18
- , )

DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

­,)

Page 2: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEHIGHWAY PAVEMENTS IN THE UNITED STATES" "

..,.by

I. J. Taylor(l) andW. J. Eney(2)

The first .concrete pavements .constructed in .the United

States consistedofcotj.crete blocks approximately six fee·t sqj.1are

and six inches thick.

Success with these firstex~.erimentsencouragedfurthe~

research .to develop abetter design and to improve construction

methods .. Pavement block dimensions were increased and .steelre-

inforcement_wa,s added fQr structural strength. Granular materials

were used to support these larger slabs and to provid~ better

drainage and insulation. Paving.machinerywas developed to speed

up the paving ,operations. By 1935 a major pqrtion of the t:lew

higl'!-ways designedfQr heavy vehicular loading were ofconcr.ete slab

cons trllc.tion.

During .the past few years jointed pavement se~tions have

'increased in size until slabs ten inches thick,. twelve feet~ide

(1) 1. J. Taylor ~. Instruments Assqciateat Fritz .Engineering Lab­oratory, Lehigh University, Bethlehem, Pa. U.S.A.Continuous Pavements Pr~ject Director.

(2) W. J. Eney - Head of Civil EngineeringDepart~ntand pirectQrof Fritz Engineering La1:>oratory, Lehigh UniversityContinuous Pavements Consultant.

Page 3: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

and one hundred feet long are not uncommon, Various connecting

devices installed between adjoining slabs and adjacenttraf£ic

lanes help facilitate load transfer and permit thermal expansion

and contraction of the individual slabs,

While this form of pavement construction has proven

quite successful, and .at present is an accepted standard for

highway pavements throughout the United States, it is not bel~eved

to be the optimum design for reinforced concrete pavements.

Highway engineers found that the random cracks which

often occurred within the longer reinforced pavement slabs did n,ot

become a maintenance problem if adequate reinforcement had been

used. While theee cracks responded slightly to thermal expansion

and contraction, they did not open to objectionable width during

cold.weather or fail under traffic loading.

This led to the theory that pavements withade.quate

continuous longitudinal steel .reinforcement could be constructed

without prepared joints, The concrete shrinkage and the tempera­

ture induced strains would cause very narrow transverse cracks

to occur at frequent intervals but the steel reinforcement would

maintain longitudinal continuity and li~it the wi,dthof the crB:c:ks.

In theory, this type of ,construction results in ac:on­

tinuous semi-flexible slab, capable of withstanding ,normal climatic

and vehicular loading conditions, The elimination of the often

troublesome transverse joints reduces maintenance costs and provides

Page 4: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

a smoother, safer riding surface for the motorist.

In September of 1938, near Stilesville, Indiana,

several sections of continuously reinforced concrete pavements

were constructed. This experimental project,under the super=

visi."· of the Indial1a State High,way Department and the u. S.

Bureau of Public Roads, was planned to investigate a large

number of·designv~riables, .Several .sizes and types of long­

itudinal steel reinforcements were usedin9~7-9=inch.thickened­

edge pavements 20 feet wide.with, a total length.of three miles,

The quantity of reinforcement was varied in selected .sections

to comprise from 0.07 to 1.82.pe.rcent of the cross-sectional

area. All of th~ pavement .:was placed on compacted native soil

without .the use of a special base course. Diffe~ent.types of

contraction-expansion joints were installed at th~ends of in­

dividual test sections in ..order to. evaluate their comparative

performance,

A complete record was maintained of the .construction

.operations and provisions were made to permit the measurement

of future dimensional changes in the pavement .

.After twenty years of service, this heavily traveled

four=lane pavement.remains in good condition. Maintenance costs

have been moderate andth,e qualitY,of the riding surface is

excellent, when compared.with conventional jointed pavements of

equal age and service.

-3

Page 5: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

The continued good performance of this first experimental

pavement has been.an important factor in maintaining .interest in

the use of continuous reinforcement as a means of building better

highways,

During the period of World War II, research and construction

.of highways for civilian use dropped far behind the post=war needs.

By 1946 most of the existing roads were in need of repair and the

increased traffic indicated a definite need for improved highway

design to meet the demands of modern vehic1eso

In 1947, the states of Illinois and New Jersey each con­

structed experimental pavements using the continuous reinforcement

design. Similar pavements were constructed in California in 1949

and in Texas in 1951.

Each of these testl pavements was designed to take advantage

of the information obtained from previous experiences. By 1956,

when the state of Pennsylvania planned the construction of two

experimental continuously reinforced pavements, many general de*

sign limitations had been established.

