4
47 JR EAST Technical Review-No.37-2017 S pecial edition paper In light of the derailment of Shinkansen cars in service in the 2004 Mid Niigata Prefecture Earthquake, JR East has been conducting R&D on and measures for prevention of Shinkansen derailment in earthquakes. at included development of the following preventive measures against derailment in earthquakes for tracks. (as of April 2017) (1) Aseismic glued insulated joint rails (installation completed) (2) Rail rollover prevention devices for slab tracks (under construction) (3) Rail rollover prevention devices for ballasted tracks (development completed) (4) Rail rollover prevention devices for solid bed track with resilient sleepers (development completed) (5) Removal of expansion joints (under construction, considering expanding the range of those subject to removal) Development is completed for rail rollover prevention devices for slab tracks, and installation of those is underway. Development is completed for rail rollover prevention devices for ballasted tracks as well, and a decision has been made to introduce those starting in fiscal 2017. is paper will thus report on development of rail rollover prevention devices for ballasted tracks. 2. Measures to Prevent Shinkansen Deviation from Rails and Derailment in Earthquakes One reason major damage to derailed cars was avoided in the Mid Niigata Prefecture Earthquake was that underfloor equipment and wheels sandwiched the rail, and the cars continued moving forward guided by the rails. On the other hand, rail fasteners were destroyed by the derailed cars, and the tail car lost the “guides” keeping it on the track, allowing it to escape to the adjacent track side (Fig. 1). is demonstrated that cars could be guided until they safely stop if rails function as running guides, so a measure for actively using rails to prevent cars from escape the track was thought up. 1. Introduction Development and Installation of Rail Rollover Prevention Device for Ballasted Track as a Shinkansen Earthquake Derailment Countermeasure * Technical Center, Research and Development Center of JR East Group ** Track maintenance Division, Engineering Department, Tokyo Branch Office of JR East (formerly at Technical Center) A Shinkansen train operating at 200 km/h was derailed by the Mid Niigata Prefecture Earthquake in 2004. As a measure at the wayside against Shinkansen train derailment, we developed a “rail rollover prevention device”, which could prevent rail rollover or large lateral displacement even if rail fastenings were broken. In this report, we give a summary description of the rail rollover prevention device for ballasted track. We validated rail rollover prevention performance, impact durability performance and electrical insulation performance, confirming that performance requirements were satisfied. Abstract Keywords: Earthquake, Derailment, Rail rollover prevention device, Ballasted track Toshiyuki Konishi * Takao Kumamura ** Marika Itakura * Fig. 1 Derailed Train Fig. 2 L-shaped Guide Lead car Rear Fig. 3 Guidance by L-shaped Guide Impact load Allowable lateral movement 225 mm 225 mm PC sleeper L-shaped guide

Development and Installation of Rail Rollover …...The rails must not roll over from this load and lateral movement must be kept under a certain amount so derailed cars do not deviate

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Development and Installation of Rail Rollover …...The rails must not roll over from this load and lateral movement must be kept under a certain amount so derailed cars do not deviate

47JR EAST Technical Review-No.37-2017

Special edition paper

In light of the derailment of Shinkansen cars in service in the 2004 Mid Niigata Prefecture Earthquake, JR East has been conducting R&D on and measures for prevention of Shinkansen derailment in earthquakes. That included development of the following preventive measures against derailment in earthquakes for tracks. (as of April 2017)

(1) Aseismic glued insulated joint rails (installation completed) (2) Rail rollover prevention devices for slab tracks (under construction)(3) Rail rollover prevention devices for ballasted tracks (development completed)(4) Rail rollover prevention devices for solid bed track with resilient sleepers (development completed)(5) Removal of expansion joints (under construction, considering expanding the range of those subject to removal) Development is completed for rail rollover prevention devices for slab tracks, and installation of those is underway.

Development is completed for rail rollover prevention devices for ballasted tracks as well, and a decision has been made to introduce those starting in fiscal 2017. This paper will thus report on development of rail rollover prevention devices for ballasted tracks.

