Upload
truongnhan
View
218
Download
2
Embed Size (px)
Citation preview
DISTRIBUTION SYSTEMS EXPANSION PLANNING BY MULTI-STAGE BRANCH EXCHANGE TAKING FAULT INTO CONSIDERATION
Koichi Nara Ibaraki University
Hitachi, Ibaraki 316 JAPAN
Hijiro Kuwabara Kinki University
Kure, Hiroshima 737-01 JAPAN
Taiji Satoh Yamaguchi Univ. Ube, Yamaguchi
JAPAN
Kenichi Aoki Hiroshima Pref. Univ.
Minoru Kitagawa Chugoku Electric Power Co. Ohno, Saeki-gun, Hiroshima
JAPAN Shobara, Hiroshima
JAPAN
ABSTRACT- The expansion planning problem in distribution system is an extremely complex combinatorial optimization problem if it takes faults into consideration. So, it is very difficult to find a practically usable solution of the problem. In this paper, the authors propose a new algorithm that can take fault cases into account. The algorithm is based on the multi-stage branch exchange method, and the solution is rather ~ccurate when compared with an existing method. The proposed method can take all the predetermined severe fault cases into consideration simultaneously, and can help in avoiding inst al lation of excess facilities without affecting the ability for fault restoration. The validity and the effectiveness of the proposed algorithm are demonstrated by several numerical examples.
Keywords : Distribution system operation and control, Transmission planning method, Fault restoration
1. INTRODUCTION
With the rapid increase of electrical energy consumption, the distribution system expansion planning problem has become an important problem in electric power industries. Many approaches for the problem have been developed and proposed[l-14]. However, the expansion planning problem in distribution system becomes an extremely complex combinatorial optimization problem if it takes faults into consideration. So, it is very difficult to find a practically usable solution of the problem. In the distribution planning area, there had been no publication which explicitly takes fault cases into consideration until the authors proposed the method based on the single-stage branch exchange method[l4]. Al though, this method is highly efficient in finding a sub-optimal planning, the calculation results are approximated ones, and even feasible solutions occasionally cannot be found through the method for real scale problems. In the meantime, the authors also have proposed what has been called the multi-stage branch exchange method[l3] so as to find more accurate solutions than the single stage branch exchange algorithm.
In this paper, the authors propose a new algorithm based on the multi ~stage branch exchange that can take fault cases into account. The calculation results are rather accurate when compared with those of the existing method. The proposed method can take all the predetermined severe fault cases into consideration simultaneously, and can help avoiding installation of excess facilities without affecting the ability for fault restoration. In other words, an expansion _plan is developed under which all load sections except the fault one can be supplied "l:_h!'ough the
fault state reconfiguration in any predetermined case. In the algorithm, the whole problem is decomposed into sub-problems according to predetermined fault cases, and is efficiently solved by using the multi-stage branch exchange algorithm and the decompositioncoordination technique.
In Chapter 2, the problem is precisely defined and mathematically formulated. The detailed solution algorithm through multistage branch exchange method is shown in Chapter 3. The validity and the effectiveness of the proposed algorithm are demonstrated by several numerical examples compared with those of the existing method in Chapter 4.
2. DESCRIPTION OF THE PROBLEM
2.1 Illustration of the Problem In the open loop radial distribution
system, although many loops are constructed by installed facilities, the system is operated as a radial system by opening several sectionalizing switches. Therefore, even in the case of a fault, power can be supplied to the black-out area by closing appropriate open sectionalizing switches.
The problem here is to . find such a minimum cost expansion plan that can supply power to all the load sections except that in which the fault exists, even in the event of any fault.
To solve the problem, if one of the existing methods is simply applied to every predetermined fault case independently, and all the facilities which are found to be necessary to supply power to all the load sections are installed, then the degree of redundancy of the installed facilities becomes large, and extra installation cost _becomes necessary. So as to avoid such extra cost, all the constraints of each fault case must be formulated simultaneously, and the problem must be solved in one lump .
