Change Request Form
DH CIMSCommon Interface GatewayChange Request Form (Deployment) (version 1.0)
Notes:
Deployment request should be made 3 days for UAT and 5 days for production in advance Source code of the deployment should be committed to SVN before 5 p.m of the deployment date.
Deployment request will be arranged in first-come-first-serve basis.
Deployment request should NOT be scheduled during office hours (9 a.m. to 6 p.m.).
Deployment would be executed between 6 p.m. to 8 p.m from Monday to Friday.
Deployment request after 8 p.m. is regarded as a special request. CIMS infra team might consider such request case-by-case. For the deployment to the Production Environment, side-by-side deployment from the Contractor is required
The following parts are to be filled in by the Requester
Service:CGS
Requested By:William NgaiDate:14-04-2014
Environment:UAT
Deployment Date:15-04-2014Deployment Time:6:00pm
Special Request for Deployment (Reason):Prepare and perform UAT test for the CGS Portal
Verification done:
Verification Date:14-04-2014
Verification By:Simon Leung
Priority :High
Expected Change Date:CIMS CGS Portal: 15-04-2014
Scheduled Change Date:CIMS CGS Portal: 15-04-2014
CIMS production service interruption during implementation period?N/A
Ignore alerts and/or by-pass daily health check for servers:None / (Please state server or device name list)Contact Point: KC Chu
Tel: 61998303
Email: [email protected]
Weblogic Changes (if applicable)
Data Source (Please state host applied, managed server applied, JNDI name, database username)
Keystore / Trust Cert (Please state host applied, managed server applied, trust cert purpose)
Other configuration (Please state host applied, managed server applied, parameter and value(s))
Middleware and Third Party Product Changes (if applicable)
Oracle HTTP Server (OHS) Policy
Oracle Access Manager (OAM) PolicyGrant the access right to the following links:
CGSPortal/progeny/progeny_signed_offical.jar
CGSPortal/progeny/ProgenyAnywhereJ_8_301.dtd
CGSPortal/progeny/ProgenyAnywhereJ8_v3.jar
OIM (User Role / User group, Description)
eForm ServerDeployment to eForm Server
Deployment Date: 15-04-2014Form program can be found inThe svn link is https://10.107.129.69/svn/DH-CIMS/CGS/trunk/app/CIMSTemplate20140415/eform
Crystal Report Server
Others
Web Services (if applicable)
Web Service Name:
Batch Job on Batch Framework (if applicable)
Job (Please state the job name, run schedule)Deployment of batch job program and job:
The svn link is https://10.107.129.69/svn/DH-CIMS/CGS/trunk/app/CIMSTemplate20140415/batch/ SharedWebLibCGS.war
Local file / folders (if applicable)
Please state the description of data, host, path, sizing, corresponding housekeep mechanism, housekeep schedule, encryption information
OSB configuration and OES policy (if applicable)
Please state the OSB configuration, system account, OES policy
Impact and Implementation
Impact Analysis: None
Impact to Other System(s): None/State the affected systems
Implementation Venue: eHRMT office
Implementation Period:
Implementation Plan/Procedure: (please attach file, if any)Deployment to CGS Portal Server
Deployment Date: 15-04-2014The svn link is https://10.107.129.69/svn/DH-CIMS/CGS/trunk/app/CIMSTemplate20140415/CGSPortal.ear
Service Down Time, if any:
Fall Back Plan:
The following parts are to be filled in by the DH CIG Team
Investigated By (DH CIG Team):Date:
Ref No.:
Remarks:
Checking Procedure, if any:
Remarks:
Change Request Approved By: CPM(eHR)1/SSM(eHR)Date:
Actions Taken By:Date:
Actual Change Date:
Remarks/Result: