Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
1947 Center Street Specification No. 16-10983-C Building Renovation Phase 2 Berkeley CA 94704 DOCUMENT 00900 ADDENDUM NO. 3 DIVISION 0 & 1 SPECIFICATIONS
1. Changes to Specifications: a. Document 00300 – a revised Bid Form is attached. b. Document 00430 – a revised Subcontractors List form is attached.
ARCHITECTURAL, MECHANICAL, AND ELECTRICAL See attached from Noll & Tam Architects and Planners. END OF DOCUMENT
Addenda (10-01) 00900 - 1
1947 Center Street Specification No. 16-10983-C Building Renovation Phase 2 Berkeley CA 94704 DOCUMENT 00300 BID FORM To be submitted by 2:00 p.m., on Tuesday, December 8, 2015. CITY OF BERKELEY
PURCHASING MANAGERS OFFICE Martin Luther King, Jr. Civic Center
2180 Milvia Street, Third Floor Berkeley, CA 94704
Telephone (510) 981-7320 Attn: Paul Kaushal, Project Manager Re: Specification No. 16-10983-C
CITY OF BERKELEY
1947 Center Street Building Renovation Phase 2
1. The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an agreement with the City of
Berkeley ("City") in the form included in the Contract Documents, Document 00510 Agreement, to perform and furnish all Work as specified or indicated in the Contract Documents for the Contract Sum and within the Contract Time indicated in this Bid and in accordance with all other terms and conditions of the Contract Documents.
2. Bidder accepts all of the terms and conditions of the Contract Documents and the Invitation to Bid and
Instructions to Bidders, including without limitation, those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for sixty (60) calendar days after the day of Bid Opening. Bidder will sign and submit the Agreement with Bonds and other documents required by Document 00100 Instructions to Bidders, within ten (10) business days after receipt of City's Notice of Intent to Award.
3. In submitting this Bid, Bidder represents: (a) Bidder has examined all of the Contract Documents and of the following Addenda (receipt of all of
which is hereby acknowledged). Date Number (b) Bidder has visited the site and performed all tasks, research, investigation, reviews, examinations,
analysis, and given notices, regarding the Project and the Site, as set forth in Document 00510 (Agreement), Article 5.
4. Based on the foregoing, Bidder proposes and agrees to fully perform the Work within the time stated and in
strict accordance with the Contract Documents for the following sum of money listed in the following Bid
Bid Form (10-01) 00300 - 1
1947 Center Street Specification No. 16-10983-C Building Renovation Phase 2 Berkeley CA 94704
Schedule:
SCHEDULE OF BID PRICES All bid items, including lump sums, unit prices, and additive alternates must be filled in completely. Quote in words and numerals. Scope of Work is listed in Section 01000 of the Contract Documents. TOTAL BASE BID: All labor, materials, services and equipment necessary for the completion of all of the Work shown in the attached plans, specifications and other Contract Documents, except for that work called for in the Additive Bid Items (if any): _____________________________________________________________Dollars $_______________________ ADDITIVE BID ITEM NO.1: All labor, materials, services and equipment necessary for the completion of the replacement of the existing Simplex Fire Alarm Panel at the Basement Main Electrical Room, as well as all related devices and wiring to and on the 5th and 6th floors. Replacement shall include removal of the existing system and devices and wiring (for the 5th and 6th floors), and installation of new devices and wiring at the 5th and 6th floors, to be tied to the new Siemens XLS System: _____________________________________________________________Dollars $_______________________ 5. Subcontractors and their sub-bids for work included in all bid items and additive or deductive alternates are
listed on the attached Document 00430 Subcontractors List. 6. The undersigned understands that City reserves the right to reject this Bid, but that this Bid shall remain open
and shall not be withdrawn for a period of sixty (60) calendar days from the date prescribed for its opening. 7. If written notice of the acceptance of this Bid, hereinafter referred to as Notice of Award, is mailed or delivered
to the Undersigned within sixty (60) calendar days after the date set for the opening of this Bid, or at any other time thereafter before it is withdrawn, the undersigned will execute and deliver the documents required by Document 00100 Instructions to Bidders including, but not limited to, Document 00510 Agreement, Document 00610 Performance Bond, and Document 00620 Labor and Material Bond, all within ten (10) business days after personal delivery or after receipt in the mails of the Notice of Intent to Award.
8. Notice of Award or request for additional information may be addressed to the undersigned at the address set
forth below. 9. The undersigned herewith encloses a cashier's check, certified check, or corporate surety bond in the amount of
ten percent (10%) of the total of the Total Base Bid and made payable to: City of Berkeley. 10. The undersigned agrees to commence work under this Contract on the date established in Document 00700
General Conditions and to complete all work within the time specified in Document 00510 Agreement.
Bid Form (10-01) 00300 - 2
1947 Center Street Specification No. 16-10983-C Building Renovation Phase 2 Berkeley CA 94704 11. The undersigned agrees that, in accordance with Document 00700 General Conditions, Paragraph 15.E,
liquidated damages for failure to complete all work in the contract within the time specified in Paragraph 10 above shall be as set forth in Document 00510 Agreement.
12. The names of all persons interested in the foregoing Bid as principals are:
(IMPORTANT NOTICE: If Bidder or other interested person is a corporation, give the legal name of corporation, state where incorporated, and names of president and secretary thereof; if a partnership, give name of the firm and names of all individual co-partners composing the firm; if Bidder or other interested person is an individual, give first and last names in full).
NAME OF BIDDER licensed in accordance with an act for the registration of Contractors, and with license number:
Signature of Bidder
NOTE: If Bidder is a corporation, set forth the legal name of the corporation together with the signature of the officer or officers authorized to sign contracts on behalf of the corporation. If Bidder is a partnership, set forth the name of the firm together with the signature of the partner or partners authorized to sign contracts on behalf of the partnership. Business Address:
_________________________________________________________ _________________________________________________________ _________________________________________________________
Telephone Numbers: _________________________________________________________ Date of Bid: ________________________________________________________________
END OF DOCUMENT
Bid Form (10-01) 00300 - 3
1947 Center Street Specification No. 16-10983-C Building Renovation Phase 2 Berkeley CA 94704 DOCUMENT 00430 SUBCONTRACTORS LIST Bidder submits the following information as to the subcontractors Bidder intends to employ if awarded the contract.
Name and Address of Subcontractor and
Location of Mill or Shop License Number
Description of Work: Reference to
Contract Items
Prices Under Subcontract
(Bidder to attach additional sheets if necessary) END OF DOCUMENT
Subcontractors List (10-02) 00430 - 1
1947 Center Street Building Renovation Phase 2
1947 Center Street, Berkeley, CA 94704
Addendum #3 Page 1 of 3 11/30/2015
BID ADDENDUM NO. 3
SUMMARY
The following enclosed substitutions, alterations, changes, clarifications, additions and/or deletions to the
plans and specifications are hereby made a part of the contract documents for the above project, and shall
conform with all applicable specifications and details contained herein. This Addendum is a Contract Document.
General
The following changes, additions and deletions shall be made to the following document(s); all other conditions
shall remain the same.
I. GENERAL & SPECIFICATIONS
Item Reference Description
1. Section 10 14 00 –
Signage and
Identification
Devices
Replace “10 14 00 Signage” with attached “Section 10 14 00 - Signage and
Identification Devices”
2. Section 22 00 50 –
Basic Plumbing
Materials &
Methods
Replace previous specification with attached specification Section 22 00 50
which includes basic plumbing materials and methods pertaining to plumbing
systems.
3. Section 22 10 00 –
Plumbing Piping
Systems
Replace previous specification with attached specification Section 22 10 00
which includes plumbing waste, water, and vent piping, and fittings.
4. Section 22 40 00 –
Plumbing Fixtures
Replace previous specification with attached specification Section 22 40 00
which includes fixtures manufacturers, trims and installation etc. Proposed
fixtures are noted on plumbing scheduled sheet P0.2.2 with all connecting
vent, waste and water pipe sizes listed.
II. DRAWINGS
Item Reference Description
1. A1.10.2-A1.14.2 Add General Note ”9. Remove gyp and replace as required to complete work
associated with detail 1/E7.11.2” (sheets not issued)
2. A1.23.2 Add (E) ceiling fan locations.
3. A2.20.2-A2.24.2 Add General Note “14. Patch and repair wall finishes for work at power and
data locations associated with electrical work, SED.” (sheets not issued)
4. A2.43.2 Add (E) ceiling fan locations.
5. A4.01.2 Detail 3/4.01.2, reverse restroom partition door swing.
6. A4.02.2 Detail 4/4.02.2, reverse restroom partition door swing.
7. A4.12.2 Revise keynote 6-07, add keynote 6-17, update permit counter casework design
per details 1, 2, 3, and 4.
8. A4.13.2 Revise Permit Center casework per Details 1, 2W, 5. Add callout 6/A8.51.2 to
detail 1.
9. A5.02.2 Revise detail 2S, 2W, 3 to include updated casework references on sheet
A5.02.2.
1947 Center Street Building Renovation Phase 2
1947 Center Street, Berkeley, CA 94704
Addendum #3 Page 2 of 3 11/30/2015
10. A7.03.2 Add detail 6/A7.03.2 to show the transition from the proposed guardrail to the
existing conditions to remain.
12. A8.51.2 Add detail 6/A8.51.2 – Display Casework. This detail is referenced on
1/A4.13.2. Revise detail 9/A8.51.2 with updated dimensions.
13. A8.52.2 Revise details 1, 6, 10, 12/A8.52.2 to show updated casework design. Add
Detail 11/A8.52.2.
14. A8.54.2 Revise connection notes at detail 9/A8.54.2
15. A8.55.2 Revise notes at details 1, 2, 3, 4, 5, and 7 on A8.55.2
16. A10.20.2 Add specified required U-Factor, RSHG and VT requirements for glazing, add
reference to Hardware group information in specifications.
17. A10.25.2 Add specified required U-Factor, RSHG and VT requirements for glazing .
18. P0.2.2 Add General Note 4 to read “Refer to specification sections 22 00 50, 22 10 00,
and 22 40 00 for sanitary sewer, sanitary venting, and water distribution system
configuration and sizes. (sheet not issued)
19. P1.10.2 Provide pipe sizes of the existing waste piping system.
20. P2.20.2 Provide pipe sizes of the existing waste piping system to be connected to new
waste piping. Connecting Vent, hot, and cold water pipes are already noted on
plan.
21. P2.23.2 Add Note 1 to fixture SS-1.
III. CLARIFICATIONS TO PRE-BID QUESTIONS
1.
We need either the specifications for your
locks/keyways, or a photo of key (both sides)
and lock core. Could you provide us with this
info so we can properly bid phase 2?
See attached photos of existing lock cores,
contractor to field verify.
2. Specs call out to match species of existing
doors for phase 2. Do you know the specs on
these doors?
See attached photos of existing door wood species
to match, contractor to field verify.
3. Could you tell me what goes back or what is
getting installed back on all flooring? carpet?
or Linoleum? the reason I ask is because demo
drawings indicate to remove flooring and
adhesive in preparation to received new
flooring, I am just trying to figure how clean we
have to leave the concrete floor from adhesive,
please advise.
Refer to Room Finish Schedule, sheets A10.30.2 –
A10.31.2, and Finish Plans, sheets A10.40.2-
A10.44.2 for new flooring, specification Sections 09
68 13 Tile Carpeting 3.02 C, and Section 09 65 00
Resilient Flooring 3.01 B.
4. Will CAD files or Architectural plans be made
available for the fifth and sixth floor to the
successful low bidding fire sprinkler contractor?
Architectural floor plans will be available.
IV. ATTACHMENTS
Section 10 14 00 Signage and Identification Devices
1947 Center Street Building Renovation Phase 2
1947 Center Street, Berkeley, CA 94704
Addendum #3 Page 3 of 3 11/30/2015
Section 22 00 50 Basic Plumbing Materials & Methods
Section 22 10 00 Plumbing Piping Systems
Section 22 40 00 Plumbing Fixtures
A1.23.2 Third Floor Demo RCP
A2.43.2 Third Floor RCP
A4.01.2 Enlarged Demo and Floor Plans - Restrooms
A4.02.2 Enlarged Demo and Floor Plans - Restrooms
A4.12.2 Enlarged Plans - Permit Center
A4.13.2 Enlarged Elevations – Permit Center
A5.02.2 Interior Elevation – First Level
A7.03.2 Stair Details – Signage and Finishes
A8.51.2 Interior Details - Casework
A8.52.2 Interior Details – Casework Permit Center
A8.54.2 Interior Details – Misc Details
A8.55.2 Interior Details – Restroom Details
A10.20.2 Door Schedule
A10.25.2 Main Entry Door Details
P1.10.2 Basement Plumbing Demo Plan
P2.20.2 Basement Plumbing Floor Plan
P2.23.2 Third Floor Plumbing Plan
Existing Door Hardware Images.pdf Example images of existing door hardware
Existing Door Images.pdf Example images of existing door finishes by floor
END OF ADDENDUM 3
CITY OF BERKELEY Specification No. 16-10983-C 1947 CENTER STREET BUILDING RENOVATION PHASE 2 Berkeley, California 94704
Signage and Identification Devices
(11-30-15) 10 14 00 - 1
SECTION 10 14 00
SIGNAGE AND IDENTIFICATION DEVICES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes provisions of exterior and interior signage including, but not limited to: 1. Building title, address, and Hours of Operation. 2. Code-required signage per CBC, ADA and Title 24. 3. Fire and life safety signage per CFC. 4. Lobby wayfinding and stairwell identification. 5. Visitor, administrative, and staff-oriented signage. 6. Directory or orientation display signage, counter information. 7. Directional, informational, and operational signage. 8. Area identification and information desk signage.
B. Section includes: 1. Providing interior and exterior identifying devices where indicated on the Drawings
complete and in place. 2. Providing all engineering of sign and graphic items including, but not limited to internal
structure and mechanical parts. 3. Providing all submittals and prototypes with copy. 4. Obtaining all government and agency approval as necessary. 5. Coordination with related trades as necessary, including structural, electrical, lighting,
casework and cabinetry work. 6. Providing all necessary services, labor, materials, insurance, barricades and safety
devices, and products to fabricate and install, remove or relocate any or all sign and/or graphic items included in the documents.
C. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this section.
D. Related Sections 1. 06 20 23: Interior Finish Carpentry 2. 06 40 23: Interior Architectural Woodwork 3. 08 11 13: Hollow Metal Doors and Frames 4. 08 14 16: Flush Wood Doors 5. 08 45 11: Translucent Linear Channel Glazing System 6. 08 62 00: Unit Skylights 7. 09 29 00: Gypsum Board
CITY OF BERKELEY Specification No. 16-10983-C 1947 CENTER STREET BUILDING RENOVATION PHASE 2 Berkeley, California 94704
Signage and Identification Devices
(11-30-15) 10 14 00 - 2
1.2 REFERENCES
A. ADA: Americans with Disabilities Act.
B. CBC: California Building Code, 2015 Edition.
C. T24: California Title 24.
D. CFC: California Fire Code.
1.3 SYSTEM DESCRIPTION
A. Design Requirements: Design all signs as indicated and to meet ADA, CBC, and Title 24 requirements. In the event a conflict is encountered between the contract documents and either of these codes, submit a proposed solution to the Architect for approval prior to fabricating signs.
1.4 QUALITY ASSURANCE
A. Regulatory Requirements Sections 1. Comply with ADA and CBC Braille signage requirements.
1.5 SUBMITTALS
A. Product Data: Submit manufacturers’ catalog sheets, brochures, diagrams, schedules, charts, illustrations, test results and/or other standard descriptive data. 1. Mark up each copy to identify pertinent materials, products or models. 2. Show dimensions and clearances required, performance characteristics and capabilities,
and wiring diagrams and/or controls as applicable.
B. Shop Drawings: 1. All shop drawings shall be neat, well organized and clearly legible. Elevations and plan
views from the Construction Drawings may be reproduced for the sake of expedience where appropriate.
2. All shop drawings shall be drawn to scale and not subsequently reduced to fit a drawing format.
3. Submit elevations and plan views for all sign types, including graphic layouts, complete dimensions, materials, locations of all exposed fasteners, colors and finishes. Determine the total quantity for each sign type and note it in the shop drawings.
4. Submit comprehensive section drawings for sign types where applicable, including sections of all typical members. Show fabrication and installation details, including details for securing members to one another, to building structures, and/or to site work. Show interior construction, reinforcements, anchorages, components and finishes. Reproduction of section drawings shown in Construction Drawings shall not be acceptable.
5. Site Condition Verification: Where required by the Architect for specific items, Contractor shall inspect site to confirm installation conditions, then submit shop
CITY OF BERKELEY Specification No. 16-10983-C 1947 CENTER STREET BUILDING RENOVATION PHASE 2 Berkeley, California 94704
Signage and Identification Devices
(11-30-15) 10 14 00 - 3
drawings and/or written documentation for approval indicating proposed mounting devices.
6. Exact replications of Bid documents will be rejected. 7. Fasteners: Detail methods of fastenings and provide exact specifications for all fasteners
noted on shop drawings. 8. Sign location: Provide Graphic Schedule and location plans to identify and locate all
signs. Item numbers listed in the Graphic Schedule shall be found on location plans and shall identify locations of specific sign items.
C. Samples: 1. Color and Finish: Submit 3 each, 6 inch by 6 inch samples of all paint
colors, screen colors, vinyl colors and material finishes. All paint and screen colors are to be applied to the appropriate substrate.
2. Contractor to submit verification of paint manufacturer used for submittal. 3. Prior to submittal, Contractor shall verify that all colors submitted as samples match
accurately the samples or specifications provided by Architect. 4. Typeface(s): Submit complete typeface font(s), including upper and lower case letters,
numbers and punctuation, for all typeface(s) specified. Include typeset “City of Berkeley 1947 Center Street”. Also submit samples of letter and word spacing for each cap height specified. Architect to provide all necessary fonts and electronic vector (Adobe Illustrator EPS) artwork where necessary.
5. Provide listing of the material and application for each coat of each finish sample. 6. Acrylic: Submit color and finish samples of plastics for approval before proceeding with
fabrication. No substitution in color, thickness, finish or plastics will be accepted without written approval of the Architect.
D. Prototypes 1. Prototypes: Submit one full-size complete prototype each for the following Sign Types: 2. 1 flat cut-out bronze letter 3. 1 room identification sign 4. 1 3Form counter identification sign 5. 1 metal sign with cutout letterforms 6. 1 3Form wayfinding directional sign 7. Vinyl samples 8. Additional samples and prototypes as requested.
E. Patterns 1. Submit one full size pattern for each sign type. All patterns shall be printed on a
single carrier sheet and shall include the perimeter of the sign panel.
F. Quality Control 1. Samples and prototypes may be permanently installed if approved, unless
otherwise noted by the Architect. 2. If requested by Architect, submit manufacturer’s installation instructions for each type of
specialty sign. Include only relevant pages, or manufacturer’s standard drawings modified to delete non-applicable data.
CITY OF BERKELEY Specification No. 16-10983-C 1947 CENTER STREET BUILDING RENOVATION PHASE 2 Berkeley, California 94704
Signage and Identification Devices
(11-30-15) 10 14 00 - 4
3. Pre-Installation Conferences: Sign location shown on the location plans are for general information only. Prior to installation and as required, arrange meetings with the Architect and COB at the site for final location for all sign items.
1.6 QUALITY ASSURANCE
A. Do not scale drawings for dimensions. Use only the written dimension indicated on the Drawings, unless such is to be found in error. Contractor shall verify and be responsible for all dimension and conditions shown by the Drawings, and shall visit the site to inspect and verify field conditions prior to fabrication and installation. The Architect shall be notified, in writing, of all discrepancies on the Drawings, in field dimensions or conditions, and of changes required in construction details.
B. Provide each type of sign as a complete unit produced by a single manufacturer, including all required mounting accessories, fittings and fastenings.
C. All details shown in the Drawings shall be followed for exterior appearance. Minor changes in interior construction will be accepted in order to conform to Contractor’s shop practices or engineering requirements when, in the Architect’s sole judgment, such changes do not detract materially from design concept or intent. Contractor shall circle all such changes on the shop drawings.
D. Completed work shall be structurally sound, and free from scratches, distortions, chips, breaks, blisters, holes, splits or other disfigurements considered as imperfections for the specific material.
PART 2 - PRODUCTS
2.1 ACCEPTABLE SIGN FABRICATORS
A. VKK Signs 812 Sweeney Avenue, Redwood City CA 94063 650-368-3688 Dan Kitzmiller
B. Lahue & Associates 2280 Palou Avenue, San Francisco CA 94124 415-206-9136 John Gallagher
C. Martinelli Environmental Graphics 1829 Egbert Avenue, San Francisco, CA 94124 415-468-4000 Jeff Osicka
CITY OF BERKELEY Specification No. 16-10983-C 1947 CENTER STREET BUILDING RENOVATION PHASE 2 Berkeley, California 94704
Signage and Identification Devices
(11-30-15) 10 14 00 - 5
D. The proposed substitution of other sign fabricators for those listed above may be considered by the Architect if said sign fabricator(s): 1. Demonstrates that his/her applicable product(s) are equal in salient characteristics such as
construction, quality, durability, appearance and warranty to those of the acceptable sign fabricators listed.
2. Supplies three positive references for comparable work.
2.2 MATERIALS
A. Plastic signs for general Room ID signage: Matte finish acrylic plastic, minimum 1/8-in thick, without frame, with corner radiused. Message and background color shall be sub-surface printed. Provide with raised room numbers and Braille. 1. Mounting tape: Double-sided vinyl foam tape, “VHB” by 3M, or equal. Provide silicone
adhesive for attachment to wall surface. 2. Fasteners: Where fasteners are indicated or required, use exposed “torx type” tamper-
proof security screws. 3. Coatings for Acrylic Plastic Sheet: Use colored coatings, including inks and paints for
copy and background colors, that are recommended by acrylic manufacturers for optimum adherence to acrylic surface and are non-fading for the application intended.
4. Acrylic Signs: comply with requirements indicated for materials, thickness, finishes, colors, designs, shapes and sizes, and details of construction.
5. Unframed Acrylic signs: Fabricate signs with edges mechanically and smoothly finished to conform with the following requirements: a. Edge conditions: square cut b. Corner conditions: ½” in radius
6. Produce smooth, even, level sign panel surfaces, constructed to remain flat under installed conditions within a tolerance of plus or minus 1/16-inch measured diagonally.
7. Graphic Content and Style: Provide sign copy that complies with the requirements indicated for size, style, spacing, content, position, material, finishes and colors of letters, numbers and other graphic devices.
8. Photopolymer (raised copy): Machine-cut copy characters from matte finish opaque acrylic sheet and chemically weld onto the acrylic sheet forming sign panel face. Produce precisely formed characters with square cut edges free from burrs and cut marks. a. Panel Material: Matte-finished acrylic stock with opaque color coating surface
applied; 2 colors, minimum 70 percent contrast between color 1 and 2. b. Raised Copy Thickness: Not less than 1/32-inch.
B. Aluminum 1. Flat Sheet or Barstock for all work as required, brushed finish fine #6.
C. Cast Acrylic Sheet 1. Provide cast (not extruded or continuous cast) methyl plastic sheet, in sizes, thickness and
finishes indicated, with an minimal flexural strength of 16,000 pounds per square inch when tested in accordance with ASTM D790, and a maximum allowable continuous service temperature of 176 degrees Fahrenheit.
CITY OF BERKELEY Specification No. 16-10983-C 1947 CENTER STREET BUILDING RENOVATION PHASE 2 Berkeley, California 94704
Signage and Identification Devices
(11-30-15) 10 14 00 - 6
2. Cast acrylic sheet shall have a flame resistance such that application of a lighted match shall not produce melting, flashing, flaring or distortion. This material shall not ignite at a temperature less than 800 degrees Fahrenheit.
3. Carefully follow manufacturer’s recommended fabrication procedures regarding expansions/contractions, fastening and restraining of acrylic plastic.
D. Braille 1. Contractor shall be responsible for the accurate translation of all applicable tactile copy to
Contracted Grade 2 Braille upper and lower case. All Braille shall be produced in accordance with California Title 24 requirements: Dots shall be 1/10 inch (2.54 mm) on centers in each cell with 2/10 inch (5.08 mm) space between cells. Dots shall be raised on a minimum of 1/40 inch (0.635 mm) above the background.
E. Applied Tactile Copy 1. Contractor shall provide 1/32” Rowmark ADA Alternative Applique in color called out
in the construction drawings. No substitutions on this item, which is available through: Laminated Fabricators 1145 San Mateo Avenue, San Bruno, CA 94066 (800) 526-3225
F. Fasteners, Hardware and Devices: Stock proprietary fastening devices approved standard manufacture such as cadmium plated screws, bolts and washers, and stainless steel hinges. Use SST fasteners where specified. 1. Conceal all fasteners expect where noted or shown otherwise. 2. Finish on all exposed devices to match overall sign finish, unless otherwise noted. 3. Provide vandal-resistant fasteners at all exposed locations unless otherwise noted. 4. Use fasteners fabricated from metals that are noncorrosive to either the sign material(s) or
mounting surface.
G. Very High Bond Tape 1. Provide #4905/.020”/clear and/or #4950/.045”/white closed cell acrylic foam carrier with
VHB adhesive, very high solvent resistance and very high shear and peel adhesion, as manufactured by 3M Scotch or approved equal.
H. Acrylic Polyurethane Paint 1. Provide acrylic polyurethane with ultraviolet inhibitors and lightfast, weather, abrasion
and graffiti resistant additives as manufacturer’s: Matthews Paint Company (800) 323-6593.
2. Prime and finish coats shall be mixed and applied in accordance with manufacturer’s specifications. Paint finish shall be smooth, free of scratched, gouges, drops, bubbles, thickness variations, foreign matter or other imperfections.
3. Provide as CCR Title 24-compliant non-glare finish for all interior applications. 4. Provide semi-gloss finish for all exterior applications.
I. Screen Media
CITY OF BERKELEY Specification No. 16-10983-C 1947 CENTER STREET BUILDING RENOVATION PHASE 2 Berkeley, California 94704
Signage and Identification Devices
(11-30-15) 10 14 00 - 7
1. Screened graphics shall be produced with screening ink or paint compatible with substrate, using mesh of 390 or finer to produce clean, sharp edges. Media must be opaque, with full even coverage, and free from hickeys, dust, bubbles and/or other blemishes or foreign matter.
J. Vinyl Film 1. Provide opaque reflective or non-reflective vinyl film as indicated, 0.0355 minimum
thickness, with pressure sensitive permanent adhesive backing; 3M Scotchcal or approved equal.
2. All colors shall be integral and not surface applied expect where custom color(s) are specified in the Drawings. All custom colors shall be flood coated on white vinyl.
K. 3Form 1. Provide 3Form in color called out in the construction drawings. No substitutions on this
item, which is available through: Debra Williges 3-Form.com 801.649.2665 415.710.9440 [email protected]
2.3 FABRICATION
A. Intent of Specifications: All finished work shall be of the highest quality in order to pass eye-level examination and scrutiny by Architect. 1. All Work shall be free from burrs, dents, raw edges and sharp corners. 2. Finish all welds on exposed surfaces as required so they are not visible in the finished
Work. 3. Finish all surfaces smooth unless otherwise indications or specified. 4. Surfaces which are intended to be flat shall be free from bulges, oil canning, gaps or other
physical deformities. Such surfaces shall be fabricated to remain flat under installed conditions.
5. Surfaces which are intended to be curved shall be smoothly free-flowing to the required shape(s).
6. Fabricate all cabinets, panels and components with smooth, mechanically finished edges. All edges shall be true, and all corners shall be square. Where edges are specified to be painted, fill and sand smooth as required prior to painting.
7. Cut routed letterforms and/or graphics clean and true to match adjacent surface-applied letterforms and/or graphics.
8. Exercise care to protect all polished and/or plated surfaces so that they remain unblemished in the finished Work.
9. Isolate dissimilar materials. Exercise particular care to isolate nonferrous metals from ferrous metals as required to prevent corrosion.
10. All surfaces shall be flat to a tolerance of plus or minus 1/16’ when measured at any point with a ten-foot straight edge.
CITY OF BERKELEY Specification No. 16-10983-C 1947 CENTER STREET BUILDING RENOVATION PHASE 2 Berkeley, California 94704
Signage and Identification Devices
(11-30-15) 10 14 00 - 8
11. All visible sign surfaces of the same type shall have the same finish. Color and/or finish shall be consistent across the entire surface of a sign.
12. All reveals shall be uniform width; all butt joints shall be tight and closed along the entire length; all access panels shall have a nominal, uniform gap all around.
13. All expansion joints, when required, shall be positioned so as not to interfere with the look or finish of any sign message or the overall appearance of the sign face.
14. All gaps between milled components, when assembled, shall not exceed a tolerance of .005.”
B. Provide colors and/or finish textures as specified or indicated in the Drawings or, where not specified or indicated, as selected by Architect. 1. Interior Colors/Finishes: Colors of sign graphics (text, arrows and/or symbols) shall have
a minimum of 70% contrast with sign background behind graphics. 2. Finish shall be non-glare on all sign backgrounds behind graphics on identifications and
directional signs.