2.2 Formulation of the Problem The distribution system model shown in
Fig.l is used to formulate the problem[9] . . In Fig.l, nodes show substations, transformers and load points. The branches represent electrical connections between nodes. Each branch has its impedance, current capacity and installation cost . This model is introduced to each fault case to formulate the constraint equations. To formulate the problem, the following is also assumed:
( 1) Candidates for facilities to be in-stalled are known beforehand,
( 2) The load is a lumped constant current load of which the power factor is 1.0,
( 3) Fault cases which should be considered are pre-determined.
131
Notations
• : source node - - - : potent.ial feeder
@ : transfonner node
~ : substation node
0 :load node
- :existing feeder
I
substation installation cost \
T31 I
~ feeder cost
~ -------T22 __ __.
---~-------0 /
T21
feeder :x------installation1 cost -(fixed cost) -------
I I I
Fig.I Distribution system planning model
Then, the problem in which faults are taken into consideration can be formulated as the following linear mixed-integer programming problem[14].
[Objective function] m
Min. Zc =. 1:cjwj J=l
. [Constraints]
(a) Installed facility constraint
(b) Constraint for radial configuration m
( l)
( 2)
1:Yjt = n-1 (with connected graph) (3) j=l
(c) Power flow availability
+ I+ Myjt-Xjt -Sjt 0
- I-Myjt-xjt -sjt 0
(j=l,2, ... ,m
(d) Kirchhoff's current law
AtXt = D,
( t= 1, 2, ... , T
(e) Node-voltage constraints
+ ' V++ V+- O (vit-Vktl-Rjxjt +Sjt -Sjt =
- V-+ V-- 0 (vit-vktl-Rjxjt +sjt -sjt =
( t = 1,2, ... ,T, j = 1,2, ... ,m
(f) Current capacity constraints
- + IM+ IM+_o xrxjt -Sjt +a jt -
- - IM- IM- 0 xrxjt -sjt +a jt =
IM+_o IM- 0 a jt - , a jt ':' '
t = 1,2; ... ,T, j = 1,2, ... ,m
(g) Voltage drop constraints
v. t-v-s. tVM+a . tVM=O, l. - l. l.
VM · (ait =0)
t = 1,2, ... ,T, i = 1,2, ... ,n)
( 4)
( 5)
( 6)
( 7)
( 8)
(h} Nonnegative and integer constraint
+ - 0 xjt' xjt' vit' sjt• ajt~ '
YjtE{O, 1), wj€{0, 1}
( t = 1,2, ... ,T, j = 1,2, ... ,m) (9)
where, m Number of branches n Number of nodes including source node T Number of predetermined fault cases D Demand vector (element di represents demand at
node i) At (n-1) x m node-branch incidence matrix of fault
case t cj Installation cost of branch j;
cj=O for existing facility wj 0-1 Integer variable;
wj=l : if fac~lity j is installed W·=O : otherwise
Yjt: 0-1 in~eger decision variable; Yjt=l · : if facility j is used in fault
case t Y·t=O : otherwise
xjt:Power flow in branch j in fault case t; X·t = X·t+-X·t-
J tjt+:torward power flow x.t-:Inverse power flow
vit: Voltage at nod~ i in fault case t xj : Capacity of branch j R· Impedance of branch j yJ Allowable voltage drop M Large constant
I+ I- v++ v+- v-+ V-- IM+ IMsj ,Sj ,Sj ,sj ,Sj ,sj ,Sj ,Sj •
sjVM : Slack variables
a ·=a .IM+ IM- VM • Violation variables J J , a j , Oj •
Total installation cost Small value to avoid the zero divide or multiplication
3. SOLUTION ALGORITHM
3.1 Brief Explanation of the Algorithm The coefficient matrix of the equations of
the above formulation is schematically shown in Fig. 2, for the example of the 3 fault cases. Coefficients exist only in the shaded area. Since coefficients exist in limited places, we can apply the decomposition-coordinat1on strategy to solve the problem[l4]. That is, by hypothetically giving the installed facilities (or by determining the value of w . ), the whole problem can be decomposed into sdb-problems according to the fault case, and we optimize the each sub-problem by using the multi-stage branch exchange algoritlun. The
fault case 1·
fault case 2
fault case 3
facility installation cost
Min . Cil
Eq. ()I Eq . ( 9)
Eq. ( 2)
Fig.2 Schematic expression of the problem
132
whole solution algorithm consists of the following steps.
