Difficult Run Stream Valley Community Meeting
April 1 2019 Navy Elementary School
Paul Shirey Manager Project Management Branch
AGENDA - FCPA Staff Presentation
bull Overview of Concept Design
bull Concept Design Process Schedule bull Bridge Design
bull Permit Requirements
bull Land Rights Requirements
bull Cost Estimate and Funding
bull Project Schedule
bull Next Steps
Bridge Recommendations Prefabricated Steel Truss Bridge with Wood Deck
70 foot long span
10 foot wide
Easement limits delineated 2600 SF ndash Permanent Trail Easement area
3800 SF - Temporary Construction Easement area
FCPA Requirements Archeological StudyInvestigation of Site
Tree Inventory Preservation Plan and Mitigation
Invasive Species Mitigation
County Permitting Requirements Minor Site Plan (MSP) ndash Land Disturbance Permit
Floodplain Use Determination Request
Resource Protection Area Exemption Request (CBAY Waiver)
Allowed use in a Major Floodplain Waiver
Building Permit under Special Inspections Program
State and Federal Permitting Requirements (Joint Permit Application)
Virginia Marine Resources Commission (VMRC)
Army Corps Wetland Preliminary Jurisdictional Determination (JD)
Army Corps Nationwide Permits (NWP) for Recreational Facilities
Total Project Estimate (from here forward)
Design and testing $91400
Permits $12000
Construction $243800
Administration $35700
Mitigation $11300
Total $394200
Available Funding
$100000 from Sully District Sidewalk Fund
$308000 from Developer Proffers in Sully District
Study Results LEASE AAEJI
HUNTE~gt VALLEY ASSOCIATIOI I PEP CED BOOK 96J4 PAGE 1520_____
I
=Ro=osrn ITMPORARV _ CO~TRUCTICN EASEtErH -
N F PEDRY MARK L amp LAURIE Z FAIRHUlT ESrATES
101 6 ED ECC~ Y I(pound Dbull
rmiddotrorcsrn runt I~ -rAll AN~
BR )G[ lt1AINTENACEshyEASEMENT
FAIRFAX COUNTY PARK AUTHORITY
- shy APAOnAli L IJIFS OIF ll~Qllt f lffl)
DOSTHC poundlaquo(
CQ)TNt _-COUClaquot (nAV[L TVL
PRltJIOSfn FM~WlARY COllSIRUCllON USpound)poundH (t7tli5ri
fmiddotmiddot middot middot ~~~~I ~~~~~~)
LO
FAIRFAX COUNTY BOARD OF
SUPERVISORS
NOTES ~flo~~lf~ t-tVO W WCAIUI 1AltUtl lI M-lgt3Mtlll - 11 ~I 4)
~~gtl bull gt JJ~U-lllCoI bullJ AllC lltO- ltC (K1 rtait I~) -- nc- --~ eounmiddot ac
~r~~~~~=lH _ l(N tj W U 1ar1w~ usmgt vu w AI mn Wlt IAMl lfbull~
r __ oJllH nJJlllbull l~i ~TCDlUt Pntlo~ sunu1r-ubulla cNJCl -_ n bullJQOUgt 1Ktl19deg -ltgtOC i--mFri _ ~1--4n71
IMRpoundL POlllA1CPpoundL~ ftlle3otY VVlll L llUlgt~1lel_ lol~~ ll~ _L~--L~
~~~1 Pfitgt-M13AUa81Wlml01WSfuacln gtClgt
~middot-- U- 017 U-
l~~tl~~ ~gtmiddotbull~
l()lIMDJn IND IOllTi WCWI ~10llT(N X1H~middotraquo1$ lS(I) Oii CO$TIKI Lcl 11~ a OJHliif OHY WOtlM bull ~tUl~ ~1-bull~all11111l)llMl~~ll)
-1 i~g roooltlllTC _ ~MUii -~ ~ (-IC )1-~t -0 KQ TCIDlr - a lNHUlL cti1laquo1 ~ncDlJ A C ZC bulll U V0 LlAI Nl-Cgt At_ Ct lllNA lX _( OUU MoP ~c~ rbull RFbull) CDJTX ~R11u C)MlVlN-PI OllJWAll ~m)(lhl)F ) Sl~~1 middot1 i-gt1~ I I
Vl llllLJll lMIAgtCJllllUNNlllraquoU Yl1lt -111ulM b bull~11middot1111 ~0lM tJAltUI ltlt+r-1ltNH I -middotmiddot
Study Results LEASE AR[A tHUHTERS VAl1EY ASSOClltllCN
- PC~ DCCgt COQC 9GJ4 PAC 1C20---
IDU I shy-- ( OB SP92 [
~
J7o Pldeg_~sJgt - _jr_
----___ ----- degNe SJgt middot middot __ ------shy-_ 1 IC2
---___ I v I 0
lt D Pu8UC TRAIL E 11 shy
CbullB 9792 ~G 400 y ~
O EX INRESS-ECRESS E UT B 9871 P S~J l f I
(fa L- (
jj l - LIMITS CF CLEARINGPOP ~MP
C()fl~TllllCTIO )ff I AID GRADING c EASE~ENT ) PFbPgtSEO BRIDGE
pr bull bulln I
PIN 0371-23-0005 ( I I ~ 0371-01-0033N 1 PEDRY MARK L amp LAURIE Z I - FAIRFAX COUNTYFAIRHUNl ESTATES PARK AUTHORITYLOT 5
~111 ~ ilb 1-AIA legtb1ccco OOOK 953bull rAc 1s2c )
I
I I
I Pl 0371-03-0007
FAIRFAX COUNTY PARK AUTHORITY
