15
Distribution Automation Plans in AEP Texas

Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Embed Size (px)

Citation preview

Page 1: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Distribution Automation Plans in AEP Texas

Page 2: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Overview

AEP Texas is deploying smart meters to roughly 1,000,000 customers

The meters utilize Landis + Gyr UtiliNet radio technology

UtiliNet mesh network requires regular placement of routers on utility poles throughout the system

Routers can be used for more than strictly AMI traffic If they’re there, why not use them?

Very limited in scale and scope so far

Page 3: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Deployment

Total of twelve smart switches deployed so far Installed in sets of three Locations: Two sets in San Angelo, one set in Abilene,

and one set in Corpus Up to ten additional locations (30 additional smart

switches) may be chosen before the end of 2011. They will most likely be deployed in the Rio Grande Valley, Corpus Christi, Laredo, Victoria, Abilene, and/or San Angelo.

Page 4: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Organizational Responsibilities

Reliability Engineering: Selects location, performs studies as necessary, program the devices

AMI construction group: Installs routers for AMI deployment

Information Technology: Creates the links between the UtiliNet system and SCADA

Dispatch: Operates and monitors the status of the devices

Page 5: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Switch Specification

Using S&C IntelliRupter 15.5kV models to support our mostly 7.2/12.47kV

system Interrupting rating: 12500A Continuous current rating: 630A Uses “pulse closing” technique

Standard reclosing could be used for fuse saving strategies, but we’ve opted not to use it

Ensures less damage to distribution equipment by limiting the amount of energy in a fault

Page 6: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Switch Specification (cont’d)

Modular communications Vendor installs Landis + Gyr UtiliNet module SpeedNet and other radios available and possible for

future use Communications infrastructure

UtiliNet mesh network Very scalable, but not very high bandwidth DA takes much higher priority in signals than AMI Proprietary UtiliNet signals converted at station to

DNP3 for SCADA master control device Latency is expected to be measured in seconds as

opposed to milliseconds or minutes

Page 7: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Mounting/Installation

Switches are mounted on 45 ft, Class 3 or better poles

Only overhead installations on wood poles so far

No location restrictions beyond engineering judgment Everybody knows of the story of the switch right

next to a drainage ditch… AMI routers must generally be installed in an

area before DA schemes are installed

Page 8: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Maintenance

S&C IntelliRupters have a life span of about 30 years or more

Batteries should be replaced on a 5 year cycle

Bypass switches are installed on both load and source side

Thus far, testing is performed live Modular communications and control module

Control module can be accessed via Wi-Fi for programming and to check error logs

Page 9: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

AMI Integration

Leaning heavily on AMI communications system Communications to the substation shares routers

and protocols with AMI system DA gets top priority in communications along mesh At the station, switch signals are translated to DNP3

and sent to the SCADA master control device Switches do not communicate directly with meters

UtiliNet mesh latency would be too high for something like this to work

Page 10: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Safety

For loop-automation, the “middle” device must be placed into non-reclose mode before work begins A non-reclose order or hot line tag may be used

on the source side device as well The S&C IntelliRupter has an interlocking

visual open To accommodate contractors/out-of-town

crews, dispatchers will let crews know they are on an automated system when they logon

Page 11: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Operations

Real-time visual representations of the status of the devices (open/closed/non-reclose/etc) are provided via SCADA Also allows remote control of functions – can be

overridden by field using physical levers Non-switch smart nodes (such as intelligent

volt-var controls) are not anticipated at this time

Page 12: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Operations (cont’d)

Alarm points are used on abnormal switch state Outage tickets are still manually generated by

dispatchers Switches can be used to gather outage

information, isolate faults, and re-energize the line – similar to breakers using SCADA

Due to the limited scope of deployment, switches will only be marginally useful in load estimation and planning functions

Page 13: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Budgeting/Cost Recovery

Costs of systems is broadly imbedded in rates until a more timely recovery mechanism is in place

Limited scope of projects means no special projects have been created; they are lumped in with general sectionalizing and reliability budgets

AMI communication devices (routers) are paid for by smart meter surcharge, and AMI remains their primary function DA is along for the ride!

Page 14: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

One Caveat

Some of the equipment may not stand up to highly corrosive environments…. Installation was on North

Padre Island, only a few months old

ALL future installations will use our own external disconnects

Page 15: Distribution Automation Plans in AEP Texas. Overview AEP Texas is deploying smart meters to roughly 1,000,000 customers The meters utilize Landis + Gyr

Questions?