2. Measures to Prevent Shinkansen Deviation from Rails and Derailment in Earthquakes

One reason major damage to derailed cars was avoided in the Mid Niigata Prefecture Earthquake was that underfloor equipment and wheels sandwiched the rail, and the cars continued moving forward guided by the rails. On the other hand, rail fasteners were destroyed by the derailed cars, and the tail car lost the “guides” keeping it on the track, allowing it to escape to the adjacent track side (Fig. 1). This demonstrated that cars could be guided until they safely stop if rails function as running guides, so a measure for actively using rails to prevent cars from escape the track was thought up.

1. Introduction

Development and Installation of Rail Rollover Prevention Device for Ballasted Track as a Shinkansen Earthquake

Derailment Countermeasure

* Technical Center, Research and Development Center of JR East Group

** Track maintenance Division, Engineering Department, Tokyo Branch Office of JR East (formerly at Technical Center)

A Shinkansen train operating at 200 km/h was derailed by the Mid Niigata Prefecture Earthquake in 2004. As a measure at the wayside against Shinkansen train derailment, we developed a “rail rollover prevention device”, which could prevent rail rollover or large lateral displacement even if rail fastenings were broken. In this report, we give a summary description of the rail rollover prevention device for ballasted track. We validated rail rollover prevention performance, impact durability performance and electrical insulation performance, confirming that performance requirements were satisfied.

Abstract

•Keywords: Earthquake, Derailment, Rail rollover prevention device, Ballasted track

Toshiyuki Konishi*Takao Kumamura**Marika Itakura*

Fig. 1 Derailed Train Fig. 2 L-shaped Guide

Lead car Rear

Fig. 3 Guidance by L-shaped Guide

Impact load

Allowable lateral movement 225 mm

225 mm

PC sleeper

L-shaped guide

Page 2: Development and Installation of Rail Rollover …...The rails must not roll over from this load and lateral movement must be kept under a certain amount so derailed cars do not deviate

48 JR EAST Technical Review-No.37-2017

Special edition paper

A policy was thus adopted at JR East to introduce “L-shaped guides” for cars and “rail rollover prevention devices” for track and prevent the spread of damage at derailment by the two measures functioning together.

L-shaped guides are inverted L-shaped devices attached to the gear boxes of bogies (Fig. 2), designed to guide cars by the rails in case of derailment. They are attached to all commercial trains operating in JR East’s Shinkansen sections. In order for those L-shaped guides to function effectively, rails need to be secured on the track and rollover and large lateral movement of rails need to be prevented. We therefore decided to install on the track rail rollover prevention devices, which prevent large lateral movement and rollover.

3. Performance Required in Rail Rollover Prevention Devices

The following performance requirements must be satisfied by rail rollover prevention devices.(1) Rail rollover prevention performanceRails receive loads from derailed wheels or from derailed cars via the L-shaped guides. The rails must not roll over from this load and lateral movement must be kept under a certain amount so derailed cars do not deviate from the track (wheels do not fall from sleepers, etc.) (Fig. 3). With ballasted track, lateral movement must be kept to within 225 mm. Load in horizontal directions applied to rails by Shinkansen cars in an earthquake is prescribed to be 200 kN as a result of studies based on relatively hard support stiffness assuming slab track.1)

(2) Impact durability performanceThe wheels of derailed cars will run over the rail rollover prevention devices. The rail rollover prevention devices must not break due to that, and rollover prevention performance must be maintained. We confirm durability of rail rollover prevention devices at time of impact by impact tests using actual bogies traveling at low speeds (60 km/h or slower), and we evaluate durability at impact by impact analysis for high speeds (up to 360 km/h). By comparing impact analysis results with those of actual bogie impact tests, we have confirmed that sufficient precision is achieved. (3) Electrical insulation performance Rail rollover prevention devices are metal devices installed to existing track, so there is a risk of them affecting track circuits. They therefore must have insulation resistance prescribed in design standards for railway structures2). The target value for leakage conductance in Shinkansen track circuits is 0.35s/km or less.