Most pavements containing less than 0.20% longitudinal

steel reinforcement had developed wide cracks in cold weather.

Under heavy traffic loads the steel at some of these cracks had

failed within a few years, resulting in excessive pumping at the

faulted jointso Where the reinforcement had been 1.0% or greater,

the cracks were more numerous but had remained very narrow and

=4

Page 6: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

had not shown any evidence of progressive deterioration.

All of the expansion .and contraction devices which were

used had shown some degree of .weakness. The conventionaldolotel

type joints were unsatisfactory, failing tQ function properly when

subj.::ctedto the greater end .movements()f long ;continuously rein-

for~edpavement sections .

. The optimum pavement thickness had not been fully estab-

lished. It appeared that the percentage of steel reinforcement

would be the major fa,ctor in the prevention of pavement damage at

contraction cracks, even in pavements six o.r seven incq.es thick.

In planning the experiments in Pennsylvania, it was

decided that, .inaddition to other measurements and observations,

a thorough investigation would be m~de of the transverse cracking

.process and the effects of these cracks upon. the steel andlconcrete

in their immediate vicinity. The:Fritz Engineering Laboratory at

Lehigh University, under contracts with the United States Bureau

of Public Roads, the Pennsylvania Department of Highways and.the

American Iron .and Steel Institute was assigned.this portion of the

project.

The first.conUnuouslyreinforced pavement in Pennsylvania

.was'.constructedon .U. S. Route 111 betw:een Harrisburg, Pa .. and

Baltimore, Md. in .the fall of 1956. It consisted of four traffic

lanes, each twelve feet wide, with a twenty foot wide median

strip separating the North and South~bound double lanes. Each

-5

LJ.. ,.... :'. :t ,'i..'. :,: J... L __ ,

:.d

Page 7: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

nine-inch thick lane was constructed separately and was supported

on a six-inch thick granular base course. The 0.48 percent longi­

tudinal reinforcement was placed at pavement mid-depth and con­

sisted of bar-mats sixteen feet long as shown in Fig. 1.

The second pavement was constructed in the summer of

1957 on U. S. Route 22 between Harrisburg, Pa. and New York City.

The design was identical to that on Route 111, except that a pave­

ment of seven, eight and nine- inch,es thickness was constructed

,upon granular bases of three or six-inch thicknesses. ,,' Also~a

short section was reinforced with welded wire mesh instead of

the convent~ona1 bar-mats.

Both experimental pavements were approximately two miles

in length and were terminated at each end with finger~type bridge

expansion joints which separated the experimental sections from

the adjacent jointed pavements and permitted complete freedom of

longitudinal movement at each end.

During construction,e1ectrica1 gages were installed at

selected locations to measure longitudinal strain in the steel

reinforcing bars and in the concrete. (Fig. 2). Resistance wire

temperature transducers were inserted in the sub~base, granular

base course and concrete pavement to determine seasonal tempera­

tures and vertical temperature _~gra:da.tions. Arrangements were

made to enable the measurement of crack widths and pavement warp­

ing adjacent to the cracks. All electrical gage lead wires were

-6

Page 8: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

placed under the pavement and terminated at a junction box near the

edge of the highway. Fig. 3.

To insure that cracks would occur at the exact locations

of the instrument installations, transverse planes of weakness were

induced in the pavement. This was accomplished by inserting a thin

metal strip transversely across the lower pavement depth prior to

the placing of the concrete. Fig. 4. Cracks developed at these

artificial planes of weakness within 48 hours after construction.

Readings taken from the electrical and .mechanical gages

immediately after the test area was paved provided the basis for '

subsequent measurements.

,During the first two days after construction and until

the instigated crack had developed, measurements were taken every

two hours. After this, measurements were taken weekly for a month

and then only once each month until the present time. The schedule

of monthly readings will probably continue for three years or until

the pavement stabilizes and responds, within a predictable pattern,

to yearly temperature cycles.

Although .the magnitude' of the periodic measurements varied

at individual test sections, the general behavior pattern at all

instigated cracks was very similar. Stresses in the pavementre­

mained low during the first two days after construction. As the

concrete began to cure and develop a stronger bond with the rein-

hi_-ci.ng .st8,,~1, shrinka?;c stresses in the concrete were transfered

-7

Page 9: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

to the steeL Continuing shrinkage and daily temperature cycling

produced sufficient tensile stress in the pavement to ca\,lse trans­

verse .cracks to form; first .at the induced plane of ,weakness and

later at random intervals throughout the length of the pavement.