OCO OOOK 275$ fAGC 125
Existing Ground Elevation=2535
Edge of 100-Year Flood=STA 0+70 Edge of 100-Year Flood=STA 7+30
100-Year Flood Depth=Approx 5 ft over the Existing Top of Bank Existing Crossing Location
100-Year Flood Width-Approx 660 Ft wide Existing Crossing Location
Or IPE
Bridge Inundation - Video
Holmes Run Accotink Creek
Accotink Creek Pohick Creek
Topographic Survey ndash Complete
Draft Schematic Plan ndash Complete
Final Schematic Plan ndash Complete
Concept Study - Complete
Final Design ndash April ndash June 2019
Permitting ndash July ndash December 2019
Bidding amp Construction ndash January -July 2020
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
AGENDA - FCPA Staff Presentation
bull Overview of Concept Design
bull Concept Design Process Schedule bull Bridge Design
bull Permit Requirements
bull Land Rights Requirements
bull Cost Estimate and Funding
bull Project Schedule
bull Next Steps
Bridge Recommendations Prefabricated Steel Truss Bridge with Wood Deck
70 foot long span
10 foot wide
Easement limits delineated 2600 SF ndash Permanent Trail Easement area
3800 SF - Temporary Construction Easement area
FCPA Requirements Archeological StudyInvestigation of Site
Tree Inventory Preservation Plan and Mitigation
Invasive Species Mitigation
County Permitting Requirements Minor Site Plan (MSP) ndash Land Disturbance Permit
Floodplain Use Determination Request
Resource Protection Area Exemption Request (CBAY Waiver)
Allowed use in a Major Floodplain Waiver
Building Permit under Special Inspections Program
State and Federal Permitting Requirements (Joint Permit Application)
Virginia Marine Resources Commission (VMRC)
Army Corps Wetland Preliminary Jurisdictional Determination (JD)
Army Corps Nationwide Permits (NWP) for Recreational Facilities
Total Project Estimate (from here forward)
Design and testing $91400
Permits $12000
Construction $243800
Administration $35700
Mitigation $11300
Total $394200
Available Funding
$100000 from Sully District Sidewalk Fund
$308000 from Developer Proffers in Sully District
Study Results LEASE AAEJI
HUNTE~gt VALLEY ASSOCIATIOI I PEP CED BOOK 96J4 PAGE 1520_____
I
=Ro=osrn ITMPORARV _ CO~TRUCTICN EASEtErH -
N F PEDRY MARK L amp LAURIE Z FAIRHUlT ESrATES
101 6 ED ECC~ Y I(pound Dbull
rmiddotrorcsrn runt I~ -rAll AN~
BR )G[ lt1AINTENACEshyEASEMENT
FAIRFAX COUNTY PARK AUTHORITY
- shy APAOnAli L IJIFS OIF ll~Qllt f lffl)
DOSTHC poundlaquo(
CQ)TNt _-COUClaquot (nAV[L TVL
PRltJIOSfn FM~WlARY COllSIRUCllON USpound)poundH (t7tli5ri
fmiddotmiddot middot middot ~~~~I ~~~~~~)
LO
FAIRFAX COUNTY BOARD OF
SUPERVISORS
NOTES ~flo~~lf~ t-tVO W WCAIUI 1AltUtl lI M-lgt3Mtlll - 11 ~I 4)
~~gtl bull gt JJ~U-lllCoI bullJ AllC lltO- ltC (K1 rtait I~) -- nc- --~ eounmiddot ac
~r~~~~~=lH _ l(N tj W U 1ar1w~ usmgt vu w AI mn Wlt IAMl lfbull~
r __ oJllH nJJlllbull l~i ~TCDlUt Pntlo~ sunu1r-ubulla cNJCl -_ n bullJQOUgt 1Ktl19deg -ltgtOC i--mFri _ ~1--4n71
IMRpoundL POlllA1CPpoundL~ ftlle3otY VVlll L llUlgt~1lel_ lol~~ ll~ _L~--L~
~~~1 Pfitgt-M13AUa81Wlml01WSfuacln gtClgt
~middot-- U- 017 U-
l~~tl~~ ~gtmiddotbull~
l()lIMDJn IND IOllTi WCWI ~10llT(N X1H~middotraquo1$ lS(I) Oii CO$TIKI Lcl 11~ a OJHliif OHY WOtlM bull ~tUl~ ~1-bull~all11111l)llMl~~ll)
-1 i~g roooltlllTC _ ~MUii -~ ~ (-IC )1-~t -0 KQ TCIDlr - a lNHUlL cti1laquo1 ~ncDlJ A C ZC bulll U V0 LlAI Nl-Cgt At_ Ct lllNA lX _( OUU MoP ~c~ rbull RFbull) CDJTX ~R11u C)MlVlN-PI OllJWAll ~m)(lhl)F ) Sl~~1 middot1 i-gt1~ I I
Vl llllLJll lMIAgtCJllllUNNlllraquoU Yl1lt -111ulM b bull~11middot1111 ~0lM tJAltUI ltlt+r-1ltNH I -middotmiddot
Study Results LEASE AR[A tHUHTERS VAl1EY ASSOClltllCN
- PC~ DCCgt COQC 9GJ4 PAC 1C20---