C. Graphics 1. All text, arrows and symbols shall be provided in the sizes, colors, typefaces
and spacing specified in the Drawings. 2. All text shall be a true, clean, digitally or photomechanically accurate reproduction of the
typeface(s) specified, with letterspacing and directional arrows as shown in the Drawings. 3. Lettering & Custom Typography: use Macintosh OSX fonts and digital files provided by
Architect. 4. Arrows and Symbols: Use digital files provided by Architect in Adobe Illustrator CS5 for
Macintosh. 5. Custom shapes and graphics: Use digital files provided by Architect in
Adobe Illustrator CS5 for Macintosh.
D. Sign Schedule
E. Digital Artwork 1. All digital artwork files prepared by the Architect for the Contractor’s use shall be in a
single layer. 2. Any and all manipulations of the files requires for subsequent use by the Contractor, such
as spreads and traps for silkscreen negatives, or conversion to outline or EPS, shall be the responsibility of the same unless explicitly agreed otherwise by the Architect.
PART 3 - EXECUTION
3.1 INSPECTION
A. Architect reserves the right to inspect the Work in the Contractor’s shop before it is shipped to the job site for installation.
B. Contractor shall inspect all installation locations for conditions which will adversely affect the execution, performance and/or quality of the Work, and notify Architect in writing of any and
CITY OF BERKELEY Specification No. 16-10983-C 1947 CENTER STREET BUILDING RENOVATION PHASE 2 Berkeley, California 94704
Signage and Identification Devices
(11-30-15) 10 14 00 - 9
all unsatisfactory conditions. Contractor shall not proceed with installation until said unsatisfactory conditions have been corrected. Commencement of the installation indicated acceptance of the site conditions and guarantees delivery of an acceptable product.
3.2 INSTALLATION
A. Pre-installation Walkthrough/Field-Staking 1. Attend a pre-installation walkthrough at the job site to confirm all typical installation
conditions and determine installation locations for non-typical conditions. 2. The exact locations of all exterior signs will be determined and field-staked at this time.
B. General 1. Install signage in neat and proper manner. 2. Install sign items, including all components, in accordance the reviewed Graphic
Schedule at locations shown. 3. Install signs properly aligned, level and true to line and dimension.
C. Install with reviewed manufacturer’s adhesive or mechanical fasteners after application of finish paintings at heights noted.
3.3 SIGN LOCATIONS
A. All signs identifying permanent rooms and spaces shall be located in compliance with CBC 11B-703. Sign to be located at latch side of door, or, if there is insufficient wall space, on the nearest wall, preferably to the right.
B. Symbol signs on restroom doors shall be located in compliance with CBC 11B-703.7.2.6.
3.4 SITE CLEANUP
A. Final Cleanup 1. Clean and /or repair all evidence of installation work or damage to site work
or other adjacent surfaces prior to completion of work. 2. Clean up work area after all installation have been completed. 3. Restore all disturbed ground cover. 4. Remove all protective materials and dispose of properly off site.
3.5 CLEANING AND PROTECTION
A. At completion of installation, clean all sign surfaces in accordance with manufacturer’s instructions.
B. Protect all signs from damage until acceptance by Architect; repair or replace damaged units as required.
CITY OF BERKELEY Specification No. 16-10983-C 1947 CENTER STREET BUILDING RENOVATION PHASE 2 Berkeley, California 94704
Signage and Identification Devices
(11-30-15) 10 14 00 - 10
C. Clean and/or repair all evidence of installation work or damage to adjacent surfaces prior to completion of work.
D. Remove all protective materials and dispose of properly off site.
3.6 CONTRACT CLOSE-OUT ITEMS
A. Provide Owner with one quart paint for each paint color specified.
B. Provide Owner with written instructions for proper cleaning of the signs.
C. Note any solvents that should not be used.
END OF SECTION 10 14 00
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 1
SECTION 22 00 50 - BASIC PLUMBING MATERIALS AND METHODS
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Valves and fittings.
B. Gauges.
C. Thermometers.
D. Access Doors.
E. Expansion loops.
F. Flexible joints.
G. Insulation.
1.2 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
B. This Section is a part of each Division 22 Section.
1.3 ADDITIONAL REQUIREMENTS
A. Furnish and install any incidental work not shown or specified which is necessary to provide a
complete and workable system.
B. Make all temporary connections required to maintain services during the course of this Contract
without additional cost to the Owner. Notify the Owner seven days in advance before
disturbing any service.
1.4 REFERENCED STANDARDS
A. Where material or equipment is specified to conform to referenced standards, it shall be
assumed that the most recent edition of the standard in effect at the time of bid shall be used.
1. CSA – Canadian Standards Association International
2. ANSI - American National Standards Institute
3. ASTM - American Society for Testing and Materials
4. CCR - California Code of Regulations
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 2
a. Title 8 - Division of Industrial Safety, Subchapter 7; General Industry Safety
Orders, Articles 31 through 36
5. NCPWB - National Certified Pipe Welding Bureau
6. CEC - California Electrical Code
7. NEMA - National Electrical Manufacturers' Association
8. NFPA - National Fire Protection Association
9. OSHA - Occupational Safety and Health Act
10. UL - Underwriters' Laboratories, Inc.
1.5 DRAWINGS
A. Examine Contract Documents prior to bidding of work and report discrepancies in writing to
Architect.
B. Contractor shall visit Project site and examine existing conditions in order to become familiar
with Project scope. Verify dimensions shown on Drawings at Project site. Bring discrepancies
to the attention of Architect. Failure to examine Project site shall not constitute basis for claims
for additional work because of lack of knowledge or location of hidden conditions that affect
Project scope.
C. Drawings showing location of equipment and materials are diagrammatic and job conditions
will not always permit installation in location shown. The Plumbing Drawings show general
arrangement of equipment and materials, etc., and shall be followed as closely as existing
conditions, actual building construction, and work of other trades permit.
1. Architectural and Structural Drawings shall be considered part of the Work. These
Drawings furnish Contractor with information relating to design and construction of the
Project. Architectural Drawings take precedence over Plumbing Drawings.
2. Because of the small scale of Plumbing Drawings, not all offsets, fittings, and accessories
required are shown. Investigate structural and finish conditions affecting the Work and
arrange Work accordingly. Provide offsets, fittings, and accessories required to meet
conditions. Inform Architect immediately when job conditions do not permit installation
of equipment and materials in the locations shown. Obtain the Architects approval prior
to relocation of equipment and materials.
3. Relocate equipment and materials installed without prior approval of the Architect.
Remove and relocate equipment and materials at Contactors’ expense upon Architects’
direction.
4. Minor changes in locations of equipment, piping, etc., from locations shown shall be
made when directed by the Architect at no additional cost to the Owner providing such
change is ordered before such items of work, or work directly connected to same are
installed and providing no additional material is required.
D. Execute work mentioned in Specifications and not shown on Drawings, or vice versa, the same
as if specifically mentioned or shown in both.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 3
1.6 REQUIREMENTS OF REGULATORY AGENCIES
A. The publications listed below form part of this specification; comply with provisions of these
publications except as otherwise shown or specified.
1. California Building Code, 2013
2. California Electrical Code, 2013
3. California Energy Code, 2013
4. California Fire Code, 2013
5. California Green Building Standards Code, 2013
6. California Mechanical Code, 2013
7. California Plumbing Code, 2013
8. California Code of Regulations, Title 24
9. California Health and Safety Code
10. CAL-OSHA
11. California State Fire Marshal, Title 19 CCR
12. National Fire Protection Association
13. Occupational Safety and Health Administration
14. Other applicable state laws
B. Nothing in Drawings or specifications shall be construed to permit work not conforming to
these codes, or to requirements of authorities having jurisdiction. It is not the intent of
Drawings or specifications to repeat requirements of codes except where necessary for clarity.
C. Comply with State of California 2013 Energy Code for all systems, equipment, and
construction.
D. When Contract Documents differ from governing codes, furnish and install larger size or higher
standards called for without extra charge.
E. No material installed as part of this Work shall contain asbestos.
1.7 FEES AND PERMITS
A. Obtain and pay for all permits and service required in installation of this work; arrange for
required inspections and secure approvals from authorities having jurisdiction. Comply with
requirements of Division 01.
B. Arrange for utility connections and pay charges incurred, including excess service charges.
1.8 UTILITY CONNECTIONS
A. Bear the cost of construction related to utility services, from point of connection to utility
services shown on Contract Documents. This includes piping, excavation, backfill, meters,
boxes, check valves, backflow prevention devices, general service valves, concrete work, and
the like, whether or not Work is performed by Contractor, local water/sanitation district, public
utility, other governmental agencies or agencies’ assigns.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 4
1.9 FRAMING, CUTTING AND PATCHING
A. Special framing, recesses, chases and backing for Work of this Section, unless otherwise
specified, are covered under other Specification Sections.
B. Contractor is responsible for placement of pipe sleeves, hangers, inserts, supports, and location
of openings for the Work.
C. Cutting, patching, and repairing of existing construction to permit installation of equipment, and
materials is the responsibility of Contractor. Repair or replace damage to existing work with
skilled mechanics for each trade.
D. Cut existing concrete construction with a concrete saw. Do not utilize pneumatic devices.
E. Core openings through existing construction for passage of new piping and conduits. Cut holes
of minimum diameter to suit size of pipe and associated insulation installed. Coordinate with
building structure, and obtain Structural Engineer's approval prior to coring through existing
construction.
1.10 SUBMITTALS
A. Submittal packages may be submitted via email as PDF electronic files, or as printed packages.
PDFs shall be legible at actual size (100 percent). Provide seven copies of printed submittal
packages.
B. Provide submittal of materials proposed for use as part of this Project. Product names in
Specifications and on Drawings are used as standards of quality. Furnish standard items on
specified equipment at no extra cost to the Contract regardless of disposition of submittal data.
Other materials or methods shall not be used unless approved in writing by Architect.
Architect's review will be required even though "or equal" or synonymous terms are used.
Refer to Division 01 for complete instructions.
1. Partial or incomplete submittals will not be considered.
2. Quantities are Contractor's responsibility and will not be reviewed.
3. Provide materials of the same brand or manufacturer for each class of equipment or
material.
4. Identify each item by manufacturer, brand, trade name, number, size, rating, or other data
necessary to properly identify and review materials and equipment. Words "as specified"
are not sufficient identification.
5. Identify each submittal item by reference to items’ Specification Section number and
paragraph, by Drawing and detail number, and by unit tag number.
6. Organize submittals in same sequence as in Specification Sections.
7. Show physical arrangement, construction details, finishes, materials used in fabrications,
provisions for piping entrance, access requirements for installation and maintenance,
physical size, mechanical characteristics, foundation and support details, and weight.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 5
a. Submit Shop Drawings, performance curves, and other pertinent data, showing
size and capacity of proposed materials.
b. Specifically indicate, by drawn detail or note, that equipment complies with each
specifically stated requirement of Contract Documents.
c. Drawings shall be drawn to scale and dimensioned (except schematic diagrams).
Drawings may be prepared by vendor but must be submitted as instruments of
Contractor, thoroughly checked and signed by Contractor before submission to
Architect for review.
d. Catalog cuts and published material may be included with supplemental scaled
drawings.
C. Review of submittals will be only for general conformance with design concept and general
compliance with information given in Contract Documents. Review will not include quantities,
dimensions, weights or gauges, fabrication processes, construction methods, coordination with
work of other trades, or construction safety precautions, which are sole responsibility of
Contractor. Review of a component of an assembly does not indicate acceptance of an
assembly. Deviations from Contract Documents not clearly identified by Contractor are
Contractor’s responsibility and will not be reviewed by Architect.
D. Within reasonable time after award of contract and in ample time to avoid delay of construction,
submit to Architect Shop Drawings or submittals on all items of equipment and materials
provided. Provide submittal in at least seven copies and in complete package.
1. Shop Drawings and submittals shall include Specification Section, Paragraph number,
and Drawing unit symbol or detail number for reference. Organize submittals into
booklets for each Specification section and submit in loose-leaf binders with index.
Deviations from the Contract Documents shall be prominently displayed in the front of
the submittal package and referenced to the applicable Contract requirement.
E. Furnish to the Project Inspector complete installation instructions on material and equipment
before starting installation.
F. Product Data for California Green Building Standards Code Compliance: For adhesives and
sealants, including primers, documentation of compliance including printed statement of VOC
content and chemical components.
G. Provide product data for insulation products, including insulation, insulation facings, jackets,
adhesives, sealants, and coatings, indicating compliance with requirement that these products
contain less than 0.1 percent (by mass) polybrominated diphenyl ethers (PBDEs) in penta, octa,
or deca formulations.
H. Pipe, pipe or plumbing fittings, fixtures, solder and flux installed in a system providing water
for human consumption shall comply with lead free requirements of the California Health and
Safety Code Section 116875. Provide submittal information for products third-party certified
by an approved laboratory as complying with California Health and Safety Code Section
116875.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 6
I. Delegated-Design Submittal: For seismic supports, anchorages, and restraints indicated to
comply with performance requirements and design criteria.
1. Calculations performed for use in selection of seismic supports, anchorages, and
restraints shall utilize criteria indicated in Structural Contract Documents.
2. Supports, anchorage and restraints for piping, ductwork, and equipment shall be an
OSHPD pre-approved system such as Tolco, Afcon, ISAT, Badger, Mason, or equal.
Pipes, ducts and equipment shall be seismically restrained in accordance with
requirements of current edition of California Building Code. System shall have current
OPM number and shall meet additional requirements of authority having jurisdiction.
Provide supporting documentation required by the reviewing authority and the Architect
and Engineer. Provide layout drawings showing piping, ductwork and restraint locations.
a. Bracing of Piping and Equipment: Specifically state how bracing attachment to
structure is accomplished. Provide shop drawings indicating seismic restraints,
including details of anchorage to building. In-line equipment must be braced
independently of piping, and in conformance with applicable building codes.
Provide calculations to show that pre-approval numbers have been correctly
applied in accordance with general information notes of pre-approval
documentation. Gas pipe bracing shall be designed in accordance with California
Building Code Section 1615A.1.22 and ASCE 7- Section 13.6. Coefficient Ip =
1.5 shall be used for gas piping bracing calculations.
3. In lieu of the above or for non-standard installations not covered in the above pre-
approved systems, Contractor shall provide layout drawings showing piping, ductwork,
and restraint locations, and detail supports, attachments and restraints, and furnish
supporting calculations and legible details sealed by a California registered structural
engineer, in accordance with 2013 California Building Code
4. Additional Requirements: In addition to the above, conform to all state and local
requirements.
1.11 SUBSTITUTIONS
A. Refer to Division 01 for complete instructions. Requirements given below are in addition to or
are intended to amplify Division 01 requirements. In the case of conflict between requirements
given herein and those of Division 01, Division 01 requirements shall apply.
B. It is the responsibility of Contractor to assume costs incurred because of additional work and or
changes required to incorporate proposed substitute into the Project. Refer to Division 01 for
complete instructions.
C. Substitutions will be interpreted to be all manufacturers other than those specifically listed in
the Contract Documents by brand name, model or catalog number.
D. Only one request for substitution will be considered for each item of equipment or material.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 7
E. Substitution requests shall include the following:
1. Reason for substitution request.
2. Complete submittal information as described herein; see “Submittals.”
3. Coordinated scale layout drawings depicting position of substituted equipment in relation
to other work, with required clearances for operation, maintenance and replacement.
4. List optional features required for substituted equipment to meet functional requirements
of the system as indicated in Contract Documents.
5. Explanation of impact on connected utilities.
6. Explanation of impact on structural supports.
F. Installation of reviewed substitution is the Contractors’ responsibility. Any mechanical,
electrical, structural, or other changes required for installation of reviewed substituted
equipment or material must be made by the Contractor without additional cost to the Owner.
Review by the Architect of the substituted equipment or material, including dimensioned
Drawings will not waive these requirements.
G. Contractor may be required to compensate the Architect for costs related to substituted
equipment or material.
1.12 OPERATION AND MAINTENANCE MANUAL
A. Furnish three complete sets of Operation and Maintenance Manual bound in hardboard binder,
and one compact disc containing complete Operation and Maintenance Manual in searchable
PDF format. Provide Table of Contents. Provide index tabs for each piece of equipment in
binder and disc. Start compiling data upon approval of submittals.
1. Sets shall incorporate the following:
a. Service telephone number, address and contact person for each category of
equipment or system.
b. Complete operating instructions for each item of plumbing equipment.
c. Copies of guarantees/warrantees for each item of equipment or systems.
d. Test data and system balancing reports.
e. Typewritten maintenance instructions for each item of equipment listing lubricants
to be used, frequency of lubrication, inspections required, adjustment, etc.
f. Manufacturers' bulletins with parts numbers, instructions, etc., for each item of
equipment.
g. Control diagrams and literature.
h. A complete list or schedule of all scheduled valves giving the number of the valve,
location and the rooms or area controlled by the valve. Identify each valve with a
permanently attached metal tag stamped with number to match schedule. Post list
in frame under plastic on wall in mechanical room or where directed by Architect.
i. Check test and start reports for each piece of plumbing equipment provided as part
of the Work.
j. Commissioning and Preliminary Operation Tests required as part of the Work.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 8
B. Post service telephone numbers and/or addresses in an appropriate place as designated by the
Architect.
1.13 SITE CONDITIONS
A. Information on Drawings relative to existing conditions is approximate. Deviations from
Drawings necessary during progress of construction to conform to actual conditions shall be
approved by the Architect and shall be made without additional cost to the Owner. The
Contractor shall be held responsible for damage caused to existing services. Promptly notify
the Architect if services are found which are not shown on Drawings.
1.14 EXISTING MATERIALS
A. Remove existing equipment, piping, wiring, construction, etc., which interferes with Work of
this Contract. Promptly return to service upon completion of work in the area. Replace items
damaged by Contractor with new material to match existing.
B. Removed materials which will not be re-installed and which are not claimed by Owner shall
become property of Contractor and shall be removed from Project site. Consult Owner before
removing any material from Project site. Carefully remove materials claimed by Owner to
prevent damage and deliver to Owner-designated storage location.
C. Existing piping and wiring not reused and are concealed in building construction may be
abandoned in place and all ends shall be capped or plugged. Remove unused piping and wiring
exposed in Equipment Rooms or occupied spaces. Material shall be removed from Project
premises. Disconnect power, water, gas, pump or any other active energy source from piping or
electrical service prior to abandoning in place.
D. Existing piping, ductwork, and equipment modified or altered as part of this Work shall comply
with the most recent applicable code requirements.
1.15 WARRANTY
A. Refer to Division 01 for warranty requirements, including effective date of warranty. Refer to
specific items of equipment specified herein for warranty duration if different from that
specified in Division 01.
B. Repair or replace defective work, material, or part that appears within the warranty period,
including damage caused by leaks.
C. On failure to comply with the above warranty within a reasonable length of time after
notification is given, the Architect/Owner shall have the repairs made at the Contractor's
expense.
1.16 RECORD DRAWINGS
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 9
A. Refer to Division 01, Record Documents, for requirements governing Work specified herein.
B. Upon completion of the work, deliver to Architect the following:
1. Originals of drawings showing the Work exactly as installed.
2. One complete set of reproducible drawings showing the Work exactly as installed.
3. One compact disc with complete set of drawings in PDF format showing the Work
exactly as installed.
C. Provide Contractor’s signature, verifying accuracy of record drawings.
D. Obtain the signature of the Project Inspector for all record drawings.
1.17 DELIVERY AND STORAGE
A. Protect equipment and piping delivered to Project site from weather, humidity and temperature
variations, dirt, dust and other contaminants.
1.18 COORDINATION
A. General:
1. Coordinate Work in this Section with trades covered in other Specifications Sections to
provide a complete, operable and sanitary installation of the highest quality
workmanship.
B. Electrical Coordination:
1. Refer to the Electrical Drawings and Specifications, Division 26, for service voltage and
power feed wiring for equipment specified under this section. Contractor has full
responsibility for the following items of work:
a. Review the Electrical Drawings and Division 26 Specifications to verify that
electrical services provided are adequate and compatible with equipment
requirements.
b. If additional electrical services are required above that indicated on Electrical
Drawings and in Division 26, such as more control interlock conductors, larger
feeder, or separate 120 volt control power source, include cost to furnish and
install additional electrical services as part of the bid.
c. Prior to proceeding with installation of additional electrical work, submit detailed
drawings indicating exact scope of additional electrical work.
C. Mechanical Coordination:
1. Arrange for pipe spaces, chases, slots and openings in building structure during progress
of construction, to accommodate mechanical system installation.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 10
2. Coordinate installation of supporting devices. Set sleeves in poured-in-place concrete and
other structural components during progress of construction.
3. Coordinate requirements for access panels and doors for mechanical items requiring
access where concealed behind finished surfaces. Access panels and doors are specified
in Division 08 Section “Access Doors and Frames.”
PART 2 - PRODUCTS
2.1 GENERAL
A. Materials or equipment of the same type shall be of the same brand wherever possible. All
materials shall be new and in first class condition.
B. All sizes, capacities, and efficiency ratings shown are minimum, except that gas capacity is
maximum available.
C. Refer to Sections 22 10 00 and 23 80 00 for specific system piping materials.
2.2 VALVES AND FITTINGS FOR POTABLE WATER SYSTEMS
A. General:
1. Provide valves and fittings conforming to lead-free requirements of California Health and
Safety Code Section 116875.
a. Provide valves listed to NSF/ANSI 61-G or NSF/ANSI 372 for valve materials for
potable-water service.
1) Exception: Main distribution gate valves above 1-1/2 inches located
underground outside building are not required to conform lead-free
requirements of California Health and Safety Code Section 116875.
B. Gate Valves:
1. General: Furnish valves in copper lines with adapters to suit valve/line requirements.
2. 1-1/2 inches and smaller: Minimum 200 psi CWP, bronze body, threaded bonnet, rising
or non-rising stem, solid wedge, threaded or solder ends, conforming to MSS SP-80.
Milwaukee UP148, UP149, Nibco T-113-LF, S-113-LF, or equal.
3. 2 inches through 3 inches: Minimum 200 psi CWP, bronze body, threaded bonnet, non-
rising stem, solid wedge, threaded or solder ends, conforming to MSS SP-80. Nibco T-
113-LF, S-113-LF, or equal.
4. Main distribution gate valves underground outside building above 1-1/2 inches:
a. Underground valves 2 inches thru 12 inches: 250 psi, iron body, Non-rising stem,
bolted bonnet, resilient wedge valves, conforming to AWWA C509, equipped with
operating nuts, Mueller Series 2360, Nibco F-619-RW-SON, or equal.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 11
1) Underground valves 3 inches and smaller may be furnished with operating
nuts or hand-wheels, and with Ring-Tite joint ends.
2) Furnish and deliver to Owner one wrench of each size required for operating
underground valves.
C. Ball Valves:
1. 2 inches and smaller: 600 psi CWP, cast bronze or brass body, full port, two piece,
threaded ends, and reinforced PTFE seal, conforming to MSS SP-110. Nibco T-685-80-
LF, Milwaukee UPBA400, Apollo 77C-LF10, Kitz 868, or equal.
2. 2-1/2 inches: Apollo 77C-LF10, or equal.
2.3 VALVES AND FITTINGS FOR NON-POTABLE WATER, COMPRESSED AIR, AND GAS
SYSTEMS
A. Gate Valves:
1. 2-1/2 inches and smaller: Class150, bronze body, union bonnet, rising stem, solid wedge,
threaded or solder ends, conforming to MSS SP-80. Hammond IB641, IB648, Nibco T-
134, S-134, Milwaukee 1151, 1169, or equal.
2. 3 inches and larger: Class 125, iron body, bronze mounted, bolted bonnet, non-rising
stem, solid wedge, flanged ends, conforming to MSS SP-70. Hammond IR-1138, Nibco
F619, Milwaukee F2882A, Stockham G-612, or equal.
3. Underground valves 2 inches thru 12 inches: 250 psi, iron body, Non-rising stem, bolted
bonnet, resilient wedge valves, conforming to AWWA C509, equipped with operating
nuts, Mueller Series 2360, Nibco F-619-RW-SON, or equal.
a. Underground valves 3 inches and smaller may be furnished with operating nuts or
hand-wheels, and with Ring-Tite joint ends.
b. Furnish and deliver to Owner one wrench of each size required for operating
underground valves.
B. Ball Valves:
1. 2 inches and smaller: 600 psi CWP, 150 psi SWP, cast bronze body, full port, two piece,
threaded ends, and reinforced PTFE seal, conforming to MSS SP-110. Nibco T585-70,
Milwaukee BA-400, Stockham T-285, or equal.
2. 2-1/2 inches and larger: Class 150, carbon steel body, full port, two piece, stainless steel
vented ball, flanged ends, and reinforced PTFE seal, conforming to MSS SP-72. Nibco
F-515-CS-F-66-FS, Milwaukee F20-CS-15-F-02-GO-VB, or equal.
3. Compressed Air Services: 600 psi CWP, 150 psi SWP, bronze body, full port, three
piece, threaded ends, and reinforced PTFE seal, conforming to MSS SP-110. Nibco
Model T-595-Y, Milwaukee BA-300, or equal.
2.4 JOINING MATERIALS
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 12
A. Refer to Division 22 and 23 piping sections for special joining materials not listed below.
B. Pipe-Flange Gasket Materials: Suitable for chemical and thermal conditions of piping system
contents.
1. ASME B16.21, nonmetallic, flat, asbestos-free, 1/8-inch (3.2-mm) maximum thickness
unless thickness or specific material is indicated
a. Full-Face Type: For flat-face, Class 125, cast iron and cast bronze flanges.
b. Narrow-Face Type: For raised-face, Class 250, cast iron and steel flanges.
2. AWWA C111, rubber, flat face, 1/8-inch (3.2mm) thick, unless otherwise indicated; and
full-face or ring type, unless other indicated.
3. Flange Bolts and Nuts: AWWA C111, carbon steel, unless otherwise indicated.
4. Plastic, Pipe-Flange Gasket, Bolts and Nuts: Type and material recommended by piping
system manufacturer, unless otherwise indicated.
C. Solder Filler Metals: ASTM B 32, 100 percent lead free alloys. Include water-flushable flux
according to ASTM B813.
D. Brazing Filler Metals: AWS A5.8, BCup-5 Series, copper-phosphorus unless otherwise
indicated. Sil-Fos 15, or equal.
E. Welding Filler Metals: Comply with ASME B31.1 for welding materials appropriate for wall
thickness and chemical analysis of steel pipe being welded.
F. Solvent Cements for Joining CPVC Piping: ASTM F 493.
1. CPVC solvent cement shall have VOC content of 490 g/L or less.
2. Adhesive primer shall have VOC content of 550 g/L or less.
3. Solvent cement and adhesive primer shall comply with testing and product requirements
of South Coast Air Quality Management District, Rule 1168.
4. Solvent cement and adhesive primer shall comply with testing and product requirements
of California Department of Health Services' "Standard Practice for the Testing of
Volatile Organic Emissions from Various Sources Using Small-Scale Environmental
Chambers."
G. Solvent Cements for Joining PVC Piping: ASTM D 2564. Include primer according to
ASTM F 656.
1. PVC solvent cement shall have VOC content of 510 g/L or less.
2. Adhesive primer shall have VOC content of 550 g/L or less.
3. Solvent cement and adhesive primer shall comply with testing and product requirements
of South Coast Air Quality Management District, Rule 1168.
4. Solvent cement and adhesive primer shall comply with testing and product requirements
of California Department of Health Services' "Standard Practice for the Testing of
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 13
Volatile Organic Emissions from Various Sources Using Small-Scale Environmental
Chambers."
2.5 GAUGES
A. Marsh "Series J", U.S. Gage, Danton 800, or equal, with bronze bushed movement and front
recalibration. Dials shall be white with black numerals, 3-1/2 inch dial face. Normal reading
shall be at mid-scale. Provide a needle valve on each gauge connection. Supply a gauge piped
with branch isolation valves across the inlet and outlet of each pump and where shown on the
Drawings.
B. Provide Pete's Plug II, Sisco P/T, or equal, test plug with Nordel core {and gasketed cap}, on
inlet and outlet of each coil, boiler, condenser, chiller and heat exchanger and where shown on
Drawings.
2.6 THERMOMETERS
A. Marsh, Taylor, Palmer, or equal, 5 inch diameter bimetal dial, adjustable from face, with
adjustable positioner, located to be easily read from normal personnel approach. Normal
reading shall be at mid-scale.
1. Provide extension for insulation.
2. Provide thermometers with steel bulb chambers and brass separable sockets.
B. Provide Pete's Plug II, Sisco P/T, or equal, test plug with Nordel core, on inlet and outlet of each
coil, boiler, and heat exchanger and provide two digital electronic test thermometers for each
range of fluid temperature and where shown on Drawings.
2.7 ACCESS DOORS
A. Where floors, walls, or ceilings must be penetrated for access to mechanical equipment, provide
access doors, 14 inch by 14 inch minimum size in usable opening. Where entrance of a
serviceman may be required, provide 20 inch by 30 inch minimum usable opening. Locate
access doors/panels for non-obstructed and easy reach.
1. All access doors less than 7'-0" above floors and exposed to public access shall have
keyed locks.
B. Access doors shall match those supplied in Division 08 in all respects, except as noted herein.
C. Provide stainless steel access doors for use in toilet rooms, shower rooms, kitchens and other
damp areas. Provide steel access doors with prime coat of baked-on paint for all other areas.
