DGNSS-Assisted Piling System PANG CHOON CHEW United Nation World Geospatial Information Congress The Geospatial Way To A Better World Spatially Enabled Future Cities

DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

• DGNSS-Assisted Piling System

PANG CHOON CHEW

United Nation World Geospatial Information CongressThe Geospatial Way To A Better World

Spatially Enabled Future Cities

Page 2: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

DGNSS-ASSISTED PILING SYSTEM

• Motivation

• PILING PROCESS

• CONVENTINAL SURVEY FOR PILING

• THE TRANSFORMATION

• NOW

Page 3: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in
Page 4: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

EngineerPrepares

Piling Plan (Position,

Type, Size)

Surveyor

Surveys and marks

position of pile

Piling Contractor

Piles at points marked by

surveyor

Surveyor

Measures and

documents difference between

actual and design

position of pile

Surveyor

Measures and

documents result of

remedy work

Piling Contractor

Piling for remedy work

Surveyor

Surveys and marks out

position for remedy work

e.g. additional

piles

Engineer

Reviews any discrepancy

between design and actual pile

position and orders

remedy work

The Piling Process

Page 5: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in
Page 6: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in
Page 7: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

Conventional Surveying and Setting Out

Two-man Team Daily Setup (15 mins per site) Assistant finds pile position

Found design positionHammers in Peg Labels Piling Peg (Marker)

Page 8: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

CURRENT PILING METHOD

Pile positions set using total station.

Riggers place reference points

Piling rig moves in and pile is installed.

Move to next pile point.

Page 9: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

Survey and findPile Position

Full-time surveyor needed if have to check peg just prior to piling.

Surveying in the Piling Process

Page 10: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

➢ The peg move when the piling machine move –in

➢ Pile displacement due to pressure from the neighboring pile

➢ Excavations ➢ Poor supervision➢ Human error

Page 11: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in
Page 12: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

BACKGROUND –PILE POSITIONING PROBLEMS

• The piling pegs get displaced from their original positions • due to soil movement caused by piling.

• due to maneuvering of heavy machines.

• No independent method is used to verify peg positions

• Pile eccentricity (error in position) is recorded too late• towards end of piling process, at cut-off-level

• when piling machines have already been deployed to other sites

Page 13: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

Transformation begin:• Set pile using conventional method.

• Check by GNSS to confirm the reliability.

• Mount the receiver on the pile.

Page 14: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

Jet-in Machine

Page 15: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in
Page 16: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

Problem:

• When Jet-in pilling machine moves in,

peg point will be displaced

• Worker have to go below the heavy

machinery to align the peg point

Page 17: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

• SiReNT is the national Differential GNSS

infrastructure supporting a wide range of positioning

applications;

• SiReNT is the realisation of Singapore’s reference

frame (SVY21) ensuring data integrity and

interoperability; &

• SiReNT Differential GNSS provides sub-metre &

centimetres positioning accuracy in real-time.

Page 18: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

• 8 GNSS (GPS/GLONASS/QZSS/COMPASS

& GALILEO) reference stations

• 1 Integrity monitoring reference station

SSTS – Sultan Shoal

SNYU NTU

SiReNT GNSS Reference Stations

Page 19: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

Jet-in Machine

Page 20: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

Installed on bored pile machine

Page 21: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

Solutions:

• Two antennae will be installed on the machine

• Operator will be guided to the design location from the

tablet in the control cabin.

• Reduced safety risk

• Saves remedy cost

• Improved productivity

Page 22: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

22

Setting Piling Pegs Using GNSS

Page 23: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

Bidadari C4 Project

• 2 machines using conventional setting out method.

• 2 machines using dual antenna solution

Page 24: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in

SIRENT WEB PORTAL

Page 25: DGNSS-Assisted Piling Systemggim.un.org/unwgic/presentations/3.5-PANG-CHOON-CHEW.pdf · Pile positions set using total station. Riggers place reference points Piling rig moves in