Upload
others
View
5
Download
1
Embed Size (px)
Citation preview
Development of Large Bore High Pressure Subsea HIPPS Valves
Chris Williamson Engineering Director BEL Valves
Overview
• What is a High Integrity Pressure Protection System (HIPPS)
• Drivers for using Subsea HIPPS
• The HIPPS valve as a key project technology enabler
• Technology Stretch
• Design Parameters
• The Qualification Journey
What HIPPS Does
• Exploits the difference
between
-Shut-in Pressure
-Flow Pressure
• Permits the downstream
flowline to be de-rated to a
lower level of pressure
• Protecting it, sensing over
pressure and shutting down
the overall system quickly
P2
P1
Final Element
Generic Subsea HIPPS Schematic
P1 P2
Logic
PT PT PT
PT PT PT PT PT
Final Elements
Logic Solver
Sensors
By-pass
Valves Chemical Injection
Test Valve
PT PT Gate Valve
A HIPPS Final Element
Drivers for Implementing Subsea HIPPS
• Fully pressure rated flow-lines not feasible
– manufacturing / installation limitations
• Use HIPPS to provide required risk reduction
• Commercial drivers define HIPPS Integrity level
• Safety is managed by flow-line fortification not by HIPPS
Additional riskreduction required
Target mitigated risk
Initial design
Existing mechanical protection e.g tree valve, ESDV
Final design
Ris
k
Technology Stretch
XHP Subsea
Valve Supply
Typical Manifold
Subsea Valve
Supply
Pressure (PSI)
No
min
al S
ize (
In)
HIPPS experience
HIPPS
Future
15,000 20,000 10,000 5,000
2
8
14
20
HP Subsea
Valve Supply
Oseberg A
Shah Deniz II
Rhum
Jura
Bardolino Penguins
Juno
Kingfisher
Devenick
Shearwater
Erskine
Mallard
Zakum Gas
Jade
Mobile Bay
Kashagan
Shah Deniz
Gulfaks
Tweedsmiur
• SIL 3 Capable (3rd party TUV Certification required)
• Valve must close on demand
• Valve must close in time required
• Valve leakage shall be minimised
• Integrity maintained over 30+ years field life
• Through conduit gate valve choice for Subsea HIPPS
• Horizontal or vertical Installation
Valve / Actuator Criteria
Large Bore HIPPS Valve Parameters
• Through Conduit Gate Valve
• Weight 18 Tonnes
• 10” (254mm) Full Bore
• Height 3.4m
• Shut In pressure 990 Bar
• Fail-Safe-Close
• Closure Time <15 seconds
• Water depth 660m
• Early life gas flow 163m3/s
Materials
9
• F22 forged body & Bonnet
• Fully clad alloy 625
• Alloy 718 trim
• HVOF Tungsten Carbide hard facing
Testing Summary
• Extended PR2 (600 cycles)
• Hyperbaric (660m)
• Open compensator testing
• Primary Qualification Scope
• Closure time testing
• SIL Certification
Extended API 6A PR2 Pressure Temperature Cycling
TEMP
100oC Max
Room
-29oCMin
TIME
450 Ambient Cycles
75 Cycles at Max Temp
75 Cycles at Min Temp
Apply Pressure
Hold Pressure For 1 Hr
Hold Pressure For 1 Hr
Release Pressure
Apply Pressure Release
Pressure Hold Pressure For 1 Hr
Hold Pressure For 1 Hr
Apply Pressure
Release Pressure
Strip Valve and Inspect
• Extended from 200 to 600 cycles
System Closure Time Testing
• Aim, to confirm as a system required closure times could be met
– Conducted in Hyperbaric chamber to mimic the affect of hydrostatic head
• Testing confirmed 15s closure time target achievable
Actuator
Valve
PT
N2
Test HPU
LV
DT
Simulated tubing and coupler restrictions
• Minimise hydraulic fluid swept volume
• Use of variable orifice damper
• 250mm diameter piston
• 21L swept volume to exhaust in <15 seconds, against seabed pressure
• Open & Closed Pressure Compensation
Valve Closure (Dynamic Balance)
Valve Closure (coupled analysis)
• Accelerate / Decelerate 1.5T gate and drive train
Status as of End of February 2015
• Valve/Actuator Qualification including PR2 - completed
• System closure time testing (inc QEV) - completed
• SIL Certification Final Report Pending
• Production valves
in manufacture
Thank You
This presentation must not be used or reproduced without written permission from BEL Valves Ltd