[Step 0)
[Step l]
[Step 2)
[Step 3]
[Step 4)
[Step 5)
Initial expanded branches (or used branches) are determined so as to construct an initial tree configuration, Multi-stage branch exchange for each fault case, Reduction of the sum of constraint violations of all the fault cases by single facility expansion, Reduction of the sum of constraint violations of all the fault cases by multi-facility expansion , Reduction of the sum of constraint violations by using all candidate facilities , Reduction of installation cost by removing installed but unnecessary facilities.
The general flowchart of the solution algorithm is shown in Fig.3.
In every step of the above algorithm, the multi-stage branch exchange algorithm[l3] is employed. The multi-stage branch exchange is effective for escaping from a local minimum which single-stage branch exchange reaches. In this method, the second-stage branch exchange is employed as it is satisfactory from the tradeoff of the computational burden and the solution accuracy.
Remembering that the distribution system ordinarily is a radial system, the basic concept of the (single-stage) branch exchange can be stated as follows: from the initial radial configuration, a loop is constructed by adding one branch, and then the loop is brought back to a radial configuration by removing another branch from the loop. The second-stage branch exchange involves the following operations. After completing the single-stage branch exchange, when no further branch exchange can improve the objective function value, a branch exchange is forced to be executed and a new radial configuration is created. Of course, here, the objective function value becomes worse. Then, again, another branch exchange is executed from the new radial configuration according to the branch exchange criteria. The resulting radial system
~ step o _c_o_n_s_t_r_u_c_t_i_n_i_t-ial treeconTi-g~1rati01~]
Step Multi-stage branch exchange for eac h I fault case __J
Step 2
~tep 3
infeasible feasible
Reduce sum of constraint violations by single faci I ity -~'i . .,,.P_a_ns_i_o_n ___ ~--~
infeasible
Reduce su11 of constraint violations by uulti-faci lily expansion
infeasibl e feasihle
Step 4 Reduce sum of constraint violations hy
Step 5
candidate faci 1 i ti es feasible
Reduce i nsta 1.1 al ion cnsL by removing i nsla 11 ed unnecessary far: i Ii li es
END
Fig.3 Flowchart of the solution algorithm
is accepted if the objective function value . is better than that of the initial radial configuration. If this operation is executed successfully, then we can succeed in escaping from the local minimum. Of course, the higher stage may be executed in the same manner if necessary.
3.2 Detailed Explanation of the Algorithm Details of each step of the sol_ution
algorithm can be explained as follows.
Step O: Initial tree configuration Any initial tree configuratio~ _ma_Y be
selected by only using existing facilities or initially expanded ones . As this algorithm basically is an approximate solution metho~. a final solution depends on an initial solution . Therefore It must be noted that we have to apply thi's algorithm to several initial tree configurations, and have to select the best expansion pattern.
Step 1: Multi stage branch exchange for each fault case
The whole problem can be decomposed into sub-problems according to fault cases. The system configuration of each fault case is optimized independently by the multi-stage branch exchange method. Note that candid~tes for the multi-stage branch exchange are existing facilities and facilities ".'hich : are assumed to be installed up to this point. The second-stage branch exchange is employed as the multi-stage branch exchange. The general flowchart of the employed second-stage branch exchange is shown in Fig·.4. In Fig.4, the
133
Uo
llo
No
START
Execute SINGLE-STAGE a Igor i thm for finding tree-I
For• a loop by adding the tie branch vh ich shows best
criteria to tree-I
Open the loop by re110v i ng the
branch vh ich shovs best
criteria and tree-2
is obtained
Construct a loop by aclding the branch which shows best
criteria to lree-2
Open the loop by re•o• ing the branch vh i eh sho\IS best er i ter i a fro•
the loop and tree-3 is obtained .