D. Do not locate access doors in highly visible public areas such as lobbies, waiting areas, and
primary entrance areas. Coordinate with the Architect when access is required in these areas.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 14
E. Where specific information or details relating to access panels different from the above is
shown or given on the Drawings or other Divisions of work, then that information shall
supersede this specification.
F. Manufacturers: Subject to compliance with requirements, available manufacturers offering
products which may be incorporated into the Work include Milcor, Karp, Nystrom, or Cesco,
equal to the following:
1. Milcor
a. Style K (plaster)
b. Style DW (gypsum board)
c. Style M (Masonry)
d. Style "Fire Rated” where required
2.8 EXPANSION LOOPS
A. Manufactured assembly consisting of inlet and outlet elbow fittings, two sections of flexible
metal hose and braid, and 180-degree return bend or center section of flexible hose. Flexible
hose shall consist of corrugated metal inner hose and braided outer sheath.
B. Where used in potable water systems, provide expansion loops of all stainless steel
construction.
C. Manufacturers: Subject to compliance with requirements, available manufacturers offering
products that may be incorporated into the Work include the following, or equal:
Metraflex Inc., Metraloop series.
Unisource Manufacturing, Inc., V series.
2.9 FLEXIBLE JOINTS
A. Where indicated on Drawings, provide Metraflex Metrasphere, Style R, Mason Industries, or
equal, Spherical Expansion Joints. Provide control units at each expansion joint, arranged to
limit both expansion and compression.
B. Flexible joints at entry points to building shall be Barco Ductile iron, Advanced Thermal
Systems, or equal, threaded style with stainless ball and mineral filled seal.
2.10 PIPE GUIDES
A. Where flexible connections are indicated on Drawings, provide Metraflex style IV, B-Line, or
equal, pipe guides in locations recommended by manufacturer. Maximum spacing from flexible
connection to first pipe guide is 4 pipe diameters, and maximum spacing from second pipe
guide is 14 pipe diameters.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 15
2.11 EQUIPMENT IDENTIFICATION
A. Identify each piece of equipment with a permanently attached engraved bakelite plate, 1/2 inch
high white letters on black background.
2.12 PIPE IDENTIFICATION
A. Identify each piping system and indicate the direction of flow by means of Seton, Inc., Marking
Services Inc., Reef Industries, Inc., or equal, pre-tensioned, coiled semi-rigid plastic pipe labels
formed to circumference of pipe, requiring no fasteners or adhesive for attachment to pipe.
B. The legends and flow arrows shall conform to ASME A13.1.
2.13 INSULATION WORK
A. General:
1. Insulation products, including insulation, insulation facings, jackets, adhesives, sealants
and coatings shall not contain polybrominated diphenyl ethers (PBDEs) in penta, octa, or
deca formulations in amounts greater than 0.1 percent (by mass).
2. Adhesives and sealants shall comply with testing and product requirements of South
Coast Air Quality Management District, Rule 1168.
3. The term "piping" used herein includes pipe, valves, strainers and fittings.
4. Apply insulating cement to fittings, valves and strainers and trowel smooth to the
thickness of adjacent covering. Cover with jacket to match piping. Extend covering on
valves up to the bonnet. Leave strainer cleanout plugs accessible.
5. Provide pre-formed PVC valve and fitting covers.
6. Provide Calcium Silicate rigid insulation and sheet metal sleeve, 18 inch minimum length
at each pipe hanger. Seal ends of insulation to make vapor tight with jacket.
7. Urethane insulation will not be allowed above ground or on hot water piping.
8. Test insulation, jackets and lap-seal adhesives as a composite product and confirm flame
spread of not more than 25 and a smoke developed rating of not more than 50 when
tested in accordance with UL723 or ASTM E84.
9. Clean thoroughly, test and have approved, all piping and equipment before installing
insulation and/or covering.
10. Repair all damage to existing pipe and equipment insulation whether or not caused during
the work of this contract, to match existing adjacent insulation for thickness and finish,
but conforming to flame spread and smoke ratings specified above.
B. Insulation of Piping:
1. Insulate domestic hot and tempered water with 1 inch thick 3-1/2# minimum density
fiberglass with ASJ-SSL jacket for sizes up to and including 3/4 inches. For larger sizes,
provide 1-1/2 inch thick 3-1/2# minimum density fiberglass insulation and ASJ-SSL
jacket.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 16
2. Exposed insulated piping within the building shall have a Zeston 2000 25/50, Proto
Lo-Smoke, or equal, PVC jacket and fitting cover installed over the insulation, applied
per manufacturer's instructions. Verify suitability with manufacturer of insulation.
Insulation with pre-applied polymer jacket may be substituted at Contractor’s option.
PART 3 - EXECUTION
3.1 PLUMBING DEMOLITION
A. Refer to Division 01 Sections “Cutting and Patching” and “Selective Demolition” for general
demolition requirements and procedures.
B. Disconnect, dismantle and remove mechanical systems, equipment, and components indicated
to be removed. Coordinate with all other trades.
1. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or
plug remaining piping with same or compatible piping material.
2. Piping to Be Abandoned in Place: Drain piping and cap or plug piping to remain with
same or compatible piping material. Refrigerant system must be evacuated per EPA
requirements.
3. Equipment to Be Removed: Drain down and cap remaining services and remove
equipment.
4. Equipment to Be Removed and Reinstalled: Disconnect and cap services and remove,
clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment
operational.
5. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove
equipment and deliver to Owner.
C. If pipe, insulation, or equipment to remain is damaged in appearance or is unserviceable,
remove damaged or unserviceable portions and replace with new products of equal capacity and
quality.
3.2 ELECTRICAL REQUIREMENTS
A. Provide adequate working space around electrical equipment in compliance with the California
Electrical Code. Coordinate the Mechanical Work with the Electrical Work to comply.
B. Furnish necessary control diagrams and instructions for the controls. Before permitting
operation of any equipment which is furnished, installed, or modified under this Section, review
all associated electrical work, including overload protection devices, and assume complete
responsibility for the correctness of the electrical connections and protective devices. Motors
and control equipment shall conform to the Standards of the National Electrical Manufacturers'
Association. All equipment and connections exposed to the weather shall be NEMA IIIR with
factory-wired strip heaters in each starter enclosure and temperature control panel where
required to inhibit condensation.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 17
C. All line voltage and low voltage wiring and conduit associated with the Temperature Control
System are included in this Section. Wiring and conduit shall comply with Division 26.
3.3 PIPING SYSTEM REQUIREMENTS
A. Drawing plans, schematic and diagrams indicate general location and arrangement of piping
systems. Indicated locations and arrangements were used to size pipe and calculate friction
loss, expansion, pump sizing, and other design considerations. Install piping as indicated unless
deviations to layout are approved on coordination drawings.
3.4 PRIMING AND PAINTING
A. Perform all priming and painting on the equipment and materials as specified herein.
B. Priming:
1. Exposed ferrous metals, including piping, which are not galvanized or factory-finished
shall be primed. Black steel pipe exposed to the weather shall be painted one coat of
Rust-Oleum #1069 primer for black steel piping or Rust-Oleum #5260, Kelly Moore, or
equal, primer for galvanized piping.
2. Metal surfaces of items to be jacketed or insulated except piping shall be given two coats
of primer unless furnished with equivalent factory finish. Items to be primed shall be
properly cleaned by effective means free of rust, dirt, scale, grease and other deleterious
matter and then primed with the best available grade of zinc rich primer. After erection
or installation, all primed surfaces shall be properly cleaned of any foreign or deleterious
matter that might impair proper bonding of subsequent paint coatings. Any abrasion or
other damage to the shop or field prime coat shall be properly repaired and touched up
with the same material used for the original priming.
3. Where equipment is provided with nameplate data, the nameplate should be masked off
prior to painting. When painting is completed, remove masking material.
C. See Painting Section for detailed requirements.
3.5 EXCAVATING
A. Perform all excavating required for work of this Section. Provide the services of a pipe/cable
locating service prior to excavating activities to determine location of existing utilities.
B. Unless shown otherwise, provide a minimum of 2'-6" cover above top of pipe to finished grade
for all service piping, unless otherwise noted. Trim trench bottom by hand or provide a 4 inch
deep minimum bed of sand to provide a uniform grade and firm support throughout entire
length of pipe. For all PVC pipe and for PE gas pipe, bed the pipe in 4 inch sand bed. Pipe
bedding materials should be clean crushed rock, gravel or sand of which 100 percent will pass a
1 inch sieve. For pipes that are larger than 10 inches in diameter, at least 95 percent should pass
a 3/4 inch sieve, and for pipes 10 inches in diameter or smaller, 100 percent should pass a 1/2
inch sieve. All other materials should have a minimum sand equivalent of 50. Only a small
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 18
proportion of the native soils will meet these requirements without extensive processing;
therefore, importation of pipe bedding materials should be anticipated. Pipe bedding materials
shall be compacted in lifts not exceeding 6 inches in compacted thickness. Each lift shall be
compacted to not less than 90 percent relative compaction at or above the optimum moisture
content, in accordance with ASTM Specification D2940, except that bedding materials graded
such that less than 100 percent will pass a No. 200 sieve shall be compacted in 6 inch lifts using
a single pass of a flat-plate, vibratory compactor or vibratory drum. Pipe bedding materials
should extend at least to the spring line.
C. Maintain all warning signs, barricades, flares, and red lanterns as required.
D. For all trenches 5 feet or more in depth, submit copy of permit detailed drawings showing
shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard
of caving ground during the excavation of such trenches. Obtain a permit from the Division of
Industrial Safety prior to beginning excavations. A copy of the permit shall be available at the
site at all times.
3.6 BACKFILLING
A. Backfill shall comply with applicable provisions of Division 31 of these Specifications.
B. Except under existing or proposed paved areas, walks, roads, or similar surfaces, backfill for
other types of pipe shall be made using suitable excavated material or other approved material.
Place backfill in 8 inch layers, measured before compaction, and compact with impact hammer
to at least 90 percent relative compaction per ASTM D2940.
1. Backfill plastic pipe and insulated pipe with sand for a minimum distance of 12 inches
above the top of the pipe. Compact using mechanical tamping equipment.
C. Entire backfill for excavations under existing or proposed pavements, walks, roads, or similar
surfaces, under new slabs on grade, shall be made with clean sand compacted with mechanical
tamping equipment vibrator to at least 90 percent relative compaction per ASTM D2940.
Remove excess earth. Increase the minimum compaction within the uppermost two feet of
backfill to 95 percent.
D. Replace or repair to its original condition all sod, concrete, asphalt paving, or other materials
disturbed by the trenching operation. Repair within the guarantee period as required.
3.7 INSTALLATION OF VALVES
A. Install valves as indicated on Drawings and in the following locations:
1. Shutoff Valves: Install on inlet of each plumbing equipment item, and on inlet of each
plumbing fixture, and elsewhere as indicated.
2. Drain Valves: Install on each plumbing equipment item located to completely drain
equipment for service or repair. Install at base of each riser, at base of each rise or drop
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 19
in piping system, and elsewhere indicated or required to completely drain potable water
system.
3. Provide gate or globe valves on inlet and outlet of each water heater or pump.
B. General:
1. Valves shall be full line size unless indicated otherwise on Drawings.
2. Install horizontal valves with valve stem above horizontal, except butterfly valves.
3. Install valves with unions or flanges at each piece of equipment arranged to allow
service, maintenance, and equipment removal without system shutdown.
4. Locate valves for easy access and provide separate support where necessary.
5. Install valves in position to allow full stem movement.
6. Install exposed polished or enameled connections with special care showing no tool
marks or exposed threads.
7. Butterfly valves conforming to the paragraph “Butterfly Valves” may be used in lieu of
gate or globe valves for locations above grade.
8. Ball valves conforming to the paragraph “Ball Valves” may be used in lieu of gate valves
for locations above grade for services 2-1/2 inches and smaller.
9. Valves 2-1/2 inches and smaller (except ball valves) in nonferrous water piping systems
may be solder joint type with bronze body and trim.
10. Rigidly fasten hose bibbs, hydrants, fixture stops, compressed air outlets, and similar
items to the building construction.
C. Gate Valves:
1. Furnish valves in copper lines with adapters to suit valve / line requirements.
2. Underground gate valves:
a. Underground valves 3 inches and smaller may be furnished with operating nuts or
hand-wheels, and with Ring-Tite joint ends.
b. Furnish and deliver to Owner one wrench of each size required for operating
underground valves.
D. Valve Adjustment: Adjust or replace valve packing after piping systems have been tested and
put into service but before final adjusting and balancing. Replace valves if persistent leaking
occurs.
3.8 INSTALLATION OF PIPING SYSTEMS
A. At time of final connection, and prior to opening valve to allow pressurization of water and gas
piping from existing systems, on site or off site, perform a pressure test to indicate static
pressure of existing systems. If pressure on water piping is greater than 80 psi, or gas pressure
is not as indicated on Contract Documents, inform Architect immediately. Do not allow piping
systems to be pressurized without written consent of the Architect.
B. General:
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 20
1. All piping shall be concealed unless shown or otherwise directed. Allow sufficient space
for ceiling panel removal.
2. Installation of piping shall be made with appropriate fittings. Bending of piping will not
be accepted.
3. Install piping to permit application of insulation and to allow valve servicing.
4. Where piping or conduit is left exposed within a room, the same shall be run true to
plumb, horizontal, or intended planes. Where possible, uniform margins are to be
maintained between parallel lines and/or adjacent wall, floor, or ceiling surfaces.
5. Horizontal runs of pipes and/or electrical conduit suspended from ceilings shall provide
for a maximum headroom clearance. The clearance shall not be less than 6'-6" without
written approval from the Architect.
6. Close ends of pipe immediately after installation. Leave closure in place until removal is
necessary for completion of installation.
7. Each piping system shall be thoroughly flushed and proved clean before connection to
equipment.
8. Pipe the discharge of each relief valve, air vent, backflow preventer, and similar device to
floor sink or drain.
9. Install exposed polished or enameled connections with special care showing no tool
marks or threads at fittings.
10. Install horizontal valves with valve stem above horizontal.
11. Use reducing fittings; bushings shall not be allowed. Use eccentric reducing fittings
wherever necessary to provide free drainage of lines and passage of air.
12. Verify final equipment locations for roughing-in.
13. Service Markers: Mark the location of each plugged or capped pipe with a 4 inch round
by 30 inch long concrete marker, set flush with finish grade. Provide 2-1/2 inch diameter
engraved brass plate as part of monument marker.
14. Furnish and install anchors or thrust blocks on PVC water lines in the ground, at all
changes in direction of piping, and at all connections or branches from mains 1-1/2 inch
and larger. Form anchors or thrust blocks by pouring concrete between pipe and trench
wall. Thrust blocks shall be of adequate size and so placed as to take thrusts created by
maximum internal water pressure. Sizing and placement shall be per manufacturer's
recommendations, CPC, and IAPMO installation standards. Anchor piping to building
construction.
15. Sanitary Sewer and Storm Drain: Grade piping inside building uniformly 1/4 inch per
foot if possible but not less than 1/8 inch per foot. Run piping as straight as possible.
Make piping connections between building piping and outside service pipe with cast iron
reducers or increasers. Slope sewers uniformly between given elevations where invert
elevations are shown.
16. Where piping is installed in walls within one inch of the face of stud, provide a 16 gauge
sheet metal shield plate on the face of the stud. The shield plate shall extend a minimum
of 1-1/2 inches beyond the outside diameter of the pipe.
C. Expansion Loops:
1. Install expansion loops where piping crosses building expansion or seismic joints,
between buildings, between buildings and canopies, and as indicated on Drawings.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 21
2. Install expansion loops of sizes matching sizes of connected piping.
3. Install grooved-joint expansion joints to grooved-end steel piping.
4. Materials of construction and end fitting type shall be consistent with pipe material and
type of gas or liquid conveyed by the piping system in which expansion loop is installed.
D. Sleeves:
1. Install Adjus-to-Crete, Pipeline Seal and Insulator, or equal, pipe sleeves of sufficient
size to allow for free motion of pipe, 24 gauge galvanized steel. The space between pipe
and sleeves through floor slabs on ground, through outside walls above or below grade,
through roof, and other locations as directed shall be caulked with oakum and mastic and
made watertight. The space between pipe and sleeve and between sleeve and slab or wall
shall be sealed watertight.
2. At Contractor's option, Link-Seal, Metraflex Metraseal, or equal, casing seals may be
used in lieu of caulking. Wrap pipes through slabs on grade with 1 inch thick fiberglass
insulation to completely isolate the pipe from the concrete.
E. Floor, Wall, and Ceiling Plates:
1. Fit all pipes with or without insulation passing through walls, floors, or ceilings, and all
hanger rods penetrating finished ceilings with chrome-plated or stainless escutcheon
plates.
F. Firestopping:
1. Pack the annular space between the pipe sleeves and the pipe through all floors and walls
with UL listed fire stop, and sealed at the ends. All pipe penetrations shall be UL listed,
Hilti, 3M Pro-Set, or equal.
a. Install fire caulking behind mechanical services installed within fire rated walls, to
maintain continuous rating of wall construction.
2. Provide SpecSeal Systems UL fire rated sleeve/coupling penetrators for each pipe
penetration or fixture opening passing through floors, walls, partitions or floor/ceiling
assemblies. All Penetrators shall comply with UL Fire Resistance Directory (Latest
Edition), and in accordance with Chapter 7, CBC requirements.
3. Sleeve penetrators shall have a built in anchor ring for waterproofing and anchoring into
concrete pours or use the special fit cored hole penetrator for cored holes.
4. Copper and steel piping shall have SpecSeal plugs on both sides of the penetrator to
reduce noise and to provide waterproofing.
5. All above Systems to be installed in strict accordance with manufacturer's instructions.
6. Alternate firestopping systems are acceptable if approved equal. However, any deviation
from the above specification requires the Contractor to be responsible for determining the
suitability of the proposed products and their intended use, and the Contractor shall
assume all risks and liabilities whatsoever in connection therewith.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 22
G. Hangers and Supports:
1. General: Support all equipment and piping so that it is firmly held in place by approved
iron hangers and supports and special hangers as required. All components shall support
weight of equipment and pipe, fluid, and pipe insulation based on spacing between
supports with minimum factor of safety of five based on ultimate strength of material
used. Do not exceed manufacturer's load rating. Pipe attachments or hangers, of same
size as pipe or tubing on which used, or nearest available. Rigidly fasten hose faucets,
fixture stops, compressed air outlets, and similar items to the building construction. The
Architect shall approve all hanger material before installation. Do not support piping
with plumbers' tape, wire rope, wood, or other makeshift devices. Where building
structural members do not match piping support spacing, provide all “bridging” support
members as required firmly attached to building structural members in a fashion
approved by the Structural Engineer.
a. Materials, design, and type numbers per Manufacturers' Standardization Society
(MSS), Standard Practice (SP)-58.
2. All hanger components shall be provided by one manufacturer B-Line, Grinnell, Uni-
Strut, Badger, or equal.
3. Hanger and Support Spacing:
a. Vertical piping support spacing: B-line #B3373 clamps attached to the pipe above
each floor to rest on the floor. Provide with lead or Teflon liners on copper tubing.
Provide additional support at base of cast iron risers and support at unsupported
riser joints and horizontal offsets per 2007 Mason Industries Seismic Restraint
Guidelines. Provide intermediate support for vertical piping, spaced at or within
the following maximum limits.
Pipe
Diameter
Steel
Fluid
Steel
Vapor
Copper
Fluid
Copper
Vapor
CPVC &
PVC (Note 2)
1/2 - 1” 12 6 10 6 Base and
Each Floor
(Note 1)
1-1/4 - 2” 12 Each
Floor
10 6 Base and
Each Floor
(Note 1)
2-1/2 - 3” 12 Each
Floor
10 10 Base and
Each Floor
(Note 1)
Over 4” 12 Each
Floor
10 10 Base and
Each Floor
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 23
(Note 1)
Note 1: Provide mid-story guides.
Note 2: For PVC piping, provide for expansion every 30 feet per IAPMO
installation standard.
b. Vertical cast iron piping support spacing: Base and each floor not to exceed 15
feet.
c. Horizontal piping, hanger and support spacing: Locate hangers and supports at
each change of direction, within one foot of elbow, and spaced at or within
following maximum limits.
Pipe
Diameter
Steel
Fluid
Steel
Vapor
Copper
Fluid
Copper
Vapor
CPVC
& PVC
1/2 - 1" 6 6 5 6 3
1-1/4 - 2" 7 10 6 6 4
2-1/2 - 3" 10 10 10 10 4
Over 4" 10 10 10 10 4
d. Horizontal cast iron piping support spacing:
1) Support piping at every other joint for piping length of less than 4 feet.
2) For piping longer than 4 feet, provide support on each side of the coupling,
within 18 inches of each joint.
3) Hanger shall not be installed on the coupling.
4) Provide support at each horizontal branch connection.
5) Provide sway brace at 40 foot maximum spacing for all suspended pipe with
no-hub joints, except where a lesser spacing is indicated in the 2007 Mason
Industries Seismic Restraint Guidelines. Provide a brace on each side of a
change in direction of 90 degrees or more. Brace riser joints at each floor
and at 15 foot maximum intervals.
4. Individually Suspended Piping:
a. Individually suspended piping: B-Line B3690 J-Hanger or B3100 Clevis,
complete with threaded rod, or equal. All hangers on supply and return piping
handling heating hot water or steam shall have a swing connector at point of
support.
Pipe Size Rod Size
2" and Smaller 3/8"
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 24
2-1/2" to 3-1/2" 1/2"
4" to 5" 5/8"
6" 3/4"
b. Provide 3/8 inch rod for support of PVC and CPVC and provide continuous
support.
c. Trapeze Suspension: B-Line 1-5/8 inch width channel in accordance with
manufacturer's published load ratings. No deflection to exceed 1/180 of a span.
d. Trapeze Supporting Rods: Shall have a safety factor of five; securely anchor to
building structure.
e. Pipe Clamps and Straps: B-Line B2000, B2400; isolate copper pipe with two
thicknesses of 2 inches wide 10-mil polyvinyl tape. Where used for seismic
support systems, provide B-Line B2400 series pipe straps.
f. Concrete Inserts: B-line B22-I continuous insert or B2500 spot insert. Do not use
actuated fasteners for support of overhead piping unless approved by Architect.
g. Steel Connectors: Beam clamps with retainers.
5. Support to Structure:
a. Wood Structure: Provide and install wood blocking as required to suit structure.
Provide lag screws or through bolts with length to suit requirements, and with size
(diameter) to match the size of hanger rods required.
1) Do not install Lag screws in tension without written review and acceptance
by Structural Engineer.
Side Beam Angle Clip B-Line B3062 MSS Type 34
Side Beam Angle Clip B-Line B3060
Ceiling Flange B-Line B3199
2) Blocking for support of piping shall be not less than 2 inch thick for piping
up to 2 inch size (water filled) or 3 inch size (vapor filled). Provide 3 inch
blocking for piping up through 5 inch size, and 4 inch blocking for larger
piping. Provide support for blocking in accordance with Structural
Engineers requirements.
3) Where lag screws are used, length of screw shall be 1/2 inch less than the
wood blocking. Pre-drill starter holes for each lag screw.
b. Steel Structure: Provide and install additional steel bracing as required to suit
structure. Provide through bolts with length to suit requirements of the structural
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 25
components. Burning or welding on any structural member may only be done if
approved by the Architect.
6. Rubber Neoprene Pipe Isolators:
a. Pipe isolators shall comprise an internal rubber or neoprene material that isolates
pipe from hanger and structure. Install at all piping located in acoustical walls.
Refer to Architectural Drawings for location of acoustical walls.
b. Isolation material shall be either a rubber or neoprene material that prevents
contact between the pipe and the structure. The rubber shall have between a 45 to
55 durometer rating and a minimum thickness of 1/2 inch.
c. Acceptable Suppliers:
1) Vertical runs: Acousto-Plumb or equal.
2) Horizontal runs: B-Line, Vibraclamp; Acousto-Plumb or equal.
7. Provide continuous V channel support for all horizontal plastic piping.
8. Provide rigid insulation and a 12 inch long, 18 gauge galvanized sheet iron shield
between the covering and the hanger whenever hangers are installed on the outside of the
pipe covering.
9. Insulate copper tubing from ferrous materials and hangers with two thicknesses of 3 inch
wide, 10 mil polyvinyl tape wrapped around pipe.
10. Provide a support or hanger close to each change of direction of pipe either horizontal or
vertical and as near as possible to concentrated loads.
11. Suspend rods from concrete inserts with removable nuts where suspended from concrete
decks. Power actuated inserts will not be allowed.
3.9 PIPE JOINTS AND CONNECTIONS
A. General:
1. Cutting: Cut pipe and tubing square, remove rough edges or burrs. Bevel plain ends of
steel pipe.
2. Remove scale, slag, dirt and debris from inside and outside of pipe before assembly.
3. Boss or saddle type fittings or mechanically extracted tube joints will not be allowed.
B. Threaded Pipe: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut
threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore
full ID. Join pipe fittings and valves as follows:
1. Apply thread compound to external pipe threads: Rectorseal No. 5, Permatex No. 1, or
equal.
2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or
damaged.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 26
C. Flanged Joints: Select appropriate asbestos-free, nonmetallic gasket material in size, type, and
thickness suitable for domestic water service. Join flanges with gasket and bolts according to
ASME B31.9.
D. Joint Construction for Solvent-Cemented Plastic Piping: Clean and dry joining surfaces. Join
pipe and fittings according to the following:
1. Comply with ASTM F 402 for safe-handling practice of cleaners, primers, and solvent
cements. Apply primer.
2. CPVC Piping: Join according to ASTM D 2846/D 2846M Appendix.
3. PVC Piping: Join according to ASTM D 2855.
E. Copper Pipe and Tubing (Except pneumatic control piping): All joints shall be brazed
according to ASME Section IX, Welding and Brazing Qualifications, except domestic water
piping 1-1/4 inches and smaller when not buried in the ground or concrete and type DWV
plumbing piping may be soldered.
1. Soldered joints: Apply water-flushable flux to end of tube. Join copper tube and fittings
according to ASTM B 828.
F. Cast Iron Soil Pipe:
1. No-Hub fittings shall be made with a torque wrench.
2. Hub joints shall be with Ty-Seal couplings.
3. Wrought iron, steel, or copper pipe shall have a ring or part of a coupling screwed on to
form a spigot end if caulked into a joint.
4. Connect cast iron sewer piping to outside service pipe with cast iron or vitrified clay
reducers or increasers as required. Caulking of smaller pipe into the larger without a
reducer or increaser will not be permitted.
G. Welded Pipe:
1. Make up with oxyacetylene or electric arc process.
2. All welding shall conform to the American Standard Code for Power Piping ASME
B-31.1. When requested by the Architect, furnish certification from an approved testing
agency or National Certified Pipe Welding Bureau that the welders performing the work
are qualified.
3. All line welds shall be of the single "V" butt type. Welds for flanges shall be of the fillet
type.
4. Where the branch is two pipe sizes smaller than the main or smaller, Bonney Weldolets,
Threadolets, Nibco, or equal, may be used in lieu of welding tees.
H. PVC Sewer and Drainage Pipe (outside building as allowed only): Four inches and larger shall
be bell and spigot, assembled in accordance with manufacturer's recommendations. Joint shall
be tested in accordance with ASTM D3212. Solvent weld joints below 4 inches in size,
schedule 40 PVC with matching fittings, assembled per manufacturer’s instructions.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 27
I. Polyethylene Pipe: Assemble with fusion joints in strict accordance with manufacturer's
instructions.
J. Make joints in PVC water pipe with PVC couplings and rubber rings, Manville Ring-Tite, PW
Pipe, or equal. Check final location of rubber rings with the couplings with gauge or as
recommended by the manufacturer. Make joints between PVC pipe and cast iron pipe or
fittings using cast iron or PVC adapter fittings, installed as recommended by the manufacturer.
Ring-Tite PVC or cast iron pipe fittings may be used in lieu of standard fittings. Make
connection to valves with cast iron adapters connected to the water pipe with PVC couplings.
K. Flexible Connections:
1. Furnish and install Thermo Tech., Inc. F/J/R, Metraflex, or equal, flexible couplings with
limiter bolts on piping connections to all equipment mounted on anti-vibration bases, on
each connection to each base mounted pump and where shown. Couplings shall be
suitable for pressure and type of service.
2. Anchor piping securely on the system side of each flexible connection.
3.10 UNIONS AND FLANGES
A. Install Watts, Epco, Nibco, or equal, dielectric unions or flanges at points of connection
between copper or brass piping or material and steel or cast iron pipe or material except in
drain, waste, vent, or rainwater piping. Bushings or couplings shall not be used. Dielectric
unions installed in potable water systems shall conform to the lead-free requirements of the
California Health and Safety Code Section 116875.
B. Install unions in piping NPS 2” and smaller, and flanges in piping NPS 2-1/2” and larger
whether shown or not at each connection to all equipment and tanks, and at all connections to
all automatic valves, such as temperature control valves. Unions installed in potable water
systems shall conform to the lead-free requirements of the California Health and Safety Code
Section 116875.
C. Locate the unions for easy removal of the equipment, tank, or valve.
3.11 ACCESS DOOR
A. Furnish and install access doors wherever required whether shown or not for easy maintenance
of mechanical systems; for example, at concealed valves, strainers, traps, cleanouts, dampers,
motors, controls, operating equipment, etc. Access doors shall provide for complete removal
and replacement of equipment.
