16
Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission Serial No. 12-495 Attention: Document Control Desk NSS&L/MAE R0 Washington, DC 20555 Docket No. 50-336 License No. DPR-65 DOMINION NUCLEAR CONNECTICUT, INC. MILLSTONE POWER STATION UNIT 2 REQUEST FOR A REVISION OF AN EXEMPTION FROM 10 CFR 50, APPENDIX R. SECTION III.G., "FIRE PROTECTION OF SAFE SHUTDOWN CAPABILITY" By letter dated June 30, 2011, Dominion Nuclear Connecticut, Inc. (DNC) submitted a request for exemption from 10 CFR 50, Appendix R, Section Ill.G, "Fire Protection of Safe Shutdown Capability" for Millstone Power Station Unit 2 (MPS2). The proposed exemption request would allow the use of operator manual actions (OMAs) in lieu of the requirements of Paragraph III.G.2. By letter dated January 13, 2012, the NRC requested additional information (RAI) regarding the MPS2 exemption request. By letter dated February 29, 2012, DNC provided a response to the requested additional information. By letter dated July 12, 2012, the NRC approved the exemption request. Upon review of the approved exemption, the following was identified: Operator manual action (OMA) 1 was omitted from Fire Area R-9. " OMA 9, OMA 11 and OMA 1 were omitted from Fire Area R-1 3. " OMA 9 and OMA 1 were omitted from Fire Area R-14. As discussed in a telephone call between the NRC and DNC on October 3, 2012, the part of the DNC response to RAI-02.1 related to loss of instrument air was meant to remove loss of Instrument Air (IA) as an initiator for OMA 1, OMA 9, OMA 10 and OMA 11 in Fire Areas R-9, R-10, R-13 and R-14. A loss of IA is not postulated in these fire areas. However, these OMAs are required for postulated fire cable damage and loss of power, as discussed in the responses to other RAIs issued in the January 13, 2012 letter. Review of the approved exemption also identified one additional item which requires clarification. Consistent with the DNC letter dated June 30, 2011, Attachment 1, pages 8 and 12, other statements are needed to be added to section 3.11.1 of the approved

Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Dmno uuConciuIc 7 DominionMillstone Power Station

Rope Ferry RoadWaterford, CT 06385

OCT 29 2012

U.S. Nuclear Regulatory Commission Serial No. 12-495Attention: Document Control Desk NSS&L/MAE R0Washington, DC 20555 Docket No. 50-336

License No. DPR-65

DOMINION NUCLEAR CONNECTICUT, INC.MILLSTONE POWER STATION UNIT 2REQUEST FOR A REVISION OF AN EXEMPTION FROM 10 CFR 50, APPENDIX R.SECTION III.G., "FIRE PROTECTION OF SAFE SHUTDOWN CAPABILITY"

By letter dated June 30, 2011, Dominion Nuclear Connecticut, Inc. (DNC) submitted arequest for exemption from 10 CFR 50, Appendix R, Section Ill.G, "Fire Protection ofSafe Shutdown Capability" for Millstone Power Station Unit 2 (MPS2). The proposedexemption request would allow the use of operator manual actions (OMAs) in lieu of therequirements of Paragraph III.G.2.

By letter dated January 13, 2012, the NRC requested additional information (RAI)regarding the MPS2 exemption request. By letter dated February 29, 2012, DNCprovided a response to the requested additional information. By letter dated July 12,2012, the NRC approved the exemption request.

Upon review of the approved exemption, the following was identified:

• Operator manual action (OMA) 1 was omitted from Fire Area R-9." OMA 9, OMA 11 and OMA 1 were omitted from Fire Area R-1 3." OMA 9 and OMA 1 were omitted from Fire Area R-14.

As discussed in a telephone call between the NRC and DNC on October 3, 2012, thepart of the DNC response to RAI-02.1 related to loss of instrument air was meant toremove loss of Instrument Air (IA) as an initiator for OMA 1, OMA 9, OMA 10 and OMA11 in Fire Areas R-9, R-10, R-13 and R-14. A loss of IA is not postulated in these fireareas. However, these OMAs are required for postulated fire cable damage and loss ofpower, as discussed in the responses to other RAIs issued in the January 13, 2012letter.

