DEVOLL HYDROPOWER PROJECTPresentation for Dambyggerforeningen
08.10.2015
Layout of the project
2
3
Banja and Stepanje village
Banja HPP
4
5
Banja HPP layout
6
Dam structure from first phase
7
Grouting gallery
Core
CofferdamSupport fill (river gravel))
Filter
8
Cross-section of Banja dam
9
Existing structure about 4.1 mill m3
New structure about 4.5 mill m3
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
Resources and quantitiesPersonnel - concrete – dam fill
Project amount(m3)
Placed amount(m3)
Remaining amount(m3)
% completed
4 458 600 4 070 500 388 000 87 %
30
Locals Expats Total
838 125 963
BoQ Actualquantity Total completed Completion
81 550 143 300 116 670 81 %
www.statkraft.com