3.12 CONCRETE WORK
A. Concrete work required for work of this Section shall be included under another section of the
Specification, unless otherwise noted, including poured-in-place concrete work for installing
precast manholes, catch basins, etc., and shall include reinforced concrete bases for pumps,
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 28
tanks, compressors, fan units, boilers, unless the work is specifically indicated on the Drawings
to be furnished under this Section.
B. Thrust blocks, underground anchors, and pads for cleanouts, valve access boxes and washer
boxes are included under this Section of the Specification. Concrete shall be 3000 psi test
minimum. Refer to Division 03 for concrete types.
3.13 PIPE PROTECTION
A. Wrap bare galvanized and black steel pipe buried in the ground and to 6" above grade, including
piping in conduit, with one of the following, or equal:
1. Polyethylene Coating: Pressure sensitive polyethylene coating, "X-Tru-Coat" as
manufactured by Pipe Line Service Corporation or "Green Line" wrap as manufactured
by Roystron Products, or equal.
a. Field Joints and Fittings: Protecto Wrap #1170 tape as manufactured by Pipe Line
Service Corporation, or Primer #200 tape by Roystron Products, or equal.
Installation shall be as per manufacturer's recommendation and instructions.
2. Tape Wrap: Pressure-sensitive polyvinyl chloride tape, "Transtex #V-l0 or V-20",
"Scotchwrap 50", Slipknot l00, Pabco, or equal, with continuous identification. Tape
shall be a minimum of 20 mils thick for fittings and irregular surfaces, two wraps, 50
percent overlap, 40 mils total thickness. Tape shall be laminated with a suitable
adhesive; widths as recommended by the manufacturer for the pipe size. Wrap straight
lengths of piping with an approved wrapping machine.
B. Field Joints: Valves and Fittings: double wrap polyvinyl chloride tape as above. Provide at
least two thicknesses of tape over the joint and extend a minimum of 4 inches over adjacent
pipe covering. Build up with primer to match adjacent covering thickness. Width of tape of
fittings shall not exceed 3 inches. Tape shall adhere tightly to all surfaces of the fittings without
air pockets.
C. Testing: Test completed wrap of piping, including all epoxy painted piping with Tinker and
Rasor Co. test machine (San Gabriel, CA - 818-287-5259), Pipeline Inspection Company
(Houston, TX - 713-681-5837), or equal.
D. Cleaning: Clean all piping thoroughly before wrapping.
1. Inspection: Damaged or defective wraps shall be repaired as directed. No wrapped pipe
shall be covered until approved by Architect.
E. Sleeve copper piping/tubing installed below slab with “Polywrap-C” polyethylene sleeve, as
manufactured by Northtown Pipe Protection Products, or equal. Sleeve shall be a minimum of
6 mils thick, colored blue for domestic water piping and orange for other piping. Install sleeve
per manufacturer’s recommendations and instructions.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 29
F. Sleeve copper piping/tubing installed outside building below grade with “Polywrap-C”
polyethylene sleeve, as manufactured by Northtown Pipe Protection Products, or equal. Sleeve
shall be a minimum of 6 mils thick, colored blue for domestic water piping. Install sleeve per
manufacturer’s recommendations and instructions.
G. Sleeve cast iron and ductile iron pipe below grade and below slab with “Polywrap”
polyethylene sleeve, as manufactured by Northtown Pipe Protection Products, or equal. Sleeve
shall be a minimum of 8 mils thick, colored natural. Install sleeve per manufacturer’s
recommendations and instructions.
H. Covering: No rocks or sharp edges shall be backfilled against the wrap. When backfilling with
other than sand, protect wrap with an outer wrapping of Kraft paper; leave in place during
backfill.
3.14 PIPE IDENTIFICATION
A. Provide temporary identification of each pipe installed, at the time of installation. Temporary
identification shall be removed and replaced with permanent identification as part of the work.
B. Apply the legend and flow arrow at all valve locations; at all points where the piping enters or
leaves a wall, partition, cluster of piping or similar obstruction, at each change of direction and
at approximately 20'-0" intervals on pipe runs. Variations or changes in locations and spacing
may be made with the approval of the Architect. There shall be at least one marking in each
room. Markings shall be located for maximum visibility from expected personnel approach.
1. Apply legend and flow arrow at approximately 10’-0” intervals in science classrooms and
science prep rooms.
C. Wherever two or more pipes run parallel, the markings shall be supplied in the same relative
location on each.
D. Each valve on non-potable water piping shall be labeled with a metal tag stamped "DANGER --
NON-POTABLE WATER" in 1/4 inch high letters.
E. Apply markings after painting and cleaning of piping and insulation is completed.
3.15 EXPANSION ANCHORS IN HARDENED CONCRETE
A. Refer to Structural Drawings.
B. Qualification Tests: The specific anchor shall have a current ICC-ES report and evaluated in
cracked concrete in accordance with Acceptance Criteria AC193. If the specific anchor satisfies
cyclic testing requirements per Acceptance Criteria AC01, Section 5.6, the full allowable shear
and tension loads listed in the current ICC-ES report and manufacturer’s recommendations for
the specific anchor may be used. Otherwise, the design shear and tension loads shall not be
more than 80% of the listed allowable shear and tension loads for the specific anchor.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 30
C. Installation: The anchors must be installed in accordance with the requirements given in ICC
Research Committee Recommendations for the specific anchor.
D. Testing: Fifty percent of the anchors shall be load-tested on each job to twice the allowable
capacity in tension, except that if the design load is less than 75 pounds; only one anchor in ten
need be tested. If any anchor fails, all anchors must be tested. The load test shall be performed
in the presence of a special inspector.
E. The load may be applied by any method that will effectively measure the tension in the anchor,
such as direct pull with a hydraulic jack, a torque wrench calibrated using the specific anchor or
calibrated spring-loading devices. Anchors in which the torque is used to expand the anchor
without applying tension to the bolt may not be verified with a torque wrench.
3.16 TESTS AND ADJUSTMENTS
A. Test the installations in accordance with the following requirements and all applicable codes:
1. Inspector of Record should witness all tests of piping systems.
2. Notify the Architect at least seven days in advance of any test.
3. All piping shall be tested at completion of roughing-in, or at other times as directed by
the Architect.
4. Furnish all necessary materials, test pumps, gases, instruments and labor required for
testing.
5. Isolate from the system all equipment that may be damaged by test pressure.
6. Make connections to existing systems with flanged connection. During testing of the
new work, provide a slip-in plate to restrict test pressure to new systems only. Remove
plate and complete connection to existing system at completion of testing.
a. Inspector of record shall witness final connection to system.
B. Test Schedule: No loss in pressure or visible leaks shall show after four hours at the pressures
indicated.
Testing of Sanitary Sewer, Drain, Vent, Storm Drain may be done in segments in order to limit
pressure to within manufacturer’s recommendations. Test to 10 feet above the highest point in
the system.
System Tested Test Pressure PSI Test With
Sanitary Sewer, Drain, Vent 10 Ft. Hd. Water
Storm Drain, Condensate Drains 10 Ft. Hd. Water
Domestic Water 125 Water
Natural Gas (PE) 60 Air & Non-corrosive
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 31
Leak Test Fluid
1. Non-corrosive leak test fluid shall be suitable for use with the piping material specified,
and with the type of gas conveyed by the piping system.
C. Perform operational tests under simulated or actual service conditions, including one test of
complete plumbing installation with all fixtures and other appliances connected, and one test of
complete installation of 48 hours each for heating and cooling with all equipment connected and
operating.
D. Should any material or work fail in any of these tests, it shall be immediately removed and
replaced for new material, and portion of the work replaced shall again be tested by Contractor
at his own expense.
E. Lubricate each item of equipment, including motors, before operation.
3.17 TRACER WIRES
A. Provide tracer wire for non-metallic gas and water pipe in ground outside of buildings. Use
AWG #12 tracer wire with low density high molecular weight polyethylene insulation, and lay
continuously on pipe so that it is not broken or stressed by backfilling operations. Secure wire
to the piping with tape at 18 inch intervals. Solder all joints. Tracer wire insulation shall be
colored yellow for gas piping, blue for water piping.
B. Terminals: Precast concrete box and cast iron locking traffic cover, Brooks 3TL, or equal;
cover marked with name of service; 6 inches of loose gravel below box. Plastic terminal board
with brass bolts; identify line direction with plastic tags. Test for continuity between terminals,
after backfilling, in presence of Inspector.
C. Alternate: Use electronically detectable plastic tape with metallic core, Terra Tape D,
manufactured by Reef Industries, Inc., Seton, Inc., Marking Services, Inc., or equal; tape 2
inches wide, continuously imprinted "CAUTION WATER (GAS, etc.) LINE BELOW". Install,
with printed side up, directly over pipe, 18 inches below finish grade. Backfill material shall be
as specified for the particular condition where pipe is installed, but avoid use of crushed rock or
of earth with particles larger than l/2 inch within the top 12 inches of backfill. Take precautions
to insure that tape is not damaged or misplaced during backfill operations. Terminal boxes not
required.
3.18 OPERATION OF SYSTEMS
A. Do not operate any plumbing equipment for any purpose, temporary or permanent, until all of
the following has been completed:
1. Complete all requirements listed under “Check, Test and Start Requirements.”
2. Piping has been properly cleaned. Piping systems shall be flushed and treated prior to
operation.
3. Filters, strainers etc. are in place.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 32
4. Bearings have been lubricated, and alignment of rotating equipment has been checked.
5. Equipment has been run under observation, and is operating in a satisfactory manner.
B. Provide test and balance agency with one set of Contract Drawings, Specifications, Addenda,
Change orders issued, applicable shop drawings and submittals and temperature control
drawings.
3.19 CHECK, TEST AND START REQUIREMENTS
A. An authorized representative of the equipment manufacturer shall perform check, test and start
of each piece of plumbing equipment. The representative may be an employee of the equipment
manufacturer, or a manufacturer-certified contractor. Submit written certification from the
manufacturer stating that the representative is qualified to perform the check test and start of the
equipment.
1. As part of the submittal process, provide a copy of each manufacturer’s printed startup
form to be used.
2. Some items of specified equipment may require that check, test and start of equipment
must be performed by the manufacturer, using manufacturer’s employees. See specific
equipment Articles in these Specifications for this requirement.
3. Provide all personnel, test instruments, and equipment to properly perform the check, test
and start work.
4. When work has been completed, provide copies of reports for review, prior to final
observation of work.
B. Provide copies of the completed check, test and start report of each item of equipment, bound
with the Operation and Maintenance Manual.
C. Upon completion of the work, provide a schedule of planned maintenance for each piece of
equipment. Indicate frequency of service, recommended spare parts (including filters and
lubricants), and methods for adjustment and alignment of all equipment components. Provide a
copy of the schedule with each operating and maintenance manual. Provide a copy of
certification from the Owner’s representative indicating that they have been properly instructed
in maintenance requirements for the equipment installed.
3.20 PRELIMINARY OPERATIONAL REQUIREMENTS AND TESTS
A. Prior to observation to determine final acceptance, put all mechanical systems into service and
check that work required for that purpose has been done, including but not limited to the
following condensed check list. Provide indexed report to tabulating the results of all work.
1. All equipment has been started, checked, lubricated and adjusted in accordance with the
manufacturer's recommendations.
2. Correct rotation of motors and ratings of overload heaters are verified.
3. Specified filters are installed and spare filters have been turned over to Owner.
4. All manufacturers’ certificates of start-up specified have been delivered to the Owner.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 33
5. All equipment has been cleaned, and damaged painted finishes touched up.
6. Missing or damaged parts have been replaced.
7. Flushing and chemical treatment of piping systems has been completed and water
treatment equipment, where specified, is in operation.
8. Equipment labels, pipe marker labels, ceiling markers and valve tags are installed.
9. Valve tag schedules, corrected control diagrams, sequence of operation lists and start-
stop instructions have been posted.
10. Preliminary test and balance work is complete, and reports have been forwarded for
review.
11. Automatic control set points are as designated and performance of controls checks out to
agree with the sequence of operation.
12. Operation and Maintenance Manuals have been delivered and instructions to the
operating personnel have been made.
B. Prior to the observation to determine final acceptance, operate all mechanical systems as
required to demonstrate that the installation and performance of these systems conform to the
requirements of these specifications.
1. Operate and test all mechanical equipment and systems for a period of at least five
consecutive 8 hour days to demonstrate the satisfactory overall operation of the project as
a complete unit.
2. Commence tests after preliminary balancing and adjustments to equipment have been
checked. Immediately before starting tests, install air filters and lubricate all running
equipment. Notify the Architect at least seven calendar days in advance of starting the
above tests.
3. During the test period, make final adjustments and balancing of equipment, systems
controls, and circuits so that all are placed in first class operating condition.
4. Where Utility District rebates are applicable, demonstrate that the systems meet the
rebate program requirements.
C. Review of Contractor's Tests:
1. All tests made by the Contractor or manufacturers' representatives are subject to
observation and review by the Owner. Provide timely notice prior to start of each test, in
order to allow for observation of testing. Upon the completion of all tests, provide a
letter to confirm that all testing has been successful.
D. Test Logs:
1. Maintain test logs listing the tests on all mechanical systems showing dates, items tested,
inspectors' names, remarks on success or failure of the tests.
E. Preliminary Operation:
1. The Owner reserves the right to operate portions of the plumbing system on a preliminary
basis without voiding the guarantee.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 34
3.21 CALIFORNIA GREEN BUILDING STANDARDS CODE COMMISSIONING
A. Systems serving new buildings less than 10,000 square feet, and new systems to serve an
addition or alteration subject to Section 301.1 of the Green Building Standards Code shall be
tested and balanced as described in the Green Building Standards Code. Title 24, Part 11,
Chapter 5, Nonresidential Mandatory Measures, Section 5.410, Building Maintenance and
Operation. The following CGBSC requirements shall be completed by Contractor:
1. 5.410.4 Testing and adjusting.
2. 5.410.4.2 Systems (Written plan for testing and adjusting).
3. 5.410.4. 3 Procedures (Perform testing and adjusting).
4. 5.410.4.4 Reporting.
5. 5.410.4.5 Operation and maintenance manual.
a. 5.410.4.5.1 Inspections and reports.
B. Systems serving new buildings 10,000 square feet and over shall be commissioned as described
in the California Green Building Standards Code (CGBSC), Title 24, Part 11, Chapter 5,
Nonresidential Mandatory Measures, Section 5.410, Building Maintenance and Operation. The
following CGBSC requirements shall be completed by Contractor:
1. 5.410.2.4 Functional performance testing.
2. 5.410.2.5 Documentation and training.
a. 5.410.2.5.1 Systems manual.
3. 5.410.2. 6 Commissioning report.
3.22 CALIFORNIA ENERGY CODE COMMISSIONING
A. Systems serving buildings between 10,000 and 50,000 square feet shall be commissioned as
described in the California Energy Code (CEC), Title 24, Part 6, Subchapter 3, Nonresidential,
High-Rise Residential Hotel/Motel Occupancies, and Covered Processes – Mandatory
Requirements, Section 120.8, Building Commissioning. The following CEC requirements shall
be completed by Contractor:
1. 120.8 (g) Functional performance testing.
2. 120.8 (h) Documentation and training.
a. 120.8 (h) 1 Systems manual.
b. 120.8 (h) 2 Systems operations training.
3. 120.8 (i) Commissioning report.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 35
B. Systems serving buildings larger than 50,000 square feet shall be commissioned as described in
California Energy Code (CEC), Title 24, Part 6, Subchapter 3, Nonresidential, High-Rise
Residential Hotel/Motel Occupancies, and Covered Processes – Mandatory Requirements,
Section 120.8, Building Commissioning. The following CEC requirements shall be completed
by Contractor:
1. 120.8 (g) Functional performance testing.
2. 120.8 (h) Documentation and training.
a. 120.8 (h) 1 Systems manual.
b. 120.8 (h) 2 Systems operations training.
3. 120.8 (i) Commissioning report.
C. Systems classified as “complex” as defined in California Energy Code (CEC), Title 24, Part 6,
Subchapter 1, All Occupancies – General Provisions, Section 100.1, Definitions and Rules of
Construction, shall be commissioned as described in Subchapter 3, Nonresidential, High-Rise
Residential Hotel/Motel Occupancies, and Covered Processes – Mandatory Requirements,
Section 120.8, Building Commissioning. The following CEC requirements shall be completed
by Contractor:
1. 120.8 (g) Functional performance testing.
2. 120.8 (h) Documentation and training.
a. 120.8 (h) 1 Systems manual.
b. 120.8 (h) 2 Systems operations training.
3. 120.8 (i) Commissioning report.
3.23 ACCEPTANCE REQUIREMENTS
A. The contractor shall complete the Acceptance Requirements of the California Building Energy
Efficiency Standards “Certificates of Acceptance” and submit such certificates to the authorities
having jurisdiction for approval and issuance of final occupancy permit.
3.24 DEMONSTRATION AND TRAINING
A. An authorized representative of the equipment manufacturer shall train Owner-designated
personnel in maintenance and adjustment of equipment. The representative may be an
employee of the equipment manufacturer, or a manufacturer-certified contractor. Submit
written certification from the manufacturer stating that the representative is qualified to perform
the Owner training for the equipment installed.
1. As part of the submittal process, provide a training agenda outlining major topics and
time allowed for each topic.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Basic Plumbing Materials And Methods
(11-30-15) 22 00 50 - 36
2. Some items of specified equipment require that training must be performed by the
manufacturer, using manufacturer’s employees. See specific equipment Articles in these
Specifications for this requirement.
3. Contractor shall provide three copies of certification by Contractor that training has been
completed, signed by Owner’s representative, for inclusion in Operation and
Maintenance Manual. Certificates shall include:
a. Listing of Owner-designated personnel completing training, by name and title.
b. Name and title of training instructor.
c. Date(s) of training.
d. List of topics covered in training sessions.
4. Refer to specific equipment Articles for minimum training period duration for each piece
of equipment.
END OF SECTION 22 00 50
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Piping Systems
(11-30-15) 22 10 00 - 1
SECTION 22 10 00 - PLUMBING PIPING SYSTEMS
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Pipe and fittings.
B. Water hammer arrestors.
C. Cleanouts.
D. Hopper drains.
1.2 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
B. Section 22 00 50 Basic Plumbing Materials and Methods.
1.3 ADDITIONAL REQUIREMENTS
A. Furnish and install any incidental work not shown or specified which is necessary to provide a
complete and workable system.
B. Coordinate all of work in this Section with all of the trades covered in other Sections of the
Specifications to provide a complete, operable and sanitary installation of the highest quality
workmanship.
C. All plumbing work required in the course of this contract shall be performed in strict
accordance with all codes and regulations. Plumbing work done under this contract shall not
adversely affect the operation of the existing plumbing systems. All materials shall be new and
shall match existing.
1.4 DESCRIPTION OF WORK
A. Furnish and install all plumbing work indicated on the drawings and described herein.
1.5 QUALITY ASSURANCE
A. Manufacturer's Qualifications: Firms regularly engaged in manufacture of plumbing piping
systems products, of types, materials, and sizes required, whose products have been in
satisfactory use in similar service for not less than 5 years.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Piping Systems
(11-30-15) 22 10 00 - 2
B. Contractor's Qualifications: Firm with at least 5 years of successful installation experience on
projects with piping systems work similar to that required for project.
C. Requirements of Regulatory Agencies: The publications listed below form a part of this
specification; comply with provisions of these publications except as otherwise shown or
specified.
1. Plumbing Code Compliance: Comply with applicable portions of California Plumbing
Code pertaining to selection and installation of plumbing materials and products.
a. NSF Compliance:
1) Pipe, tube, and fittings used in potable water systems intended to supply
drinking water shall meet the requirements of NSF-61 2010a, “Drinking
Water System Components – Health Effects.”
2) Plastic potable water-service piping shall meet the requirements of NSF 14
2010, “Plastic Piping Components and Related Materials.”
2. California Health and Safety Code Compliance: For products covered under the scope of
HSC 116875 for potable water service. Products for potable water service shall be third-
party certified by an approved laboratory as complying with California Health and Safety
Code Section 116875.
1.6 SUBMITTALS
A. Product Data: Submit manufacturer's technical product data and installation instructions for
plumbing piping systems materials and products.
B. Record Drawings: At project closeout, submit Record Drawings of installed piping systems, in
accordance with requirements of Division 01.
C. Maintenance Data: Submit maintenance data and parts lists for plumbing piping systems
materials and products. Include this data, product data, shop drawings, and record drawings in
Operation and Maintenance Manual; in accordance with requirements of Division 01.
D. Pipe, pipe or plumbing fittings, fixtures, solder and flux installed in a system providing water
for human consumption shall comply with lead free requirements of the California Health and
Safety Code Section 116875. Provide submittal information for products third-party certified
by an approved laboratory as complying with California Health and Safety Code Section
116875.
1.7 JOB CONDITIONS
A. Cooperation with other trades: Coordinate Work of this Section with that of other Sections to
ensure that Work is carried out in an orderly fashion.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Piping Systems
(11-30-15) 22 10 00 - 3
B. Coordinate with other trades all equipment locations, pipe, duct and conduit runs, electrical
outlets and fixtures, air inlets and outlets, and structural and architectural features. Provide
information on location of piping and seismic bracing to all other trades as required for a
completely coordinated project.
PART 2 - PRODUCTS
2.1 MATERIALS AND PRODUCTS
A. Provide piping materials and factory-fabricated piping products of sizes, types, pressure ratings,
temperature ratings, and capacities as indicated. Provide materials and products complying with
California Plumbing Code. Where more than one type of material or product is indicated,
selection from materials or products specified is Contractor's option.
2.2 PIPE AND FITTINGS INSIDE BUILDINGS AND BELOW COVERED WALKS AND
CORRIDORS
A. Drain and Waste Pipe Above Grade: Cast iron soil pipe and fittings, asphaltic coated,
conforming to ASTM A888 and Cast Iron Soil Pipe Institute Standard (CISPI) 301 and so
marked. Pipe and fittings shall be as manufactured by AB&I, Charlotte, Tyler Pipe, or equal.
Pipe and fittings shall be the products of a single manufacturer. At Contractor’s option, vertical
piping above floor from lavatories, sinks, and drinking fountains may be Schedule 40
galvanized steel pipe with black cast iron drainage fittings, or DWV copper pipe and fittings.
1. Joints above grade: No-Hub pipe conforming to ASTM A888 and CISPI 301. Couplings
conforming to ASTM 1277 and CISPI 310, with stainless steel bands. Provide products
by ANACO-Husky, Tyler, Ideal or equal. Provide sway brace at 20'-0" maximum
spacing for suspended pipe with No-Hub joints. Provide a brace on each side of a change
in direction of 90 degrees or more. Brace riser joints at each floor and at 15 foot
maximum intervals (also see Specification Section 22 00 50).
B. Drain and Waste Pipe Below Grade: Cast iron soil pipe and fittings, asphaltic coated,
conforming to ASTM A888 and CISPI 301 and so marked. Pipe and fittings shall be as
manufactured by AB&I, Charlotte, Tyler Pipe, or equal. Pipe and fittings shall be the products
of a single manufacturer. At Contractor’s option, hub and spigot cast iron soil pipe and fittings,
asphaltic coated, conforming to ASTM A-74 and so marked, may be used.
1. Joints below grade: ANACO-Husky SD 4000, Clamp-All 125, or equal couplings and
No-Hub fittings, meeting the requirements of FM 1680, SD Class I and ASTM C1540.
2. Joints below grade (hub and spigot option): neoprene gaskets conforming to ASTM
C564, as manufactured by Ty-Seal, Dual-Tite, or equal.
C. Vent Pipe:
1. 3 inch and larger: Cast iron soil pipe and fittings conforming to ASTM A888 and Cast
Iron Soil Pipe Institute Standard 301 and so marked.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Piping Systems
(11-30-15) 22 10 00 - 4
2. 2-1/2 inch and smaller: Schedule 40 galvanized steel pipe with black cast iron drainage
fittings, or DWV copper pipe and fittings.
3. Vent pipe buried in ground and to 6 inches above ground: Cast iron soil pipe and fittings
conforming to ASTM A888 and Cast Iron Soil Pipe Institute Standard 301 and so
marked. Joints in cast iron vent pipe shall be the same as specified for cast iron waste
pipe below ground.
D. Water Pipe (Tempered Water, Tempered Water Return, Hot Water, Hot Water Return and Cold
Water): ASTM B88, Type L copper tubing, hard-temper, with wrought copper fittings. Provide
full solder cup for all fittings. Capped or plugged outlets shall be Schedule 40 screwed brass.
Water piping below slab: ASTM B88, Type K copper tubing, hard temper, with wrought
copper fittings. At Contractor’s option, pipe runs below slab having no branches may be ASTM
B88, Type K annealed copper tubing without joints. See Section 22 00 50 for pipe protection
requirements for below slab copper piping.
E. Condensate Drain Piping:
1. Inside buildings provide ASTM B88, Type L copper tubing and fittings. Provide Wye
fittings with capped cleanout plug for tubing up to 1 inch size. Provide wrought or cast
DWV fittings for sizes 1-1/4 inch and larger.
2. Connect condensate drains to mechanical equipment per equipment manufacturer's
recommendations; provide P-trap where required. Slope piping to drain, with 1 inch in
10 foot minimum pitch. Provide di-electric couplings or unions at connections to
dissimilar materials.
3. Where Drawings indicate installation of mechanical equipment on spring isolation rails
or spring mounted curbs, provide threaded metal connector at mechanical equipment,
Metraflex Model SST or BST, Unisource Mfg. Co. “V” connector, or equal, CSA listed
for 4 inches of movement. Arrange flexible connection to insure drainage of condensate
under all installation conditions, and arrange for support of flexible connection at each
end of the connector, to insure alignment at all times.
4. Where condensate drain P-traps are required, install trap using Wye fitting on inlet and
outlet of trap. Provide cap on top of each Wye, made removable for cleaning and
inspection. Drill 1/8 inch diameter hole in cap at outlet of the trap to allow venting of the
system. Minimum depth of trap should be 4 inches, or as recommended by the
manufacturer in printed literature.
5. Provide cleanout tees or “Y” at each change in direction.
F. Condensing-Type Equipment Condensate Drain Pipe: CPVC pipe and fittings conforming to
ASTM 2618.
1. Provide CPVC condensate drain pipe for condensing water heaters, furnaces, and where
shown on Drawings.
2. Provide continuous support for horizontal piping.
3. Piping and fittings shall be as manufactured by Spears Manufacturing, Charlotte Pipe and
foundry Co., or equal.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Piping Systems
(11-30-15) 22 10 00 - 5
2.3 WATER HAMMER ARRESTORS
A. Provide water hammer arrestors conforming to lead-free requirements of California Health and
Safety Code Section 116875, with nesting type bellows contained within a casing having
sufficient displacement volume to dissipate the calculated kinetic energy generated in the piping
system. Water hammer arrestors shall be sized for type and number of fixtures served. Provide
all stainless steel shell construction with stainless steel bellows and threaded connection to
water system.
B. Water hammer arrestors shall be certified under P.D.I. Standard WH201 and by ASSE Standard
1010.
C. Select units in accordance with the requirements of Plumbing and Drainage Institute Standard
P.D.I. WH201. Install above ceilings or behind wall access door at each plumbing fixture, or
where plumbing fixtures are installed in groups, at each group of fixtures.
D. Manufacturers: Subject to compliance with requirements, available manufacturers offering
products that may be incorporated into the Work include the following, or equal:
Josam Company, series 75000
Smith (Jay R.) Mfg. Co., Hydrotrol 5005-5050
Mifab, series WHB
2.4 CLEANOUTS
A. General: Install cleanouts of same diameter as pipe (4 inch maximum) in all horizontal soil and
waste lines where indicated and at all points of change in direction. Cleanouts shall be located
not less than 18 inches from building construction so as to provide sufficient space for rodding.
No horizontal run over 50 feet inside buildings or 100 feet outside buildings shall be without
cleanout, whether shown on Drawings or not. Provide two-way cleanouts where indicated on
drawings, and where required for satisfactory use.
1. Provide cleanouts in waste drop from each sink and urinal.
2. Provide one wrench for each size and type of cleanout used. Turn over to Owner at
completion of the project, and obtain receipt. Place receipt in Operation and
Maintenance Manuals.
B. Cleanouts in floor and in concrete sidewalks: Ducco Cast Iron with nickel bronze top, clamping
collar and ABS plastic plug: Zurn ZN-1400-KC, or equal, with square or round top to suit floor
construction.
C. Cleanouts in composition floors: Zurn ZN-1400-X-DX, or equal (nickel bronze top).
D. Cleanouts in concealed, aboveground cast-iron soil or waste lines: Zurn Z-1440A, or equal, with
ABS plastic plug.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Piping Systems
(11-30-15) 22 10 00 - 6
E. Cleanouts in walls: Zurn Z-1441 or Z-1443, or equal, with stainless steel cover. Provide long
sweep elbow or combination wye at connection to riser and install with surface of cleanout
within 1/2 inch of front face of finished wall.
1. Where space does not permit the above installation, provide Zurn Z-1446, or equal, with
stainless steel access cover, and vandal resistant screw.