Review of the approved exemption also identified one additional item which requiresclarification. Consistent with the DNC letter dated June 30, 2011, Attachment 1, pages8 and 12, other statements are needed to be added to section 3.11.1 of the approved

Page 2: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Page 2 of 3

exemption to clarify the nature of the combustible loading in fire area R-14 (i.e., lowcombustible loading in the lower 6.9 and 4.16 kV switchgear room and moderatecombustible loading in the East Cable Vault area versus low combustible loading in bothareas).

Consistent with the suggested clarifications provided above, it is requested that theapproved exemption be revised to consistently address the subject OMAs and fireloadings. Attachment 1 contains a summary of requested changes to the affectedsections of the issued exemption. The summary specifically includes the identifiedOMAs to fire areas where cable damage or loss of power is postulated and clarificationof the combustible loading in fire area R-14.

If you have any questions regarding this submittal, please contact Ms. Wanda Craft at(804) 273-4687.

Sincerely,

J. AIl PriceVice President - Nuclear Engineering

Commitments made in this letter: None

Attachments:

1. Summary of Recommended Changes to the Affected Sections in the NRCApproved Exemption from Specific Requirements of 10 CFR 50, Appendix R,Section III.G.2.

Page 3: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Page 3 of 3

cc: U.S. Nuclear Regulatory CommissionRegion I2100 Renaissance BlvdSuite 100King of Prussia, PA 19406-2713

J. S. KimProject ManagerU.S. Nuclear Regulatory CommissionOne White Flint North, Mail Stop 08 C2A11555 Rockville PikeRockville, MD 20852-2738

NRC Senior Resident InspectorMillstone Power Station

DirectorBureau of Air ManagementMonitoring and Radiation DivisionDepartment of Environmental Protection79 Elm StreetHartford, CT 06106-5127

Page 4: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

ATTACHMENT I

Summary of Recommended Changes to the Affected Sections in the NRCApproved Exemption from Specific Requirements of 10 CFR 50, Appendix R.

Section III.G.2

DOMINION NUCLEAR CONNECTICUT, INC.MILLSTONE POWER STATION UNIT 2

Page 5: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Attachment 1 page 1 of 12

Summary of Changes to the Affected SectionsChanges are shown in red

Table 1

Area of Area Name Actions OMAFire

OriginOpen Valve 2-CH-508 to Obtain OMACharging Pump Suction from Boric 4

Facility Z1 Direct Current Acid Storage TankFire Area Facility Roo Dire end Open Valve 2-CH-509 to Obtain Pump OMA

R-9 Switchgear Room and Suction from Boric Acid Storage Tank 5Open Valve 2-CH-192 to Establish OMACharging Pump Suction from IRefueling Water Storage Tank

Area of Area Name Actions OMAFire

OriginOperate Valve SV-4188 from Panel C-10 OMA

22Operate Speed Control Circuit H-21 from OMAPanel C-10 to Control Turbine Driven 17Auxiliary Feedwater Pump SpeedOperate 2-FW-43B from Panel C-10 OMA-9Operate 2-MS-190B from Panel C-10 to OMATransition from Main Steam Safety 11ValvesCheck Local Condensate Storage Tank OMA20Level Indication at LIS-54 89

Fire Area West (Facility Z1) Pull Control Power Fuses and Ensure OMAR-1 3 480 VAC Swichgear Breaker A406 is Open 16

Room Close Breaker DV2021 at Panel DV20 OMA24

Open Valve 2-CH-508 to Obtain Charging OMA 4Pump Suction from Boric Acid StorageTankOpen Valve 2-CH-509 to Obtain Pump OMA 5Suction from Boric Acid Storage TankOperate Pump P18C from Panel C-10 OMA

21Open Valve 2-CH-192 to Establish OMA ICharging Pump Suction from RefuelingWater Storage Tank I I

