DLR CITY AIRPORT EXT.

Colin Burnikell9th Feb. 2021Ashford Section Meeting

Page 2: DLR CITY AIRPORT EXT

DOCKLANDS LIGHT RAILWAY – CITY AIRPORT EXTENSION (DEC 2005)

Facts & FiguresMain Contractor – Amec Spie RailProject Value - £6mConstruction of:4.5km viaductNew Stations including:• West Silvertown• Pontoon Dock• London City Airport

2PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 3: DLR CITY AIRPORT EXT

SITE OPERATION - PRE-CAST YARD

OverviewSite located at: Dock Road, Canning Town. London E16.• Office facilities & factory set up

on site.• Manufacture of the various

concrete products.

3PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 4: DLR CITY AIRPORT EXT

4

CIVIL ENGINEERING

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 5: DLR CITY AIRPORT EXT

SITE OPERATION – CONSTRUCTING THE VIADUCT

5PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 6: DLR CITY AIRPORT EXT

SITE OPERATION – CONSTRUCTING THE VIADUCT

Constructing the viaductThe viaduct segments were cast on site, stored & installed over the first phase of the project duration.

Services.Cable penetrations for services were catered for to eliminate any external fastening to the structure.

Alignment.This was essential & each segment was moulded from the previous section to ensure an exact fit.

6PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 7: DLR CITY AIRPORT EXT

THAMES WHARF VIADUCT

7PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 8: DLR CITY AIRPORT EXT

TRANSITION SLAB

8PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 9: DLR CITY AIRPORT EXT

9

TRACK BED PREPERATION

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 10: DLR CITY AIRPORT EXT

TRACK BED CONSTRUCTION

10

Permanent Way installation could take place once the viaduct was assembled.Various light rail components were utilised.Preparation was key.• Resourcing.• Logistics (delivery).• Availability of products.• Storage.

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 11: DLR CITY AIRPORT EXT

TRACK BED CONSTRUCTION

11

Permanent Way installation could take place once the viaduct was assembled.Various light rail components were utilised.Preparation was key.• Resourcing.• Logistics (delivery).• Availability of products.• Storage.

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Drainage

Page 12: DLR CITY AIRPORT EXT

TRACK BED PREPARATION - SCABBLING

12

• Scabbling of the concrete surface was part of the preparation works.

• This would provide the ideal base for the grout that was going to be installed.

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 13: DLR CITY AIRPORT EXT

TRACK BED PREPARATION - SCABBLING

13

• Scabbling of the concrete surface was part of the preparation works.

• This would provide the ideal base for the grout that was going to be installed.

• Working in a controlled fashion although a manual process a template was used.

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 14: DLR CITY AIRPORT EXT

TRACK BED PREPARATION - SCABBLING

14

• Scabbling of the concrete surface was part of the preparation works.

• This would provide the ideal base for the grout that was going to be installed.

• Working in a controlled fashion although a manual process a template was used.

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 15: DLR CITY AIRPORT EXT

TRACKWORK PREPARATION

Component parts laid out.On both the curved track & straight.

15PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 16: DLR CITY AIRPORT EXT

TRACKWORK PREPARATION

Track geometryTrackwork set up to represent the initial layout.

16PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 17: DLR CITY AIRPORT EXT

TRACKWORK PREPARATION – PANDROL VIPA BASEPLATE

Plain line track assembly• Pandrol Vipa 2 hole baseplate was used.

• Shown here suspended from the rail above the prepared ‘scabbled’ concrete.

17PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 18: DLR CITY AIRPORT EXT

18

ANCHOR TESTING

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 19: DLR CITY AIRPORT EXT

TRACKWORK – ANCHOR PROOF TESTING

Anchor testing (70kN)• 5 different chemical anchors tested with an M24 anchor.

– Injectable resin & Capsule.• Results were quite ‘variable’…….• Bond failure in some cases.

19PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 20: DLR CITY AIRPORT EXT

TRACKWORK – ANCHOR PROOF TESTING

Anchor testing.• 2 Hilti chemical anchor variants were tested with Hilti HRT anchors:

– Injectable resin (RE500) & Capsule (HVU).• Concrete cone failure was the mode of failure.• 150kN achieved (RE).

20PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 21: DLR CITY AIRPORT EXT

TRACKWORK – ANCHOR PROOF TESTING

Replication of ‘poor workmanship’.• 28mm Dia. holes were drilled. Holes were filled with water.

– Hilti Injectable resin (RE500) was installed into the holes with standing water.• Once cured, the anchors were tested.

21PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 22: DLR CITY AIRPORT EXT

TRACKWORK – INTERNAL/INDEPENDENT ANCHOR TESTING

Test Reports.

Internal (Schaan)• 3m cycles.

