Perception Index of (i) households and (ii) civil service employees.
Value
(quantitative or
qualitative)
(i) 2.2
(ii) 3.0
(i) 10%
increase
2.6 3.2 3.4 3.0 2.6 NA
Date achieved 2005 2010 2010
32
Baseline Value Original
Target
Value
(from
approval
documents)
Formally
Revised
Target
Values
Actual Value Achieved at
Completion of Target
Years
2007 2008 2009 2010 2011
Comment
(incl. %
achievement)
Target not met. Data is global in the sense that it does not distinguish by target.
Indicator 7: Share of annual central budget transferred to local governments.
Value
(quantitative or
qualitative)
1.4% 2.7% 1.9% 2.6% 1.8% 2.3% 1.7% 1.9%
Date achieved 2006 2010 2011
Comment
(incl. %
achievement)
Target not met. The share of the central budget going to local governments improved from the baseline, but it is still
short of the target value. (The baseline and target indicators in PRSC-4 had a typo in the target values. PRSC-5
corrected this to the targets shown above.)
C. BASIC SERVICE DELIVERY
Indicator 8: Primary net enrollment rate.
Value
(quantitative or
qualitative)
83% 90% 87.7% 86.0%
88.9% 88.4% 87.7% NA
Date achieved 2006 2010 2010
Comment
(incl. %
achievement)
Target not met, but showed improvement. (The baseline and target indicators were revised in PRSC-5 for the series
based on the availability of better data. Initially, the baseline was 97% and the target was not specified.)
Indicator 9: Primary school completion.
Value
(quantitative or
qualitative)
50% 74% 63% 60% 66% 64% 63% NA
Date achieved 2006 2010 2010
Comment
(incl. %
Target not met. (The baseline and target indicators were revised in PRSC-5 for the series based on the availability of
better data. Initially, the baseline was 60% and the target was not specified.)
33
Baseline Value Original
Target
Value
(from
approval
documents)
Formally
Revised
Target
Values
Actual Value Achieved at
Completion of Target
Years
2007 2008 2009 2010 2011
achievement)
Indicator 10: Repetition rate.
Value
(quantitative or
qualitative)
19% 14% 19% 20% 20% 20% 19% NA
Date achieved 2006 2010 2010
Comment
(incl. %
achievement)
Target not met. (The baseline and target indicators were revised in PRSC-5 for the series based on the availability of
better data. Initially, the baseline was 18% and the target was not specified.)
Indicator 11: Skilled birth attendance in (i) CSB, (ii) CHD1 and (iii) in all public CHD2.
Value
(quantitative or
qualitative)
(i) 18.8
(ii) 1.4
(iii) 2.1
(i) 20.8
(ii) 3.4
(iii) 4.0
(i) 24.9
(ii) 3.4
(iii) 3.4
23.2
3.4
1.9
24.6
4.3
4.2
25.7
3.7
4.6
24.9
3.4
3.4
NA
Date achieved 2006 2010 2010
Comment
(incl. %
achievement)
Target met. Although skill birth attendance at all public CHD2 was not met, overall birth attendance surpassed the
target.
Indicator 12: Consultation rate for treatment in CSB (number of curative outpatient visits/total population).
Value
(quantitative or
qualitative)
44.4 Not
specified
31.2
38.2 37.6 34.5 31.2 NA
Date achieved 2006 2010 2010
Comment
(incl. %
achievement)
Target not met. (The baseline was revised from 32.4 to 44.4 due to the availability of better data. The target value was
never specified, but one would expect the target to be above the baseline value).
34
Baseline Value Original
Target
Value
(from
approval
documents)
Formally
Revised
Target
Values
Actual Value Achieved at
Completion of Target
Years
2007 2008 2009 2010 2011
Indicator 13: Availability of medicines in CSB for each of the following: (i)Chloroquine, (ii)FAF, (iii)Cotrimoxazole,
(iv)Paracetamol andVitaminA.
Value
(quantitative or
qualitative)
(i) 96.6%
(ii) 89.3%
(iii) 95.7%
(iv) 92.2%
(v) 93.4%
(i) >95%
(ii) >95%
(iii) >95%
(iv) >95%
(v) >95%
i)ACT:
98.5%
(ii)88.3%
(iii)96.7%
(iv)96.6%
(v)95.3%
(i) 92.%
(ii)92.%
(ii)95.7%
(iv)95.%
(v)94.5%
(i)91.6%
(ii)92.4%
(iii)97.1
(iv)97.2%
(v)96.2%
(i)94.5%
(ii)94.9%
(iii)97.7%
(iv)97.3%
(v)96.8%
(i)ACT:
98.5%
(ii)89.7%
(iii)95.9%
(iv)94.1%
(v)96%
(i)ACT:
99.0%
(ii)88.3%
(iii)96.7%
(iv)96.6%
(v)95.3%
Date achieved 2006 2010 2011
Comment
(incl. %
achievement)
Target met for all sub-indicators except FAF (Fer Acid Folic). Note that Chloroquine no longer exists due to policy
change in malaria treatment. Equivalent treatment was replaced by ACT.