Page 6: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Attachment 1 page 2 of 12

Area of Area Name Actions OMAFire Origin

Operate 2-FW-43B from Panel C-10 OMA-9Open Valve 2-CH-508 to Obtain OMA 4Charging Pump Suction from Boric AcidStorage TankOpen Valve 2-CH-509 to Obtain Pump OMA 5Suction from Boric Acid Storage TankPull Control Power Fuses and Ensure OMA 14Breaker A410 is Open to IsolateRequired Bus

Facility Z1 Pull Control Power Fuses and Ensure OMA 13Fire Area Lower 4.16kV Breaker A408 is Open to Isolate

R-14 Switchgear Required BusRom Vant Pull Control Power Fuses and Ensure OMA 23Cable Vault Breaker A401 is Closed to Power Bus

from the Emergency Diesel GeneratorPull Control Power Fuses and Ensure OMA 15Breaker A411 is Open to IsolateRequired BusClose Breaker DV2021 at Panel DV20 OMA 24Open Valve 2-CH-192 to Establish OMA 1Charging Pump Suction fromRefueling Water Storage Tank

Page 17

characteristics, The licensee further stated that a failure of MCC B-41 B could also

serve as an ignition source and that an MCC failure normally results in a high intensity

fire that lasts for a short duration, which makes it unlikely that it will cause sustained

combustion of IEEE 383 qualified cables despite the fact that the subject cable trays

are located approximately 6-81-e CC. The smoke detection system, whichIinches

consists of an ionization smoke detector located directly over MCC B61, will aid

providing prompt Fire Brigade response.

Page 7: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Attachment 1 page 3 of 12

page- 42

changes to fire area R-9 discussion;

3.7.4 OMAs Credited for a Fire in this Area

In their letter dated February 29, 2012 the licensee deleted OMAs 1 and 11

from the exemption request for fire area R-9 since loss of IA is no longer postulated.

3.7.4.1 AFW and Charging System Flow

3.7.4.1.1 OMAs 1., 4 and 5, - Open Valve 2-CH-192. Open Valve 2-CH-508 and

Open Valve 2-CH-509

The licensee stated that for a fire in fire area R-9, the Charging system has

OMAs identified and that the BASTs gravity feed valves, 2-CH-508 (OMA 4) and 2-

CH-509 (OMA 5), may fail as is (closed) due to a loss of power supply. The licensee

also stated that an OMA is in place to locally open the valves as part of restoring the

Charging system and that once these valves are opened, the CR can establish

charging flow within 2-3 minutes. The licensee further stated that establishing

charging pump suction from the BASTs and restoring charging is required within

three hours of reactor shutdown/loss of charging and that Charging is reestablished

within 24 minutes (21 minutes to open the BASTs valves and 3 minutes to establish

charging flow in the CR) which provides a 156 minute margin. The licensee further

stated that prior to BAST depletion, Operators switch over to the RWST. The

licensee further stated that cables for 2-CH-192 do not pass through the fire

area but the valve may fail closed if DV10 lost power and that an OMA would be

required to open valve 2-CH-192 (OMA 1). OMA I establishes the RWST as the

suction supply for the charging system. The BASTs have a minimum TRM

Page 8: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Attachment 1 page 4 of 12

specified inventory to ensure 72 minutes of flow after charging is reestablished

and OMA I can be completed in 32 minutes which results in 40 minutes of

margin.

3.7.4.2 OMA Timing

AFW flow is established from the CR within the required 45 minute time

period. The OMA to establish Charging system flow from the BASTs can be

completed in 24 minutes which provides a 156 minute margin since the required

completion time is 180 minutes. The OMA to establish Charging system flow

from the RWST prior to BAST depletion can be completed in 32 minutes which

provides a 40 minute margin since the required completion time is 72 minutes.

Changes to fire area R-13, starting on page 49

3.10.4 OMAs Credited for a Fire in this Area

In their letter dated February 29, 2012, the licensee stated that deleted

OMA. 1, 0, and 11, from the o -ompti.n roquet for fire area R-13-sUtie loss of IA

is no longer postulated.