The objective of tree-3 is better than that of tree-I?
llo Predeter11 i ned number of
candidates for •ak ing a loop fro• tree-2 is checked?
Yes
Predeter•ined number of
candidates for ;oak i ng
tree-2 is checked?
Yes
A 11 the candidate branches
for constructing a loop
fro• tree-I are tried?
. Yes EllO
~ "'
..., " n ., =r ~ "' I x "' n rt =r "' .. .. " "' .. "'
Yes
Fig.4 Second-stage branch exchange
t;erms "tree-1" fol lowing: · '
"tree-2" and "tree- 3" mean the the fault cases and no candidate branch found in Step 2, then Step 3 is executed.
is
tree-1: radial distribution system configuration before branch exchange,
tree-2: radial distribution system configuration after first-stage branch exchange,
tree-3: radial distribution system configuration after second-stage branch exchange.
The details of the multi-stage branch exchange can be shown in reference[l3].
If no constraint violation exists after the multi-stage branch exchange, the distribution system can be operated successfully in any fault case by using the existing facilities. In this case, after the sum of voltage margins is maximized, [Step l] terminates, and Step 5 is executed. If constraint violations still exist, Step 2 is proceeded with.
Step 2: Reduction of constraint violations by single facility expansion
It must be noted that, in this step, constraint violations still exist at least in one fault case. To decrease the sum of constraint violations in all the fault cases, a new facility is added to the existing system one by one. The criteria of the branch expansion are expressed as eq.(10)-eq.(12).
Let superscripts "tree• and tree configuration and loop respectively in the following.
"loop " denote configuration,
[Criteria for selecting one facility expansion]
(I) In the case of z1 loop=O
min.
where, T
Z tree_ ,.. z tree 1 -,<.u
t=l T
Z loop_ ,... z loop 1 -,<.u
t= l T
Ll Zo ]· = L Ll Zto ]. . t= l .
T
sum of constraint the existing tree
(12)
violations of configurations
sum of constraint violations after constructing a loop
sum of deviations of voltage margin after constructing a loop
LlZ1 j= ELlZu j: sum of ' t=l ' violations
deviations of constraint after constructing a loop
One branch is selected for installing according to criteria (I) (III). After assuming the selected branch to be installed, Step 1 is carried out in each fault case. After executing Step 1, if we succeed in eliminating or decreasing the sum of constraint violations, installation of the selected faci 1 i ty is decided upon ; otherwise, it is rejected. If we succeed in eliminating the constraint violations in all the fault cases, Step 5 is performed to decrease installation cost. Otherwise, the next candidate branch is selected according to criteria (I)-(III), and the same steps are repeated. If we fail to eliminate the constraint violations in some of
Step 3: Reduction of constraint violations by multiple facility expans i on
In this step, constraint violations still exist because they cannot be eliminated by the single facility expansion procedure in [Step 2]. Then, the following is tried.
Two branches, which are selected in turn according to criteria (I)- (I I I), are assumed to be simultaneously installed into the distribution system. By utilizing the two new facilities, multi-stage branch exchange (Step 1) is carried out for each fault case so as to eliminate the constraint violations. After this procedure, if the sum of constraint violations is eliminated or decreased , installation of the two facilities selected is decided upon; otherwise they are rejected. In case no constraint violations exist in any fault case, and the sum of voltage margins cannot be further improved upon, then, [Step 5] is carried out . Otherwise, the two
next best branches are selected, and this procedure is repeated. If the sum of constraint violations cannot be eliminated in this step, then [Step 4] is performed.