2. Install face of cleanout plug within 1/2 inch of front face of finished wall.
F. Manufacturers: Subject to compliance with requirements, available manufacturers offering
products that may be incorporated into the Work include the following, or equal:
Zurn
J.R. Smith
Josam
2.5 HOPPER DRAINS
A. Manufacturers: Drawing schedules indicate Basis of Design products. Subject to compliance
with requirements, provide product indicated on Drawings, or comparable product by one of the
following, or equal:
Zurn
J.R. Smith
PART 3 - EXECUTION
3.1 INSPECTION
A. Examine areas and conditions under which plumbing piping systems are to be installed. Do not
proceed with Work until unsatisfactory conditions have been corrected in manner acceptable to
Contractor.
B. Make all arrangements for the utilities required. Pay all costs involved in obtaining the services
including gas service and meter, water meter, pressure reducing valve, access boxes, street
work. Connect to site utilities. Verify the location of all services. No extra cost will be
allowed if services are not as shown.
C. At time of final connection, and prior to opening valve to allow pressurization of water and gas
piping from existing systems, on site or off site, perform a pressure test to indicate static
pressure of existing systems. If pressure on water piping is greater than 80 psi, or gas pressure
is not as indicated on Contract Documents, inform Architect immediately. Do not allow piping
systems to be pressurized without written consent of the Architect.
3.2 INSTALLATION OF WATER PIPING
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Piping Systems
(11-30-15) 22 10 00 - 7
A. Run all water piping generally level, free of traps or unnecessary bends, arranged to conform to
the building requirements, and to suit clearance for other mechanical work such as ducts, flues,
conduits, and other work. No piping shall be installed so as to cause unusual noise from the
flow of water therein under normal conditions.
B. Provide manufactured water hammer arrestors, sized and installed in accordance with Plumbing
and Drainage Institute Standard PDI WH201.
1. Locate water hammer arrestors at every plumbing fixture, or, where fixtures are located
in groups, at every group of fixtures, and as indicated on Drawings.
2. Install water hammer arresters above accessible ceilings, or install access doors for
service.
C. Install piping on room side of building insulation.
D. Check final location of rubber rings within couplings on PVC water piping with gauge or as
recommended by manufacturer. Make connection to valves with cast iron adapters connected to
water pipe with cast iron couplings. Furnish and install anchors or thrust blocks.
E. For all faucets, hose bibbs, or other water outlets delivering industrial hot and/or cold water,
provide a sign, permanently mounted, indicating "CAUTION: NON-POTABLE WATER, DO
NOT DRINK". Each sign shall be permanently engraved with black uppercase letters on a
yellow background. Letters shall be minimum 1-1/4 inch high.
3.3 INSTALLATION OF SANITARY AND STORM DRAINAGE SYSTEMS
A. Sewer Piping: Run all horizontal sanitary drain piping inside of building on a uniform grade of
not less than 1/4 inch per foot unless otherwise noted or later approved. Unless otherwise noted
on the plans, piping shall have invert elevations as shown and slope uniformly between given
elevations.
B. Run all drainage piping as straight as possible and provide easy bends with long turns; make all
offsets at an angle of 45 degrees or less.
C. Grade all vent piping so as to free itself quickly of any water condensation.
D. Where possible, join groups of vent risers together with one enlarged outlet through roof.
Maintain minimum of 10 foot horizontal or 3 foot vertical clearance from air intakes.
E. Hubless Cast Iron Joints: Comply with coupling manufacturer's installation instructions.
3.4 INSTALLATION OF CLEANOUTS
A. Cleanouts: Install in piping as indicated, as required by California Plumbing Code, at each
change in direction of piping greater than 45 degrees. Install at maximum intervals of 50 feet
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Piping Systems
(11-30-15) 22 10 00 - 8
for piping 4 inches and smaller and 100 feet for larger piping inside buildings, and at base of
each conductor.
B. Flashing Flanges: Install flashing flange and clamping device with each cleanout passing
through water resistant membrane.
3.5 INSTALLATION OF HOPPER DRAINS
A. Install hopper drain in wall, in sheet metal box, with access door.
1. Size access door and box to suit the size required for hopper drain and trap primer, and
solder all seams of box. Seal all penetrations to box with non-hardening waterproof
sealant. Provide locking door in occupied spaces.
B. Grind top and sides of funnel, if required, to suit wall thickness.
3.6 EQUIPMENT CONNECTIONS
A. Piping Runouts to Fixtures: Provide hot and cold water piping runouts to fixtures of sizes
indicated.
B. Mechanical Equipment Connections: Connect hot and cold water piping system and gas piping
system to mechanical equipment as indicated, and provide with shutoff valve and union for each
connection.
3.7 SPARE PARTS
A. Furnish to Owner, with receipt, one valve key for each key operated hydrant, bibb, or faucet
installed.
3.8 DOMESTIC WATER SYSTEM STERILIZATION
A. Clean and disinfect new or altered hot and cold water piping connected to domestic water
systems using methods prescribed by the Health Authority. If the Health Authority does not
prescribe methods, clean and disinfect new or altered hot and cold water piping using methods
given in the California Plumbing Code.
1. A water treatment company that has a current state EPA license to apply disinfectant
chlorine in potable water shall perform the procedure.
3.9 CARE AND CLEANING
A. Repair or replace broken, damaged, or otherwise defective parts, materials, and work. Leave
entire work in condition satisfactory to Architect. At completion, carefully clean and adjust
equipment, fixtures, and trim that are installed as part of this work. Remove labels from
stainless steel sinks, except 316 stainless steel sink labels should be retained to confirm that the
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Piping Systems
(11-30-15) 22 10 00 - 9
correct material has been provided. Leave systems and equipment in satisfactory operating
condition.
3.10 OPERATION TEST
A. Test each piece of equipment to show that it will operate in accordance with indicated
requirements.
3.11 TESTING AND BALANCING
A. See Section 23 05 93 of these specifications for testing and balancing requirements.
3.12 CLEANING UP
A. Upon completion of Work remove materials, equipment, apparatus, tools, and the like, and
leave premises clean, neat, and orderly.
END OF SECTION 22 10 00
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Piping Systems
(11-30-15) 22 10 00 - 10
This Page Left Intentionally Blank
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Fixtures
(11-30-15) 22 40 00 - 1
SECTION 22 40 00 - PLUMBING FIXTURES
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Water supplies and stops.
B. Plumbing fixture hangers and supports.
C. Refrigerator ice maker.
D. Dishwasher air gap fitting.
1.2 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
B. Section 22 00 50 Basic Plumbing Materials and Methods.
1.3 ADDITIONAL REQUIREMENTS
A. Furnish and install any incidental work not shown or specified which is necessary to provide a
complete and workable system.
B. Coordinate all of work in this Section with all of the Trades covered in other Sections of the
Specifications to provide a complete, operable and sanitary installation of the highest quality
workmanship.
1.4 DESCRIPTION OF WORK
A. Furnish and install all plumbing work indicated on the Drawings and described herein.
1.5 QUALITY ASSURANCE
A. Manufacturers: Firms regularly engaged in manufacture of plumbing fixtures of the type, style
and configuration required. All companies providing products with warranties must have been
engaged in manufacturing of such products for as long as the warranty states.
B. Plumbing Fixture Standards: Comply with applicable portions of the following codes and
requirements for all work in this section:
California Building Code – CBC
California Plumbing Code – CPC
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Fixtures
(11-30-15) 22 40 00 - 2
California Health and Safety Code
American National Standards Institute - ANSI
Federal Standards - F.S.
National Sanitary Foundation – NSF International
C. ANSI Standards: Comply with ANSI/NSF 61, “Drinking Water System Components – Health
Effects.”
D. PDI Compliance: Comply with standards established by Plumbing and Drainage Institute
pertaining to plumbing fixture supports.
E. Americans with Disabilities Act (ADA).
F. California Health and Safety Code Compliance: For products covered under the scope of HSC
116875 for potable water service. Products for potable water service shall be third-party
certified by an approved laboratory as complying with California Health and Safety Code
Section 116875.
1.6 SUBMITTALS
A. Product Data: Submit manufacturer's specifications for plumbing fixtures and trim, including
catalog cut of each fixture type and trim item furnished.
B. Maintenance Data: Submit maintenance data and parts lists for each fixture type and trim item,
including instructions for care of finishes. Include this data in Operation and Maintenance
Manual.
C. Pipe, pipe or plumbing fittings, fixtures, solder and flux installed in a system providing water
for human consumption shall comply with lead free requirements of the California Health and
Safety Code Section 116875. Provide submittal information for products third-party certified
by an approved laboratory as complying with California Health and Safety Code Section
116875.
1.7 QUALITY ASSURANCE
A. California Green Building Standards Code Requirements:
1. Tank-type water closets shall be certified to the performance criteria of the U.S. EPA
WaterSense Specification for Tank-Type Toilets.
2. Single Showerheads shall be certified to the performance criteria of the U.S. EPA
WaterSense Specification for Showerheads.
PART 2 - PRODUCTS
2.1 PLUMBING FIXTURES
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Fixtures
(11-30-15) 22 40 00 - 3
A. General: Provide factory fabricated fixtures of type, style and material indicated. For each type
fixture, provide fixture manufacturer's standard trim, carrier, seats, and valves as indicated by
their published product information; either as designed and constructed, or as recommended by
the manufacturer, and as required for a complete, installation. Where more than one type is
dedicated, selection is Contractor's option; but, all fixtures of same type must be furnished by
single manufacturer.
1. Take special care with the roughing-in and finished plumbing where batteries of fixtures
occur.
2. Take location and mounting heights for roughing-in from Architectural Drawings.
3. Follow schedule on Plumbing Drawings for roughing-in connections. Set roughing-in for
all fixtures exactly as per measurements furnished by the manufacturers of the fixtures
used.
4. Roughing-in for lavatories and sinks shall be brought in through the wall under the
centerline of the drain from the fixture wherever possible and as close to the fixture as
possible.
2.2 MATERIALS
A. Provide materials that have been selected for their surface flatness and smoothness. Exposed
surfaces that exhibit pitting, seam marks, roller marks, foundry sand holes, stains, discoloration,
or other surface imperfections on finished units are not acceptable.
B. Where fittings, trim and accessories are exposed or semi-exposed, provide, chromium plated 17
gauge seamless brass and match faucets and fittings. Provide 17 gauge seamless copper or
brass where not exposed.
C. Handles on all faucets and stops shall be all metal chromium plated.
2.3 PLUMBING FITTINGS, TRIM AND ACCESSORIES
A. Water Outlets: At locations where water is supplied (by manual, automatic or remote control),
provide commercial quality faucets, valves, or dispensing devices, of type and size indicated,
and as required to operate as indicated.
1. Include manual shutoff valves and connecting stem pipes to permit outlet servicing
without shut-down of water supply piping systems.
B. P-Traps: Include IAPMO approved removable P-traps where drains are indicated for direct
connection to drainage system. P-Traps shall be less trap screw cleanout, and incorporate a
chrome plated cast brass body, brass connection nuts, 17 gauge seamless brass wall return and
chrome plated wall escutcheon to match trap finish.
C. Carriers: Provide cast iron supports for fixtures of graphitic gray iron, ductile iron, or malleable
iron as indicated. Where the carrier for wall mounted water closets are installed more than 6
inches behind the finished wall, provide water closet support for wide pipe chase.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Fixtures
(11-30-15) 22 40 00 - 4
D. Fixture Bolt Caps: Provide manufacturer's standard exposed fixture bolt caps finished to match
fixture finish.
E. Escutcheons: Where fixture supplies and drains penetrate walls in exposed location, provide
chrome-plated cast brass escutcheons with setscrews.
F. Aerators: Provide aerators of types approved by Health Departments having jurisdiction.
Delete aerators where not allowed by CPC for health care occupancies.
G. Comply with additional fixture requirements contained in Fixture Schedule shown on the
drawings.
2.4 MANUFACTURERS
A. In accordance with California Plumbing Code, provide indelibly marked or embossed
manufacturers name or logo, arranged so as to be visible after installation.
B. Manufacturers: Drawing schedules indicate Basis of Design products. Subject to compliance
with requirements, provide product indicated on Drawings, or comparable product by one of the
following:
1. Vitrified China Plumbing Fixtures:
American Standard, U.S. Plumbing Products
Crane Plumbing
Eljer Plumbingware Div., Wallace-Murray Corp.
Kohler Co.
VitrA
2. Modular Lavatories:
Badeloft
Bradley
Acorn
Willoughby Industries, Inc.
3. Plumbing Trim:
McGuire Manufacturing Co., Inc.
Delta Commercial
Chicago Faucet Co.
T&S Brass and Bronze Works, Inc.
4. Flush Valves:
Sloan Valve Co.
Zurn Industries, Hydromechanics Div.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Fixtures
(11-30-15) 22 40 00 - 5
Toto USA, Inc.
5. Faucets:
Chicago Faucet Co.
Symmons Scott
T&S Brass and Bronze Works, Inc.
Delta Commercial
6. Fixture Seats:
Church Seat Co.
Bemis Mfg. Co.
Beneke Corp.
7. Service Sinks:
Acorn
American Standard
Kohler Co.
Williams Serviceptor
Florestone
8. Stainless Steel Sinks:
Elkay Mfg. Co.
Just Mfg. Co.
Haws Corporation
9. Fixture Carriers:
Josam Mfg. Co.
J. R. Smith
Tyler Pipe; Wade Div.
Zurn Industries; Hydromechanics Div.
Mifab, Inc.
2.5 FLUSH VALVE REQUIREMENTS
A. Metering flush valves where required and specified shall be non-hold open type with exposed
parts chrome plated. Conform to all codes and manufacturers' recommendations. All
diaphragms are to have multiple filtered bypass and be chloramine resistant synthetic rubber
with internal components suitable for l80 degree hot water to l50 pounds pressure, plastic or
leather diaphragm not acceptable.
2.6 FIXTURE CONNECTIONS
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Fixtures
(11-30-15) 22 40 00 - 6
A. Make connection between fixtures and flanges on soil pipe absolutely gastight and watertight
with neoprene type gaskets (wall hung fixtures) or bowl wax (floor outlet fixtures). Rubber
gaskets or putty will not be permitted.
B. Provide fixtures not having integral traps with P-traps of chromium-plated 17 gauge cast brass,
with 17 gauge seamless brass wall return, connected to concealed waste in wall and sanitary
fittings. Provide IAPMO approval for trap, and provide less trap screw cleanout.
1. Manufacturers: Subject to compliance with requirements, available manufacturers
offering products that may be incorporated into the Work include the following, or equal:
Dearborn Brass, Commercial series with brass nuts
Delta Commercial
McGuire Manufacturing Co., Inc.
C. Connections from stacks or horizontal wastes to wall or floor finish for wastes from lavatories,
urinals, sinks, and drinking fountains and connection between floor drains and traps shall be IPS
85 percent red brass pipe.
D. Unions on waste pipes on fixture side of traps may be slip or flange joints with soft rubber or
lead gaskets. Traps shall rough in full size to waste and vent connection, using deep escutcheon
plate to cover wall penetration. Compression adaptor extensions or sweat adaptors are not
acceptable.
2.7 WATER SUPPLIES AND STOPS
A. Provide 85 percent IPS threaded red brass nipple, conforming to the lead-free requirements of
California Health and Safety Code Section 116875, securely anchored to building construction,
for each connection to stops, hose bibbs, etc. Each fixture, except hose bibbs, shall have stop
valves installed on water supply lines.
B. Provide water supplies to fixtures with compression shut-off stops with IPS inlets and lock
shield-loose key handles. Provide combination fixtures with compression stop and IPS inlet on
each water supply fitting. Provide lock shield-loose key handle for each stop.
C. Provide 1/2 inch riser tubes with reducing coupling for fixtures, unless otherwise noted.
D. Provide cast brass escutcheon.
E. Furnish shut-off valves on hose bibbs where directly connected to mains with no intervening
valves.
F. Manufacturers: Subject to compliance with requirements, available manufacturers offering
products that may be incorporated into the Work include the following, or equal:
BrassCraft Manufacturing model SR37XC stop with 3-12AC riser and 647 escutcheon.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Fixtures
(11-30-15) 22 40 00 - 7
McGuire Manufacturing Company, Inc. model LFH2167LK.
Watts model LF890 203LK.
2.8 PLUMBING FIXTURE HANGERS AND SUPPORTS
A. Residential type fixture supports are not acceptable.
B. Install wall mounted water closets with combination support and waste fittings, with feet of
support securely anchored to floor.
C. Install floor mounted water closets with J.R. Smith, Zurn, or equal government pattern cast iron
closet flanges with brass bolts, nuts, washers, and porcelain caps secured with Spackle.
D. Install the following fixtures on concealed support with feet of support securely anchored to
floor. Anchor top of support to wall construction in an approved manner.
1. Wall hung lavatories.
2. Wall mounted urinals.
2.9 PLUMBING FIXTURES
A. Install all plumbing fixtures at height indicated on Architectural Drawings. Where mounting
height is not indicated, install at height required by Code.
B. Special Requirements For Accessible Fixtures:
1. Operating handle or valve for accessible water closets, urinals, lavatories, and sinks shall
operate with less than 5 pounds force. Metering faucets shall be adjusted to operate
between 10 and 15 seconds.
2. Insulate exposed waste piping and domestic water supplies below accessible fixtures with
CBC access code compliant molded “closed-cell” vinyl covers. Covers shall be installed
using vandal resistant fasteners and must be removable. Covers shall meet flame spread
rating not to exceed 25 and smoke density not to exceed 50 when tested in accordance
with ASTM E-84, and shall comply with the requirements of California Code of
Regulations, Title 24. Plumberex – Handy Shield, Johns Manville – Zeston 2000, or
equal.
C. Refrigerator Ice Maker:
1. Manufacturers: Drawing schedules indicate Basis of Design products. Subject to
compliance with requirements, provide product indicated on Drawings, or comparable
product by one of the following, or equal:
Guy Gray
Water-Tite
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Fixtures
(11-30-15) 22 40 00 - 8
PART 3 - EXECUTION
3.1 PRODUCT HANDLING AND PROTECTION
A. Deliver packaged materials in their original, unopened wrapping with labels intact. Protect
materials from water, the elements and other damage during delivery, storage and handling.
3.2 PREPARATORY PROVISIONS
A. The Contractor is responsible for the examination and acceptance of all conditions affecting the
proper construction and/or installation of the Work of this Section. Do not proceed until all
unsatisfactory conditions have been corrected. Commencing work will be construed as
acceptance of all conditions by the Contractor as satisfactory for the construction and/or
installation of the Work.
3.3 INSPECTION AND PREPARATION
A. Examine roughing-in work of domestic water and waste piping systems to verify actual
locations of piping connections prior to installing fixtures. Also examine floors and substrates,
and conditions under which fixture work is to be accomplished. Correct any incorrect locations
of piping, and other unsatisfactory conditions for installation of plumbing fixtures. Do not
proceed with work until unsatisfactory conditions have been corrected.
B. Install plumbing fixtures of types indicated where shown and at indicated heights; in accordance
with fixture manufacturer's written instructions, roughing-in drawings. Ensure that plumbing
fixtures comply with requirements and serve intended purposes. Comply with applicable
requirements of the National Standard Plumbing Code pertaining to installation of plumbing
fixtures.
C. Fasten plumbing fixtures securely to supports or building structure; and ensure that fixtures are
level and plumb. Secure plumbing supplies to blocking behind or within wall construction so as
to be rigid, and not subject to pull or push movement.
D. Install CBC accessible fixtures in accordance with Chapter 4 California Plumbing Code, and
Chapters 11A and 11B California Building Code.
E. Refer to Division 26 for wiring for electronic flush valves.
3.4 INSTALLATION OF FAUCETS
A. Provide 85 percent IPS red brass pipe, conforming to lead-free requirements of California
Health and Safety Code Section 116875, securely anchored to building construction, for each
connection to faucets, stops, hose bibbs, etc. Each fixture, except hose bibbs, shall have a stop
valve installed on water supply lines to permit repairs without shutting off water mains.
B. Adjust metering faucets to run for 10 to 15 seconds.
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Fixtures
(11-30-15) 22 40 00 - 9
3.5 CLEAN AND PROTECT
A. Clean plumbing fixtures of dirt and debris upon completion of installation.
B. Protect installed fixtures from damage during the remainder of the construction period.
C. Grout voids between all fixtures and adjacent surfaces with white Dow Silicone Sealant,
arranged to shed water.
3.6 FIELD QUALITY CONTROL
A. Upon completion of installation of plumbing fixtures and after units are water pressurized, test
fixtures to demonstrate capability and compliance with requirements. When possible, correct
malfunctioning units at site, then retest to demonstrate compliance; otherwise, remove and
replace with new units and proceed with retesting.
3.7 EXTRA STOCK
A. General: Furnish special wrenches and other devices necessary for servicing plumbing fixtures
and trim to Owner with receipt. Furnish one device for every ten units.
END OF SECTION 22 40 00
CITY OF BERKELEY Specification No. 16-10983-C
1947 CENTER STREET BUILDING RENOVATION
PHASE 2
Berkeley, California 94704
Plumbing Fixtures
(11-30-15) 22 40 00 - 10
This Page Left Intentionally Blank
FE FE
FE
FE
FE
FE
FE
EXISTING GYP BD CEILING TO REMAIN
EXISTING ACT 24 X 24 TO REMAIN
OPEN TO STRUCTURE
REMOVE EXISTING GYP BD CEILING
REMOVE EXISTING ACT 24 X 24.SALVAGE UNDAMAGED TILES FOR REINSTALLATION
EXISTING (E) TO REMAIN
DEMOLITION
DEMOLITION RCP LEGEND
[ACT (E)]
[ACT (D)]
[GYP BD (E)]
[GYP BD (D)]
[OTS]
NOT IN SCOPE
1 2
G
H
F
E
D
C
B
A
4 5 6 7 8
[ACT (D)]+9' - 4"
[ACT (D)]+9' - 8"
[OTS]+12' - 6"
[ACT (D)]+9' - 11"
[OTS]+12' - 4"
[ACT (E)]+8' - 4"
[ACT (D)]+8' - 4"
[OTS]+12' - 4"
[OTS]+12' - 4"
[ACT (E)]+9' - 8"
[OTS]+12' - 4"
[OTS]+12' - 4"
[ACT (D)]+9' - 2"
[ACT (E)]+8' - 6"
[ACT (D)]+9' - 8"
[ACT (D)]+8' - 9"
[ACT (D)]+8' - 6"
[ACT (D)]+8' - 4"
[ACT (D)]+8' - 4"
[ACT (D)]+9' - 9"
[ACT (D)]+9' - 9"
[ACT (D)]+9' - 5"
[ACT (D)]+8' - 6"
[GYP BD (E)]+9' - 3"
[ACT (E)]+9' - 3"
[ACT (E)]+9' - 3"
[GYP BD (E)]+8' - 5"
[ACT (D)]+9' - 7"
[ACT (D)]+9' - 3"
[ACT (E)]+8' - 6"
[ACT (E)]+9' - 4"
[ACT (D)]+9' - 9"
[ACT (D)]+9' - 9"
345IT
320BOPEN OFFICE
320AOPEN OFFICE
350CONFERENCE
352OFFICE
310AOPEN OFFICE
310BOPEN OFFICE
311CONFERENCE/TRAINING
301LOBBY
330PLAN CHECK
331OFFICE
347OFFICE
346OFFICE
341OFFICE
342STORAGE
344BREAK
307STORAGE
361OFFICE
362OFFICE
334RECEPTION
325SHARED OFFICE
[OTS]+12' - 4"
343STORAGE
[ACT (D)]+8' - 4"
[ACT (E)]+8' - 3"
CONFERENCE/TRAINING321
MECH322
CONFERENCE360
ELEC303
PSCCOORDINATOR
333
B&S OFFICE335
B&S OFFICE336
ASSISTANTBUILDINGOFFICIAL
351
332COPY
332AJAN
[GYP BD (E)]+7' - 4"
[ACT (E)]+8' - 6"
[ACT (D)]+9' - 11"
MEN306
WOMEN304
HALL305
[ACT (D)]+9' - 0"
3
ELEV 2
ELEV 1
STAIR NO.2S2-3RD
STAIR NO.3S3-3RD
STAIR NO. 1S1-3RD
[GYP BD (E)]+7' - 4"
CLOSET325A
[GYB BD (E) -VIF]
[GYB BD (E) -VIF]
147' - 11 1/4"
15' - 1" VIF 23' - 8" VIF 23' - 6" VIF 23' - 6" VIF 23' - 7" VIF 23' - 7" VIF 15' - 0 1/4" VIF
D-18 TYPD-18
D-18 TYPD-18
D-18 TYPD-18
TYPD-37D-18 TYPD-18
D-18 TYPD-18
(E) (E)
(E)(E)
A2.3
1. REFER TO RCP FOR AREAS OF (E )CEILING TO REMAIN AND EXTENT OF DEMOLITION.REFER TO M/E/P/FP DRAWINGS FOR AREAS WHERE ADDITIONAL DEMOLITION ISREQUIRED. PATCH AND REPAIR CEILINGS TO MATCH EXISTING ADJACENT.
2. PATCH AND REPAIR ALL FLOOR SLABS, WALLS, AND CEILINGS AS REQ'D TO PROVIDESMOOTH SURFACE FOR (N) FINISHES.
3. SALVAGE ALL (E) BUILDING STANDARD ACOUSTICAL CEILING TILES DEEMED TO BE INLIKE-NEW CONDITION FOR FUTURE RE-USE. COORDINATE STORAGE LOCATION W/OWNER.
4. REMOVE (E) WINDOW TREATMENTS IN ALL AREAS, BASEMENT THROUGH FOURTHFLOORS.
5. (E) SHADES AT ALL SKYLIGHTS TO REMAIN.6. REFER TO RCP FOR CONTRACTOR'S OPTION TO REMOVE EXISTING CEILING GRID AND
LIGHTING AND PROVIDE NEW AT NO ADDITIONAL COST IN AREAS WHERE NEWDUCTWORK IS INDICATED TO BE INSTALLED.
GENERAL NOTES - RCP DEMO
architects and planners
Berkeley, CA 94710tel 510.542.2200fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
1/8" = 1'-0"
11/3
0/2
015 1
0:5
4:2
5 A
MC
:\Use
rs\p
ha
n.d
ung
\Do
cum
ents
\Berk
ele
y 1947 C
ente
r_p
han.d
ung
.rvt
A1.23.2
THIRD FLOORDEMO RCP
CITY OF BERKELEY1947 Center StreetBuilding Renovation
PHASE 2
BN
MB
Nov. 4, 2015
21401
BID SET
1947 Center StreetBerkeley CA
▲N
1/8" = 1'-0"A1.23.2THIRD FLOOR RCP - DEMO1
Keynote Legend
# KEYNOTE
D-18 REMOVE EXISTING CEILING GRID. SALVAGE 20% OF EXISTING CEILING TILES THATARE UNDAMAGED FOR EACH AREA FOR REINSTALLATION, REFER TO RCP
D-37 REMOVE EXISTING LIGHT FIXTURE, SED FOR ELECTRICAL WORK
▲N
FATS
ETFO LAC I
NROIA
R
CIL
EDESN
AECT
TICH
REN. 01-31-17
JANET TAM
No. C-14064
NO. DATE DESCRIPTIONA2.3 11/30/15 Phase 2 Addendum 03
(E)
(E)
(E)
(E) (E)
(E)
1 2
G
H
F
E
D
C
B
A
4 5 6 7 8
CONFERENCE/TRAINING321
MECH322
PLAN CHECKSUPERVISOR
OFFICE347
P/C SENIORENGINEER
OFFICE346
BUILDINGOFFICIAL
361
PWENGINEERINGPLAN CHECK
362
CONFERENCE360
PSC PLANCHECKER
352
ASSISTANTBUILDINGOFFICIAL
351
B&S OFFICE336
B&S OFFICE335
BREAK ROOM331
PSCCOORDINATOR
333
STAIR NO. 1S1-3RD
INFO CENTER +WELCOME DESK
301
PLAN CHECKEROFFICE
341
P/C PLANCHECKEROFFICE
342
P/C CHECKEROFFICE
343
PLAN CHECK /STATION 13
344
PERMIT CENTERPUBLIC WAITING
302
ELEC303
PSC PLANCHECK
COORDINATION330
CASHIER334
HOUSINGINSPECTOR
SUPERVISOR325
OPEN OFFICE -BLDG INSPECT
320
OPEN OFFICE -ADMIN
350
P/C ENGINEERPLAN CHECK
OFFICE348
WOMEN304
MEN306
P/C FIRE OFFICE349
PUBLIC / STAFFCONFERENCE
328
HALL305
OPEN OFFICE -PS329
PUBLIC SERVICECOUNTERS
310
[ACT - NEW]+9' - 6"
[ACT - NEW]+9' - 0"
B&S OFFICE326
[ACT - NEW]+9' - 0"
PLANCOLLATION &
STORAGE307
[ACT - NEW]+9' - 9"
BLDGINSPECTOR
SUPERVISOR363
CSS3 OFFICE359
[ACT - NEW]+9' - 6"
IT345
3
ELEV 2
ELEV 1
STAIR NO.2S2-3RD
STAIR NO.3S3-3RD
[GYP BD (E)]+8' - 5"
[ACT (E)]+8' - 6"
[ACT (E)]+9' - 4"
[ACT (E)]+8' - 3"
[ACT (E)]+8' - 4"
[OTS]+12' - 4"
[ACT (E)]+9' - 8"
[OTS]+12' - 4"
[OTS]+12' - 4"
HOUSINGINSPECTIONDESK AREA
323
HALL340
HALL340
HALL337
[OTS]+12' - 4" [OTS]
+12' - 4"
[OTS]+12' - 4"
[ACT - NEW]+9' - 11"
[ACT (E)]+8' - 6"
[ACT (E)]+9' - 3"
[ACT (E)]+9' - 3"
[ACT - NEW]+8' - 4"
[ACT - NEW]+8' - 4"
[GYB BD (E) -VIF]
JANITOR332
[OTS]
[OTS]
[ACT (E)]+8' - 6" [ACT - NEW]
+9' - 9"
[ACT - NEW]+9' - 3"
[ACT - NEW]+9' - 9"
ALIGN
[ACT - NEW]+8' - 6"
[ACT - NEW]+9' - 11"
[ACT - NEW]+9' - 9"
E-09
[ACT - NEW]+9' - 11"
[ACT - NEW]+9' - 8"
[ACT - NEW]+9' - 8"
[ACT - NEW]+9' - 9"
[ACT - NEW]+9' - 9"
[ACT - NEW]+9' - 5"
[ACT - NEW]+8' - 4"
[ACT - NEW]+8' - 4"
[ACT - NEW]+9' - 8"
E-09E-09
09-05
09-05
E-09
09-08 TYP09-08
E-09 TYPE-09
09-2509-25
12A8.42.2
._______
(E) (E)
(E)(E)
A2.3
EXISTING GYP BD CEILING TO REMAIN
EXISTING ACOUSTICAL CEILING 24 x 24 TO REMAIN
ACOUSTICAL WOOD PANEL
EXISTING (E) TO REMAIN
DEMOLITION
RCP LEGEND
[ACT (E)]
[GYP BD (E)]
GYP BD CEILING[GYP BD - NEW]
ACOUSTICAL CEILING 24 x 24[ACT - NEW]
PRIMARY DAYLIGHTING ZONE
SECONDARY DAYLIGHTING ZONE
OPEN TO STRUCTURE[OTS]
ACOUSTICAL FIBER BOARD
1. SEE ROOM FINISH SCHEDULE FOR ADDITIONAL INFORMATION.2. SEE ELECTRICAL DRAWINGS FOR ADDITIONAL INFORMATION3. SEE MECHANICAL DRAWINGS FOR ADDITIONAL INFORMATION4. WHERE CONCRETE STRUCTURE PENETRATES GWB - CUT GWB TIGHT TO
STRUCTURE. MUD, TAPE & SEAL, PAINT TO MATCH ADJACENT WALL5. PAINT ALL EXPOSED STRUCTURE, PIPES, DUCTS, CONDUIT AND ALL OTHER
EXPOSED ITEMS TYP6. ACOUSTIC TILE SHALL BE CENTERED IN ROOM UON7. REFER TO SHEET A8.40.2 AND A8.41.1 FOR TYPICAL SUSPENDED ACOUSTIC
CEILING AND TYP. GYP BOARD CEILING DETAILS.8. MANUAL SHADES AT EXTERIOR WALLS ARE MOUNTED INSIDE WINDOW OPENING,
TYP WHERE MOUNTING CONFLICTS OCCUR, IT SHOULD BE BROUGHT TOARCHITECT'S ATTENTION.