3.10.4.1 AFW Flow

3.10.4.1 1 OMAs 9, 22 and 17 -Operate Feed Regulating Valve 2-FW-43B from

the C10 panel, Operate Supply Valve SV-4188 from Panel C10 and

Operate Turbine Driven AFW Pump Speed Control Circuit H-21 from Panel

C10

The licensee stated that for a fire in the area, OMAs are required to provide decay

heat removal and restore Charging system flow to the RCS and that establishing

Page 9: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Attachment 1 page 5 of 12

AFW flow to the credited SG is required within 45 minutes. The licensee stated that

for a fire in the area, the required AFW flow path utilizes the TDAFW pump and that

due to fire induced cable damage, AFW turbine steam supply valve (SV-4188) (OMA

22), and TDAFW turbine speed control (H21) (OMA 17) may not be available from

the CR. The licensee further stated that the cable damage can be isolated and the

TDAFW pump can be operated from the Fire Shutdown Panel (C-10) located in fire

area R-2 and that an OMA is necessary to isolate the damaged cables and operate

the TDAFW turbine speed control to maintain level in the SG. The licensee stated

that in the case of 2-FW-43B, cable damage could result in spurious operation and

that isolation of the affected cables and control of the valve can be accomplished at

the C-10 panel (OMA 9), and that control of SG water level can be maintained using

the speed control function of the TDAFW pump. The licensee further stated that the

timeframe to establish control of TDAFW at the C-10 panel is 45 minutes and that

after Reactor Operator 1 (RO-1) has established control of TDAFW pump speed at

the C-10 panel (8 minutes), it will take an additional 2 minutes to establish AFW flow

which results in a total time to establish AFW flow of 10 minutes, leaving a 35 minute

margin.

3.10.4.1.2 OMAs 11 and 20 - Operate Valve 2-MS-190B from panel C10, Obtain,

CST Level at Local Level Indicating Switch LIS-5489A

The licensee stated that valves 2-MS-190B and 2-FW-43B can be operated

from the C10 panel and that the OMA for local or C-10 operation of 2-MS-1 90B (OMA

11) is not required until after AFW flow is established and that PEO-1 will remain with

the ADV to modulate steam flow per direction from the CR. The licensee further

Page 10: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Attachment 1 page 6 of 12

stated that the final decay heat removal function is to monitor CST level from either

the C-10 panel (LT-5282) or locally at the CST (11S-5489) (OMA 20) and that

checking the level is not a short-term requirement because there is sufficient

inventory in the CST to provide over 10 hours of water flow to the AFW system. The

licensee further stated that a spurious start of the TDAFW coupled with 2-FW-43B

failing open should not result in a SG overfill and that the nominal water level in the

SG is maintained between 60-75% as indicated on the Narrow Range (NR) level

instruments (i.e., the normal operating band). The licensee further stated that from

the top of the normal operating band, more than 8000 gallons of water can be added

before reaching 100 percent on the NR level instruments and allotting 8 minutes to

establish operations from the C-1 0 panel and assuming all the flow from the TDAFW

is filling one SG, approximately 4800 gallons can be added before regaining level

control. The licensee further stated that there is also an additional 14,000 gallons of

margin available before the SG would overfill (i.e., from 100 percent NR to the Main

Steam nozzle).

3.10.4.2 Charging System Flow

3.10.4.2.1 OMAs 1, 4. 5, 16, 21, and 24 - Open Valve 2-CH-192, Open Valve 2-CH-

508, Open Valve 2-CH-509, Pull Control Power Fuses for Breaker A406

and Ensure Breaker is Open, Operate Pumr P 18C from Panel C 10. and

Locally Close Breaker DV2021

The licensee stated that for a fire in the area, the Charging system has OMAs

identified. The BASTs gravity feed valves, 2-CH-508 and 2-CH-509, may fail as is,

