37
1 CANADA’S INTERMEDIATE GOLD PRODUCER CIBC Mining Conference Big Opportunities on the Home Front Toronto, June 23, 2015 One-on-one Meetings

Dgc 15 06_23 - cibc corporate presentation 1-1

Embed Size (px)

Citation preview

1

CANADA’S INTERMEDIATE GOLD PRODUCER

CIBC Mining Conference – Big Opportunities on the Home Front

Toronto, June 23, 2015

One-on-one Meetings

2

Forward Looking Information This presentation contains certain forward-looking information and statements as defined in applicable securities law (referred to herein as

“forward-looking statements”). Forward-looking statements include, but are not limited to, statements with respect to 2015 guidance for

production, total cash costs, all-in sustaining costs, capital costs, deferred stripping costs, and exploration costs; expected throughput,

mining and recovery rates; expected future production and mining activities; opportunities to optimize the mine operation; timeline for the

life of mine plan update, second test for the processing of fines, and exploration program; and opportunities to optimize the mine operation.

Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause actual results, performance

or achievements to be materially different from any of its future results, performance or achievements expressed or implied by forward-

looking statements. These risks, uncertainties and other factors include, but are not limited to, assumptions and parameters underlying the

life of mine update not being realized, a decrease in the future gold price, discrepancies between actual and estimated production, changes

in costs (including labour, supplies, fuel and equipment), changes to tax rates; environmental compliance and changes in environmental

legislation and regulation, exchange rate fluctuations, general economic conditions and other risks involved in the gold exploration and

development industry, as well as those risk factors discussed in the section entitled “Description of Business - Risk Factors” in Detour

Gold’s 2014 AIF and in the continuous disclosure documents filed by Detour Gold on and available on SEDAR at www.sedar.com.

Such forward-looking statements are also based on a number of assumptions which may prove to be incorrect, including, but not limited to,

assumptions about the following: the availability of financing for exploration and development activities; operating and sustaining capital

costs; the Company’s ability to attract and retain skilled staff; sensitivity to metal prices and other sensitivities; the supply and demand for,

and the level and volatility of the price of, gold; the supply and availability of consumables and services; the exchange rates of the Canadian

dollar to the U.S. dollar; energy and fuel costs; the accuracy of reserve and resource estimates and the assumptions on which the reserve

and resource estimates are based; market competition; ongoing relations with employees and impacted communities and general business

and economic conditions. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking

statements contained herein are made as of the date hereof, or such other date or dates specified in such statements.

All forward-looking statements in this presentation are necessarily based on opinions and estimates made as of the date such statements

are made and are subject to important risk factors and uncertainties, many of which cannot be controlled or predicted. Detour Gold and the

Qualified Persons who authored the associated Technical Report undertake no obligation to update publicly or otherwise revise any

forward-looking statements contained herein whether as a result of new information or future events or otherwise, except as may be

required by law.

3

Notes to Investors

The scientific and technical content of this presentation was reviewed, verified and approved by Drew Anwyll, P.Eng., Senior Vice President Technical

Services, and exploration results was reviewed, verified and approved by Guy MacGillivray, P.Geo.., Exploration Manager , both Qualified Person as

defined by Canadian Securities Administrators National Instrument 43-101 “Standards of Disclosure for Mineral Projects”.

Qualified Persons

Non-IFRS Financial Performance Measures The Company has included non-IFRS measures in this presentation: total cash costs, all-in sustaining costs, adjusted net loss and adjusted net loss per

share. The Company believes that these measures, in addition to conventional measures prepared in accordance with IFRS, provide investors an improved

ability to evaluate the underlying performance of the Company. The non-IFRS measures are intended to provide additional information and should not be

considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. These measures do not have any standardized

meaning prescribed under IFRS, and therefore may not be comparable to other issuers. Other companies may calculate these measure differently.

Detour Gold reports total cash costs on a sales basis. Total cash costs include production costs such as mining, processing, refining and site

administration, less non-cash share-based compensation and net of silver sales divided by gold ounces sold to arrive at total cash costs per gold ounce

sold. The measure also includes other mine related costs incurred such as mine standby costs and current inventory write downs. Production costs are

exclusive of depreciation and depletion. Production costs include the costs associated with providing the royalty in kind ounces.