9. AT RESTROOMS, PATCH AND REPAIR CEILING TO MATCH ADJACENT
GENERAL NOTES - RCP
architects and planners
Berkeley, CA 94710tel 510.542.2200fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
1/8" = 1'-0"
11/3
0/2
015 1
0:5
5:2
6 A
MC
:\Use
rs\p
ha
n.d
ung
\Do
cum
ents
\Berk
ele
y 1947 C
ente
r_p
han.d
ung
.rvt
A2.43.2
THIRD FLOOR RCP
CITY OF BERKELEY1947 Center StreetBuilding Renovation
PHASE 2
BN
MB
Nov. 4, 2015
21401
BID SET
1947 Center StreetBerkeley CA
1/8" = 1'-0"A2.43.2THIRD FLOOR RCP1
▲N
Keynote Legend
# KEYNOTE
09-05 PATCH AND REPAIR CEILING AS REQUIRED AFTER INSTALLATION OF NEWMECHANICAL EQUIPMENT - SMD
09-08 PATCH AND PAINT EXISTING STRUCTURE AND MEP ELEMENTS AS REQUIRED TOMATCH NEW TYPICAL BUILDING STANDARD TREATMENTS. SEE DEMO PLAN FOREXTENTS.
09-25 PROVIDE ACOUSTIC TREATMENT PANELS DIRECT MOUNTED TO UNDERSIDE OFEXPOSED SLAB BETWEEN CONCRETE STRUCTURE FOR ROOMS 302 AND 310
12-02 MANUAL WINDOW SHADEE-09 CONTRACTOR'S OPTION TO REMOVE EXISTING CEILING GRID AND LIGHTING AND
PROVIDE NEW AT NO ADDITIONAL COST IN AREAS WHERE NEW DUCTWORK ISINDICATED TO BE INSTALLED. SEE MECHANICAL DRAWINGS FOR REFERENCE
▲N
FATS
ETFO LAC I
NROIA
R
CIL
EDESN
AECT
TICH
REN. 01-31-17
JANET TAM
No. C-14064
NO. DATE DESCRIPTION2 11/4/15 Permit Re-submittal
A2 11/16/15 Phase 2 Addendum 01A2.3 11/30/15 Phase 2 Addendum 03
FE
FE
FE
FE
E
D
4 5
WOMEN004
64 1/8"
HALL005
MEN006
LOBBY001
TYP
30"
26 1
/4"
34" AFF
17" AFFMAX
REGION OF PERMITTEDDOOR SWING
60"x59" CLEAR SPACE
48x60 CLEAR SPACE
A4.04.21W
1N
1E
1S
A4.04.2
2N
2S1
2W
A4.04.2
2S2
60" M
INEQ
EQ
EQ EQ
EQ EQ
52"
EQ EQ
60"
10-07
A-09
TYP10-08
4" M
AX.
32" M
IN
60"
22-04
31 1/2"SIM
TYP10-11
TYP10-08
TYP22-06
TYP22-06
48"
4" M
AX.
32" M
IN.
59"
36 3
/4"
_______A8.55.2
7
60" CLEAR
E
D
4 5
21 1
/2"
53"
64 1/8"
53"
6"
19 1/2"
43 3/4"
5' -
0"
14"
96"
6' - 7"
76 1
/2"
38 1
/2"
59 3/4"
4"
17 1/4" 17 1/2"
14 3/4"
18.5" AFF
18.5" AFF
15.5" AFFD-4
004WOMEN
006MEN
005HALL
TYPD-24
D-8
001LOBBY
TYPA-05
56 1
/2"
19"
34" AFF
33" AFF
69"
13"
TYPD-24D-26
TYPD-11
TYPD-14
D-9D-10
5' - 11"
2' -
8 1/
2" 1' -
4 1/
2"6
1/2"
TYPD-39
33 1
/2"
D-35
D
4 5
WOMEN104
67"
HALL105
LOBBY101
24 1
/2"
30"
A-07
A-06
34" AFF
A-06
2' - 0 1/2"
3' - 8"
17"-18"
A4.04.2
3N
3E
3S
3W
A4.04.2
4S1
4N
4W
8' -
3 1/
2"
REGION OF PERMITTEDDOOR SWING
60"x59" CLEAR SPACE
48x60 CLEAR SPACE
A-07
60"
2' -
10"
A4.04.2
4S2
TYP22-06
TYP10-08
A-09
4" M
AX
1' - 6"
10-07
5' -
0"
TYP10-11
TYP22-06
48"
TYP10-08
10-12
10-12
E
32" M
IN.
59"
40 1
/2"
_______A8.55.2
7
60" CLEAR
60"
4" M
AX
A2.3
E
D
4 5
22 1
/2"
67"
18.5" AFF
104WOMEN
106MEN
105HALL
101LOBBY
D-8
TYPA-05
D-11
23" AFF
TYPD-24
17.5" AFF
2' - 2"
4' - 5"
10' - 0 1/2"
8' -
3 1/
2"
4' - 10 1/2"2' - 6"2' - 6"
5' - 11"
15' -
10
1/2"
3' - 8"
5' -
5 1/
2"
6' - 3"
1' -
7"
D-9
TYPD-11
TYPD-24
TYPD-14
4' -
11"
1' - 5 3/4" 1' - 6 1/4"
4"
32 3/4"C-TOP28 1/2" BOTTOM EDGE
D-35
TYPD-39
D-26
D-10
TYPD-13
TYPD-13TYPD-14
EXISTING (E) TO REMAIN
DEMO (E) WALL AND ASSEMBLY
DEMOLITION PLAN LEGEND
NOT IN SCOPE
EXISTING (E) TO REMAIN
NEW CONSTRUCTION- FULL HEIGHT TO UNDERSIDEOF STRUCTURE, UON
FLOOR PLAN LEGEND
1. PATCH AND REPAIR ALL FLOOR SLABS, WALLS, AND CEILINGS AS REQ'D TO PROVIDESMOOTH SURFACE FOR (N) FINISHES
2. ALL EXISTING CONDITIONS TO REMAIN UNLESS NOTED OTHERWISE.3. EXISTING TOILET ROOM FIXTURES AND FINISHES TO REMAIN, UNLESS NOTED
OTHERWISE.4. WALL THICKNESSES ARE NOMINAL, UNLESS NOTED OTHERWISE.5. ALL DOORS, FRAMES, AND HARDWARE TO MATCH EXISTING BUILDING STANDARDS.6. PROVIDE BACKING FOR WALL-HUNG FIXTURES, PER A8.00.2
GENERAL NOTES - FLOOR PLANS
1. WALLS, DOORS, AND FIXTURES SHOWN DASHED ARE TO BE DEMOLISHED.CONTRACTOR SHALL PERFORM ALL DEMOLITION WORK REQUIRED TO CONSTRUCT THEFINISHED CONDITIONS AS SHOWN AND SPECIFIED. REFER TO FLOOR PLANS FORDIMENSIONS
2. DEMO (E) FINISH CEILINGS AT AREAS OF WORK ONLY, UON. REFER TO RCP FOR AREASOF (E ) CEILING TO REMAIN
3. DEMO (E) FINISH FLOORING AT AREAS OF WORK ONLY, UON.4. PATCH AND REPAIR ALL FLOOR SLABS, WALLS, AND CEILINGS AS REQ'D TO PROVIDE
SMOOTH SURFACE FOR (N) FINISHES.5. SALVAGE 20% OF EXISTING CEILING TILES THAT ARE UNDAMAGED FOR EACH AREA
FOR REINSTALLATION. COORDINATE STORAGE LOCATION W/ OWNER.
GENERAL NOTES - DEMOLITION
architects and planners
Berkeley, CA 94710tel 510.542.2200fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
As indicated
11/3
0/2
015 3
:03:4
2 P
MC
:\Use
rs\p
ha
n.d
ung
\Do
cum
ents
\Berk
ele
y 1947 C
ente
r_p
han.d
ung
.rvt
A4.01.2
ENLARGED DEMOAND FLOOR PLANS- RESTROOMS
CITY OF BERKELEY1947 Center StreetBuilding Renovation
PHASE 2
Checker
Author
Nov. 4, 2015
21401
BID SET
1947 Center StreetBerkeley CA
Keynote Legend
# KEYNOTE
D-4 REMOVE EXISTING DOOR. EXISTING FRAME TO REMAIN.D-8 REMOVE EXISTING WALL BASE, FLOOR FINISH AND FLOOR COVERING ADHESIVE.
CLEAN AND PREPARE SLAB FOR NEW FLOOR FINISH. REFER TO FINISH PLANS FOREXTENTS.
D-9 REMOVE EXISTING MIRROR, PREP WALL TO RECEIVE NEW MIRRORD-10 REMOVE EXISTING COUNTER, LAVATORIES, FIXTURES, AND SOAP DISPENSERS.
SALVAGE WHERE INDICATED. SEE PLAN.D-11 REMOVE EXISTING COMBO SEAT COVER-TOILET-TISSUE DISPENSER FROM
DEMOLISHED PARTITION, AND SALVAGE FOR REINSTALLATION IN NEW PARTITION.EXISTING IN-WALL DISPENSER INSTALLED TO REMAIN WHERE DIMENSIONS ARECODE COMPLIANT, VIF.
D-13 REMOVE EXISTING GRAB BAR FROM DEMOLISHED PARTITION, AND SALVAGE FORREINSTALLATION IN NEW PARTITION
D-14 REMOVE EXISTING TOILETS AND URINALS AND PREP FOR NEW. CAP OFF UTILITIES.TILE TO BE PATCHED TO MATCH EXISTING AFTER INSTALLATION OF NEW FIXTURES.
D-24 REMOVE (E) TOILET PARTITIONS. SALVAGE TOILET PAPER DISPENSERS FOR RE-USED-26 REMOVE (E) PARTITION IN ORDER TO CREATE ADEQUATE CLEARANCE. PATCH AND
REPAIR WALL TO RECEIVE NEW TILE.D-35 EXISTING COUNTER AND FIXTURES TO REMAIN. PLANE BOTTOM EDGE OF APRON TO
REACH ADA CLEARANCE AND REFINISH LAMINATE EDGE.D-39 REMOVE EXISTING URINAL PARTITIONS
Keynote Legend
# KEYNOTE
10-07 PROVIDE FULL HEIGHT MIRROR TO UNDERSIDE OF CEILING10-08 PROVIDE TOILET PARTITIONS10-11 PROVIDE URINAL PARTITIONS10-12 PROVIDE STAINLESS STEEL WALL-MOUNTED BABY CHANGING STATION22-04 PROVIDE WALL MOUNTED DOUBLE LAVATORY AND FAUCET. REINSTALL SALVAGED
SOAP DISPENSER. EXTEND WALL TILE TO 4" ABOVE SINK HEIGHT.22-06 PROVIDE TOILETS AND URINALS TO REPLACE (E) FIXTURES. REINSTALL SALVAGED
ACCESSORIES. REFER TO PLUMBING DRAWINGSA-05 (E) ACCESSIBLE DRINKING FOUNTAIN TO REMAIN.A-06 36" MIN. GRAB BAR, USE SALVAGED WHERE AVAILABLEA-07 42" MIN. GRAB BAR, USE SALVAGED WHERE AVAILABLEA-09 REBUILD PARTITION TO CREATE CODE COMPLIANT CLEARANCE. PATCH TILE TO
MATCH EXISTING, WHERE WALL WAS REMOVED. TILE NEW PARTITION TO MATCHEXISTING TILE.
1/4" = 1'-0"A4.01.2ENLARGED PLAN - BASEMENT RESTROOMS1
1/4" = 1'-0"A4.01.2ENLARGED DEMO PLAN - BASEMENT RESTROOMS2
1/4" = 1'-0"A4.01.2ENLARGED PLAN - FIRST FLOOR RESTROOMS3
1/4" = 1'-0"A4.01.2ENLARGED DEMO PLAN - FIRST FLOOR RESTROOMS4
▲N
FATS
ETFO LAC I
NROIA
R
CIL
EDESN
AECT
TICH
REN. 01-31-17
JANET TAM
No. C-14064
NO. DATE DESCRIPTION2 11/4/15 Permit Re-submittal
A2.3 11/30/15 Phase 2 Addendum 03
FEFE
E
D
4 5
18 1/2" 15"
22 1
/2"
18 1/4"
13 1/4"
41 3/4"
17.5" AFF
60 3/8"
97"
NO PARTITIONS41 1
/2"
68"
45"
263WOMEN
265MEN
264HALL
201LOBBY
TYPD-24
TYPD-24
D-8
TYPA-05
33" AFF
18" AFF 32.5" AFF
16" AFF
59 1/2"
10' - 1 1/2"
43 1
/4"
3' - 8 1/2"
6' -
1 1/
2"
20 1/4"
5"
2' -
0"
5' -
0"
6' - 4"
D-9D-10
3' -
1"
TYPD-39
D-35
TYPD-26
TYPD-11TYPD-14
3' -
2 1/
4" V
IF
TYPD-13
E
D
4 5
17 1/2" 17 1/2"
15 3/4"14"
23"
18.5" AFF
304WOMEN
306MEN
305HALL
301LOBBY
TYPD-24
TYPD-24
D-8
TYPA-05
34.25" AFF
TOP: 34 1/4"BOTTOM: 28 7/8"
15" AFF
6' -
0 1/
2"
4' - 9 1/2"
97 3
/4"
5' - 9 1/4"
3' -
11"
1' -
8 1/
2"
2' - 7 1/4"2' - 7 1/2"
11' - 1 1/2"
5' - 3 1/2"
4' -
8"
1' -
6 1/
2"
3' - 8 1/2"
7' -
10 1
/2"
1' - 5 1/2" 1' - 6 1/4"
D-26
D-10
D-9
4' -
11"
2' -
10 3
/4"
3 3/4"
D-35
TYPD-39
TYPD-11
TYPD-14
TYPD-13
TYPD-13
EXISTING (E) TO REMAIN
NEW CONSTRUCTION- FULL HEIGHT TO UNDERSIDEOF STRUCTURE, UON
FLOOR PLAN LEGEND
EXISTING (E) TO REMAIN
DEMO (E) WALL AND ASSEMBLY
DEMOLITION PLAN LEGEND
NOT IN SCOPE
E
D
4 5
18 1/4" 20 1/2"
MEN265
WOMEN263 HALL
264
A-07A-06
5' -
0"
30"
24 1
/2"
34" AFF
32.5" AFF
44 1/2"
A4.04.2
5N
5E
5S
5W
A4.05.2
1N
A4.05.2
1S2
1W
1S1
REGION OF PERMITTEDDOOR SWING
60"x59" CLEAR SPACE
48x60 CLEAR SPACE
17"-
18"
TYP10-08
TYP22-06
A-09 TYP10-08
32" M
IN
60" M
IN.
A-09
6' - 4 3/4"
2' - 5 7/8" 2' - 5 7/8"
TYP10-11
TYP22-06
22-0410-07
4" M
AX.
32" M
IN.
48"59
"
18 1
/2"
_______A8.55.2
7
_______A8.55.2
7
4" M
AX.
38"
60" CLEAR
60"
4 5
18 3
/4"
MEN306
WOMEN304
HALL305
18"
23"
34" AFF
A-06
A-07
17"-
18"
A4.05.22W
2N
2E
2S
A4.05.2
3N
3W
3S1
A4.05.2
3S2
REGION OF PERMITTEDDOOR SWING
60"x59" CLEAR SPACE
48x60 CLEAR SPACE
17"-18"EQ EQ
5' - 7"
A-06A-07
4' -
1" 60"
EQEQ
60" CLEAR
22-0510-07
TYP22-06
TYP10-08
TYP22-06
4" M
AX. 3
2" M
IN
5' -
0"
6' - 6 1/2"
30" MIN
TYP10-11
TYP10-08
10-12
10-12
E
48"45"
59"
39"
_______A8.55.2
7
4" M
AX
A2.3
1. WALLS, DOORS, AND FIXTURES SHOWN DASHED ARE TO BE DEMOLISHED.CONTRACTOR SHALL PERFORM ALL DEMOLITION WORK REQUIRED TO CONSTRUCT THEFINISHED CONDITIONS AS SHOWN AND SPECIFIED. REFER TO FLOOR PLANS FORDIMENSIONS
2. DEMO (E) FINISH CEILINGS AT AREAS OF WORK ONLY, UON. REFER TO RCP FOR AREASOF (E ) CEILING TO REMAIN
3. DEMO (E) FINISH FLOORING AT AREAS OF WORK ONLY, UON.4. PATCH AND REPAIR ALL FLOOR SLABS, WALLS, AND CEILINGS AS REQ'D TO PROVIDE
SMOOTH SURFACE FOR (N) FINISHES.5. SALVAGE 20% OF EXISTING CEILING TILES THAT ARE UNDAMAGED FOR EACH AREA
FOR REINSTALLATION. COORDINATE STORAGE LOCATION W/ OWNER.
GENERAL NOTES - DEMOLITION
1. PATCH AND REPAIR ALL FLOOR SLABS, WALLS, AND CEILINGS AS REQ'D TO PROVIDESMOOTH SURFACE FOR (N) FINISHES
2. ALL EXISTING CONDITIONS TO REMAIN UNLESS NOTED OTHERWISE.3. EXISTING TOILET ROOM FIXTURES AND FINISHES TO REMAIN, UNLESS NOTED
OTHERWISE.4. WALL THICKNESSES ARE NOMINAL, UNLESS NOTED OTHERWISE.5. ALL DOORS, FRAMES, AND HARDWARE TO MATCH EXISTING BUILDING STANDARDS.6. PROVIDE BACKING FOR WALL-HUNG FIXTURES, PER A8.00.2
GENERAL NOTES - FLOOR PLANS
architects and planners
Berkeley, CA 94710tel 510.542.2200fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
As indicated
11/3
0/2
015 3
:03:1
9 P
MC
:\Use
rs\p
ha
n.d
ung
\Do
cum
ents
\Berk
ele
y 1947 C
ente
r_p
han.d
ung
.rvt
A4.02.2
ENLARGED DEMOAND FLOOR PLANS- RESTROOMS
CITY OF BERKELEY1947 Center StreetBuilding Renovation
PHASE 2
Checker
Author
Nov. 4, 2015
21401
BID SET
1947 Center StreetBerkeley CA
▲N
1/4" = 1'-0"A4.02.2
ENLARGED DEMO PLAN - SECOND FLOORRESTROOMS1
1/4" = 1'-0"A4.02.2
ENLARGED DEMO PLAN - THIRD FLOORRESTROOMS2
Keynote Legend
# KEYNOTE
D-8 REMOVE EXISTING WALL BASE, FLOOR FINISH AND FLOOR COVERING ADHESIVE.CLEAN AND PREPARE SLAB FOR NEW FLOOR FINISH. REFER TO FINISH PLANS FOREXTENTS.
D-9 REMOVE EXISTING MIRROR, PREP WALL TO RECEIVE NEW MIRRORD-10 REMOVE EXISTING COUNTER, LAVATORIES, FIXTURES, AND SOAP DISPENSERS.
SALVAGE WHERE INDICATED. SEE PLAN.D-11 REMOVE EXISTING COMBO SEAT COVER-TOILET-TISSUE DISPENSER FROM
DEMOLISHED PARTITION, AND SALVAGE FOR REINSTALLATION IN NEW PARTITION.EXISTING IN-WALL DISPENSER INSTALLED TO REMAIN WHERE DIMENSIONS ARECODE COMPLIANT, VIF.
D-13 REMOVE EXISTING GRAB BAR FROM DEMOLISHED PARTITION, AND SALVAGE FORREINSTALLATION IN NEW PARTITION
D-14 REMOVE EXISTING TOILETS AND URINALS AND PREP FOR NEW. CAP OFF UTILITIES.TILE TO BE PATCHED TO MATCH EXISTING AFTER INSTALLATION OF NEW FIXTURES.
D-24 REMOVE (E) TOILET PARTITIONS. SALVAGE TOILET PAPER DISPENSERS FOR RE-USED-26 REMOVE (E) PARTITION IN ORDER TO CREATE ADEQUATE CLEARANCE. PATCH AND
REPAIR WALL TO RECEIVE NEW TILE.D-35 EXISTING COUNTER AND FIXTURES TO REMAIN. PLANE BOTTOM EDGE OF APRON TO
REACH ADA CLEARANCE AND REFINISH LAMINATE EDGE.D-39 REMOVE EXISTING URINAL PARTITIONS
Keynote Legend
# KEYNOTE
10-07 PROVIDE FULL HEIGHT MIRROR TO UNDERSIDE OF CEILING10-08 PROVIDE TOILET PARTITIONS10-11 PROVIDE URINAL PARTITIONS10-12 PROVIDE STAINLESS STEEL WALL-MOUNTED BABY CHANGING STATION22-04 PROVIDE WALL MOUNTED DOUBLE LAVATORY AND FAUCET. REINSTALL SALVAGED
SOAP DISPENSER. EXTEND WALL TILE TO 4" ABOVE SINK HEIGHT.22-05 PROVIDE COUNTER, REINSTALL SALVAGED LAVATORIES, FIXTURES, AND SOAP
DISPENSERS22-06 PROVIDE TOILETS AND URINALS TO REPLACE (E) FIXTURES. REINSTALL SALVAGED
ACCESSORIES. REFER TO PLUMBING DRAWINGSA-05 (E) ACCESSIBLE DRINKING FOUNTAIN TO REMAIN.A-06 36" MIN. GRAB BAR, USE SALVAGED WHERE AVAILABLEA-07 42" MIN. GRAB BAR, USE SALVAGED WHERE AVAILABLEA-09 REBUILD PARTITION TO CREATE CODE COMPLIANT CLEARANCE. PATCH TILE TO
MATCH EXISTING, WHERE WALL WAS REMOVED. TILE NEW PARTITION TO MATCHEXISTING TILE.
1/4" = 1'-0"A4.02.2ENLARGED PLAN - SECOND FLOOR RESTROOMS3
1/4" = 1'-0"A4.02.2ENLARGED PLAN - THIRD FLOOR RESTROOMS4
FATS
ETFO LAC I
NROIA
R
CIL
EDESN
AECT
TICH
REN. 01-31-17
JANET TAM
No. C-14064
NO. DATE DESCRIPTION2 11/4/15 Permit Re-submittal
A2.3 11/30/15 Phase 2 Addendum 03
_______A8.52.2
6
10-1610-1610-1610-16
OPEN
A2.3
06-1706-1706-1706-17
_______A8.52.2
610-1610-1610-1610-16
OPEN OPEN
A2.3
A2.306-1706-1706-1706-17 06-1706-1706-1706-17
2' -
6"
11' -
1"
_______A8.52.2
6 10-1610-1610-1610-16
OPEN
A2.3
06-1706-1706-1706-17
GENERAL NOTES
1. REFER TO MECHANICAL, ELECTRICAL, SIGNAGE DRAWING FOR ADDITIONAL
INFORMATION.
2. REFER TO INTERIOR FINISH SCHEDULE FOR ADDITIONAL INFORMATION ON BASE,
FLOORING, WALL FINISH AND CEILING.
3. CABLE MOUNTED PENDANTS MOUNTED TO ALLOW 45 DEGREE SWING FROM
VERTICAL IN ANY DIRECTION WITHOUT CONTACTING OBSTRUCTION.
4. PATCH AND REPAIR OF (E) GYPSUM BOARD OR PLASTER SURFACE AS AFFECTED
BY DEMO AND WORK ASSOCIATED WITH ELECTRICAL AND TEL/AV WORK.
5. MANUAL SHADES ARE MOUNTED INSIDE WINDOW OPENING, TYP.
D
C
B
A
4 5 63
A4.12.2
A4.13.2
2N
A4.12.24
A4.12.2
3
2
A10.21.2
4
2W
INFO CENTER +
WELCOME DESK
301
CASHIER
334
PERMIT CENTER
PUBLIC WAITING
302
PUBLIC SERVICE
COUNTERS
310
PLAN CHECK /
STATION 13
344
30"AFF
06-0706-0706-0706-07
34"AFF
30"AFF
FILE
AR
EAFI
LE A
REA
06-0706-0706-0706-07
OPEN SHELVING, TYP
16' -
8"
06-0706-0706-0706-07
20' -
8"
53' - 3"
ELEV 2
ELEV 1
APPROVED PLANSINCOMING PLANS / AGENCIES
B&S
1
B&S
2
PS 8
ZONING
11
FIRE 4
ZONING
12
ENG
3
27-0227-0227-0227-02 27-0227-0227-0227-02
FILE
AR
EA
CA
RT
T1
29"AFF
40"AFF
40"AFF
29"AFF29"AFF
29"AFF
OPEN SHELVING, TYP
PS 9PS 10 PS 7 PS 6 PS 5
A4.13.2
5
9' -
11
1/4"
5A8.53.2
_______ 5A8.53.2
_______
SIM
A4.13.2
4
A4.13.2 3
A4.13.26
A4.13.2
1
11' - 6" 8' - 2" 3' - 8 1/2" 23' - 6" 3' - 8 1/2" 8' - 2" 11' - 6"
A5.06.2
5
4
_______A8.52.2
4
_______A8.52.2
4
_______A8.52.2
4
_______A8.52.2
4
06-1706-1706-1706-1706-1706-1706-1706-1706-1706-1706-1706-1706-1706-1706-1706-17
A2.3
A2.3
architects and planners
Berkeley, CA 94710
tel 510.542.2200
fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
As indicated
12/1
/2015 1
0:1
0:4
9 A
MC
:\U
sers
\em
ily.r
osa\D
ocum
ents
\Revit\B
erk
ele
y 1
947 C
ente
r_em
ily.r
osa@
Nolla
nd
Tam
.com
.rvt
A4.12.2
ENLARGED PLANS -
PERMIT CENTER
CITY OF BERKELEY
1947 Center Street
Building Renovation
PHASE 2
BN
MB
Nov. 4, 2015
21401
BID SET
1947 Center Street1947 Center Street1947 Center Street1947 Center Street
Berkeley CABerkeley CABerkeley CABerkeley CA
▲N
Keynote Legend
# KEYNOTE
06-07 BUILT-IN PERMIT COUNTER
06-17 HEIGHT ADJUSTABLE WORKSTATION STAND
10-16 REFER TO SG4.31 FOR SIGNAGE DESIGN
27-02 WALL-MOUNTED LCD SCREEN
1/4" = 1'-0"A4.12.2
03- PERMIT COUNTER- WEST4
1/4" = 1'-0"A4.12.2
03- PERMIT COUNTER -SOUTH3
1/4" = 1'-0"A4.12.2
03- PERMIT COUNTER -E2
FAT
S
ETFO LAC I
NRO
IA
R
CIL
EDESN
A
EC
T
TICH
REN. 01-31-17
JANET TAM
No. C-14064
1/4" = 1'-0"A4.12.2
ENLARGED PLAN - PERMIT SERVICE CENTER1
NO. DATE DESCRIPTION
2 11/4/15 Permit Re-submittal
A2 11/16/15 Phase 2 Addendum 01
A2.3 11/30/15 Phase 2 Addendum 03
A2.3
12' -
4"
OPEN TO
BEYOND
SEE
./2N A4.13.2
10' - 6"
T1
10A8.51.2
_______
5' -
3"
8' -
5"
9A9.39.2
._______
10-1310-1310-1310-13
3' -
2"
6A8.51.2
_______
A2.3
12' -
4"
FILE AREA LATERAL FILE AREA
3' -
4"
2' -
5"
FLAT FILE
47" x 36" x 31"
4A8.53.2
_______
10' - 1" 17' - 4 3/8"
4A8.53.2
_______
FILE AREA4' - 4"
1' - 9 1/4"
3' - 7"
EQEQ
12A8.53.2
_______
OPEN TO
BEYOND8' -
5"
COPY / SCANAPPROVED PLANS INCOMING PLANS / AGENCIES -
7 DEPARTMENTS
1
2
3
4
5
6
7
8
TYP12-0212-0212-0212-02
2A8.42.2
_______
1
2
3
4
5
6
7
83' -
4"
2' -
5"
1A8.53.2
_______3A8.53.2
_______2A8.53.2
_______ 2A8.53.2
_______
4' - 1 1/2"
TYP
3' - 4"(6) EQ (6) EQ
9
10
11
12
9
10
11
12
4' - 1 1/2"
GENERAL NOTES
1. REFER TO MECHANICAL, ELECTRICAL, SIGNAGE DRAWING FOR ADDITIONAL
INFORMATION.