(closed) due to cable damage and that OMAs are (OMA 4 and 5) in place to locally

Page 11: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Attachment 1 page 7 of 12

open these valves as part of restoring the Charging system. The licensee further

stated that cable damage due to fire may also cause a spurious start of the P18C

Charging Pump and that cable damage may be mitigated by isolating and operating

P18C (OMA 21) at the C-10 panel. The licensee further stated that RO-1 is at C-10

and must manipulate the controls for P18C and that establishing pump suction from

the BASTs and operating P18C is required within 3 hours of reactor shutdown/loss of

Charging. The licensee further stated that completing the OMAs to reestablish

Charging would take 23 minutes leaving a margin of 157 minutes, which includes the

parallel actions of PEO-2 establishing control of Bus 240 (by pulling control power

fuses to circuit breaker A406 (OMA 16), ensuring A406 is open and closing breaker

DV2021 (OMA 24) and PEO-3 (by manually aligning valves 2-CH-508 and 2-CH-

509). The licensee further stated that after the BASTs have reached the 10 percent

level, Operators switch Charging Pump suction over to the RWST and valve 2-CH-

192 may fail closed, but it can be controlled from the CR for approximately 8 hours

until after the depletion of the "A" battery, due to a loss of power supply to the

battery charger. The licensee further stated that cables for 2-CH-192 do not

pass through the fire area but the valve fails closed when battery "A" is

depleted, and that an OMA would be required to maintain open valve 2-CH-192

(OMA 1). OMA I establishes the RWST as the suction supply for the charging

system.

Page 12: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Attachment 1 page 8 of 12

R-14 Changes, starting on page 53

3.11 Fire Area R-14. Lower 6.9 and 4.16 kV Switchqear Room. East Cable Vault

3.11.1 Fire Prevention

The licensee stated that the Lower 6.9 and 4.16 kV Switchgear Room

areas have low combustible loading that predominantly consists of cable insulation

and Thermo-Lag fire resistant wrap, and that potential ignition sources include

electrical faults.

The licensee stated that the East Cable Vault area have moderate

combustible loading that predominantly consists of cable insulation and

Thermo-Lag fire resistant wrap, and that potential ignition sources include

electrical faults.

Continuing on page 55

3.11.4 OMAs Credited for a Fire in this Area

In their letter dated February 29,2012, the licensee deleted OMAe--19--and

11 from the exemption request for fire area R-14 since loss of IA is no longer

postulated.

The licensee stated that during verification and validation of the AOPs, it was

identified that for a fire in fire area R-14 an additional operator might be necessary to

place the plant into hot standby. The staffing requirements for MPS2 were changed to

add one licensed or non-licensed operator over the minimum technical specification

(TS) requirement to be on duty each shift during Modes 1, 2, 3, or 4, with this operator

being designated as the Appendix R operator and is not part of the credited five man

Fire Brigade crew.

Page 13: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Attachment 1 page 9 of 12

3.11.4.1 Charginq and AFW System Flow

3.11.4.1.1 OMAs 4 and 5 - Open Valve 2-CH-508 and Open Valve 2-CH-509

The licensee stated that the Charging system has OMAs identified in that

the BASTs gravity feed valves, 2-CH-508 and 2-CH-509, may fail as is (closed) due

to a loss of power supply and that OMAs are in place (OMA 4 for 2-CH-508 and OMA

5 for 2-CH-509) to locally open these valves as part of restoring the Charging system.

The licensee further stated that establishing Charging Pump suction from the BASTs

is required within 3 hours of reactor shutdown/loss of Charging and that RO-1 and

PEO-3 will perform their OMAs in parallel (see Section 3.11.4.1.2) to restore

Charging. OMAs 4 and 5 are completed in 21 minutes.

