16
Head Office: UK Power Solutions Ltd, River View House, Bonds Mill Estate, Stonehouse, Gloucestershire, GL10 3RF Company Reg No. 06256696 VAT Reg No. 910 4276 54 CONFIDENTIAL - Revision 1.0 When printed this document becomes uncontrolled. Please ensure you refer to the latest version. All content and graphics are Copyright © 2016 UK Power Solutions Ltd. All rights reserved. Reproduction in whole or in part in any form or medium without express permission from UKPS is prohibited DEVELOPERS GUIDE (GAS)

DEVELOPERS GUIDE (GAS) - UK Power Solutions

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Head Office: UK Power Solutions Ltd, River View House,

Bonds Mill Estate, Stonehouse, Gloucestershire, GL10 3RF

Company Reg No. 06256696 VAT Reg No. 910 4276 54

CONFIDENTIAL - Revision 1.0

When printed this document becomes uncontrolled. Please ensure you refer to the latest version.

All content and graphics are Copyright © 2016 UK Power Solutions Ltd. All rights reserved.

Reproduction in whole or in part in any form or medium without express permission from UKPS is prohibited

DEVELOPERS GUIDE (GAS)

Introduction & Process

Responsibilities

Excavation for mains pipes

Minimum excavation requirements

Utility pipe and cable positions

Service positions and routes

Service pipe trenches

Meter box installation

General Advice

Plot Connection Request

Contacts

3

4-5

6

7

8

9

10

11

12-13

14

15

Contents

CONFIDENTIAL Revision 1.0 3

Introduction & Process

We will be installing the gas distribution infrastructure to ensure the new supplies you have requested are installed/commissioned to the required metering points. Once this infrastructure has been commissioned it will then become fully owned and maintained by the adopting Network Operator.

An approved design will be provided for you which will have been validated by the adopting Network Operator. It is essential that the elements of the installation that you are responsible for are

installed to the exact specification required on the design, failure to adhere to this could result in the commissioning of the new infrastructure being delayed and/or incurring additional costs, something we are very keen to avoid.

Finally, if there is any part of this project that you are unsure, unhappy or really pleased about, please don’t hesitate to contact us. In addition, we will also provide you with details of our Area Construction Manager should you wish to escalate any queries.

UK Power Solutions aim to provide the highest standard of customer service throughout the entire connection process providing the customer with a single point of contact at every stage of the project.

Smell Gas? To report a gas or carbon monoxide emergency, or if a pipeline is struck (even if no gas leak has occurred) call the National Gas Emergency Service 24 hours a day on 0800 111 999.

Tasks Customer UKPS

Request call off of service connections from UKPS

Provision of Meter Point Reference Numbers (MPRN’s)

Excavation and reinstatement of onsite pipe trenches

Supply and installation of onsite ducting and draw cord

Supply of meterboxes, preformed bends & gas warning marker tape

Installation of meterboxes, preformed bends & gas warning marker tape

Excavation of onsite joint bays

Supply and installation of gas pipe

The below table clearly defines who is responsible for the various tasks required for the installation of the gas services on your site, these may vary slightly if specifically requested at quotation stage. Please check your proposal to confirm or call your Project Manager to discuss.

MaterialsMains Pipe - We will arrange for the mains pipe tobe delivered ready for our teams to install. Pleasetake care of delivered pipe as if any pipes have cuts or scratches to a depth greater than 10% of their wall thickness then they must be discarded.

Requesting WorksOnce the main supply has been installed onto your site you will be able to call off any remaining mains pipe installation and service connections in line with your requirements.

Lead times for calling off work are:• Mains pipe installation – 20 working days• Service connections – 15 working days• Work in public highway – 40 working days

Gas mains pipe installation should be requested through your Dedicated Project Manager.

Responsibilities

4Revision 1.0CONFIDENTIAL

CONFIDENTIAL Revision 1.0 5

Responsibilities (cont.)

Gas Service connections should be requested via the UKPS plot Call Off team by simply filling out the Service “Connection Request Form” (Page 14) and either faxing it to 0845 2577 106 or emailing the form to [email protected].

Please be aware that the below requirements need to have been met prior to our site attendance to ensure the works can be completed without aborted visits.

• Premises are watertight and lockable

• Meter boxes/positions are installed and complete

• Final Ground Lines and Levels are determinable

• Excavations are suitable and safe

• Scaffolding has been removed from our work area

• Ducting has been installed to the correct specification and position

CONFIDENTIAL Revision 1.0

CONFIDENTIAL Revision 1.0 6

UK Power Solutions is responsible for laying all mains in trenches (unless otherwise stated) to the following minimum depths, using the diagram opposite as a guide:

Minimum depth of cover for mains pipes

Road and vehicular/ pedestrian access

750mm

Footpath 600mm

Verges 750mm

Open fields and agricultural land

1100mm

Excavation for mains pipes

75m

m -

100m

m fi

ne fi

ll su

rrou

nd

Gas warning marker tape to belaid at least 150mm above main

Ground Level

300mm approx. trench width

Ground Level

The pipe should be installedwith a sand/finefill surround to a

minimum cover of 75mm toprevent damage during final

reinstatement

For trench with multiple utilities gas pipe must beminimum 250mm from all other pipes and cables

Bottom of trench must be leveland free from sharp stones.

Recommended Depth of Cover for Mains Pipes

Road & vehicular/pedestrian areas 750mm

Footpath 600mm

Verges 750mm

Open fields andagricultural land 1100mm

xxx is responsible for laying all mains 63mm in diameter and above intrenches pre-excavated by the client (unless otherwise stated) to thefollowing minimum depths, using the diagram opposite as a guide.

300mm plus external pipe diameter trench width

250mm

CONFIDENTIAL Revision 1.0 7

Minimum excavation requirements

Minimum excavation requirements to support connections. Excavation base to be 150mm below pipe

Connection typeApplicable mains diameters

Excavation sizeAdditional bell hole in middle in direction of offtake

Excavation shape

End on connection(Note: the excavation dimension is for the live main to be exposed)

≤180mm mains diameter

2.1m x 0.7m n/a

250/315mm diameter

3.3m x 0.9m n/a

Insert Tee

≤180mm mains diameter

7.3m x 0.7m 1m x 0.7m

250/315mm diameter

10.6m x 0.9m 1m x 0.9m

Branched offtake

≤180mm mains diameter

1.5m x 0.7m 1m x 0.7m

250/315mm diameter

1.5m x 0.9m 1m x 0.9m

CONFIDENTIAL Revision 1.0 8

Utility pipe and cable positions

The diagram opposite illustrates the recommended positioning for new utility apparatus in a 2m footway.

Depth of cover required in a Carriageway or Verge is 750mm with proximities to other utilities remaining as per the diagram.

The gas network design will be discussed at the pre-start meeting. If you have any subsequent problems or queries, please contact your Project Manager who will be happy to advise and help resolve any issues.

Please also note that a minimum 250mm clearance must be achieved from the gas main to all other utilities.

TelecommunicationsDepth 350mm

Water Depth 750mm

Gas Depth 600mm

Cable TV/Communications Depth 250mm - 350mm

430260270295295450

Electricity Depth HV450mm - 1200mm, LV 450mmBoundary

Surface

Box

Boundary

430260270295295450

2000

Carriageway

Utility Pipe and Cable Positions

Note: This drawing is NOT to scale

The diagram opposite illustrates the recommended positioningfor new utility apparatus in a 2m footway.

Depth of cover required in a carriageway or verge is 750mm withproximities to other utilities reaming as per the diagram.

The gas network design will be discussed at the pre-startmeeting, if you have any subsequent problems or queries thenplease contact your Project Manger who will be happy to adviseand help resolve any issues.

Smell Gas? To report a gas or carbon monoxide emergency, or if a pipeline is struck (even if no gas leak has occurred) call the National Gas Emergency Service 24 hours a day on 0800 111 999.