Electrical insulation required per 1 km R = 10.35⁄ = 2.86Ω/km (Shinkansen)

1

R=

1

r+

1

r+

1

r+ … +

1

r

n

r=

r = n × R = 1720 × 2.86 ≈ 4.9kΩ (n: number of sleepers)

As sleepers are parallel circuits in track circuits, from

R = 10.35⁄ = 2.86Ω/km (Shinkansen)

1

R=

1

r+

1

r+

1

r+ … +

1

r

n

r=

r = n × R = 1720 × 2.86 ≈ 4.9kΩ (n: number of sleepers)we know that insulation resistance per sleeper is

R = 10.35⁄ = 2.86Ω/km (Shinkansen)

1

R=

1

r+

1

r+

1

r+ … +

1

r

n

r=

r = n × R = 1720 × 2.86 ≈ 4.9kΩ (n: number of sleepers)

4. Development of Rail Rollover Prevention Device for Ballasted Track

Fig. 4 shows a rail rollover prevention device for ballasted track. With ballasted track, rail rollover prevention devices cannot be installed between rail fasteners as is possible with those for slab track where introduction is already underway (Fig. 5). So, by protecting all rail fasteners from the derailed wheels, load from horizontal impact is borne by rail fasteners’ resistance to tilting, and performance to prevent rail overturn and large lateral movement is secured by the entire ballasted track (rails + rail fasteners + PC sleepers + ballast).

For inside rail

For outside rail

Rail rollover prevention device

Rail fastener

Direction of travel

Fig. 4 Rail Rollover Prevention Device for Ballasted Track Fig. 5 Rail Rollover Prevention Device for Slab Track

Page 3: Development and Installation of Rail Rollover …...The rails must not roll over from this load and lateral movement must be kept under a certain amount so derailed cars do not deviate

49JR EAST Technical Review-No.37-2017

Special edition paper

Rail rollover prevention devices have a structure where fastening bolts of the rail fasteners are used to attach to existing PC sleepers in order to make installation work easier. They are also light enough to enable manual installation (approx. 6 kg each for both inside and outside rail). Shape meets the following requirements taking into consideration maintenance management after installation.

1) Improved visibility of spring clips2) Ability to adjust clip supporting wedges3) Water, dirt, etc. does not accumulate on fastening bolt part Also, the device was made to be a shape that allows judgment of fastening bolt looseness by Shinkansen track material

monitoring that is being studied for future introduction.(1) Rail rollover prevention performanceRail rollover prevention performance is confirmed by weight tests as shown in Fig. 6. In tests, we impacted rails with weights with the height from which weights were dropped set to that where impact forces would be the design load (200 kN for slab track). Weights were impacted against the side of the rail head, and the results of that are shown in Fig. 73). From the results, impact load on receiving side with all ballasted track rail fasteners fastened was 115 kN and rail head lateral displacement was approx. 26 mm. Displacement is within tolerance of 225 mm, so rail rollover prevention performance requirements were confirmed to be satisfied. (2) Confirmation of impact durability performanceImpact resistance performance was confirmed by impact analysis using non-linear dynamic analysis. Fig. 8 shows the analysis model. In analysis, we modeled Shinkansen ballasted track and Shinkansen cars and confirmed state of individual materials and behavior of wheels when derailed wheels impact rail rollover prevention devices.

In confirming impact durability performance, we studied durability with “continuous arrangement” where rail rollover prevention devices are attached to all sleepers as well as “discrete arrangement” where the devices are attached to every other sleeper and “intermittent arrangement” where they are attached intermittently to a certain number as shown in Fig. 9.

Fig. 10 shows an example of analysis results. We confirmed that with continuous arrangement where rail rollover prevention devices are attached to all sleepers, impact durability performance is achieved against wheels impacting at a speed of 360 km/h. On the other hand, more vertical movement of wheels is required to climb over the rail rollover prevention devices with discrete arrangement and intermittent arrangement, and the possibility of the devices being destroyed was high.

From those results, we decided to use continuous arrangement of rail rollover prevention devices.