IDU I shy-- ( OB SP92 [
~
J7o Pldeg_~sJgt - _jr_
----___ ----- degNe SJgt middot middot __ ------shy-_ 1 IC2
---___ I v I 0
lt D Pu8UC TRAIL E 11 shy
CbullB 9792 ~G 400 y ~
O EX INRESS-ECRESS E UT B 9871 P S~J l f I
(fa L- (
jj l - LIMITS CF CLEARINGPOP ~MP
C()fl~TllllCTIO )ff I AID GRADING c EASE~ENT ) PFbPgtSEO BRIDGE
pr bull bulln I
PIN 0371-23-0005 ( I I ~ 0371-01-0033N 1 PEDRY MARK L amp LAURIE Z I - FAIRFAX COUNTYFAIRHUNl ESTATES PARK AUTHORITYLOT 5
~111 ~ ilb 1-AIA legtb1ccco OOOK 953bull rAc 1s2c )
I
I I
I Pl 0371-03-0007
FAIRFAX COUNTY PARK AUTHORITY
OCO OOOK 275$ fAGC 125
Existing Ground Elevation=2535
Edge of 100-Year Flood=STA 0+70 Edge of 100-Year Flood=STA 7+30
100-Year Flood Depth=Approx 5 ft over the Existing Top of Bank Existing Crossing Location
100-Year Flood Width-Approx 660 Ft wide Existing Crossing Location
Or IPE
Bridge Inundation - Video
Holmes Run Accotink Creek
Accotink Creek Pohick Creek
Topographic Survey ndash Complete
Draft Schematic Plan ndash Complete
Final Schematic Plan ndash Complete
Concept Study - Complete
Final Design ndash April ndash June 2019
Permitting ndash July ndash December 2019
Bidding amp Construction ndash January -July 2020
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
Bridge Recommendations Prefabricated Steel Truss Bridge with Wood Deck
70 foot long span
10 foot wide
Easement limits delineated 2600 SF ndash Permanent Trail Easement area
3800 SF - Temporary Construction Easement area
FCPA Requirements Archeological StudyInvestigation of Site
Tree Inventory Preservation Plan and Mitigation
Invasive Species Mitigation
County Permitting Requirements Minor Site Plan (MSP) ndash Land Disturbance Permit
Floodplain Use Determination Request
Resource Protection Area Exemption Request (CBAY Waiver)
Allowed use in a Major Floodplain Waiver
Building Permit under Special Inspections Program
State and Federal Permitting Requirements (Joint Permit Application)
Virginia Marine Resources Commission (VMRC)
Army Corps Wetland Preliminary Jurisdictional Determination (JD)
Army Corps Nationwide Permits (NWP) for Recreational Facilities
Total Project Estimate (from here forward)
Design and testing $91400
Permits $12000
Construction $243800
Administration $35700
Mitigation $11300
Total $394200
Available Funding
$100000 from Sully District Sidewalk Fund
$308000 from Developer Proffers in Sully District
Study Results LEASE AAEJI
HUNTE~gt VALLEY ASSOCIATIOI I PEP CED BOOK 96J4 PAGE 1520_____
I
=Ro=osrn ITMPORARV _ CO~TRUCTICN EASEtErH -
N F PEDRY MARK L amp LAURIE Z FAIRHUlT ESrATES
101 6 ED ECC~ Y I(pound Dbull
rmiddotrorcsrn runt I~ -rAll AN~
BR )G[ lt1AINTENACEshyEASEMENT
FAIRFAX COUNTY PARK AUTHORITY
- shy APAOnAli L IJIFS OIF ll~Qllt f lffl)
DOSTHC poundlaquo(
CQ)TNt _-COUClaquot (nAV[L TVL
PRltJIOSfn FM~WlARY COllSIRUCllON USpound)poundH (t7tli5ri
fmiddotmiddot middot middot ~~~~I ~~~~~~)
LO
FAIRFAX COUNTY BOARD OF
SUPERVISORS
NOTES ~flo~~lf~ t-tVO W WCAIUI 1AltUtl lI M-lgt3Mtlll - 11 ~I 4)
~~gtl bull gt JJ~U-lllCoI bullJ AllC lltO- ltC (K1 rtait I~) -- nc- --~ eounmiddot ac
~r~~~~~=lH _ l(N tj W U 1ar1w~ usmgt vu w AI mn Wlt IAMl lfbull~
r __ oJllH nJJlllbull l~i ~TCDlUt Pntlo~ sunu1r-ubulla cNJCl -_ n bullJQOUgt 1Ktl19deg -ltgtOC i--mFri _ ~1--4n71
IMRpoundL POlllA1CPpoundL~ ftlle3otY VVlll L llUlgt~1lel_ lol~~ ll~ _L~--L~
~~~1 Pfitgt-M13AUa81Wlml01WSfuacln gtClgt
~middot-- U- 017 U-
l~~tl~~ ~gtmiddotbull~
l()lIMDJn IND IOllTi WCWI ~10llT(N X1H~middotraquo1$ lS(I) Oii CO$TIKI Lcl 11~ a OJHliif OHY WOtlM bull ~tUl~ ~1-bull~all11111l)llMl~~ll)
