Designers Guide 200707

Embed Size (px)

Citation preview

  • 7/28/2019 Designers Guide 200707

    1/2

    Designer's GuideIPC vs. UPC Stack Sizing

    By Timothy Allinson, P.E.

    Murray Company, Long Beach, Calif.

    As a Southern California design-build contractor, my projects are all locally based, and as such, they are governed by UPC-or moreaccurately, the CPC, which is the UPC with California amendments. The differences between UPC and the code of my former stompingground, New York City, are significant with respect to stack sizing. Recently, I began wondering about NYC's new code, the IPC (withamendments) and how it compares to UPC.

    I am somewhat embarrassed to admit that I am shamefully ignorant about IPC. As that code developed its presence I have neverworked in a jurisdiction under its governance, so I never had cause to familiarize myself with IPC. But UPC is so different than the oldNYC Code that I decided to explore how it compared with NYC's new Code.

    It turns out that the IPC lies somewhere between the NYC Code of old and the UPC, leaning more toward the old NYC Code, at leastwith respect to stack sizing. In fact, the stack sizing table in the IPC are nearly identical to those in the old NYC Code.

    So how do the IPC and UPC compare? To start, they are very different inappearance. Figure 1 is an abbreviated version of the IPC waste stack-sizing table.There is a separate table for sizing building drains not shown here. Figure 2 is anabbreviated version of the IPC vent-sizing table. In contrast, Figure 3 is an

    abbreviated version of the UPC waste and vent sizing table. This one small table isa Reader's Digest version of four separate tables in the IPC. So, the first and mostobvious difference is that the UPC sizing criteria is much more concise. Is this agood thing? It's too early to tell. Brevity is not necessarily superior to verbosity. Inorder to judge the differences between these two codes we'll have to look at someexamples.

    Take, for example, a 30-story, 300-ft. tall building with a stack (one of many) servinga typical toilet room on each floor -- one water closet, one lavatory, and onebath/shower. Regardless of which Code you reference, the sum on these fixturesyield 6 drainage fixture units. Since the stack serves 30 floors that totals 180 DFUsfor the stack.Since both Codes allow the stack to telescope in size, and since water closetsrequire a 3-in. minimum waste, the top of the stack will be a 3-in. minimum. The IPCallows three water closets on a 3-in. stack; the UPC allows four, so the transitionfrom 3-in. to 4-in. can occur one floor lower using the UPC -- but that's a subtledifference.

    Once the stack transitions to 4 in. both codes yield the same stack sizing result: a 4-in. stack is required sown to the first floor. Looking at IPC, Figure 1 reveals that a 4-in. stack can serve as many as 500 fixture units. Figure 2 further reveals that a 4-in.vent stack is required, since the stack is 4-in. with 180 DFUs and 300 ft. in height. Ifyou are reading the table correctly you will see that a 4-in. stack with up to 320DFUs requires a parallel 4-in. vent when it is greater than 170 ft. and less than 640-ft. long.

    Looking at UPC, Figure 3 reveals that a 4-in. vertical stack can carry as many as256 DFUs and cannot exceed 300 ft. in height. A 4-in. vent can serve up to 256fixture units with a maximum length of 300 ft. Based on UPC sizing, we are on the

    cusp of the 4-in. stack criteria. @body:Although the sizing in this random example produces the same results with these two codes, acomparison of their numbers reveals great differences. For example, as noted, a 4-in. stack in the IPC can serve 500 fixture units andhas no length limitations, whereas a 4-in. stack in the UPC can only serve 256 DFUs and is limited to 300 ft. in length. Therefore, if thesubject building were a few stories taller, the stack sized by the IPC would remain 4 in. in size, while the waste stack sized by the UPCwould grow to 5 in. for the lower few floors and the entire vent would increase to 5 in.

    Oddly, while the sizing criteria for vertical stacks are dramatically different in these two codes, the sizing for the horizontal building drainis very much the same. In both Codes a 4-in. drain with 2% slope can service 216 DFUs. Not all of the building drain sizing criteria areidentical, but it is close -- much closer than the vertical stack sizing criteria.

    Also noteworthy is the fact that both codes require relief vents interconnecting the waste and vent stacks when the stacks are 10 storiesor more in height; however, the IPC requires relief vents every 10 floors while the UPC requires them every 5 floors.

    So the UPC is much more conservative than the IPC when it comes to waste and vent sizing, since the pipes in the UPC system areoften larger than the IPC system. Or are they?

    We should consider that both codes have an allowance for "bathroom group" sizing. In the IPC it is in the body of the code whereas inthe UPC it is in the appendix. The IPC assigns 5 DFUs to the typical bathroom group in our example, while the UPC assigns only 3DFUs. If one applies the bathroom group sizing technique, then the sizing difference between the two codes narrows. However, the

  • 7/28/2019 Designers Guide 200707

    2/2

    length limitations of the UPC will still generate larger pips sizes, and as noted above, the UPC requires twice as many relief vents.

    So why do these differences exist between these two codes? And for that matter, why the similarities? I wish I knew the answer to thesequestions. There are surely others out there with greater Code history knowledge than myself who might be able to answer theserhetorical questions.

    It is my personal opinion that UPC produces stack sizing that is larger than necessary. I base this statement on the fact that IPC sizingmimics the NYC criteria of old, and clearly NYC has many high-rise buildings sized with this criteria that have functioned well for many,many years. I think it would be prudent for IAPMO to consider embracing these sizing criteria for the sake of economy and uniformity, butI won't hold my breath in anticipation of such a code change.

    Timothy Allinson is a Senior Professional Engineer with Murray Company, Mechanical Contractors, in

    Long Beach, Calif. Prior to entering the design-build industry he worked for Popov Engineers, Inc. in

    Irvine, Calif, and JB&B in New York City. Tim holds a BSME from Tufts University and an MBA from

    New York University. He is a professional engineer licensed in both mechanical and fire protection

    engineering in various states, and is a leed Accredited Professional. Tim is a past-president of ASPE,

    both the New York and Orange County Chapters, and sits on the board of the Society of American

    Military Engineers, Orange County Post.