CONFIDENTIAL Revision 1.0 9

Service positions and routes

PositionsThe position of the meter must be on the wall of the property facing the parent main, or, where it is required, on the side of the property no more than 2m down the gable. Meters cannot be installed to the rear of the property.

If you feel you cannot achieve the requirements, please contact your Project Manager.

RoutesThe service pipe must not be installed in any land other than that of the property it is supplying or public/shared driveway. Where a service is required to cross the road to a main on the opposite footpath, it must be laid in an individual road crossing (it is acceptable to install ducts for these road crossings as required). We will try to minimise this as much as possible during the design stage.

Examples of serviceroutes where roadcrossings required.

Note: Drawings are NOTto Scale

Service Positions

All services must be laid individually and perpendicular to the building takingthe shortest route practicable to the main unless otherwise indicated on theapproved construction drawing.

The position of the meter must be on the front of the property or where it isrequired on the side of the property must be no more than 2m from the frontgable end.

Where a service is required to cross the road to a main on the oppositefootpath it must be laid an individual road crossing. We will try and minimisethis as much as possible during the design stage. If you feel you cannotachieve the requirements, please contact your Project Manager.

Min 250

2m M

ax

Examples of serviceroutes where roadcrossings required.

Note: Drawings are NOTto Scale

Service Positions

All services must be laid individually and perpendicular to the building takingthe shortest route practicable to the main unless otherwise indicated on theapproved construction drawing.

The position of the meter must be on the front of the property or where it isrequired on the side of the property must be no more than 2m from the frontgable end.

Where a service is required to cross the road to a main on the oppositefootpath it must be laid an individual road crossing. We will try and minimisethis as much as possible during the design stage. If you feel you cannotachieve the requirements, please contact your Project Manager.

Min 250

2m M

ax

All services must be laid individually and perpendicular to the building taking the shortest route practicable to the main, unless otherwise indicated.

Service pipe trenchesYour Responsibilities:

Lay service pipes as per construction drawing. Ensure 75mm cover of finefill material round whole of pipe. Place marker tape above finefill. Provide and install yellow perforated ducts for road crossings. Excavate at meter positions and to soft fill over gas main. Install meter boxes and doors/lids.

Minimum Depth of Cover for Service Pipes:

Private Ground - 375mm Footpath/Highways - 450mm

75m

m -

100m

m fi

nefil

l sur

roun

d

Gas warning marker tape to belaid at least 150mm above main

Ground Level

300mm approx.trench width Ground Level

The pipe should be installedwith a sand/finefill surround to a

minimum cover of 75mm toprevent damage during final

reinstatement

For trench with multiple utilities gas pipe must beminimum 250mm from all other pipes and cables

Bottom of trench must be leveland free from sharp stones.

450m

m d

epth

960mm

600m

m M

in C

over

500m

m

450m

m M

in C

over

Main End Termination

Plastic seal inpipe end

Gas Main

Road

PE GasService

Gas warning marker tape to be laid at least 150mm above service

For trench with multiple utilities gas pipe must be minimum 250mm from all other pipes and cables

CONFIDENTIAL Revision 1.0 10

Your responsibilities:Ensure a minimum of 75mm of fine fill material around the service pipe.

Place marker tape above fine fill

Provide and install yellow perforated ducts (to BS4962) for road crossings

Excavate at meter positions and to soft fill over gas main

Install meter boxes and doors/lids

Minimum depth of cover for service pipes:Private Ground = 375mmFootpath/Highways = 450mm

CONFIDENTIAL Revision 1.0 11

Meter box installation

Unibox

Fitted at ground level submerged into the ground by 75mm or fixed onto the wall ensuring the ground level is as per indicator on the box.

Must be a minimum 150mm away from any air bricks.

Ensure box is supported following installation.

Fit meter box lid.

Route outlet pipe through right hand side of box.

Make continuity bond to outlet.