Step 4: Reduction of constraint violations by using all candidate facilities
Even here, at least one fault case exists in which the constraint violations still remain. In this step, it is assumed that all the facilities are installed into the distribution system so as to eliminate the remaining constraint violations. Under this assumption, the multi-stage branch exchange is independently carried out for the fault cases in which constraint violations still exist.
Since all the facilities are assumed to be installed, constraint violations may be eliminated in all the fault cases. Then, the facility expansion pattern for each fault case may be obtained. The final facility expansion pattern is composed of the logical sum of the facilities which are used in at least one fault case. If a feasible expansion pattern is found , [Step 5] is executed.
If constraint violations any case even at this stage, failed to find a feasible algorithm terminates here.
still remain in the algorithm has solution and the
Step 5: Reduction of the installation cost Up to here, a feasible expansion planning
in which al 1 fault cases are taken into account is obtained by installing several facilities in the preceding steps. However, we can reduce the installation cost by removing unnecessary facilities or by replacing the expensive facilities with cheaper ones, provided these operations do not cause any constraint violations.
If an installed facility that is not used in at least one fault case exists, then the multi-stage branch exchange is carried out to eliminate this facility. To execute the step, the multi-stage branch exchange is carried out for every fault case by temporarily setting the cost of the selected branch somewhat higher, and that of other newly installed facilities somewhat lower. Since a feasible solution has already been found, constraint violations must not be created in the branch exchange procedures.
After the branch exchange, if the result-
134
ing cost is lower than the previous one, then the new installation pattern is employed. This procedure is repeated until no candidat~ facility can be found.
The resulting expansion planning is the sub-optimal one which we intended to find.
4. NUMERICAL RESULTS
The proposed algorithm is tested on FACOMS3500 computer(4MIPS) by applying it to the 6.6 KV, 59 node, 69 branch distribution system shown in Fig. 5 (a). In this figure, solid lines show the initial tree configuration of the example system, and symbol "o" on the branch denotes installation candidate facilities. Other notations in this figure are the same as those in Fig . l. In Fig. 5 (a), solid lines with "a" are the facilities which are initially installed to construct the initial tree configuration. Initial installation cost of these 25 facilities is 1268.2[~:hypothetical money unit]. The topological confi_guration of the initial system is the same as that of reference[l4]. However, so as to demonstrate the effectiveness of the proposed method, section loads in selected ten nodes are somewhat increased to make the problem difficult to solve. The total load in the system is 1505.0[A] in this example, whereas 1375.0[A] in reference [14].
The calculation processes started from this initial tree configuration and the calculation results are shown in Table 1 for three test cases. In Case 1, four fault cases are pre-determined for this system . They are one non-fault case and three transformer fault cases: #5, #6 and #58. In Case 2, five fault cases are incorporated; one non-fault case and four transformer fault cases: #3, #4, #5 and #58. In Case 3, the non-fault case and every transformer fault, i.e. #3, #4, #5, #6 and #58, are assumed. The last line of Table 1 shows the calculation time for each case. In order to demonstrate the effectiveness of this method, the calculation results given by the single-stage branch exchange method[l4] are shown in Table 2.
By comparison of Table 1 and Table 2, we can easily find that fat Case 1 and 3, a feasible solution cannot be derived through the single-stage method(Table 2), whereas a feasible solution can be found using this method( Table 1) al though calculation burdens are several ten times larger than those of the other method.
The authors have independently applied the multi-stage branch exchange algorithm[l3] to all the single transformer fault cases (nonfault case is included and the condition is the same as Case 3) of the system shown in Fig . I. From the calculation results, by making the logical sum of tne installed faci 1 i ties for each fault case, the authors found that the total installation cost is 1972.6(~]. This result can be compared with the calculation result of Case 3. Then, we can al so eas i 1 y find that the resulting cost of this method (1724.5[~]) is 248.1[~] cheaper than that of the above installation cost (1972.6(~]). This advantage comes from the fact that the all fault cases are processed simultaneously in one lump in this method.