-1 i~g roooltlllTC _ ~MUii -~ ~ (-IC )1-~t -0 KQ TCIDlr - a lNHUlL cti1laquo1 ~ncDlJ A C ZC bulll U V0 LlAI Nl-Cgt At_ Ct lllNA lX _( OUU MoP ~c~ rbull RFbull) CDJTX ~R11u C)MlVlN-PI OllJWAll ~m)(lhl)F ) Sl~~1 middot1 i-gt1~ I I
Vl llllLJll lMIAgtCJllllUNNlllraquoU Yl1lt -111ulM b bull~11middot1111 ~0lM tJAltUI ltlt+r-1ltNH I -middotmiddot
Study Results LEASE AR[A tHUHTERS VAl1EY ASSOClltllCN
- PC~ DCCgt COQC 9GJ4 PAC 1C20---
IDU I shy-- ( OB SP92 [
~
J7o Pldeg_~sJgt - _jr_
----___ ----- degNe SJgt middot middot __ ------shy-_ 1 IC2
---___ I v I 0
lt D Pu8UC TRAIL E 11 shy
CbullB 9792 ~G 400 y ~
O EX INRESS-ECRESS E UT B 9871 P S~J l f I
(fa L- (
jj l - LIMITS CF CLEARINGPOP ~MP
C()fl~TllllCTIO )ff I AID GRADING c EASE~ENT ) PFbPgtSEO BRIDGE
pr bull bulln I
PIN 0371-23-0005 ( I I ~ 0371-01-0033N 1 PEDRY MARK L amp LAURIE Z I - FAIRFAX COUNTYFAIRHUNl ESTATES PARK AUTHORITYLOT 5
~111 ~ ilb 1-AIA legtb1ccco OOOK 953bull rAc 1s2c )
I
I I
I Pl 0371-03-0007
FAIRFAX COUNTY PARK AUTHORITY
OCO OOOK 275$ fAGC 125
Existing Ground Elevation=2535
Edge of 100-Year Flood=STA 0+70 Edge of 100-Year Flood=STA 7+30
100-Year Flood Depth=Approx 5 ft over the Existing Top of Bank Existing Crossing Location
100-Year Flood Width-Approx 660 Ft wide Existing Crossing Location
Or IPE
Bridge Inundation - Video
Holmes Run Accotink Creek
Accotink Creek Pohick Creek
Topographic Survey ndash Complete
Draft Schematic Plan ndash Complete
Final Schematic Plan ndash Complete
Concept Study - Complete
Final Design ndash April ndash June 2019
Permitting ndash July ndash December 2019
Bidding amp Construction ndash January -July 2020
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
FCPA Requirements Archeological StudyInvestigation of Site
Tree Inventory Preservation Plan and Mitigation
Invasive Species Mitigation
County Permitting Requirements Minor Site Plan (MSP) ndash Land Disturbance Permit
Floodplain Use Determination Request
Resource Protection Area Exemption Request (CBAY Waiver)
Allowed use in a Major Floodplain Waiver
Building Permit under Special Inspections Program
State and Federal Permitting Requirements (Joint Permit Application)
Virginia Marine Resources Commission (VMRC)
Army Corps Wetland Preliminary Jurisdictional Determination (JD)
Army Corps Nationwide Permits (NWP) for Recreational Facilities
Total Project Estimate (from here forward)
Design and testing $91400
Permits $12000
Construction $243800
Administration $35700
Mitigation $11300
Total $394200
Available Funding
$100000 from Sully District Sidewalk Fund
$308000 from Developer Proffers in Sully District
Study Results LEASE AAEJI
HUNTE~gt VALLEY ASSOCIATIOI I PEP CED BOOK 96J4 PAGE 1520_____
I
=Ro=osrn ITMPORARV _ CO~TRUCTICN EASEtErH -
N F PEDRY MARK L amp LAURIE Z FAIRHUlT ESrATES
101 6 ED ECC~ Y I(pound Dbull
rmiddotrorcsrn runt I~ -rAll AN~
BR )G[ lt1AINTENACEshyEASEMENT
FAIRFAX COUNTY PARK AUTHORITY
- shy APAOnAli L IJIFS OIF ll~Qllt f lffl)
DOSTHC poundlaquo(
CQ)TNt _-COUClaquot (nAV[L TVL
PRltJIOSfn FM~WlARY COllSIRUCllON USpound)poundH (t7tli5ri
fmiddotmiddot middot middot ~~~~I ~~~~~~)
LO
FAIRFAX COUNTY BOARD OF
SUPERVISORS
NOTES ~flo~~lf~ t-tVO W WCAIUI 1AltUtl lI M-lgt3Mtlll - 11 ~I 4)
~~gtl bull gt JJ~U-lllCoI bullJ AllC lltO- ltC (K1 rtait I~) -- nc- --~ eounmiddot ac
~r~~~~~=lH _ l(N tj W U 1ar1w~ usmgt vu w AI mn Wlt IAMl lfbull~
r __ oJllH nJJlllbull l~i ~TCDlUt Pntlo~ sunu1r-ubulla cNJCl -_ n bullJQOUgt 1Ktl19deg -ltgtOC i--mFri _ ~1--4n71
IMRpoundL POlllA1CPpoundL~ ftlle3otY VVlll L llUlgt~1lel_ lol~~ ll~ _L~--L~
~~~1 Pfitgt-M13AUa81Wlml01WSfuacln gtClgt
~middot-- U- 017 U-
l~~tl~~ ~gtmiddotbull~
l()lIMDJn IND IOllTi WCWI ~10llT(N X1H~middotraquo1$ lS(I) Oii CO$TIKI Lcl 11~ a OJHliif OHY WOtlM bull ~tUl~ ~1-bull~all11111l)llMl~~ll)