Commencing in 2015, the Company adopted all-in sustaining costs on a prospective basis. The Company believes this measure more fully defines the total

costs associated with producing gold. The Company calculates all-in sustaining costs as the sum of total cash costs (as described above), share-based

compensation, corporate general and administrative expense, exploration and evaluation expenses that are sustaining in nature, reclamation cost

accretion, sustaining capital including deferred stripping, and realized gains and losses on hedges due to operating and capital costs, all divided by the gold

ounces sold to arrive at a per ounce figure.

Costs excluded from all-in sustaining costs are non-sustaining capital expenditures and exploration costs that are expected to materially increase

production, financing costs and tax expense. Consequently, this measure is not representative of all of the Company’s cash expenditures. In addition, the

calculation of all-in sustaining costs does not include depreciation and depletion expense as it does not reflect the impact of expenditures incurred in prior

periods.

Adjusted net loss and adjusted basic loss per share are used by management and investors to measure the underlying operating performance of the

Company. Presenting these measures from period to period helps management and investors evaluate earnings trends more readily in comparison with

results from prior periods. Adjusted net loss is defined as net loss adjusted to exclude specific items that are significant, but not reflective of the underlying

operations of the Company, including: fair value change of the convertible notes, the impact of foreign exchange gains and losses, including the foreign

exchange on deferred income and mining taxes, non-cash unrealized gains and losses on derivative instruments, accretion on convertible notes, unwinding

of discount on decommissioning and restoration provisions, impairment provisions and reversals thereof, and other non-recurring items. Adjusted basic net

loss per share is calculated using the weighted average number of shares outstanding under the basic method of loss per share as determined under

IFRS.

4

Unique Investment Opportunity

Mining-friendly Jurisdiction

Large-scale, long mine life

Largest gold producing mine not

controlled by a senior producer

Growing cash flow profile

Production growth opportunities

Favourable exposure to

Canadian Dollar

DOMINANT

GOLD PRODUCER

IN CANADA

5

2015 Production Guidance (Koz)

#2 in Production and #1 in Reserves

DGC Detour Lake

AEM/YRI Canadian

Malartic

AEM Meadowbank

G Red Lake

Canadian Intermediate Gold Producer

400-

425

560 475-

525 400

Gold Reserves (Moz)

DGC Detour Lake

AEM/YRI Canadian

Malartic

AEM Meadowbank

G Red Lake

2.1

15.0

8.7

1.2

6

2015 Drivers to Success

Execution of Plan

Gold production increase with higher

mining and milling rates

Strengthen balance sheet

Added Benefits

Significant leverage to gold price and

Canadian dollar

Low power and diesel costs

Near to Long-Term Value Enhancements

Plant optimization (with limited capital)

Development of Block A

Exploration potential

7

third year

of operation

2015

2015 Guidance1

TCC2

$780-

$850

AISC/oz sold2

$1,050-$1,150

Capital Expenditures

Sustaining capital: US$90-100 M

ON TARGET

475,000 -

525,000

Gold ounces

ESTIMATED

COSTS

ESTIMATED

PRODUCTION

Deferred stripping: US$20-25 M

1. Cost assumptions (US$): Gold price of $1,200/oz, diesel fuel price of $0.82 per litre; power cost of $0.04 per kilowatt hour;

and exchange rate of $1.00US:$1.15Cdn.