For each of the tree cases in Table l, the calculation processes can be explained ·step by step as follows. For every case, in Step O or for the initial tree configuration, the number of newly installed facilities is 25 with the initial cost of 1268.2[~], and the sum of constraint violation is 2088.0.
[Case l] In Step 1, by applying multi-stage branch
exchange to the initial system, constraint violation is reduced to 1618. 0. To eliminate this violation, 4 branches are added in Step 2. Although the installation cost has increased to 1497.1, the violation is reduced to 13. 9. No further reduction of the violation can be achieved by multi-stage branch exchange, and Step 3 is carried out. However, no improvement can be achieved in Step 3. In Step 4, 4 more branches are added, and the feasible solution can be found. The · installation cost here, 1895.5[il is reduced by removing 4 branches in Step 5, and the final feasible solution with the cost 1164.7 [~] is given.
Table 1 Numer i cal re sults of this algorithm
Case 1 Case 2 Case 3 Step E. F. c. v. Cost E. F. c. v. Cost E. F. c. v. Cost
0 25 2088. 0 1268 . 2 25 1760. 0 1268. 2 25 30 I 0. 0 1268. 2 I 25 1618 . 0 1268.2 25 812 . 0 1268 . 2 25 2062 . 0 1268. 2 2 29* 13. 9 14 79 . I 30* 0. 0 1556 . I 32* o. 0 1724.5 3 29 13 . 9 1479. 1 - - - - - -
4 3 3* o. a 1895. 5 - - - - - -5 29 o. 0 1164 . 7 29 o. 0 1536. 6 32 o. 0 1724. 5
CPU 25m - 55s 19m - 20s 40m - 18s Note: E.F . Total number of newly installed fac1l 1t1es ,
C. V. Sum of cons t raint viol a tions, CPU Co mputation t ime . "*" in E. F. column means that multi - stage branch exchange has effectively ~· orked in the step. •
Table 2 Numerical results of the me t hod in reference [ 14]
Case l Case 2 Case 3 Step E. F. C. V. Cost E. y. C. Y. Cost E. F. c. v. Cost
0 25 2088. 0 1268 . 2 25 1760 . 0 1268 . 2 25 30 I O. 0 1268 . 2 1 25 1618~ 0 1268 . 2 25 812 . 0 1268 . 2 25 2062. 0 1268 . 2 2 30 23 . 0 165 1. 8 31 o. 0 1764. 0 32 3. 0 1724. 6 3 30 23 . 0 1651. 8 - - - 32 3. 0 1724 . 6 4 31 23 . 0 1760 . 8 - - - 32 3. 0 1724. 6 5 31 ?/23/:D. 1760. 8 29 0. 0 1617. 0 32 :;:;rn:;: :o 1724 . 6
CPU OOm - 40s 03m - 23s OOm - 54s Note : Notations E. F., C. V. and CPU mean the same as those of Table 1.
135
(a) Initial configuration
Note Branches marked by "•" are the installed ones
(b) Calculation result by this algorithm
Note Branches marked by "•" are the installed ones
(c) Calculation result by reference[l4]
Fig.S System configurations of example systems
136
[Case 2] In Step 1, the · constraint violation is
reduced to 812.0, and it is eliminated by adding 5 branches in Step 2. Since the feasible solution is found in Step 2, Step 5 is proceeded to without processing Steps 3 and 4. In Step 5, one branch is deleted from the system, and the final cost is reduced to 1536.6[~]. This cost can be compared with the cost 1617. 0 [~] of Case 2 in Table 2, since the feasible solution is found in this case. The final topological system configurations of these two cases are shown in Fig. 5 ( b) and (c). From these figures, it can be seen that the cost difference of these two cases mainly comes from the fact that unnecessary transformer #4 is inevitably installed through the method proposed in reference [14].
