San Pablo Park Restroom Renovation Specification No. 18-11210-C
Addenda 00 9113-1
DOCUMENT 00 9113
ADDENDA
SPECIFICATION NO. 18-11210-C
CITY OF BERKELEY
SAN PABLO PARK RESTROOM RENOVATION
2800 PARK ST., BERKELEY, CA 94702
The following Addenda were issued, modifying the Project Manual:
Addendum No. 1, issued on August 28, 2018
(Addenda have been incorporated into the conformed Project Manual.)
END OF DOCUMENT
ADDENDUM Addendum No.1
08/27/2018 ELS Project No. 201320.20
PROJECT: San Pablo Restroom Remodel OWNER: City of Berkeley CONTRACT: Issue Set
ARCHITECT: ELS Architecture and Urban Design
Description:
The following items are additions, revisions or clarifications to the Permit Set dated January 9, 2018.
ITEM DESCRIPTION
GENERAL
Sheet A201
1. Added dimension on Floor Plan (Detail 2) between urinal screen F11 and Partition Door F6 and between first and second F11 urinal screen in Men Rm. 101
2. Additional clearance dimensions added as well as existing overall dimensions provided for reference.
Sheet A401
1. Removed Restroom Accessory T05 from accessory schedule and where shown on interior elevations.
Sheet MP102
1. Plumbing fixture schedule updated to show correct model numbers for WC-1 and WC-2
Sheet MP201
1. WC-1 and WC-2 designation added to WC’s on Floor Plan 3 (Plumbing).
End of Addendum
CITY OF BERKELEY
PARKS, RECREATION & WATERFRONT
1947 CENTER STREET, 4TH FLOOR
BERKELEY, CA 94704
CITY OF BERKELEY
PARKS, RECREATION & WATERFRONT
1947 CENTER STREET, 4TH FLOOR
BERKELEY, CA 94704
AIR MAX
FLOW TSP MAX SOUND WT
SYMBOL AREA SERVED MFR MODEL TYPE DRIVE
(CFM) (IN H2O)
RPM
(SONES)
VOLTS PH MHP
(LBS)
NOTES
EF-1 MEN'S RESTROOM GREENHECK G-075-VG CENT. DIRECT 210 0.236 1300 3.5 115 1 1/6 48 1
EF-2 WOMEN'S RESTROOM GREENHECK G-075-VG CENT. DIRECT 210 0.236 1300 3.5 115 1 1/6 48 1
NOTES:
1
FAN SCHEDULE
BASIS OF DESIGN ELECTRICAL
PROVIDE CONTROL WIRING. EXHAUST FANS SHALL BE ACTIVATED BY LIGHT SWITCH AND OCCUPANCY SENSOR. COORDINATE WITH ELECTRICAL.
PRIVATE PUBLIC PUBLIC PRIVATE PUBLIC PUBLIC
(.75)
INDIVIDUAL GENERAL HEAVY USE INDIVIDUAL GENERAL HEAVY-USE COLD HOT
DWELLING USE ASSEMBLY DESCRIPTION DWELLING USE ASSEMBLY WATER WATER
0 1 0 DRINKING FOUNTAIN OR WATER COOLER 0.00 0.50 0.75 0.50 ---
0 1 0 HOSE BIBB 2.50 2.50 0.00 2.50 ---
0 3 0
HOSE BIBB, EACH ADDITIONAL
1.00 1.00 0.00 3.00 ---
0 4 0 LAVATORY 1.00 1.00 1.00 4.00 3.00
0 2 0
URINAL, 1.0 GPF
3.00 4.00 5.00 8.00 ---
0 3 0
WATER CLOSET, 1.6 GPF, FLUSHOMETER VALVE
5.00 5.00 8.00 15.00 ---
TOTAL 33.00 3.00
FLOW IN GPM 44 NA
TOTAL GPM REQUIRED44
MAXIMUM FRICTION LOSS
PRESS. AVAIL. X 100'/EQUIV. LENGTH45.600
psi
( E) SERVICE SIZE FROM METER TO BUILDING
2"
WATER SERVICE
CALCULATIONS
(BASED ON APPENDIX 'A' - 2016 CPC)
FIXTURE QUANTITYAPPENDIX 'A' - TABLE A-2.1 TOTAL FIXTURE UNITS
2016 CPC
PUBLIC PRIVATE PUBLIC PUBLIC TOTAL
GENERAL INDIVIDUAL GENERAL HEAVY-USE FIXTURE
USE DESCRIPTION DWELLING USE ASSEMBLY UNITS
0 4 0
LAVATORY, SINGLE
1.00 1.00 1.00 4.00
0 2 0
URINAL, 1.0 GPF
2.00 2.00 5.00 4.00
0 3 0
WATER CLOSET, 1.6 GPF, FLUSHOMETER VALVE
3.00 4.00 6.00 12.00
TOTAL 20.00
PIPE SIZE (EXISTING)
4"
SANITARY DRAINAGE
CALCULATIONS
FIXTURE QUANTITYTABLE 7-3
SYMBOL FIXTURE TYPE DESCRIPTION MFR MODEL ACCESSORIES W V CW NOTES
L-1 LAVATORY
(ADA)
18" LAVATORY WITH OVAL BOWL - ADA
COMPLIANT
ACORN
ENGINEERING
COMPANY
PENAL -WARE 1652-1-LF-
03-M
LAVATORY VALVE PNUEMATICALLY
OPERATED, SET TO 15 SEC., 0.5 GPM FLOW
CONTROL. PROVIDE WITH WALL MOUNTING
HARDWARE.