2. Refer to the section on Non-IFRS Performance Measures on slide 3 of this presentation.

8

MINE MILL

BUDGET:

238,000 (approx. 87 Mt total mined)

RESULTS UPDATE:

Currently exceeding budget

271,000 achieved over last 3 months

BUDGET:

54,000 (milling rates of ~2,600 tpoh

at 87% availability)

RESULTS UPDATE:

Currently exceeding budget

59,370* achieved over last 3 months

2015 Key Targets

Achieving Results Through Optimization and Efficiency

TPD avg mining rate

TPD avg mining rate

TPD mill throughput

TPD mill throughput

No major planned shutdown in this period. *

9

220

271

238 238 238 5

20 30

Q1

280

Positive progress on drilling rates, blasted inventory, and shovel

productivity

Operating at 271,000 tpd for last 3 months

Q2E Q4E Q3E Mining Rates (ktpd)

2015

targets for

improvement

260

220

180

2015 Plan for Mine

2015 Budget of 238,000 tpd (Phase 1 & 2)

200

240

Last

3 months

Achieved Budget

10

Drivers

Average production drilling rates:

3,077 m/d over last 3 months

Mineable broken and drilled

inventory: 5.2 Mt at end of May

Result

Shovel productivity increase

Mining rates exceeding budget

levels

Positive Impact

Commencing to de-risk Q4 by

accessing higher grade ore earlier

Drivers: Drilling Rates/Blasted Inventory

1.6 2.3

3.1 3.9

2.5 1.7

1.9 1.6 0.8 2.7

2,297

2,640

3,010 3,100 3,122

0

500

1,000

1,500

2,000

2,500

3,000

3,500

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

Jan Feb Mar Apr May

Drilled Inventory at month's end (Mt)

Mineable Broken Inventory at month's end (Mt)

Drilling Rate (m/d)

Higher Mining Rates Achieved Over Last 3 Months

11

Q4 Target of 268,000 tpd Met in Q2

SCORE CARD:

Achieved Q4 stretch goal of

268,000* 6 months ahead of plan

TPD avg mining rate

Phase 1 & 2. *

Targeting

250,000 to

290,000 tpd

for remainder

of 2015

Work towards stabilization of mine operation with focus on:

1. Accelerating east end pit access (former Campbell pit area)

2. Maximizing TMA placement efficiency (using CAT795 trucks)

3. Reducing mobile maintenance costs and optimizing use of

contractors

1.

2.

3.

12

0

20

40

60

80

100

120

140

160

180

200

Work towards bringing Q4

ounces into Q3 (i.e. Q4 ROM

stockpile of 1.8 Mt at 0.80 g/t)

200

160

120

80

40

0

Higher Mining Rates Provides Operational Flexibility

2015 Mine Plan Upside

H H

H L

L L

SP

106

Q2E Q4E Q3E Q1 Gold Production (koz)

ROM Stockpile

10,000-15,000 additional in Q3

OZ gold

NOW TARGETING APPROX.

Budget

SP

2015 Budget

MT mined

3.5:1 STRIP RATIO waste:ore

MT ROM stockpiles

87

1.8

13

48

59

55 55 55

30

35

40

45

50

55

60

Q1'15 Last 3months

Q2'15 Q3'15 Q4'15

Last 3 months at 59,370 tpd with no major planned shutdowns

Targeting throughput rate of 55,000 tpd for next 3 quarters

Planned shutdowns scheduled in June and November

Plant Stabilization Since Mid-February

2015 Plan for Plant

Mill Throughput (ktpd)1

1. 55,000 tpd is the budget average throughput

for the period Q2 to Q4.

60

50

40

30 Q2E Q4E Q3E Q1 Last

3 months

Achieved

35

55

45

Budget 2015 Budget

MT ore milled

0.86 G/T AU head grade

% gold recovery

19.7

91.5

14

70 72

91 91 92

92

80

94 94 94

70.0

75.0

80.0

85.0

90.0

95.0

100.0

Jan Feb Mar Apr May

Operating Time (%)

Mechanical Availability (%)

Above budget since March

Mill operating time improved to 91%

over last 3 months with no major

planned shutdowns

4-day planned shutdown scheduled

for June: SAG liner changes on

both lines

Stabilization of mill: 136 days at

55,000 tpd design capacity (up to

May 31)

Last 3 months: 5.46 Mt of ore

processed

2,401

2,542

2,677 2,724 2,724

2,300.0

2,400.0

2,500.0

2,600.0

2,700.0

2,800.0

Jan Feb Mar Apr May

Milling Rate (tpoh)

2015 Plant Performance

Budget: 2,600

Budget: 87%

Design: 2,500

15

~80% of costs in Cdn$

2015 Operating Costs

Maintenance

Labour &

Contractors

Power

Fuel

G&A and

other

Consumables

30%

15%

33%

7%

11%

4% On target to achieve 2015 objectives

Cost reduction task force formed

in H2

Breakdown of 2015

Operating Costs

Q1’15 March

& April 2015E

Mining (C$/t mined) $3.16 $2.64 $2.60

Processing (C$/t milled) $11.35 $8.10 $9.87

G&A (C$/t milled) $3.89 $2.72 $3.05

* No major planned shutdown during these two months.

*

16

Overall timing of expenditures

weighted in Q2 & Q3

Capitalized stripping costs to be

incurred within the first 9

months

Mine

$30 M

TMA

$34 M

Other

$13 M

Mill

$9 M

Water Management

$10 M

Breakdown of 2015

Sustaining Capital (US$)

~90% of costs in Cdn$

16

2015 Capital Expenditures

Q1’15 2015 E

Sustaining Capital $19.8 M $90-100 M

Capitalized Stripping $10.0 M $20-25 M

Total (US$) $29.8 M $110-125 M

17

Upside for Lowering Opex & Capex Costs (US$ M)

Now 1.20 vs

1.15 budget

If 2015 avg rate

is same as 2014

If 10% lower than

budget US$0.82/L

Up to

$20 M

LOWER

CANADIAN

DOLLAR

COST

REDUCTION

PROGRAM

ELECTRICITY

CONTRACT

BENEFIT

LOWER

DIESEL

PRICE

Consumables

and contractors

$4 M

Probability factor of 50% = approx. $25 M reduction

$7 M

2015 Potential Cost Reductions

Up to

$20 M Up to

18

Cash position at

March 31, 2015:

US$118.1 M1

Balance Sheet Improvements

Reduce Debt

Repaid revolver and CAT lease of US$124 M

in Q1’15

Credit Facilities in Process

Amending terms of credit facility to reflect

“operating” company status

Repay Convertible Notes

Surplus cash towards repaying Notes

maturing Nov. 2017

Refinance balance of the Notes

1. In Q1 2015, approximately US$12 M was tied up in working capital due to the buyout of the CAT leases. This refundable HST has now

been received.

19

Prudent Financial Management

Hedge up to 50% of 2015 Gold Production

Forward sales on 85,000 oz @ US$1,255/oz

Currency Exchange Contracts

Zero-cost collars for US$90 M with a ceiling

of 1.20; Forward contracts for US$50 M at

average 1.26

Hedge ~50% of Q2-Q3 Diesel Use

Purchasing diesel product (~12 M litres) at

effective hedge price of C$0.80/litre

As at March 31, 2015

20

Realizing on Near-Term Opportunities

LOM Plan Update at end of Q4

5 options being reviewed that include Block A

Assessing Ultimate Plant Capacity

Improve 410-conveyor availability short-

term

Modify 410-conveyor long-term

Increase productivity of secondary and

pebble crushers

Low-grade Stockpiles (not in reserves)

Second test in H2: 4,000 tpd of enriched

material to be processed

Increase Exploration Activities

Start 30,000 metre drilling program at Lower

Detour this summer

21

Optimize capital allocation of the mining fleet

Add only valuable incremental ounces

Evaluate production ranging from 105 to 140 Mt annually

(equivalent to mining rates of 288,000 to 385,000 tpd)

Mining rates and timing of ongoing production increases year to

year:

1. No new shovels

2. Incremental shovel(s):

CAT6030 and/or CAT6060

Timing of Block A (at earliest 2018)

TMA options and potential co-disposal in Block A pit

LOM Plan Update

Options being

considered

1.

2.