Colder winter temperatures caused these cracks to open wider and

some new cracks to occur in the longer uncracked sections. After

approximately one week, temperature became the major influence in

the behavior of the pavement, with crack widths and strain ,in the

·reinforcing steel responding directly with changes in seasonal

temperature. This very close relationship is graphically evident

in Fig. 5.

After one year of service all of the experimental pave­

ments in Pennsylvania are in very good condition. No longitudinal

cracking .has occurred, and the normal transverse cracks have not

opened to excessive widths. The results of previous research com­

bined with information .obtained from.the current field .tests pro­

vide th~ basis for the following conclusions:

1. Continuous concrete pavements with, 0.5% .steel reinforce­

ment develop a pattern of transverse cracks with average spacing

.of approximately fourteen feet. These cr~cks open to a maximum

width of ,03 inch when the air temperature is zero degrees Fahren­

heit and close very tightly when the temperature reaches 80 degrees.

2. The crack pattern depends more upon the percentage of

steel reinforcement than upon pavement thickness. There was no

significant difference in .the crack pattern.or crack width in the

-8

Page 10: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

seven, eigb,t and nine=inch pavements.

3. If less than 0.5% st~e1 reinf~rcemeqt is used,the

distance between cracks will be greater and the crack openings

proportionally wider as the amount ·of longitudinal .reinforcement

is n.duced. Sonte yielding .of the steel will OCClJr at the cracksI

duringco1dwe'a'ther and damage to the pavement may result from

heavy traffic loads.

4. Theresu1 ts ,of field ,tests indicate that an eight ""inch

thick pavemE!nt with 0 . 7% longitudinal steel reinforc.ement ,may be

the optimum practical p'av-emertt design; considering ,durability an~

e~onomy. Atb,ree-inchth~ckgranular base.course on compacted,

we1i drained native soU appears to offer a suitable f~undation

for this type of pavement.

5. Continuous pavement sections may be constructed to any

desired length, but ,the continuity o.f ~he reinforcing ste¢l must

be car~fully.maintained thr(),l:Jghouteach secti.on. . When the ,con-

tinuity of. the pavement :mustbe interrupted" it: is necessary to.

install an expansion join,t. capable of permitting .. two inches of

movement at the free.end.

6. Construction costs of continuouslyreinforce~pavement:s

compare favorably with those of conventional jointed d~signs~

Lowermaintenancec()l:lts th..roughout the life of these pavements~.

should give them a significant economic advantage.

-9

Page 11: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

·His believE!d that continuing research and development

will establish continuous pavements as the accepted design for

fut\lrehighways.

ACKNOWLEDGEMENT

The research program .currently under way at the Fri.tz

.Engineering,Laboratory of Lehigh University is sponsored by the

United States Bureau of Public Roads and th~ Pennsylvania Depart-

mentof Highways. The authors are particularly indebted to the

following ,men for their cooperation and assistance:

Mr. Harold A, Allen,

Mr. H., D. Cashell,

Mr. RobertA. Farley,

Mr. FrankC. Witkoski,

Chief of Physical ResearchDiv:':",'ision,United States Bureau ofPublic Roads.

~ection Chief of Rigid PavementDesign, United States Bureau ofPublic Roads.

Ch~ef Engineer, PennsylvaniaDepartment of Highways

Direc tor of Research, PennsylvaniaDepartment of Highways.

Page 12: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

-oE

BarsillIt.. of Pavement Lan e

tII

4 11 -4 2I+- -.l 4 11

21-81/~8I/Min. Lap of Transverse41l~2"-. ~8 Spaces @

. ~ 7"= 41

-811

1 IIII 6- 2 .2 t1~-------~-

End to End

=1~ 0 1:O 1'­

- 0m V J

BAR-MAT REINFORCEMENT(9 INCH PAVEMENT)

FfGURE NO; I

Page 13: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

,,-1 SR-4 gage•

GAGE POSITIONS IN TEST SECTION - YORK, PA.

'--7E.~ .~

I

1---===---------Z-8/7----1-5-a-16~t4I4~~2~1--:O:"~J~"r-z-z---------===---I

I. I

I1,- 2 SR -4 gagesI" .. -

TemperatureCompensatingPlates

I 4' - a" Il.....j...f--------1II1/5 a 6 /17. -11"--'--:l'ji- Whitt emore Plugs

• I •I , ..

16 - a

FIGURE 2

Page 14: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

Figure 3

Taking ,electrical gage readings at terminalbox placed near edge of pavement.

Figure 4

Steel reinforcing ,mat in position, withtransverse metal strip to cause crack atexact location of installed electrical gages.