3.11.4.1.2 OMAs 1. 13, 14, 15, 23, and 24 - Open Valve 2-CH-192, Pull Control

Power Fuses for Breaker A408 and Ensure Breaker is Open, Pull Control

Power Fuses for Breaker A41 0 and Ensure Breaker is Open, Pull Control

Power Fuses for Breaker A411 and Ensure Breaker is Open, Pull Control

Power Fuses for Breaker A401 and Ensure Breaker is Closed, and Locally

Close Breaker OV2021

The licensee stated that as part of the restoration of Charging flow to the RCS, Bus

24D must be isolated from cross-ties to Bus 24B, Bus 24E and the RSST and that

this is due to fire induced cable damage which may result in spurious operation/loss

of control from the CR of breakers A401, A410, A408 and A411, The OMAs

associated with these breakers are to pull the control power fuses and ensure that

breakers A410 (OMA 14), A408 (OMA 13) and A411 (OMA 15) are open and that

breaker A401 (OMA 23) is closed, The licensee also stated that once RO-1

Page 14: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Attachment 1 page 10 of 12

completes the OMAs, PEO-1 will then reset and close breaker DV2021 (OMA 24).

OMAs 13, 14, 15, 23 and 24 are completed in 24 minutes, then it will take an

additional 3 minutes for the CR to establish Charging flow for a total of 27 minutes

which results in a 153 minute margin since the required completion time is 180

minutes. The licensee further stated that after the BASTs have reached the 10

percent level, Operators switch Charging Pump suction over to the RWST.

Cables for valve 2-CH-192 do not pass through the fire area but the valve fail

close when battery "A" is depleted, approximately 8 hours, due to a loss of

power supply to the battery charger. OMA would be required to maintain open

valve 2-CH-192 (OMA 1). OMA I maintains the RWST as the suction supply for

the charging system.

3.11.4.1.3 OMA 9-Operate Feed Regulating Valve 2-FW-43B from the C10 panel

The licensee stated that for a fire in the area, OMA 9 is required to

provide decay heat removal. Establishing AFW flow to the credited SG is

required within 45 minutes. The licensee stated that for a fire in the area valve

2-FW-43B cable damage could result in the valve not operational from the CR

and that isolation of the affected cables and control of the valve can be

accomplished at the C-10 panel (OMA 9). The licensee further stated that the

timeframe to establish control of AFW at the C-10 panel is 45 minutes and that

after Reactor Operator 1 (RO-1) has established control of 2-FW-43B at the C-10

panel (4 minutes), it will take an additional 2 minutes to establish AFW flow

which results in a total time to establish AFW flow of 6 minutes, leaving a 39

minute margin.

Page 15: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Attachment 1 page 11 of 12

3.11.4.2 OMA Timing

The OMAs to establish Charging system flow from the BASTs can be

completed in 27 minutes which provides for a margin of 153 minutes since the

required completion time is 180 minutes. The OMA to establish AFW flow can be

completed in 6 minutes which provides a 39 minute margin since the required

completion time is 45 minutes.

Changes to table 3:

Available Time toFire Area of Activity OMAs Time Conduct MarginFire Origin (min) OMAs (min)

(me) (min)Fire Area R-9 Establish 4,5 180 24 156

(Facility Z1 DC ChargingSwitchgear Suction fromRoom and BAST

Battery Room) Establish 1 72 32 40ChargingSuction

from RWST

Page 16: Dmno uuConciuIc Dominion - NRC: Home Page · Dmno uuConciuIc 7 Dominion Millstone Power Station Rope Ferry Road Waterford, CT 06385 OCT 29 2012 U.S. Nuclear Regulatory Commission

Serial No. 12-495Docket No. 50-336

Attachment 1 page 12 of 12

Available Time toFire Area of Fire AAvime Conduct Margin

Origin Activity OMAs Time OMAs (min)(mi) (min)

Fire Area R-13 (West Establish 9, 17, 45 10 35(Facility Z1) 480 VAC AFW Flow 22

Switchgear Room) Establish 4, 5, 16, 180 23 157Charging 20, 21,

Suction from 24BASTs

Establish 1 72 32 40ChargingSuction

from RWSTFire Area R-14 Establish 9 45 6 39

(Facility Z1 Lower AFW Flow4.16kV Switchgear Establish 4, 5,13, 180 27 153Room and Cable Charging 14,15,

Vault) Suction from 23, 24BASTs

Establish 1 72 32 40ChargingSuction

from RWST

I

A