2. REFER TO INTERIOR FINISH SCHEDULE FOR ADDITIONAL INFORMATION ON BASE,
FLOORING, WALL FINISH AND CEILING.
3. CABLE MOUNTED PENDANTS MOUNTED TO ALLOW 45 DEGREE SWING FROM
VERTICAL IN ANY DIRECTION WITHOUT CONTACTING OBSTRUCTION.
4. PATCH AND REPAIR OF (E) GYPSUM BOARD OR PLASTER SURFACE AS AFFECTED
BY DEMO AND WORK ASSOCIATED WITH ELECTRICAL AND TEL/AV WORK.
5. MANUAL SHADES ARE MOUNTED INSIDE WINDOW OPENING, TYP.
_______A8.52.2
122
A8.53.2
_______ 2A8.53.2
_______
SIM
TYP10-1610-1610-1610-16
OPEN OPEN
A2.3 A2.306-1706-1706-1706-17 06-1706-1706-1706-17
2' -
10"
SOLID SURFACE
PLASTIC LAMINATE7' - 0"
9A8.51.2
_______OPEN
TO
BEYOND
11A8.50.2
_______
2' - 0"
3' -
2"
A2.3
architects and planners
Berkeley, CA 94710
tel 510.542.2200
fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
As indicated
11/3
0/2
015 7
:36:0
7 P
MC
:\U
sers
\em
ily.r
osa\D
ocum
ents
\Revit\B
erk
ele
y 1
947 C
ente
r_em
ily.r
osa@
Nolla
nd
Tam
.com
.rvt
A4.13.2
ENLARGED
ELEVATIONS -
PERMIT CENTER
CITY OF BERKELEY
1947 Center Street
Building Renovation
PHASE 2
Checker
Author
Nov. 4, 2015
21401
BID SET
1947 Center Street1947 Center Street1947 Center Street1947 Center Street
Berkeley CABerkeley CABerkeley CABerkeley CA
Keynote Legend
# KEYNOTE
06-17 HEIGHT ADJUSTABLE WORKSTATION STAND
10-13 PROVIDE RECESSED FIRE EXTINGUISHER CABINET
10-16 REFER TO SG4.31 FOR SIGNAGE DESIGN
12-02 MANUAL WINDOW SHADE
1/4" = 1'-0"A4.13.2
03- PERMIT CENTER- NORTH1111
1/4" = 1'-0"A4.13.2
03- PERMIT CENTER- EAST3333
1/4" = 1'-0"A4.13.2
03- PERMIT CENTER- WEST6666
1/4" = 1'-0"A4.13.2
03- PERMIT CENTER LOBBY2N2N2N2N
2N
1/4" = 1'-0"A4.13.2
03- PERMIT CENTER- SOUTH4444
FAT
S
ETFO LAC I
NRO
IA
R
CIL
EDESN
A
EC
T
TICH
REN. 01-31-17
JANET TAM
No. C-14064
1/4" = 1'-0"A4.13.2
03- PERMIT CENTER- STAFF5555
NO. DATE DESCRIPTION
2 11/4/15 Permit Re-submittal
A2 11/16/15 Phase 2 Addendum 01
A2.3 11/30/15 Phase 2 Addendum 03
2W
TYP06-1606-1606-1606-16 TYP06-1606-1606-1606-16
TYP06-1606-1606-1606-16TYP06-1606-1606-1606-16
TYP06-1606-1606-1606-16
2' -
10"
4' - 0" 3' - 0"
6A8.50.2
_______9A8.50.2
_______ 8A8.51.2
_______
3' - 3"
PRINTER, OFOI
PLAM
PLAM9
A8.51.2
_______SIMA2.3
TYP06-1606-1606-1606-16
EQEQ
10' - 0"
4' -
0"
2' -
6"
TYP10-1010-1010-1010-10
_______A8.50.2
11
PLAM
PLAM
2' -
10"
6A8.53.2
_______
11' - 6"
A2.3
11A8.50.2
_______
PLAM
PLAM
2' -
10"
9A8.51.2
_______
11' - 2 1/2"
SIMA2.3
GENERAL NOTES
1. REFER TO MECHANICAL, ELECTRICAL, SIGNAGE DRAWING FOR ADDITIONAL
INFORMATION.
2. REFER TO INTERIOR FINISH SCHEDULE FOR ADDITIONAL INFORMATION ON BASE,
FLOORING, WALL FINISH AND CEILING.
3. CABLE MOUNTED PENDANTS MOUNTED TO ALLOW 45 DEGREE SWING FROM
VERTICAL IN ANY DIRECTION WITHOUT CONTACTING OBSTRUCTION.
4. PATCH AND REPAIR OF (E) GYPSUM BOARD OR PLASTER SURFACE AS AFFECTED
BY DEMO AND WORK ASSOCIATED WITH ELECTRICAL AND TEL/AV WORK.
5. MANUAL SHADES ARE MOUNTED INSIDE WINDOW OPENING, TYP.
architects and planners
Berkeley, CA 94710
tel 510.542.2200
fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
As indicated
12/1
/2015 1
1:2
2:3
9 A
MC
:\U
sers
\em
ily.r
osa\D
ocum
ents
\Revit\B
erk
ele
y 1
947 C
ente
r_em
ily.r
osa@
Nolla
nd
Tam
.com
.rvt
A5.02.2
INTERIOR
ELEVATION - FIRST
LEVEL
CITY OF BERKELEY
1947 Center Street
Building Renovation
PHASE 2
Checker
Author
Nov. 4, 2015
21401
BID SET
1947 Center Street1947 Center Street1947 Center Street1947 Center Street
Berkeley CABerkeley CABerkeley CABerkeley CA
1/4" = 1'-0"A5.02.2
01 OPEN OFFICE - TOXICS 111-NORTH1N1N1N1N
1N
1/4" = 1'-0"A5.02.2
01 OPEN OFFICE - TOXICS 111-EAST1E1E1E1E
1E
1/4" = 1'-0"A5.02.2
01 OPEN OFFICE - TOXICS 111-WEST1W1W1W1W
1W
1/4" = 1'-0"A5.02.2
01 OPEN OFFICE - TOXICS 111-SOUTH1S1S1S1S
1S
1/4" = 1'-0"A5.02.2
01 FIRST FLOOR TOXICS MANAGER OFFICE 112-NORTH4N4N4N4N
4N 4E 4S 4W
1/4" = 1'-0"A5.02.2
01 RECEPTION - TOXICS 1112E2E2E2E
2E
1/4" = 1'-0"A5.02.2
01 PUBLIC WAITING AREA - TOXICS 114-EAST3333
1/4" = 1'-0"A5.02.2
01 FIRST FLOOR CONFERENCE/HEARING ROOM 116-NORTH6N6N6N6N
6N 5E 5S 5W
Keynote Legend
# KEYNOTE
06-16 4" RUBBER WALL BASE. INSTALL PER MFR SPECIFICATION
10-10 WHITEBOARD, SEE ELEVATION FOR SIZE
2S 2W
FAT
S
ETFO LAC I
NRO
IA
R
CIL
EDESN
A
EC
T
TICH
REN. 01-31-17
JANET TAM
No. C-14064
NO. DATE DESCRIPTION
A2.3 11/30/15 Phase 2 Addendum 03
42"
42"
42"
36"
36"
PAINT CONCRETE BASETO MATCH CONCRETE COLOR
PAINT SIDES ANDUNDERSIDES OF STAIRTO MATCH CONCRETE
RUBBER FLOORAT LANDINGS, HELDBACK 2" FROM WALLS
RUBBER TREADS WITHINTEGRATED RISERS, HELDBACK 2" FROM EDGE OF STAIR
2"
PAINT WALLFIELD COLOR
GLASS GUARDRAILPANELS, CUSTOM SIZED.ATTACHED TO STRUCTURE
HANDRAIL
2"2"
(E) CONC. BASE
(E) CONCRETE BEAM
(E)WOOD PANELSIN WOOD FRAME, TO REMAIN
(E) PIPES, V.I.F.
VIF
(E) 19"
(E) 8' - 8" , VIF
PAINT (E) SURFACE. PAINT OVEREXISTING FLOOR NUMBERS
CLEAN AND PAINT (E) PIPES, TYP.
LEVEL SIGNAGE. SEE SIGNAGEDRAWINGS
ANGLED WALL, SEE PLAN
LINE OF UNDERSIDE OF STAIR ABOVE
(E) CONCRETE BASE,PAINT TO MATCHCONCRETE COLOR
WALL COLOR: FIELD
EQEQ
8' -
0"
WALL SCONCE, LIGHTFIXTURE, SED. MOUNTOVER J-BOX. PAINTEXPOSED CONDUIT
STAINLESS STEELHANDRAIL
ANGLED WALL, SEE PLAN
LINE OF UNDERSIDE OF LANDING ABOVE
(E) CONCRETE BASE,PAINT TO MATCHCONCRETE COLOR
WALL COLOR: FIELD
WALL SCONCE, LIGHT FIXTURE,SED. MOUNT OVER J-BOX. PAINTEXPOSED CONDUIT
EQEQ
8' -
0"
1"
1/2" CLEAR TEMPEREDLAMINATED GLASS WITH ININTERLAYER
EASED EDGES AT CORNERS 36" H
ANDR
AIL
LINE OF STAIR UP BEYOND,TYP - NO WORK AT STAIRRISER-TREAD
(E) STEEL NEWEL POST,CONCEALED INSIDE BOX
(E) WOOD PANEL BOX
(E) WOOD HANDRAIL OVERBALUSTER RAILING
(E) WOODHANDRAIL
STAINLESS STEEL HANDRAIL
5TH FLOOR LANDING AND UP - NO WORK
(E) TO REMAIN
GLASS GUARDRAIL. ATTACH TOHSS SPANNING BETWEEN TOP ANDBOTTOM NEWEL POST
NOTE: REMOVE BACKSIDEOF WOOD PANEL BOX ASREQUIRED FOR HSSRAILING, TOP ANDBOTTOM. REPLACE WOODPANEL IN KIND
RUBBER TREAD ON (E) CONCRETESTAIR - TERMINATE AT FIFTHFLOOR LANDING
A2.3
architects and planners
Berkeley, CA 94710tel 510.542.2200
fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
As indicated
11/3
0/2
015 2
:45:3
1 P
MC
:\Use
rs\p
ha
n.d
ung
\Do
cum
ents
\Berk
ele
y 1947 C
ente
r_p
han.d
ung
.rvt
A7.03.2
STAIR DETAILS -SIGNAGE ANDFINISHES
CITY OF BERKELEY1947 Center StreetBuilding Renovation
PHASE 2
Checker
Author
Nov. 4, 2015
21401
BID SET
1947 Center StreetBerkeley CA
FATS
ETFO LAC I
NROIA
R
CIL
EDESN
AECT
TICH
REN. 01-31-17
JANET TAM
No. C-14064
NO. DATE DESCRIPTION2 11/4/15 Permit Re-submittal
A2.3 11/30/15 Phase 2 Addendum 03
3/4" = 1'-0"A7.03.2
STAIR - GUARDRAIL AT MID-LANDING RISER AXONAND FINISHES1
1/2" = 1'-0"A7.03.2STAIR LANDING ELEVATION2
1/2" = 1'-0"A7.03.2
STAIR - INTERMEDIATE LANDING WITHMID-LANDING RISER3
1/2" = 1'-0"A7.03.2
STAIR - INTERMEDIATE LANDING - TYPICALLANDING4
3" = 1'-0"A7.03.2FINISH OF GLASS5
1/2" = 1'-0"A7.03.2ELEVATION AT GUARDRAIL- NEW TO EXISTING6
PLASTIC LAMINATE
PER PLANS AND DETAILS, 24" MAXPER PLANS AND DETAILS, 24" MAXPER PLANS AND DETAILS, 24" MAXPER PLANS AND DETAILS, 24" MAX
4-3/8" DIA MACHINE BOLT W/
WASHER AND NUT
2x2x1/4" STL ANGLE
@ 3'-0" MAX AND AT
EACH END WHERE NO
WALL OCCURS
3X4X1/4" STL ANGLE X 18" LONG
3/16"
NOTE: COUNTERTOP
WITH END WALL PROVIDE
2x2x1/4" STL ANGLE AT
WALL WITH SMS
FASTENERS INTO TYPE 2
BACKING @ 6" OC
PARTITION AS SCHEDULED
1/4" DIA SSTL SEISMIC RAIL
@ SHELF FRONT, AT
OPEN SHELVES, DOWELED
INTO SIDES, TYP.; 36"
MAX UNSUPPORTED
LENGTH
FIXED MIDDLE SHELF, ALL
OTHER SHELVES
ADJUSTABLE
SEE
ELV
ATI
ON
SEE
ELE
VA
TIO
N
2' - 0 3/4"
DOOR FRONT
CABINET LINER
_______A8.50.2
2
_______A8.50.2
2 _______A8.50.2
2
SOLID SURFACE OVER 3/4" SUBSTRATE
COUNTERTOP HEIGHT
+/- 8'-5" AFF
(E) GYP BOARD CEILING. REPAIR
SURROUNDING AS REQUIRED
PLASTIC PANELIING TOP
SUPPORT" HARDWARE, OR
SIMILAR, ATTACHED TO
STRUCTURE, TYP
3/8" PLASTIC PANELING
SOLID WOOD BLOCKING
SOFFIT HANGER - 3 5/8" MTL
STUD @ 16" OC MAX, TYP
FOR BALANCE OF SOFFIT
HANGER AND BRACING INFO,
SEE DET. 1
A8.42.2
1
A8.41.2
FACE OF WALL
ADJUSTABLE PLAM SHELF, TYP
CABINET LINER
SHIM AS REQUIRED
SEE
ELE
VA
TIO
NS
_______A8.50.2
2
PLAM DOOR FRONT
2" CABINET LIP
2"
LIGHT FIXTURE WHERE
INDICATED ON ELEC PLANS
END FEED FROM WALL @ END
OF CABINET
LIGHT FIXTURE
WHERE INDICATED
WHITE PAINTED SURFACES
WV-1
ADJ SHELF, WV-1
2X BLOCKING
SWD-1 BASE
_______A8.50.2
2_______
A8.50.2
2
3' -
0"
PLAM FINISH OVER
3/4" SUBSTRATE
SWD-1
EDGEBANDING
1 1/
2"
PLASTIC PANELING TOP SUPPORT
HARDWARE, OR SIMILAR FOR TOP
AN D BOTTOM CHANNEL
LIGHT FIXTURE, SED
PLASTIC PANELING "HALF LAP
QUIRK" SEAM OVERLAP WITH
SEAM COVER HARDWARE
END CAP, BOTH ENDS1/8" MIN
1' -
6"
, VIF
PAINT INSIDE SURFACES OF
WALL AND FLOOR, WHITE, TYP
1/2" PLASTIC PANELING
FULL HEIGHT PARTITION
END WALL WITH GYP BD
EXISTING WALL
(E) SUSPENDED GYP BD CEILING,
MODIFY AROUND BUILD-OUT FOR
BACKLIT PLASTIC PANELING
DASHED LINE OF FULL HEIGHT
WALL BEYOND, TO UNDERSIDE OF
(E) CONCRETE DECK
1' - 6" ,VIF
LIGHT FIXTURE AROUND
PERIMETER TYP. SED12" CLR
PLASTIC PANELING TOP
SUPPORT HARDWARE
SYSTEM OR SIMILIAR, FOR
TOP AND BOTTOM CHANNEL
FLOOR AS SCHEDULED
3 5/8" MTL STUD DIAGONAL
BRACING TO (E) WALL, 4'-0" OC
MAX WITH (3) #10 SELF TAPPING
SCREWS AT CONNECTIONS
PAINT INSIDE SURFACES OF
WALL AND FLOOR, WHITE, TYP
6"
1/2" PLASTIC PANELING,
TEXTURE AND COLOR TO BE
SELECTED BY ARCHITECT
SEALANT, TYP
3 5/8" MTL STUD @
16" OC MAX, TYP
0.157" DIA W/ 3/4"
EMBEDMENT @ 12" O.C
(E) CONCRETE DECK
DIAGONAL BRACING 4'-0" OC MAX
PA
NEL
HEI
GH
T
OP
ENIN
G O
R O
VER
ALL
HEI
GH
T
(E) WALL
5/8" GYP BD, TYP
ALIGN WITH (E) COLUMN
FACE BEYOND
PLAM
COUNTERTOP
SOLID WD TRIM
WIRE MANAGEMENT
SYSTEM
SOLID POLYMER
PANEL, OVER PLAM
OUTLET, WO
SOLID WD TRIM
PLAM COVERED
EXPOSED SURFACES,
TYP
SOLID WD MOLDING
SOLID WD FRAME
SEE
PLA
N/E
LEV
ATI
ON
4"
2'-6" AT SIM.
3' - 0"
A2.3
HINGED DISPLAY SHELF,
TYP. WD (WD VENEER W/
SOLID WD TRIM, UPPER
PIVOT HINGES & LOWER
ADJUSTABLE PIN STOPS)
SOLID WD TRIM, TYP
WD VENEER ALL EXPOSED
SURFACES, UON
A2.3
1 1/
2"
1' - 1 1/2"
3' -
2 1
/4"
2' - 1"
EQEQ
2X BLOCKING
FIN FLOORING AND BASE
AS SCHEDULED
4"
1' - 2"
architects and planners
Berkeley, CA 94710
tel 510.542.2200
fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
As indicated
12/1
/2015 1
1:2
1:4
9 A
MC
:\U
sers
\em
ily.r
osa\D
ocum
ents
\Revit\B
erk
ele
y 1
947 C
ente
r_em
ily.r
osa@
Nolla
nd
Tam
.com
.rvt
A8.51.2
INTERIOR DETAILS -
CASEWORK
CITY OF BERKELEY
1947 Center Street
Building Renovation
PHASE 2
Checker
Author
Nov. 4, 2015
21401
BID SET
1947 Center Street1947 Center Street1947 Center Street1947 Center Street
Berkeley CABerkeley CABerkeley CABerkeley CA
3" = 1'-0"A8.51.21 CANTILEVERED COUNTERTOP SUPPORT - 24" MAX
1" = 1'-0"A8.51.23 FULL-HT CABINET
1 1/2" = 1'-0"A8.51.210 LIGHT BOX WALL PANEL CASEWORK
FAT
S
ETFO LAC I
NRO
IA
R
CIL
EDESN
A
EC
T
TICH
REN. 01-31-17
JANET TAM
No. C-14064
1 1/2" = 1'-0"A8.51.24 UPPER CABINETS
1 1/2" = 1'-0"A8.51.28 OPEN SHELVES - LOWER CABINET
1 1/2" = 1'-0"A8.51.27 LIGHTBOX WALL PANEL CASEWORK - PLAN DETAIL
1 1/2" = 1'-0"A8.51.212 LIGHT BOX WALL PANEL CASEWORK
1 1/2" = 1'-0"A8.51.29 COUNTER - WITH POWER
NO. DATE DESCRIPTION
1 9/8/15 Phase 1 Plan Check Revisions
2 11/4/15 Permit Re-submittal
A2.3 11/30/15 Phase 2 Addendum 03
1 1/2" = 1'-0"A8.51.26 PERMIT CENTER - DISPLAY CASEWORK
A A
A S
IM
A A
BB
A1 A1
BB
2 3/4"
WOOD VENEER
DRAWER FRONTS
CABINET LINER
2X BLOCKING
CONFIRM DRAWER
DIMENSIONS WITH
OWNER
1' -
0"
7 1/
2"6
1/4"
SECTION ATSECTION ATSECTION ATSECTION AT
DRAWER MODULEDRAWER MODULEDRAWER MODULEDRAWER MODULE
SEE DETAIL
1/A8.52.2 FOR
ADDITIONAL
INFORMATION
SOLID SURFACE
2' -
8"
11"
A2.3
SECTION AT DIVIDERSECTION AT DIVIDERSECTION AT DIVIDERSECTION AT DIVIDER
2"
EDGE OF COUNTER ABOVE
SOLID HARDWOOD
TRIM w/ EASED EDGES
(A) PLAN DETAIL(A) PLAN DETAIL(A) PLAN DETAIL(A) PLAN DETAIL
WOOD VENEER FINISH4"
WOOD VENEER FINISH
SOLID HARDWOOD
TRIM w/ EASED EDGES
6"
3' - 4"
2' -
8"
TYPICAL SECTION
SHOWN DASHED, FOR
REFERENCE
4"
SOLID HARDWOOD
SOLID SURFACE
6"
10A8.52.2
_______ 1A8.52.2
_______4A8.52.2
_______
WOOD VENEER
SOLID HARDWOOD
2' -
8"
3' - 0"
EQ EQ
11A8.52.2
_______
AREA OPEN AT ACCESSIBLE SERVICE
COUNTER LOCATIONS. REFER TO SHEET
A4.12.2 FOR COUNTER LOCATIONS27"
CLR
A2.3
SOLID HARDWOOD
SOLID SURFACE
SOLID WOOD
1 1/2"
10A8.52.2
_______1A8.52.2
_______ 4A8.52.2
_______
P LAM FINISH
RUBBER BASE
WOOD VENEER
COMPUTER MONITOR, NIC
COORDINATE WITH OWNER
CPU SUPPORT (TOP/SIDE MOUNTED), NIC
COORDINATE WITH OWNER
5' - 2" VERIFY, SEE PLAN 1' - 4" 4"
EQ EQ
3' - 0"
AREA OPEN AT ACCESSIBLE SERVICE
COUNTER LOCATIONS. REFER TO SHEET
A4.12.2 FOR COUNTER LOCATIONS
11A8.52.2
_______
27"
CLR
POWER/DATA OUTLET
A2.3
TYPICAL SECTION AT COUNTER STATIONTYPICAL SECTION AT COUNTER STATIONTYPICAL SECTION AT COUNTER STATIONTYPICAL SECTION AT COUNTER STATION
4" SOLID WOOD BASE
WOOD VENEER FINISH
1' - 9 1/2"
3/4" PLYWOOD SUBSTRATE
CARPET FLOOR FINISH,
SEE FINISH SCHEDULE
WALL BASE, SEE
FINISH SCHEDULE
SOLID HARDWOODWOOD
TRIM (AT SUPPORT
PANEL BEYOND)
SOLID HARDWOOD TRIM
P LAM FINISH
WOOD VENEER FINISH AT
DIVIDER/SUPPORT PANEL/
DRAWER MODULE, AS OCCURS
CASEWORK FRAMING
POWER/DATA OUTLET; CONCEALED
CONDUIT INSIDE CASEWORK;
POKE- THRU SLAB; COORDINATE
LOCATION; SED, SSD
1 1/
2"
SOLID SURFACE EDGE
WIRE MANAGEMENT TRAY
3/4"
3/4"
EDGE OF COUNTER ABOVE
SOLID HARDWOOD
TRIM w/ EASED EDGES
(A) PLAN DETAIL AT SUPPORT PANEL(A) PLAN DETAIL AT SUPPORT PANEL(A) PLAN DETAIL AT SUPPORT PANEL(A) PLAN DETAIL AT SUPPORT PANEL
WOOD VENEER FINISH
1 1/
2"
(B) SECTION AT PANEL ATTACHMENT(B) SECTION AT PANEL ATTACHMENT(B) SECTION AT PANEL ATTACHMENT(B) SECTION AT PANEL ATTACHMENT
TILE FLOOR FINISH,
SEE FINISH SCHEDULE
CPU SUPPORT, NIC
2" DIA GROMMET, ONE (1) PER
STATION, COORDINATE
LOCATION WITH OWNER
SOLID SURFACE
3' - 0"
2 1/
2"
2' -
8"
11"3 1/2"
27"
CLR
STEEL ANGLE; CONCEAL VERT
LEG OF ANGLE WITHIN PANEL
CARPET FLOOR OVER PLATE
TOP OF CONC
(2) COUNTERSUNK TAPCON
ANCHOR TO CONC SLAB; 2" EMBED
A2.3
19" CLR
27"
CLR
SECTION AT OPEN COUNTER STATIONSECTION AT OPEN COUNTER STATIONSECTION AT OPEN COUNTER STATIONSECTION AT OPEN COUNTER STATION
WOOD VENEER FINISH
1' - 9 1/2"
3/4" PLYWOOD SUBSTRATE
CARPET FLOOR FINISH,
SEE FINISH SCHEDULE
SOLID HARDWOOD WOOD
TRIM (AT SUPPORT PANEL
BEYOND)
SOLID HARDWOOD TRIM
P LAM FINISH
WOOD VENEER FINISH AT
DIVIDER/SUPPORT PANEL/
DRAWER MODULE, AS OCCURS
2x2x1/4" STEEL ANGLE
POWER/DATA OUTLET BEYOND;
CONCEALED CONDUIT INSIDE
CASEWORK; POKE- THRU SLAB;
COORDINATE LOCATION; SED, SSD
1 1/
2"
SOLID SURFACE EDGE
WIRE MANAGEMENT TRAY
3/4"
3/4"
EDGE OF COUNTER ABOVE
SOLID HARDWOOD
TRIM w/ EASED EDGES
(A1) PLAN DETAIL AT SUPPORT PANEL(A1) PLAN DETAIL AT SUPPORT PANEL(A1) PLAN DETAIL AT SUPPORT PANEL(A1) PLAN DETAIL AT SUPPORT PANEL
WOOD VENEER FINISH
1 1/
2"
TILE FLOOR FINISH,
SEE FINISH SCHEDULE
CPU SUPPORT, NIC
2" DIA GROMMET, ONE (1) PER
STATION, COORDINATE
LOCATION WITH OWNERSOLID SURFACE
3' - 0"
2 1/
2"
2' -
8"
11"3 1/2"
2x2x1/4" STEEL ANGLE W/ FASCIA
2x2x1/4" STEEL
ANGLE W/ FASCIA
_______TYP
A8.60.2
11
CONDUIT RUNS
A2.3
19" CLR
1' - 2"
27"
CLR
architects and planners
Berkeley, CA 94710
tel 510.542.2200
fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
1 1/2" = 1'-0"
12/1
/2015 9
:59:2
4 A
MC
:\U
sers
\em
ily.r
osa\D
ocum
ents
\Revit\B
erk
ele
y 1
947 C
ente
r_em
ily.r
osa@
Nolla
nd
Tam
.com
.rvt
A8.52.2
INTERIOR DETAILS -
CASEWORK
PERMIT CENTER
CITY OF BERKELEY
1947 Center Street
Building Renovation
PHASE 2
Checker
Author
Nov. 4, 2015
21401
BID SET
1947 Center Street1947 Center Street1947 Center Street1947 Center Street
Berkeley CABerkeley CABerkeley CABerkeley CA
FAT
S
ETFO LAC I
NRO
IA
R
CIL
EDESN
A
EC
T
TICH
REN. 01-31-17
JANET TAM
No. C-14064
1 1/2" = 1'-0"A8.52.210 PERMIT CENTER SERVICE COUNTER - SECTION DTL AT DRAWERS
1 1/2" = 1'-0"A8.52.24 PERMIT CENTER SERVICE COUNTER - SECTION DTL AT DIVIDER
1 1/2" = 1'-0"A8.52.26 PERMIT CENTER SERVICE COUNTER - TYPICAL FRONT ELEVATION
1 1/2" = 1'-0"A8.52.212 PERMIT CENTER SERVICE COUNTER - TYPICAL BACK ELEVATION
NO. DATE DESCRIPTION
2 11/4/15 Permit Re-submittal
A2.3 11/30/15 Phase 2 Addendum 03
NEW SHEET
1 1/2" = 1'-0"A8.52.21 PERMIT CENTER SERVICE COUNTER - TYPICAL SECTION DTL
1 1/2" = 1'-0"A8.52.211 PERMIT CENTER SERVICE COUNTER - TYPICAL SECTION DTL w/ PANEL OPEN
CHAIN LINK: 1 1/2"
FULL
HEI
GHT
- FLR
TO
CEIL
ING
WRAP ALL EXPOSEDEDGES AND STRETCHERBARS W/ U CHANNEL
3" POST
PLAN ELEVATION
3" DIAMETER POST,GALVANIZED
ANCHOR TO CONCRETEWITH 1/4" STEEL BASEPLATE - 1/2" HILTI KB-TZ,MIN 2" EMBEDMENT
9"
5"
FULL HEIGHTINTERIOR PARTITION
ANCHOR INTO WALLBACKING, TYP
PADLOCKABEGATE LATCH
CHAIN LINK: 1 1/2"
FRONT WHEEL WITHCARRIER
REAR WHEEL
TOP AND BOTTOMTRACK FOR WHEEL
STEEL BASEPLATE, TYP
ROLLING GATE
TOP FILLERCHAINLINK PANEL
FE 1
4 7/
8" R
O
4" M
AX2
1/2"
11 5/8" RO TYP
EXTINGUISHER CABINET SEMIRECESSED FIRE RATED HOUSING
PARTITION OR EXTERIOR WALLAS INDICATED
MINIMUM ROUGH OPENING
SOLID WD FRAME
1 1/4"
STAFF SIDE PUBLIC SIDE
1/4"
TYP
1/4" TYP
WOOD VENEEROVER 3/4"SUBSTRATE
FULL HEIGHT SOLIDBACKING AT PIVOTS
FACE OF WALL
GATE IN OPEN POSITION
GATE PIVOT
GATE IN CLOSED POSITION
DOUBLE-ACTING SPRINGPIVOT SET
SOLID WD FRAME
3' - 0"
4"
4"
4"
2" WD CAP w/ EASEDEDGES
3' -
0"
SMO O
TH S
U RFA
CE
10"
WOOD VENEER PANEL
3 3/4"
3 3/
4"
3 3/4"
SMOO
TH S
URFA
CE
10"
SOLID WD FRAME
WOOD VENEER FINISH
PUBLIC SIDE STAFF SIDE
1A8.54.2
._______1
A8.54.2
._______
4A8.54.2
._______ 4
A8.54.2
._______
(2) STEEL HINGE - SINGLE ACTINGSPRING CLOSER- WELD TO FRAME
HSS 1-1/2"X1-1/2" X 3/16"GATE FRAME
3/4" BALUSTERS @ 4" OC
HSS 2X4X3/16" POST, WELD TO(E) NEWEL POST
(E) NEWEL POST, PAINTNOTE: PAINT GATE TO MATCH STAIRBALUSTERS.FOR BALANCE OF NOTES, SEEGUARDRAIL ELEVATION AT LANDING
HSS 2X4X3/16" POST, WELD TO(E) NEWEL POST
HSS 1-1/2"X1-1/2" X 3/16"GATE FRAME
3/4" BALUSTERS @ 4" OC
4"2'
- 5"
1 1/
2"
EXISTING CONCRETE SLAB
1" ACOUSTICAL TREATMENTPANELS WITH BEVELED EDGE,PAINTED. FIELD VERIFY AND
CUT TO SIZE
1 1/2"PANEL FASTENERS PER
MANUFACTURER'SRECOMMENDATION
EXISTING CONCRETE JOIST
1X FURRING STRIP @ 24" OCWITH 0.157" DIA HILTI X-U
WITH 3/4" EMBEDMENT MAX
A2.3
A2.3
architects and planners
Berkeley, CA 94710tel 510.542.2200fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
As indicated
11/3
0/2
015 1
0:5
6:1
6 A
MC
:\Use
rs\p
ha
n.d
ung
\Do
cum
ents
\Berk
ele
y 1947 C
ente
r_p
han.d
ung
.rvt
A8.54.2
INTERIOR DETAILS -MISC DETAILS
CITY OF BERKELEY1947 Center StreetBuilding Renovation
PHASE 2
Checker
Author
Nov. 4, 2015
21401
BID SET
1947 Center StreetBerkeley CA
FATS
ETFO LAC I
NROIA
R
CIL
EDESN
AECT
TICH
REN. 01-31-17
JANET TAM
No. C-14064
1 1/2" = 1'-0"A8.54.26 FENCE - SLIDING CHAIN LINK FENCE AND GATE - STORAGE
1 1/2" = 1'-0"A8.54.27 FIRE EXTINGUISHER CABINET - METAL STUD
3" = 1'-0"A8.54.24 GATE SECTION
3" = 1'-0"A8.54.21 GATE - PLAN VIEW
1 1/2" = 1'-0"A8.54.25 PIVOT GATE - ELEVATION
NO. DATE DESCRIPTION2 11/4/15 Permit Re-submittal
A2 11/16/15 Phase 2 Addendum 01A2.3 11/30/15 Phase 2 Addendum 03
1 1/2" = 1'-0"A8.54.28 STAIRWAY GATE
3" = 1'-0"A8.54.2ACOUSTICAL TREATMENT PANELS9
CERAMIC TILE TO MATCH (E)
CEMENTITIOUS BOND COAT
(E) WALL ASSEMBLY
(E) CERAMIC TILE
ALIG
N
GROUT
WATER RESISTANT GYP BD, MATCHINGTHICKNESS. REPLACE WHERE REQUIRED FROMCENTER STUD TO CENTER STUD FOR BACKING
(E) CERAMIC TILE
GRAB BAR
(E) WALL ASSEMBLY &(E) BACKING
WHERE GRAB BAR ISRELOCATED TOWALL WITHOUT EXISTINGBACKING, PROVIDE BACKINGPER DETAIL.REPLACE WATER RESISTANTGYP BD AND TILE , CENTER OFSTUD TO CENTER OF STUD.TILE TO MATCH EXISTINGADJACENT. SEE DETAILFOR TILE REPAIR
/3 A8.00.2
A2.3/1 A8.55.2
(E) PARTITION
2'-5 1/2" AFF
4"
(E) TILE
33" AFF
METAL STRAPPING ATTACHED TOSTUDS
SCREW INTO EITHER STUD ORMETAL BACKING, ACCORDING TOMFR SPECIFICATION. BACKINGPER SHEET A8.00.2. SEE DETAILPRE-DRILL TILE AS REQUIRED
A2.3
/1 A8.55.2
(E) WALL ASSEMBLY
(E) BACKING
WHERE PARTITION IS RELOCATED TOWALL WITHOUT EXISTING BACKING,PROVIDE BACKING PER DETAILREPLACE WATER RESISTANT GYP BDAND TILE , CENTER OF STUD TOCENTER OF STUD. TILE TO MATCHEXISTING ADJACENT. SEE DETAILFOR TILE REPAIR
DRILL FOR BOLTSPARTITION BRACKETPARTITION PANEL
(E) CERAMIC TILE
/2 A8.00.2
/10 A8.60.2
(E)FLOOR ASSEMBLY
WATER RESISTANT GYP BD
BULLNOSE CERAMIC TILE, WHERE OCCURS.MATCH EXISTING ADJACENT
METAL STUDS
CERAMIC WALL TILE OVERCEMETITIOUS BOND COAT(TCNA-W243-15)
CERAMIC TILE COVE BASE - MATCHEXISTING ADJACENT
CERAMIC FLOOR TILE OVERCEMENTITIOUS LEVELINGMATERIAL. ADJUST SUBSTRATETO ADJACENT FLOOR LEVEL
HOLD GWB BACK 1/4" CAULK AIRTIGHTWITH ACOUSTICAL SEALANT
0.157" DIA W/ 3/4" EMBED AT12" O.C.
