Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
DeSSC Jun 12 124
DeSSC UpdateAlvin Upgrade Project
Susan HumphrisPrincipal Investigator
Kurt UetzProject Manager
DeSSC Jun 12 125
DeSSC Update
• A significantly enhanced submersible for the scientific community built in two stages:
• Stage 1 4,500 m Alvin Upgrade: 2012• Stage 2 6,500 m Alvin Upgrade: future scheduling
Project Objectives
DeSSC Jun 12
Vehicle CharacteristicsDeSSC Update
Project ObjectiveStage 1 Vehicle
Stage 2 Vehicle
Remarks
6,500 meter depth capability X Stage 1 designs and fabricates select 6,500 meter components (sphere, penetrators, syntactic foam)
Larger personnel sphere, improved interior ergonomics
X 18% increase in interior volume; redesign of observer and pilot seating
Better visibility and overlapping views
X Three 7” forward viewports with overlapping fields of view; two 5” side port
Improved interior electronics X Fiber optic network, touch screen controls, and upgraded observer monitors
Increased science payload X Double the vehicle payload to 400 pounds as well as expand the manipulator work area
Improved lighting and imaging X HD video, publication quality still imaging, and increased lighting output (LED)
Improved data collection, logging, and science interface
X A fiber optic network and upgrades to the data recording and logging systems
Increased bottom time; mid‐water capability
X Requires increased battery capacity
Increased thruster horsepower X Requires increased battery capacityIncreased hydraulic plant capacity X Requires increased battery capacityAutomatic station keeping X Stage 1 includes auto‐heading control
Vehicle Certification: NAVSEA X Potential double classification with ABS in Stage 2
126
DeSSC Jun 12 127
UpdatesDeSSC Update
Personnel:Don Peters is the project Chief Engineer and managing the the engineering effort
Descoping:• The project is suspending ABS classification of the vehicle
• Reduces risk in the project related to double classification• The vehicle will continue the Navy certification process
• The project will review systems for witnessing by ABS to maximize the potential for future double classification
• The personnel sphere and LARS will also continue the ABS classification process
DeSSC Jun 12 128
DeSSC Update
NAVSEA Certification:• Weekly program and technical meetings to review certification
progress and expedite resolution of issues• June 8th Hydrostatic Test Readiness Review
• NSF reviewed and authorized pressure testing of the sphere
Personnel Sphere Hydrostatic Test:Planned start: June 20th
Delivery to WHOI: July 6th
Updates
DeSSC Jun 12 129
Personnel Sphere UpdateDeSSC Update
Ready for Hydrostatic Test
DeSSC Jun 12 130
Hydrostatic Test FacilityDeSSC Update
10 ft diameter
Chamber
12,000 psi max pressure
End cap
Northrop Grumman Oceanic Test Facility
Annapolis, MD
DeSSC Jun 12
Hydrostatic TestDeSSC Update
0
1,354
2,708
4,063
5,417
6,771
8,125
0
2,000
4,000
6,000
8,000
10,000
12,000
0 10 20 30 40 50 60 70 80 90 100
Dep
th (m
sw)
Pres
sure
(psi
g)
Dive Duration, minutes
Dive Profile - Test 3: 1.24 x MOPPressure (Depth) vs. Dive Time
MOP Test 3 1.24 x MOP
10 hour test to 6,500 meters
10 hour test to 6,800 meters
Final test to 8,125 meters
Final Dive Profile
131
DeSSC Jun 12 132
Blue area: current 60 ft2
Gray area: upgrade 114 ft2
New Capability - Manipulator ReachDeSSC Update
DeSSC Jun 12 133
New Capability - Imaging
Pri Pri
Sci #2Sci #1
S SituationalPri PrimarySci Science Cameras
• File-based image storage to reusable HDD• Long�term data storage• Situational Cameras: HD Video, 2 forward, internal pan and tilt• Primary Cameras: HD Video, 10x zoom (Mini-Zeus)• Science Cam #1: HD Video• Science Cam #2: HD Video + Still Imaging
DeSSC Update
S
SS
DeSSC Jun 12 134
Vehicle LayoutDeSSC Update
DeSSC Jun 12 135
Work in ProgressDeSSC Update
May 2012
DeSSC Jun 12 136
DeSSC UpdateWork in Progress
DeSSC Jun 12 137
Status of Major ComponentsDeSSC Update
• Penetrators:• Fiber optic units delivered and in testing• Electrical units fabricated, preparing for testing
• Foam:• All foam purchased, tested, and accepted• Shaping is in process with several pieces delivered
• Frame:• Front section removed• Fabrication of new section started
DeSSC Jun 12 138
R/V Atlantis StatusDeSSC Update
Launch and Recovery System Schedule
•Increase lift capability to 50,000 pounds
•A-Frame upgrade complete March 2011
•Deliver modified swinging beam to WHOI July 2012
• Shipyard maintenance period Aug – Sept 2012
• Reinstall swinging beam onto A-frame• Complete hangar modifications
•Complete LARS integration October 2012• ABS classify and NAVSEA certify
DeSSC Jun 12
Project TimelineDeSSC Update
139
Toda
y
DeSSC Jun 12 140
Frame Modifications:•Proceeding with fabrication in parallel with NAVSEA reviews
Vehicle NAVSEA Certification:•Completing assembly and testing concurrent with certifying the vehicle for manned operations
R/V Atlantis LARS•Completion of swinging beam modifications in July•Classify through ABS and certify with NAVSEA in time to support November dock trials
Budget:• Any schedule delay will jeopardize completion within budget
Challenges AheadDeSSC Update
DeSSC Jun 12 141
Back to Alvin OperationsDeSSC Update