External• TUM submitted.• Joseff Eisenmann.

22PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 23: DLR CITY AIRPORT EXT

TRACKWORK – HOLE CLEANING

Anchor hole cleaningEssential for when using chemical anchors.

23PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 24: DLR CITY AIRPORT EXT

24

DRILLING TRIALS

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 25: DLR CITY AIRPORT EXT

TRACKWORK – DRILLING TRIALS

Options for drilling holes for holding down bolts.• Diamond drilling (DD150 & DD200).

• Percussive (TE80).

25PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 26: DLR CITY AIRPORT EXT

TRACKWORK – DRILLING METHOD CONFIRMED

Preference Hilti ‘rig mounted’ drilling wagon.• Perpendicular to slab.• Percussive Hilti TE80 drill with TE-YX 28 drill bits were attached (x 2).

– Reduced HAV’s.• Depth stop was attached to prevent over drilling & minimize resin wastage.

26PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 27: DLR CITY AIRPORT EXT

TRACKWORK – DRILLING METHOD CONFIRMED

Preference Hilti ‘rig mounted’ drilling wagon.• Perpendicular to slab.• Percussive Hilti TE80 drill with TE-YX 28 drill bits were attached (x 2).

– Reduced HAV’s.• Depth stop was attached to prevent over drilling & minimize resin wastage.• Drilling jig used.

27PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 28: DLR CITY AIRPORT EXT

28

VIBRATION TESTING

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 29: DLR CITY AIRPORT EXT

TRACKWORK – VIBRATION TESTING

Testing set up.• Wired up to rig.• Vibration measured over several trials.• Results ave. 7ms2.

29PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 30: DLR CITY AIRPORT EXT

30

TRACKWORK INSTALLATION

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 31: DLR CITY AIRPORT EXT

TRACKWORK INSTALLATION – PART 1 (HOLDING DOWN BOLTS)

Installation of M24 holding down bolts• Using Hilti RE500 injectable resin.• Piston Plugs were also supplied.• P8000 pneumatic dispenser.

– Dosage meter.31PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 32: DLR CITY AIRPORT EXT

TRACKWORK INSTALLATION – PART 2 (GROUT BED)

Grout bed installation• Shuttering applied confirming ‘footprint’.

• For inclement weather, covering was used.

32PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 33: DLR CITY AIRPORT EXT

TRACKWORK INSTALLATION – PART 2 (GROUT BED)

Grout bed installation• Grout mixed & applied.• Plasticine used to prevent any overflow.• Sand around the base.

33PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 34: DLR CITY AIRPORT EXT

34

ADDITIONAL P. WAY COMPONENTRY

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 35: DLR CITY AIRPORT EXT

TRACKWORK – S. & C. COMPONENTRY

S. & C. Baseplate• Cologne Egg 4-hole baseplate was specified.• Installed with Hilti RE500 injectable resin.

35PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 36: DLR CITY AIRPORT EXT

TRACKWORK – ADDITIONAL COMPONENTRY

36PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 37: DLR CITY AIRPORT EXT

TRACKWORK – ADDITIONAL COMPONENTRY

Third Rail• Brecknell Willis system deployed in pre-cast spacing.• ‘Pick up’ from the underside.• Fastening ‘cast in’.

37PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 38: DLR CITY AIRPORT EXT

38

ANCHOR INTEGRITY

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 39: DLR CITY AIRPORT EXT

TRACKWORK – ANCHOR INTEGRITY

Testing & Recording• 5% of anchors tested.• Independent Company used.

– Sheer load recorded.39PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 40: DLR CITY AIRPORT EXT

40

STATION WORKS

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 41: DLR CITY AIRPORT EXT

DOCKLANDS LIGHT RAILWAY – CITY AIRPORT EXTENSION (DEC 2005)

Station ConstructionSilver Town & Pontoon Dock

Presentation title | Month 202x 41

Page 42: DLR CITY AIRPORT EXT

42

SUMMARY

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 43: DLR CITY AIRPORT EXT

DLR CITY AIRPORT EXTENSION – TRACKWORK SUMMARY• 80Lb Rail used.• Plain line.

– Pandrol Vipa 2-hole baseplate.• S. & C.

– Cologne Egg 4-hole baseplate• Drilling wagons & Hilti TE80’s with TE-YX

28/81 drill bits.• Hilti RE500 (1400ml) injectable resin.• M24 HDG Holding down bolts.• Grout – SBD Epoxy plus.• Third Rail – Brecknell Willis

43PWI Ashford Section Mtg – Colin Burnikell | Feb 2021

Page 44: DLR CITY AIRPORT EXT

PWI Ashford Section Mtg – Colin Burnikell | Feb 2021 44