-1 i~g roooltlllTC _ ~MUii -~ ~ (-IC )1-~t -0 KQ TCIDlr - a lNHUlL cti1laquo1 ~ncDlJ A C ZC bulll U V0 LlAI Nl-Cgt At_ Ct lllNA lX _( OUU MoP ~c~ rbull RFbull) CDJTX ~R11u C)MlVlN-PI OllJWAll ~m)(lhl)F ) Sl~~1 middot1 i-gt1~ I I
Vl llllLJll lMIAgtCJllllUNNlllraquoU Yl1lt -111ulM b bull~11middot1111 ~0lM tJAltUI ltlt+r-1ltNH I -middotmiddot
Study Results LEASE AR[A tHUHTERS VAl1EY ASSOClltllCN
- PC~ DCCgt COQC 9GJ4 PAC 1C20---
IDU I shy-- ( OB SP92 [
~
J7o Pldeg_~sJgt - _jr_
----___ ----- degNe SJgt middot middot __ ------shy-_ 1 IC2
---___ I v I 0
lt D Pu8UC TRAIL E 11 shy
CbullB 9792 ~G 400 y ~
O EX INRESS-ECRESS E UT B 9871 P S~J l f I
(fa L- (
jj l - LIMITS CF CLEARINGPOP ~MP
C()fl~TllllCTIO )ff I AID GRADING c EASE~ENT ) PFbPgtSEO BRIDGE
pr bull bulln I
PIN 0371-23-0005 ( I I ~ 0371-01-0033N 1 PEDRY MARK L amp LAURIE Z I - FAIRFAX COUNTYFAIRHUNl ESTATES PARK AUTHORITYLOT 5
~111 ~ ilb 1-AIA legtb1ccco OOOK 953bull rAc 1s2c )
I
I I
I Pl 0371-03-0007
FAIRFAX COUNTY PARK AUTHORITY
OCO OOOK 275$ fAGC 125
Existing Ground Elevation=2535
Edge of 100-Year Flood=STA 0+70 Edge of 100-Year Flood=STA 7+30
100-Year Flood Depth=Approx 5 ft over the Existing Top of Bank Existing Crossing Location
100-Year Flood Width-Approx 660 Ft wide Existing Crossing Location
Or IPE
Bridge Inundation - Video
Holmes Run Accotink Creek
Accotink Creek Pohick Creek
Topographic Survey ndash Complete
Draft Schematic Plan ndash Complete
Final Schematic Plan ndash Complete
Concept Study - Complete
Final Design ndash April ndash June 2019
Permitting ndash July ndash December 2019
Bidding amp Construction ndash January -July 2020
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
State and Federal Permitting Requirements (Joint Permit Application)
Virginia Marine Resources Commission (VMRC)
Army Corps Wetland Preliminary Jurisdictional Determination (JD)
Army Corps Nationwide Permits (NWP) for Recreational Facilities
Total Project Estimate (from here forward)
Design and testing $91400
Permits $12000
Construction $243800
Administration $35700
Mitigation $11300
Total $394200
Available Funding
$100000 from Sully District Sidewalk Fund
$308000 from Developer Proffers in Sully District
Study Results LEASE AAEJI
HUNTE~gt VALLEY ASSOCIATIOI I PEP CED BOOK 96J4 PAGE 1520_____
I
=Ro=osrn ITMPORARV _ CO~TRUCTICN EASEtErH -
N F PEDRY MARK L amp LAURIE Z FAIRHUlT ESrATES
101 6 ED ECC~ Y I(pound Dbull
rmiddotrorcsrn runt I~ -rAll AN~
BR )G[ lt1AINTENACEshyEASEMENT
FAIRFAX COUNTY PARK AUTHORITY
- shy APAOnAli L IJIFS OIF ll~Qllt f lffl)
DOSTHC poundlaquo(
CQ)TNt _-COUClaquot (nAV[L TVL
PRltJIOSfn FM~WlARY COllSIRUCllON USpound)poundH (t7tli5ri
fmiddotmiddot middot middot ~~~~I ~~~~~~)
LO
FAIRFAX COUNTY BOARD OF
SUPERVISORS
NOTES ~flo~~lf~ t-tVO W WCAIUI 1AltUtl lI M-lgt3Mtlll - 11 ~I 4)
~~gtl bull gt JJ~U-lllCoI bullJ AllC lltO- ltC (K1 rtait I~) -- nc- --~ eounmiddot ac
~r~~~~~=lH _ l(N tj W U 1ar1w~ usmgt vu w AI mn Wlt IAMl lfbull~
r __ oJllH nJJlllbull l~i ~TCDlUt Pntlo~ sunu1r-ubulla cNJCl -_ n bullJQOUgt 1Ktl19deg -ltgtOC i--mFri _ ~1--4n71
IMRpoundL POlllA1CPpoundL~ ftlle3otY VVlll L llUlgt~1lel_ lol~~ ll~ _L~--L~
~~~1 Pfitgt-M13AUa81Wlml01WSfuacln gtClgt
~middot-- U- 017 U-
l~~tl~~ ~gtmiddotbull~
l()lIMDJn IND IOllTi WCWI ~10llT(N X1H~middotraquo1$ lS(I) Oii CO$TIKI Lcl 11~ a OJHliif OHY WOtlM bull ~tUl~ ~1-bull~all11111l)llMl~~ll)
-1 i~g roooltlllTC _ ~MUii -~ ~ (-IC )1-~t -0 KQ TCIDlr - a lNHUlL cti1laquo1 ~ncDlJ A C ZC bulll U V0 LlAI Nl-Cgt At_ Ct lllNA lX _( OUU MoP ~c~ rbull RFbull) CDJTX ~R11u C)MlVlN-PI OllJWAll ~m)(lhl)F ) Sl~~1 middot1 i-gt1~ I I
Vl llllLJll lMIAgtCJllllUNNlllraquoU Yl1lt -111ulM b bull~11middot1111 ~0lM tJAltUI ltlt+r-1ltNH I -middotmiddot
