Dis Aggregation

Embed Size (px)

Citation preview

  • 8/13/2019 Dis Aggregation

    1/20

    Disaggregation

    Working with aggregate units facilitates intermediate planning.

    But to put this plan into action we should translate it,

    decompose it, disaggregate itand state it in terms of actual units

    of products and for a shorter period

    Aggregate planning was for12or more months.Now we should break it down into shorter periods, say 2-3 months.

    Disaggregation:

    Breaking down the aggregate plan into specific products - fromaggregate product to real specific products - based on the

    specific products, then calculating detail of manpower,

    material and inventory requirements.

  • 8/13/2019 Dis Aggregation

    2/20

    Disaggregation

    Aggregate Plan

    Month Jan Feb MarLawn Mower 200 300 400

    Master Schedule

    Push 100 100 100Self-propelled 75 150 200

    Riding 25 50 100

    Total 200 300 400Total of aggregate and

    disaggregate products are not

    necessarily equal

  • 8/13/2019 Dis Aggregation

    3/20

    Master Schedule

    The result of disaggregationis a master schedule.

    The Master Schedule shows quantity and timingof specific products.

    It usually covers 6 to 12 weeks.

    After preparing a tentative Master Schedule, a planner can do Rough-cut

    Capacity Planning.

    Rough-cut capacity planningis to check the feasibility of the Master

    Schedule with respect to available manpowerand machinerycapacities,

    storagespaces, and vendorcapabilities.

    It is just a rough check to ensure that the master schedule is achievable.

    The master schedule then is used as the basis for short term planning.

  • 8/13/2019 Dis Aggregation

    4/20

    Master Schedule

    Aggregate plan: 12 months.

    Master schedule: 12 weeks.

    Master schedule is updated every 2 weeks.

    Therefore, it is on a rolling basis, always we

    have a disaggregated plan for the next 12weeks.

  • 8/13/2019 Dis Aggregation

    5/20

    Master Production Schedule (MPS)

    Master schedulestates quantityand delivery timeof

    specific products.

    It says we need 75 push lawnmowers in January. But it does

    not say how we get it - from production,or from inventory.

    MasterProductionSchedule(MPS)is developed

    based on Master Schedule.

    MPS: Quantity and timing of planned production.

    MPS determines the Promised Inventory, and the

    Production Requirements availableto promise inventoryfor

    each period.

  • 8/13/2019 Dis Aggregation

    6/20

    Master

    scheduling

    Beginning inventory

    Forecast

    Customer orders

    Inputs Outputs

    Projected inventory

    Master production schedule

    Uncommitted inventory

    (Available to Promise)

    Master Scheduling Process

    The key idea is: we have a forecast, but it turns into and actualorder when we receive a customer order.

    MPS starts with a preliminary calculation of projected inventory.

    This reveals when we need production to get additional inventory.

  • 8/13/2019 Dis Aggregation

    7/20

    64 1 2 3 4 5 6 7 8

    Forecast 30 30 30 30 40 40 40 40

    Customer Orders

    (committed) 33 20 10 4 2

    Projected on-hand

    inventory 31 1 -29

    JUNE JULY

    Beginning

    Inventory

    Customer orders are

    larger than forecast in

    week 1

    Forecast is larger than

    Customer orders in week 2

    Forecast is larger than

    Customer orders in week 3

    Example; Projected on-hand Inventory

  • 8/13/2019 Dis Aggregation

    8/20

  • 8/13/2019 Dis Aggregation

    9/20

  • 8/13/2019 Dis Aggregation

    10/20

    Example; Projected on-hand Inventory

    64 June July

    1 2 3 4 5 6 7 8

    Forecast 30 30 30 30 40 40 40 40

    Customer Orders

    (committed)33 20 10 4 2

    Projected onhand inventory

    31 1 41 11 41 1 31 61

    MPS 70 70 70 70

  • 8/13/2019 Dis Aggregation

    11/20

    Available To Promise (ATP)

    Now we can determine available to promiseat each period.

    We use a look ahead procedure.

    Sum booked customer orders week by week up to (not including)

    the next week of production. This is booked orders.

    The remaining inventory is ATP.