Page 15: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

NO. 340R -20 DIETZGEN GRAPH PAPER

20 X 20 PER INCHEUGENE DIETZGEN CO.

.... "'OE ' .... u.s'"

80

380

25

0 ,! ! I t ;,. >VI. ~ .... I I

~~ r

t ,: '" I__ L_ I_~-

,~~~~..... . -1-.--- - -+--. - . 1--- -- I- . . _.-

~Tt~FI ~, I I llR! , R ~IIV' it-i . ( ~TP;~d I. ~ ~AdK, rn..H - \ . ~ It-

O~

I ~,, I _·L. '"', IV\, / \. I !-I , , .,

I ./ .. ... \~-

---~ I~ '-- '-iT I--.+--- -t ~~ t·- ._,.[%' r~

-I I ! , '.1 t ~Vl: It;<~ .bt .1 j

I, ! \ i ... - 1':- "' .. I0 I \

__ I --c--~. 1c;, tV\;.

Z , ..'(/) _~_L - ,-ru - I

- - -

I.J

_~4_ ••_-1-.

\,

I~ / " I " I . '0 I I

0 - I

(!) /1, I \

~-+-I· I " IV\, - }-w I 0 I

--~-\ ..

\ -I,'0' - ----- --,--- 1-- f-:--'

".2 -- \

~/ i I \.

I:n ; I ,,, .... ,1 I

...,-

I i , I .\ T) .vv , ..j II

I __ .~ : -_-L \ .I-L- • I--J-_.- ---1-\ --f--- -- I--- ----t-.-, I ! I \ I . I \ I I

/1,

I0 I .. \ I

~.. I --L v/t "', '101 V V .i II , ......... ! ,'a I I. - ;- - -. - --T ........ • I .~'~r-I -.----- ;'-.,

.. .......I --+- -T

0I ~ .

:>0 I IW' , ..

290) _ .. 4 0 SQ _; '. ! e.:-Q_ 21~.Q.- _,241 0 2c,0 ! 3 0 '3'~O !SO :> 4:> 'S0 . I >0 I~O -200 .2 0 320 '360 l3i, '-... - r c. t - - -+ ---

I 0 ~YSi FROU ("ON STF ucnON .. DA 's FRPM C( NS PRlJCT1 ON I i

( 410 eo ! I 0I I )0 200 2~01 280 "3 ~o' 3~0 ~e( .) 40 'eo: PO f~O 200. ,2 ~o 280 320 ~OII

, + ~oo -- ..I - .. ... .. ..'.- ..

IU vvv(/)

, : v .... -"l .I 1

I •I '.- _. ...hI. __ _.-...:-. -I" - _.

-~6- -r- . -:r"K WI OT~ \ ST ~A0 : I 1 ~ SI ~E N

uuv ~. I W'

(/~-A1I ~ . \. r-..,...,I ...• -ft...: _. f- I fA\I 'Ia' f,. U r ;Kr~ -" ----,-- -

0 /, .................. ' EF:A(,E) J \ " -J I'V I~I

0::. /, IOvvv ~, I 1', , l"'V\"l . ~ '( AV t=.Q 1\(. E)

-~-+, I " \ ....,

+~--/ I I ~ I' ~

, :\

5 ............ I I ' .... -- • : \ .. /1"'...,...,

/l t- "\ I ') v .... 0 , .. ~ ..i I 0::' \. /1/ '" ;

--~ - - ~ - -,I I .. j ~ ,

! I I ,f, \ ~ "10 vv~ I

~I ! - ... _..f-_ '--- '1 PV' .... ./ ,

-tlf- r--e- '-- .' '--!''--1- _. --e-

1~11 15

, -1__.

r""\'~ t- -J, IQV\

-. , .L.,~- I

I- .

; ~ -. ;t .",... -, .. - ~,r 1+ • . ,

..., -;;I,QV\,

2

7

6

5

4

2

8

FIGURE 5

Page 16: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

,

Figure 6

Resistance wire strain gages were attacheddirectly to the reinforcing steel and madewater-proof by a coating of vulcanized rubber.

Figure 7

A general view of the paving .operation

L _

Page 17: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

Figure 8

Frequent testing of the concrete used in thepavement construction assured a uniform mixtureof known properties.

Figure 9

Steel reinforcing mats were placed at thevertical center of the pavement betweentwo separate layers of concrete.

Page 18: DEVELOPMENT OF CONTINUOUSLY REINFORCED CONCRETEdigital.lib.lehigh.edu/fritz/pdf/256_5.pdfto be the optimum design for reinforced concrete pavements. Highway engineers found that the

,

(

Figure 10

Gage measurements were taken throughoutthe early curing period of the pavement.