Study Results LEASE AR[A tHUHTERS VAl1EY ASSOClltllCN
- PC~ DCCgt COQC 9GJ4 PAC 1C20---
IDU I shy-- ( OB SP92 [
~
J7o Pldeg_~sJgt - _jr_
----___ ----- degNe SJgt middot middot __ ------shy-_ 1 IC2
---___ I v I 0
lt D Pu8UC TRAIL E 11 shy
CbullB 9792 ~G 400 y ~
O EX INRESS-ECRESS E UT B 9871 P S~J l f I
(fa L- (
jj l - LIMITS CF CLEARINGPOP ~MP
C()fl~TllllCTIO )ff I AID GRADING c EASE~ENT ) PFbPgtSEO BRIDGE
pr bull bulln I
PIN 0371-23-0005 ( I I ~ 0371-01-0033N 1 PEDRY MARK L amp LAURIE Z I - FAIRFAX COUNTYFAIRHUNl ESTATES PARK AUTHORITYLOT 5
~111 ~ ilb 1-AIA legtb1ccco OOOK 953bull rAc 1s2c )
I
I I
I Pl 0371-03-0007
FAIRFAX COUNTY PARK AUTHORITY
OCO OOOK 275$ fAGC 125
Existing Ground Elevation=2535
Edge of 100-Year Flood=STA 0+70 Edge of 100-Year Flood=STA 7+30
100-Year Flood Depth=Approx 5 ft over the Existing Top of Bank Existing Crossing Location
100-Year Flood Width-Approx 660 Ft wide Existing Crossing Location
Or IPE
Bridge Inundation - Video
Holmes Run Accotink Creek
Accotink Creek Pohick Creek
Topographic Survey ndash Complete
Draft Schematic Plan ndash Complete
Final Schematic Plan ndash Complete
Concept Study - Complete
Final Design ndash April ndash June 2019
Permitting ndash July ndash December 2019
Bidding amp Construction ndash January -July 2020
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
Total Project Estimate (from here forward)
Design and testing $91400
Permits $12000
Construction $243800
Administration $35700
Mitigation $11300
Total $394200
Available Funding
$100000 from Sully District Sidewalk Fund
$308000 from Developer Proffers in Sully District
Study Results LEASE AAEJI
HUNTE~gt VALLEY ASSOCIATIOI I PEP CED BOOK 96J4 PAGE 1520_____
I
=Ro=osrn ITMPORARV _ CO~TRUCTICN EASEtErH -
N F PEDRY MARK L amp LAURIE Z FAIRHUlT ESrATES
101 6 ED ECC~ Y I(pound Dbull
rmiddotrorcsrn runt I~ -rAll AN~
BR )G[ lt1AINTENACEshyEASEMENT
FAIRFAX COUNTY PARK AUTHORITY
- shy APAOnAli L IJIFS OIF ll~Qllt f lffl)
DOSTHC poundlaquo(
CQ)TNt _-COUClaquot (nAV[L TVL
PRltJIOSfn FM~WlARY COllSIRUCllON USpound)poundH (t7tli5ri
fmiddotmiddot middot middot ~~~~I ~~~~~~)
LO
FAIRFAX COUNTY BOARD OF
SUPERVISORS
NOTES ~flo~~lf~ t-tVO W WCAIUI 1AltUtl lI M-lgt3Mtlll - 11 ~I 4)
~~gtl bull gt JJ~U-lllCoI bullJ AllC lltO- ltC (K1 rtait I~) -- nc- --~ eounmiddot ac
~r~~~~~=lH _ l(N tj W U 1ar1w~ usmgt vu w AI mn Wlt IAMl lfbull~
r __ oJllH nJJlllbull l~i ~TCDlUt Pntlo~ sunu1r-ubulla cNJCl -_ n bullJQOUgt 1Ktl19deg -ltgtOC i--mFri _ ~1--4n71
IMRpoundL POlllA1CPpoundL~ ftlle3otY VVlll L llUlgt~1lel_ lol~~ ll~ _L~--L~
~~~1 Pfitgt-M13AUa81Wlml01WSfuacln gtClgt
~middot-- U- 017 U-
l~~tl~~ ~gtmiddotbull~
l()lIMDJn IND IOllTi WCWI ~10llT(N X1H~middotraquo1$ lS(I) Oii CO$TIKI Lcl 11~ a OJHliif OHY WOtlM bull ~tUl~ ~1-bull~all11111l)llMl~~ll)
-1 i~g roooltlllTC _ ~MUii -~ ~ (-IC )1-~t -0 KQ TCIDlr - a lNHUlL cti1laquo1 ~ncDlJ A C ZC bulll U V0 LlAI Nl-Cgt At_ Ct lllNA lX _( OUU MoP ~c~ rbull RFbull) CDJTX ~R11u C)MlVlN-PI OllJWAll ~m)(lhl)F ) Sl~~1 middot1 i-gt1~ I I
Vl llllLJll lMIAgtCJllllUNNlllraquoU Yl1lt -111ulM b bull~11middot1111 ~0lM tJAltUI ltlt+r-1ltNH I -middotmiddot
Study Results LEASE AR[A tHUHTERS VAl1EY ASSOClltllCN
- PC~ DCCgt COQC 9GJ4 PAC 1C20---
IDU I shy-- ( OB SP92 [
~
J7o Pldeg_~sJgt - _jr_
----___ ----- degNe SJgt middot middot __ ------shy-_ 1 IC2
---___ I v I 0
lt D Pu8UC TRAIL E 11 shy
CbullB 9792 ~G 400 y ~
O EX INRESS-ECRESS E UT B 9871 P S~J l f I
(fa L- (
jj l - LIMITS CF CLEARINGPOP ~MP
C()fl~TllllCTIO )ff I AID GRADING c EASE~ENT ) PFbPgtSEO BRIDGE
pr bull bulln I
PIN 0371-23-0005 ( I I ~ 0371-01-0033N 1 PEDRY MARK L amp LAURIE Z I - FAIRFAX COUNTYFAIRHUNl ESTATES PARK AUTHORITYLOT 5
