Upload
jholo-bucton
View
216
Download
0
Tags:
Embed Size (px)
DESCRIPTION
civil engineering
Citation preview
PROJECT: PROPOSED TWO STOREY RESIDENTIAL BUILDING LOCATION: PATAG CAGAYAN DE ORO CITYSUBJECT: PROGRESS REPORT FOR OCTOBER 2015 – CURRENT
SCOPE OF ACCOMPLISHMENT ARCHITECTURAL PHASE (OCTOBER 2015 – CURRENT)
1.) CONCRETING OF STAIRS2.) INSTALLATION OF, DOORS, GLASS, WATERPROOFING3.) TILE SETTING, ROOFING WORKS, METAL FURRINGS, HAND RAILS, PIPE FITTINGS.
TOTAL ACCOMPLISHMENT PERCENTAGE AS OF NOVEMBER 6 2015: (75.63% )
PROJECT: PROPOSED TWO STOREY RESIDENTIAL BUILDING LOCATION: PATAG CAGAYAN DE ORO CITYSUBJECT: PROGRESS REPORT FOR OCTOBER 2015 – CURRENT
PIPE FITTINGS AND CONCRETING OF STAIRS
PROJECT: PROPOSED TWO STOREY RESIDENTIAL BUILDING LOCATION: PATAG CAGAYAN DE ORO CITYSUBJECT: PROGRESS REPORT FOR OCTOBER 2015 – CURRENT
RAILINGS AND METAL FURRING INSTALLATION
PROJECT: PROPOSED TWO STOREY RESIDENTIAL BUILDING LOCATION: PATAG CAGAYAN DE ORO CITYSUBJECT: PROGRESS REPORT FOR OCTOBER 2015 – CURRENT
ROOFING AND CEILING CLOSURE
PROJECT: PROPOSED TWO STOREY RESIDENTIAL BUILDING LOCATION: PATAG CAGAYAN DE ORO CITYSUBJECT: PROGRESS REPORT FOR OCTOBER 2015 – CURRENT
PAINTING WORKS (SKIMCOAT)
THANK YOU AND GOD BLESS ! !