[Case 3] All the constraint violations are elimi
nated in Step 2 by installing 7 branches. Installation cost is 1724.5[~] which cannot be reduced even in Step 5 in this case.
In Case 3, computation time is twice as large as that of Case 2. This is because much computation burden is necessary in the multistage branch exchange procedures for eliminating the constraint violations in the fault case of transformer #6. In Table 1, t~e typical numerical results in which the multi-stage branch exchange is effective for finding the feasible solution are shown. It must be noted that we cannot necessarily find a better solution by the multi-stage branch exchange than that by single-stage branch exchange in most of the cases. In such a case, of course, the calculation result is the same as that through single-stage branch exchange although more calculation time is necessary for the multi-stage branch exchange processes.
5. CONCLUSIONS
In this paper, an expansion planning algorithm for distribution systems in which multiple fault cases are taken into account is proposed. The solution algorithm is developed by applying the decomposition-coordination method and the multi-stage branch exchange method. Through the multi-stage branch exchange method, the accuracy of the calculation results is fairly improved. From the numerical example,
it can be found that the result of the proposed method is far better than that of the existing methods. Our task for the future will be to expand this algorithm to include multiyear expansion planning.
REFERENCES
(l] T.Gonen et al. : "Bibliography of Power Distribution System Planning•, IEEE Trans . PAS, Vol.PAS-102, No.6, June (1983)
[2] H.L.Willis and J.E.D.Northcote-Green : "Comparison of Several Computerized Distribution Planning Methods", IEEE Trans.PAS, Vol.PAS-104, No.l, Jan. (1985)
[3]
[4]
[5]
T.Gonen and B.L.Foote : "Distribution-System Planning Using Mixed-Integer Programming", IEE Proc., Vol.128, Part C, No.2, March (1981) D.I.San, D.R.Farris, P.J.Cote, R.R.Shoults and M.S.Chen : "Optimal Distribution Substation and
Net-101,
Primary Feeder Planning via the Fixed Charge work Formulation" : IEEE Trans.PAS, Vol.PASNo . 3, March (1982) D.W.Ross, M.Carson and Advanced Methods for Distribution Systems•, 1845, Feb. (1980)
A.I.Cohen : "Development of Planning Electric Energy
U.S.DOE Report, ET-78-C-03-
[6] M.A.El-Kady : "Computer-aided Planning of Distribution Substation and Primary Feeders", IEEE Trans.PAS, Vol.PAS-103, No.6, June (1984)
(7] O.M.Mikic : "Mathematical Dynamic Model for Long-term Distribution System Planning•, IEEE Trans.PWRS, Vol.PWRS-1, No.l, Feb. (1986)
[8] J . Partanen : "Dynamic Programming Algorithm for Sizing, Locating and Timing of Feeder Reinforcement•, IEEE Trans.PWRD, Vol.5, No.l (1990)
[9] K.Aoki, K.Nara et al. : "New Approximate Optimization Method for Distribution System Planning•, IEEE Trans.PWRS, Vol.5, No.l (1990)
[lO]C.W.Hassefield et al.: "An Automated Method for Least Cost Distribution Planning•, IEEE Trans.PWRD, Vol.5; No.2 (1990)
[ll]K.Nara, et al.: "Fast Approximate Solution Algorithm for Distribution Systems Planning", Trans. IEEJ, Vol.110-B, No.l, Nov. (1990)
[12]K.Nara, et al.: "Multi-year Expansion Planning for Distribution Systems• IEEE Trans.PWRS, Vol.6, No.3 (1991)
(13]K.Nara et al.: "Distribution Systems Expansion Planning by Multi-stage Branch Exchange". IEEE Trans.PWRS, Vol.7, No.l (1992)
[14]K.Nara et al.: "Algorittun for Expansion Planning in Distribution Systems Taking Fault into Consideration", Accepted to 1993 IEEE PES Winter Meeting
137