METAL TRACK
+/-6'-0" AFF, FIELD VERIFY A2.3
5/8" WATER RESISTANT GYP BD
BULLNOSE CERAMIC TILE
METAL STUD FRAMING
CERAMIC WALL TILE SET OVERCEMENTITIOUS BOND COAT(TCNA-W243-5)
CERAMIC TILE , MATCHINGEXSITING ADJACENT
WHERE NEW PARTITION WALLOCCURS, REMOVE AND REPLACEMIN. WIDTH OF 2 TILES ON EACHSIDE OF PARTITION TO MATCHADJACENT
WHERE DEMOLITION OF FLOOR TILEOCCURS TO REMOVE PARTITIONWALL, REMOVE MIN. WIDTH OF 2TILES ON EACH SIDE OF PARTITION TOFULL TILE JOINT. PATCH ANDREPLACE TILE TO MATCH ADJACENT,TILE SIZE VARIES PER FLOOR
EXISTING FLOOR TILE
NEW FLOOR TILE
2 TILE WIDTH MIN.
2 TI
LE W
IDTH
MIN
.
5A8.55.2
_______
A2.3
A2.3
architects and planners
Berkeley, CA 94710tel 510.542.2200fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
As indicated
11/3
0/2
015 1
:45:4
8 P
MC
:\Use
rs\p
ha
n.d
ung
\Do
cum
ents
\Berk
ele
y 1947 C
ente
r_p
han.d
ung
.rvt
A8.55.2
INTERIOR DETAILS -RESTROOMDETAILS
CITY OF BERKELEY1947 Center StreetBuilding Renovation
PHASE 2
Checker
Author
Nov. 4, 2015
21401
BID SET
1947 Center StreetBerkeley CA
FATS
ETFO LAC I
NROIA
R
CIL
EDESN
AECT
TICH
REN. 01-31-17
JANET TAM
No. C-14064
3" = 1'-0"A8.55.21 CERAMIC WALL TILE PATCH
3" = 1'-0"A8.55.22 GRAB BAR BACKING
1 1/2" = 1'-0"A8.55.23 BABY CHANGING STATION
3" = 1'-0"A8.55.24 TOILET PARTITION ANCHOR
3" = 1'-0"A8.55.25 CERAMIC TILE WAINSCOT
3" = 1'-0"A8.55.27 CERAMIC TILE AT PARTITION - PLAN
NO. DATE DESCRIPTION2 11/4/15 Permit Re-submittal
A2.3 11/30/15 Phase 2 Addendum 03
TYPE A
TYPE B
TYPE A1
TYPE B1
WIDTH SIDELITE WIDTH
SIDELITE WIDTH WIDTH
9' -
0"
HEIG
HT
HEIG
HT
HEIG
HT
WIDTH WIDTH
2A9.39.2
1A9.39.2
3A9.39.2
5A9.39.2
4A9.39.2
4A9.39.2
4A9.39.2
4A9.39.2
12"
6"6"
3'-6
".
6"6"
HEIG
HT
TYPE A2 TYPE A3
TYPE C TYPE C1 TYPE ETYPE D
HEIG
HT
WIDTH
WIDTH SIDELITE WIDTH
HEIG
HT
2A9.39.2
MAT
CH (E
)
2'-9
1/2
", VI
F(NOTE; FIELD VERIFY WITH EXISTINGADJACENT FOR HORIZONTAL MULLION,WHERE OCCURS - VARIES BY FLOOR)
3' -
6"
6"
HEIG
HT
WIDTH
3' -
0"6"
6"
HEIG
HT
(VIF)
5' - 6 1/8"
(NOTE: REFER TO MAIN ENTRYDOOR DETAILS)
4A9.39.2
4A9.39.2
4A9.39.2
TYPE F
T1 T1
T1
T1
T1
2'-0": T1
T1 T1
T20 T20
4'-0": T2
T3
T4 T4
1. DOOR FRAME THROAT DEPTH VARIES. COORDINATE WITH WALL PARTITION TYPES ANDEXISTING CONDITIONS. WHERE DOOR IS INSTALLED INTO EXISTING CONDITIONS, FIELDVERIFY DOOR AND FRAME WIDTH AND HEIGHT
2. ALL LOCKS AND LATCHES SHALL BE LEVER OPERATED AND SHALL BE OF SUCHCONSTRUCTION THAT WHEN LOCKED THE DOOR MAY BE OPENED FROM WITHIN BY USINGLEVER AND WITHOUT USE OF A KEY OR SPECIAL KNOWLEDGE, PER CBC 1008.1.9
3. ALL WOOD DOORS TO BE PREFINISHED4. PROVIDE DOOR HARDWARE AT ALL INTEROR DOORS TO MEET CBC SECTION 11B-404.2.9
DOOR OPENING FORCE & CLOSER SPEED5. ALL HAND OPERATED HARDWARE AND DOOR CONTROLS TO BE MOUNTED BETWEEN 34" MIN
AND 48" MAX TO TOP OF CONTROLS6. ALL GLASS IN DOORS AND ADJACENT GLAZING TO BE SAFETY GLAZING.7. VISION LIGHTS IN DOORS WITHOUT ADJACENT SIDELIGHTS TO HAVE LOWER EDGE MOUNTED
43" MAX ABOVE FLOOR, PER CBC 11B-404.2.118. SEE FLOOR PLAN FOR LOCATION AND TYPES OF SIGNAGE ASSOCIATED WITH DOORS. REFER
TO SG DRAWINGS FOR ADDITIONAL SIGNS AT MAIN ENTRY DOORS, SOUTH ELEVATION,FIRST FLOOR LOBBY, STAIR NO.1, PERMIT CENTER PUBLIC SERVICE COUNTERS, ANDWELCOME DESK.
GENERAL NOTES - DOORS
GLAZING TYPE
T1 1/4" TEMPERED GLASS
T2 3/8" TEMPERED GLASS
T3 FIRE-RATED GLAZING - 20 MIN
T20 1" IGU - 1/4" TEMPERED -SURFACE COATING, 1/2" AIRSPACE, 1/4" TEMPERED -GLAZING WITH SOLOR TINT TOMATCH EXISTING ADJACENTTRANSOM WINDOW. GLAZINGTO MEET CBEES TABLE 141.0-A,1" IGU TO MEET MAX U FACTOR0.58, MIN RSHGC 0.41 AND VT0.17 FOR GLAZED DOOR, VT 0.42FOR FIXED WINDOW
T4 1/4" TEMPERED RIBBED GLASS
A2.3
architects and planners
Berkeley, CA 94710tel 510.542.2200fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
As indicated
11/3
0/2
015 1
1:0
3:2
9 A
MC
:\Use
rs\p
ha
n.d
ung
\Do
cum
ents
\Berk
ele
y 1947 C
ente
r_p
han.d
ung
.rvt
A10.20.2
DOOR SCHEDULE
CITY OF BERKELEY1947 Center StreetBuilding Renovation
PHASE 2
BN
MB
Nov. 4, 2015
21401
BID SET
1947 Center StreetBerkeley CA
PHASE 2- DOOR SCHEDULE - BASEMENT-FIRST
CW TypeDoor Sidelite
WidthFire
RatingHardware
GroupFrame
CommentsWidth Height Thickness Material Finish Material Finish
BASEMENT001 B C 6' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 4 HM PT ACTIVE-INACTIVE LEAF002 A C 6' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 5 HM PT PANIC HARDWARE - HOLD OPEN NOT TIED TO FA,
ACTIVE-ACTIVE LEAF003 A C1 6' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 6 HM PT PANIC HARDWARE - LITE005 A A2 3' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 7 HM PT010 A C 5' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 8 HM PT011 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 6' - 0" NR 9 ALUM ANOD DOOR WITH SIDELIGHT011 B C 6' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 10 HM PT012 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 6' - 0" NR 9 ALUM ANOD DOOR WITH SIDELIGHT013 A A2 3' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 11 HM PT013 B R 6' - 0" 7' - 0" 12 IT STORAGE GATE015 B A2 3' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 11 HM PT038 A A2 3' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 13 HM PT OCCUPANCY-VACANCY INDICATORS1-B-1 A2 3' - 0" 7' - 0" 0' - 1 3/4" SC HM 90 MIN 20 HM PT 90 MIN DOOR
FIRST FLOOR105 A A1 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 20 Minute 15 HM PT DOOR WITH FIRE RATED HALF LITE - VERTICAL BAR
ACTUATOR107 E A2 3' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 16 HM PT CARD READER110 A I 5' - 6" 6' - 8" 0' - 1 3/4" STL BRZ 17 STL BRZ STEEL DOOR AND FRAME WITH BRONZE FINISH - RECONNECT
CARD READER - OVERHEAD AUTOMATIC DOOR OPERATOR -RECONNECT TO TWO BUTTON DOOR OPERATOR - MANUALLOCK IN CASE CARD ACCESS FAILS AND MANUAL OVERRIDENEEDED TO OPEN/CLOSE DOORS
111 A A2 3' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 18 HM PT112 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT114 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 25 ALUM ANOD DOOR WITH SIDELIGHT - CARD READER114 B B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 9 ALUM ANOD DOOR WITH SIDELIGHT129A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT134 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT139 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 9 ALUM ANOD DOOR WITH SIDELIGHT150 A B1 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 4' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT AND TRANSOM151 A B1 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 4' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT AND TRANSOM153 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 9 ALUM ANOD DOOR WITH SIDELIGHT154 A A2 3' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 11 ALUM PTS1-1A F 2' - 7
3/4"2' - 0" 0' - 1" NR 26 STL STL METAL PIVOT GATE - NON-LOCKING
PHASE 2- DOOR SCHEDULE - SECOND-FOURTH
CW TypeDoor Sidelite
WidthFire
RatingHardware
GroupFrame
CommentsWidth Height Thickness Material Finish Material Finish
SECOND FLOOR223 G D 2' - 6" 2' - 10" 0' - 1 3/4" SC WD NR 14 PIVOT GATE - NO FRAME258 A B 3' - 0" 8' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT - FIELD VERIFY HEIGHT TO MATCH
ADJACENT DOORS260 A A2 2' - 6" 7' - 0" 0' - 1 3/4" SC WD NR 11 HM PT
THIRD FLOOR302 A A3 3' - 0" 7' - 0" 0' - 1 3/4" SC WD -- 18 HM PT302 B B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 4' - 0" -- 9 ALUM ANOD DOOR WITH SIDELIGHT302 C B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 1' - 6" NR 18 HM PT302 D A3 3' - 0" 7' - 0" 0' - 1 3/4" SC WD -- 18 HM PT305 A A2 3' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 16 HM PT CARD READER325 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT326 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT328 B B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 9 ALUM ANOD DOOR WITH SIDELIGHT332 A A2 2' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 11 HM PT332 B B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 9 ALUM ANOD DOOR WITH SIDELIGHT334 A A2 3' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 19 STL PT341 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT342 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT343 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT344 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT345 A A2 3' - 0" 7' - 0" 0' - 1 3/4" SC WD NR 11 HM PT348 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT349 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT359 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT363 A B 3' - 0" 7' - 0" 0' - 1 3/4" SC WD 2' - 0" NR 19 ALUM ANOD DOOR WITH SIDELIGHT
PHASE 2- DOOR SCHEDULE - EXISTING WITH (N) HARDWARE
CW TypeDoor Sidelite
WidthFire
RatingHardware
GroupFrame
CommentsWidth Height Thickness Material Finish Material Finish
BASEMENTE-003 B A2 3' - 0" 7' - 0" 0' - 1 3/4" EXIST PT-1 90 MIN 21 EXIST EXIST (E) 90 MIN OPENING - PANIC HARDWARE
FIRST FLOORE-S1-1 A2 3' - 0" 7' - 0" 0' - 1 3/4" EXIST EXIST 90 MIN 22 EXIST EXIST (E) 90 MIN OPENING - ADD MAGNETIC HOLD OPEN - TIE TO
SMOKE DETECTORS
SECOND FLOORE-238 A B 3' - 0" 7' - 0" 0' - 1 3/4" EXIST WD NR 23 EXIST EXIST EXISTING DOOR AND SIDELITE RELOCATEDE-264 A A2 3' - 0" 7' - 0" 0' - 1 3/4" EXIST EXIST 24 EXIST EXIST REMOVE (E) DOOR CLOSER
FOURTH FLOORE-405 A A2 3' - 0" 7' - 0" 0' - 1 3/4" EXIST EXIST 24 EXIST EXIST REMOVE (E) DOOR CLOSER
FATS
ETFO LAC I
NROIA
R
CIL
EDESN
AECT
TICH
REN. 01-31-17
JANET TAM
No. C-14064
NO. DATE DESCRIPTION2 11/4/15 Permit Re-submittal
A2.3 11/30/15 Phase 2 Addendum 03
NOTE: REFER TO SPECIFICATION SECTION FOR 08 71 00 FOR HARDWARE GROUP INFORMATIONA2.3
+/-
32
3/4"
5 1/
2"
(E) AUTO DOOR OPERATOR., AT 9" AND 36" A.F.F.VERIFY AND ADJUST LOCATION OF PUSH PLATE -CENTERLINE OF PUSH PLATE AT 7" MIN TO 8" MAXAFF. OTHER PUSH PLATE TO REMAIN, BETWEEN 30"MIN TO 44" MAX, BOTH INTERIOR AND EXTERIORSIDE. CONNECT TO OVERHEAD DOOR ACTUATOR
(E) AUTO DOOROP., AT 9" AND36" A.F.F.
(E) DOORUNLOCK BUTTON
EXTERIOR
INTERIOR
+/- 5" +/- 33" +/- 5 1/2" +/- 72" +/- 5 1/2" +/- 33" +/- 5"
(E) CARDREADER
5' -
1"
FIRST FLOOR0' - 0"
(E)CARD READER, TOREMAIN
(E) SATIN BRONZEFRAME, TO REMAIN.CLEAN TO SATINBRONZE FINISH, TYP
VIF
6' -
10 3
/8" R
.O.
WINDOW SIDELITEWITH IGU - SOLARTINT, TYP. MATCHEXISTING TINT IN THEABOVE WINDOW
(E) BRONZEDECORATIVE FLUTES,TO REMAIN. CLEAN TOSATIN BRONZE FINISH
(E) BRONZE WINDOW UNITS,JAMB, HEAD, TO REMAIN. CLEANTO SATIN BRONZE FINISH. CLEANWINDOW GLAZING
4A10.26.2
._______ 1
A10.26.2
._______
2A10.26.2
._______
5A10.26.2
._______
T20
T20 T20
T20
GLAZING TO MEET CBEESTABLE 141.0-A.GLAZING: 1" IGU TO MEETMAX U FACTOR 0.58, MINRSHGC 0.41 AND VT 0.17FOR GLAZED DOOR, VT0.42 FOR FIXED WINDOW
A2.3
NOTE: REFER TO SIGNAGESHEETS FOR SIGNAGE ONMAIN ENTRY DOORS
architects and planners
Berkeley, CA 94710tel 510.542.2200fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
As indicated
11/3
0/2
015 1
1:0
4:0
0 A
MC
:\Use
rs\p
ha
n.d
ung
\Do
cum
ents
\Berk
ele
y 1947 C
ente
r_p
han.d
ung
.rvt
A10.25.2
MAIN ENTRY DOORDETAILS
CITY OF BERKELEY1947 Center StreetBuilding Renovation
PHASE 2
PD
PD
Nov. 4, 2015
21401
BID SET
1947 Center StreetBerkeley CA
1/2" = 1'-0"A10.25.2ENLARGED PLAN - MAIN ENTRY DOORS2
1/2" = 1'-0"A10.25.2ELEVATION - MAIN ENTRY DOORS1
NOT TO SCALEA10.25.23 TYPICAL - PHOTOS OF EXISTING CONDITION
FATS
ETFO LAC I
NROIA
R
CIL
EDESN
AECT
TICH
REN. 01-31-17
JANET TAM
No. C-14064
NO. DATE DESCRIPTION2 11/4/15 Permit Re-submittal
A2.3 11/30/15 Phase 2 Addendum 03
UP
1 2
G
H
F
E
D
C
B
A
4 5 6 7 83
STORAGE031
HHCS STORAGE026
BOILER ROOM040
BLDGMAINT/STORAGE
060
LOBBY001
MECHANICAL064
MAINELECTRICAL
061
GAS METER062
JANITOR044
MACHINE RM043
STORAGE042
MEN006
WOMEN004
BREAK ROOM041
ELEC008
STOR009
033OFFICE
034OFFICE
035OFFICE
036CONFERENCE
037OFFICE
030OPEN OFFICE
MECH052
SERVER/SUPPLY039
EXITPASSAGEWAY
051
EXITPASSAGEWAY
050
STORAGE054
032STORAGE
023MAIL
022OFFICE/FILE
020STORAGE
021DUPLICATION/PRINTING
024STORAGE
025SUPPLIES
071STORAGE
HALL007
BUILDINGSUPPLY
063
HALL005
STAIR1-B
STORAGE010
ELEV MACHROOM037A
STAIR3-B
STAIR2-B
HALL002
038STORAGE
architects and planners
Berkeley, CA 94710
tel 510.542.2200
fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
LS
NS/SL
NOVEMBER 4, 2015
21401
BID SET
1947 Center StreetBerkeley CA
NO. DATE DESCRIPTION
AS NOTED
2 11/04/15 Permit Re-SubmittalA2 11/16/15 Addendum 01
A2.3 11/30/15 Addendum 03
UP
1 2
G
H
F
E
D
C
B
A
4 5 6 7 83
LAND USEPLANNINGLIBRARY
032
STORAGE031
STORAGE022
FINANCE MAILROOM023
ENGINEERING +PUBLIC WORKS
STORAGE020
FACILITIESSTORAGE
021
IT STORAGE019
HHCS STORAGE026
NEW ITSTORAGE
024
PUBLIC WORKSSTORAGE
071
STORAGE013
COMPUTERTRAINING
012
HR TRAINING011
LUNCH ROOM003
LACTATIONROOM038
BOILER ROOM040
BLDGMAINT/STORAGE
060
LOBBY001
MECHANICAL064
MAINELECTRICAL
061
GAS METER062
JANITOR044
MACHINE RM043
STORAGE042
MEN006
WOMEN004
BREAK ROOM041
ELEC008
STOR009
STAIR3-B
MECH052
SERVER/SUPPLY039
EXITPASSAGEWAY
050
STORAGE054
STAIR2-B
HALL007
HALL005
STAIR1-B
STORAGE010
BUILDINGSUPPLY
063
EXITPASSAGEWAY
051
ELEV MACHROOM037A
HALL002
HALL014
architects and planners
Berkeley, CA 94710
tel 510.542.2200
fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
LS
NS/SL
NOVEMBER 4, 2015
21401
BID SET
1947 Center StreetBerkeley CA
NO. DATE DESCRIPTION
AS NOTED
2 11/04/15 Permit Re-SubmittalA2 11/16/15 Addendum 01
A2.3 11/30/15 Addendum 03
DNUP
1 2
G
H
F
E
D
C
B
A
4 5 6 7 83
T1
PSC PLANCHECK
COORDINATOR330
CONFERENCE/TRAINING321
MECH322
P/C ENGINEEROFFICE
343 PW MANAGEROFFICE
361
PWENGINEERINGPLAN CHECK
362
HALL340
CASHIER334
BREAK ROOM331
HOUSINGINTERVIEW
ROOM333
B&S OFFICE335
B&s OFFICE336
PSCCOORDINATOR
351
SENIOR PERMITSPECIALIST
OFFICE352
PUBLICCONFERENCE
328OPEN OFFICE -PS329
INFO +WELCOME DESK
301
PERMIT CENTER302
ELEC303
WOMEN304
HALL305
MEN306
P/C SENIORENGINEER
OFFICE341
P/C PLANCHECKEROFFICE
342
PLAN CHECK /STATION 13
344
PLAN CHECKSUPERVISOR
OFFICE347
P/C SENIORENGINEER
OFFICE346
P/C SENIORPLAN CHECKER
OFFICE348
P/C FIRE OFFICE349
CONFERENCE360
HOUSINGINSPECTOR
SUPERVISOR325
PLANCOLLATION &
STORAGE307
STAIR1-3RD
OPEN OFFICE -BUILDING
INSPECTION320
HOUSINGINSPECTIONDESK AREA
323
HALL337
OPEN OFFICE -ADMIN
350
PERMITCOUNTER
310
CSS3 OFFICE359
BLDGINSPECTOR
SUPERVISOR363
B&S OFFICE326
architects and planners
Berkeley, CA 94710
tel 510.542.2200
fax 510.542.2201
729 Heinz Avenue
JOB NO.
SCALE
CHECKED
DRAWN
SHEET NUMBER
DATE
SHEET TITLE
REVISIONS
LS
NS/SL
NOVEMBER 4, 2015
21401
BID SET
1947 Center StreetBerkeley CA
NO. DATE DESCRIPTION
AS NOTED
2 11/04/15 Permit Re-SubmittalA2 11/16/15 Addendum 01
A2.3 11/30/15 Addendum 03
1947 CENTER ST ADDENDUM 3 11.30.2015
(E) DOOR HARDWARE
1947 CENTER ST ADDENDUM 3 11.30.2015
(E) DOOR HARDWARE
1947 CENTER ST ADDENDUM 3 11.30.2015
(E) DOOR HARDWARE
BASEMENT
FIRST FLOOR
1947 CENTER ST ADDENDUM 3 11.30.2015
(E) DOOR WOOD SPECIES
THIRD FLOOR
SECOND FLOOR
1947 CENTER ST ADDENDUM 3 11.30.2015
(E) DOOR WOOD SPECIES