~111 ~ ilb 1-AIA legtb1ccco OOOK 953bull rAc 1s2c )
I
I I
I Pl 0371-03-0007
FAIRFAX COUNTY PARK AUTHORITY
OCO OOOK 275$ fAGC 125
Existing Ground Elevation=2535
Edge of 100-Year Flood=STA 0+70 Edge of 100-Year Flood=STA 7+30
100-Year Flood Depth=Approx 5 ft over the Existing Top of Bank Existing Crossing Location
100-Year Flood Width-Approx 660 Ft wide Existing Crossing Location
Or IPE
Bridge Inundation - Video
Holmes Run Accotink Creek
Accotink Creek Pohick Creek
Topographic Survey ndash Complete
Draft Schematic Plan ndash Complete
Final Schematic Plan ndash Complete
Concept Study - Complete
Final Design ndash April ndash June 2019
Permitting ndash July ndash December 2019
Bidding amp Construction ndash January -July 2020
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
Study Results LEASE AAEJI
HUNTE~gt VALLEY ASSOCIATIOI I PEP CED BOOK 96J4 PAGE 1520_____
I
=Ro=osrn ITMPORARV _ CO~TRUCTICN EASEtErH -
N F PEDRY MARK L amp LAURIE Z FAIRHUlT ESrATES
101 6 ED ECC~ Y I(pound Dbull
rmiddotrorcsrn runt I~ -rAll AN~
BR )G[ lt1AINTENACEshyEASEMENT
FAIRFAX COUNTY PARK AUTHORITY
- shy APAOnAli L IJIFS OIF ll~Qllt f lffl)
DOSTHC poundlaquo(
CQ)TNt _-COUClaquot (nAV[L TVL
PRltJIOSfn FM~WlARY COllSIRUCllON USpound)poundH (t7tli5ri
fmiddotmiddot middot middot ~~~~I ~~~~~~)
LO
FAIRFAX COUNTY BOARD OF
SUPERVISORS
NOTES ~flo~~lf~ t-tVO W WCAIUI 1AltUtl lI M-lgt3Mtlll - 11 ~I 4)
~~gtl bull gt JJ~U-lllCoI bullJ AllC lltO- ltC (K1 rtait I~) -- nc- --~ eounmiddot ac
~r~~~~~=lH _ l(N tj W U 1ar1w~ usmgt vu w AI mn Wlt IAMl lfbull~
r __ oJllH nJJlllbull l~i ~TCDlUt Pntlo~ sunu1r-ubulla cNJCl -_ n bullJQOUgt 1Ktl19deg -ltgtOC i--mFri _ ~1--4n71
IMRpoundL POlllA1CPpoundL~ ftlle3otY VVlll L llUlgt~1lel_ lol~~ ll~ _L~--L~
~~~1 Pfitgt-M13AUa81Wlml01WSfuacln gtClgt
~middot-- U- 017 U-
l~~tl~~ ~gtmiddotbull~
l()lIMDJn IND IOllTi WCWI ~10llT(N X1H~middotraquo1$ lS(I) Oii CO$TIKI Lcl 11~ a OJHliif OHY WOtlM bull ~tUl~ ~1-bull~all11111l)llMl~~ll)
-1 i~g roooltlllTC _ ~MUii -~ ~ (-IC )1-~t -0 KQ TCIDlr - a lNHUlL cti1laquo1 ~ncDlJ A C ZC bulll U V0 LlAI Nl-Cgt At_ Ct lllNA lX _( OUU MoP ~c~ rbull RFbull) CDJTX ~R11u C)MlVlN-PI OllJWAll ~m)(lhl)F ) Sl~~1 middot1 i-gt1~ I I
Vl llllLJll lMIAgtCJllllUNNlllraquoU Yl1lt -111ulM b bull~11middot1111 ~0lM tJAltUI ltlt+r-1ltNH I -middotmiddot
Study Results LEASE AR[A tHUHTERS VAl1EY ASSOClltllCN
- PC~ DCCgt COQC 9GJ4 PAC 1C20---
IDU I shy-- ( OB SP92 [
~
J7o Pldeg_~sJgt - _jr_
----___ ----- degNe SJgt middot middot __ ------shy-_ 1 IC2
---___ I v I 0
lt D Pu8UC TRAIL E 11 shy
CbullB 9792 ~G 400 y ~
O EX INRESS-ECRESS E UT B 9871 P S~J l f I
(fa L- (
jj l - LIMITS CF CLEARINGPOP ~MP
C()fl~TllllCTIO )ff I AID GRADING c EASE~ENT ) PFbPgtSEO BRIDGE
pr bull bulln I
PIN 0371-23-0005 ( I I ~ 0371-01-0033N 1 PEDRY MARK L amp LAURIE Z I - FAIRFAX COUNTYFAIRHUNl ESTATES PARK AUTHORITYLOT 5
~111 ~ ilb 1-AIA legtb1ccco OOOK 953bull rAc 1s2c )
I
I I
I Pl 0371-03-0007
FAIRFAX COUNTY PARK AUTHORITY
OCO OOOK 275$ fAGC 125
Existing Ground Elevation=2535
Edge of 100-Year Flood=STA 0+70 Edge of 100-Year Flood=STA 7+30
100-Year Flood Depth=Approx 5 ft over the Existing Top of Bank Existing Crossing Location
100-Year Flood Width-Approx 660 Ft wide Existing Crossing Location
Or IPE
Bridge Inundation - Video
Holmes Run Accotink Creek
Accotink Creek Pohick Creek
Topographic Survey ndash Complete
Draft Schematic Plan ndash Complete
Final Schematic Plan ndash Complete
Concept Study - Complete
Final Design ndash April ndash June 2019
Permitting ndash July ndash December 2019
Bidding amp Construction ndash January -July 2020
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