(3) Confirmation of electrical insulation performanceWe confirmed that electrical insulation resistance met requirement of resistance to be 4.9 kΩ for Shinkansen ballasted track in all conditions—dry, rain, and fouled—prescribed in design standards for railway structures2). We then test installed on 1.3 km (one unit length of track circuit) of commercial track and confirmed effects on track circuits (Fig. 11).

In continuously investigating signal reception level fluctuation in sections where the devices are installed, we confirmed that rail rollover prevention devices do not affect track circuits by comparing before and after installation and comparing to adjacent lines. However, peeling and the like of some insulating material were confirmed six months after installing. We therefore gave the foot part and insulating material of rail rollover prevention devices a shape where peeling does not easily occur and changed to a structure where, on the chance that adhesion area does peel, insulating material does not fall or scatter (Fig. 12).

Drop height

Load cell

Buffer spring

Sleeper

Rail rollover prevention device

重錘

試験体

Intermittent arrangement

No rollover prevention devices are destroyed

Discrete arrangement

Continuous arrangement

None of the rollover prevention devices installed are destroyed

No damage to at least one of 12 locations

(Conditions) 連続配置 断続配置

Impa

ct lo

ad (k

N)

Rai

l hea

d di

spla

cem

ent (

mm

)

Impact load

Rail head displacement

Weight

Test sample

Continuousarrangement

Intermittentarrangement

Fig. 6 Overview of Weight Test

Fig. 9 Image of Placement of Rail Rollover Prevention Devices

Fig. 8 Impact Analysis Model

Fig. 10 Example of Impact Analysis Results

Fig. 7 Impact Loading Test Results (Testing done by RTRI)

Page 4: Development and Installation of Rail Rollover …...The rails must not roll over from this load and lateral movement must be kept under a certain amount so derailed cars do not deviate

50 JR EAST Technical Review-No.37-2017

Special edition paper

5. Rail Rollover Prevention Device Installation Plan

Table 1 shows the plan for future installation of rail rollover prevention devices. Measures for slab track implemented up to now will be expanded to ballasted track from fiscal 2017 with completion expected by fiscal 2029. In that, priority sections (Tohoku Shinkansen approx. 50 km, Joetsu Shinkansen approx. 150 km) are set based on the latest findings on active seismic faults with installation planned to be done by fiscal 2020.

6. Conclusion

We have confirmed that performance requirements for rail rollover prevention devices for ballasted track are met through various performance confirmation tests and test installation on commercial lines, and we have been gradually installing them since fiscal 2017. Into the future, we will continue pursuing R&D for Shinkansen earthquake derailment countermeasures with an aim of further improving Shinkansen safety and reliability.

Acknowledgements We have received much cooperation in this development from members of the “rail rollover prevention device working group” technical study group on Shinkansen derailment, including the Railway Technical Research Institute, JR companies, and concerned manufacturers. We would like to take this opportunity to express our gratitude to all those involved.

Reference:1) Takuya Teshirogi, Toshiyuki Konishi, Koichi Nomoto, “Shinkansen Jishin Dassen Taisaku-you Rail Tentou Boushi Souchi no Kaihatsu” [in Japanese],

Shinsenro ( June 2009).2) Railway Technical Research Institute, Design Standards for Railway Structures and Commentary (Track Structures) [in Japanese] Appendix 12.3) Takeaki Matsumoto, Yuichiro Hori, Masahiko Suzuki, “Development of a rail rollover prevention device for ballast track” [abstract in English]

Proceedings of the 19th Jointed Railway Technology Symposium ( J-Rail 2012) (2012).

For inside of track

Insulating material

Device foot

Sleeper

Fig. 11 Test Installation on Commercial Line Fig. 12 Improvement of Foot and Insulating Material

Line Section Track length [km]

Plan length [km]

Slab (installation complete) Ballast Total

Tohoku Shinkansen Tokyo - Shin-Aomori 1,352 967 (473) 80 1,047

Joetsu Shinkansen Omiya - Shimbashi 539 484 (103) 23 507

Hokuriku Shinkansen Takasaki - Joetsumyoko 352 103 (103) — 103

Total 2,243 1,554 (679) 103 1,657

Table 1 Rail Rollover Prevention Device Installation Plan