    ATP is only calculated for the first week and for weeks in which

    there is a MPS quantity. (In this example: weeks 1, 3, 5, 7, 8)

    64 June July

    1 2 3 4 5 6 7 8

    Forecast 30 30 30 30 40 40 40 40

    Customer Orders (committed) 33 20 10 4 2

    Projected on hand inventory 31 1 41 11 41 1 31 61

    MPS 70 70 70 70

  • 8/13/2019 Dis Aggregation

    12/20

    Available To Promise (ATP); First week

    Available to promise in week 1 = Inventory in week 0 + Production

    in week 1 - Customer Orders at week 1 - Customer Orders at week 2

    ATP(1) = I(0)+ P(1) - CO(1) - CO(2)ATP(1) = 64+0 -33 -20= 11

    This is an uncommitted inventory.

    It can be assigned to week 1, week 2, or both.

    64 June July

    1 2 3 4 5 6 7 8

    Forecast 30 30 30 30 40 40 40 40

    Customer Orders (committed) 33 20 10 4 2

    Projected on hand inventory 31 1 41 11 41 1 31 61

    MPS 70 70 70 70

    ATP 11 56 68 70 70

  • 8/13/2019 Dis Aggregation

    13/20

    Available To Promise (ATP); Other weeks

    For other weeks, beginning inventory is removed from the formula:

    ATP(3) = P(3)-CO(3)-CO(4)

    ATP(3)= 70-10-4= 56

    64 June July

    1 2 3 4 5 6 7 8

    Forecast 30 30 30 30 40 40 40 40

    Customer Orders (committed) 33 20 10 4 2

    Projected on hand inventory 31 1 41 11 41 1 31 61MPS 70 70 70 70

    ATP 11 56 68 70 70

    64 June July1 2 3 4 5 6 7 8

    Forecast 30 30 30 30 40 40 40 40

    Customer Orders (committed) 33 20 10 4 2

    Projected on hand inventory 31 1 41 11 41 1 31 61

    MPS 70 70 70 70

    ATP 11 56 68 70 70

    For weeks 7 and 8, no CO, therefore ATP = MPS

  • 8/13/2019 Dis Aggregation

    14/20

    Updating ATP

    As additional orders are booked, they would be entered into the

    schedule.

    ATP would be updated to reflect new booked orders.

    Marketing can use updated ATP amounts to provide realistic

    delivery dates to customers

  • 8/13/2019 Dis Aggregation

    15/20

    Updating MPS

    Changing to a master production schedule can be disruptive.

    Particularly changes in the immediate periods of the schedule

    Aggregate Plan is developed for say 1 year

    Master Production Schedule is developed for a period of say 12

    weeks.

    MPS is updated say every 2 weeks, it is on a rolling basis.

    Frozen Firm Full Open

    1 2 3 4 5 6 7 8 9 10 11 12

  • 8/13/2019 Dis Aggregation

    16/20

    Problem 1. Book Page 627.

    Forecast of demand for the next four months is 70 units permonth

    Committed customer orders for the next four months are 80,50, 30, and 10, respectively. Order size is 100 units.Beginning inventory is 0.

    Prepare MPS

    Prepare ATP

    Assignment

  • 8/13/2019 Dis Aggregation

    17/20

  • 8/13/2019 Dis Aggregation

    18/20

    Solution to Problem 1

    1 2 3 4Forecast 70 70 70 70

    Customer Orders 80 50 30 10

    Inventory on hand 20

    MPS 100

    ATP

    Month

    1 2 3 4

    Forecast 70 70 70 70

    Customer Orders 80 50 30 10

    Inventory on hand 20 50MPS 100 100

    ATP

    Month

  • 8/13/2019 Dis Aggregation

    19/20

    Solution to Problem 1

    1 2 3 4

    Forecast 70 70 70 70

    Customer Orders 80 50 30 10

    Inventory on hand 20 50 80

    MPS 100 100 100

    ATP

    Month

    1 2 3 4

    Forecast 70 70 70 70

    Customer Orders 80 50 30 10Inventory on hand 20 50 80 10

    MPS 100 100 100

    ATP

    Month

  • 8/13/2019 Dis Aggregation

    20/20

    Solution to Problem 1

    1 2 3 4

    Forecast 70 70 70 70Customer Orders 80 50 30 10

    Inventory on hand 20 50 80 10

    MPS 100 100 100ATP 20

    Month

    1 2 3 4

    Forecast 70 70 70 70

    Customer Orders 80 50 30 10

    Inventory on hand 20 50 80 10

    MPS 100 100 100

    ATP 20 50

    Month

    1 2 3 4

    Forecast 70 70 70 70

    Customer Orders 80 50 30 10

    Inventory on hand 20 50 80 10

    MPS 100 100 100ATP 20 50 60

    Month