2" 1-1/2" 1/2" 1,2
WC-1 WATER CLOSET
(ADA)
WALL MOUNTED ELONGATED SIPHON
JET TOILET - FLOOR OUTLET - ADA
COMPLIANT
ACORN
ENGINEERING
COMPANY
PENAL -WARE
1695-W-3-HET-FVL-ADA
FV WALL SUPPLY 1.28 GPF. PROVIDE WITH
WALL MOUNTING HARDWARE, AND SUICIDE
PREVENTION SKIRT.
4" 2" 1-1/2" 1,2
WC-2 WATER CLOSET WALL MOUNTED ELONGATED SIPHON
JET TOILET - FLOOR OUTLET
ACORN
ENGINEERING
COMPANY
PENAL -WARE
1695-W-3-HET-FV
FV WALL SUPPLY 1.28 GPF. PROVIDE WITH
WALL MOUNTING HARDWARE, AND SUICIDE
PREVENTION SKIRT.
4" 2" 1-1/2" 1,2
U-1 URINAL
(ADA)
WALL MOUNTED WASHOUT URINAL ACORN
ENGINEERING
COMPANY
PENAL -WARE
1709HEU-W-1-FVL-ADA
FV WALL SUPPLY 0.125 GPF. PROVIDE WITH
WALL MOUNTING HARDWARE.
2" 1-1/2" 3/4'' 1,2,3
NOTES:
1
2
3
PLUMBING FIXTURE SCHEDULE
BASIS OF DESIGN CONNECTION
SEE ARCHITECTURAL DRAWINGS FOR ALL FIXTURE MOUNTING HEIGHTS AND LOCATIONS. COORDINATE FINISH WITH ARCHITECT.
PROVIDE EXTENSIONS AND REDUCERS AS NECESSARY FOR CONECTION TO EXISTING ROUGH-INS
INSTALL ONE URINAL WITH MAXIMUM LIP HEIGHT OF 15-1/4" FOR ADA.
1
CONTACT
PROJECT
135 Main Street
Suite 400
San Francisco, CA 94105
TEL 415.489.7240
FAX 415.489.7289
www.interfaceengineering.com
Jan CaroJan Caro
2016-0388
SAN PABLO PARK
RESTROOM RENOVATION
201320 .07
PERMIT SET
JANUARY 9, 2018
CITY OF BERKELEY
PARKS, RECREATION & WATERFRONT
1947 CENTER STREET, 4TH FLOOR
BERKELEY, CA 94704
03/30/18
PLAN CHECK RESPONSE
08/24/18
ADDENDUM #11
MP102
SCHEDULES - MECHANICALAND PLUMBING
GENERAL SHEET NOTES
A. INSTALL ALL EQUIPMENT AND FIXTURES PER MANUFACTURER'S
RECOMMENDATIONS.
B. PERFORM CUTTING AND CORE DRILLING WITH MINIMAL DAMAGE TO CONCRETE
STRUCTURE, WALLS AND FLOOR. RESTORE TO MATCH EXISTING CONCRETE
WHEN MECHANICAL AND PLUMBING WORK IS DONE.
SHEET KEYNOTES
1 EF OUTLINE ON THE ROOF.
2 REMOVE EXISTING PLUMBING FIXTURES. PREPARE EXISTING
ROUGH-IN CONNECTIONS FOR NEW FIXTURES.
RE-REOUTE/RE-LOCATE ROUGH-INS AS NEEDED.
3 INSTALL NEW FIXTURES. PROVIDE OFFSETS TO CONNECTIONS AS
NEEDED.