Provide 2m of excavation from the front of the box, 500mm wide,

Flush Fit or Bolt On

Fix meter box to wall

Fit meter box door

Securely fit spigot outlet to prevent passage of gas into property

The meter installer will seal the route of the outlet pipework and label the meter accordingly

Flush fit or Bolt On

Fix meter box to wall Fit meter box door Securely fit spigot outlet to

prevent passage of gas intoproperty.

The meter installer will seal theroute of the outlet pipework andlabel the meter accordingly.

Unibox

Fitted at ground level submerged intogroud by 75mm of fixed onto the wall.

Must be minimum 150mm away fromany air brick where no risk of waterentering.

Ensure box supported followinginstallation.

Fit meter box lid. Route outlet pipe through right hand

side of box. Make continuity bond to outlet pipe.

Provide 2m of excavation fromthe front of the box - 500mm wide

. Developer toexcavate toexposeservice pipe

Ground levelindicator on box

DPC

Emergency ControlValve (ECV)

GRP sleeve fittedby our team DPC

FinishedLevel

Developer toexcavate 2m backdown service routefrom box position

PVC black bendfitted by our team

Developer to excavateto expose service pipe

Gas Pipe ExternalDiameter

Duct internalDiameter

20/25/32mm 50mm63mm 100mm90mm 150mm

125/180mm 225mm250mm 350mm

Meter Box Installation Details(NTS)

Gas Meter Box

ElectricalMeter Box

75

480mm

500m

m

390mm 205mm

290mm

Gas Meter Box Detail(Scale 1:10)

Developer toexcavate to expose service duct

Gas Meter Box

duct

12Revision 1.0CONFIDENTIAL

General Advice

Sealing of outlets

The meter installer will fit the meter and label accordingly. It is your responsibility to ensure that the meter box outlet spigot or any through-wall sleeve carrying the meter outlet pipework is correctly sealed to prevent the passage of gas into the property.

Failure to do this is a breach of the Gas Safety (Installation and Use) Regulations.

Handling of Pipe

Mains pipe may be delivered to site in coils or straight lengths. Individual smaller coils are generally capable of being handled manually. However, larger coils will require mechanical lifting using soft straps.

The handling of straight pipe lengths requires some expertise, especially once any pipe packs have been unbound.

UK Power Solutions will move individual mains pipe lengths from the storage point to the construction location.

Electrical Cross Bonding

An electrical cross bonding wire (where required) should be connected to the gas meter outlet in accordance with IEE Regulations. When the bonding wire enters a built-in box from the rear it must pass through the outlet installation pipe spigot and be contained within the seal.

The box must not be broken to accommodate the bonding wire.

Please remember that you are not permitted to lay any gas pipe. This must be done by one of our qualified installers.

CONFIDENTIAL Revision 1.0 1313 Revision 1.0CONFIDENTIAL

General Advice (cont.)

Ducts

Yellow perforated rigid plastic ducting (complying with BS4962) can be used for perpendicular road crossings only and will be discussed at your pre-start meeting.

It is your responsibility to supply ducts and install to the correct specification (ensuring minimum depth is achieved) otherwise we may not be able to lay pipe through incorrectly laid ducts.

Gas marker tape must be laid at least 250mm above mains ducts & 150mm above service ducts.

If you need any further help or information,

please contact your Project Manager or our

team on 0845 257 7105

Gas Pipe External Diameter Duct Internal Diameter

32mm 60mm

63/90mm 150mm

125/180mm 225mm

250mm 350mm

Smell Gas? To report a gas or carbon monoxide emergency, or if a pipeline is struck (even if no gas leak has occurred) call the National Gas Emergency Service 24 hours a day on 0800 111 999.