Indicator 14: Child underweight rate.
Value
(quantitative or
qualitative)
42% Decreased
by 10% of
baseline
30% 30%
Date achieved 2003/04 2010 2011
Comment
(incl. %
achievement)
Target met. Baseline data is based on the 2003/04 Household Survey, while data for 2011 is based on the
Anthropometric and Child Development Survey.
Indicator 15: Percentage of the rural population with access to safe drinking water.
Value
(quantitative or
qualitative)
31.6% 37% 38.5% 38.5%
Date achieved 2006 2010 2010
Comment Target met. Data for 2010 is based on the 2010 Household Survey.
35
Baseline Value Original
Target
Value
(from
approval
documents)
Formally
Revised
Target
Values
Actual Value Achieved at
Completion of Target
Years
2007 2008 2009 2010 2011
(incl. %
achievement)
Indicator 16: Percentage of the rural population with access to sanitation.
Value
(quantitative or
qualitative)
47% 51% 41.5% 41.5%
Date achieved 2006 2010 2010
Comment
(incl. %
achievement)
Target not met. Data for 2010, based in the 2010 Household Survey, refers to access to latrines/toilets. (The baseline
indicator was slightly revised to 46% in PRSC-5 based on the availability of better data).
36
Annex 8: Summary of PEFA Indicators
Indicators 2006 2008 Variations
Credibility of the Budget
PI-1 Aggregate expenditures outturn compared to original approved
budget
D D =
PI-2 Composition of expenditure outturn compared to original
approved budget
A A =
PI-3 Aggregate revenue outturn compared to original approved
budget
D B +
PI-4 Stock and monitoring of expenditure payment arrears D+* C+ +
Comprehensiveness and transparency
PI-5 Classification of the budget A A =
PI-6 Comprehensiveness of information included in budget
documentation
C C =
PI-7 Extent of unreported government operations C+* C+ =
PI-8 Transparency of inter-governmental fiscal relations B B =
PI-9 Oversight of aggregate fiscal risk for other public sector entities D+* D+ =
PI-10 Public access to key fiscal information D C +
Budget cycle
Policy-Based Budgeting
PI-11 Orderliness and participation in the annual budget process B+ A +
PI-12 Multi-year perspective in fiscal planning, expenditure policy
and budgeting
C+ C+ =
Predictability and Control in Budget Execution
PI-13 Transparency of taxpayers obligations and liabilities D+* B +
PI-14 Effectiveness of measures for taxpayers registration and tax
assessment
C+ B +
PI-15 Effectiveness in collection of tax payments D+ D+ =
PI-16 Predictability in the availability of funds for commitment of
expenditures
B B+ +
PI-17 Recording and management of cash balances, debt and
guarantees
B B =
PI-18 Effectiveness of payroll controls D+ D+ =
PI-19 Competition, value for money and controls in procurement D+* C +
PI-20 Effectiveness of internal controls in procurement C+ C+ =
PI-21 Effectiveness of internal audit C+ C+ =
Accounting, Recording and Reporting
PI-22 Timeliness and regularity of accounts reconciliation D+ D+ =
PI-23 Availability of information on resources received by service
delivery units
D D =
PI-24 Quality and timeliness on in-year budget reports C+ C+ =
PI-25 Quality and timeliness of annual financial statements D+ D+ =
External Scrutiny and Audit
PI-26 Scope, nature and follow up of external audits D D =
PI-27 Legislative scrutiny of the annual budget law C+ C+
PI-28 Legislative scrutiny of external audits D D +
C+ C+
D-1 Predictability of direct budget support A A =
D-2 Financial information provided by donors for budgeting and
reporting on project and program aid
B+ B+ =
D-3 Proportion of aid that is managed by use of national procedures D D =
Source: PEFA, 2009.