4 (E)
3
4
" GAS AND REGULATOR TO REMAIN. PROVIDE TERMINATION CAP
AND TIGHTEN ALL JOINTS. ENSURE THAT NO LEAKS ARE FOUND.
5 REMOVE EXISTING GAS PIPE.
6 REMOVE (E) SHOWER HEADS INCLUDING ASSOCIATED VALVES AND
PIPES.
7 (E) FIXTURE TO REMAIN. MAINTAIN CW SUPPLY TO THIS FIXTURE.
RE-ROUTE CW SUPPLY PIPE UP HIGH IN THE CEILING. VERIFY CW
CONNECTION AND ROUTING IN FIELD.
8 REMOVE (E) PIPING; CW, GAS AND HW SERVING (E) SHOWERS AND
REMOVE WATER HEATER. CUT WATER DISTRIBUTION PIPES AND CAP
FROM MAIN WATER TIGHT, FLUSH TO FLOOR AND WALLS.
9 REMOVE EXISTING LAVATORY VALVE CONTROLS. INSTALL NEW
CONTROLS FOR NEW VALVES.
10 REMOVE (E) FLUSH VALVES AND REPLACE WITH NEW. PROVIDE
OFFSETS AND TRANSITIONS AS REQUIRED.
11 REUSE EXISTING LOCATION OF FLUSH VALVE LEVERS FOR NEW
LEVERS.
12 CLEAN-UP (E) VALVE BOX TO EXPOSE 2" CW PIPE. REMOVE (E) SOV
AND PIPE FOR NEW SOV CONNECTION.
13 PROVIDE NEW 2" SOV.
14 PROVIDE LOCK FOR VALVE BOX COVER TO SECURE VALVE.
15 MOUNT EF ON ROOF.
16 PROVIDE STOPS AND CAPS OF ALL DEMOLISHED BRANCHES FROM
THIS MAIN CW PIPE. BACKFILL AND RESTORE TO MATCH EXISTING
FLOOR.
17 NEW
3
4
" CW SUPPLY TO EXISTING MOP SINK AND HB. SEE KEYNOTE 7.
18 CW RISER. CONNECT TO (E) MOP SINK AND HB.
19 RELOCATE SS, V, DCW AND ACCESSORIES TO NEW LOCATION ON
3/MP201.
0 4' 8'
SCALE: 1/4"=1'-0"
2'
1 DEMOLITION FLOOR PLAN - MECHANICAL & PLUMBING
0 4' 8'
SCALE: 1/4"=1'-0"
2'
2 FLOOR PLAN - MECHANICAL
0 4' 8'
SCALE: 1/4"=1'-0"
2'
3 FLOOR PLAN - PLUMBING
2
9
2
2
2
2
2
2
1
3
3
3
3
3
3
3
3
3
EF-1 EF-215 15
(E) HB
(E) HB
2
(E) HB
(E) HB
7
(E) 2" CW
(E) VALVE BOX
12
8
7
5
4
6
(E) HB
(E) HB
10
11
11
11
19
19
(E) HB
13 14
(E) MOP SINK
16
1817
1
20
20. VERIFY LOCATION OF (E) BFP & WATER METER
21. SEPARATE BID ITEM 1: ALL WORK INSIDE EXISTING SHOWER ROOMS
AND EXISTING PLUMBING ROOM WILL BE PART OF SEPARATE BID
ITEM 1.
22. CONTRACTOR TO FIELD VERIFY EXISTING CONDITIONS. REPLACE
EXISTING WASTE PIPE WITH NEW 4" AS REQUIRED. USE EXISTING
TRENCH, PATCH & REPAIR FLOOR TO MATCH EXISTING FOR
INSTALLATION OF NEW PIPES
21 21
22
22
2
WC-1
WC-2
WC-1
U-1
U-1
L-1
L-1
L-1
L-1
1
CONTACT
PROJECT
135 Main Street
Suite 400
San Francisco, CA 94105
TEL 415.489.7240
FAX 415.489.7289
www.interfaceengineering.com
Jan CaroJan Caro
2016-0388
SAN PABLO PARK
RESTROOM RENOVATION
201320 .07
PERMIT SET
JANUARY 9, 2018
CITY OF BERKELEY
PARKS, RECREATION & WATERFRONT
1947 CENTER STREET, 4TH FLOOR
BERKELEY, CA 94704
03/30/18
PLAN CHECK RESPONSE
08/24/18
ADDENDUM #11
MP201
DEMOLITION PLAN & FLOOR PLANS - MECHANICAL & PLUMBING