14Revision 1.0CONFIDENTIAL

Se

rvice

Con

nec+

onR

eque

st

FM

186

Plot

Con

nec+

onR

eque

st

E-M

ail:

plot

callo

ff@uk

pow

erso

lu+o

ns.co

.uk

Tel:

084

525

771

05

Fax:

084

525

771

06

PLEA

SEN

OTE:

Am

inim

umo

f15

wor

king

day

sno8

cefo

rser

vice

conn

ec+o

nsis

requ

ired

and

am

inim

umo

f5p

lots

to

beco

nnec

ted

perv

isit.

Inth

eev

ento

faca

ncel

la+o

n/po

stpo

nem

enta

min

imum

of5

day

sno8

ceis

requ

ired.

A

sepa

rate

conn

ec8o

nre

ques

tfor

mis

requ

ired

fore

ach

prop

osed

dat

ean

da

new

conn

ec8o

nre

ques

tfor

mis

re

quire

dfo

rany

am

endm

ents

tob

ooki

ng.S

itew

illb

ere

quire

dto

sign

off

any

abor

ted

wor

ksin

the

boxb

elow

.Th

ere

ques

ted

conn

ec+o

nsw

orks

will

not

take

pla

ceu

n+lt

heb

elow

requ

irem

ents

oft

hea

dop+

ngn

etw

ork

owne

rha

veb

een

met

prio

rto

ours

itea

Send

ance

: •P

rem

isesa

rew

ater

+ght

and

lock

able

Expo

sea

min

imum

of1

.2m

ofm

ain

fors

ervi

cejo

in+n

g

•Met

erb

oxes

/hoc

key

s+ck

s/pr

efor

med

ben

dsa

refi

xed

•Fi

nalg

roun

dlin

esa

ndle

vels

are

appr

opria

te

•All

exca

va+o

nsa

resu

itabl

ean

dsa

fe

•D

uc+n

g/co

ntai

nmen

thas

bee

nin

stal

led

toth

eco

rrec

t

sp

ecifi

ca+o

nan

dpo

si+on

Date

ofR

eque

st:

UKPS

Pro

ject

No:

Site

Nam

e:Si

teC

onta

ct:

Site

Add

ress

:

TelN

o:Em

ail:

FaxN

o:

Prop

osed

Dat

e:Fo

rUKP

SUs

eOn

ly

Confi

rmed

Dat

e:

Plot

Nu

mbe

r

Elec

tric

(+ck

)Ga

s(+c

k)

Com

men

ts

Site

Age

nt

toP

rinta

nd

Sign

for

Abor

ted

wor

ks

Outs

ide

Met

er

Box

Inte

rnal

Stre

et

Light

Met

erB

oxIn

tern

alBu

ilt-in

Grou

nd

Co

nfide

n+al

Allc

onte

nta

ndg

raph

icsa

reC

opyr

ight

©2

015

UKP

ower

Sol

u+on

sLtd

.All

right

sres

erve

d.

Revi

sion

1.2

Repr

oduc

+on

inw

hole

ori

npa

rtin

any

form

orm

ediu

mw

ithou

texp

ress

per

miss

ion

from

UKP

Sis

proh

ibite

d.

ForU

KPS

Use

Only

PC

O/__

____

___

EXAMPLE

CONFIDENTIAL Revision 1.0 15

Contacts

Project Manager:

Mobile:

Office:

Email:

Connections Co-ordinator:

Mobile:

Office:

Email:

Regional Construction Manager:

Mobile:

Office:

Email:

Revision 1.0CONFIDENTIAL 15

Tel: 0845 257 7105 | Fax: 0845 257 7106 | Email: [email protected]

www.ukpowersolutions.co.ukRegistered in England & Wales. Registered Address: UK Power Solutions Ltd Head Office, River View House, Bonds Mill Estate, Stonehouse, GL10 3RF

UK Power Solutions Ltd London Office, 4th Floor West World, West Gate, Ealing, London, W5 1DT

Company Reg No. 06256696 VAT Reg No. 910 4276 54

All content and graphics are Copyright © 2017 UK Power Solutions Ltd. All rights reserved.

Reproduction in whole or in part in any form or medium without express permission from UKPS is prohibited