Study Results LEASE AR[A tHUHTERS VAl1EY ASSOClltllCN
- PC~ DCCgt COQC 9GJ4 PAC 1C20---
IDU I shy-- ( OB SP92 [
~
J7o Pldeg_~sJgt - _jr_
----___ ----- degNe SJgt middot middot __ ------shy-_ 1 IC2
---___ I v I 0
lt D Pu8UC TRAIL E 11 shy
CbullB 9792 ~G 400 y ~
O EX INRESS-ECRESS E UT B 9871 P S~J l f I
(fa L- (
jj l - LIMITS CF CLEARINGPOP ~MP
C()fl~TllllCTIO )ff I AID GRADING c EASE~ENT ) PFbPgtSEO BRIDGE
pr bull bulln I
PIN 0371-23-0005 ( I I ~ 0371-01-0033N 1 PEDRY MARK L amp LAURIE Z I - FAIRFAX COUNTYFAIRHUNl ESTATES PARK AUTHORITYLOT 5
~111 ~ ilb 1-AIA legtb1ccco OOOK 953bull rAc 1s2c )
I
I I
I Pl 0371-03-0007
FAIRFAX COUNTY PARK AUTHORITY
OCO OOOK 275$ fAGC 125
Existing Ground Elevation=2535
Edge of 100-Year Flood=STA 0+70 Edge of 100-Year Flood=STA 7+30
100-Year Flood Depth=Approx 5 ft over the Existing Top of Bank Existing Crossing Location
100-Year Flood Width-Approx 660 Ft wide Existing Crossing Location
Or IPE
Bridge Inundation - Video
Holmes Run Accotink Creek
Accotink Creek Pohick Creek
Topographic Survey ndash Complete
Draft Schematic Plan ndash Complete
Final Schematic Plan ndash Complete
Concept Study - Complete
Final Design ndash April ndash June 2019
Permitting ndash July ndash December 2019
Bidding amp Construction ndash January -July 2020
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
Existing Ground Elevation=2535
Edge of 100-Year Flood=STA 0+70 Edge of 100-Year Flood=STA 7+30
100-Year Flood Depth=Approx 5 ft over the Existing Top of Bank Existing Crossing Location
100-Year Flood Width-Approx 660 Ft wide Existing Crossing Location
Or IPE
Bridge Inundation - Video
Holmes Run Accotink Creek
Accotink Creek Pohick Creek
Topographic Survey ndash Complete
Draft Schematic Plan ndash Complete
Final Schematic Plan ndash Complete
Concept Study - Complete
Final Design ndash April ndash June 2019
Permitting ndash July ndash December 2019
Bidding amp Construction ndash January -July 2020
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
Or IPE
Bridge Inundation - Video
Holmes Run Accotink Creek
Accotink Creek Pohick Creek
Topographic Survey ndash Complete
Draft Schematic Plan ndash Complete
Final Schematic Plan ndash Complete
Concept Study - Complete
Final Design ndash April ndash June 2019
Permitting ndash July ndash December 2019
Bidding amp Construction ndash January -July 2020
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
Bridge Inundation - Video
Holmes Run Accotink Creek
Accotink Creek Pohick Creek
Topographic Survey ndash Complete
Draft Schematic Plan ndash Complete
Final Schematic Plan ndash Complete
Concept Study - Complete
Final Design ndash April ndash June 2019
Permitting ndash July ndash December 2019
Bidding amp Construction ndash January -July 2020
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
Holmes Run Accotink Creek
Accotink Creek Pohick Creek
Topographic Survey ndash Complete
Draft Schematic Plan ndash Complete
Final Schematic Plan ndash Complete
Concept Study - Complete
Final Design ndash April ndash June 2019
Permitting ndash July ndash December 2019
Bidding amp Construction ndash January -July 2020
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
Topographic Survey ndash Complete
Draft Schematic Plan ndash Complete
Final Schematic Plan ndash Complete
Concept Study - Complete
Final Design ndash April ndash June 2019
Permitting ndash July ndash December 2019
Bidding amp Construction ndash January -July 2020
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
Initiate Land Acquisition
Complete Final Design and Permitting
Continue to provide and update project information on the FCPA website
Questions
Questions