VatomandryVatomandry
MahanoroMahanoro
VarikaVarika
MananjaryMananjary
TsivoryTsivory
BeraketeBerakete
BelohaBeloha
BetrokaBetroka
ManjaManja
MandabeMandabe
MorombeMorombe
AnkazoaboAnkazoabo
BerorohaBeroroha
SakarahaSakaraha
BetiokyBetioky
AndrokaAndroka
AmpanihyAmpanihy
Midongy-Midongy-AtsimoAtsimo
AmbohimahasoaAmbohimahasoa
AntalahaAntalaha
MaroantsetraMaroantsetra
MananaraMananara
MoramangaMoramanga
AntanifotsyAntanifotsy
Ambatofinan-Ambatofinan-drahanadrahana
MiandrivazoMiandrivazo
MalaimbandyMalaimbandy
Belo TsiribihinaBelo Tsiribihina
AndilanatobyAndilanatoby
AndilamenaAndilamena Soanierana-IvongoSoanierana-Ivongo
AndriamenaAndriamena
SoalalaSoalala
BesalampyBesalampy
AntsalovaAntsalova
KandrehoKandreho
AnkazobeAnkazobe
VohimarinaVohimarina
AmbilobeAmbilobe
MandritsaraMandritsaraMampikonyMampikony
BefandrianaBefandriana
BealananaBealanana
AmbanjaAmbanja
AmboasaryAmboasary
ToamasinaToamasina
AmbatondrazakaAmbatondrazaka
AntsirananaAntsiranana
MahajangaMahajanga
ToliaraToliara
FianarantsoaFianarantsoa
ManakaraManakara
FarafanganaFarafangana
AntsirabeAntsirabe
MorondavaMorondava
MiarinarivoMiarinarivoTsiroanomandidyTsiroanomandidy
SambavaSambava
AntsohihyAntsohihy
TolanaroTolanaroAmbovombeAmbovombe
IhosyIhosy
MaevatananaMaevatanana
AmbositraAmbositra
MaintiranoMaintirano
Fenoarivo-AtsinananaFenoarivo-Atsinanana
ANTANANARIVOANTANANARIVO
DIANADIANA
SAVASAVA
SOFIASOFIA
ANALANJIROFOANALANJIROFOBOÉNYBOÉNY
BETSIBOKABETSIBOKA
ANALAMANGAANALAMANGABONGOLAVABONGOLAVA
ITASYITASY
MELAKYMELAKYALAOTRAALAOTRA
MANGOROMANGORO
ATSINANANAATSINANANA
AMORON’I MANIAAMORON’I MANIA
HAUTE-MATSIATRAHAUTE-MATSIATRA
IHOROMBEIHOROMBEATSIMO-ATSIMO-
ANDREFANAANDREFANA
ANOSYANOSY
ANDROYANDROY
ATSIMO-ATSIMO-ATSINANANAATSINANANA
MENABEMENABE
VATOVAVY-VATOVAVY-FITOVINANYFITOVINANY
VAKINANKARATRAVAKINANKARATRA
MayotteMayotte(France)(France)
Ank
arat
a
Massi fMassi fTsaratananaTsaratanana
Androy Plateau
Cli
f f o
f A
ng
av
o
Cl i
f f o
f B o n g o l a
v a
MaromokotroMaromokotro(2,876 m)(2,876 m)
Pic BobyPic Boby(2,658 m)(2,658 m)
TsiafajovonaTsiafajovona(2,642 m)(2,642 m) Vatomandry
Mahanoro
Varika
Mananjary
Tsivory
Berakete
Beloha
Betroka
Manja
Mandabe
Morombe
Ankazoabo
Beroroha
Sakaraha
Betioky
Androka
Ampanihy
Midongy-Atsimo
Ambohimahasoa
Antalaha
Maroantsetra
Mananara
Moramanga
Antanifotsy
Ambatofinan-drahana
Miandrivazo
Malaimbandy
Belo Tsiribihina
Andilanatoby
Andilamena Soanierana-Ivongo
Andriamena
Soalala
Besalampy
Antsalova
Kandreho
Ankazobe
Vohimarina
Ambilobe
MandritsaraMampikony
Befandriana
Bealanana
Ambanja
Amboasary
Toamasina
Ambatondrazaka
Antsiranana
Mahajanga
Toliara
Fianarantsoa
Manakara
Farafangana
Antsirabe
Morondava
MiarinarivoTsiroanomandidy
Sambava
Antsohihy
TolanaroAmbovombe
Ihosy
Maevatanana
Ambositra
Maintirano
Fenoarivo-Atsinanana
ANTANANARIVO
DIANA
SAVA
SOFIA
ANALANJIROFOBOÉNY
BETSIBOKA
ANALAMANGABONGOLAVA
ITASY
MELAKYALAOTRA
MANGORO
ATSINANANA
AMORON’I MANIA
HAUTE-MATSIATRA
IHOROMBEATSIMO-
ANDREFANA
ANOSY
ANDROY
ATSIMO-ATSINANANA
MENABE
VATOVAVY-FITOVINANY
VAKINANKARATRA
Mayotte(France)
Mah
avav
y
Betsiboka
Bemarivo Sofia
LakeAlaotra
Mangoro Mania
Tsiribihina
Mananara
Onilahy
Man
drav
e
Mangoky
Fihere
chana
Menarand
ra
Manambaho
Mahajamba
I N D I A N
O C E A N
Mo z a m
b i q u e C
h a n n e l
Ank
arat
a
Massi fTsaratanana
Androy Plateau
Cli
f f o
f A
ng
av
o
Cl i
f f o
f B o n g o l a
v a
Maromokotro(2,876 m)
Pic Boby(2,658 m)
Tsiafajovona(2,642 m)
45°E 50°E
50°E
45°E
25°S
20°S
15°S
20°S
15°S
MADAGASCAR
0 40 80 120 160
0 120 Miles8040
200 Kilometers
IBRD 33439R
MAY 2011
MADAGASCAR
This map was produced by the Map Design Unit of The World Bank. The boundaries, colors, denominations and any other information shown on this map do not imply, on the part of The World Bank Group, any judgment on the legal status of any territory, o r any endo r s emen t o r a c c e p t a n c e o f s u c h boundaries.
SELECTED CITIES AND TOWNS
REGION CAPITALS
NATIONAL CAPITAL
RIVERS
MAIN ROADS
RAILROADS
REGION BOUNDARIES