Goal: Maximize Returns for Next 5-10 yrs and Optimize NAV

22

2015 Exploration focus: Lower Detour

Promising Exploration on 630 km2

Q1 Drilling Program

5,700 m completed at Lower Detour:

extended high-grade mineralization of

Zone 58N

Q2-Q3 Drilling Program

30,000 m additional drilling: 50-metre infill

totaling 50 holes to assess UG potential

(budget of $5 M)

Regional Potential

Target identification following airborne

magnetics and IP ground surveys

23

PRODUCTION GROWTH /

DECLINING UNIT COSTS

REALIZE VALUE-ENHANCING

OPPORTUNITIES

MATERIAL INPUTS TRENDING

FAVOURABLY

GROWING CASH FLOW

A GREAT TIME TO BE A

GOLD PRODUCER!

24

ADDITIONAL information

Analyst Coverage

Shareholder Information

Q1 2015 Operational Statistics

Q1 2015 Financial Results

Detour Gold Reserves &

Resources

Detour Lake & Block A

Exploration Focus: Lower Detour

Corporate Responsibility

Management & Directors

Contact Information

25

Initiating

Research Firm Analyst Target Price at

June 23, 2015

07.06.11 Haywood Kerry Smith $14.00

07.07.09 Paradigm Don Blyth/Don MacLean $18.50

07.08.07 Raymond James Phil Russo $18.50

07.11.26 National Bank Steve Parsons $16.50

07.12.20 Macquarie Mike Siperco $20.00

08.01.14 Canaccord Rahul Paul $18.50

08.07.14 TD Dan Earle $20.00

08.09.04 RBC Dan Rollins $19.00

08.11.06 BMO NB Brian Quast $16.00

09.06.17 Laurentian Killian Charles $16.40

10.05.19 CIBC World Markets Cosmos Chiu $16.50

10.07.22 Credit Suisse Anita Soni $17.50

13.04.16 Scotiabank Trevor Turnbull $19.00

13.08.14 Desjardins Michael Parkin $17.50

13.11.12 Beacon Securities Michael Curran $14.75

13.12.09 GMP Securities Ian Parkinson $10.20

14.02.06 Cormark Securities Richard Gray/Tyron Breytenbach $20.00

14.04.22 Goldman Sachs Andrew Quail $17.00

14.06.17 Dundee Capital Markets Joseph Fazzini $17.00

14.09.03 Morgan Stanley Brad Humphrey $15.25

Average target C$17.11

Analyst Coverage (20)

26

1. Conversion price for the Notes is US$38.50.

2. Cash and short-term investments at March 31, 2015.

Shareholder Information

Paulson & Co.

>80% INSTITUTIONS TOTAL 9.8 M Share options

13.0 M Convertible notes 1

193.4 M FULLY DILUTED

170.6 M Issued & outstanding

Share Structure (03/31/2014) Top Shareholders

13%

C$2.5

6

BILLION market cap US$118.1

3

MILLION cash position2

Share Structure (May 31, 2015) Top Shareholders

27

Q1 2015 Operational Results

Q1’14 Q2’14 Q3’14 Q4’14 Q1’15

Ore mined (Mt) 4.88 2.89 4.20 4.30 3.82

Waste mined (Mt) 14.29 16.11 14.71 15.39 15.97

Total mined (Mt) 19.17 19.00 18.91 19.69 19.79

Strip ratio (waste:ore) 2.9 5.6 3.5 3.6 4.2

Mining rate (tpd) 213,000 209,000 206,000 214,000 220,000

Ore milled (Mt) 4.08 4.42 4.53 4.71 4.30

Mill grade (g/t Au) 0.90 0.91 0.88 0.85 0.84

Recovery (%) 91 91 90 91 91

Mill throughput (tpd) 45,282 48,569 49,186 51,142 47,797

Mill operating time (%) 80 83 81 83 78

Mechanical availability (%) 84 86 83 85 89

Ounces produced (oz) 107,154 117,366 115,344 116,770 105,572

Ounces sold (oz) 84,560 107,206 106,334 124,913 104,497

28

Q1 2015 Financial Results

Key Financial Statistics (US$ M, unless noted)

Q1’15

Metal sales $127.4

Production costs $97.7

Depreciation & depletion $36.9

Loss from mine operations ($7.2)

Loss from operations ($15.5)

Loss/Adjusted net loss1 ($63.1) / ($23.5)

Basic Loss & Adjusted basic loss

per share1 ($0.38) / ($0.14)

Cash & short-term investments2 $116.4

1. Refer to the section on Non-IFRS Financial Performance Measures on slide 3 of this presentation.

2. HST refund of $12.3 M expected in Q2 as a result of the Q1 equipment finance leases repayment.

29

Effective December 31, 2014 Tonnes (Mt) Grade (g/t Au) Contained Gold (koz)

Reserves

(1,2,3,4,5)

Detour Lake Mine Proven 94.2 1.25 3,795

Probable 364.6 0.95 11,146

P&P 458.8 1.01 14,941

Stockpiles 0.7 0.74 16

Total P&P 459.4 1.01 14,957

Resources (1,3,4,5)

Detour Lake Mine Measured (M) 16.4 1.37 725

Indicated (I) 65.9 1.01 2,150

M+I 82.4 1.09 2,874

Block A Measured (M) 1.5 1.21 57

Indicated (I) 52.5 1.15 1,934

M+I 53.9 1.15 1,991

Total M+I 136.3 1.11 4,866

Detour Lake Mine Inferred 19.1 0.75 463

Block A Inferred 2.5 1.23 99

Total Inferred 21.6 0.81 562

Detour Gold: Reserves & Resources

1. Mineral reserves calculated using a gold price of US$1,000/oz; mineral resources calculated using US$1,200/oz. Foreign exchange

rate of C$1.03 to US$1.00 (refer to the “Detour Lake Mine NI 43-101 Technical Report dated February 4, 2014).

2. Mineral reserves estimated using a 4% dilution at 0.20 g/t Au and 5% ore loss.

3. Based on an elevated cut-off grade of 0.5 g/t Au for Detour Lake and cut-off grade of 0.6 g/t Au for Block A.

4. Mineral resources are exclusive of mineral reserves. Mineral resources that are not mineral reserves do not have demonstrated

economic viability. Mineral reserves and resources are compliant with CIM definitions.

5. Totals may not add due to rounding.

30

Detour Lake & Block A

US$1,000/oz

US$1,200/oz

15.0 Moz

@ 1.01 g/t Au P+P

2.0 Moz

@ 1.15 g/t Au M+I

~5.5 km

Current

North

Pit

Note: Mineral reserves and resources as of December 31, 2013. Refer to February 2014 Technical Report.

31

Lower Detour Area

630 km2

Exploration Focus: Lower Detour

Block A

Resource

Detour Lake

OP Mine

32

Lower Detour Drilling Program

33

Lower Detour Drilling Program

34

Lower Detour Drilling Program

35

Responsible mining is more than a commitment

- It’s what we do every day

Our commitments to

community benefits are

being realized and will

grow as the mine matures

Steady state operations

allows us to report on our

operational, environmental,

and social impacts.

Our first CSR update has been published and is available on

our website

Our Life Saving Rules help raise the visibility of safety to

ensure everyone on our site goes home safely

Corporate Responsibility

MAINTENANCE

LABOUR

18%

36

Paul Martin President and CEO

Pierre Beaudoin COO

James Mavor CFO

Drew Anwyll Sr VP Technical Services

Julie Galloway Sr VP General Counsel &

Corporate Secretary

Derek Teevan Sr VP Corporate &

Aboriginal Affairs

Jean-Francois Metail VP Mineral Resource

Management

Rachel Pineault VP HR & Aboriginal Affairs

Jim Robertson VP Environment &

Sustainability

Charles Hennessey Mine General Manager

Andrew Croal Director Technical Services

Laurie Gaborit Director Investor Relations

Alberto Heredia Controller

Bill Snelling Director Corporate Systems & Controls

Lisa Colnett

Robert E. Doyle

André Falzon

Alex G. Morrison

Jonathan Rubenstein

Graham Wozniak

Ingrid Hibbard

Michael Kenyon

Paul Martin

Management & Directors

Management

Directors

37

Laurie Gaborit Director Investor Relations

Email: [email protected]

Phone: 416.304.0581

Paul Martin President and Chief Executive Officer

Email: [email protected]

Phone: 416.304.0800

www.detourgold.com

Contact Information